PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

PROYECTO: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE PIURA -
PIURA''

ESPECIALIDA ARQUITECTURA VALORIZADO A CONTRATO DE


EXPEDIENTE TECNICO REAL SALDO POR VALORIZAR
CHIQUIHUANCA

Item Descripción UND METRADO PU PARCIAL METRADO PU PARCIAL METRADO PU PARCIAL METRADO PU PARCIAL
02.00.00 ARQUITECTURA
2.11 PINTURA
02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS m2 11,235.10 5.89 66,174.74 11,408.79 5.89 67,197.77 5,403.98 5.51 29,767.70 6,004.81 5.51 33,077.33
02.11.02 PINTURA LATEX VINILICO 2 MANOS EN CIELO RASO Y VIGAS m2 5,436.40 5.89 32,020.42 5,147.89 5.89 30,321.07 2,978.23 5.51 16,405.50 2,169.66 5.51 11,951.52
02.11.03 PINTURA EN CASETAS m2 329.54 5.89 1,940.96 236.40 5.89 1,392.40 236.40 5.51 1,302.20
02.11.04 PINTURA ESMALTE EN CONTRAZOCALOs de 10 cm- ml 1,006.53 6.48 6,522.31
02.11.05 PINTURA ESMALTE EN CONTRAZOCALOs de 20 cm ml 250.90 6.48 1,625.83 1,685.59 6.48 10,922.62 505.68 5.51 2,785.51
02.11.06 PINTURA ESMALTE EN CONTRAZOCALOs de 30 cm ml 209.25 6.48 1,355.94
02.11.07 PINTURA ESMALTE EN CONTRAZOCALOs de 55 cm ml 139.62 6.48 904.74 465.53 6.48 3,016.63 256.04 5.51 1,410.40
COSTO DIRECTO 110,544.94 112,850.49 46,173.20 50,526.96
GG (10%) 11,054.49 0.00 0.00 0.00
UTI ( 10%) 11,054.49 0.00 0.00 0.00
SUB TOTAL 132,653.93 112,850.49 46,173.20 50,526.96
IGV (18%) 23,877.71 20,313.09 8,311.18 9,094.85
TOTAL 156,531.64 133,163.58 54,484.38 59,621.81
HOJA DE METRADOS DE ARQUITECTURA

“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE
OBRA : PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: MUROS Y ALBAÑILERIA

02.01.01 MURO DE LADRILLO KK TIPO IV SOGA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2

ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL

PRIMER PISO
PABELLON P-1
AULA P-01
MUROS INTERIORES HASTA VIGAS 2 3.65 2.95 21.54
MUROS INTERIORES HASTA VIGAS 1 3.65 2.95 10.77
MUROS INTERIORES HASTA VIGAS 1 3.65 2.95 10.77
VENTANA V-02 -2 4.43 0.85 -7.53
VENTANA V-02 -2 4.43 0.85 -7.53
PUERTA P-01 -1 1.10 2.10 -2.31

AULA P-02
MUROS INTERIORES HASTA VIGAS 1 3.55 2.95 10.47
MUROS INTERIORES HASTA VIGAS 1 3.55 2.95 10.47
MUROS INTERIORES HASTA VIGAS 1 3.53 2.95 10.40
MUROS INTERIORES HASTA VIGAS 1 3.43 2.95 10.10
VENTANA V-03 -1 4.06 1.65 -6.69
VENTANA V-03 -1 4.03 1.65 -6.64
VENTANA V-02 -1 4.06 0.85 -3.45
VENTANA V-04 -1 4.06 0.85 -3.45
PUERTA P-01 -1 1.10 2.10 -2.31

AULA P-03
MUROS INTERIORES HASTA VIGAS 1 3.62 2.95 10.66
MUROS INTERIORES HASTA VIGAS 1 3.42 2.95 10.07
MUROS INTERIORES HASTA VIGAS 1 3.66 2.95 10.80
MUROS INTERIORES HASTA VIGAS 1 3.56 2.95 10.50
VENTANA V-03 -1 4.12 1.65 -6.79
VENTANA V-01 -1 4.16 1.65 -6.86
VENTANA V-02 -1 4.06 0.85 -3.45
VENTANA V-04 -1 3.92 0.85 -3.33
PUERTA P-01 -1 1.10 2.10 -2.31

ESCALERA
MUROS BAJOS 1 2.70 1.00 2.70

PABELLON P-2
SS.HH - NIÑOS
MUROS INTERIORES HASTA VIGAS 1 3.55 2.95 10.47
MUROS INTERIORES HASTA VIGAS 1 3.55 2.95 10.47
MUROS INTERIORES HASTA VIGAS 1 4.80 2.95 14.16
MUROS INTERIORES HASTA TECHO 1 3.13 2.95 9.22
VENTANA V-16 -2 4.05 0.85 -6.89
PUERTA P-02a -1 1.00 2.10 -2.10

SS.HH - DISCAPACIDAD
MUROS INTERIORES HASTA TECHO 1 4.80 2.95 14.16
MUROS INTERIORES HASTA TECHO 1 3.93 2.95 11.58
VENTANA V-17 -2 1.85 0.85 -3.14
PUERTA P-02 -2 1.00 2.10 -4.20

SS. HH. NIÑAS


MUROS INTERIORES HASTA TECHO 2 3.43 2.95 20.21
MUROS INTERIORES HASTA TECHO 1 0.65 2.95 1.92
VENTANA V-15 -2 3.93 0.85 -6.67
PUERTA P-02a -1 1.00 2.10 -2.10

SS. HH. HOMBRES Y MUJERES


MUROS INTERIORES HASTA TECHO 1 4.23 3.25 13.73
MUROS INTERIORES HASTA TECHO 1 3.40 3.25 11.05
MUROS INTERIORES HASTA TECHO 1 4.25 3.25 13.81
VENTANA V-18 -1 8.78 0.85 -7.46
PUERTA P-02a -2 1.00 2.10 -4.20

ESCALERA
MUROS BAJOS 1 2.70 1.00 2.70
HOJA DE METRADOS DE ARQUITECTURA

“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE
OBRA : PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: MUROS Y ALBAÑILERIA

02.01.01 MURO DE LADRILLO KK TIPO IV SOGA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2

ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL

PABELLON P-3
AULA P-04
MUROS INTERIORES HASTA VIGAS 1 3.66 2.95 10.80
MUROS INTERIORES HASTA VIGAS 1 3.62 2.95 10.68
MUROS INTERIORES HASTA VIGAS 1 3.56 2.95 10.50
MUROS INTERIORES HASTA VIGAS 1 3.41 2.95 10.06
VENTANA V-2 -1 4.06 0.85 -3.45
VENTANA V-4 -1 3.92 0.85 -3.33
VENTANA V-1 -1 4.16 1.65 -6.86
VENTANA V-3 -1 4.12 1.65 -6.80
PUERTA P-01 -1 1.10 2.10 -2.31

AULA P-05
MUROS INTERIORES HASTA VIGAS 1 3.43 2.95 10.10
MUROS INTERIORES HASTA VIGAS 1 3.55 2.95 10.47
MUROS INTERIORES HASTA VIGAS 1 3.53 2.95 10.40
MUROS INTERIORES HASTA VIGAS 1 3.55 2.95 10.47
VENTANA V-2 -1 4.05 0.85 -3.44
VENTANA V-4 -1 3.93 0.85 -3.34
VENTANA V-1 -1 4.05 1.65 -6.68
VENTANA V-3 -1 4.03 1.65 -6.64
PUERTA P-01 -1 1.10 2.10 -2.31

DIRECCION, SECRETARUA. SAL DE PROF. SUBDIR


MUROS INTERIORES HASTA VIGAS 1 2.40 3.25 7.80
MUROS INTERIORES HASTA VIGAS 1 2.31 3.25 7.51
MUROS INTERIORES HASTA VIGAS 1 2.58 3.25 8.39
MUROS INTERIORES HASTA VIGAS 1 2.40 3.25 7.80
MUROS INTERIORES HASTA VIGAS 1 2.31 3.25 7.51
MUROS INTERIORES HASTA VIGAS 1 2.31 3.25 7.51
VENTANA V-12 -1 9.50 0.85 -8.08
VENTANA V-11 -1 8.79 1.65 -14.50
PUERTA P-01 -1 1.10 2.10 -2.31

ESCALERA
MUROS BAJOS 1 2.70 1.00 2.70

PABELLON I-1
ESCALERA
MUROS INTERIORES HASTA VIGAS 1 2.00 2.95 5.90

AULA I-01
MUROS INTERIORES HASTA VIGAS 4 3.65 3.25 47.45
VENTANA V-02-4 -2 4.15 0.85 -7.06
VENTANA V-01-3 -2 4.15 1.65 -13.70
PUERTA P-01 -1 1.10 2.10 -2.31

SS. HH. NIÑOS (as)


MUROS INTERIORES HASTA VIGAS 1 3.05 2.95 9.00
MUROS INTERIORES HASTA TECHO 1 1.75 3.25 5.67
MUROS INTERIORES HASTA VIGAS 2 2.03 2.95 11.95
VENTANA V-20 -4 2.03 0.85 -6.89

AULA I-02
MUROS INTERIORES HASTA VIGAS 4 3.65 2.95 43.07
VENTANA V-03-01 -2 4.15 1.65 -13.70
VENTANA V-04-02 -2 4.15 0.85 -7.06

SS.HH. NIÑOS-NIÑAS
MUROS INTERIORES HASTA TECHO 1 4.10 3.25 13.33
MUROS INTERIORES HASTA VIGAS 2 1.58 2.68 8.44
VENTANA V-21 -2 1.58 0.85 -2.68

AULA I-03
MUROS INTERIORES HASTA VIGAS 2 3.55 2.68 19.06
MUROS INTERIORES HASTA VIGAS 2 3.28 2.95 19.32
VENTANA V-01 -1 4.05 0.85 -3.44
HOJA DE METRADOS DE ARQUITECTURA

“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE
OBRA : PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: MUROS Y ALBAÑILERIA

02.01.01 MURO DE LADRILLO KK TIPO IV SOGA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2

ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL


VENTANA V-02 -1 4.05 1.65 -6.68
VENTANA V-01 -1 3.78 0.85 -3.21
VENTANA V-02 -1 3.78 1.65 -6.23
PUERTA P-01 -1 1.10 2.10 -2.31

SUM
MUROS INTERIORES HASTA VIGAS 2 3.55 2.95 20.95
MUROS INTERIORES HASTA VIGAS 4 3.43 2.95 40.42
MUROS INTERIORES HASTA VIGAS 1 5.05 2.95 14.90
VENTANA V-01 -1 2.95 1.65 -4.87
VENTANA V-01 -1 2.83 1.65 -4.66
VENTANA V-01 -1 4.05 1.65 -6.68
VENTANA V-01 -2 3.93 1.65 -12.95
VENTANA V-03 -1 3.93 1.65 -6.48
VENTANA V-00 -1 2.00 1.65 -3.30
PUERTA -2 1.10 2.40 -5.28
PUERTA -1 1.00 2.10 -2.10

COCINA ALMACEN
MUROS INTERIORES HASTA VIGAS 1 4.48 2.95 13.20
MUROS INTERIORES HASTA VIGAS 2 3.47 2.95 20.47
VENTANA V-02 -1 4.05 0.85 -3.44
VENTANA V-01 -1 4.05 1.65 -6.68
PUERTA P-01a -1 1.00 2.10 -2.10

ESCALERA
MUROS BAJOS 1 2.00 1.00 2.00

PABELLON S-3
SS.HH NIÑOS
MUROS INTERIORES HASTA VIGAS 1 13.65 2.95 40.27
MURO INTERIOR 5 1.15 1.85 10.64
MUROS INTERIORES HASTA TECHO 1 1.85 3.25 6.01
MUROS INTERIORES HASTA TECHO 1 7.40 3.25 24.05
MUROS INTERIORES HASTA TECHO 1 3.55 2.95 10.47
VENTANA V-16 - 22 -1 11.08 0.85 -9.41
VENTANA V-12 -2 3.10 0.85 -5.27
VENTANA V--- -1 4.05 0.85 -3.44
PUERTA P-02 -2 1.00 2.10 -4.20

SS.HH NIÑAS
MUROS INTERIORES HASTA VIGAS 1 9.70 2.95 28.62
MURO INTERIOR 5 1.15 1.85 10.64
VENTANA V-16 - -1 4.88 0.85 -4.14
VENTANA V-12 -1 4.05 0.85 -3.44

PABELLON S-2
AULA S-4
MUROS INTERIORES HASTA VIGAS 1 14.05 2.95 41.45
VENTANA V-07 - 05 -1 8.08 1.65 -13.32
VENTANA V-06-05 -1 7.98 0.85 -6.78
PUERTA P-01 -1 1.10 2.10 -2.31

AULA S-5
MUROS INTERIORES HASTA VIGAS 1 14.26 2.95 42.05
VENTANA V-07 - 05 -1 8.17 1.65 -13.48
VENTANA V-06-05 -1 7.98 0.85 -6.78
PUERTA P-01 -1 1.10 2.10 -2.31

ESCALERA
MUROS BAJOS 1 2.00 1.00 2.00

SEGUNDO PISO
PABELLON P-01
AULA P-06
MUROS INTERIORES HASTA VIGAS 4 3.65 2.95 43.07
VENTANA V-05 -2 4.15 1.65 -13.70
VENTANA V-06 -2 4.15 0.85 -7.06
HOJA DE METRADOS DE ARQUITECTURA

“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE
OBRA : PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: MUROS Y ALBAÑILERIA

02.01.01 MURO DE LADRILLO KK TIPO IV SOGA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2

ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL


PUERTA P-01 -1 1.10 2.10 -2.31

AULA P-07
MUROS INTERIORES HASTA VIGAS 1 16.05 2.95 47.35
VENTANA V-01-+03 -1 7.98 1.65 -13.16
VENTANA V-06 -1 7.98 0.85 -6.78
PUERTA P-01 -1 1.10 2.10 -2.31

AULA P-08
MUROS INTERIORES HASTA VIGAS 1 14.25 2.95 42.04
VENTANA V-01- 03 -1 8.28 1.65 -13.65
VENTANA V-06 -1 7.98 0.85 -6.78
PUERTA P-01 -1 1.10 2.10 -2.31

ESCALERA
MUROS BAJOS 1 2.70 1.00 2.70

PABELLON P-03
AULA P-09
MUROS INTERIORES HASTA VIGAS 1 14.26 2.95 42.06
VENTANA V-04-02 -1 8.13 1.65 -13.42
VENTANA V-03-01 -1 7.98 0.85 -6.78
PUERTA P-01 -1 1.10 2.10 -2.31

AULA P-10
MUROS INTERIORES HASTA VIGAS 1 14.05 2.95 41.43
VENTANA V-04-02 -1 7.98 1.65 -13.16
VENTANA V-03.-01 -1 8.08 0.85 -6.86
PUERTA P-01 -1 1.10 2.10 -2.31

AULA P-11
MUROS INTERIORES HASTA VIGAS 1 14.56 2.95 42.95
VENTANA V-04-02 -1 8.78 0.85 -7.46
VENTANA V-03.-01 -1 8.78 1.65 -14.49
PUERTA P-01 -1 1.10 2.10 -2.31

ESCALERA
MUROS BAJOS 1 2.70 1.00 2.70

PABELLON P-02
AULA P-12
MUROS INTERIORES HASTA VIGAS 1 18.00 2.95 53.10
VENTANA V-04-02 -1 9.00 0.85 -7.65
VENTANA V-03.-01 -1 9.00 1.65 -14.85
PUERTA P-01 -1 1.10 2.10 -2.31

AULA P-13
MUROS INTERIORES HASTA VIGAS 1 18.00 2.95 53.10
VENTANA V-04-02 -1 9.00 0.85 -7.65
VENTANA V-03.-01 -1 9.00 1.65 -14.85
PUERTA P-01 -1 1.10 2.10 -2.31

LABORATORIO
MUROS INTERIORES HASTA VIGAS 1 36.00 2.95 106.20
VENTANAS -1 18.00 0.85 -15.30
VENTANAS -1 18.00 1.65 -29.70

AULA SPICOMOTRIZ
MUROS INTERIORES HASTA VIGAS 1 14.60 2.95 43.07
VENTANA V-4-2 -2 4.15 0.85 -7.06
VENTANA V-1-3 -2 4.15 1.65 -13.70
PUERTA P-01 -1 1.10 2.10 -2.31

SS. HH. NIÑOS - NIÑAS


MUROS INTERIORES HASTA VIGAS 1 11.59 2.95 34.19
VENTANA V-20 -4 2.03 0.85 -6.90
PUERTA P-03 -2 0.90 2.10 -3.78
HOJA DE METRADOS DE ARQUITECTURA

“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE
OBRA : PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: MUROS Y ALBAÑILERIA

02.01.01 MURO DE LADRILLO KK TIPO IV SOGA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2

ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL


AULA I-4
MUROS INTERIORES HASTA VIGAS 4 3.65 2.95 43.07
VENTANAS -2 4.15 0.85 -7.06
VENTANAS -2 4.15 1.65 -13.70

ESCALERA
MUROS BAJOS 1 2.70 1.00 2.70

PABELLON S-3
AULA DE INNOVACIÓN
MUROS INTERIORES HASTA VIGAS 1 28.01 2.95 82.63
MUROS INTERIORES HASTA VIGAS 1 11.80 2.95 34.81
VENTANAS -1 16.05 1.65 -26.48
VENTANA V-27 -1 15.96 0.85 -13.57
PUERTA P-01 -3 1.10 2.10 -6.93
PUERTA P-02 -1 1.00 2.10 -2.10

ESCALERA
MUROS BAJOS 1 2.00 1.00 2.00

PABELLON S-2
AULA S-10
MUROS INTERIORES HASTA VIGAS 1 14.05 2.95 41.45
VENTANAS -1 7.98 0.85 -6.78
VENTANAS -1 7.98 1.65 -13.16
PUERTA P-01 -1 1.10 2.10 -2.31

AULA S-11
MUROS INTERIORES HASTA VIGAS 1 14.24 2.95 42.01
VENTANAS -1 7.97 0.85 -6.77
VENTANAS -1 8.27 1.65 -13.65
PUERTA P-01 -1 1.10 2.10 -2.31

ESCALERA
MUROS BAJOS 1 2.00 1.00 2.00

MUROS BAAJOS EN LOS PASILLOS


MUROS INTERIORES HASTA VIGAS 1 218.28 1.00 218.28

TERCER PISO
PABELLON P-1
AULA - P-14
MUROS INTERIORES HASTA VIGAS 1 3.65 2.95 10.77
VENTANAS -1 4.15 1.65 -6.85
VENTANAS -1 4.15 0.85 -3.53
PUERTAS P-01 -1 1.10 2.10 -2.31

AULA - P-15
MUROS INTERIORES HASTA VIGAS 1 14.05 2.95 41.45
VENTANAS -1 7.98 0.85 -6.78
VENTANAS -1 8.08 1.65 -13.32
PUERTAS P-01 -1 1.10 2.10 -2.31

AULA - P-16
MUROS INTERIORES HASTA VIGAS 1 14.26 2.95 42.05
VENTANAS -1 8.28 1.65 -13.65
VENTANAS -1 7.98 0.85 -6.78
PUERTAS P-01 -1 1.10 2.10 -2.31

ESCALERA
MUROS BAJOS 1 2.70 1.00 2.70

PABELLON P-3
AULA P-17
MUROS INTERIORES HASTA VIGAS 1 14.26 2.95 42.05
VENTANAS -1 7.98 0.85 -6.78
VENTANAS -1 8.27 1.65 -13.64
PUERTA P-01 -1 1.10 2.10 -2.31
HOJA DE METRADOS DE ARQUITECTURA

“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE
OBRA : PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: MUROS Y ALBAÑILERIA

02.01.01 MURO DE LADRILLO KK TIPO IV SOGA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2

ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL

AULA P-18
MUROS INTERIORES HASTA VIGAS 1 14.05 2.95 41.45
VENTANAS -1 7.98 0.85 -6.78
VENTANAS -1 8.08 1.65 -13.32
PUERTA P-01 -1 1.10 2.10 -2.31

AULA P-19
MUROS INTERIORES HASTA VIGAS 1 14.58 2.95 43.01
VENTANAS -1 8.79 0.85 -7.47
VENTANAS -1 8.79 1.65 -14.50
PUERTA P-01 -1 1.10 2.10 -2.31

ESCALERA
MUROS BAJOS 1 2.70 1.00 2.70

PABELLON P-2
BIBLIOTEA DEPOSITO
MUROS INTERIORES HASTA VIGAS 1 41.75 2.95 123.16
VENTANAS -1 18.00 0.85 -15.30
VENTANAS -1 18.00 1.65 -29.70
VENTANA … -1 4.75 1.75 -8.31
PUERTA P-01 -1 1.10 2.10 -2.31

AULA INNOVACION - CONECTIVIDAD


MUROS INTERIORES HASTA VIGAS 1 47.00 2.95 138.65
VENTANAS -1 18.00 0.85 -15.30
VENTANAS -1 18.00 1.65 -29.70
PUERTA P-01 -1 1.10 2.10 -2.31

ESCALERA
MUROS BAJOS 1 2.70 1.00 2.70

PABELLON S-3
AULA INNOVACION AREA CONECTIVIDAD
MUROS INTERIORES HASTA VIGAS 1 31.91 2.95 94.13
MUROS INTERIORES HASTA VIGAS 1 10.80 2.95 31.86
VENTANAS -1 15.96 0.85 -13.57
VENTANAS -1 15.95 1.65 -26.32
PUERTA P-01 -3 1.10 2.10 -6.93

ESCALERA
MUROS BAJOS 1 2.00 1.00 2.00

PABELLON S-2
AULA S-12 - S-13
MUROS INTERIORES HASTA VIGAS 1 32.28 2.95 95.23
VENTANAS -1 15.94 0.85 -13.55
VENTANAS -1 16.34 1.65 -26.96
PUERTA P-01 -2 1.10 2.10 -4.62

ESCALERA
MUROS BAJOS 1 2.00 1.00 2.00

MUROS BAAJOS EN LOS PASILLOS


MUROS INTERIORES HASTA VIGAS 1 185.91 1.00 185.91

TOTAL 1750.88

02.01.02 MURO DE LADRILLO KK TIPO IV CABEZA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2


ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL

PRIMER PISO
PABELLON P-01
AULA P-01
MUROS INTERIORES HASTA TECHO 1 5.80 3.25 18.85
HOJA DE METRADOS DE ARQUITECTURA

“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE
OBRA : PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: MUROS Y ALBAÑILERIA

02.01.01 MURO DE LADRILLO KK TIPO IV SOGA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2

ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL


MUROS INTERIORES HASTA TECHO 1 5.55 3.25 18.03

ESCALERA
MUROS INTERIORES HASTA TECHO 1 4.84 3.25 15.73
MUROS INTERIORES 1 2.70 3.25 8.78

AULA P-02
MUROS INTERIORES HASTA TECHO 1 5.80 3.25 18.85
MUROS INTERIORES HASTA TECHO 1 5.30 3.25 17.23

AULA P-03
MUROS INTERIORES HASTA TECHO 1 5.80 3.25 18.85

PABELLON P-02
SS. HH. NIÑOS
MUROS INTERIORES HASTA TECHO 1 5.80 3.25 18.85
MUROS INTERIORES HASTA TECHO 1 2.25 3.25 7.31

SS. HH. NIÑAS


MUROS INTERIORES HASTA TECHO 1 5.05 3.25 16.41

SS. HH. M
MUROS INTERIORES HASTA TECHO 1 5.80 3.25 18.85

ESCALERA
MUROS INTERIORES HASTA VIGAS 1 5.30 3.25 17.23
MUROS INTERIORES HASTA VIGAS 1 2.45 3.25 7.96
MUROS INTERIORES HASTA VIGAS 1 5.30 3.25 17.23

PABELLON 03
AULA P-04
MUROS INTERIORES HASTA VIGAS 1 5.80 3.25 18.85
MUROS INTERIORES HASTA VIGAS 1 5.30 3.25 17.23

AULA P-05
MUROS INTERIORES HASTA VIGAS 1 5.80 3.25 18.85

ESCALERA
MUROS INTERIORES HASTA VIGAS 1 7.75 3.25 25.19

DIRECCION, SECRETARIA, SALA PROF.


MUROS INTERIORES HASTA TECHO 1 5.30 3.25 17.23
MUROS INTERIORES HASTA TECHO 1 5.80 3.25 18.85

PABELLON I-1
ESCALERA
MUROS INTERIORES HASTA TECHO 2 5.50 3.25 35.75
MUROS INTERIORES HASTA TECHO 1 2.45 3.25 7.96

AULA I-01
MUROS INTERIORES HASTA TECHO 1 6.00 3.25 19.50
MUROS INTERIORES HASTA TECHO 1 5.20 3.25 16.90
PUERTA P-04 -1 0.80 2.10 -1.68

SS.HH. NIÑOS - NIÑAS


MUROS INTERIORES HASTA TECHO 1 11.10 3.65 40.52
PUERTA P-04 -1 0.80 2.10 -1.68

AULA I-02
MUROS INTERIORES HASTA TECHO 1 6.00 3.25 19.50

SS. HH. NIÑOS NIÑAS


MUROS INTERIORES HASTA TECHO 1 11.50 3.25 37.38
VENTANA V-0OO -1 1.25 0.85 -1.06
PUERTA P-03 -2 0.90 2.10 -3.78
PUERTA P-04 -1 0.80 2.10 -1.68

AULA I-03
HOJA DE METRADOS DE ARQUITECTURA

“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE
OBRA : PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: MUROS Y ALBAÑILERIA

02.01.01 MURO DE LADRILLO KK TIPO IV SOGA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2

ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL


MUROS INTERIORES HASTA TECHO 1 6.25 3.25 20.31

COCINA - ALMACEN
COCINA - ALMACEN
MUROS INTERIORES HASTA TECHO 1 5.65 3.25 18.36

SS. HH PABELLON S-3


MUROS INTERIORES HASTA TECHO 1 12.80 3.25 41.60
MUROS INTERIORES HASTA TECHO 1 12.38 3.25 40.24

SS. HH PABELLON S-2


MUROS INTERIORES HASTA TECHO 1 15.66 3.25 50.90
MUROS INTERIORES HASTA TECHO 1 11.86 3.25 38.55

SEGUNDO PISO
PABELLON P-1
AULA P-06
MUROS INTERIORES HASTA VIGAS 1 11.60 3.25 37.70

ESCALERA
MUROS INTERIORES HASTA VIGAS 1 7.30 3.25 23.73

AULA P-07-08
MUROS INTERIORES HASTA VIGAS 1 16.90 3.25 54.93

PABELLON P-3
AULA P-09-10
MUROS INTERIORES HASTA VIGAS 1 16.90 3.25 54.93

ESCALERA
MUROS INTERIORES HASTA VIGAS 1 7.50 3.25 24.38

AULA P-11
MUROS INTERIORES HASTA VIGAS 1 11.10 3.25 36.08

PABELLON P-2
AULA P-12-13
MUROS INTERIORES HASTA VIGAS 3 6.05 3.25 58.99

ESCALERA
MUROS INTERIORES HASTA VIGAS 1 9.00 3.25 29.25

LABORATORIO
MUROS INTERIORES HASTA VIGAS 2 6.05 3.25 39.33

AULA PSICOMOTRIZ - AULA I-04


MUROS INTERIORES HASTA VIGAS 1 26.92 3.25 87.49

ESCALERA
MUROS INTERIORES HASTA VIGAS 1 13.45 3.25 43.71

PABELLON S-3
AULA INNOVACION - CONECTIVIDAD
MUROS INTERIORES HASTA VIGAS 1 24.15 3.25 78.49

PABELLON S-2
AULA S-10-11
MUROS INTERIORES HASTA VIGAS 1 29.95 3.25 97.34

TERCER PISO
PABELLON P-01
AULA P-14
MUROS INTERIORES HASTA VIGAS 1 11.35 3.63 41.14

ESCALERA
MUROS INTERIORES HASTA VIGAS 1 7.55 3.63 27.37

AULA P-15-16
HOJA DE METRADOS DE ARQUITECTURA

“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE
OBRA : PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: MUROS Y ALBAÑILERIA

02.01.01 MURO DE LADRILLO KK TIPO IV SOGA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2

ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL


MUROS INTERIORES HASTA VIGAS 1 16.90 3.63 61.26

PABELLON P-03
AULA P-147-18
MUROS INTERIORES HASTA VIGAS 1 16.65 3.63 60.36

ESCALERA
MUROS INTERIORES HASTA VIGAS 1 7.55 3.63 27.37

AULA P-19
MUROS INTERIORES HASTA VIGAS 1 11.31 3.63 40.98

PABELLON P-02
BIBLIOTECA - DEPOSITO
MUROS INTERIORES HASTA VIGAS 1 11.60 3.63 42.05

ESCALERA
MUROS INTERIORES HASTA VIGAS 1 7.55 3.63 27.37

AREA CONECTIVIDAD
MUROS INTERIORES HASTA VIGAS 1 11.60 3.63 42.05

PABELLON S-3
AULA DE INNOVACION
MUROS INTERIORES HASTA VIGAS 1 11.10 3.63 40.24

ESCALERA
MUROS INTERIORES HASTA VIGAS 1 12.85 3.63 46.58

PABELLON S-2
AULA S-12-13
MUROS INTERIORES HASTA VIGAS 1 16.90 3.63 61.26

ESCALERA
MUROS INTERIORES HASTA VIGAS 1 7.55 3.63 27.37

TOTAL 1,925.62

02.01.03 MURO DE LADRILLO KK TIPO IV CANTO M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2


ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL

PRIMER PISO
SSHH PABELLON I-01
MUROS INTERIORES 1 2.60 1.85 4.81

SSHH PABELLON I-01


MUROS INTERIORES 4 1.10 1.85 8.14
MUROS INTERIORES 2 0.70 1.85 2.59

SS.HH VARONES Y MUJERES PABELLON 2


MUROS INTERIORES 1 6.13 1.85 11.34

SS.HH NIÑAS PABELLON 2


MUROS INTERIORES 7 1.50 1.85 19.43

SS.HH NIÑOS PABELLON 2


MUROS INTERIORES 7 1.50 1.85 19.43

SEGUNDO PISO
SSHH NIÑOS - NIÑAS
MUROS INTERIORES 1 5.80 1.85 10.73

TOTAL 76.46
HOJA DE METRADOS DE ARQUITECTURA

“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE
OBRA : PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: MUROS Y ALBAÑILERIA

02.01.01 MURO DE LADRILLO KK TIPO IV SOGA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2

ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL

02.01.04 FIERRO REFUERZO HORIZONTAL EN MUROS DIMENSIONES N° DE MECHAS M


ITEM DESCRIPCION N°VECES L CANTIDAD H 3MECHAS @1M TOTAL

PRIMER PISO
PABELLON P-1
AULA P-01
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.05 3.00 17.52

AULA P-02
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.05 3.00 17.52

AULA P-03
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.05 3.00 17.52

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.75 2.00 5.84

PABELLON P-2
SS.HH - NIÑOS
MUROS INTERIORES DE 2.10m 2 0.73 2.00 1.85 6.00 17.52
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 1.85 6.00 17.52
MUROS INTERIORES, DE 3.25m 4 0.73 2.00 3.00 10.00 58.4
MUROS INTERIORES, DE 2.95m 4 0.73 2.00 2.60 8.00 46.72

SS.HH - DISCAPACIDAD
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 2.95m 4 0.73 2.00 2.70 9.00 52.56

SS. HH. NIÑAS


MUROS INTERIORES DE 2.10m 2 0.73 2.00 1.85 6.00 17.52
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 1.85 6.00 17.52
MUROS INTERIORES, DE 3.25m 2 0.73 2.00 3.00 10.00 29.2
MUROS INTERIORES, DE 2.95m 4 0.73 2.00 2.60 8.00 46.72

SS. HH. HOMBRES Y MUJERES


MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 3.25m 4 0.73 2.00 3.00 10.00 58.4

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.75 2.00 5.84

PABELLON P-3
AULA P-04
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.05 3.00 17.52

AULA P-05
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.05 3.00 17.52

DIRECCION, SECRETARUA. SAL DE PROF. SUBDIR


MUROS INTERIORES DE 2.10m 6 0.73 2.00 1.85 6.00 52.56
MUROS INTERIORES, DE 1.30m 6 0.73 2.00 1.05 3.00 26.28

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.75 2.00 5.84

PABELLON I-1
ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.75 2.00 5.84

AULA I-01
HOJA DE METRADOS DE ARQUITECTURA

“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE
OBRA : PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: MUROS Y ALBAÑILERIA

02.01.01 MURO DE LADRILLO KK TIPO IV SOGA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2

ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL


MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.05 3.00 17.52

SS. HH. NIÑOS (as)


MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 3.25m 4 0.73 2.00 3.00 10.00 58.4

AULA I-02
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.05 3.00 17.52

SS.HH. NIÑOS-NIÑAS
MUROS INTERIORES DE 2.10m 2 0.73 2.00 1.85 6.00 17.52
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 1.85 6.00 17.52
MUROS INTERIORES, DE 3.25m 4 0.73 2.00 3.00 10.00 58.4

AULA I-03
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.05 3.00 17.52

SUM
MUROS INTERIORES DE 2.10m 6 0.73 2.00 1.85 6.00 52.56
MUROS INTERIORES, DE 1.30m 6 0.73 2.00 1.05 3.00 26.28

COCINA ALMACEN
MUROS INTERIORES DE 2.10m 2 0.73 2.00 1.85 6.00 17.52
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 1.85 6.00 17.52
MUROS INTERIORES, DE 3.25m 5 0.73 2.00 3.00 10.00 73

