Inversiones Operativas
Costo total por naturaleza
2
Costo total por área
CU Chungar Jul 13 Acum a Jul
Feb 13 Mar 13 Abr 13 May 13 Jun 13
(US$/TM) Real Ppto Var Real Ppto Var
Mina 45.4 37.5 38.5 39.7 39.7 33.9 35.7 -1.8 39.5 37.8 1.7
Animón 52.4 41.1 42.2 44.8 43.5 39.9 43.3 -3.4 44.1 46.1 -2.0
Islay 29.5 27.6 29.2 28.2 29.8 21.5 21.1 0.4 27.5 20.6 6.9
Planta 4.6 6.0 4.9 6.1 5.4 5.1 4.7 0.4 5.5 5.1 0.4
Taller 2.5 2.2 2.2 2.2 1.9 1.9 2.2 -0.2 2.3 2.2 0.0
Energía 2.4 2.9 2.3 1.9 2.8 3.2 2.5 0.7 2.6 2.4 0.3
Administración y Otros 9.5 10.5 9.6 9.2 9.9 8.1 10.9 -2.8 9.7 11.9 -2.2
Costo Propio 64.4 59.5 57.7 59.0 60.0 52.4 55.9 -3.5 59.7 59.4 0.3
3
Costo Mina por naturaleza
TME 98,146 118,778 114,036 110,597 116,079 122,042 115,900 6,142 796,421 783,400 13,021
4
por Animón
Costo Mina etapa
Chungar Jul 13
Abr 13 May 13 Jun 13
Animón Real Mano Obra Suministros Servicios Misceláneos Ppto Var
Real Jul 13 3.6 11.2 24.7 0.4
Perforación 4.1 4.8 4.4 4.4 -0.1 -0.1 -0.3 0.0 4.8 -0.4
Voladura 3.1 3.3 3.7 3.3 -0.2 0.3 0.0 0.1 3.1 0.2
Sostenimiento 13.4 14.1 13.3 11.4 -0.1 -1.3 -1.6 0.0 14.3 -2.9
Limpieza 3.9 4.7 4.9 4.1 -0.0 -0.3 -0.2 0.0 4.7 -0.6
Transporte 5.4 4.7 4.8 4.2 -0.0 -0.2 1.0 0.0 3.5 0.8
Relleno 1.5 1.8 1.7 1.8 -0.0 -0.0 0.3 0.0 1.5 0.3
Servicios 3.1 3.7 3.0 2.8 0.1 -0.1 -0.2 -0.5 3.5 -0.7
Bombeo 4.5 4.3 4.4 4.2 0.0 -0.0 0.2 -0.1 4.1 0.2
Supervisión 0.8 0.7 0.7 0.8 -0.3 0.0 0.0 0.1 1.0 -0.2
Otros 2.4 2.5 2.6 2.7 -0.1 0.1 -0.1 0.0 2.8 -0.1
Total 42.2 44.8 43.5 39.9 -0.6 -1.5 -0.9 -0.3 43.3 -3.4
Ppto Jul 13 4.2 12.8 25.6 0.7
Se ha incrementado el metro de avance en preparación 207 metros respecto a Junio y 241 metros por sobre lo
programado, esto ha ocasionado mayor consumo de explosivos y otros elementos de la operación.
La postergación del inicio de operación del Pique Jacob Timmers sigue generando diferencias en el costo de transporte
presupuestado.
El exceso de producción de 6,142 TM ha incidido en el decrecimiento del índice en el mes.
