CRONOGRAMA DE EJECUCION FISICO Y FINANCIERO

PROYECTO : MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE DE LA LOCALIDAD DE MATIBAMBA FECHA : ABRIL
UBICACIÓN : DISTRITO MASIN, PROVINCIA HUARI, DEPARTAMENTO ANCASH COSTO DIRECTO TOTAL S/.: 178,988.88
FECHA : ABRIL 2009

Descripción MES 01 MES 02 MES 03


Item
Parcial (S/.) S1 S2 S3 S4 S1 S2 S3 S4 S1 S2 S3 S4
S/. 2196.00
01 0BRAS PRELIMINARES 2,196.00 P X
E
S/. 2666.40 2666.40 2666.40
02 CAPTACION DE MANANTIAL (01 UNIDAD) 7,999.20 P X X X
E
S/. 5237.77 5237.77 5237.77 5237.77
03 LINEA DE CONDUCCION CON TUBERIA (1213.00 ML) 20,951.08 P X X X X
E
S/. 493.90 493.90
04 CRP-6 (01 UNIDAD) 987.79 P X X
E
S/. 3184.36 3184.36 3184.36 3184.36
05 RESERVORIO RECTANGULAR DE 10 m3 12,737.42 P X X X X
E
S/. 1413.68
06 CAJA DE VALVULAS 1,413.68 P X
E
S/. 1775.52 1775.52
07 LINEA DE ADUCCION CON TUBERIA (212.20 ML) 3,551.03 P X X
E
S/. 6348.97 6348.97 6348.97 6348.97
08 RED DE DISTRIBUCION (1515.62 ml) 25,395.86 P X X X X
E
S/. 6398.44 6398.44
09 C.R.P TIPO 7 (03 UNIDADES) 12,796.88 P X X
E
S/. 3466.18 3466.18 3466.18
10 CONEXION DOMICILIRIA (56 UNIDADES) 10,398.55 P X X X
E
S/. 7317.40 7317.40 7317.40 7317.40 7317.40
11 LAVADERO DOMICILIARI (56 UNIDADES) 36,587.02 P X X X X X
E
S/. 2194.14 2194.14
12 VALVULA DE PURGA (09 UNIDADES) 4,388.28 P X X
E
S/. 140.00 140.00
13 PRUEBA DE RESISTENCIA A LA COMPRESION DEL CONCRETO 280.00 P X X
E
S/. 4367.34 4367.34 4367.34 4367.34 4367.34 4367.34 4367.34 4367.34 4367.34
14 FLETE 39,306.09 P X X X X X X X X X
E
TOTAL 33912.77 46954.32 98121.79
33,912.77 ( 19%) 46,954.32 ( 26%) 98,121.79 ( 55%)
AVANCE MENSUAL % PROGRAMADO
33,912.77 ( 19%) 80,867.09 ( 45%) 178,988.88 ( 100%)
AVANCE ACUMULADO % PROGRAMADO