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.75 2.00 5.84

PABELLON S-3
SS.HH NIÑOS
MUROS INTERIORES DE 2.10m 12 0.73 2.00 1.85 6.00 105.12
MUROS INTERIORES, DE 3.25m 8 0.73 2.00 3.00 10.00 116.8

SS.HH NIÑAS
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 3.25m 6 0.73 2.00 3.00 10.00 87.6

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.75 2.00 5.84

PABELLON S-2
AULA S-4
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.05 3.00 17.52

AULA S-5
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.85 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.05 3.00 17.52

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.75 2.00 5.84

SEGUNDO PISO
PABELLON P-01
AULA P-06
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

AULA P-07
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

AULA P-08
HOJA DE METRADOS DE ARQUITECTURA

“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE
OBRA : PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: MUROS Y ALBAÑILERIA

02.01.01 MURO DE LADRILLO KK TIPO IV SOGA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2

ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL


MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.85 2.00 5.84

PABELLON P-03
AULA P-09
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

AULA P-10
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

AULA P-11
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.85 2.00 5.84

PABELLON P-02
AULA P-12
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

AULA P-13
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

LABORATORIO
MUROS INTERIORES DE 2.10m 8 0.73 2.00 1.95 6.00 70.08
MUROS INTERIORES, DE 1.30m 8 0.73 2.00 1.15 3.00 35.04

AULA SPICOMOTRIZ
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

SS. HH. NIÑOS - NIÑAS


MUROS INTERIORES DE 2.10m 8 0.73 2.00 1.95 6.00 70.08
MUROS INTERIORES, DE 3.25m 4 0.73 2.00 3.10 10.00 58.4

AULA I-4
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.85 2.00 5.84

PABELLON S-3
AULA DE INNOVACIÓN
MUROS INTERIORES DE 2.10m 16 0.73 2.00 1.95 6.00 140.16
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 3.10 10.00 58.4

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.85 2.00 5.84

PABELLON S-2
AULA S-10
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

AULA S-11
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

ESCALERA
HOJA DE METRADOS DE ARQUITECTURA

“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE
OBRA : PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: MUROS Y ALBAÑILERIA

02.01.01 MURO DE LADRILLO KK TIPO IV SOGA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2

ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL


MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.85 2.00 5.84

MUROS BAAJOS EN LOS PASILLOS


MUROS INTERIORES HASTA VIGAS 1 218.28 1.00 218.28

TERCER PISO
PABELLON P-1
AULA - P-14
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

AULA - P-15
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

AULA - P-16
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.85 2.00 5.84

PABELLON P-3
AULA P-17
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

AULA P-18
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

AULA P-19
MUROS INTERIORES DE 2.10m 4 0.73 2.00 1.95 6.00 35.04
MUROS INTERIORES, DE 1.30m 4 0.73 2.00 1.15 3.00 17.52

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.85 2.00 5.84

PABELLON P-2
BIBLIOTECA DEPOSITO
MUROS INTERIORES DE 2.10m 10 0.73 2.00 1.95 6.00 87.6
MUROS INTERIORES, DE 1.30m 12 0.73 2.00 1.15 3.00 52.56

AULA INNOVACION - CONECTIVIDAD


MUROS INTERIORES DE 2.10m 8 0.73 2.00 1.95 6.00 70.08
MUROS INTERIORES, DE 1.30m 8 0.73 2.00 1.15 3.00 35.04
MUROS INTERIORES, DE 3.25m 2 0.73 2.00 3.10 10.00 29.2
MUROS INTERIORES, DE 2.85m 2 0.73 2.00 2.60 8.00 23.36

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.75 2.00 5.84

PABELLON S-3
AULA INNOVACION AREA CONECTIVIDAD
MUROS INTERIORES DE 2.10m 16 0.73 2.00 1.85 6.00 140.16
MUROS INTERIORES, DE 3.25m 2 0.73 2.00 3.00 10.00 29.2
MUROS INTERIORES, DE 2.85m 2 0.73 2.00 2.60 8.00 23.36

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.85 2.00 5.84

PABELLON S-2
AULA S-12 - S-13
MUROS INTERIORES DE 2.10m 6 0.73 2.00 1.95 6.00 52.56
MUROS INTERIORES, DE 1.30m 6 0.73 2.00 1.15 3.00 26.28

ESCALERA
MUROS INTERIORES, DE 1.30m 2 0.73 2.00 0.85 2.00 5.84
HOJA DE METRADOS DE ARQUITECTURA

“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE
OBRA : PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: MUROS Y ALBAÑILERIA

02.01.01 MURO DE LADRILLO KK TIPO IV SOGA M : 1:1:4 e=1.5cm DIMENSIONES UNIDAD M2

ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL

MUROS BAAJOS EN LOS PASILLOS


MUROS INTERIORES HASTA VIGAS 1 185.91 1.00 185.91

TOTAL 3871.92

0 REFUERZO EN MUROS DE CANTO DIMENSIONES UNIDAD M2


ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL

PRIMER PISO
SSHH PABELLON I-01
MUROS INTERIORES, DE 2.10m 62 0.73 2.00 1.85 6.00 543.12

SEGUNDO PISO
SSHH NIÑOS - NIÑAS
MUROS INTERIORES, DE 2.10m 12 0.73 2.00 1.85 6.00 105.12

TOTAL 648.24

M 4520.16
PESO DE ALAMBRE N° 8 0.18

TOTAL KG 813.6288

02.01.05 MURO DE LADRILLO EN CERCO EXTERIORES DIMENSIONES UNIDAD M2


ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL

AV. BLAS DE ATIENZA


MUROS CARAVISTA 1 2.10 2.50 5.25
MUROS CARAVISTA 12 2.75 2.50 82.50
MUROS CARAVISTA 1 2.83 2.50 7.08
MUROS CARAVISTA 1 4.10 2.50 10.25
0.00
JIRON 3
MUROS CARAVISTA 1 2.20 2.50 5.50
MUROS CARAVISTA 1 2.28 2.50 5.69
MUROS CARAVISTA 9 2.75 2.50 61.88

TOTAL 178.14
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

PRIMER PISO
PABELLON I-1
SSHH NIÑOS PABELLON INICIAL 1 19.90 1.80 35.82
SSHH NIÑAS PABELLON INICIAL 1 19.90 1.80 35.82
PUERTAS -2 0.90 1.80 -3.24
SSHH NIÑOS PABELLON INICIAL 1 13.45 1.80 24.21
SSHH NIÑAS PABELLON INICIAL 1 10.45 1.80 18.81
PUERTAS -2 0.90 1.80 -3.24
COCINA 1 18.09 1.80 32.56
ALMACEN 1 14.47 1.80 26.05
PUERTAS -2 1.00 1.80 -3.60
VENTANA ALMACEN -1 4.05 0.50 -2.03
VENTANA PASE COCINA -1 2.00 0.60 -1.20
PABELLON P-2
SSHH NIÑOS 1 51.00 1.80 91.80
SSHH NIÑAS 1 45.00 1.80 81.00
PUERTAS -2 1.00 1.80 -3.60
SSHH DISC 1 10.27 1.80 18.49
SSHH DISC 1 10.27 1.80 18.49
PUERTAS -2 1.00 1.80 -3.60
SS. HH. H 1 20.41 1.80 36.74
SS. HH. M 1 20.41 1.80 36.74
PUERTAS -2 1.00 1.80 -3.60

PABELLON S-3
SSHH NIÑOS 1 36.05 1.80 64.89
SSHH NIÑAS 1 36.45 1.80 65.61
PUERTAS -2 1.00 1.80 -3.60
SSHH DISC 1 11.75 1.80 21.15
SSHH DISC 1 11.75 1.80 21.15
PUERTAS -2 1.00 1.80 -3.60
SEGUNDO PISO
PABELLON I-1
SSHH NIÑOS 1 19.93 1.80 35.87
SSHH NIÑAS 1 19.90 1.80 35.82
PUERTAS -2 0.90 1.80 -3.24

TOTAL 666.47

02.02.02 TARRAJEO EN MUROS INTERIORES DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

PRIMER PISO
PABELLON P-01
AULA P-01 MURO AP-01 AC-01 1 34.17 2.95 100.80
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA ALTA -2 4.15 0.85 -7.06
VENTANA BAJA -2 4.15 1.65 -13.70
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-02 MURO AP-02 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.08 1.65 -13.32
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-03 MURO AP-03 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.24 1.65 -13.60
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 2.95 45.73


MURO 1 5.40 2.95 15.93
VENTANA ALTA -1 2.70 1.95 -5.27
CONTRAZOCALO -1 0.10 0.00

PABELLON I-01
ESCALERA MURO 1 15.90 2.95 46.91
MURO 1 6.40 2.95 18.88
VENTANA ALTA -1 2.00 1.95 -3.90
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
CONTRAZOCALO -1 0.10 0.00

AULA I - 01 MURO AI-01 AC-02 1 34.74 2.95 102.48


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -2 4.15 1.65 -13.70
VENTANA ALTA -2 4.15 0.85 -7.06
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA I - 02 MURO AI-02 AC-02 1 34.70 2.95 102.37


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -2 4.15 1.65 -13.70
VENTANA ALTA -2 4.15 0.85 -7.06
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

SS.HH - NIÑOS MURO SHN - 01 AC-03 1 14.10 1.45 20.45


MURO -1 2.03 0.30 -0.61
VENTANA ALTA -1 2.03 0.85 -1.73
PUERTA -1 0.90 2.10 -1.89
ZOCALO -1 16.52 1.80 -29.74

SS.HH - NIÑAS MURO SHN - 02 AC-03 1 14.10 1.45 20.45


MURO -1 2.03 0.30 -0.61
VENTANA ALTA -1 2.03 0.85 -1.73
PUERTA P-04 -1 0.90 2.10 -1.89
ZOCALO -1 1.80 0.00
0.00
DEPOSITO MURO 1 7.11 3.25 23.11
MURO -1 2.03 0.30 -0.61
VENTANA ALTA -1 2.03 0.85 -1.73
PUERTA P-04 -1 0.80 2.10 -1.68
CONTRAZOCALO -1 0.10 0.00
0.00
DEPOSITO MURO 1 7.11 3.25 23.11
MURO -1 2.03 0.30 -0.61
VENTANA ALTA -1 2.03 0.85 -1.73
PUERTA P-04 -1 0.80 2.10 -1.68
CONTRAZOCALO -1 0.10 0.00
0.00
SS.HH - NIÑOS MURO SHN - 03 AC-03 1 10.26 1.45 14.87
MURO -1 1.90 0.30 -0.57
VENTANA ALTA -1 2.03 0.85 -1.73
PUERTA -1 0.90 2.10 -1.89
ZOCALO -1 16.52 1.80 -29.74

SS.HH - NIÑAS MURO SHN - 04 AC-03 1 8.45 1.45 12.25


MURO -1 1.90 0.30 -0.57
VENTANA ALTA -1 1.90 0.85 -1.62
PUERTA P-04 -1 0.90 2.10 -1.89
ZOCALO -1 1.80 0.00
0.00
DEPOSITO MURO 1 6.97 3.25 22.65
VENTANA ALTA -1 1.25 0.85 -1.06
PUERTA P-04 -1 0.80 2.10 -1.68
CONTRAZOCALO -1 0.10 0.00
0.00
AULA I - 03 MURO AI-03 AC-02 1 34.71 2.95 102.39
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 7.83 0.85 -6.66
VENTANA ALTA -1 7.82 1.65 -12.90
PUERTA -1 1.10 2.10 -2.31
PUERTA -1 2.60 2.10 -5.46
CONTRAZOCALO -1 0.10 0.00

AULAS EXTERIORES MUROS EN PATIO 4 3.00 1.25 15.00


0.00
PABELLON P-03
AULA P-04 MURO AP - 04 AC-01 1 33.80 2.95 99.71
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.28 1.65 -13.66
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-05 MURO AP-05 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.08 1.65 -13.33
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AMBIENTE DE ADMINISTRACION MURO ADM-01 AC-01 1 38.56 2.95 113.75


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.93 1.65 -14.73
VENTANA ALTA -1 8.79 0.85 -7.47
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 3.25 50.38


MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.70 1.95 -5.27
CONTRAZOCALO -1 0.10 0.00

PABELLON P-02
SS. HH. NIÑOS MURO SHV-01 AC-03 1 30.10 2.95 88.80
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA ALTA -2 4.05 0.85 -6.89
PUERTA -1 1.00 2.10 -2.10
CONTRAZOCALO -1 0.10 0.00

SS. H.. DISC MURO SHD -01 AC-03 1 10.27 1.45 14.89
MURO -1 1.84 0.30 -0.55
VENTANA ALTA -1 1.84 0.85 -1.56
PUERTA -1 1.00 0.30 -0.30
CONTRAZOCALO -1 0.10 0.00

SS. H.. DISC MURO SHD - 02 AC-03 1 10.27 1.45 14.89


MURO -1 1.84 0.30 -0.55
VENTANA ALTA -1 1.84 0.85 -1.56
PUERTA -1 1.00 0.30 -0.30
CONTRAZOCALO -1 0.10 0.00

SS. HH. NIÑAS MURO SHV-01 AC-03 1 24.00 1.45 34.80


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA ALTA -2 3.93 0.85 -6.68
PUERTA -1 1.00 2.10 -2.10
CONTRAZOCALO -1 0.10 0.00

SS. HH. H MURO SHP - 01 AC-03 1 14.28 1.45 20.71


MURO -1 4.24 0.30 -1.27
VENTANA ALTA -1 4.24 0.85 -3.60
PUERTA -1 1.00 0.30 -0.30
CONTRAZOCALO -1 0.10 0.00

SS. HH. M MURO SHP - 02 AC-03 1 14.28 1.45 20.71


MURO -1 4.37 0.30 -1.31
VENTANA ALTA -1 4.37 0.85 -3.71
PUERTA -1 1.00 0.30 -0.30
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 3.25 50.38


MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.00 1.95 -3.90
CONTRAZOCALO -1 0.10 0.00

SUMM MURO 1 46.93 2.95 138.44


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 11.88 1.65 -19.60
VENTANA BAJA -1 9.71 1.65 -16.06
VENTANA ALTA -1 2.20 0.85 -1.87
PUERTA -2 1.10 2.10 -4.62
CONTRAZOCALO -1 0.10 0.00

COCINA MURO CO-01 AC-03 1 18.09 1.45 26.23


MURO -1 4.05 1.45 -5.87
VENTANA ALTA -1 4.05 0.85 -3.44
VENTANA ALTA -1 2.00 1.15 -2.30
PUERTA P-01a -1 1.00 0.30 -0.30
CONTRAZOCALO -1 0.10 0.00

ALMACEN MURO CO-02 AC-03 1 14.47 1.45 20.98


MURO -1 2.00 0.30 -0.60
VENTANA BAJA -1 4.05 1.15 -4.66
PUERTA -2 1.00 0.30 -0.60
CONTRAZOCALO -1 0.10 0.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
PABELLON S-03
SS.HH NIÑOS MURO SHV-02 AC-03 1 21.05 1.15 24.21
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA ALTA -1 8.93 0.85 -7.59
PUERTA -1 1.00 0.30 -0.30
ZOCALO -1 1.80 0.00

SSHH DISCAPACITADOS MURO SHD - 03 AC-03 1 11.75 1.45 17.04


VENTANA ALTA -2 3.10 0.85 -5.27
PUERTA -1 1.00 0.30 -0.30
ZOCALO -1 1.80 0.00
0.00
SSHH DISCAPACITADOS MURO SHD - 03 AC-03 1 11.75 1.45 17.04
PUERTA -1 1.00 0.30 -0.30
VENTANA ALTA -2 3.10 0.85 -5.27
0.00
SS.HH NIÑAS MURO SHV-02 AC-03 1 21.45 1.15 24.67
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA ALTA -1 8.92 0.85 -7.58
PUERTA -1 1.00 0.30 -0.30
ZOCALO -1 1.80 0.00

ESCALERA MURO 1 21.90 3.25 71.18


VENTANA BAJA -1 2.00 1.95 -3.90
0.00
PABELLON S-02
ESCALERA MURO 1 21.90 3.25 71.18
VENTANA BAJA -1 2.00 1.95 -3.90
0.00
AULA S-04 MURO A5-04 AC-01 1 34.18 2.95 100.83
MURO 2 6.05 0.30 3.63
VENTANA -1 7.97 0.85 -6.77
VENTANA -1 8.08 1.65 -13.33
PUERTA -1 1.10 2.10 -2.31

AULA S-05 MURO A5-04 AC-01 1 34.12 2.95 100.65


MURO 2 6.05 0.30 3.63
VENTANA -1 7.97 0.85 -6.77
VENTANA -1 8.27 1.65 -13.65
PUERTA -1 1.10 2.10 -2.31

SEGUNDO PISO
PABELLON P-01
AULA P-06 MURO AP-06 AC-01 1 34.17 2.95 100.80
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA ALTA -2 4.15 0.85 -7.06
VENTANA BAJA -2 4.15 1.65 -13.70
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-07 MURO AP-07 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.08 1.65 -13.32
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-08 MURO AP-08 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.24 1.65 -13.60
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 2.95 45.73


MURO 1 5.40 2.95 15.93
VENTANA ALTA -1 2.70 1.95 -5.27
CONTRAZOCALO -1 0.10 0.00

PABELLON P-03
AULA P-09 MURO AP - 09 AC-01 1 34.17 2.95 100.80
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.28 1.65 -13.66
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
CONTRAZOCALO -1 0.10 0.00

AULA P-10 MURO AP-10 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.08 1.65 -13.33
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-11 MURO AP-11 AC-01 1 38.56 2.95 113.75


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.79 1.65 -14.50
VENTANA ALTA -1 8.79 0.85 -7.47
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 3.25 50.38


MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.70 1.95 -5.27
CONTRAZOCALO -1 0.10 0.00

PABELLON P-02
AULA P-12 MURO AP-12 AC-01 1 33.77 2.95 99.62
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 9.00 1.65 -14.85
VENTANA ALTA -1 9.00 0.85 -7.65
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-13 MURO AP-13 AC-01 1 33.77 2.95 99.62


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 9.01 1.65 -14.87
VENTANA ALTA -1 8.80 0.85 -7.48
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 26.48 0.10 -2.65

LABORATORIO MURO LAB-01 AC-01 1 56.53 2.95 166.76


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 18.02 1.65 -29.73
VENTANA ALTA -1 18.02 0.85 -15.32
PUERTA P-01 -2 1.10 2.10 -4.62
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 3.25 50.38


MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.70 1.95 -5.27
CONTRAZOCALO -1 0.10 0.00

PABELLON I-01
AULA PSICOMOTRIZ MURO PSI-01 AC-01 1 34.70 2.95 102.37
MURO 1 24.80 0.75 18.60
MURO 2 6.05 0.68 8.17
VENTANA -2 4.15 0.85 -7.06
VENTANA -2 4.15 1.65 -13.70
PUERTA -1 1.10 2.10 -2.31

AULA I-04 MURO AI - 04 AC-02 1 34.70 2.95 102.37


MURO 2 6.05 0.30 3.63
VENTANA BAJA -2 4.15 1.65 -13.70
VENTANA ALTA -2 4.15 0.85 -7.06
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

SS. HH. NIÑOS MURO SHN - 01 AC-03 1 14.30 1.45 20.74


MURO -1 2.03 0.30 -0.61
VENTANA ALTA -1 2.03 0.85 -1.73
PUERTA -1 0.90 0.30 -0.27
CONTRAZOCALO -1 0.10 0.00

SS. HH. NIÑAS MURO SHN - 02 AC-03 1 14.10 1.45 20.45


MURO -1 2.03 0.30 -0.61
VENTANA ALTA -1 2.03 0.85 -1.73
PUERTA -1 0.90 0.30 -0.27
CONTRAZOCALO -1 0.10 0.00

DEPOSITO MURO 1 7.12 3.25 23.14


MURO -1 2.03 0.30 -0.61
VENTANA -1 2.03 0.85 -1.73
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
PUERTA -1 0.80 2.10 -1.68
CONTRAZOCALO -1 0.10 0.00

DEPOSITO MURO 1 7.12 3.25 23.14


MURO -1 2.03 0.30 -0.61
VENTANA -1 2.03 0.85 -1.73
PUERTA -1 0.80 2.10 -1.68
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.90 3.25 51.68


MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.00 1.95 -3.90
CONTRAZOCALO -1 0.10 0.00

PABELLON S-3
AULA INNOVACION MURO INN-01 AC-01 1 41.24 2.95 121.66
MURO 2 6.05 0.30 3.63
VENTANA BAJA -1 7.99 1.65 -13.18
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -2 1.10 2.10 -4.62
PUERTA -1 1.00 2.10 -2.10

DEPOSITO TIC MURO TIC-01 AC-01 1 17.56 2.95 51.80


MURO 1 6.26 0.30 1.88
PUERTA -1 1.00 2.10 -2.10

AREA DE CONECTIVIDAD MURO ARC-01 AC-01 1 22.52 2.95 66.43


MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 4.05 1.65 -6.68
VENTANA ALTA -1 4.05 0.85 -3.44
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00
0.00
ESCALERA MURO 1 15.90 3.25 51.68
MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.00 1.95 -3.90

PABELLON S-2
ESCALERA MURO 1 15.90 3.25 51.68
MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.00 1.95 -3.90

AULA S-10 MURO AS-10 AC-01 1 34.18 2.95 100.83


MURO 2 6.05 0.30 3.63
VENTANA BAJA -1 7.97 0.85 -6.77
VENTANA ALTA -1 8.08 1.65 -13.33
PUERTA -1 1.10 2.10 -2.31

AULA S-11 MURO AS-11 AC-01 1 34.18 2.95 100.83


MURO 2 6.05 0.30 3.63
VENTANA BAJA -1 8.07 0.85 -6.86
VENTANA ALTA -1 8.27 1.65 -13.65
PUERTA -1 1.10 2.10 -2.31

TERCER PISO
PABELLON P-01
AULA P-14 MURO AP-14 AC-01 1 34.17 2.95 100.80
MURO 1 6.05 0.68 4.08
MURO 1 6.05 0.68 4.08
VENTANA ALTA -2 4.15 0.85 -7.06
VENTANA BAJA -2 4.15 1.65 -13.70
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-15 MURO AP-15 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.68 4.08
MURO 1 6.05 0.68 4.08
VENTANA BAJA -1 8.08 1.65 -13.32
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-16 MURO AP-16 AC-01 1 34.17 2.95 100.80


MURO 1 33.80 0.75 25.35
MURO 1 6.05 0.68 4.11
MURO 1 6.05 0.68 4.11
VENTANA BAJA -1 8.24 1.65 -13.60
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 2.95 45.73


PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
MURO 1 5.40 2.95 15.93
VENTANA ALTA -1 2.70 1.95 -5.27
CONTRAZOCALO -1 0.10 0.00

PABELLON P-03
AULA P-17 MURO AP - 17 AC-01 1 34.17 2.95 100.80
MURO 1 6.05 0.68 4.11
MURO 1 6.05 0.68 4.11
VENTANA BAJA -1 8.28 1.65 -13.66
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-18 MURO AP-18 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.68 4.11
MURO 1 6.05 0.68 4.11
VENTANA BAJA -1 8.08 1.65 -13.33
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-19 MURO AP-19 AC-01 1 38.56 2.95 113.75


MURO 1 35.30 0.75 26.48
MURO 1 6.05 0.68 4.11
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.79 1.65 -14.50
VENTANA ALTA -1 8.79 0.85 -7.47
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 3.25 50.38


MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.70 1.95 -5.27
CONTRAZOCALO -1 0.10 0.00

PABELLON P-02
BIBLIOTECA MURO 1 45.64 2.95 134.64
MURO 1 6.05 0.68 4.11
PUERTA -2 1.10 2.10 -4.62
VENTANA ALTA -1 13.59 0.85 -11.55
VENTANA BAJA -1 13.59 1.65 -22.42
PUERTA -1 0.90 2.10 -1.89

DEPOSITO MURO 1 22.40 2.95 66.08


MURO 1 6.05 0.68 4.11
VENTANA 1 4.75 1.75 8.31
VENTANA BAJA -1 4.43 1.65 -7.30
VENTANA ALTA -1 4.43 0.85 -3.77
PUERTA -1 0.90 2.10 -1.89

ESCALERA MURO 1 15.90 3.25 51.68


MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.70 1.95 -5.27

AREA DE CONECTIVIDAD MURO ARC AC-01 1 22.52 2.95 66.43


MURO 1 6.05 0.68 4.08
VENTANA BAJA -1 4.43 1.65 -7.31
VENTANA ALTA -1 4.43 0.85 -3.77
PUERTA -1 1.10 2.10 -2.31

DEPOSITO TIC MURO ARC AC-01 1 17.55 2.95 51.77


MURO 1 6.05 0.68 4.11
VENTANA BAJA -1 4.26 1.65 -7.03
VENTANA ALTA -1 4.58 0.85 -3.89
PUERTA -1 0.90 2.10 -1.89

AULA DE INNOVACION MURO INN-03 AC-01 1 40.43 2.95 119.27


MURO 2 6.05 0.68 8.17
MURO 1 20.25 0.75 15.19
VENTANA BAJA -1 9.01 1.65 -14.87
VENTANA ALTA -1 9.01 0.85 -7.66
PUERTA -2 1.10 2.10 -4.62
PUERTA -1 0.90 2.10 -1.89

PABELLON S-03
AULA INNOVACION MURO INN-01 AC-01 1 41.24 2.95 121.66
MURO 2 6.05 0.68 8.17
VENTANA BAJA -1 7.99 1.65 -13.18
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -2 1.10 2.10 -4.62
PUERTA -1 1.00 2.10 -2.10

DEPOSITO TIC MURO TIC-01 AC-01 1 17.56 2.95 51.80


PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
MURO 1 6.26 0.30 1.88
PUERTA -1 1.00 2.10 -2.10

AREA DE CONECTIVIDAD MURO ARC-01 AC-01 1 22.52 2.95 66.43


MURO 1 20.25 0.75 15.19
MURO 1 6.05 0.68 4.08
VENTANA BAJA -1 4.05 1.65 -6.68
VENTANA ALTA -1 4.05 0.85 -3.44
PUERTA -1 1.10 2.10 -2.31
0.00
ESCALERA MURO 1 15.90 3.25 51.68
MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.00 1.95 -3.90

PABELLON S-2
ESCALERA MURO 1 15.90 3.25 51.68
MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.00 1.95 -3.90

AULA S-12 MURO AS-12 AC-01 1 34.18 2.95 100.83


MURO 1 10.00 0.75 7.50
MURO 2 6.05 0.68 8.17
VENTANA BAJA -1 7.97 0.85 -6.77
VENTANA ALTA -1 8.08 1.65 -13.33
PUERTA -1 1.10 2.10 -2.31

AULA S-13 MURO AS-13 AC-01 1 34.18 2.95 100.83


MURO 1 10.00 0.75 7.50
MURO 2 6.05 0.68 8.17
VENTANA BAJA -1 8.07 0.85 -6.86
VENTANA ALTA -1 8.27 1.65 -13.65
PUERTA -1 1.10 2.10 -2.31

0.375

TOTAL 5224.43

02.02.03 TARRAJEO EN MUROS EXTERIORES DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

PRIMER PISO
PABELLON P-1 MURO EXT 1 82.99 3.25 269.72
MURO EXT 1 45.65 0.25 11.41
VENTANA ALTA -1 24.26 0.85 -20.62
VENTANA BAJA -1 24.66 1.65 -40.69
VENTANA BAJA -1 2.70 1.95 -5.27
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
0.00
PABELLON P-3 MURO EXT 1 84.78 3.25 275.54
MURO EXT 1 48.89 0.25 12.22
VENTANA ALTA -1 28.80 0.85 -24.48
VENTANA BAJA -1 25.29 1.65 -41.73
VENTANA BAJA -1 2.70 1.95 -5.27
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
0.00
PABELLON P-2 MURO EXT 1 107.73 3.25 350.12
MURO EXT 1 57.95 0.25 14.49
VENTANA ALTA -1 32.30 0.85 -27.46
VENTANA BAJA -1 27.84 1.65 -45.94
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -2 1.10 2.10 -4.62
PUERTA -6 1.00 2.10 -12.60
VACIO ESCAL -1 2.70 3.25 -8.78
0.00
PABELLON I-1 MURO EXT 1 70.97 3.25 230.65
MURO EXT 1 42.05 0.25 10.51
VENTANA ALTA -1 24.72 0.85 -21.01
VENTANA BAJA -4 4.15 1.65 -27.39
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -2 1.10 2.10 -4.62
PUERTA -2 0.90 2.10 -3.78
VACIO ESCAL -1 2.70 3.25 -8.78
0.00
PABELLON AULA I-03 MURO EXT 1 38.83 4.80 186.38
MURO EXT 26.15 0.25 0.00
VENTANA ALTA -1 12.88 0.85 -10.95
VENTANA BAJA -1 7.82 1.65 -12.90
PUERTA -1 1.10 2.10 -2.31
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
0.00
PABELLON S-3 MURO EXT 1 72.10 3.25 234.33
MURO EXT 1 14.65 0.25 3.66
VENTANA ALTA -1 30.25 0.85 -25.71
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -4 1.00 2.10 -8.40
VACIO ESCAL -1 2.70 3.25 -8.78
0.00
PABELLON S-4 MURO EXT 1 61.31 3.25 199.26
MURO EXT 1 37.15 0.25 9.29
VENTANA ALTA -1 15.94 0.85 -13.55
VENTANA BAJA -1 16.35 1.65 -26.98
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -2 1.10 2.10 -4.62
VACIO ESCAL -1 2.70 3.25 -8.78
0.00
SEGUNDO PISO
PABELLON P-1 MURO EXT 1 82.99 3.25 269.72
MURO EXT 1 45.65 0.25 11.41
VENTANA ALTA -1 24.26 0.85 -20.62
VENTANA BAJA -1 24.66 1.65 -40.69
VENTANA BAJA -1 2.70 1.95 -5.27
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 40.25 2.40 96.60
0.00
PABELLON P-3 MURO EXT 1 84.78 3.25 275.54
MURO EXT 1 48.89 0.25 12.22
VENTANA ALTA -1 28.80 0.85 -24.48
VENTANA BAJA -1 25.29 1.65 -41.73
VENTANA BAJA -1 2.70 1.95 -5.27
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 36.05 2.40 86.52
0.00
PABELLON P-2 MURO EXT 1 102.19 3.25 332.12
MURO EXT 1 57.60 0.25 14.40
VENTANA ALTA -1 30.79 0.85 -26.17
VENTANA BAJA -1 33.49 1.65 -55.26
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -4 1.10 2.10 -9.24
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 54.30 2.40 130.32
0.00
PABELLON I-1 MURO EXT 1 70.67 3.25 229.68
MURO EXT 1 42.05 0.25 10.51
MURO EXT 1 28.55 0.79 22.55
MURO EXT 2 6.75 0.55 7.43
VENTANA ALTA -1 24.72 0.85 -21.01
VENTANA BAJA -4 4.15 1.65 -27.39
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -2 1.10 2.10 -4.62
PUERTA -2 0.80 2.10 -3.36
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 32.13 2.40 77.11
0.00
PABELLON S-3 MURO EXT 1 72.10 3.25 234.33
MURO EXT 1 37.15 0.25 9.29
VENTANA ALTA -1 30.25 0.85 -25.71
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -4 1.00 2.10 -8.40
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 27.65 2.40 66.36
0.00
PABELLON S-4 MURO EXT 1 61.25 3.25 199.06
MURO EXT 1 37.15 0.25 9.29
VENTANA ALTA -1 16.04 0.85 -13.63
VENTANA BAJA -1 16.35 1.65 -26.98
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 27.65 2.40 66.36
0.00
TERCER PISO
PABELLON P-1 MURO EXT 1 82.99 3.25 269.72
MURO EXT 1 45.65 0.25 11.41
MURO EXT 1 34.30 0.79 27.10
MURO EXT 2 6.55 0.55 7.21
VENTANA ALTA -1 24.26 0.85 -20.62
VENTANA BAJA -1 24.66 1.65 -40.69
VENTANA BAJA -1 2.70 1.95 -5.27
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
MUROS BAJOS 1 40.25 2.40 96.60
0.00
PABELLON P-3 MURO EXT 1 84.78 3.25 275.54
MURO EXT 1 48.89 0.25 12.22
MURO EXT 1 35.80 0.79 28.28
MURO EXT 2 6.55 0.55 7.21
VENTANA ALTA -1 27.80 0.85 -23.63
VENTANA BAJA -1 27.82 1.65 -45.90
VENTANA BAJA -1 2.70 1.95 -5.27
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 36.05 2.40 86.52
0.00
PABELLON P-2 MURO EXT 1 102.19 3.25 332.12
MURO EXT 1 57.60 0.25 14.40
MURO EXT 1 44.50 0.79 35.16
MURO EXT 2 6.55 0.55 7.21
VENTANA ALTA -1 30.79 0.85 -26.17
VENTANA BAJA -1 33.49 1.65 -55.26
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -4 1.10 2.10 -9.24
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 54.30 2.40 130.32
0.00
PABELLON S-3 MURO EXT 1 72.10 3.25 234.33
MURO EXT 1 37.15 0.25 9.29
MURO EXT 1 24.05 0.79 19.00
MURO EXT 2 6.55 0.55 7.21
VENTANA ALTA -1 15.96 0.85 -13.57
VENTANA BAJA -1 15.97 1.65 -26.35
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 27.65 2.40 66.36
0.00
PABELLON S-4 MURO EXT 1 61.25 3.25 199.06
MURO EXT 1 37.15 0.25 9.29
MURO EXT 1 24.05 0.79 19.00
MURO EXT 2 6.55 0.55 7.21
VENTANA ALTA -1 16.04 0.85 -13.63
VENTANA BAJA -1 16.35 1.65 -26.98
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 27.65 2.40 66.36
0.00