5
Mina Animon
0.30
Suministros Voladura
DINAMITA SEMEXSA 65 1-1/8X12" (UN ) 211,516 112,945 0.53 199,722 102,913 0.52 3,954.45 6,077.20 10,032 0.04
EMULSION EXPLOSIVA A GRANEL (KG ) 7,500 17,850 2.38 - 17,850 - 17,850 0.15
EXPLOSIVO EMULSION SENATEL 2X16" (UN ) 1,820 3,430 1.88 - 3,430.00 - 3,430 0.03
EXPLOSIVO EMULNOR 3000 1-1/4X12" (KG ) 3,030 6,271 2.07 154.23 334 2.17 -299.15 6,236.06 5,937 0.05
EXPLOSIVO EMULNOR 1000 1-1/8X12" (UN ) 4,512 1,905 0.42 11,751 5,183 0.44 -84.49 -3,193.22 -3,278 -0.03
EXPLOSIVO EMULNOR 3000 1-1/2X12" (UN ) 256 por
192 etapa
0.75 - 192.39 - 192 0.00
TUBERIA SAL PVC 3M (UN ) 12,000 12,717 1.06 873.00 944 1.08 -261.01 12,033.86 11,773 0.10
DETONADOR NO ELEC 30,288 42,716 1.41 29,423 42,420 1.44 -951 1,247 296 -0.02
198,027 151,794 46,232 0.3
Debido a un mayor avance en preparaciones (979 mt real vs 738 mt plan), el consumo de explosivos y
detonantes ha sufrido un ligero incremento.
6
Mina Animon
1.00
Servicios Transporte
Servicios Real Plan Diferencia US$/T
Ctda. USD PU Real Ctda. USD PU Plan Dif Precio Dif Ctdad. Dif Total
Animon
TRANSP. MINERAL 159,295 285,112 1.79 73,806 145,500 1.97 -28,919 168,531 139,612 1.08
139,612 1.08
TRANSP. DESMONTE 25,594 83,472 3.26 21,780 74,011 3.40 -3,502 12,963 9,461 0.05
9,461 0.05
TRANSP. SHOTCRETE 125 299 2.39 100 153 1.53 107 39 146 0.00
146 0.00
SERVICIO CARGADOR FRONTAL 3.00 YD3 (H ) 41 2,446 59.66 43 2,651 61.02 -56 -150 -205 -0.00
SERV. EXCAVADORA C/MARTILLO HIDRAULICO (H) 367 39,397 107.35 194.00 21,922 113.00 -2,074 19,549 17,475 0.13
SERVICIO RETROEXCAVADORA 75 HP (H ) 38.50 3,528 91.65 5.82 269 46.20 1,750 1,510 3,260 0.03
SERVICIO EXCAVADORA 235 HP - PC300 (H ) - 9 841 95.70 - -841 -841 -0.01
SERVICIO EXCAVADORA 247 HP (H ) - 3 346 105.47 - -346 -346 -0.00
SERVICIO EXCAVADORA EC 360 BLC (H ) - 16 1,455 90.04 - -1,455 -1,455 -0.01
SERVICIO EXCAVADORA 329D (H ) - 13 1,164 90.02 - -1,164 -1,164 -0.01
SERVICIO VOLQUETE 15 M3 (H ) 2.70 87 32.30 28 950 34.01 -4.61 -859 -863 -0.01
SERVICIO VOLQUETE 22 M3 (H ) - 594 23,147 39.00 - -23,147 -23,147 -0.20
45,459 52,746 -7,287 -0.08
141,931 1.04
El inicio de la operación del Pique estaba considerado en el presupuesto desde el inicio del segundo
trimestre, por lo que la demora del arranque de sus operaciones está generando variaciones.
7
Mina Animon
0.30
Servicios Relleno
Miro Vidal
LIMPIEZA RELLENO DETRITICO C/SCOOP (M3 ) 6,691 47,978 7.17 2,723 21,481 7.89 -4,801.34 31,298 26,497 0.21
47,978 21,481 26,497 0.21
Semiglo
SERV. RELLENO DETRITICO C1 SCP 6.0YD3 (M3) 3,668 25,820 7.04 1,777 13,475 7.58 -1,990.91 14,336 12,345 0.10
25,820 13,475 12,345 0.10
38,842 0.30