TOTAL 4628.69

2.02 TARRAJEO EN MUROS CERCO CODIGO ACABADO DIMENSIONES UNIDAD M2


ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL

AV. BLAS DE ATIENZA


INGRESO SECUNDARIA 2 3.50 4.00 28.00
CASETA 1 14.64 3.00 43.92
TARRAJEO E TACHO 1 7.85 1.50 11.78
PUERTA -1 1.20 2.65 -3.18
MUROS ENCHAPADOS CON LAJA 2 4.05 3.00 24.30
MUROS ENCHAPADOS CON LAJA 2 1.37 3.00 8.22
MUROS ENCHAPADOS CON LAJA 2 0.55 3.00 3.30
MUROS ENCHAPADOS CON LAJA 2 6.25 3.00 37.50
JIRON 3
INGRESO PRIMARIA 2 3.50 4.00 28.00
CASETA 1 14.72 3.00 44.16
TARRAJEO E TECHO 1 7.90 1.50 11.85
PUERTA -1 1.20 2.65 -3.18

INGRESO INICIAL 2 3.50 4.00 28.00


CASETA 1 14.72 3.00 44.16
TARRAJEO E TECHO 1 7.90 1.50 11.85
PUERTA -1 1.20 2.65 -3.18

MUROS ENCHAPADOS CON LAJA 2 4.35 3.00 26.10


MUROS ENCHAPADOS CON LAJA 2 2.55 3.00 15.30
MUROS ENCHAPADOS CON LAJA 2 1.80 3.00 10.80
MUROS ENCHAPADOS CON LAJA 2 7.30 3.00 43.80
MUROS ENCHAPADOS CON LAJA 2 0.90 3.00 5.40
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
TOTAL 416.90

02.02.05 TARRAJEO DE COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

1°PISO PABELLON P-01


12 0.45 3.25 17.55
6 1.70 3.25 33.15

1°PISO PABELLON P-02


12 0.45 3.25 17.55
8 1.70 3.25 44.20

1°PISO PABELLON P-03


10 0.45 3.25 14.63
6 1.70 3.25 33.15
6 0.73 3.25 14.14
2 0.80 3.25 5.20

1°PISO PABELLON I-1


6 0.45 3.25 8.78
8 1.70 3.25 44.20
2 1.10 3.25 7.15

PABELLON S-3
1 2.20 3.25 7.15
3 3.40 3.25 33.15
1 2.10 3.25 6.83

PABELLON S-2
10 0.45 3.25 14.63
4 1.70 3.25 22.10
2°PISO PABELLON P-01
11 0.45 3.25 16.09
6 1.70 3.25 33.15

2°PISO PABELLON P-02


14 0.45 3.25 20.48
10 1.70 3.25 55.25

2°PISO PABELLON P-03


13 0.45 3.25 19.01
8 1.70 3.25 44.20

2°PISO PABELLON I-1


10 0.45 3.25 14.63
4 1.70 3.25 22.10

2°PISO PABELLON S-3


10 0.45 3.25 14.63
4 1.70 3.25 22.10

2°PISO PABELLON S-2


10 0.45 3.25 14.63
4 1.70 3.25 22.10
3°PISO PABELLON P-01
11 0.45 3.25 16.09
6 1.70 3.25 33.15

3°PISO PABELLON P-02


14 0.45 3.25 20.48
10 1.70 3.25 55.25

3°PISO PABELLON P-03


13 0.45 3.25 19.01
8 1.70 3.25 44.20

3°PISO PABELLON I-1


10 0.45 3.25 14.63
4 1.70 3.25 22.10

3°PISO PABELLON S-3


10 0.45 3.25 14.63
4 1.70 3.25 22.10

3°PISO PABELLON S-2


10 0.45 3.25 14.63
4 1.70 3.25 22.10

CERCO CERCO PERIMETRICO


32 0.70 2.50 56.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
6 0.45 2.50 6.75

COLUMNAS EN LA ENTRADA DE PRIMARIA


PRIMER PISO 1 2.85 2.95 8.41
1 4.60 2.95 13.57
2 1.30 2.95 7.67
SEGUNDO PISO 1 2.85 2.95 8.41
1 4.60 2.95 13.57
2 1.30 2.95 7.67
2 1.25 2.95 7.38

TOTAL 1049.73

02.02.06 TARRAJEO DE VIGAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
PABELLON P-01
1⁰ PISO AULA P-01 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
1⁰ PISO AULA P-02 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
1⁰ PISO AULA P-03 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
PABELLON P-03
1⁰ PISO AULA P-04 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
1⁰ PISO AULA P-05 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
1⁰ PISO SALA ADMINISTRATIVA 2 6.05 1.05 12.71
2 11.00 0.85 18.70
4 1.95 0.65 5.07
PABELLON P-02
1⁰ PISO SS. HH. 1 6.05 0.65 3.93
8 4.88 0.85 33.15
5 1.95 0.65 6.34
1⁰ PISO SUM - COCINA 3 6.05 1.05 19.06
8 4.88 0.85 33.15
5 1.95 0.65 6.34
PABELLON I-01
1⁰ PISO AULA I-01 1 6.05 0.65 3.93
4 4.88 0.85 16.58
3 1.95 0.65 3.80
1⁰ PISO AULA I-02 1 6.05 1.05 6.35
1 13.80 0.85 11.73
4 1.95 0.65 5.07
1⁰ PISO AULA I-03 1 6.05 1.05 6.35
1 11.65 0.85 9.90
4 1.95 0.65 5.07
PABELLON S-3
1⁰ PISO SS - HH 1 6.05 0.65 3.93
4 4.88 0.85 16.58
6 1.95 0.65 7.61
1 22.60 0.85 19.21
PABELLON S-2
1⁰ PISO AULA S-4 1 6.05 0.65 3.93
4 4.88 0.85 16.58
4 1.95 0.65 5.07
1⁰ PISO AULA S-5 1 6.05 0.65 3.93
4 4.88 0.85 16.58
2 1.95 0.65 2.54
SEGUNDO PISO
PABELLON P-01
2° PIISO AULA P-06 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
2° PIISO AULA P-07 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
2° PIISO AULA P-08 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
PABELLON P-03
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
2° PIISO AULA P-09 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
2° PIISO AULA P-10 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
2° PIISO AULA 11 2 6.05 1.05 12.71
2 11.00 0.85 18.70
4 1.95 0.65 5.07
PABELLON P-02
2° PIISO AULA P-12 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
2° PIISO AULA 13 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
2° PIISO LABORATORIO 3 6.05 1.05 19.06
8 4.88 0.85 33.15
5 1.95 0.65 6.34
PABELLON I-1
2° PIISO AULA PSICOMOTRIZ 1 6.05 1.05 6.35
4 4.88 0.85 16.59
4 1.95 0.65 5.07
2° PIISO AULA I-04 1 6.05 1.05 6.35
4 4.88 0.85 16.59
3 1.95 0.65 3.80
2° PIISO SS.HH. 2 4.30 0.85 7.31
PABELLON S-3
2° PIISO AULA DE INNOVACION 2 6.05 1.05 12.71
1 6.05 0.50 3.03
2 22.40 0.85 38.08
6 1.95 0.65 7.61
PABELLON S-2
2° PIISO AULA S-10 2 6.05 0.65 7.87
4 4.88 0.85 16.58
3 1.95 0.65 3.80
2° PIISO AULA S-11 1 6.05 0.65 3.93
4 4.88 0.85 16.58
3 1.95 0.65 3.80

TERCER PISO
PABELLON P-01
3ERR PISO AULA P-14 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
3ERR PISO AULA P-15 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
3ERR PISO AULA P-16 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
PABELLON P-03
3ERR PISO AULA P-17 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
3ERR PISO AULA P-18 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
3ERR PISO AULA 19 2 6.05 1.05 12.71
2 11.00 0.85 18.70
4 1.95 0.65 5.07
PABELLON P-02
3ERR PISO BIBLIOTECA 2 6.05 1.05 12.71
6 4.88 0.85 24.86
5 1.95 0.65 6.34
3ERR PISO DEPOSITO 1 6.05 1.05 6.35
2 4.88 0.85 8.29
3ERR PISO AULA DCE INNOVACION 2 6.05 1.05 12.71
8 4.88 0.85 33.15
5 1.95 0.65 6.34
1 6.05 0.55 3.33
PABELLON S-3
3ERR PISO AULA DE INNOVACION 2 6.05 1.05 12.71
1 6.05 0.55 3.33
2 22.40 0.85 38.08
6 1.95 0.65 7.61
PABELLON S-2
3ERR PISO AULA S-12 1 6.05 0.65 3.93
4 4.88 0.85 16.58
3 1.95 0.65 3.80
3ERR PISO AULA S-13 1 6.05 0.65 3.93
4 4.88 0.85 16.58
3 1.95 0.65 3.80
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

CERCO CERCO PERIMETRICO 1 42.78 0.65 27.81


1 33.05 0.65 21.48

VIGAS EN EL INGRESO PRIMARIA 4 5.55 1.80 39.96


2 1.90 1.80 6.84
2 2.00 0.90 3.60
1 8.45 1.80 15.21
1 2.25 1.80 4.05

TOTAL 1399.59

02.02.07 TARRAJEO CON IMPERMEABILIZANTE DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO A L H PARCIAL TOTAL

1°PISO CISTERNA MURO 15.80 1.85 29.23


LOSA DE FONDO 4.6 2.50 11.50
CIELO 4.6 2.50 11.50
T.E MURO 9.80 1.45 14.21
LOSA DE FONDO 2.5 2.40 6.00
CIELO 2.5 2.40 6.00

TOTAL 78.44

02.02.08 VESTIDURA DE DERRAMES (1:5) DIMENSIONES UNIDAD ML


ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
PRIMER PISO
PABELLON P-01
1°PISO AULA P-01 VENTANA BAJA 2 4.15 1.65 14.90
VENTANA ALTA 2 4.15 0.85 11.70
PUERTA 1 2.10 2.10
0.00
AULA P-02 VENTANA BAJA 1 4.05 1.65 7.35
VENTANA BAJA 1 4.03 0.85 5.73
VENTANA ALTA 1 4.05 0.85 5.75
VENTANA ALTA 1 3.93 0.85 5.63
PUERTA 1 2.10 2.10
0.00
AULA P-03 VENTANA BAJA 1 4.12 1.65 7.42
VENTANA BAJA 1 4.16 1.65 7.46
VENTANA ALTA 1 3.92 0.85 5.62
VENTANA ALTA 1 4.06 0.85 5.76
PUERTA 1 2.10 2.10
PABELLON P-3 0.00
AULA P-04 VENTANA BAJA 1 4.16 1.65 7.46
VENTANA BAJA 1 4.12 1.65 7.42
VENTANA ALTA 1 3.92 0.85 5.62
VENTANA ALTA 1 4.06 0.85 5.76
PUERTA 1 2.10 2.10

AULA P-05 VENTANA BAJA 1 4.03 1.65 7.33


VENTANA BAJA 1 4.05 1.65 7.35
VENTANA ALTA 1 3.93 0.85 5.63
VENTANA ALTA 1 4.05 0.85 5.75
PUERTA 1 2.10 2.10
0.00
SALA ADMINISTRATIVA VENTANA ALTA 1 2.90 0.85 4.60
VENTANA ALTA 1 2.81 0.85 4.51
VENTANA ALTA 1 3.08 0.85 4.78
VENTANA BAJA 1 2.95 1.65 6.25
VENTANA BAJA 1 2.90 1.65 6.20
VENTANA BAJA 1 3.08 1.65 6.38
PUERTA 1 2.10 2.10
PABELLON P-02 0.00
SS.HH. NIÑOS - NIÑAS VENTANA ALTA 2 2.36 0.85 8.12
VENTANA ALTA 1 2.01 0.85 3.71
VENTANA ALTA 1 1.88 0.85 3.58
VENTANA ALTA 2 3.93 0.85 11.26
VENTANA ALTA 2 1.84 0.85 7.08
VENTANA ALTA 2 4.05 0.85 11.50
PUERTA 6 2.10 12.60
0.00
SUM VENTANA BAJA 2 3.93 1.65 14.46
VENTANA BAJA 1 4.03 1.65 7.33
VENTANA ALTA 1 4.05 0.85 5.75
VENTANA ALTA 2 3.93 0.85 11.26
VENTANA ALTA 1 3.93 0.85 5.63
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
PUERTA 2 2.10 4.20
0.00
COCINA - ALMACEN VENTANA BAJA 1 4.05 1.65 7.35
VENTANA ALTA 1 4.05 0.85 5.75
VENTANA ALTA 1 2.00 1.65 5.30
PUERTA 2 2.10 4.20
PABELLON P-02 0.00
AULA I-01 VENTANA BAJA 2 4.15 1.65 14.90
VENTANA ALTA 2 4.15 0.85 11.70
PUERTA 1 2.10 2.10
0.00
SS. HH-. NIÑOS - DEPOSITOS VENTANA ALTA 4 2.03 0.85 14.92
PUERTA 4 2.10 8.40
PABELLON I-1 0.00
AULA I-02 VENTANA BAJA 2 4.15 1.65 14.90
VENTANA ALTA 2 4.15 0.85 11.70
PUERTA 1 2.10 2.10
0.00
SS. HH. NIÑOS NIÑAS VENTANA ALTA 2 1.90 0.85 7.20
VENTANA ALTA 1 1.25 0.85 2.95
PUERTA 3 2.10 6.30

AULA I-03 VENTANA BAJA 1 4.05 1.65 7.35


VENTANA BAJA 1 3.77 1.65 7.07
VENTANA ALTA 1 3.78 0.85 5.48
VENTANA ALTA 1 4.05 0.85 5.75
PUERTA 1 2.10 2.10
PABELLON S-3 0.00
SS. HH. NIÑOS DISCAPACITADO Y VENTANA ALTA 2 4.05 0.85 11.50
VENTANA ALTA 2 4.88 0.85 13.16
VENTANA ALTA 4 3.10 0.85 19.20
PUERTA 4 2.10 8.40
0.00
PABELLON S-2 0.00
AULA S-04 VENTANA BAJA 2 4.05 1.65 14.70
VENTANA ALTA 1 4.05 0.85 5.75
VENTANA ALTA 1 3.92 0.85 5.62
PUERTA 1 2.10 2.10

AULA S-05 VENTANA BAJA 1 4.12 1.65 7.42


VENTANA BAJA 1 4.15 1.65 7.45
VENTANA BAJA 1 3.92 0.85 5.62
VENTANA ALTA 1 4.05 0.85 5.75
PUERTA 1 2.10 2.10
0.00
SEGUNDO PISO
PABELLON P-01
1°PISO AULA P-06 VENTANA BAJA 2 4.15 1.65 14.90
VENTANA ALTA 2 4.15 0.85 11.70
PUERTA 1 2.10 2.10
0.00
AULA P-07 VENTANA BAJA 1 4.05 1.65 7.35
VENTANA BAJA 1 4.03 0.85 5.73
VENTANA ALTA 1 4.05 0.85 5.75
VENTANA ALTA 1 3.93 0.85 5.63
PUERTA 1 2.10 2.10
0.00
AULA P-08 VENTANA BAJA 1 4.12 1.65 7.42
VENTANA BAJA 1 4.16 1.65 7.46
VENTANA ALTA 1 3.92 0.85 5.62
VENTANA ALTA 1 4.06 0.85 5.76
PUERTA 1 2.10 2.10
PABELLON P-3 0.00
AULA P-09 VENTANA BAJA 1 4.16 1.65 7.46
VENTANA BAJA 1 4.12 1.65 7.42
VENTANA ALTA 1 3.92 0.85 5.62
VENTANA ALTA 1 4.06 0.85 5.76
PUERTA 1 2.10 2.10

AULA P-10 VENTANA BAJA 1 4.03 1.65 7.33


VENTANA BAJA 1 4.05 1.65 7.35
VENTANA ALTA 1 3.93 0.85 5.63
VENTANA ALTA 1 4.05 0.85 5.75
PUERTA 1 2.10 2.10
0.00
AULA P-11 VENTANA ALTA 1 2.90 0.85 4.60
VENTANA ALTA 1 2.81 0.85 4.51
VENTANA ALTA 1 3.08 0.85 4.78
VENTANA BAJA 1 2.95 1.65 6.25
VENTANA BAJA 1 2.90 1.65 6.20
VENTANA BAJA 1 3.08 1.65 6.38
PUERTA 1 2.10 2.10
PABELLON P-02 0.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
AULA P-12 VENTANA BAJA 1 4.43 1.65 7.74
VENTANA BAJA 1 4.57 1.65 7.87
VENTANA ALTA 1 4.43 0.85 6.13
VENTANA ALTA 1 4.57 0.85 6.27
PUERTA 1 2.10 2.10
0.00
AULA P-13 VENTANA BAJA 1 4.43 1.65 7.74
VENTANA BAJA 1 4.57 1.65 7.87
VENTANA ALTA 1 4.43 0.85 6.13
VENTANA ALTA 1 4.57 0.85 6.27
PUERTA 1 2.10 2.10
0.00
LABORATORIO VENTANA BAJA 4 4.43 1.65 30.92
VENTANA ALTA 4 4.43 0.85 24.52
PUERTA 2 2.10 4.20
0.00
PABELLON I-1 0.00
AULA PSICOMOTRIZ VENTANA BAJA 2 4.15 1.65 14.90
VENTANA ALTA 2 4.15 0.85 11.70
PUERTA 1 2.10 2.10
0.00
SS. HH-. NIÑOS - DEPOSITOS VENTANA ALTA 4 2.03 0.85 14.92
PUERTA 4 2.10 8.40
0.00
AULA I-04 VENTANA BAJA 2 4.15 1.65 14.90
VENTANA ALTA 2 4.15 0.85 11.70
PUERTA 1 2.10 2.10
0.00
PABELLON S-3 0.00
AULA DE INNOVACION VENTANA BAJA 1 4.05 1.65 7.35
VENTANA BAJA 1 3.93 1.65 7.23
VENTANA ALTA 1 4.05 0.85 5.75
VENTANA ALTA 1 3.93 0.85 5.63
PUERTA 2 2.10 4.20
0.00
DEPOSITO TIC VENTANA ALTA 1 3.93 0.85 5.63
VENTANA BAJA 1 3.93 0.85 5.63
PUERTA 1 2.10 2.10
0.00
AREA DE CONECTIVIDAD VENTANA BAJA 1 4.05 1.65 7.35
VENTANA ALTA 1 4.05 0.85 5.75
PUERTA 1 2.10 2.10
0.00
PABELLON S-2 0.00
AULA S-10 VENTANA BAJA 2 4.05 1.65 14.70
VENTANA ALTA 1 4.05 0.85 5.75
VENTANA ALTA 1 3.92 0.85 5.62
PUERTA 1 2.10 2.10

AULA S-11 VENTANA BAJA 1 4.12 1.65 7.42


VENTANA BAJA 1 4.15 1.65 7.45
VENTANA BAJA 1 3.92 0.85 5.62
VENTANA ALTA 1 4.15 0.85 5.85
PUERTA 1 2.10 2.10
0.00
TERCER PISO
PABELLON P-01
1°PISO AULA P-14 VENTANA BAJA 2 4.15 1.65 14.90
VENTANA ALTA 2 4.15 0.85 11.70
PUERTA 1 2.10 2.10
0.00
AULA P-15 VENTANA BAJA 1 4.05 1.65 7.35
VENTANA BAJA 1 4.03 0.85 5.73
VENTANA ALTA 1 4.05 0.85 5.75
VENTANA ALTA 1 3.93 0.85 5.63
PUERTA 1 2.10 2.10
0.00
AULA P-16 VENTANA BAJA 1 4.12 1.65 7.42
VENTANA BAJA 1 4.16 1.65 7.46
VENTANA ALTA 1 3.92 0.85 5.62
VENTANA ALTA 1 4.06 0.85 5.76
PUERTA 1 2.10 2.10
PABELLON P-3 0.00
AULA P-17 VENTANA BAJA 1 4.16 1.65 7.46
VENTANA BAJA 1 4.12 1.65 7.42
VENTANA ALTA 1 3.92 0.85 5.62
VENTANA ALTA 1 4.06 0.85 5.76
PUERTA 1 2.10 2.10

AULA P-18 VENTANA BAJA 1 4.03 1.65 7.33


VENTANA BAJA 1 4.05 1.65 7.35
VENTANA ALTA 1 3.93 0.85 5.63
VENTANA ALTA 1 4.05 0.85 5.75
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
PUERTA 1 2.10 2.10
0.00
AULA P-19 VENTANA ALTA 1 2.90 0.85 4.60
VENTANA ALTA 1 2.81 0.85 4.51
VENTANA ALTA 1 3.08 0.85 4.78
VENTANA BAJA 1 2.95 1.65 6.25
VENTANA BAJA 1 2.90 1.65 6.20
VENTANA BAJA 1 3.08 1.65 6.38
PUERTA 1 2.10 2.10
PABELLON P-02 0.00
BIBLIOTECA VENTANA BAJA 1 4.43 1.65 7.74
VENTANA BAJA 2 4.58 1.65 15.76
VENTANA ALTA 1 4.43 0.85 6.13
VENTANA ALTA 2 4.58 0.85 12.56
PUERTA 2 2.10 4.20
0.00
DEPOSITO VENTANA BAJA 1 4.43 1.65 7.74
VENTANA ALTA 1 4.43 0.85 6.13
PUERTA 1 2.10 2.10
0.00
AREWA DE CONECTIVIDAD VENTANA BAJA 1 4.43 1.65 7.73
VENTANA ALTA 1 4.43 0.85 6.13
PUERTA 1 2.10 2.10
0.00
AULA DE INNOVACION VENTANA BAJA 2 4.58 1.65 15.76
VENTANA BAJA 1 4.43 1.65 7.73
VENTANA ALTA 1 4.43 0.85 6.13
VENTANA ALTA 2 4.58 0.85 12.56
PUERTA 3 2.10 6.30
0.00
PABELLON S-3 0.00
AULA DE INNOVACION VENTANA BAJA 1 4.05 1.65 7.35
VENTANA BAJA 1 3.93 1.65 7.23
VENTANA ALTA 1 4.05 0.85 5.75
VENTANA ALTA 1 3.93 0.85 5.63
PUERTA 2 2.10 4.20
0.00
DEPOSITO TIC VENTANA ALTA 1 3.93 1.65 7.23
VENTANA BAJA 1 3.93 0.85 5.63
PUERTA 1 2.10 2.10
0.00
AREA DE CONECTIVIDAD VENTANA BAJA 1 4.05 1.65 7.35
VENTANA ALTA 1 4.05 0.85 5.75
PUERTA 1 2.10 2.10
0.00
PABELLON S-2 0.00
AULA S-12 VENTANA BAJA 1 4.42 1.65 7.72
VENTANA ALTA 1 4.57 1.65 7.87
VENTANA ALTA 1 4.42 0.85 6.12
VENTANA ALTA 1 4.57 0.85 6.27
PUERTA 1 2.10 2.10

AULA S-13 VENTANA BAJA 1 4.42 1.65 7.72


VENTANA BAJA 1 4.58 1.65 7.88
VENTANA BAJA 1 4.42 0.85 6.12
VENTANA ALTA 1 4.57 0.85 6.27
PUERTA 1 2.10 2.10
0.00

1450.84

02.02.09 BRUÑAS SEGÚN DETALLE DIMENSIONES UNIDAD ML


ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

PRIMER PISO
PABELLON P-01
AULA P-01 MURO AP-01 AC-01 1 34.17 34.17
PUERTA -1 1.10 -1.10

AULA P-02 MURO AP-02 AC-01 1 34.17 34.17


PUERTA -1 1.10 -1.10

AULA P-03 MURO AP-03 AC-01 1 34.17 34.17


PUERTA -1 1.10 -1.10

ESCALERA MURO 1 15.50 15.50

PABELLON I-01
ESCALERA MURO 1 15.90 15.90
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

AULA I - 01 MURO AI-01 AC-02 1 34.74 34.74


PUERTA -1 1.10 -1.10

AULA I - 02 MURO AI-02 AC-02 1 34.70 34.70


PUERTA -1 1.10 -1.10

SS.HH - NIÑOS MURO SHN - 01 AC-03 1 14.10 14.10


PUERTA -1 0.90 -0.90

SS.HH - NIÑAS MURO SHN - 02 AC-03 1 14.10 14.10


PUERTA P-04 -1 0.90 -0.90
0.00
DEPOSITO MURO 1 7.11 7.11
PUERTA P-04 -1 0.80 -0.80
0.00
DEPOSITO MURO 1 7.11 7.11
PUERTA P-04 -1 0.80 -0.80
0.00
SS.HH - NIÑOS MURO SHN - 03 AC-03 1 10.26 10.26
PUERTA -1 0.90 -0.90

SS.HH - NIÑAS MURO SHN - 04 AC-03 1 8.45 8.45


PUERTA P-04 -1 0.90 -0.90
0.00
DEPOSITO MURO 1 6.97 6.97
PUERTA P-04 -1 0.80 -0.80
0.00
AULA I - 03 MURO AI-03 AC-02 1 34.71 34.71
PUERTA -1 1.10 -1.10
PUERTA -1 2.60 -2.60

PABELLON P-03
AULA P-04 MURO AP - 04 AC-01 1 33.80 33.80
PUERTA -1 1.10 -1.10

AULA P-05 MURO AP-05 AC-01 1 34.17 34.17


PUERTA -1 1.10 -1.10

AMBIENTE DE ADMINISTRACION MURO ADM-01 AC-01 1 38.56 38.56


PUERTA -1 1.10 -1.10

ESCALERA MURO 1 15.50 15.50

PABELLON P-02
SS. HH. NIÑOS MURO SHV-01 AC-03 1 30.10 30.10
PUERTA -1 1.00 -1.00

SS. H.. DISC MURO SHD -01 AC-03 1 10.27 10.27


PUERTA -1 1.00 -1.00

SS. H.. DISC MURO SHD - 02 AC-03 1 10.27 10.27


PUERTA -1 1.00 -1.00

SS. HH. NIÑAS MURO SHV-01 AC-03 1 24.00 24.00


PUERTA -1 1.00 -1.00

SS. HH. H MURO SHP - 01 AC-03 1 14.28 14.28


PUERTA -1 1.00 -1.00

SS. HH. M MURO SHP - 02 AC-03 1 14.28 14.28


PUERTA -1 1.00 -1.00

ESCALERA MURO 1 15.50 15.50

SUMM MURO 1 46.93 46.93


PUERTA -2 1.10 -2.20

COCINA MURO CO-01 AC-03 1 18.09 18.09


PUERTA P-01a -1 1.00 -1.00

ALMACEN MURO CO-02 AC-03 1 14.47 14.47


PUERTA -2 1.00 -2.00

PABELLON S-03
SS.HH NIÑOS MURO SHV-02 AC-03 1 21.05 21.05
PUERTA -1 1.00 -1.00

SSHH DISCAPACITADOS MURO SHD - 03 AC-03 1 11.75 11.75


PUERTA -1 1.00 -1.00
0.00
SSHH DISCAPACITADOS MURO SHD - 03 AC-03 1 11.75 11.75
PUERTA -1 1.00 -1.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
0.00
SS.HH NIÑAS MURO SHV-02 AC-03 1 21.45 21.45
PUERTA -1 1.00 -1.00

ESCALERA MURO 1 21.90 21.90


0.00
PABELLON S-02
ESCALERA MURO 1 21.90 21.90
0.00
AULA S-04 MURO A5-04 AC-01 1 34.18 34.18
PUERTA -1 1.10 -1.10

AULA S-05 MURO A5-04 AC-01 1 34.12 34.12


PUERTA -1 1.10 -1.10

SEGUNDO PISO
PABELLON P-01
AULA P-06 MURO AP-06 AC-01 1 34.17 34.17
PUERTA -1 1.10 -1.10

AULA P-07 MURO AP-07 AC-01 1 34.17 34.17


PUERTA -1 1.10 -1.10

AULA P-08 MURO AP-08 AC-01 1 34.17 34.17


PUERTA -1 1.10 -1.10

ESCALERA MURO 1 15.50 15.50

PABELLON P-03
AULA P-09 MURO AP - 09 AC-01 1 34.17 34.17
PUERTA -1 1.10 -1.10

AULA P-10 MURO AP-10 AC-01 1 34.17 34.17


PUERTA -1 1.10 -1.10

AULA P-11 MURO AP-11 AC-01 1 38.56 38.56


PUERTA -1 1.10 -1.10

ESCALERA MURO 1 15.50 15.50

PABELLON P-02
AULA P-12 MURO AP-12 AC-01 1 33.77 33.77
PUERTA -1 1.10 -1.10

AULA P-13 MURO AP-13 AC-01 1 33.77 33.77


PUERTA -1 1.10 -1.10

LABORATORIO MURO LAB-01 AC-01 1 56.53 56.53


PUERTA P-01 -2 1.10 -2.20

ESCALERA MURO 1 15.50 15.50

PABELLON I-01
AULA PSICOMOTRIZ MURO PSI-01 AC-01 1 34.70 34.70
PUERTA -1 1.10 -1.10

AULA I-04 MURO AI - 04 AC-02 1 34.70 34.70


PUERTA -1 1.10 -1.10

SS. HH. NIÑOS MURO SHN - 01 AC-03 1 14.30 14.30


PUERTA -1 0.90 -0.90

SS. HH. NIÑAS MURO SHN - 02 AC-03 1 14.10 14.10


PUERTA -1 0.90 -0.90

DEPOSITO MURO 1 7.12 7.12


PUERTA -1 0.80 -0.80

DEPOSITO MURO 1 7.12 7.12


PUERTA -1 0.80 -0.80

ESCALERA MURO 1 15.90 15.90

PABELLON S-3
AULA INNOVACION MURO INN-01 AC-01 1 41.24 41.24
PUERTA -2 1.10 -2.20
PUERTA -1 1.00 -1.00

DEPOSITO TIC MURO TIC-01 AC-01 1 17.56 17.56


PUERTA -1 1.00 -1.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
AREA DE CONECTIVIDAD MURO ARC-01 AC-01 1 22.52 22.52
PUERTA -1 1.10 -1.10
0.00
ESCALERA MURO 1 15.90 15.90

PABELLON S-2
ESCALERA MURO 1 15.90 15.90

AULA S-10 MURO AS-10 AC-01 1 34.18 34.18


PUERTA -1 1.10 -1.10

AULA S-11 MURO AS-11 AC-01 1 34.18 34.18


PUERTA -1 1.10 -1.10

TERCER PISO
PABELLON P-01
AULA P-14 MURO AP-14 AC-01 1 34.17 34.17
PUERTA -1 1.10 -1.10

AULA P-15 MURO AP-15 AC-01 1 34.17 34.17


PUERTA -1 1.10 -1.10

AULA P-16 MURO AP-16 AC-01 1 34.17 34.17


PUERTA -1 1.10 -1.10

ESCALERA MURO 1 15.50 15.50

PABELLON P-03
AULA P-17 MURO AP - 17 AC-01 1 34.17 34.17
PUERTA -1 1.10 -1.10

AULA P-18 MURO AP-18 AC-01 1 34.17 34.17


PUERTA -1 1.10 -1.10

AULA P-19 MURO AP-19 AC-01 1 38.56 38.56


PUERTA -1 1.10 -1.10

ESCALERA MURO 1 15.50 15.50

PABELLON P-02
BIBLIOTECA MURO 1 45.64 45.64
PUERTA -2 1.10 -2.20
PUERTA -1 0.90 -0.90

DEPOSITO MURO 1 22.40 22.40


PUERTA -1 0.90 -0.90

ESCALERA MURO 1 15.90 15.90

AREA DE CONECTIVIDAD MURO ARC AC-01 1 22.52 22.52


PUERTA -1 1.10 -1.10

DEPOSITO TIC MURO ARC AC-01 1 17.55 17.55


PUERTA -1 0.90 -0.90

AULA DE INNOVACION MURO INN-03 AC-01 1 40.43 40.43


PUERTA -2 1.10 -2.20
PUERTA -1 0.90 -0.90

PABELLON S-03
AULA INNOVACION MURO INN-01 AC-01 1 41.24 41.24
PUERTA -2 1.10 -2.20
PUERTA -1 1.00 -1.00

DEPOSITO TIC MURO TIC-01 AC-01 1 17.56 17.56


PUERTA -1 1.00 -1.00

AREA DE CONECTIVIDAD MURO ARC-01 AC-01 1 22.52 22.52


PUERTA -1 1.10 -1.10
0.00
ESCALERA MURO 1 15.90 15.90

PABELLON S-2
ESCALERA MURO 1 15.90 15.90

AULA S-12 MURO AS-12 AC-01 1 34.18 34.18


PUERTA -1 1.10 -1.10

AULA S-13 MURO AS-13 AC-01 1 34.18 34.18


PUERTA -1 1.10 -1.10
COLUMNAS
AULA P-01 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
AULA P-02 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-03 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-04 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-05 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
SALA DE ADMINISTRATIVO ENTRE COLY 12 1.30 15.60
10 2.10 21.00
SS.HH. NIÑOS Y NIÑAS ENTRE COLY 8 2.95 23.60
24 2.10 50.40
SUM COCINA ENTRE COLY 16 1.30 20.80
12 2.10 25.20
2 2.95 5.90
PABELLON I-01 ENTRE COLY 16 1.30 20.80
20 2.10 42.00
2 2.95 5.90
AULA I-03 ENTRE COLY 8 1.30 10.40
14 2.10 29.40
2 3.25 6.50
PABELLON S-3 ENTRE COLY 0 0.00
10 2.10 21.00
PABELLON S-2 ENTRE COLY 16 1.30 20.80
12 2.10 25.20
SEGUNDO
AULA P-06 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-07 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-08 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-09 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-10 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-11 ENTRE COLY 12 1.30 15.60
12 2.10 25.20
AULA P-12 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-13 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
LABOARATORIO ENTRE COLY 16 1.30 20.80
12 2.10 25.20
PABELLON I-01 ENTRE COLY 16 1.30 20.80
20 2.10 42.00
4 2.95 11.80
PABELLON S-3 ENTRE COLY 26 2.10 54.60
0.00
PABELLON S-2 ENTRE COLY 16 1.30 20.80
12 2.10 25.20

TERCER PISO
AULA P-14 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-15 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-16 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-17 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-18 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-19 ENTRE COLY 12 1.30 15.60
10 2.10 21.00
BIBLIOTECA ENTRE COLY 12 1.30 15.60
8 2.10 16.80
DEPOSITO ENTRE COLY 4 1.30 5.20
4 2.10 8.40
AREA DE CONECTIV ENTRE COLY 16 1.30 20.80
16 2.10 33.60
PABELLON S-3 ENTRE COLY 26 2.10 54.60
0.00
PABELLON S-2 ENTRE COLY 16 1.30 20.80
12 2.10 25.20
BRUÑAS EN MUROS EXTERIORESPABELLON P-01 2 46.32 92.64
PABELLON P-02 2 46.32 92.64
PABELLON S-3 PABELLON P-03 2 46.32 92.64
PABELLON I-1 2 29.22 58.44
PABELLON S-2 PABELLON I-I 2 16.50 33.00
PABELLON S-3 2 46.32 92.64
PABELLON S-2 2 46.32 92.64
ML 3786.75
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

TOTAL M 3786.75

02.02.10 MEDIA CAÑA PARA DRENAJE EN TECHOS DIMENSIONES UNIDAD ML


ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

1°PISO PABELLON P-01 1 65.00 65.00


PABELLON P-03 1 35.45 35.45
PABELLON P-02 1 44.20 44.20
PABELLON I-01 1 28.25 28.25
PABELLON I-01 1 12.35 12.35
PABELLON S-3 1 23.40 23.40
2°PISO PABELLON S-2 1 23.95 23.95
0.00

TOTAL 232.60

02.02.10 TARRAJEO DE JARDINERAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

MURO 16 4.71 0.60 45.22


16 3.15 0.60 30.24
16 0.98 15.68

TOTAL 91.14

02.02.11 TARRAJEO EN SARDINELES DIMENSIONES UNIDAD ML


ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

ENTRE EJE B Y B´ 1 47.34 0.65 30.77

TOTAL 30.77

02.02.12 TARRAJEO CON IMPERMEABILIZANTE PARA CUNETAS DE CONCRETO DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

PABELLON P-01 1 25.37 1.00 25.37


PABELLON P-02 1 24.33 1.00 24.33
INICIAL 1 12.62 1.00 12.62
PABELLON P-02 SECUNDARIA 1 45.05 1.00 45.05
PABELLON S-3 1 23.7 1.00 23.70
PABELLON S-3 1 5.35 1.00 5.35

TOTAL 136.42

02.04.09 TARRAJEO DE ESCALERAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

ESCALERA PABELLON P-01 1 2.7 1.99 5.37


TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
SEGUNDO PISO PABELLON P-01 1 2.675 1.00 2.68
1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
1 2.675 1.00 2.68
ESCALERA PABELLON P-02 1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
SEGUNDO PISO PABELLON P-02 1 2.675 1.00 2.68
1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
1 2.675 1.00 2.68
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: REVOQUES Y ENLUCIDOS #REF! #REF!

2.02 REVOQUES ENLUCIDOS Y MOLDURAS

02.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
ESCALERA PABELLON P-03 1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
SEGUNDO PISO PABELLON P-03 1 2.675 1.00 2.68
1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
1 2.675 1.00 2.68
ESCALERA PABELLON I-1 1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
ESCALERA PABELLON S-03 1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
SEGUNDO PISO PABELLON S-03 1 2.675 1.00 2.68
1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
1 2.675 1.00 2.68
ESCALERA PABELLON S-02 1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
SEGUNDO PISO PABELLON S-02 1 2.675 1.00 2.68
1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
1 2.675 1.00 2.68

TOTAL 332.25

2.13 FORJADO EN PASOS Y CONTRAPASOS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

ESCALERA PABELLON P-01


PASOS 20 1.23 24.60
CONTRAPASOS 20 1.23 24.60
SEGUNDO PISO PABELLON P-01
PASOS 20 1.23 24.60
CONTRAPASOS 20 1.23 24.60
ESCALERA PABELLON P-02
PASOS 20 1.23 24.60
CONTRAPASOS 20 1.23 24.60
SEGUNDO PISO PABELLON P-02
PASOS 20 1.23 24.60
CONTRAPASOS 20 1.23 24.60
ESCALERA PABELLON P-03
PASOS 20 1.23 24.60
CONTRAPASOS 20 1.23 24.60
SEGUNDO PISO PABELLON P-03
PASOS 20 1.23 24.60
CONTRAPASOS 20 1.23 24.60
ESCALERA PABELLON I-1
PASOS 20 1.23 24.60
CONTRAPASOS 20 1.23 24.60
ESCALERA PABELLON S-03
PASOS 20 1.23 24.60
CONTRAPASOS 20 1.23 24.60
SEGUNDO PISO PABELLON S-03
PASOS 20 1.23 24.60
CONTRAPASOS 20 1.23 24.60
ESCALERA PABELLON S-02
PASOS 20 1.23 24.60
CONTRAPASOS 20 1.23 24.60
SEGUNDO PISO PABELLON S-02
PASOS 20 1.23 24.60
CONTRAPASOS 20 1.23 24.60

TOTAL 541.20
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA: CIELORASO

2.03 CIELO RASO

02.03.01 CIELO RASO CON MEZCLA C:A 1:5 DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL

AREA
PRIMER PISO
PABELLON P-1
AULA P-01 1 62.18 62.18
0.00
AULA P-02 1 62.13 62.13
0.00
AULA P-03 1 62.15 62.15
0.00
ALERO DE PASILLO 1 78.48 78.48
0.00
PABELLON P-3
AULA P-04 1 62.15 62.15
0.00
AULA P-05 1 62.13 62.13
0.00
AREA ADMINISTRATIVA 1 71.21 71.21
0.00
ALERO DE PASILLO 1 70.30 70.30
0.00
PABELLON P-2
SS.HH. M 1 10.88 10.88
0.00
SS. HH. H 1 10.88 10.88
0.00
SS. HH. NIÑAS 1 28.94 28.94
0.00
SS. HH. DISC 1 6.43 6.43
0.00
SS. HH. DISC 1 6.43 6.43
0.00
SSHH NIÑOS 1 29.54 29.54
0.00
SUM 1 96.13 96.13
0.00
COCINA 1 19.84 19.84
0.00
ALMACEN 1 10.51 10.51
0.00
ALERO DE PASILLO 1 95.18 95.18
0.00
CIELO RASO DETRÁS DE LOOS SERVICIOS HIGIENICOS 1 46.79 46.79
0.00
PABELLON I-1
AIULA I-01 1 64.36 64.36
0.00
SS. HH. NIÑOS 1 10.09 10.09
0.00
SS. HH. NIÑAS 1 10.09 10.09
0.00
DEPOSITO 2 2.88 5.76
0.00
AULA MI-025 1 64.24 64.24
0.00
SS. HH. NIÑOS 1 6.05 6.05
0.00
SS. HH. NIÑAS 1 4.21 4.21
0.00
DEPOSITO 1 2.71 2.71
0.00
AULA I-03 1 63.34 63.34
0.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA: CIELORASO

2.03 CIELO RASO

02.03.01 CIELO RASO CON MEZCLA C:A 1:5 DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
ALERO DE PASILLO 1 55.67 55.67
0.00
PABELLON S-3
SS.HH. NIÑOS 1 23.40 23.40
0.00
SS. HH. DISC 1 7.71 7.71
0.00
SS. HH. DISC 1 7.71 7.71
0.00
SS. HH. NIÑAS 1 23.35 23.35
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
PABELLON S-2
AULA S-04 1 62.13 62.13
0.00
AULA S-05 1 62.10 62.10
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
SEGUNDO PISO 0.00
PABELLON P-01
AULA P-06 1 62.18 62.18
0.00
AULA P-07 1 62.13 62.13
0.00
AULA P-08 1 62.15 62.15
0.00
ALERO DE PASILLO 1 78.48 78.48
0.00
PABELLON P-3
AULA P-09 1 62.15 62.15
0.00
AULA P-10 1 62.13 62.13
0.00
AULA P-11 1 71.21 71.21
0.00
ALERO DE PASILLO 1 70.30 70.30
0.00
PABELLON P-2
AULA P-12 1 62.37 62.37
0.00
AULA P-13 1 62.37 62.37
0.00
LABORATORIO 1 126.18 126.18
0.00
ALERO DE PASILLO 1 95.18 95.18
0.00
PABELLON I-1
AIULA PSICOMOTRIZ 1 64.23 64.23
0.00
SS. HH. NIÑOS 1 10.10 10.10
0.00
SS. HH. NIÑAS 1 10.09 10.09
0.00
AULA I-04 1 64.23 64.23
0.00
DEPOSITO 1 2.88 2.88
0.00
DEPOSITO 1 2.88 2.88
0.00
ALERO DE PASILLO 1 55.67 55.67
0.00
PABELLON S-3
AULA INNOVACION 1 78.41 78.41
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA: CIELORASO

2.03 CIELO RASO

02.03.01 CIELO RASO CON MEZCLA C:A 1:5 DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
0.00
DEPOSITO TIC 1 15.29 15.29
0.00
AREA DE CONECTIVIDAD 1 30.45 30.45
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
PABELLON S-2
AULA S-10 1 62.14 62.14
0.00
AULA S-11 1 62.16 62.16
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
TERCER PISO 0.00
PABELLON P-01
AULA P-14 1 62.18 62.18
0.00
AULA P-15 1 62.13 62.13
0.00
AULA P-16 1 62.15 62.15
0.00
ALERO DE PASILLO 1 78.48 78.48
0.00
PABELLON P-3
AULA P-17 1 62.15 62.15
0.00
AULA P-18 1 62.13 62.13
0.00
AULA P-19 1 71.21 71.21
0.00
ALERO DE PASILLO 1 70.30 70.30
0.00
PABELLON P-2
BIBLIOTECA 1 95.02 95.02
0.00
DEPOSITO 1 30.45 30.45
0.00
AREA DE CONECTIVIDAD 1 30.53 30.53
0.00
DEPOSITO TIC 1 15.37 15.37
0.00
AULA DE INNOVACION 1 78.78 78.78
0.00
ALERO DE PASILLO 1 95.18 95.18
0.00
PABELLON S-3
AULA INNOVACION 1 78.41 78.41
0.00
DEPOSITO TIC 1 15.29 15.29
0.00
AREA DE CONECTIVIDAD 1 30.45 30.45
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
PABELLON S-2
AULA S-12 1 62.14 62.14
0.00
AULA S-13 1 62.16 62.16
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
TOTAL 4106.47
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA: CIELORASO

2.03 CIELO RASO

02.03.01 CIELO RASO CON MEZCLA C:A 1:5 DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA :PISOS Y PAVIMENTOS #REF! #REF!

id PISO Nº
DESCRIPCION VECES
AREA PARCIAL TOTAL

id PISO DESCRIPCION TIPO VANO CODIGO ACABADO Nº VECES AREA PARCIAL TOTAL

2.04 PISOS Y PAVIMENTOS

02.04.01 CONTRAPISO DE 40 mm
PRIMER PISO 0.00
PABELLON P-1
AULA P-01 AP-01 AC-01 1 62.18 62.18
0.00
AULA P-02 AP-02 AC-01 1 62.13 62.13
0.00
AULA P-03 AP-03 AC-01 1 62.15 62.15
0.00
PABELLON P-3
AULA P-04 AP-04 AC-01 1 62.15 62.15
0.00
AULA P-05 AP-05 AC-01 1 62.13 62.13
0.00
AREA ADMINISTRATIVA ADM-01 AC-01 1 71.21 71.21
0.00
PABELLON P-2
SS.HH. M SHP-02 AC-03 1 10.88 10.88
0.00
SS. HH. H SHP-01 AC-03 1 10.88 10.88
0.00
SS. HH. NIÑAS SHM-01 AC-03 1 28.94 28.94
0.00
SS. HH. DISC SHD-01 AC-03 1 6.43 6.43
0.00
SS. HH. DISC SHD-02 AC-03 1 6.43 6.43
0.00
SSHH NIÑOS SHV-01 AC-01 1 28.49 28.49
0.00
SUM SUM AC-01 1 96.13 96.13
0.00
COCINA CO-01 AC-03 1 19.84 19.84
0.00
ALMACEN CO-02 AC-03 1 10.51 10.51
0.00
PABELLON I-1
SS. HH. NIÑOS SHN-01 AC-03 1 10.09 10.09
0.00
SS. HH. NIÑAS SHN-02 AC-03 1 10.09 10.09
0.00
SS. HH. NIÑOS SHN-03 AC-03 1 5.89 5.89
0.00
SS. HH. NIÑAS SHN-04 AC-03 1 4.11 4.11
0.00
PABELLON S-3
SS.HH. NIÑOS SHV-01 AC-03 1 22.28 22.28
0.00
SS. HH. DISC SHD-03 AC-03 1 7.71 7.71
0.00
SS. HH. DISC SHD-04 AC-03 1 7.71 7.71
0.00
SS. HH. NIÑAS SHM-02 AC-03 1 22.23 22.23
0.00
PABELLON S-2
AULA S-04 AS-04 AC-01 1 62.13 62.13
0.00
AULA S-05 AS-05 AC-01 1 62.10 62.10
0.00
SEGUNDO PISO 0.00
PABELLON P-01
AULA P-06 AP-06 AC-01 1 62.18 62.18
0.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA :PISOS Y PAVIMENTOS #REF! #REF!

id PISO Nº
DESCRIPCION VECES
AREA PARCIAL TOTAL

id PISO DESCRIPCION TIPO VANO CODIGO ACABADO Nº VECES AREA PARCIAL TOTAL
AULA P-07 AP-07 AC-01 1 62.13 62.13
0.00
AULA P-08 AP-08 AC-01 1 62.15 62.15
0.00
PABELLON P-3
AULA P-09 AP-09 AC-01 1 62.15 62.15
0.00
AULA P-10 AP-10 AC-01 1 62.13 62.13
0.00
AULA P-11 AP-11 AC-01 1 71.21 71.21
0.00
PABELLON P-2
AULA P-12 AP-12 AC-01 1 62.37 62.37
0.00
AULA P-13 AP-13 AC-01 1 62.37 62.37
0.00
LABORATORIO LAB-01 AC-01 1 126.18 126.18
0.00
PABELLON I-1
AIULA PSICOMOTRIZ PSI-01 AC-01 1 64.23 64.23
0.00
SS. HH. NIÑOS SHN-01 AC-03 1 9.81 9.81
0.00
SS. HH. NIÑAS SHN-02 AC-03 1 9.80 9.80
0.00
PABELLON S-3
AULA INNOVACION INN-01 AC-01 1 78.41 78.41
0.00
DEPOSITO TIC TIC-01 AC-01 1 15.29 15.29
0.00
AREA DE CONECTIVIDAD ARC-01 AC-01 1 30.45 30.45
0.00
PABELLON S-2
AULA S-10 AS-10 AC-01 1 62.14 62.14
0.00
AULA S-11 AS-11 AC-01 1 62.16 62.16
0.00
TERCER PISO 0.00
PABELLON P-01
AULA P-14 AP-14 AC-01 1 62.18 62.18
0.00
AULA P-15 AP-15 AC-01 1 62.13 62.13
0.00
AULA P-16 AP-16 AC-01 1 62.15 62.15
0.00
PABELLON P-3
AULA P-17 AP-17 AC-01 1 62.15 62.15
0.00
AULA P-18 AP-18 AC-01 1 62.13 62.13
0.00
AULA P-19 AP-19 AC-01 1 71.21 71.21
0.00
PABELLON P-2
BIBLIOTECA BIB-01 AC-01 1 95.02 95.02
0.00
AREA DE CONECTIVIDAD ARC-03 AC-01 1 30.53 30.53
0.00
DEPOSITO TIC TIC-03 AC-01 1 15.37 15.37
0.00
AULA DE INNOVACION INN-03 AC-01 1 78.78 78.78
0.00
PABELLON S-3
AULA INNOVACION INN-02 AC-01 1 78.41 78.41
0.00
DEPOSITO TIC TIC-02 AC-01 1 15.29 15.29
0.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA :PISOS Y PAVIMENTOS #REF! #REF!

id PISO Nº
DESCRIPCION VECES
AREA PARCIAL TOTAL

id PISO DESCRIPCION TIPO VANO CODIGO ACABADO Nº VECES AREA PARCIAL TOTAL
AREA DE CONECTIVIDAD ARC-02 AC-01 1 30.45 30.45
0.00
PABELLON S-2
AULA S-12 AS-12 AC-01 1 62.14 62.14
0.00
AULA S-13 AS-13 AC-01 1 62.16 62.16
0.00
TOTAL 2630.08

02.04.02 CONTRAPISO DE 48 mm

PRIMER PISO 0.00


PABELLON I-1
AIULA I-01 AI-01 AC-02 1 64.36 64.36
0.00
DEPOSITO AC-04 2 2.88 5.76
0.00
AULA MI-025 AI-01 AC-02 1 64.24 64.24
0.00
DEPOSITO AC-04 1 2.71 2.71
0.00
AULA I-03 AI-03 AC-02 1 63.34 63.34
0.00
PASADIZO AC-04 1 46.79 46.79
0.00
SEGUNDO PISO 0.00
PABELLON P-01
ALERO DE PASILLO AC-04 1 72.17 72.17
0.00
PABELLON P-3
ALERO DE PASILLO AC-04 1 64.62 64.62
0.00
PABELLON P-2
ALERO DE PASILLO AC-04 1 87.05 87.05
0.00
PABELLON I-1
AULA I-04 AI-04 AC-02 1 64.23 64.23
0.00
DEPOSITO AC-04 1 2.88 2.88
0.00
DEPOSITO AC-04 1 2.88 2.88
0.00
ALERO DE PASILLO AC-04 1 50.81 50.81
0.00
PABELLON S-3
ALERO DE PASILLO AC-04 1 42.71 42.71
0.00
PABELLON S-2
ALERO DE PASILLO AC-04 1 42.75 42.75
0.00
TERCER PISO 0.00
PABELLON P-01
ALERO DE PASILLO AC-04 1 72.18 72.18
0.00
PABELLON P-3
ALERO DE PASILLO AC-04 1 64.62 64.62
0.00
PABELLON P-2
DEPOSITO AC-04 1 30.45 30.45
0.00
ALERO DE PASILLO AC-04 1 87.39 87.39
0.00
PABELLON S-3
ALERO DE PASILLO AC-04 1 42.75 42.75
0.00
PABELLON S-2
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA :PISOS Y PAVIMENTOS #REF! #REF!

id PISO Nº
DESCRIPCION VECES
AREA PARCIAL TOTAL

id PISO DESCRIPCION TIPO VANO CODIGO ACABADO Nº VECES AREA PARCIAL TOTAL
ALERO DE PASILLO AC-04 1 42.75 42.75
0.00

TOTAL 1017.44

02.04.03 PISO DE CERAMICA DE COLOR ALTO TRANSITO DE 30X30 cm


PRIMER PISO 0.00
PABELLON P-1
AULA P-01 AP-01 AC-01 1 62.18 62.18
0.00
AULA P-02 AP-02 AC-01 1 62.13 62.13
0.00
AULA P-03 AP-03 AC-01 1 62.15 62.15
0.00
PABELLON P-3
AULA P-04 AP-04 AC-01 1 62.15 62.15
0.00
AULA P-05 AP-05 AC-01 1 62.13 62.13
0.00
AREA ADMINISTRATIVA ADM-01 AC-01 1 71.21 71.21
0.00
PABELLON P-2
SS.HH. M SHP-02 AC-03 1 10.88 10.88
0.00
SS. HH. H SHP-01 AC-03 1 10.88 10.88
0.00
SS. HH. NIÑAS SHM-01 AC-03 1 28.94 28.94
0.00
SS. HH. DISC SHD-01 AC-03 1 6.43 6.43
0.00
SS. HH. DISC SHD-02 AC-03 1 6.43 6.43
0.00
SSHH NIÑOS SHV-01 AC-01 1 28.49 28.49
0.00
SUM SUM AC-01 1 96.13 96.13
0.00
COCINA CO-01 AC-03 1 19.84 19.84
0.00
ALMACEN CO-02 AC-03 1 10.51 10.51
0.00
PABELLON I-1
SS. HH. NIÑOS SHN-01 AC-03 1 10.09 10.09
0.00
SS. HH. NIÑAS SHN-02 AC-03 1 10.09 10.09
0.00
SS. HH. NIÑOS SHN-03 AC-03 1 5.89 5.89
0.00
SS. HH. NIÑAS SHN-04 AC-03 1 4.11 4.11
0.00
PABELLON S-3
SS.HH. NIÑOS SHV-01 AC-03 1 22.28 22.28
0.00
SS. HH. DISC SHD-03 AC-03 1 7.71 7.71
0.00
SS. HH. DISC SHD-04 AC-03 1 7.71 7.71
0.00
SS. HH. NIÑAS SHM-02 AC-03 1 22.23 22.23
0.00
PABELLON S-2
AULA S-04 AS-04 AC-01 1 62.13 62.13
0.00
AULA S-05 AS-05 AC-01 1 62.10 62.10
0.00
SEGUNDO PISO 0.00
PABELLON P-01
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA :PISOS Y PAVIMENTOS #REF! #REF!

id PISO Nº
DESCRIPCION VECES
AREA PARCIAL TOTAL

id PISO DESCRIPCION TIPO VANO CODIGO ACABADO Nº VECES AREA PARCIAL TOTAL
AULA P-06 AP-06 AC-01 1 62.18 62.18
0.00
AULA P-07 AP-07 AC-01 1 62.13 62.13
0.00
AULA P-08 AP-08 AC-01 1 62.15 62.15
0.00
PABELLON P-3
AULA P-09 AP-09 AC-01 1 62.15 62.15
0.00
AULA P-10 AP-10 AC-01 1 62.13 62.13
0.00
AULA P-11 AP-11 AC-01 1 71.21 71.21
0.00
PABELLON P-2
AULA P-12 AP-12 AC-01 1 62.37 62.37
0.00
AULA P-13 AP-13 AC-01 1 62.37 62.37
0.00
LABORATORIO LAB-01 AC-01 1 126.18 126.18
0.00
PABELLON I-1
AIULA PSICOMOTRIZ PSI-01 AC-01 1 64.23 64.23
0.00
SS. HH. NIÑOS SHN-01 AC-03 1 9.81 9.81
0.00
SS. HH. NIÑAS SHN-02 AC-03 1 9.80 9.80
0.00
PABELLON S-3
AULA INNOVACION INN-01 AC-01 1 78.41 78.41
0.00
DEPOSITO TIC TIC-01 AC-01 1 15.29 15.29
0.00
AREA DE CONECTIVIDAD ARC-01 AC-01 1 30.45 30.45
0.00
PABELLON S-2
AULA S-10 AS-10 AC-01 1 62.14 62.14
0.00
AULA S-11 AS-11 AC-01 1 62.16 62.16
0.00
TERCER PISO 0.00
PABELLON P-01
AULA P-14 AP-14 AC-01 1 62.18 62.18
0.00
AULA P-15 AP-15 AC-01 1 62.13 62.13
0.00
AULA P-16 AP-16 AC-01 1 62.15 62.15
0.00
PABELLON P-3
AULA P-17 AP-17 AC-01 1 62.15 62.15
0.00
AULA P-18 AP-18 AC-01 1 62.13 62.13
0.00
AULA P-19 AP-19 AC-01 1 71.21 71.21
0.00
PABELLON P-2
BIBLIOTECA BIB-01 AC-01 1 95.02 95.02
0.00
AREA DE CONECTIVIDAD ARC-03 AC-01 1 30.53 30.53
0.00
DEPOSITO TIC TIC-03 AC-01 1 15.37 15.37
0.00
AULA DE INNOVACION INN-03 AC-01 1 78.78 78.78
0.00
PABELLON S-3
AULA INNOVACION INN-02 AC-01 1 78.41 78.41
0.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA :PISOS Y PAVIMENTOS #REF! #REF!

id PISO Nº
DESCRIPCION VECES
AREA PARCIAL TOTAL

id PISO DESCRIPCION TIPO VANO CODIGO ACABADO Nº VECES AREA PARCIAL TOTAL
DEPOSITO TIC TIC-02 AC-01 1 15.29 15.29
0.00
AREA DE CONECTIVIDAD ARC-02 AC-01 1 30.45 30.45
0.00
PABELLON S-2
AULA S-12 AS-12 AC-01 1 62.14 62.14
0.00
AULA S-13 AS-13 AC-01 1 62.16 62.16
0.00

TOTAL 2630.08

02.04.04 PISO DE MICROCEMENTO PULIDO DE COLOR E=2MM

PRIMER PISO
PABELLON I-1
AIULA I-01 AI-01 AC-02 1 64.36 64.36
0.00
AULA MI-025 AI-01 AC-02 1 64.24 64.24
0.00
AULA I-03 AI-03 AC-02 1 63.34 63.34
0.00
SEGUNDO PISO 0.00
AULA I-04 AI-04 AC-02 1 64.23 64.23
0.00
TOTAL 256.17
0.00
02.04.05 PISO DE CONCRETO SIN COLOREAR e=5" (BRUÑADO)

PRIMER PISO 0.00


PABELLON I-1
DEPOSITO AC-04 2 2.88 5.76
0.00
DEPOSITO AC-04 1 2.71 2.71
0.00
PASADIZO AC-04 1 46.79 46.79
0.00
SEGUNDO PISO 0.00
PABELLON P-01
ALERO DE PASILLO AC-04 1 72.17 72.17
0.00
PABELLON P-3
ALERO DE PASILLO AC-04 1 64.62 64.62
0.00
PABELLON P-2
ALERO DE PASILLO AC-04 1 87.05 87.05
0.00
PABELLON I-1
DEPOSITO AC-04 1 2.88 2.88
0.00
DEPOSITO AC-04 1 2.88 2.88
0.00
ALERO DE PASILLO C-04 1 50.81 50.81
0.00
PABELLON S-3
ALERO DE PASILLO AC-04 1 42.71 42.71
0.00
PABELLON S-2
ALERO DE PASILLO AC-04 1 42.75 42.75
0.00
TERCER PISO 0.00
PABELLON P-01
ALERO DE PASILLO AC-04 1 72.18 72.18
0.00
PABELLON P-3
ALERO DE PASILLO AC-04 1 64.62 64.62
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA :PISOS Y PAVIMENTOS #REF! #REF!

id PISO Nº
DESCRIPCION VECES
AREA PARCIAL TOTAL

id PISO DESCRIPCION TIPO VANO CODIGO ACABADO Nº VECES AREA PARCIAL TOTAL
0.00
PABELLON P-2
DEPOSITO AC-04 1 30.45 30.45
0.00
ALERO DE PASILLO AC-04 1 87.39 87.39
0.00
PABELLON S-3
ALERO DE PASILLO AC-04 1 42.75 42.75
0.00
PABELLON S-2
ALERO DE PASILLO AC-04 1 42.75 42.75
0.00

TOTAL(M2) TOTAL 761.27


02.04.06 PISO DE CEMENTO PULIDO BRUÑADO e=2" (CISTERNA)
SALA DE MAQUINAS - CISTERNA CTO-01 AC-04 1 6.21 6.21
TOTAL 6.21

TOTAL(M2)
02.04.07 VEREDAS e=4" DE CONCRETO f'c=175kg/cm2 ACABADO PULIDO Y BRUÑADO

PABELLON 01 1 66.85 66.85


PABELLON 03 1 77.57 77.57
PABELLON 02 1 129.02 129.02
PABELLON 02 - CISTERNA 1 17.08 17.08
PABELLON I-1 1 67.89 67.89
PABELLON I-1 1 84.87 84.87
HALL 1 21.41 21.41
PABELLON S-3 1 64.39 64.39
PABELLON S-3 1 46.79 46.79
PABELLON S-2 1 46.87 46.87

TOTAL 622.74

02.04.08 RAMPAS e=4" DE CONCRETO f'c=175kg/cm2 ACABADO PULIDO Y BRUÑADO (INCLUYE SARD

RAMPA (S 7%) 1 5.90 5.90


RAMPA (S 5%) 1 5.91 5.91
RAMPA (S 7%) 1 3.60 3.60
RAMPA (S 7%) 1 4.41 4.41
RAMPA (S 7%) 1 5.85 5.85
RAMPA (S 7%) 1 5.85 5.85
RAMPA (S 7%) 1 3.60 3.60
RAMPA (S 7%) 1 3.60 3.60
RAMPA (S 7%) 1 5.10 5.10
RAMPA (S 7%) 1 4.50 4.50
RAMPA (S 7%) 1 4.50 4.50

TOTAL 52.82

02.04.09 PISO DE CONCRETO EN PATIO Y PLATAFORMA f'c=175kg/cm2; e=15cm FROTACHADO

PATIO INICIAL 1 198.41 198.41


PATIO DE PRIMARIA 1 128.45 128.45
PATIO PRIMARIA 1 103.13 103.13
0.00
0.00
-
-
TOTAL(M2) TOTAL 429.99

02.04.10 VEREDAS, RAMPAS, PATIOS .- ENCOFRADO Y DESENCOFRADO

PABELLON 01 1 66.85 66.85


PABELLON 03 1 77.57 77.57
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA,
DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA :PISOS Y PAVIMENTOS #REF! #REF!

id PISO Nº
DESCRIPCION VECES
AREA PARCIAL TOTAL

id PISO DESCRIPCION TIPO VANO CODIGO ACABADO Nº VECES AREA PARCIAL TOTAL
PABELLON 02 1 129.02 129.02
PABELLON 02 - CISTERNA 1 17.08 17.08
PABELLON I-1 1 67.89 67.89
PABELLON I-1 1 84.87 84.87
HALL 1 21.41 21.41
PABELLON S-3 1 64.39 64.39
PABELLON S-3 1 46.79 46.79
PABELLON S-2 1 46.87 46.87
PATIO INICIAL 1 198.41 198.41
PATIO DE PRIMARIA 1 128.45 128.45
PATIO PRIMARIA 1 103.13 103.13
1,052.7 0.10

TOTAL(M2) TOTAL M2 105.27

02.04.11 PISO BLANDO EN AULAS EXTERIORES DE INICIAL

PISO BLANDO 1 207.75 207.75

TOTAL M2 207.75
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA : PUERTAS #REF! #REF!

ID PISO DESCRIPCION CODIGO TIPO CERRADURABISAGRASACCESORIO ANCHO ALTO N° VECES M2

2.07 CARPINTERIA DE MADERA


02.07.01 PUERTA MACHIMBRADA
PABELLON P-01
1°PISO AULA P- 01 AP-01 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA P-02 AP-02 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA P-03 AP-03 P-01 G 2 Q2 1.10 2.10 1.00 2.31
PABELLON P-03
AULA P-04 AP-04 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA P-05 AP-05 P-01 G 2 Q2 1.10 2.10 1.00 2.31
SALA DE ADMINISTRACION ADM-01 P-01 G 2 Q2 1.10 2.10 1.00 2.31
PABELLON P-02
SS.HH. H SHP-01 P-02a G 2 Q2 1.00 2.10 1.00 2.1
SS.HH.M SHP-02 P-02a G 2 Q2 1.00 2.10 1.00 2.1
SS.HH. NIÑAS SHM-01 P-02a G 2 Q2 1.00 2.10 1.00 2.1
SS.HH. DISCAPAC SHD-01 P-02 G 2 Q2 1.00 2.10 1.00 2.1
SS.HH. DISCAPAC SHD-02 P-02 G 2 Q2 1.00 2.10 1.00 2.1
SS.HH. NIÑOS SSHV-01 P-02a G 2 Q2 1.00 2.10 1.00 2.1
SUM SUM-01 P-01 G 2 Q2 1.10 2.10 1.00 2.31
SUM SUM-01 P-01 G 2 Q2 1.10 2.10 1.00 2.31
PABELLON I-1 0
AULA I-01 AI-01 P-01 G 2 Q2 1.10 2.10 1.00 2.31
DEPOSITO DEP P-04 G 1 Q2 0.80 2.10 1.00 1.68
DEPOSITO DEP P-04 G 1 Q2 1.10 2.10 1.00 2.31
SS.HH. NIÑOS SHN-01 P-03 G 1 Q2 0.90 2.10 1.00 1.89
SS.HH. NIÑAS SHN-02 P-03 G 1 Q2 0.90 2.10 1.00 1.89
AULA I-02 AI-02 P-01 G 2 Q2 1.10 2.10 1.00 2.31
SSHH. NIÑOS SHN-03 P-03 G 1 Q2 0.90 2.10 1.00 1.89
SS.HH. NIÑAS SHN-04 P-03 G 1 Q2 0.90 2.10 1.00 1.89
DEPOSITO DEP P-04 G 1 Q2 0.80 2.10 1.00 1.68
AULA I-03 AI-03 P-01 G 2 Q2 1.10 2.10 1.00 2.31
3°PISO PABELLON S-3 0
SS.HH. NIÑOS SHV-02 P-02a G 2 Q2 1.00 2.10 1.00 2.1
SS.HH. DISCAPAC SHD-03 P-02 G 2 Q2 1.00 2.10 1.00 2.1
SS.HH. DISCAPC SHD-04 P-02 G 2 Q2 1.00 2.10 1.00 2.1
SS.HH NIÑAS SHM-02 P-02a G 2 Q2 1.00 2.10 1.00 2.1
PABELLON S-2
AULA S-04 AS-04 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA S.05 AS-05 P-01 G 2 Q2 1.10 2.10 1.00 2.31
SEGUNDO PISO
PABELLON P-01
1°PISO AULA P- 06 AP-06 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA P-07 AP-07 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA P-08 AP-08 P-01 G 2 Q2 1.10 2.10 1.00 2.31
PABELLON P-03
AULA P-09 AP-09 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA P-10 AP-10 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA P-11 AP-11 P-01 G 2 Q2 1.10 2.10 1.00 2.31
PABELLON P-02
AULA P-12 AP-12 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA P-13 AP-13 P-01 G 2 Q2 1.10 2.10 1.00 2.31
LABORATORIO LAB-01 P-02a G 2 Q2 1.00 2.10 1.00 2.1
LABORATORIO LAB-01 P-02a G 2 Q2 1.00 2.10 1.00 2.1
PABELLON I-1 0
AULA PSICOMOTRIZ PSI-01 P-01 G 2 Q2 1.10 2.10 1.00 2.31
SS.HH. NIÑOS SHN-01 P-03 G 1 Q2 0.90 2.10 1.00 1.89
SS.HH. NIÑAS SHN-02 P-03 G 1 Q2 0.90 2.10 1.00 1.89
AULA I-04 AI-04 P-01 G 2 Q2 1.10 2.10 1.00 2.31
3°PISO PABELLON S-3 0
AULA DE INNOVACION INN-01 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA DE INNOVACION INN-01 P-01 G 2 Q2 1.10 2.10 1.00 2.31
DEPOSITO TIC TIC-01 P-02 G 1 Q2 1.00 2.10 1.00 2.1
AREEA DE CONECTIVIDAD ARC-01 P-01 G 2 Q2 1.10 2.10 1.00 2.31
PABELLON S-2
AULA S-10 AS-10 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA S-11 AS-11 P-01 G 2 Q2 1.10 2.10 1.00 2.31
TERCER PISO
PABELLON P-01
1°PISO AULA P- 14 AP-14 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA P-15 AP-15 P-01 G 2 Q2 1.10 2.10 1.00 2.31
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA : PUERTAS #REF! #REF!

ID PISO DESCRIPCION CODIGO TIPO CERRADURABISAGRASACCESORIO ANCHO ALTO N° VECES M2

AULA P-16 AP-16 P-01 G 2 Q2 1.10 2.10 1.00 2.31


PABELLON P-03
AULA P-17 AP-17 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA P-18 AP-18 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA P-19 AP-19 P-01 G 2 Q2 1.10 2.10 1.00 2.31
PABELLON P-02
BIBLIOTECA BIBL-01 P-01 G 2 Q2 1.10 2.10 1.00 2.31
BIBLIOTECA BIBL-01 P-01 G 2 Q2 1.10 2.10 1.00 2.31
DEPOSITO DEP P-02 G 1 Q2 0.90 2.10 1.00 1.89
AREA DE CONECTIVIDAD ARC-03 P-01 G 2 Q2 1.10 2.10 1.00 2.31
DEPOSITO TIC TIC-03 P-02 G 1 Q2 0.90 2.10 1.00 1.89
AULA INNOVACION INN-03 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA INNOVACION INN-03 P-01 G 2 Q2 1.10 2.10 1.00 2.31
3°PISO PABELLON S-3 0
AULA DE INNOVACION INN-02 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA DE INNOVACION INN-02 P-01 G 2 Q2 1.10 2.10 1.00 2.31
DEPOSITO TIC TIC-02 P-02 G 1 Q2 1.00 2.10 1.00 2.1
AREEA DE CONECTIVIDAD ARC-02 P-01 G 2 Q2 1.10 2.10 1.00 2.31
PABELLON S-2
AULA S-12 AS-12 P-01 G 2 Q2 1.10 2.10 1.00 2.31
AULA S-13 AS-13 P-01 G 2 Q2 1.10 2.10 1.00 2.31
69.00
M2 151.83
02.07.02 PUERTA APANELADA C/TRIPLAY 10mm
PABELLON P-02
COCINA CO-01 P-01a B 2 Q2 1.00 2.10 1.00 2.1
ALMACEN CO.02 P-01a B 2 Q2 1.00 2.10 1.00 2.1

PUERTA CONTRAPLACADA 40 mm CON TRIPLAY 6 mm INCLUYE MARCO CEDRO M2 4.2


02.07.03 2"x4"
PABELLON 04 0
PABELLON P-02
COCINA CO-01 P-01a B 2 Q2 1.00 2.10 1.00 2.1
ALMACEN CO.02 P-01a B 2 Q2 1.00 2.10 1.00 2.1
BISAGRAS TIPO 2 58 2.00
BISAGRAS TIPO 1 13
M2 4.2
02.07.04 PIZARRA ACRILICA
PABELLON P-01 PRIMER PISO
AULA P-01 4.80 1.20 1.00 5.76
AULA P-02 4.80 1.20 1.00 5.76
AULA P-03 4.80 1.20 1.00 5.76
PABELLON P-03 0
AULA P-04 4.80 1.20 1.00 5.76
AULA P-05 4.80 1.20 1.00 5.76
PABELLON I-01 0
AULA I-01 4.80 1.20 1.00 5.76
AULA I-02 4.80 1.20 1.00 5.76
AULA I-03 4.80 1.20 1.00 5.76
PABELLON S-2 0
AULA S.04 4.80 1.20 1.00 5.76
AULA S-05 4.80 1.20 1.00 5.76
PABELLON P-01 SEGUNDO PISO
AULA P-06 4.80 1.20 1.00 5.76
AULA P-07 4.80 1.20 1.00 5.76
AULA P-08 4.80 1.20 1.00 5.76
PABELLON P-03 0
AULA P-09 4.80 1.20 1.00 5.76
AULA P-10 4.80 1.20 1.00 5.76
AULA P-11 4.80 1.20 1.00 5.76
PABELLON P-02 0
AULA P-12 4.80 1.20 1.00 5.76
AULA P-13 4.80 1.20 1.00 5.76
LABORATORIO 4.80 1.20 1.00 5.76
PABELLON I-01 0
AULA PSICOMOTRIZ 4.80 1.20 1.00 5.76
AULA I-04 4.80 1.20 1.00 5.76
PABELLON S-3 0
AULA DE INNOVACION 4.80 1.20 1.00 5.76
PABELLON S-2 0
AULA S-10 4.80 1.20 1.00 5.76
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA : PUERTAS #REF! #REF!

ID PISO DESCRIPCION CODIGO TIPO CERRADURABISAGRASACCESORIO ANCHO ALTO N° VECES M2

AULA S-11 4.80 1.20 1.00 5.76


PABELLON P-01 TERCER PISO
AULA P-14 4.80 1.20 1.00 5.76
AULA P-15 4.80 1.20 1.00 5.76
AULA P-16 4.80 1.20 1.00 5.76
PABELLON P-03 0
AULA P-17 4.80 1.20 1.00 5.76
AULA P-18 4.80 1.20 1.00 5.76
AULA P-19 4.80 1.20 1.00 5.76
PABELLON P-02 0
AULA INNOVACION 4.80 1.20 1.00 5.76
PABELLON S-3 0
AULA DE INNOVACION 4.80 1.20 1.00 5.76
PABELLON S-2 0
AULA S-12 4.80 1.20 1.00 5.76
AULA S-13 4.80 1.20 1.00 5.76

M2 195.84
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA : “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE PIURA
-PIURA''

PARTIDA :SARDINELES

02.05.01 SARDINEL.-CONCRETO f'c=175 kg/cm2 (INC. EXCAVACION) EN AREAS VERDES DIMENSIONES UNIDAD M
ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL

JARDIN 1 4.58 4.58


JARDIN 1 3.25 3.25
JARDIN 1 1.25 1.25
PAB-P-2 JARDIN 1 67.63 67.63
PAB-I-1 JARDIN 1 31.94 31.94

TOTAL 108.65

02.05.02 SARDINEL.- ENCOFRADO Y DESENCOFRADO DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL

JARDIN 1 4.58 0.30 1.37


JARDIN 1 3.25 0.30 0.98
JARDIN 1 1.25 0.30 0.38
PAB-P-2 JARDIN 1 67.63 0.30 20.29
PAB-I-1 JARDIN 1 31.94 0.30 9.58

TOTAL 32.60
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE
PIURA -PIURA''

PARTIDA :CONTRAZOCALOS #REF!

02.06.01 CONTRAZOCALO DE CERAMICA DE 10 X 30 cm DIMENSIONES UNIDAD


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES A H PARCIAL

PRIMER PISO
PABELLON P-01
AULA P-01 MURO AP-01 AC-01 1 34.17 ###
PUERTA -1 1.10 -1.10

AULA P-02 MURO AP-02 AC-01 1 34.17 ###


PUERTA -1 1.10 -1.10

AULA P-03 MURO AP-03 AC-01 1 34.17 ###


PUERTA -1 1.10 -1.10

ESCALERA MURO 1 15.50 ###

PABELLON I-01
ESCALERA MURO 1 15.90 ###

AULA I - 01 MURO AI-01 AC-02 1 34.74 ###


PUERTA -1 1.10 -1.10

AULA I - 02 MURO AI-02 AC-02 1 34.70 ###


PUERTA -1 1.10 -1.10

AULA I - 03 MURO AI-03 AC-02 1 34.71 ###


PUERTA -1 1.10 -1.10
PUERTA -1 2.60 -2.60

PABELLON P-03
AULA P-04 MURO AP - 04 AC-01 1 33.80 ###
PUERTA -1 1.10 -1.10

AULA P-05 MURO AP-05 AC-01 1 34.17 ###


PUERTA -1 1.10 -1.10

AMBIENTE DE ADMINISTRACION MURO ADM-01 AC-01 1 38.56 ###


PUERTA -1 1.10 -1.10

PABELLON P-02
SUMM MURO 1 46.93 ###
PUERTA -2 1.10 -2.20

PABELLON S-03
PABELLON S-02
AULA S-04 MURO A5-04 AC-01 1 34.18 ###
PUERTA -1 1.10 -1.10

AULA S-05 MURO A5-04 AC-01 1 34.12 ###


PUERTA -1 1.10 -1.10

SEGUNDO PISO
PABELLON P-01
AULA P-06 MURO AP-06 AC-01 1 34.17 ###
PUERTA -1 1.10 -1.10

AULA P-07 MURO AP-07 AC-01 1 34.17 ###


PUERTA -1 1.10 -1.10

AULA P-08 MURO AP-08 AC-01 1 34.17 ###


PUERTA -1 1.10 -1.10

PABELLON P-03
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE
PIURA -PIURA''

PARTIDA :CONTRAZOCALOS #REF!

AULA P-09 MURO AP - 09 AC-01 1 34.17 ###


PUERTA -1 1.10 -1.10

AULA P-10 MURO AP-10 AC-01 1 34.17 ###


PUERTA -1 1.10 -1.10

AULA P-11 MURO AP-11 AC-01 1 38.56 ###


PUERTA -1 1.10 -1.10

PABELLON P-02
AULA P-12 MURO AP-12 AC-01 1 33.77 ###
PUERTA -1 1.10 -1.10

AULA P-13 MURO AP-13 AC-01 1 33.77 ###


PUERTA -1 1.10 -1.10

LABORATORIO MURO LAB-01 AC-01 1 56.53 ###


PUERTA P-01 -2 1.10 -2.20

PABELLON I-01
AULA PSICOMOTRIZ MURO PSI-01 AC-01 1 34.70 ###
PUERTA -1 1.10 -1.10

AULA I-04 MURO AI - 04 AC-02 1 34.70 ###


PUERTA -1 1.10 -1.10

PABELLON S-3
AULA INNOVACION MURO INN-01 AC-01 1 41.24 ###
PUERTA -2 1.10 -2.20
PUERTA -1 1.00 -1.00

DEPOSITO TIC MURO TIC-01 AC-01 1 17.56 ###


PUERTA -1 1.00 -1.00

AREA DE CONECTIVIDAD MURO ARC-01 AC-01 1 22.52 ###


PUERTA -1 1.10 -1.10
0.00
PABELLON S-2
AULA S-10 MURO AS-10 AC-01 1 34.18 ###
PUERTA -1 1.10 -1.10

AULA S-11 MURO AS-11 AC-01 1 34.18 ###


PUERTA -1 1.10 -1.10

TERCER PISO
PABELLON P-01
AULA P-14 MURO AP-14 AC-01 1 34.17 ###
PUERTA -1 1.10 -1.10

AULA P-15 MURO AP-15 AC-01 1 34.17 ###


PUERTA -1 1.10 -1.10

AULA P-16 MURO AP-16 AC-01 1 34.17 ###


PUERTA -1 1.10 -1.10

PABELLON P-03
AULA P-17 MURO AP - 17 AC-01 1 34.17 ###
PUERTA -1 1.10 -1.10

AULA P-18 MURO AP-18 AC-01 1 34.17 ###


PUERTA -1 1.10 -1.10

AULA P-19 MURO AP-19 AC-01 1 38.56 ###


PUERTA -1 1.10 -1.10

PABELLON P-02
BIBLIOTECA MURO 1 45.64 ###
PUERTA -2 1.10 -2.20
PUERTA -1 0.90 -0.90
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE
PIURA -PIURA''

PARTIDA :CONTRAZOCALOS #REF!

AREA DE CONECTIVIDAD MURO ARC AC-01 1 22.52 ###


PUERTA -1 1.10 -1.10

DEPOSITO TIC MURO ARC AC-01 1 17.55 ###


PUERTA -1 0.90 -0.90

AULA DE INNOVACION MURO INN-03 AC-01 1 40.43 ###


PUERTA -2 1.10 -2.20
PUERTA -1 0.90 -0.90

PABELLON S-03
AULA INNOVACION MURO INN-01 AC-01 1 41.24 ###
PUERTA -2 1.10 -2.20
PUERTA -1 1.00 -1.00

DEPOSITO TIC MURO TIC-01 AC-01 1 17.56 ###


PUERTA -1 1.00 -1.00

AREA DE CONECTIVIDAD MURO ARC-01 AC-01 1 22.52 ###


PUERTA -1 1.10 -1.10
0.00
PABELLON S-2
ESCALERA MURO 1 15.90 ###

AULA S-12 MURO AS-12 AC-01 1 34.18 ###


PUERTA -1 1.10 -1.10

AULA S-13 MURO AS-13 AC-01 1 34.18 ###


PUERTA -1 1.10 -1.10

ML

02.06.02 CONTRAZOCALO DE CEMENTO SIN COLOREAR DE H=10 cm DIMENSIONES UNIDAD


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES A H PARCIAL

PRIMER PISO
PABELLON P-01
ESCALERA MURO 1 15.50 ###

PABELLON I-01
ESCALERA MURO 1 15.90 ###

DEPOSITO MURO 1 7.11 7.11


PUERTA P-04 -1 0.80 -0.80
0.00
DEPOSITO MURO 1 7.11 7.11
PUERTA P-04 -1 0.80 -0.80
0.00
DEPOSITO MURO 1 6.97 6.97
PUERTA P-04 -1 0.80 -0.80
0.00
PABELLON P-03
ESCALERA MURO 1 15.50 ###

PABELLON P-02
ESCALERA MURO 1 15.50 ###

PABELLON S-03
ESCALERA MURO 1 21.90 ###
0.00
PABELLON S-02
ESCALERA MURO 1 21.90 ###
0.00
SEGUNDO PISO
PABELLON P-01
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE
PIURA -PIURA''

PARTIDA :CONTRAZOCALOS #REF!

ESCALERA MURO 1 15.50 ###

ALERO PASILLO 1 68.55 ###

PABELLON P-03
ESCALERA MURO 1 15.50 ###

ALERO PASILLO 1 66.40 ###

PABELLON P-02
ESCALERA MURO 1 15.50 ###

ALERO PASILLO 1 83.10 ###

PABELLON I-01
DEPOSITO MURO 1 7.12 7.12
PUERTA -1 0.80 -0.80
ALERO PASILLO 1 55.80 ###

DEPOSITO MURO 1 7.12 7.12


PUERTA -1 0.80 -0.80

ESCALERA MURO 1 15.90 ###

PABELLON S-3
ESCALERA MURO 1 15.90 ###

ALERO PASILLO 1 45.10 ###

PABELLON S-2
ESCALERA MURO 1 15.90 ###

ALERO PASILLO 1 46.20 ###

TERCER PISO
PABELLON P-01
ESCALERA MURO 1 15.50 ###

ALERO PASILLO 1 68.55 ###

PABELLON P-03

ESCALERA MURO 1 15.50 ###

ALERO PASILLO 1 66.40 ###

PABELLON P-02
DEPOSITO MURO 1 22.40 ###
PUERTA -1 0.90 -0.90

ALERO PASILLO 1 83.10 ###

ESCALERA MURO 1 15.90 ###

PABELLON S-03
ESCALERA MURO 1 15.90 ###

ALERO PASILLO 1 45.10 ###

PABELLON S-2
ESCALERA MURO 1 15.90 ###
ALERO PASILLO 1 46.20 ###

ML

02.06.03 CONTRAZOCALO DE CEMENTO SIN COLOREAR DE H=20 cm DIMENSIONES UNIDAD


PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE
PIURA -PIURA''

PARTIDA :CONTRAZOCALOS #REF!

ITEM PISO DESCRIPCION VANO CODIGO ACABADO


N° VECES A H PARCIAL

MURO LATERAL PABELLON P-01 1 28.50 ###


MURO LATERAL PABELLON P-03 1 29.80 ###
MURO LATERAL PABELLON P-02 1 54.35 ###
MURO LATERAL PABELLON I-I-1 1 68.65 ###
MURO LATERAL PABELLON I-I-1 1 50.45 ###
MURO LATERAL PABELLON I-I-1 1 19.15 ###

ML

02.06.04 CONTRAZOCALO DE CEMENTO SIN COLOREAR DE H=30 cm DIMENSIONES UNIDAD


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES A H PARCIAL

PABELLON P-01 CON JARDIN 1 45.65 45.65


PABELLON P-03 CON JARDIN 1 48.90 48.90
PABELLON P-02 CON JARDIN 1 57.95 57.95
PABELLON I-1 CON JARDIN 1 19.60 19.60
PABELLON S-2 CON JARDIN 1 37.15 37.15

ML

02.07.05.04 CONTRAZOCALO DE 0.55 m. EN CERCO CON IMPERMEABILIZANTE DIMENSIONES UNIDAD


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES A H PARCIAL

CALLE AV. BLAS DE ATIENZA 1 93.67 93.67


CALLE JR- 3 1 45.95 45.95

ML

02.06.06 ZOCALO CERAMICO 30X30 DIMENSIONES UNIDAD


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES A H PARCIAL

PRIMER PISO
PABELLON I-01
SS.HH - NIÑOS MURO SHN - 01 AC-03 1 14.10 1.80 ###
PUERTA -1 0.90 1.80 -1.62

SS.HH - NIÑAS MURO SHN - 02 AC-03 1 14.10 1.80 ###


PUERTA P-04 -1 0.90 1.80 -1.62
0.00
SS.HH - NIÑOS MURO SHN - 03 AC-03 1 10.26 1.80 ###
PUERTA -1 0.90 1.80 -1.62

SS.HH - NIÑAS MURO SHN - 04 AC-03 1 8.45 1.80 ###


PUERTA P-04 -1 0.90 1.80 -1.62
0.00
PABELLON P-02
SS. HH. NIÑOS MURO SHV-01 AC-03 1 30.10 1.80 ###
PUERTA -1 1.00 1.80 -1.80

SS. H.. DISC MURO SHD -01 AC-03 1 10.27 1.80 ###
PUERTA -1 1.00 1.80 -1.80

SS. H.. DISC MURO SHD - 02 AC-03 1 10.27 1.80 ###


PUERTA -1 1.00 1.80 -1.80

SS. HH. NIÑAS MURO SHV-01 AC-03 1 24.00 1.80 ###


PUERTA -1 1.00 1.80 -1.80

SS. HH. H MURO SHP - 01 AC-03 1 14.28 1.80 ###


PUERTA -1 1.00 1.80 -1.80

SS. HH. M MURO SHP - 02 AC-03 1 14.28 1.80 ###


PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE
PIURA -PIURA''

PARTIDA :CONTRAZOCALOS #REF!

PUERTA -1 1.00 1.80 -1.80

COCINA MURO CO-01 AC-03 1 18.09 1.80 ###


PUERTA P-01a -1 1.00 1.80 -1.80

ALMACEN MURO CO-02 AC-03 1 14.47 1.80 ###


PUERTA -2 1.00 1.80 -3.60

PABELLON S-03
SS.HH NIÑOS MURO SHV-02 AC-03 1 21.05 1.80 ###
PUERTA -1 1.00 1.80 -1.80

SSHH DISCAPACITADOS MURO SHD - 03 AC-03 1 11.75 1.80 ###


PUERTA -1 1.00 1.80 -1.80
0.00
SSHH DISCAPACITADOS MURO SHD - 03 AC-03 1 11.75 1.80 ###
PUERTA -1 1.00 1.80 -1.80
0.00
SS.HH NIÑAS MURO SHV-02 AC-03 1 21.45 1.80 ###
PUERTA -1 1.00 1.80 -1.80

SEGUNDO PISO
PABELLON I-01
SS. HH. NIÑOS MURO SHN - 01 AC-03 1 14.30 1.80 ###
PUERTA -1 0.90 1.80 -1.62

SS. HH. NIÑAS MURO SHN - 02 AC-03 1 14.10 1.80 ###


PUERTA -1 0.90 1.80 -1.62

M2

02.06.07 ENCHAPE DE PIEDRA LAJA ENTRADAS CODIGO ACABADODIMENSIONES UNIDAD


ITEM DESCRIPCION N° VECES L A H PARCIAL

AV. BLAS DE ATIENZA


MUROS ENCHAPADOS CON LAJA 1 4.05 3.00 ###
MUROS ENCHAPADOS CON LAJA 1 1.37 3.00 4.11
MUROS ENCHAPADOS CON LAJA 1 0.55 3.00 1.65
MUROS ENCHAPADOS CON LAJA 1 6.25 3.00 ###
JIRON 3
MUROS ENCHAPADOS CON LAJA 1 4.35 3.00 ###
MUROS ENCHAPADOS CON LAJA 1 2.55 3.00 7.65
MUROS ENCHAPADOS CON LAJA 1 1.80 3.00 5.40
MUROS ENCHAPADOS CON LAJA 1 7.30 3.00 ###
MUROS ENCHAPADOS CON LAJA 1 0.90 3.00 2.70

TOTAL
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE PIURA -
PIURA''

PARTIDA : PUERTAS Y REJAS #REF! #REF!

id PISO
DESCRIPCION Nº VECES DIMENSIONES PARCIAL TOTAL

id PISO DESCRIPCION .. CODIGO ACABADO Nº VECES a h PARCIAL TOTAL

2.08 CARPINTERIA METALICA Y HERRERÍA

02.08.01 CANTONERA DE ALUMINIO EN ESCALERA

PABELLON P-01 SEGUNDO PISO 20 1.225 24.50

PABELLON P-03 SEGUNDO PISO 20 1.225 24.50

PABELLON P-02 SEGUNDO PISO 20 1.225 24.50

PABELLON I-01 SEGUNDO PISO 20 1.225 24.50

PABELLON S-03 SEGUNDO PISO 20 1.225 24.50

PABELLON S-02 SEGUNDO PISO 20 1.225 24.50

PABELLON P-01 TERCER PISO 20 1.225 24.50

PABELLON P-03 TERCER PISO 20 1.225 24.50

PABELLON P-02 TERCER PISO 20 1.225 24.50

PABELLON S-03 TERCER PISO 20 1.225 24.50

PABELLON S-02 TERCER PISO 20 1.225 24.50

###

02.08.02 PUERTAS DE INGRESOS PRINCIPALES

INGRESO 03 PF-02 1 4.5 2.65 11.93

PF-01 1 1.2 2.65 3.18

INGRESO 02 PF-02 1 4.5 2.65 11.93

PF-01 1 1.2 2.65 3.18

INGRESO 01 PF-02 1 4.5 2.65 11.93

PF-01 1 1.2 2.65 3.18

PUERTA DE CUARTO DE BOMBAS PF-03 1 0.8 2.10 1.68


###

02.08.04 ASTA DE BANDERA

PATIO INICIAL 1 1.00


PATIO PRIMARIA 1 1.00
PATIO SECUNDARIO 1 1.00
###

02.08.05 ESCALERA DE GATO DE FIERRO GALVANIZADO

CISTERNA SG-12 1 9.55 9.55


- ###

02.08.06 ESCALERA DE ALUMINIO EN CISTERNA

CISTERNA SG-12 1 1.00


###

02.08.07 BARANDA METALICA EN ESCALERA

PABELLON P.01 SEGUNDO PISO 4 3 12.00

PABELLON P-03 SEGUNDO PISO 4 3 12.00

PABELLON P-02 SEGUNDO PISO 4 3 12.00


PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE PIURA -
PIURA''

PARTIDA : PUERTAS Y REJAS #REF! #REF!

id PISO
DESCRIPCION Nº VECES DIMENSIONES PARCIAL TOTAL

id PISO DESCRIPCION .. CODIGO ACABADO Nº VECES a h PARCIAL TOTAL


PABELLON I-01 SEGUNDO PISO 4 3 12.00

PABELLON S-3 SEGUNDO PISO 4 3 12.00

PABELLON S-2 SEGUNDO PISO 4 3 12.00

PABELLON P.01 TERCER PISO 4 3 12.00

PABELLON P-03 TERCER PISO 4 3 12.00

PABELLON P-02 TERCER PISO 4 3 12.00

PABELLON S-3 TERCER PISO 4 3 12.00

PABELLON S-2 TERCER PISO 4 3 12.00

BARANDA METALICA EN LOS EJES J-1, I-3, J-a SEGUNDO PSIO 1 8.00 8.00

BARANDA METALICA EN LOS EJES J-1, I-3, J-a TERCER PISO 1 8.00 8.00
###

02.08.08 TAPAJUNTA METALICA

PRIMER PISO
1°PISO PABELLON P-01 1 3.25 3.25
1°PISO PABELLON P-01 1 3.50 3.50
1°PISO PABELLON P-01 1 6.15 6.15
EJE J-a - J-1 2 3.25 6.50
1°PISO PABELLON P-03 1 3.25 3.25
1°PISO PABELLON P-03 1 3.50 3.50
1°PISO PABELLON P-03 1 6.15 6.15
1°PISO PABELLON P-02 2 3.25 6.50
1°PISO PABELLON P-02 2 3.50 7.00
1°PISO PABELLON P-02 2 6.15 12.30
1°PISO PABELLON I-01 1 3.25 3.25
1°PISO PABELLON I-01 1 3.50 3.50
1°PISO PABELLON I-01 1 6.15 6.15
1°PISO PABELLON S-3 1 3.25 3.25
1°PISO PABELLON S-3 1 3.50 3.50
1°PISO PABELLON S-3 1 6.15 6.15
1°PISO PABELLON S-2 1 3.25 3.25
1°PISO PABELLON S-2 1 3.50 3.50
1°PISO PABELLON S-2 1 6.15 6.15
SEGUNDO PISO
1°PISO PABELLON P-01 1 3.25 3.25
1°PISO PABELLON P-01 1 3.50 3.50
1°PISO PABELLON P-01 1 6.15 6.15
EJE J-a - J-1 2 3.25 6.50
1°PISO PABELLON P-03 1 3.25 3.25
1°PISO PABELLON P-03 1 3.50 3.50
1°PISO PABELLON P-03 1 6.15 6.15
1°PISO PABELLON P-02 2 3.25 6.50
1°PISO PABELLON P-02 2 3.50 7.00
1°PISO PABELLON P-02 2 6.15 12.30
1°PISO PABELLON I-01 1 4.05 4.05
1°PISO PABELLON I-01 1 3.50 3.50
1°PISO PABELLON I-01 1 9.40 9.40
1°PISO PABELLON S-3 1 3.25 3.25
1°PISO PABELLON S-3 1 3.50 3.50
1°PISO PABELLON S-3 1 9.40 9.40
1°PISO PABELLON S-2 1 3.25 3.25
1°PISO PABELLON S-2 1 3.50 3.50
1°PISO PABELLON S-2 1 6.15 6.15
TERCER PISO
1°PISO PABELLON P-01 1 4.05 4.05
1°PISO PABELLON P-01 1 3.50 3.50
1°PISO PABELLON P-01 1 9.40 9.40
EJE J-a - J-1 2 3.25 6.50
1°PISO PABELLON P-03 1 4.05 4.05
1°PISO PABELLON P-03 1 3.50 3.50
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE PIURA -
PIURA''

PARTIDA : PUERTAS Y REJAS #REF! #REF!

id PISO
DESCRIPCION Nº VECES DIMENSIONES PARCIAL TOTAL

id PISO DESCRIPCION .. CODIGO ACABADO Nº VECES a h PARCIAL TOTAL


1°PISO PABELLON P-03 1 9.40 9.40
1°PISO PABELLON P-02 2 4.05 8.10
1°PISO PABELLON P-02 2 3.50 7.00
1°PISO PABELLON P-02 2 9.40 18.80
1°PISO PABELLON I-01 TECHO 1 9 9.00
1°PISO PABELLON S-3 1 3.25 3.25
1°PISO PABELLON S-3 1 3.50 3.50
1°PISO PABELLON S-3 1 9.40 9.40
1°PISO PABELLON S-2 1 3.25 3.25
1°PISO PABELLON S-2 1 3.50 3.50
1°PISO PABELLON S-2 1 9.40 9.40
TECHO
1°PISO PABELLON P-01 1 8.8 8.80
1°PISO PABELLON P-03 1 8.8 8.80
1°PISO PABELLON P-02 2 8.8 17.60
1°PISO PABELLON S-3 1 9.40 9.40
1°PISO PABELLON S-2 1 3.25 3.25
PISO
1°PISO PABELLON P-01 1 1.95 1.95
1°PISO PABELLON P-03 1 1.95 1.95
1°PISO PABELLON P-02 2 1.95 3.90
1°PISO PABELLON I-01 1 1.95 1.95
1°PISO PABELLON S-3 1 1.95 1.95
1°PISO PABELLON S-2 1 1.95 1.95

TOTAL ###

02.08.09 SUMINISTRO E INSTALACION DE ENCUENTRO METALICO ENTRE SOBRETECHO Y PARAPETO

PABELLON P-01 66.8 1 66.8 66.80


PABELLON P-03 68.3 1 68.3 68.30
PABELLON P-02 93.25 1 93.25 93.25
PABELLON I-1 89.65 1 89.65 89.65
PABELLON S-3 56.6 1 56.6 56.60
PABELLON S-4 57.15 1 57.15 57.15

TOTAL ###

02.08.10 SUMINISTRO E INSTALACION DE CANALETA METALICA DE EVACUACION PLUVIAL 610 mm

PATIO TECHADO INICIAL 2 14.2 28.40


PATIO TECHADO SECUNDARIA 2 25 50.00
PATIO TECHADO PRIMARIA 2 30.48 60.96

###

02.08.11 CERCO METALICO

ENTRE PABELLON P-01 HALL 1 1.975 2.30 4.54


ENTRE PABELLON P-01 HALL 1 0.97 2.30 2.23
TOTAL ###

02.08.12 VENTANA DE FIERRO TIPO REJA EN SALA DE MAQUINAS

VENTANA VR-01 1 2.1 0.60 1.26


TOTAL ###

02.08.13 JUEGO DE ARCOS Y TABLERO DE BASQUET METALICOS PARA PLATAFORMA

JUEGO DE ARCOS 1 2 2.00


TABLERO DE BASQUET 1 2 2.00
TOTAL ###

02.08.14 REJILLA METALICA PARA CUNETA DE 1"X1"X1/8" (INCLUYE COLOCACION)

PABELLON P-01 1 25.37 1.00 25.37


PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE PIURA -
PIURA''

PARTIDA : PUERTAS Y REJAS #REF! #REF!

id PISO
DESCRIPCION Nº VECES DIMENSIONES PARCIAL TOTAL

id PISO DESCRIPCION .. CODIGO ACABADO Nº VECES a h PARCIAL TOTAL


PABELLON P-02 1 24.33 1.00 24.33
INICIAL 1 12.62 1.00 12.62
PABELLON P-02 SECUNDARIA 1 45.05 1.00 45.05
PABELLON S-3 1 23.7 1.00 23.70
PABELLON S-3 1 5.35 1.00 5.35

TOTAL ###

2.09.02 MAMPARAS

PABELLON P-01 1 25.37 1.00 25.37


PABELLON P-02 1 24.33 1.00 24.33
INICIAL 1 12.62 1.00 12.62
PABELLON P-02 SECUNDARIA 1 45.05 1.00 45.05
PABELLON S-3 1 23.7 1.00 23.70
PABELLON S-3 1 5.35 1.00 5.35

TOTAL ###

02.11.02 VENTANAS METALICAS POR ENCIMA DE LA puerta principal

ingreso inicial 1 8.25 1.00 8.25


ingreso primaria 1 8.25 1.00 8.25
ingreso secundaria 1 8.25 1.00 8.25

TOTAL ###
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA : VENTANAS #REF! #REF!

ID PISO AMBIENTE CODIGO TIPO ANCHO ALTO M2 CANTIDAD

2.09 CARPINTERIA DE ALUMINIO


2.09.01 VENTANAS DE ALUMINIO
02.09.01.01 SUMINISTRO E INSTALACION DE VENTANA DE ALUMINIO CON CRISTAL CRUDO DE 6 mm + LAMINA DE SEGURIDAD DE 4 MICRAS
PRIMER PISO
PABELLON P-01
1 AULA P-01 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 AULA P-02 V-3 4.05 1.65 6.68 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-6 3.93 0.85 3.34 1.00
1 AULA P-03 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
1 V-9 4.16 1.65 6.86 1.00
1 V-10 4.06 0.85 3.45 1.00
PABELLON P-03
1 AULA P-04 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
1 V-9 4.16 1.65 6.86 1.00
1 V-10 4.06 0.85 3.45 1.00
1 AULA P-05 V-3 4.05 1.65 6.68 1.00
1 V-2 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-8 3.92 0.85 3.33 1.00
1 AREEA DE ADMINISTRACION V-12 2.90 0.85 2.47 1.00
1 V-11 2.90 1.65 4.79 1.00
1 V-13 2.81 1.65 4.64 1.00
1 V-15 3.08 1.65 5.08 1.00
1 V-14 2.81 0.85 2.39 1.00
1 V-16 3.08 0.85 2.62 1.00
PABELLON P-02
1 SSHH. H SSS, HH. M V-18 1.89 0.85 1.61 1.00
1 V- 2.36 0.85 2.01 1.00
1 V-19 2.01 0.85 1.71 1.00
1 V- 2.36 0.85 2.01 1.00
1 SS.HH. NIÑAS V-6 3.93 0.85 3.34 1.00
1 V-6 3.93 0.85 3.34 1.00
1 SS.HH. DISCAP V-20 1.84 0.85 1.56 1.00
1 V-20 1.84 0.85 1.56 1.00
1 SS.HH. NIÑOS V-4 4.05 0.85 3.44 1.00
1 V-4 4.05 0.85 3.44 1.00
1 SUM V-4 4.05 1.65 6.68 1.00
1 V-3 4.06 1.65 6.70 1.00
1 V-6 3.93 1.65 6.48 1.00
1 V-21 3.93 1.65 6.48 1.00
1 V-21 3.93 1.65 6.48 1.00
1 V-6 3.93 0.85 3.34 1.00
1 ALMACEN V-3 4.05 1.65 6.68 1.00
1 COCINA V-4 4.05 0.85 3.44 1.00
PABELLON I-01
1 AULA I-01 V-2 4.15 0.85 3.53 1.00
1 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 V-1 4.15 1.65 6.85 1.00
1 SS.HH. NIÑAS Y NIÑOS V-17 2.03 0.85 1.73 1.00
1 V-17 2.03 0.85 1.73 1.00
1 DEPOSITOS V-17 2.03 0.85 1.73 1.00
1 V-17 2.03 0.85 1.73 1.00
1 AULA I-02 V-2 4.15 0.85 3.53 1.00
1 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 V-1 4.15 1.65 6.85 1.00
1 SSHH. NIÑOS Y NIÑAS V-22 1.90 0.85 1.62 1.00
1 V-22 1.90 0.85 1.62 1.00
1 DEPOSITO V-23 1.25 0.85 1.06 1.00
1 AULA I-03 V-1 4.05 0.85 3.44 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-24 4.20 0.85 3.57 1.00
1 V-25 4.20 1.65 6.93 1.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA : VENTANAS #REF! #REF!

ID PISO AMBIENTE CODIGO TIPO ANCHO ALTO M2 CANTIDAD

PABELLON S-3
1 SS.HH. NIÑOS V-26 4.88 0.85 4.15 1.00
1 V-16 4.05 0.85 3.44 1.00
1 SS.HH. DISCAP V-27 3.10 0.85 2.64 1.00
1 V-27 3.10 0.85 2.64 1.00
1 SS.HH. DISCAP V-27 3.10 0.85 2.64 1.00
1 V-27 3.10 0.85 2.64 1.00
1 SSHH. NIÑAS V-26 4.88 0.85 4.15 1.00
1 V-16 4.05 0.85 3.44 1.00
PABELLON S-2
1 AULA S-04 V-3 4.05 1.65 6.68 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-8 3.92 0.85 3.33 1.00
1 AULA S-05 V-1 4.15 1.65 6.85 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
SEGUNDO PISO
PABELLON P-01
1 AULA P-06 V-2 4.15 0.85 3.53 1.00
1 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 V-1 4.15 1.65 6.85 1.00
1 AULA P-07 V-3 4.05 1.65 6.68 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-6 3.93 0.85 3.34 1.00
1 AULA P-08 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
1 V-9 4.16 1.65 6.86 1.00
1 V-10 4.06 0.85 3.45 1.00
PABELLON P-03
1 AULA P-09 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
1 V-9 4.16 1.65 6.86 1.00
1 V-10 4.06 0.85 3.45 1.00
1 AULA P-10 V-3 4.05 1.65 6.68 1.00
1 V-2 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-8 3.92 0.85 3.33 1.00
1 AULA P-11 V-12 2.90 0.85 2.47 1.00
1 V-11 2.90 1.65 4.79 1.00
1 V-13 2.81 1.65 4.64 1.00
1 V-15 3.08 1.65 5.08 1.00
1 V-14 2.81 0.85 2.39 1.00
1 V-16 3.08 0.85 2.62 1.00
PABELLON P-02
1 AULA P-12 V-16 4.05 1.65 6.68 1.00
1 V-2 4.05 0.85 3.44 1.00
1 V-16 3.93 1.65 6.48 1.00
1 V-2 3.93 0.85 3.34 1.00
1 AULA,P-13 V-2 3.93 0.85 3.34 1.00
1 V-16 3.93 1.65 6.48 1.00
1 V-2 4.05 0.85 3.44 1.00
1 V-16 4.05 1.65 6.68 1.00
1 LABORATORIO V-2 4.05 0.85 3.44 1.00
1 V-16 4.05 1.65 6.68 1.00
1 V-2 3.93 0.85 3.34 1.00
1 V-16 3.93 1.65 6.48 1.00
1 V-2 3.93 0.85 3.34 1.00
1 V-16 3.93 1.65 6.48 1.00
1 V-2 4.05 0.85 3.44 1.00
1 V-16 4.05 1.65 6.68 1.00
PABELLON I-01
1 AULA PSICOMOTRIZ V-2 4.15 0.85 3.53 1.00
1 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 V-1 4.15 1.65 6.85 1.00
1 SS.HH. NIÑAS Y NIÑOS V-17 2.03 0.85 1.73 1.00
1 V-17 2.03 0.85 1.73 1.00
1 DEPOSITOS V-17 2.03 0.85 1.73 1.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA : VENTANAS #REF! #REF!

ID PISO AMBIENTE CODIGO TIPO ANCHO ALTO M2 CANTIDAD

1 V-17 2.03 0.85 1.73 1.00


1 AULA I-04 V-2 4.15 0.85 3.53 1.00
1 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 V-1 4.15 1.65 6.85 1.00
PABELLON S-3
1 AULA INNOVACION V-4 4.05 0.85 3.44 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-6 3.93 0.85 3.34 1.00
1 V-6 3.93 0.85 3.34 1.00
1 V-6 3.93 0.85 3.34 1.00
1 V-6 3.93 0.85 3.34 1.00
1 AREA DE CONECTIVIDAD V-4 4.05 0.85 3.44 1.00
1 V-4 4.05 0.85 3.44 1.00
PABELLON S-2
1 AULA S-10 V-3 4.05 1.65 6.68 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-8 3.92 0.85 3.33 1.00
1 AULA S-11 V-1 4.15 1.65 6.85 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
TERCER PISO
PABELLON P-01
1 AULA P-14 V-2 4.15 0.85 3.53 1.00
1 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 V-1 4.15 1.65 6.85 1.00
1 AULA P-15 V-3 4.05 1.65 6.68 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-6 3.93 0.85 3.34 1.00
1 AULA P-16 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
1 V-9 4.16 1.65 6.86 1.00
1 V-10 4.06 0.85 3.45 1.00
PABELLON P-03
1 AULA P-17 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
1 V-9 4.16 1.65 6.86 1.00
1 V-10 4.06 0.85 3.45 1.00
1 AULA P-18 V-3 4.05 1.65 6.68 1.00
1 V-2 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-8 3.92 0.85 3.33 1.00
1 AULA P-19 V-12 2.90 0.85 2.47 1.00
1 V-11 2.90 1.65 4.79 1.00
1 V-13 2.81 1.65 4.64 1.00
1 V-15 3.08 1.65 5.08 1.00
1 V-14 2.81 0.85 2.39 1.00
1 V-16 3.08 0.85 2.62 1.00
PABELLON P-02
1 BIBLIOTECA V-16 4.05 1.65 6.68 1.00
1 V-2 4.05 0.85 3.44 1.00
1 V-16 3.93 1.65 6.48 1.00
1 V-2 3.93 0.85 3.34 1.00
1 V-2 3.93 0.85 3.34 1.00
1 V-16 3.93 1.65 6.48 1.00
1 DEPOSITO V-2 4.05 0.85 3.44 1.00
1 V-16 4.05 1.65 6.68 1.00
1 AREA DE CONECTIVIDAD V-2 4.05 0.85 3.44 1.00
1 V-16 4.05 1.65 6.68 1.00
1 DEPOSITO TIC V-2 3.93 0.85 3.34 1.00
1 V-16 3.93 1.65 6.48 1.00
1 AULA DE INNOVACION V-2 3.93 0.85 3.34 1.00
1 V-16 3.93 1.65 6.48 1.00
1 V-2 4.05 0.85 3.44 1.00
1 V-16 4.05 1.65 6.68 1.00
PABELLON S-3
1 AULA INNOVACION V-4 4.05 0.85 3.44 1.00
1 V-4 4.05 0.85 3.44 1.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA : VENTANAS #REF! #REF!

ID PISO AMBIENTE CODIGO TIPO ANCHO ALTO M2 CANTIDAD

1 V-6 3.93 0.85 3.34 1.00


1 V-6 3.93 0.85 3.34 1.00
1 V-6 3.93 0.85 3.34 1.00
1 V-6 3.93 0.85 3.34 1.00
1 AREA DE CONECTIVIDAD V-4 4.05 0.85 3.44 1.00
1 V-4 4.05 0.85 3.44 1.00
PABELLON S-2
1 AULA S-12 V-3 4.05 1.65 6.68 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-8 3.92 0.85 3.33 1.00
1 AULA S-13 V-1 4.15 1.65 6.85 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00

TOTAL UNID 207.00

TOTAL M2 921.48

02.09.01.02 SUMINISTRO E INSTALACION DE PROTECTOR DE SEGURIDAD DE ALUMINIO


PRIMER PISO
PABELLON P-01
1 AULA P-01 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 AULA P-02 V-3 4.05 1.65 6.68 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-6 3.93 0.85 3.34 1.00
1 AULA P-03 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
1 V-9 4.16 1.65 6.86 1.00
1 V-10 4.06 0.85 3.45 1.00
PABELLON P-03
1 AULA P-04 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
1 V-9 4.16 1.65 6.86 1.00
1 V-10 4.06 0.85 3.45 1.00
1 AULA P-05 V-3 4.05 1.65 6.68 1.00
1 V-2 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-8 3.92 0.85 3.33 1.00
1 AREEA DE ADMINISTRACION V-12 2.90 0.85 2.47 1.00
1 V-11 2.90 1.65 4.79 1.00
1 V-13 2.81 1.65 4.64 1.00
1 V-15 3.08 1.65 5.08 1.00
1 V-14 2.81 0.85 2.39 1.00
1 V-16 3.08 0.85 2.62 1.00
PABELLON P-02
1 SSHH. H SSS, HH. M V-18 1.89 0.85 1.61 1.00
1 V- 2.36 0.85 2.01 1.00
1 V-19 2.01 0.85 1.71 1.00
1 V- 2.36 0.85 2.01 1.00
1 SS.HH. NIÑAS V-6 3.93 0.85 3.34 1.00
1 V-6 3.93 0.85 3.34 1.00
1 SS.HH. DISCAP V-20 1.84 0.85 1.56 1.00
1 V-20 1.84 0.85 1.56 1.00
1 SS.HH. NIÑOS V-4 4.05 0.85 3.44 1.00
1 V-4 4.05 0.85 3.44 1.00
1 SUM V-4 4.05 1.65 6.68 1.00
1 V-3 4.06 1.65 6.70 1.00
1 V-6 3.93 1.65 6.48 1.00
1 V-21 3.93 1.65 6.48 1.00
1 V-21 3.93 1.65 6.48 1.00
1 V-6 3.93 0.85 3.34 1.00
1 ALMACEN V-3 4.05 1.65 6.68 1.00
1 COCINA V-4 4.05 0.85 3.44 1.00
PABELLON I-01
1 AULA I-01 V-2 4.15 0.85 3.53 1.00
1 V-2 4.15 0.85 3.53 1.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA : VENTANAS #REF! #REF!

ID PISO AMBIENTE CODIGO TIPO ANCHO ALTO M2 CANTIDAD

1 V-1 4.15 1.65 6.85 1.00


1 V-1 4.15 1.65 6.85 1.00
1 SS.HH. NIÑAS Y NIÑOS V-17 2.03 0.85 1.73 1.00
1 V-17 2.03 0.85 1.73 1.00
1 DEPOSITOS V-17 2.03 0.85 1.73 1.00
1 V-17 2.03 0.85 1.73 1.00
1 AULA I-02 V-2 4.15 0.85 3.53 1.00
1 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 V-1 4.15 1.65 6.85 1.00
1 SSHH. NIÑOS Y NIÑAS V-22 1.90 0.85 1.62 1.00
1 V-22 1.90 0.85 1.62 1.00
1 DEPOSITO V-23 1.25 0.85 1.06 1.00
1 AULA I-03 V-1 4.05 0.85 3.44 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-24 4.20 0.85 3.57 1.00
1 V-25 4.20 1.65 6.93 1.00
PABELLON S-3
1 SS.HH. NIÑOS V-26 4.88 0.85 4.15 1.00
1 V-16 4.05 0.85 3.44 1.00
1 SS.HH. DISCAP V-27 3.10 0.85 2.64 1.00
1 V-27 3.10 0.85 2.64 1.00
1 SS.HH. DISCAP V-27 3.10 0.85 2.64 1.00
1 V-27 3.10 0.85 2.64 1.00
1 SSHH. NIÑAS V-26 4.88 0.85 4.15 1.00
1 V-16 4.05 0.85 3.44 1.00
PABELLON S-2
1 AULA S-04 V-3 4.05 1.65 6.68 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-8 3.92 0.85 3.33 1.00
1 AULA S-05 V-1 4.15 1.65 6.85 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
SEGUNDO PISO
PABELLON P-01
1 AULA P-06 V-2 4.15 0.85 3.53 1.00
1 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 V-1 4.15 1.65 6.85 1.00
1 AULA P-07 V-3 4.05 1.65 6.68 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-6 3.93 0.85 3.34 1.00
1 AULA P-08 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
1 V-9 4.16 1.65 6.86 1.00
1 V-10 4.06 0.85 3.45 1.00
PABELLON P-03
1 AULA P-09 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
1 V-9 4.16 1.65 6.86 1.00
1 V-10 4.06 0.85 3.45 1.00
1 AULA P-10 V-3 4.05 1.65 6.68 1.00
1 V-2 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-8 3.92 0.85 3.33 1.00
1 AULA P-11 V-12 2.90 0.85 2.47 1.00
1 V-11 2.90 1.65 4.79 1.00
1 V-13 2.81 1.65 4.64 1.00
1 V-15 3.08 1.65 5.08 1.00
1 V-14 2.81 0.85 2.39 1.00
1 V-16 3.08 0.85 2.62 1.00
PABELLON P-02
1 AULA P-12 V-16 4.05 1.65 6.68 1.00
1 V-2 4.05 0.85 3.44 1.00
1 V-16 3.93 1.65 6.48 1.00
1 V-2 3.93 0.85 3.34 1.00
1 AULA,P-13 V-2 3.93 0.85 3.34 1.00
1 V-16 3.93 1.65 6.48 1.00
1 V-2 4.05 0.85 3.44 1.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA : VENTANAS #REF! #REF!

ID PISO AMBIENTE CODIGO TIPO ANCHO ALTO M2 CANTIDAD

1 V-16 4.05 1.65 6.68 1.00


1 LABORATORIO V-2 4.05 0.85 3.44 1.00
1 V-16 4.05 1.65 6.68 1.00
1 V-2 3.93 0.85 3.34 1.00
1 V-16 3.93 1.65 6.48 1.00
1 V-2 3.93 0.85 3.34 1.00
1 V-16 3.93 1.65 6.48 1.00
1 V-2 4.05 0.85 3.44 1.00
1 V-16 4.05 1.65 6.68 1.00
PABELLON I-01
1 AULA PSICOMOTRIZ V-2 4.15 0.85 3.53 1.00
1 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 V-1 4.15 1.65 6.85 1.00
1 SS.HH. NIÑAS Y NIÑOS V-17 2.03 0.85 1.73 1.00
1 V-17 2.03 0.85 1.73 1.00
1 DEPOSITOS V-17 2.03 0.85 1.73 1.00
1 V-17 2.03 0.85 1.73 1.00
1 AULA I-04 V-2 4.15 0.85 3.53 1.00
1 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 V-1 4.15 1.65 6.85 1.00
PABELLON S-3
1 AULA INNOVACION V-4 4.05 0.85 3.44 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-6 3.93 0.85 3.34 1.00
1 V-6 3.93 0.85 3.34 1.00
1 V-6 3.93 0.85 3.34 1.00
1 V-6 3.93 0.85 3.34 1.00
1 AREA DE CONECTIVIDAD V-4 4.05 0.85 3.44 1.00
1 V-4 4.05 0.85 3.44 1.00
PABELLON S-2
1 AULA S-10 V-3 4.05 1.65 6.68 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-8 3.92 0.85 3.33 1.00
1 AULA S-11 V-1 4.15 1.65 6.85 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
TERCER PISO
PABELLON P-01
1 AULA P-14 V-2 4.15 0.85 3.53 1.00
1 V-2 4.15 0.85 3.53 1.00
1 V-1 4.15 1.65 6.85 1.00
1 V-1 4.15 1.65 6.85 1.00
1 AULA P-15 V-3 4.05 1.65 6.68 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-6 3.93 0.85 3.34 1.00
1 AULA P-16 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
1 V-9 4.16 1.65 6.86 1.00
1 V-10 4.06 0.85 3.45 1.00
PABELLON P-03
1 AULA P-17 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
1 V-9 4.16 1.65 6.86 1.00
1 V-10 4.06 0.85 3.45 1.00
1 AULA P-18 V-3 4.05 1.65 6.68 1.00
1 V-2 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-8 3.92 0.85 3.33 1.00
1 AULA P-19 V-12 2.90 0.85 2.47 1.00
1 V-11 2.90 1.65 4.79 1.00
1 V-13 2.81 1.65 4.64 1.00
1 V-15 3.08 1.65 5.08 1.00
1 V-14 2.81 0.85 2.39 1.00
1 V-16 3.08 0.85 2.62 1.00
PABELLON P-02
1 BIBLIOTECA V-16 4.05 1.65 6.68 1.00
1 V-2 4.05 0.85 3.44 1.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA : VENTANAS #REF! #REF!

ID PISO AMBIENTE CODIGO TIPO ANCHO ALTO M2 CANTIDAD

1 V-16 3.93 1.65 6.48 1.00


1 V-2 3.93 0.85 3.34 1.00
1 V-2 3.93 0.85 3.34 1.00
1 V-16 3.93 1.65 6.48 1.00
1 DEPOSITO V-2 4.05 0.85 3.44 1.00
1 V-16 4.05 1.65 6.68 1.00
1 AREA DE CONECTIVIDAD V-2 4.05 0.85 3.44 1.00
1 V-16 4.05 1.65 6.68 1.00
1 DEPOSITO TIC V-2 3.93 0.85 3.34 1.00
1 V-16 3.93 1.65 6.48 1.00
1 AULA DE INNOVACION V-2 3.93 0.85 3.34 1.00
1 V-16 3.93 1.65 6.48 1.00
1 V-2 4.05 0.85 3.44 1.00
1 V-16 4.05 1.65 6.68 1.00
PABELLON S-3
1 AULA INNOVACION V-4 4.05 0.85 3.44 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-6 3.93 0.85 3.34 1.00
1 V-6 3.93 0.85 3.34 1.00
1 V-6 3.93 0.85 3.34 1.00
1 V-6 3.93 0.85 3.34 1.00
1 AREA DE CONECTIVIDAD V-4 4.05 0.85 3.44 1.00
1 V-4 4.05 0.85 3.44 1.00
PABELLON S-2
1 AULA S-12 V-3 4.05 1.65 6.68 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-5 4.03 1.65 6.65 1.00
1 V-8 3.92 0.85 3.33 1.00
1 AULA S-13 V-1 4.15 1.65 6.85 1.00
1 V-4 4.05 0.85 3.44 1.00
1 V-7 4.12 1.65 6.80 1.00
1 V-8 3.92 0.85 3.33 1.00
1 VENTANA VR-01 VR-01 2.10 0.50 1.05 1.00

TOTAL UNID 208.00

TOTAL M2 922.53

2.09.02 MAMPARAS
02.09.02.01 SUMINISTRO E INSTALACION DE MAMPARAS DE ALUMINIO CON CRISTAL CRUDO DE 6 mm + LAMINA SE SEGURIDAD DE 4 MICRAS

PABELLON P-03
AREA ADMINISTRATIVA ADM-01 MF 3.85 2.10 8.09
MP 5.55 2.10 11.66
M-P 5.55 2.10 11.66
M-P 3.80 2.10 7.98
MF 2.10 2.10 4.41

TOTAL M2 43.79
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL

PINTURA MUROS INT.


PRIMER PISO
PABELLON P-01
AULA P-01 MURO AP-01 AC-01 1 34.17 2.95 100.80
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA ALTA -2 4.15 0.85 -7.06
VENTANA BAJA -2 4.15 1.65 -13.70
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-02 MURO AP-02 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.08 1.65 -13.32
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-03 MURO AP-03 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.24 1.65 -13.60
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 2.95 45.73


MURO 1 5.40 2.95 15.93
VENTANA ALTA -1 2.70 1.95 -5.27
CONTRAZOCALO -1 0.10 0.00

PABELLON I-01
ESCALERA MURO 1 15.90 2.95 46.91
MURO 1 6.40 2.95 18.88
VENTANA ALTA -1 2.00 1.95 -3.90
CONTRAZOCALO -1 0.10 0.00

AULA I - 01 MURO AI-01 AC-02 1 34.74 2.95 102.48


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -2 4.15 1.65 -13.70
VENTANA ALTA -2 4.15 0.85 -7.06
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA I - 02 MURO AI-02 AC-02 1 34.70 2.95 102.37


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -2 4.15 1.65 -13.70
VENTANA ALTA -2 4.15 0.85 -7.06
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

SS.HH - NIÑOS MURO SHN - 01 AC-03 1 14.10 1.45 20.45


MURO -1 2.03 0.30 -0.61
VENTANA ALTA -1 2.03 0.85 -1.73
PUERTA -1 0.90 2.10 -1.89
ZOCALO -1 16.52 1.80 -29.74
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL

SS.HH - NIÑAS MURO SHN - 02 AC-03 1 14.10 1.45 20.45


MURO -1 2.03 0.30 -0.61
VENTANA ALTA -1 2.03 0.85 -1.73
PUERTA P-04 -1 0.90 2.10 -1.89
ZOCALO -1 1.80 0.00
0.00
DEPOSITO MURO 1 7.11 3.25 23.11
MURO -1 2.03 0.30 -0.61
VENTANA ALTA -1 2.03 0.85 -1.73
PUERTA P-04 -1 0.80 2.10 -1.68
CONTRAZOCALO -1 0.10 0.00
0.00
DEPOSITO MURO 1 7.11 3.25 23.11
MURO -1 2.03 0.30 -0.61
VENTANA ALTA -1 2.03 0.85 -1.73
PUERTA P-04 -1 0.80 2.10 -1.68
CONTRAZOCALO -1 0.10 0.00
0.00
SS.HH - NIÑOS MURO SHN - 03 AC-03 1 10.26 1.45 14.87
MURO -1 1.90 0.30 -0.57
VENTANA ALTA -1 2.03 0.85 -1.73
PUERTA -1 0.90 2.10 -1.89
ZOCALO -1 16.52 1.80 -29.74

SS.HH - NIÑAS MURO SHN - 04 AC-03 1 8.45 1.45 12.25


MURO -1 1.90 0.30 -0.57
VENTANA ALTA -1 1.90 0.85 -1.62
PUERTA P-04 -1 0.90 2.10 -1.89
ZOCALO -1 1.80 0.00
0.00
DEPOSITO MURO 1 6.97 3.25 22.65
VENTANA ALTA -1 1.25 0.85 -1.06
PUERTA P-04 -1 0.80 2.10 -1.68
CONTRAZOCALO -1 0.10 0.00
0.00
AULA I - 03 MURO AI-03 AC-02 1 34.71 2.95 102.39
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 7.83 0.85 -6.66
VENTANA ALTA -1 7.82 1.65 -12.90
PUERTA -1 1.10 2.10 -2.31
PUERTA -1 2.60 2.10 -5.46
CONTRAZOCALO -1 0.10 0.00

AULAS EXTERIORES MUROS EN PATIO 4 3.00 1.25 15.00


0.00
PABELLON P-03
AULA P-04 MURO AP - 04 AC-01 1 33.80 2.95 99.71
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.28 1.65 -13.66
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-05 MURO AP-05 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.08 1.65 -13.33
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
CONTRAZOCALO -1 0.10 0.00

AMBIENTE DE ADMINISTRACION MURO ADM-01 AC-01 1 38.56 2.95 113.75


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.93 1.65 -14.73
VENTANA ALTA -1 8.79 0.85 -7.47
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 3.25 50.38


MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.70 1.95 -5.27
CONTRAZOCALO -1 0.10 0.00

PABELLON P-02
SS. HH. NIÑOS MURO SHV-01 AC-03 1 30.10 2.95 88.80
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA ALTA -2 4.05 0.85 -6.89
PUERTA -1 1.00 2.10 -2.10
CONTRAZOCALO -1 0.10 0.00

SS. H.. DISC MURO SHD -01 AC-03 1 10.27 1.45 14.89
MURO -1 1.84 0.30 -0.55
VENTANA ALTA -1 1.84 0.85 -1.56
PUERTA -1 1.00 0.30 -0.30
CONTRAZOCALO -1 0.10 0.00

SS. H.. DISC MURO SHD - 02 AC-03 1 10.27 1.45 14.89


MURO -1 1.84 0.30 -0.55
VENTANA ALTA -1 1.84 0.85 -1.56
PUERTA -1 1.00 0.30 -0.30
CONTRAZOCALO -1 0.10 0.00

SS. HH. NIÑAS MURO SHV-01 AC-03 1 24.00 1.45 34.80


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA ALTA -2 3.93 0.85 -6.68
PUERTA -1 1.00 2.10 -2.10
CONTRAZOCALO -1 0.10 0.00

SS. HH. H MURO SHP - 01 AC-03 1 14.28 1.45 20.71


MURO -1 4.24 0.30 -1.27
VENTANA ALTA -1 4.24 0.85 -3.60
PUERTA -1 1.00 0.30 -0.30
CONTRAZOCALO -1 0.10 0.00

SS. HH. M MURO SHP - 02 AC-03 1 14.28 1.45 20.71


MURO -1 4.37 0.30 -1.31
VENTANA ALTA -1 4.37 0.85 -3.71
PUERTA -1 1.00 0.30 -0.30
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 3.25 50.38


MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.00 1.95 -3.90
CONTRAZOCALO -1 0.10 0.00

SUMM MURO 1 46.93 2.95 138.44


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
VENTANA BAJA -1 11.88 1.65 -19.60
VENTANA BAJA -1 9.71 1.65 -16.06
VENTANA ALTA -1 2.20 0.85 -1.87
PUERTA -2 1.10 2.10 -4.62
CONTRAZOCALO -1 0.10 0.00

COCINA MURO CO-01 AC-03 1 18.09 1.45 26.23


MURO -1 4.05 1.45 -5.87
VENTANA ALTA -1 4.05 0.85 -3.44
VENTANA ALTA -1 2.00 1.15 -2.30
PUERTA P-01a -1 1.00 0.30 -0.30
CONTRAZOCALO -1 0.10 0.00

ALMACEN MURO CO-02 AC-03 1 14.47 1.45 20.98


MURO -1 2.00 0.30 -0.60
VENTANA BAJA -1 4.05 1.15 -4.66
PUERTA -2 1.00 0.30 -0.60
CONTRAZOCALO -1 0.10 0.00

PABELLON S-03
SS.HH NIÑOS MURO SHV-02 AC-03 1 21.05 1.15 24.21
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA ALTA -1 8.93 0.85 -7.59
PUERTA -1 1.00 0.30 -0.30
ZOCALO -1 1.80 0.00

SSHH DISCAPACITADOS MURO SHD - 03 AC-03 1 11.75 1.45 17.04


VENTANA ALTA -2 3.10 0.85 -5.27
PUERTA -1 1.00 0.30 -0.30
ZOCALO -1 1.80 0.00
0.00
SSHH DISCAPACITADOS MURO SHD - 03 AC-03 1 11.75 1.45 17.04
PUERTA -1 1.00 0.30 -0.30
VENTANA ALTA -2 3.10 0.85 -5.27
0.00
SS.HH NIÑAS MURO SHV-02 AC-03 1 21.45 1.15 24.67
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA ALTA -1 8.92 0.85 -7.58
PUERTA -1 1.00 0.30 -0.30
ZOCALO -1 1.80 0.00

ESCALERA MURO 1 21.90 3.25 71.18


VENTANA BAJA -1 2.00 1.95 -3.90
0.00
PABELLON S-02
ESCALERA MURO 1 21.90 3.25 71.18
VENTANA BAJA -1 2.00 1.95 -3.90
0.00
AULA S-04 MURO A5-04 AC-01 1 34.18 2.95 100.83
MURO 2 6.05 0.30 3.63
VENTANA -1 7.97 0.85 -6.77
VENTANA -1 8.08 1.65 -13.33
PUERTA -1 1.10 2.10 -2.31

AULA S-05 MURO A5-04 AC-01 1 34.12 2.95 100.65


MURO 2 6.05 0.30 3.63
VENTANA -1 7.97 0.85 -6.77
VENTANA -1 8.27 1.65 -13.65
PUERTA -1 1.10 2.10 -2.31
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL

SEGUNDO PISO
PABELLON P-01
AULA P-06 MURO AP-06 AC-01 1 34.17 2.95 100.80
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA ALTA -2 4.15 0.85 -7.06
VENTANA BAJA -2 4.15 1.65 -13.70
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-07 MURO AP-07 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.08 1.65 -13.32
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-08 MURO AP-08 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.24 1.65 -13.60
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 2.95 45.73


MURO 1 5.40 2.95 15.93
VENTANA ALTA -1 2.70 1.95 -5.27
CONTRAZOCALO -1 0.10 0.00

PABELLON P-03
AULA P-09 MURO AP - 09 AC-01 1 34.17 2.95 100.80
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.28 1.65 -13.66
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-10 MURO AP-10 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.08 1.65 -13.33
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-11 MURO AP-11 AC-01 1 38.56 2.95 113.75


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.79 1.65 -14.50
VENTANA ALTA -1 8.79 0.85 -7.47
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 3.25 50.38


MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.70 1.95 -5.27
CONTRAZOCALO -1 0.10 0.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL

PABELLON P-02
AULA P-12 MURO AP-12 AC-01 1 33.77 2.95 99.62
MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 9.00 1.65 -14.85
VENTANA ALTA -1 9.00 0.85 -7.65
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-13 MURO AP-13 AC-01 1 33.77 2.95 99.62


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 9.01 1.65 -14.87
VENTANA ALTA -1 8.80 0.85 -7.48
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 26.48 0.10 -2.65

LABORATORIO MURO LAB-01 AC-01 1 56.53 2.95 166.76


MURO 1 6.05 0.30 1.82
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 18.02 1.65 -29.73
VENTANA ALTA -1 18.02 0.85 -15.32
PUERTA P-01 -2 1.10 2.10 -4.62
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 3.25 50.38


MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.70 1.95 -5.27
CONTRAZOCALO -1 0.10 0.00

PABELLON I-01
AULA PSICOMOTRIZ MURO PSI-01 AC-01 1 34.70 2.95 102.37
MURO 1 24.80 0.75 18.60
MURO 2 6.05 0.68 8.17
VENTANA -2 4.15 0.85 -7.06
VENTANA -2 4.15 1.65 -13.70
PUERTA -1 1.10 2.10 -2.31

AULA I-04 MURO AI - 04 AC-02 1 34.70 2.95 102.37


MURO 2 6.05 0.30 3.63
VENTANA BAJA -2 4.15 1.65 -13.70
VENTANA ALTA -2 4.15 0.85 -7.06
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

SS. HH. NIÑOS MURO SHN - 01 AC-03 1 14.30 1.45 20.74


MURO -1 2.03 0.30 -0.61
VENTANA ALTA -1 2.03 0.85 -1.73
PUERTA -1 0.90 0.30 -0.27
CONTRAZOCALO -1 0.10 0.00

SS. HH. NIÑAS MURO SHN - 02 AC-03 1 14.10 1.45 20.45


MURO -1 2.03 0.30 -0.61
VENTANA ALTA -1 2.03 0.85 -1.73
PUERTA -1 0.90 0.30 -0.27
CONTRAZOCALO -1 0.10 0.00

DEPOSITO MURO 1 7.12 3.25 23.14


MURO -1 2.03 0.30 -0.61
VENTANA -1 2.03 0.85 -1.73
PUERTA -1 0.80 2.10 -1.68
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
CONTRAZOCALO -1 0.10 0.00

DEPOSITO MURO 1 7.12 3.25 23.14


MURO -1 2.03 0.30 -0.61
VENTANA -1 2.03 0.85 -1.73
PUERTA -1 0.80 2.10 -1.68
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.90 3.25 51.68


MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.00 1.95 -3.90
CONTRAZOCALO -1 0.10 0.00

PABELLON S-3
AULA INNOVACION MURO INN-01 AC-01 1 41.24 2.95 121.66
MURO 2 6.05 0.30 3.63
VENTANA BAJA -1 7.99 1.65 -13.18
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -2 1.10 2.10 -4.62
PUERTA -1 1.00 2.10 -2.10

DEPOSITO TIC MURO TIC-01 AC-01 1 17.56 2.95 51.80


MURO 1 6.26 0.30 1.88
PUERTA -1 1.00 2.10 -2.10

AREA DE CONECTIVIDAD MURO ARC-01 AC-01 1 22.52 2.95 66.43


MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 4.05 1.65 -6.68
VENTANA ALTA -1 4.05 0.85 -3.44
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00
0.00
ESCALERA MURO 1 15.90 3.25 51.68
MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.00 1.95 -3.90

PABELLON S-2
ESCALERA MURO 1 15.90 3.25 51.68
MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.00 1.95 -3.90

AULA S-10 MURO AS-10 AC-01 1 34.18 2.95 100.83


MURO 2 6.05 0.30 3.63
VENTANA BAJA -1 7.97 0.85 -6.77
VENTANA ALTA -1 8.08 1.65 -13.33
PUERTA -1 1.10 2.10 -2.31

AULA S-11 MURO AS-11 AC-01 1 34.18 2.95 100.83


MURO 2 6.05 0.30 3.63
VENTANA BAJA -1 8.07 0.85 -6.86
VENTANA ALTA -1 8.27 1.65 -13.65
PUERTA -1 1.10 2.10 -2.31

TERCER PISO
PABELLON P-01
AULA P-14 MURO AP-14 AC-01 1 34.17 2.95 100.80
MURO 1 6.05 0.68 4.08
MURO 1 6.05 0.68 4.08
VENTANA ALTA -2 4.15 0.85 -7.06
VENTANA BAJA -2 4.15 1.65 -13.70
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL

AULA P-15 MURO AP-15 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.68 4.08
MURO 1 6.05 0.68 4.08
VENTANA BAJA -1 8.08 1.65 -13.32
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-16 MURO AP-16 AC-01 1 34.17 2.95 100.80


MURO 1 33.80 0.75 25.35
MURO 1 6.05 0.68 4.11
MURO 1 6.05 0.68 4.11
VENTANA BAJA -1 8.24 1.65 -13.60
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 2.95 45.73


MURO 1 5.40 2.95 15.93
VENTANA ALTA -1 2.70 1.95 -5.27
CONTRAZOCALO -1 0.10 0.00

PABELLON P-03
AULA P-17 MURO AP - 17 AC-01 1 34.17 2.95 100.80
MURO 1 6.05 0.68 4.11
MURO 1 6.05 0.68 4.11
VENTANA BAJA -1 8.28 1.65 -13.66
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-18 MURO AP-18 AC-01 1 34.17 2.95 100.80


MURO 1 6.05 0.68 4.11
MURO 1 6.05 0.68 4.11
VENTANA BAJA -1 8.08 1.65 -13.33
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

AULA P-19 MURO AP-19 AC-01 1 38.56 2.95 113.75


MURO 1 35.30 0.75 26.48
MURO 1 6.05 0.68 4.11
MURO 1 6.05 0.30 1.82
VENTANA BAJA -1 8.79 1.65 -14.50
VENTANA ALTA -1 8.79 0.85 -7.47
PUERTA -1 1.10 2.10 -2.31
CONTRAZOCALO -1 0.10 0.00

ESCALERA MURO 1 15.50 3.25 50.38


MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.70 1.95 -5.27
CONTRAZOCALO -1 0.10 0.00

PABELLON P-02
BIBLIOTECA MURO 1 45.64 2.95 134.64
MURO 1 6.05 0.68 4.11
PUERTA -2 1.10 2.10 -4.62
VENTANA ALTA -1 13.59 0.85 -11.55
VENTANA BAJA -1 13.59 1.65 -22.42
PUERTA -1 0.90 2.10 -1.89
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL

DEPOSITO MURO 1 22.40 2.95 66.08


MURO 1 6.05 0.68 4.11
VENTANA 1 4.75 1.75 8.31
VENTANA BAJA -1 4.43 1.65 -7.30
VENTANA ALTA -1 4.43 0.85 -3.77
PUERTA -1 0.90 2.10 -1.89

ESCALERA MURO 1 15.90 3.25 51.68


MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.70 1.95 -5.27

AREA DE CONECTIVIDAD MURO ARC AC-01 1 22.52 2.95 66.43


MURO 1 6.05 0.68 4.08
VENTANA BAJA -1 4.43 1.65 -7.31
VENTANA ALTA -1 4.43 0.85 -3.77
PUERTA -1 1.10 2.10 -2.31

DEPOSITO TIC MURO ARC AC-01 1 17.55 2.95 51.77


MURO 1 6.05 0.68 4.11
VENTANA BAJA -1 4.26 1.65 -7.03
VENTANA ALTA -1 4.58 0.85 -3.89
PUERTA -1 0.90 2.10 -1.89

AULA DE INNOVACION MURO INN-03 AC-01 1 40.43 2.95 119.27


MURO 2 6.05 0.68 8.17
MURO 1 20.25 0.75 15.19
VENTANA BAJA -1 9.01 1.65 -14.87
VENTANA ALTA -1 9.01 0.85 -7.66
PUERTA -2 1.10 2.10 -4.62
PUERTA -1 0.90 2.10 -1.89

PABELLON S-03
AULA INNOVACION MURO INN-01 AC-01 1 41.24 2.95 121.66
MURO 2 6.05 0.68 8.17
VENTANA BAJA -1 7.99 1.65 -13.18
VENTANA ALTA -1 7.98 0.85 -6.78
PUERTA -2 1.10 2.10 -4.62
PUERTA -1 1.00 2.10 -2.10

DEPOSITO TIC MURO TIC-01 AC-01 1 17.56 2.95 51.80


MURO 1 6.26 0.30 1.88
PUERTA -1 1.00 2.10 -2.10

AREA DE CONECTIVIDAD MURO ARC-01 AC-01 1 22.52 2.95 66.43


MURO 1 20.25 0.75 15.19
MURO 1 6.05 0.68 4.08
VENTANA BAJA -1 4.05 1.65 -6.68
VENTANA ALTA -1 4.05 0.85 -3.44
PUERTA -1 1.10 2.10 -2.31
0.00
ESCALERA MURO 1 15.90 3.25 51.68
MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.00 1.95 -3.90

PABELLON S-2
ESCALERA MURO 1 15.90 3.25 51.68
MURO 1 6.40 3.25 20.80
VENTANA ALTA -1 2.00 1.95 -3.90

AULA S-12 MURO AS-12 AC-01 1 34.18 2.95 100.83


MURO 1 10.00 0.75 7.50
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
MURO 2 6.05 0.68 8.17
VENTANA BAJA -1 7.97 0.85 -6.77
VENTANA ALTA -1 8.08 1.65 -13.33
PUERTA -1 1.10 2.10 -2.31

AULA S-13 MURO AS-13 AC-01 1 34.18 2.95 100.83


MURO 1 10.00 0.75 7.50
MURO 2 6.05 0.68 8.17
VENTANA BAJA -1 8.07 0.85 -6.86
VENTANA ALTA -1 8.27 1.65 -13.65
PUERTA -1 1.10 2.10 -2.31

TOTAL 5224.43

PINTURA MUROS EXT.


PRIMER PISO
PRIMER PISO
PABELLON P-1 MURO EXT 1 82.99 3.25 269.72
MURO EXT 1 45.65 0.25 11.41
VENTANA ALTA -1 24.26 0.85 -20.62
VENTANA BAJA -1 24.66 1.65 -40.69
VENTANA BAJA -1 2.70 1.95 -5.27
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
0.00
PABELLON P-3 MURO EXT 1 84.78 3.25 275.54
MURO EXT 1 48.89 0.25 12.22
VENTANA ALTA -1 28.80 0.85 -24.48
VENTANA BAJA -1 25.29 1.65 -41.73
VENTANA BAJA -1 2.70 1.95 -5.27
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
0.00
PABELLON P-2 MURO EXT 1 107.73 3.25 350.12
MURO EXT 1 57.95 0.25 14.49
VENTANA ALTA -1 32.30 0.85 -27.46
VENTANA BAJA -1 27.84 1.65 -45.94
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -2 1.10 2.10 -4.62
PUERTA -6 1.00 2.10 -12.60
VACIO ESCAL -1 2.70 3.25 -8.78
0.00
PABELLON I-1 MURO EXT 1 70.97 3.25 230.65
MURO EXT 1 42.05 0.25 10.51
VENTANA ALTA -1 24.72 0.85 -21.01
VENTANA BAJA -4 4.15 1.65 -27.39
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -2 1.10 2.10 -4.62
PUERTA -2 0.90 2.10 -3.78
VACIO ESCAL -1 2.70 3.25 -8.78
0.00
PABELLON AULA I-03 MURO EXT 1 38.83 4.80 186.38
MURO EXT 26.15 0.25 0.00
VENTANA ALTA -1 12.88 0.85 -10.95
VENTANA BAJA -1 7.82 1.65 -12.90
PUERTA -1 1.10 2.10 -2.31
0.00
PABELLON S-3 MURO EXT 1 72.10 3.25 234.33
MURO EXT 1 14.65 0.25 3.66
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
VENTANA ALTA -1 30.25 0.85 -25.71
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -4 1.00 2.10 -8.40
VACIO ESCAL -1 2.70 3.25 -8.78
0.00
PABELLON S-4 MURO EXT 1 61.31 3.25 199.26
MURO EXT 1 37.15 0.25 9.29
VENTANA ALTA -1 15.94 0.85 -13.55
VENTANA BAJA -1 16.35 1.65 -26.98
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -2 1.10 2.10 -4.62
VACIO ESCAL -1 2.70 3.25 -8.78
0.00
SEGUNDO PISO
PABELLON P-1 MURO EXT 1 82.99 3.25 269.72
MURO EXT 1 45.65 0.25 11.41
VENTANA ALTA -1 24.26 0.85 -20.62
VENTANA BAJA -1 24.66 1.65 -40.69
VENTANA BAJA -1 2.70 1.95 -5.27
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 40.25 2.40 96.60
0.00
PABELLON P-3 MURO EXT 1 84.78 3.25 275.54
MURO EXT 1 48.89 0.25 12.22
VENTANA ALTA -1 28.80 0.85 -24.48
VENTANA BAJA -1 25.29 1.65 -41.73
VENTANA BAJA -1 2.70 1.95 -5.27
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 36.05 2.40 86.52
0.00
PABELLON P-2 MURO EXT 1 102.19 3.25 332.12
MURO EXT 1 57.60 0.25 14.40
VENTANA ALTA -1 30.79 0.85 -26.17
VENTANA BAJA -1 33.49 1.65 -55.26
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -4 1.10 2.10 -9.24
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 54.30 2.40 130.32
0.00
PABELLON I-1 MURO EXT 1 70.67 3.25 229.68
MURO EXT 1 42.05 0.25 10.51
MURO EXT 1 28.55 0.79 22.55
MURO EXT 2 6.75 0.55 7.43
VENTANA ALTA -1 24.72 0.85 -21.01
VENTANA BAJA -4 4.15 1.65 -27.39
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -2 1.10 2.10 -4.62
PUERTA -2 0.80 2.10 -3.36
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 32.13 2.40 77.11
0.00
PABELLON S-3 MURO EXT 1 72.10 3.25 234.33
MURO EXT 1 37.15 0.25 9.29
VENTANA ALTA -1 30.25 0.85 -25.71
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -4 1.00 2.10 -8.40
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 27.65 2.40 66.36
0.00
PABELLON S-4 MURO EXT 1 61.25 3.25 199.06
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
MURO EXT 1 37.15 0.25 9.29
VENTANA ALTA -1 16.04 0.85 -13.63
VENTANA BAJA -1 16.35 1.65 -26.98
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 27.65 2.40 66.36
0.00
TERCER PISO
PABELLON P-1 MURO EXT 1 82.99 3.25 269.72
MURO EXT 1 45.65 0.25 11.41
MURO EXT 1 34.30 0.79 27.10
MURO EXT 2 6.55 0.55 7.21
VENTANA ALTA -1 24.26 0.85 -20.62
VENTANA BAJA -1 24.66 1.65 -40.69
VENTANA BAJA -1 2.70 1.95 -5.27
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 40.25 2.40 96.60
0.00
PABELLON P-3 MURO EXT 1 84.78 3.25 275.54
MURO EXT 1 48.89 0.25 12.22
MURO EXT 1 35.80 0.79 28.28
MURO EXT 2 6.55 0.55 7.21
VENTANA ALTA -1 27.80 0.85 -23.63
VENTANA BAJA -1 27.82 1.65 -45.90
VENTANA BAJA -1 2.70 1.95 -5.27
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 36.05 2.40 86.52
0.00
PABELLON P-2 MURO EXT 1 102.19 3.25 332.12
MURO EXT 1 57.60 0.25 14.40
MURO EXT 1 44.50 0.79 35.16
MURO EXT 2 6.55 0.55 7.21
VENTANA ALTA -1 30.79 0.85 -26.17
VENTANA BAJA -1 33.49 1.65 -55.26
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -4 1.10 2.10 -9.24
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 54.30 2.40 130.32
0.00
PABELLON S-3 MURO EXT 1 72.10 3.25 234.33
MURO EXT 1 37.15 0.25 9.29
MURO EXT 1 24.05 0.79 19.00
MURO EXT 2 6.55 0.55 7.21
VENTANA ALTA -1 15.96 0.85 -13.57
VENTANA BAJA -1 15.97 1.65 -26.35
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
MUROS BAJOS 1 27.65 2.40 66.36
0.00
PABELLON S-4 MURO EXT 1 61.25 3.25 199.06
MURO EXT 1 37.15 0.25 9.29
MURO EXT 1 24.05 0.79 19.00
MURO EXT 2 6.55 0.55 7.21
VENTANA ALTA -1 16.04 0.85 -13.63
VENTANA BAJA -1 16.35 1.65 -26.98
VENTANA BAJA -1 2.00 1.95 -3.90
PUERTA -3 1.10 2.10 -6.93
VACIO ESCAL -1 2.70 3.25 -8.78
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
MUROS BAJOS 1 27.65 2.40 66.36
0.00
ESCALERA PABELLON P-01 1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
SEGUNDO PISO PABELLON P-01 1 2.675 1.00 2.68
1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
1 2.675 1.00 2.68
ESCALERA PABELLON P-02 1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
SEGUNDO PISO PABELLON P-02 1 2.675 1.00 2.68
1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
1 2.675 1.00 2.68
ESCALERA PABELLON P-03 1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
SEGUNDO PISO PABELLON P-03 1 2.675 1.00 2.68
1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
1 2.675 1.00 2.68
ESCALERA PABELLON I-1 1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
ESCALERA PABELLON S-03 1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
SEGUNDO PISO PABELLON S-03 1 2.675 1.00 2.68
1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
1 2.675 1.00 2.68
ESCALERA PABELLON S-02 1 2.7 1.99 5.37
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
SEGUNDO PISO PABELLON S-02 1 2.675 1.00 2.68
1 2.7 1.99 5.37
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
TARRAJEO EN FONDO DE DESCANSO 1 2.7 1.60 4.32
DESCANSO MEDIO 1 2.83 1.23 3.48
1 3.18 1.23 3.91
TARRAJEO DE PARED 1 3.75 2.85 10.69
1 2.675 1.00 2.68
TOTAL 4960.94
PINTURA COLUMNAS
PABELLON P-01
1°PISO 12 0.45 3.25 17.55
6 1.70 3.25 33.15

PABELLON P-02
12 0.45 3.25 17.55
8 1.70 3.25 44.20

PABELLON P-03
10 0.45 3.25 14.63
6 1.70 3.25 33.15
6 0.73 3.25 14.14
2 0.80 3.25 5.20

PABELLON I-1
6 0.45 3.25 8.78
8 1.70 3.25 44.20
2 1.10 3.25 7.15

PABELLON S-3
1 2.20 3.25 7.15
3 3.40 3.25 33.15
1 2.10 3.25 6.83

PABELLON S-2
10 0.45 3.25 14.63
4 1.70 3.25 22.10
PABELLON P-01
11 0.45 3.25 16.09
6 1.70 3.25 33.15

PABELLON P-02
14 0.45 3.25 20.48
10 1.70 3.25 55.25

PABELLON P-03
13 0.45 3.25 19.01
8 1.70 3.25 44.20

PABELLON I-1
10 0.45 3.25 14.63
4 1.70 3.25 22.10

PABELLON S-3
10 0.45 3.25 14.63
4 1.70 3.25 22.10

PABELLON S-2
10 0.45 3.25 14.63
4 1.70 3.25 22.10
PABELLON P-01
11 0.45 3.25 16.09
6 1.70 3.25 33.15

PABELLON P-02
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
14 0.45 3.25 20.48
10 1.70 3.25 55.25

PABELLON P-03
13 0.45 3.25 19.01
8 1.70 3.25 44.20

PABELLON I-1
10 0.45 3.25 14.63
4 1.70 3.25 22.10

PABELLON S-3
10 0.45 3.25 14.63
4 1.70 3.25 22.10

PABELLON S-2
10 0.45 3.25 14.63
4 1.70 3.25 22.10
CERCO CERCO PERIMETRICO
32 0.70 2.50 56.00
6 0.45 2.50 6.75
COLUMNAS EN LA ENTRADA DE PRIMARIA
PRIMER PISO 1 2.85 2.95 8.41
1 4.60 2.95 13.57
2 1.30 2.95 7.67
1 1.25 2.95 3.69
SEGUNDO PISO 1 2.85 2.95 8.41
1 4.60 2.95 13.57
2 1.30 2.95 7.67
1 1.25 2.95 3.69

1049.73

TOTAL 11235.10

02.11.02 PINTURA LATEX VINILICO 2 MANOS EN CIELO RASO Y VIGAS DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL

PINTURA EN CIELO RASO AREA


PRIMER PISO
PABELLON P-1
AULA P-01 1 62.18 62.18
0.00
AULA P-02 1 62.13 62.13
0.00
AULA P-03 1 62.15 62.15
0.00
ALERO DE PASILLO 1 78.48 78.48
0.00
PABELLON P-3
AULA P-04 1 62.15 62.15
0.00
AULA P-05 1 62.13 62.13
0.00
AREA ADMINISTRATIVA 1 71.21 71.21
0.00
ALERO DE PASILLO 1 70.30 70.30
0.00
PABELLON P-2
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
SS.HH. M 1 10.88 10.88
0.00
SS. HH. H 1 10.88 10.88
0.00
SS. HH. NIÑAS 1 28.94 28.94
0.00
SS. HH. DISC 1 6.43 6.43
0.00
SS. HH. DISC 1 6.43 6.43
0.00
SSHH NIÑOS 1 29.54 29.54
0.00
SUM 1 96.13 96.13
0.00
COCINA 1 19.84 19.84
0.00
ALMACEN 1 10.51 10.51
0.00
ALERO DE PASILLO 1 95.18 95.18
0.00
CIELO RASO DETRÁS DE LOOS SERVICIOS HIGIENICOS 1 46.79 46.79
0.00
PABELLON I-1
AIULA I-01 1 64.36 64.36
0.00
SS. HH. NIÑOS 1 10.09 10.09
0.00
SS. HH. NIÑAS 1 10.09 10.09
0.00
DEPOSITO 2 2.88 5.76
0.00
AULA MI-025 1 64.24 64.24
0.00
SS. HH. NIÑOS 1 6.05 6.05
0.00
SS. HH. NIÑAS 1 4.21 4.21
0.00
DEPOSITO 1 2.71 2.71
0.00
AULA I-03 1 63.34 63.34
0.00
ALERO DE PASILLO 1 55.67 55.67
0.00
PABELLON S-3
SS.HH. NIÑOS 1 23.40 23.40
0.00
SS. HH. DISC 1 7.71 7.71
0.00
SS. HH. DISC 1 7.71 7.71
0.00
SS. HH. NIÑAS 1 23.35 23.35
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
PABELLON S-2
AULA S-04 1 62.13 62.13
0.00
AULA S-05 1 62.10 62.10
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
SEGUNDO PISO 0.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
PABELLON P-01
AULA P-06 1 62.18 62.18
0.00
AULA P-07 1 62.13 62.13
0.00
AULA P-08 1 62.15 62.15
0.00
ALERO DE PASILLO 1 78.48 78.48
0.00
PABELLON P-3
AULA P-09 1 62.15 62.15
0.00
AULA P-10 1 62.13 62.13
0.00
AULA P-11 1 71.21 71.21
0.00
ALERO DE PASILLO 1 70.30 70.30
0.00
PABELLON P-2
AULA P-12 1 62.37 62.37
0.00
AULA P-13 1 62.37 62.37
0.00
LABORATORIO 1 126.18 126.18
0.00
ALERO DE PASILLO 1 95.18 95.18
0.00
PABELLON I-1
AIULA PSICOMOTRIZ 1 64.23 64.23
0.00
SS. HH. NIÑOS 1 10.10 10.10
0.00
SS. HH. NIÑAS 1 10.09 10.09
0.00
AULA I-04 1 64.23 64.23
0.00
DEPOSITO 1 2.88 2.88
0.00
DEPOSITO 1 2.88 2.88
0.00
ALERO DE PASILLO 1 55.67 55.67
0.00
PABELLON S-3
AULA INNOVACION 1 78.41 78.41
0.00
DEPOSITO TIC 1 15.29 15.29
0.00
AREA DE CONECTIVIDAD 1 30.45 30.45
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
PABELLON S-2
AULA S-10 1 62.14 62.14
0.00
AULA S-11 1 62.16 62.16
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
TERCER PISO 0.00
PABELLON P-01
AULA P-14 1 62.18 62.18
0.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
AULA P-15 1 62.13 62.13
0.00
AULA P-16 1 62.15 62.15
0.00
ALERO DE PASILLO 1 78.48 78.48
0.00
PABELLON P-3
AULA P-17 1 62.15 62.15
0.00
AULA P-18 1 62.13 62.13
0.00
AULA P-19 1 71.21 71.21
0.00
ALERO DE PASILLO 1 70.30 70.30
0.00
PABELLON P-2
BIBLIOTECA 1 95.02 95.02
0.00
DEPOSITO 1 30.45 30.45
0.00
AREA DE CONECTIVIDAD 1 30.53 30.53
0.00
DEPOSITO TIC 1 15.37 15.37
0.00
AULA DE INNOVACION 1 78.78 78.78
0.00
ALERO DE PASILLO 1 95.18 95.18
0.00
PABELLON S-3
AULA INNOVACION 1 78.41 78.41
0.00
DEPOSITO TIC 1 15.29 15.29
0.00
AREA DE CONECTIVIDAD 1 30.45 30.45
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
PABELLON S-2
AULA S-12 1 62.14 62.14
0.00
AULA S-13 1 62.16 62.16
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00

TOTAL 4106.47

PINTURA EN VIGAS
PABELLON P-01
AULA P-01 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
AULA P-02 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
AULA P-03 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
PABELLON P-03
AULA P-04 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
AULA P-05 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
SALA ADMINISTRATIVA 2 6.05 1.05 12.71
2 11.00 0.85 18.70
4 1.95 0.65 5.07
PABELLON P-02
SS. HH. 1 6.05 0.65 3.93
8 4.88 0.85 33.15
5 1.95 0.65 6.34
SUM - COCINA 3 6.05 1.05 19.06
8 4.88 0.85 33.15
5 1.95 0.65 6.34
PABELLON I-01
AULA I-01 1 6.05 0.65 3.93
4 4.88 0.85 16.58
3 1.95 0.65 3.80
AULA I-02 1 6.05 1.05 6.35
1 13.80 0.85 11.73
4 1.95 0.65 5.07
AULA I-03 1 6.05 1.05 6.35
1 11.65 0.85 9.90
4 1.95 0.65 5.07
PABELLON S-3
SS - HH 1 6.05 0.65 3.93
4 4.88 0.85 16.58
6 1.95 0.65 7.61
1 22.60 0.85 19.21
PABELLON S-2
AULA S-4 1 6.05 0.65 3.93
4 4.88 0.85 16.58
4 1.95 0.65 5.07
AULA S-5 1 6.05 0.65 3.93
4 4.88 0.85 16.58
2 1.95 0.65 2.54
SEGUNDO PISO
PABELLON P-01
AULA P-06 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
AULA P-07 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
AULA P-08 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
PABELLON P-03
AULA P-09 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
AULA P-10 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
AULA 11 2 6.05 1.05 12.71
2 11.00 0.85 18.70
4 1.95 0.65 5.07
PABELLON P-02
AULA P-12 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
AULA 13 1 6.05 1.05 6.35
4 4.88 0.85 16.58
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
2 1.95 0.65 2.54
LABORATORIO 3 6.05 1.05 19.06
8 4.88 0.85 33.15
5 1.95 0.65 6.34
PABELLON I-1
AULA PSICOMOTRIZ 1 6.05 1.05 6.35
4 4.88 0.85 16.59
4 1.95 0.65 5.07
AULA I-04 1 6.05 1.05 6.35
4 4.88 0.85 16.59
3 1.95 0.65 3.80
SS.HH. 2 4.30 0.85 7.31
PABELLON S-3
AULA DE INNOVACION 2 6.05 1.05 12.71
1 6.05 0.50 3.03
2 22.40 0.85 38.08
6 1.95 0.65 7.61
PABELLON S-2
AULA S-10 2 6.05 0.65 7.87
4 4.88 0.85 16.58
3 1.95 0.65 3.80
AULA S-11 1 6.05 0.65 3.93
4 4.88 0.85 16.58
3 1.95 0.65 3.80

TERCER PISO
PABELLON P-01
AULA P-14 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
AULA P-15 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
AULA P-16 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
PABELLON P-03
AULA P-17 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
AULA P-18 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
AULA 19 2 6.05 1.05 12.71
2 11.00 0.85 18.70
4 1.95 0.65 5.07
PABELLON P-02
BIBLIOTECA 2 6.05 1.05 12.71
6 4.88 0.85 24.86
5 1.95 0.65 6.34
DEPOSITO 1 6.05 1.05 6.35
2 4.88 0.85 8.29
AULA DCE INNOVACION 2 6.05 1.05 12.71
8 4.88 0.85 33.15
5 1.95 0.65 6.34
1 6.05 0.55 3.33
PABELLON S-3
AULA DE INNOVACION 2 6.05 1.05 12.71
1 6.05 0.55 3.33
2 22.40 0.85 38.08
6 1.95 0.65 7.61
PABELLON S-2
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
AULA S-12 1 6.05 0.65 3.93
4 4.88 0.85 16.58
3 1.95 0.65 3.80
AULA S-13 1 6.05 0.65 3.93
4 4.88 0.85 16.58
3 1.95 0.65 3.80
CERCO CERCO PERIMETRICO 1 42.78 0.65 27.81
1 33.05 0.65 21.48
1329.93

TOTAL 5436.40

0 PINTURA EN CASETAS CODIGO ACABADODIMENSIONES UNIDAD M2


ITEM DESCRIPCION N° VECES L A H PARCIAL TOTAL

AV. BLAS DE ATIENZA


INGRESO SECUNDARIA 2 3.50 4.00 28.00
CASETA 1 14.64 3.00 43.92
TARRAJEO E TACHO 1 7.85 1.50 11.78
PUERTA -1 1.20 2.65 -3.18
MUROS ENCHAPADOS CON LAJA 1 4.05 3.00 12.15
MUROS ENCHAPADOS CON LAJA 1 1.37 3.00 4.11
MUROS ENCHAPADOS CON LAJA 1 0.55 3.00 1.65
MUROS ENCHAPADOS CON LAJA 1 6.25 3.00 18.75
JIRON 3
INGRESO PRIMARIA 2 3.50 4.00 28.00
CASETA 1 14.72 3.00 44.16
TARRAJEO E TECHO 1 7.90 1.50 11.85
PUERTA -1 1.20 2.65 -3.18

INGRESO INICIAL 2 3.50 4.00 28.00


CASETA 1 14.72 3.00 44.16
TARRAJEO E TECHO 1 7.90 1.50 11.85
PUERTA -1 1.20 2.65 -3.18

MUROS ENCHAPADOS CON LAJA 1 4.35 3.00 13.05


MUROS ENCHAPADOS CON LAJA 1 2.55 3.00 7.65
MUROS ENCHAPADOS CON LAJA 1 1.80 3.00 5.40
MUROS ENCHAPADOS CON LAJA 1 7.30 3.00 21.90
MUROS ENCHAPADOS CON LAJA 1 0.90 3.00 2.70

TOTAL 329.54

02.11.04 PINTURA ESMALTE EN CONTRAZOCALOs de 10 cm- DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL

PRIMER PISO
PABELLON P-01
ESCALERA MURO 1 15.50 15.50

PABELLON I-01
ESCALERA MURO 1 15.90 15.90

DEPOSITO MURO 1 7.11 7.11


PUERTA P-04 -1 0.80 -0.80
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
0.00
DEPOSITO MURO 1 7.11 7.11
PUERTA P-04 -1 0.80 -0.80
0.00
DEPOSITO MURO 1 6.97 6.97
PUERTA P-04 -1 0.80 -0.80
0.00
PABELLON P-03
ESCALERA MURO 1 15.50 15.50

PABELLON P-02
ESCALERA MURO 1 15.50 15.50

PABELLON S-03
ESCALERA MURO 1 21.90 21.90
0.00
PABELLON S-02
ESCALERA MURO 1 21.90 21.90
0.00
SEGUNDO PISO
PABELLON P-01
ESCALERA MURO 1 15.50 15.50

ALERO PASILLO 1 68.55 68.55

PABELLON P-03
ESCALERA MURO 1 15.50 15.50

ALERO PASILLO 1 66.40 66.40

PABELLON P-02
ESCALERA MURO 1 15.50 15.50

ALERO PASILLO 1 83.10 83.10

PABELLON I-01
DEPOSITO MURO 1 7.12 7.12
PUERTA -1 0.80 -0.80
ALERO PASILLO 1 55.80 55.80

DEPOSITO MURO 1 7.12 7.12


PUERTA -1 0.80 -0.80

ESCALERA MURO 1 15.90 15.90

PABELLON S-3
ESCALERA MURO 1 15.90 15.90

ALERO PASILLO 1 45.10 45.10

PABELLON S-2
ESCALERA MURO 1 15.90 15.90

ALERO PASILLO 1 46.20 46.20

TERCER PISO
PABELLON P-01
ESCALERA MURO 1 15.50 15.50

ALERO PASILLO 1 68.55 68.55


PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
PABELLON P-03

ESCALERA MURO 1 15.50 15.50

ALERO PASILLO 1 66.40 66.40

PABELLON P-02
DEPOSITO MURO 1 22.40 22.40
PUERTA -1 0.90 -0.90

ALERO PASILLO 1 83.10 83.10

ESCALERA MURO 1 15.90 15.90

PABELLON S-03
ESCALERA MURO 1 15.90 15.90

ALERO PASILLO 1 45.10 45.10

PABELLON S-2
ESCALERA MURO 1 15.90 15.90
ALERO PASILLO 1 46.20 46.20

ML 1006.53

0 CONTRAZOCALO DE CEMENTO SIN COLOREAR DE H=20 cm DIMENSIONES UNIDAD ML


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES A H PARCIAL TOTAL

MURO LATERAL PABELLON P-01 1 28.50 28.50


MURO LATERAL PABELLON P-03 1 29.80 29.80
MURO LATERAL PABELLON P-02 1 54.35 54.35
MURO LATERAL PABELLON I-I-1 1 68.65 68.65
MURO LATERAL PABELLON I-I-1 1 50.45 50.45
MURO LATERAL PABELLON I-I-1 1 19.15 19.15

ML 250.90

02.06.04 CONTRAZOCALO DE CEMENTO SIN COLOREAR DE H=30 cm DIMENSIONES UNIDAD ML


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES A H PARCIAL TOTAL

PABELLON P-01 CON JARDIN 1 45.65 45.65


PABELLON P-03 CON JARDIN 1 48.90 48.90
PABELLON P-02 CON JARDIN 1 57.95 57.95
PABELLON I-1 CON JARDIN 1 19.60 19.60
PABELLON S-2 CON JARDIN 1 37.15 37.15

ML 209.25

Ml 1,466.68

0 CONTRAZOCALO DE 0.55 m. EN CERCO CON IMPERMEABILIZANTE DIMENSIONES UNIDAD ML


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES A H PARCIAL TOTAL

CALLE AV. BLAS DE ATIENZA 1 93.67 93.67


PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
CALLE JR- 3 1 45.95 45.95

ML 139.62

0 0 DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL

PABELLON P-01
AULA P- 01 1.00 1.10 2.10 2.31
AULA P-02 1.00 1.10 2.10 2.31
AULA P-03 1.00 1.10 2.10 2.31
PABELLON P-03 0
AULA P-04 1.00 1.10 2.10 2.31
AULA P-05 1.00 1.10 2.10 2.31
SALA DE ADMINISTRACION 1.00 1.10 2.10 2.31
PABELLON P-02 0
SS.HH. H 1.00 1.00 2.10 2.1
SS.HH.M 1.00 1.00 2.10 2.1
SS.HH. NIÑAS 1.00 1.00 2.10 2.1
SS.HH. DISCAPAC 1.00 1.00 2.10 2.1
SS.HH. DISCAPAC 1.00 1.00 2.10 2.1
SS.HH. NIÑOS 1.00 1.00 2.10 2.1
SUM 1.00 1.10 2.10 2.31
SUM 1.00 1.10 2.10 2.31
PABELLON I-1 0
AULA I-01 1.00 1.10 2.10 2.31
DEPOSITO 1.00 0.80 2.10 1.68
DEPOSITO 1.00 1.10 2.10 2.31
SS.HH. NIÑOS 1.00 0.90 2.10 1.89
SS.HH. NIÑAS 1.00 0.90 2.10 1.89
AULA I-02 1.00 1.10 2.10 2.31
SSHH. NIÑOS 1.00 0.90 2.10 1.89
SS.HH. NIÑAS 1.00 0.90 2.10 1.89
DEPOSITO 1.00 0.80 2.10 1.68
AULA I-03 1.00 1.10 2.10 2.31
PABELLON S-3 0
SS.HH. NIÑOS 1.00 1.00 2.10 2.1
SS.HH. DISCAPAC 1.00 1.00 2.10 2.1
SS.HH. DISCAPC 1.00 1.00 2.10 2.1
SS.HH NIÑAS 1.00 1.00 2.10 2.1
PABELLON S-2 0
AULA S-04 1.00 1.10 2.10 2.31
AULA S.05 1.00 1.10 2.10 2.31
SEGUNDO PISO 0
PABELLON P-01 0
AULA P- 06 1.00 1.10 2.10 2.31
AULA P-07 1.00 1.10 2.10 2.31
AULA P-08 1.00 1.10 2.10 2.31
PABELLON P-03 0
AULA P-09 1.00 1.10 2.10 2.31
AULA P-10 1.00 1.10 2.10 2.31
AULA P-11 1.00 1.10 2.10 2.31
PABELLON P-02 0
AULA P-12 1.00 1.10 2.10 2.31
AULA P-13 1.00 1.10 2.10 2.31
LABORATORIO 1.00 1.00 2.10 2.1
LABORATORIO 1.00 1.00 2.10 2.1
PABELLON I-1 0
AULA PSICOMOTRIZ 1.00 1.10 2.10 2.31
SS.HH. NIÑOS 1.00 0.90 2.10 1.89
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO

OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA,
PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX

02.11.01 PINTURA LATEX VINILICO 2 MANOS EN MUROS Y COLUMNAS DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL
SS.HH. NIÑAS 1.00 0.90 2.10 1.89
AULA I-04 1.00 1.10 2.10 2.31
PABELLON S-3 0
AULA DE INNOVACION 1.00 1.10 2.10 2.31
AULA DE INNOVACION 1.00 1.10 2.10 2.31
DEPOSITO TIC 1.00 1.00 2.10 2.1
AREEA DE CONECTIVIDAD 1.00 1.10 2.10 2.31
PABELLON S-2 0
AULA S-10 1.00 1.10 2.10 2.31
AULA S-11 1.00 1.10 2.10 2.31
TERCER PISO 0
PABELLON P-01 0
AULA P- 14 1.00 1.10 2.10 2.31
AULA P-15 1.00 1.10 2.10 2.31
AULA P-16 1.00 1.10 2.10 2.31
PABELLON P-03 0
AULA P-17 1.00 1.10 2.10 2.31
AULA P-18 1.00 1.10 2.10 2.31
AULA P-19 1.00 1.10 2.10 2.31
PABELLON P-02 0
BIBLIOTECA 1.00 1.10 2.10 2.31
BIBLIOTECA 1.00 1.10 2.10 2.31
DEPOSITO 1.00 0.90 2.10 1.89
AREA DE CONECTIVIDAD 1.00 1.10 2.10 2.31
DEPOSITO TIC 1.00 0.90 2.10 1.89
AULA INNOVACION 1.00 1.10 2.10 2.31
AULA INNOVACION 1.00 1.10 2.10 2.31
PABELLON S-3 0
AULA DE INNOVACION 1.00 1.10 2.10 2.31
AULA DE INNOVACION 1.00 1.10 2.10 2.31
DEPOSITO TIC 1.00 1.00 2.10 2.1
AREEA DE CONECTIVIDAD 1.00 1.10 2.10 2.31
PABELLON S-2 0
AULA S-12 1.00 1.10 2.10 2.31
AULA S-13 1.00 1.10 2.10 2.31

COCINA 1.00 1.10 2.10 2.31


ALMACEN

154.14

02.11.08 PINTURA ANTICORROSIVA Y ESMALTE 2 MANOS EN CERCO METALICO DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADON° VECES L H PARCIAL TOTAL

TUBO f⁰ n⁰ 2´´ 7 0.40 2.20 6.14


ANGULO 1´´ x 1/8´´ - Horizontal 7 1.41427 9.90
ANGULO 1´´ x 1/8´´ - Vertical 7 1.5687 10.98
ANGULO 1´´ x 1/8´´ - Parte central 7 1.44272 10.10

37.12

02.11.10 PINTURA PARA DEMARCACION DE LOSA DEPORTIVA DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO
N° VECES L H PARCIAL TOTAL

LOSA DEPORTIVA - N. PRIMARIA 1 546.21 0.05 27.31

TOTAL 27.31
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX - -

02.12.01 JUNTAS DE DILATACION CON ESPUMA PLÁSTICA + JEBE MICROPOROSO DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

COLUMNAS
AULA P-01 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-02 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-03 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-04 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-05 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
SALA DE ADMINISTRATIVO ENTRE COLY 12 1.30 15.60
10 2.10 21.00
SS.HH. NIÑOS Y NIÑAS ENTRE COLY 8 2.95 23.60
24 2.10 50.40
SUM COCINA ENTRE COLY 16 1.30 20.80
12 2.10 25.20
2 2.95 5.90
PABELLON I-01 ENTRE COLY 16 1.30 20.80
20 2.10 42.00
2 2.95 5.90
AULA I-03 ENTRE COLY 8 1.30 10.40
14 2.10 29.40
2 3.25 6.50
PABELLON S-3 ENTRE COLY 0 0.00
10 2.10 21.00
PABELLON S-2 ENTRE COLY 16 1.30 20.80
12 2.10 25.20
SEGUNDO
AULA P-06 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-07 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-08 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-09 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-10 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-11 ENTRE COLY 12 1.30 15.60
12 2.10 25.20
AULA P-12 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-13 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
LABOARATORIO ENTRE COLY 16 1.30 20.80
12 2.10 25.20
PABELLON I-01 ENTRE COLY 16 1.30 20.80
20 2.10 42.00
4 2.95 11.80
PABELLON S-3 ENTRE COLY 26 2.10 54.60
0.00
PABELLON S-2 ENTRE COLY 16 1.30 20.80
12 2.10 25.20

TERCER PISO
AULA P-14 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-15 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-16 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-17 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-18 ENTRE COLY 8 1.30 10.40
6 2.10 12.60
AULA P-19 ENTRE COLY 12 1.30 15.60
10 2.10 21.00
BIBLIOTECA ENTRE COLY 12 1.30 15.60
8 2.10 16.80
DEPOSITO ENTRE COLY 4 1.30 5.20
4 2.10 8.40
AREA DE CONECTIV ENTRE COLY 16 1.30 20.80
16 2.10 33.60
PABELLON S-3 ENTRE COLY 26 2.10 54.60
0.00
PABELLON S-2 ENTRE COLY 16 1.30 20.80
12 2.10 25.20
ML 1235.10
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX - -

02.12.01 JUNTAS DE DILATACION CON ESPUMA PLÁSTICA + JEBE MICROPOROSO DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

02.12.02 TAPAJUNTA DE ACERO INOXIDABLE EN PISOS Y PARED DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

PRIMER PISO
PABELLON P-01 PARED 1 6.75 6.75
PISO 1 4.25 4.25
PABELLON P-03 PARED 1 6.75 6.75
PISO 1 4.25 4.25
PABELLON P-02 PARED 2 6.75 13.50
PISO 2 4.25 8.50
PABELLON I-1 PARED 1 6.75 6.75
PISO 1 4.25 4.25
PABELLON S-3 PARED 1 6.75 6.75
PISO 1 4.25 4.25
PABELLON S-2 PARED 1 6.75 6.75
PISO 1 4.25 4.25

SEGUNDO PISO
PABELLON P-01 PARED 1 6.75 6.75
PISO 1 6.40 6.40
PABELLON P-03 PARED 1 6.75 6.75
PISO 1 6.40 6.40
PABELLON P-02 PARED 2 6.75 13.50
PISO 2 6.40 12.80
PABELLON I-1 PARED 1 7.53 7.53
PISO 1 6.40 6.40
PABELLON S-3 PARED 1 6.75 6.75
PISO 1 6.40 6.40
PABELLON S-2 PARED 1 6.75 6.75
PISO 1 6.40 6.40
TERCER PISO
PABELLON P-01 PARED 1 7.53 7.53
PISO 1 6.40 6.40
PABELLON P-03 PARED 1 7.53 7.53
PISO 1 6.40 6.40
PABELLON P-02 PARED 2 7.53 15.06
PISO 2 6.40 12.80
PABELLON S-3 PARED 1 7.53 7.53
PISO 1 6.40 6.40
PABELLON S-2 PARED 1 7.53 7.53
PISO 1 6.40 6.40

ML 253.41

02.13.05 TAPAJUNTA DE ACERO INOXIDABLE + SELLO ASFALTICO BITUMINOSO EN TECHO - EXTERIOR DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

SEGUNDO PISO
PABELLON I-1 TECHO 1 9.95 9.95
TERCER PISO
PABELLON P-01 TECHO 1 9.95 9.95
PABELLON P-03 TECHO 1 9.95 9.95
PABELLON P-02 TECHO 2 9.95 19.90
PABELLON S-3 TECHO 1 9.95 9.95
PABELLON S-2 TECHO 1 9.95 9.95

ML 69.65

02.12.04 JUNTA DE DILATACION EN PISOS CON TECNOPORT DE e= 3/8" RELLENO CON POLIURETANO DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

PABELLON 01
AULAS 09 Y 10 2 29.9 59.80
DEPOSITO 1 21.2 21.20
LABORATORIO DE CIENCIAS - PRIMARIA 1 44.6 44.60
DEPOSITO 02 1 13.92 13.92
BIBLIOTECA PRIMARIA 1 45.50 45.50
PABELLON 02
AULAS 6 29.90 179.40
DEPOSITO 02 1 14.07 14.07
PABELLON 03
ADMINISTRACION 1 29.90 29.90
DEPOSITO LABORATORIO 1 13.76 13.76
TOPICO DE PSICOLOGIA 1 13.01 13.01
LABORATORIO BIOLOGIA QUIMICA - SEC. 1 37.70 37.70
DEPOSITO 01 1 14.07 14.07
BIBLIOTECA SECUNDARIA 1 37.70 37.70
AULA DE INNOVACION - PRIMARIA 1 37.70 37.70
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA
“ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA :PINTURA LATEX - -

02.12.01 JUNTAS DE DILATACION CON ESPUMA PLÁSTICA + JEBE MICROPOROSO DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL
SALA DE INNOVACION - SEC 1 37.70 37.70
SUM 1 37.70 37.70

CAFETERIA COMEDOR 1 26.14 26.14

SS.HH MODULO 01 Y MODULO 02 2 43.05 86.10

ML 749.97
02.12.05 JUNTAS ASFALTICAS e=1´´ DIMENSIONES UNIDAD M2
ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

VEREDAS DEL PABELLON P-1 12 1.95 23.40


VEREDAS ENCUENTRO CON PARED DEL PANBELLON P-1 1 71.95 71.95
VEREDAS PABELLON I-1 1 147.97 147.97
VEREDAS PABELLON I-1 23 1.95 44.85
VEREDAS PABELLON P-3 1 92.25 92.25
VEREDAS PABELLON P-3 12 1.95 23.40
VEREDAS PABELLON P-2 1 144.65 144.65
VEREDAS PABELLON P-2 16 1.95 31.20
VEREDAS EN PABELLON S-3 1 54 54.00
VEREDAS EN PABELLON S-3 10 1.95 19.50
VEREDAS EN PABELLON S-2 1 60 60.00
VEREDAS EN PABELLON S-2 11 1.95 21.45
PLATAFORMA INICIAL 5 17.02 85.10
PLATAFORMA INICIAL 6 12.03 72.18
PLATAFORMA PRIMARIA 2 27.5 55.00
PLATAFORMA PRIMARIA 8 4.65 37.20
PLATAFORMA PRIMARIA 2 26.55 53.10
PLATAFORMA PRIMARIA 10 4.05 40.50
ML 1,077.70

02.12.06 JUNTA ESLASTOMERICA PARA CUNETAS e=1/2´´ DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADO N° VECES L H PARCIAL TOTAL

PABELLON P-01 7 0.95 6.65


PABELLON I-1 3 0.95 2.85
PABELLON P-2 7 0.95 6.65
PABELLON P-2 14 0.95 13.30
PABEELON S-3 8 0.95 7.60

ML 37.05
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE PIURA -
PIURA''

PARTIDA : CUBIERTAS #REF! #REF!

id PISO Nº
DESCRIPCION VECES
DIMENSIONES PARCIAL TOTAL

id PISO DESCRIPCION TIPO VANO CODIGO ACABADO Nº VECES a L PARCIAL TOTAL

2.13 COBERTURA

02.13.01 COBERTURA CON PLANCHA TERMOACUSTICA DE CALAMINON (INC. ESTRUCTURA DE SOPORTE DE MADERA)

PABELLON P-01 1 8.55 13.50 115.43


PABELLON P-01 1 8.55 20.45 174.85
PABELLON P-03 1 8.55 20.45 174.85
PABELLON P-03 1 8.55 14.65 125.26
PABELLON P-02 1 8.55 20.45 174.85
PABELLON P-02 ESCALERA 1 8.55 2.95 25.22
PABELLON P-02 1 8.55 20.10 171.86
PABELLON I-1 ESCALERA 1 8.55 2.90 24.80
PABELLON I-1 1 8.55 25.00 213.75
PABELLON I-1 1 8.55 12.35 105.59
PABELLON S-3 1 8.55 23.40 200.07
PABELLON S-2 1 8.55 23.95 204.77

1711.28

02.13.02 COBERTURA CON PLANCHA TERMOACUSTICA DE CALAMINON (INC. ESTRUCTURA DE SOPORTE METALICA)

COBERTURA AULAS EXTERIORES 1,2,3 AL LADO DE LA ENTRADA DE INICIAL Y PRIMARIA 1 77.17 77.17

77.17
02.13.03 COBERTURA DE POLICARBONATO EN TAPASOL (INC.ESTRUCTURA DE SOPORTE METALICA)

PABELLON P-01 3 31.25 1.05 98.44


PABELLON P-03 3 32.75 1.05 103.16
PABELLON P-02 3 41.85 1.05 131.83
PABELLON I-1 2 21.00 1.05 44.10
PABELLON S-2 3 20.75 1.05 65.36
442.89

02.13.04 COBERTURA CURVA CON PLANCHA CU. DE ALUMINIO ZINC E= 0.4mm


0.00
PATIO TECHADO DE INICIAL 1 9.95 14.20 141.29
TECHO DE LOSA DEPORTIVA PABELLON 02 1 21.82 30.47 664.86
TECHO DE PATIO SECUNDARIA 1 16.00 25.00 400.00

1206.15

02.13.05 COBERTURA LADRILLO PASTELERO ASENTADO CON MEZCLA DE CEMENTO

T.E 1 2.80 2.90 8.12


SALA DE MAQUINAS 1 2.93 3.03 8.88
ENTRADA JARDIN 1 1.50 8.40 12.60
ENTRADA PRIMARIA 1 1.50 8.40 12.60
ENTRADA SECUNDARIA 1 1.50 8.40 12.60
0.00 54.80
0.00
02.13.06 IMPERMEABILIZANTE DE TECHOS CON PINTURA ASFALTICA 0.00
0.00
PABELLON P-01 1 8.55 13.50 115.43
PABELLON P-01 1 8.55 20.45 174.85
PABELLON P-03 1 8.55 20.45 174.85
PABELLON P-03 1 8.55 14.65 125.26
PABELLON P-02 1 8.55 20.45 174.85
PABELLON P-02 ESCALERA 1 8.55 2.95 25.22
PABELLON P-02 1 8.55 20.10 171.86
PABELLON I-1 ESCALERA 1 8.55 2.90 24.80
PABELLON I-1 1 8.55 25.00 213.75
PABELLON I-1 1 8.55 12.35 105.59
PABELLON S-3 1 8.55 23.40 200.07
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO DE PIURA, PROVINCIA DE PIURA -
PIURA''

PARTIDA : CUBIERTAS #REF! #REF!

id PISO Nº
DESCRIPCION VECES
DIMENSIONES PARCIAL TOTAL

id PISO DESCRIPCION TIPO VANO CODIGO ACABADO Nº VECES a L PARCIAL TOTAL


PABELLON S-2 1 8.55 23.95 204.77
1711.28
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO
DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: VARIOS #REF! #REF!

id PISO
DESCRIPCION DIMENSIONESPARCIAL
Nº VECES TOTAL

id PISO DESCRIPCION Nº VECES a PARCIAL TOTAL

02.14.01 TABLERO CON REVESTIMIENTO DE POLVO DE MARMOL PARA OVALINES SS.HH


PABELLON I-1 SS.HH NIÑOS- NIÑÑAS 2 1.40 2.8
SS.HH NIÑOS- NIÑÑAS 2 0.70 1.4
PABELLON P-02 SS.HH. H -M 2 1.36 2.72
SS.HH. DISCA 2 0.90 1.8
PABELLON S-3 SS.HH. DISCA 2 0.90 1.8
PABELLON I-1 SS.HH NIÑOS- NIÑÑAS 2 1.40 2.8

TOTAL ML 13.32

#REF! #REF!

PABELLON P-01 AREA 86.44 8.64


PABELLON P-03 AREA 76.22 7.62
PABELLON P-02 AREA 74.61 7.46
PABELLON I-1 AREA 32.57 3.26
PABELLON S-2 AREA 201.45 20.15
PABELLON EXISTENTE AREA 74.78 7.48
0.00
0.00
TOTAL M3 54.61

#REF! #REF!

PABELLON P-01 AREA 86.44 86.44


PABELLON P-03 AREA 76.22 76.22
PABELLON P-02 AREA 74.61 74.61
PABELLON I-1 AREA 32.57 32.57
PABELLON S-2 AREA 201.45 201.45
PABELLON EXISTENTE AREA 74.78 74.78

0.00
TOTAL M2 546.07

#REF! #REF!
20.00 UNID

02.14.02 CURADO CON CURADOR QUIMICO PARA CONCRETO DIMENSIONES UNIDAD M2


ITEM PISO DESCRIPCION VANO CODIGO ACABADON° VECES L H PARCIAL TOTAL

PRIMER PISO
PABELLON P-1
AULA P-01 1 62.18 62.18
0.00
AULA P-02 1 62.13 62.13
0.00
AULA P-03 1 62.15 62.15
0.00
ALERO DE PASILLO 1 78.48 78.48
0.00
PABELLON P-3
AULA P-04 1 62.15 62.15
0.00
AULA P-05 1 62.13 62.13
0.00
AREA ADMINISTRATIVA 1 71.21 71.21
0.00
ALERO DE PASILLO 1 70.30 70.30
0.00
PABELLON P-2
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO
DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: VARIOS #REF! #REF!


SS.HH. M 1 10.88 10.88
0.00
SS. HH. H 1 10.88 10.88
0.00
SS. HH. NIÑAS 1 28.94 28.94
0.00
SS. HH. DISC 1 6.43 6.43
0.00
SS. HH. DISC 1 6.43 6.43
0.00
SSHH NIÑOS 1 29.54 29.54
0.00
SUM 1 96.13 96.13
0.00
COCINA 1 19.84 19.84
0.00
ALMACEN 1 10.51 10.51
0.00
ALERO DE PASILLO 1 95.18 95.18
0.00
CIELO RASO DETRÁS DE LOOS SERVICIOS HIGIENICOS 1 46.79 46.79
0.00
PABELLON I-1
AIULA I-01 1 64.36 64.36
0.00
SS. HH. NIÑOS 1 10.09 10.09
0.00
SS. HH. NIÑAS 1 10.09 10.09
0.00
DEPOSITO 2 2.88 5.76
0.00
AULA MI-025 1 64.24 64.24
0.00
SS. HH. NIÑOS 1 6.05 6.05
0.00
SS. HH. NIÑAS 1 4.21 4.21
0.00
DEPOSITO 1 2.71 2.71
0.00
AULA I-03 1 63.34 63.34
0.00
ALERO DE PASILLO 1 55.67 55.67
0.00
PABELLON S-3
SS.HH. NIÑOS 1 23.40 23.40
0.00
SS. HH. DISC 1 7.71 7.71
0.00
SS. HH. DISC 1 7.71 7.71
0.00
SS. HH. NIÑAS 1 23.35 23.35
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
PABELLON S-2
AULA S-04 1 62.13 62.13
0.00
AULA S-05 1 62.10 62.10
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
SEGUNDO PISO 0.00
PABELLON P-01
AULA P-06 1 62.18 62.18
0.00
AULA P-07 1 62.13 62.13
0.00
AULA P-08 1 62.15 62.15
0.00
ALERO DE PASILLO 1 78.48 78.48
0.00
PABELLON P-3
AULA P-09 1 62.15 62.15
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO
DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: VARIOS #REF! #REF!


0.00
AULA P-10 1 62.13 62.13
0.00
AULA P-11 1 71.21 71.21
0.00
ALERO DE PASILLO 1 70.30 70.30
0.00
PABELLON P-2
AULA P-12 1 62.37 62.37
0.00
AULA P-13 1 62.37 62.37
0.00
LABORATORIO 1 126.18 126.18
0.00
ALERO DE PASILLO 1 95.18 95.18
0.00
PABELLON I-1
AIULA PSICOMOTRIZ 1 64.23 64.23
0.00
SS. HH. NIÑOS 1 10.10 10.10
0.00
SS. HH. NIÑAS 1 10.09 10.09
0.00
AULA I-04 1 64.23 64.23
0.00
DEPOSITO 1 2.88 2.88
0.00
DEPOSITO 1 2.88 2.88
0.00
ALERO DE PASILLO 1 55.67 55.67
0.00
PABELLON S-3
AULA INNOVACION 1 78.41 78.41
0.00
DEPOSITO TIC 1 15.29 15.29
0.00
AREA DE CONECTIVIDAD 1 30.45 30.45
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
PABELLON S-2
AULA S-10 1 62.14 62.14
0.00
AULA S-11 1 62.16 62.16
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
TERCER PISO 0.00
PABELLON P-01
AULA P-14 1 62.18 62.18
0.00
AULA P-15 1 62.13 62.13
0.00
AULA P-16 1 62.15 62.15
0.00
ALERO DE PASILLO 1 78.48 78.48
0.00
PABELLON P-3
AULA P-17 1 62.15 62.15
0.00
AULA P-18 1 62.13 62.13
0.00
AULA P-19 1 71.21 71.21
0.00
ALERO DE PASILLO 1 70.30 70.30
0.00
PABELLON P-2
BIBLIOTECA 1 95.02 95.02
0.00
DEPOSITO 1 30.45 30.45
0.00
AREA DE CONECTIVIDAD 1 30.53 30.53
0.00
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO
DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: VARIOS #REF! #REF!


DEPOSITO TIC 1 15.37 15.37
0.00
AULA DE INNOVACION 1 78.78 78.78
0.00
ALERO DE PASILLO 1 95.18 95.18
0.00
PABELLON S-3
AULA INNOVACION 1 78.41 78.41
0.00
DEPOSITO TIC 1 15.29 15.29
0.00
AREA DE CONECTIVIDAD 1 30.45 30.45
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00
PABELLON S-2
AULA S-12 1 62.14 62.14
0.00
AULA S-13 1 62.16 62.16
0.00
ALERO DE PASILLO 1 46.90 46.90
0.00

VEREDAS

PABELLON 01 1 66.85 66.85


PABELLON 03 1 77.57 77.57
PABELLON 02 1 129.02 129.02
PABELLON 02 - CISTERNA 1 17.08 17.08
PABELLON I-1 1 67.89 67.89
PABELLON I-1 1 84.87 84.87
HALL 1 21.41 21.41
PABELLON S-3 1 64.39 64.39
PABELLON S-3 1 46.79 46.79
PABELLON S-2 1 46.87 46.87

TOTAL 4729.21
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO
DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: VARIOS #REF! #REF!


COLUMNAS
1°PISO PABELLON P-01
12 0.45 3.25 17.55
6 1.70 3.25 33.15

1°PISO PABELLON P-02


12 0.45 3.25 17.55
8 1.70 3.25 44.20

1°PISO PABELLON P-03


10 0.45 3.25 14.63
6 1.70 3.25 33.15
6 0.73 3.25 14.14
2 0.80 3.25 5.20

1°PISO PABELLON I-1


6 0.45 3.25 8.78
8 1.70 3.25 44.20
2 1.10 3.25 7.15

PABELLON S-3
1 2.20 3.25 7.15
3 3.40 3.25 33.15
1 2.10 3.25 6.83

PABELLON S-2
10 0.45 3.25 14.63
4 1.70 3.25 22.10
2°PISO PABELLON P-01
11 0.45 3.25 16.09
6 1.70 3.25 33.15

2°PISO PABELLON P-02


14 0.45 3.25 20.48
10 1.70 3.25 55.25

2°PISO PABELLON P-03


13 0.45 3.25 19.01
8 1.70 3.25 44.20

2°PISO PABELLON I-1


10 0.45 3.25 14.63
4 1.70 3.25 22.10

2°PISO PABELLON S-3


10 0.45 3.25 14.63
4 1.70 3.25 22.10

2°PISO PABELLON S-2


10 0.45 3.25 14.63
4 1.70 3.25 22.10
3°PISO PABELLON P-01
11 0.45 3.25 16.09
6 1.70 3.25 33.15

3°PISO PABELLON P-02


14 0.45 3.25 20.48
10 1.70 3.25 55.25

3°PISO PABELLON P-03


13 0.45 3.25 19.01
8 1.70 3.25 44.20

3°PISO PABELLON I-1


10 0.45 3.25 14.63
4 1.70 3.25 22.10

3°PISO PABELLON S-3


10 0.45 3.25 14.63
4 1.70 3.25 22.10

3°PISO PABELLON S-2


10 0.45 3.25 14.63
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO
DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: VARIOS #REF! #REF!


4 1.70 3.25 22.10

TOTAL 920.30

VIGAS
PABELLON P-01
1⁰ PISO AULA P-01 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
1⁰ PISO AULA P-02 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
1⁰ PISO AULA P-03 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
PABELLON P-03
1⁰ PISO AULA P-04 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
1⁰ PISO AULA P-05 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
1⁰ PISO SALA ADMINISTRATIVA 2 6.05 1.05 12.71
2 11.00 0.85 18.70
4 1.95 0.65 5.07
PABELLON P-02
1⁰ PISO SS. HH. 1 6.05 0.65 3.93
8 4.88 0.85 33.15
5 1.95 0.65 6.34
1⁰ PISO SUM - COCINA 3 6.05 1.05 19.06
8 4.88 0.85 33.15
5 1.95 0.65 6.34
PABELLON I-01
1⁰ PISO AULA I-01 1 6.05 0.65 3.93
4 4.88 0.85 16.58
3 1.95 0.65 3.80
1⁰ PISO AULA I-02 1 6.05 1.05 6.35
1 13.80 0.85 11.73
4 1.95 0.65 5.07
1⁰ PISO AULA I-03 1 6.05 1.05 6.35
1 11.65 0.85 9.90
4 1.95 0.65 5.07
PABELLON S-3
1⁰ PISO SS - HH 1 6.05 0.65 3.93
4 4.88 0.85 16.58
6 1.95 0.65 7.61
1 22.60 0.85 19.21
PABELLON S-2
1⁰ PISO AULA S-4 1 6.05 0.65 3.93
4 4.88 0.85 16.58
4 1.95 0.65 5.07
1⁰ PISO AULA S-5 1 6.05 0.65 3.93
4 4.88 0.85 16.58
2 1.95 0.65 2.54
SEGUNDO PISO
PABELLON P-01
2° PIISO AULA P-06 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
2° PIISO AULA P-07 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
2° PIISO AULA P-08 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
PABELLON P-03
2° PIISO AULA P-09 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
2° PIISO AULA P-10 1 6.05 1.05 6.35
4 4.88 0.85 16.58
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO
DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: VARIOS #REF! #REF!


2 1.95 0.65 2.54
2° PIISO AULA 11 2 6.05 1.05 12.71
2 11.00 0.85 18.70
4 1.95 0.65 5.07
PABELLON P-02
2° PIISO AULA P-12 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
2° PIISO AULA 13 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
2° PIISO LABORATORIO 3 6.05 1.05 19.06
8 4.88 0.85 33.15
5 1.95 0.65 6.34
PABELLON I-1
2° PIISO AULA PSICOMOTRIZ 1 6.05 1.05 6.35
4 4.88 0.85 16.59
4 1.95 0.65 5.07
2° PIISO AULA I-04 1 6.05 1.05 6.35
4 4.88 0.85 16.59
3 1.95 0.65 3.80
2° PIISO SS.HH. 2 4.30 0.85 7.31
PABELLON S-3
2° PIISO AULA DE INNOVACION 2 6.05 1.05 12.71
1 6.05 0.50 3.03
2 22.40 0.85 38.08
6 1.95 0.65 7.61
PABELLON S-2
2° PIISO AULA S-10 2 6.05 0.65 7.87
4 4.88 0.85 16.58
3 1.95 0.65 3.80
2° PIISO AULA S-11 1 6.05 0.65 3.93
4 4.88 0.85 16.58
3 1.95 0.65 3.80

TERCER PISO
PABELLON P-01
3ERR PISO AULA P-14 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
3ERR PISO AULA P-15 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
3ERR PISO AULA P-16 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
PABELLON P-03
3ERR PISO AULA P-17 1 6.05 1.05 6.35
4 4.88 0.85 16.58
3 1.95 0.65 3.80
3ERR PISO AULA P-18 1 6.05 1.05 6.35
4 4.88 0.85 16.58
2 1.95 0.65 2.54
3ERR PISO AULA 19 2 6.05 1.05 12.71
2 11.00 0.85 18.70
4 1.95 0.65 5.07
PABELLON P-02
3ERR PISO BIBLIOTECA 2 6.05 1.05 12.71
6 4.88 0.85 24.86
5 1.95 0.65 6.34
3ERR PISO DEPOSITO 1 6.05 1.05 6.35
2 4.88 0.85 8.29
3ERR PISO AULA DCE INNOVACION 2 6.05 1.05 12.71
8 4.88 0.85 33.15
5 1.95 0.65 6.34
1 6.05 0.55 3.33
PABELLON S-3
3ERR PISO AULA DE INNOVACION 2 6.05 1.05 12.71
1 6.05 0.55 3.33
2 22.40 0.85 38.08
6 1.95 0.65 7.61
PABELLON S-2
3ERR PISO AULA S-12 1 6.05 0.65 3.93
PRESUPUESTO DE PINTURA - EXPEDIENTE TECNICO
OBRA: “ELABORACION DEL EXPEDIENTE TÉCNICO: '' REHABILITACION DEL LOCAL ESCOLAR VÍCTOR FRANCISCO ROSALES ORTEGA, DISTRITO
DE PIURA, PROVINCIA DE PIURA -PIURA''

PARTIDA: VARIOS #REF! #REF!


4 4.88 0.85 16.58
3 1.95 0.65 3.80
3ERR PISO AULA S-13 1 6.05 0.65 3.93
4 4.88 0.85 16.58
3 1.95 0.65 3.80

TOTAL 1280.64

TOTAL CURADO 6930.15

02.14.03 ELEMENTO ESTRUCTURAL EN PATIO

GRUTA 1 1.00 1.00 1.00 1.00

TOTAL UND 1.00

02.14.06 IMPLEMENTACION DE ESTRUCTURA EN SERVICIOS HIGIENICOS DE INICIAL


CLOSET
PABELLON I-1 1 1.44 0.60 0.86
PABELLON S-3 4 2.05 0.60 4.92
PABELLON S-3 2 1.25 0.40 1.00
PABELLON I-1 1 1.44 0.60 0.86
PABELLON P-2 1 1.98 0.60 1.19

UNDS. 9 TOTAL M2 8.83