COMPUTOS METRICOS

FECHA:
DIMENSIONES
COD ITEM DESCRIPCION EJES UNID. Largo (m) Ancho(m) Alto (m) PARCIAL TOTAL
MO1 HORMIGO ARMADO 29.14
BASE M3 10.82
BASE A1 47.00 1.15 0.10 5.41
A2 47.00 1.15 0.10 5.41
0.00
LADO IZQUIERDO M3 3.20
A1 47.00 0.40 0.02 0.38 0.19
A2 47.00 0.40 0.15 2.82 2.82
A3 47.00 0.40 0.02 0.38 0.19
LADO DERECHO M3 3.20
A1 47.00 0.40 0.02 0.38 0.19
A2 47.00 0.40 0.15 2.82 2.82
A3 47.00 0.40 0.02 0.38 0.19
ARCO M3 10.55
A1 47.00 1.00 1.00 22.70 22.70
47.00 1.00 1.00 12.15 12.15
ACERO DE VIGA SEGÚN EL PLANO
DIAMETRO LONGITUD (m) DETALLE
POS CANTIDAD
mm UNITARIA TOTAL BARRAS TOTAL cm
1 9.5 32 12 384 32 #REF! 1 12.0
2 6 230 1.05 241.5 20.125 #REF!
2 1.05
Acero de una LOSA TOTAL (Kg) #REF!

Empedrado M3 10.58
A1 47.00 2.25 0.10 10.58 10.58

EXCABACION M3 115.15
A1 47.00 2.45 1.00 115.15 115.15

CAPA SUBBASE M3 39.95


A1 47.00 1.70 0.50 39.95 39.95

CAPA BASE M3 94.00


A1 47.00 2.00 1.00 94.00 94.00
ITEMS
MO1 HORMIGO ARMADO m3 29.14
MO2 EMPEDRADO m3 7.29
MO3 EXCAVACION m3 186.12
MO4 CAPA BASE m3 86.95
MO5 CAPA SUBBASE m3 103.40
MO6 EMBOQUILLADO m3 23.50

TOTAL PRESUPUESTO BS 58.568,49


DESCRIPCIONHORMIGON SIMPLE P/BOVEDA CANTIDAD:
UNIDAD: m3 MONEDA:Bs

A:MATERIALES unidad cantidad unitario total


arena Nº4 m3 0.38 100 38
grava3/4'' m3 0.43 120 51.6
cemento kg 400 0.96 384
alambre kg 2 12 24
clavos kg 2 10 20
madera pie 2 27.01 7.2 194.472
agua m3 0.196 25 4.9
galleta pza 12 0.2 2.4
A= 719.37

B: MANO DE OBRA rend jornal


albañil 16 180 360
peon 16 130 260
subtotal 620.00
cargas sociales (55-71,18) 60 620*60% = 372.00
iva (14,94) (372+620)*14.94% = 148.20
TO TOTAL MANO DE OBRA B= 620+372+148.2 = 1140.20

C : HERRAMIENTAS Y EQUIPO
herramientas(3-8) 5 57.01
equipo 10 114.02
OSTO TOTAL HERR. Y EQU C= 57.01+114.02 = 171.03

D: COSTO DIRECTO D= 719.37+1140.2+171.03 = 2030.61

E: GASTOS GENERALES (5-15) E= 2030.61*10% = 203.06


10
F: UTILIDAD(5-15) F= (2030.61 + 203.06*10% = 223.37
10
G: PRECIO DEL ITEM G= 2030.61+203.06+223.37 = 2457.04

H: IT + ITF (3,09) H= 2457.04*3.09% = 75.92


3.09
I: PRECIO DE APLICACION I= 2457.04+75.92 = 2532.96
DESCRIPCION: CANTIDAD: CUANTIA DE ACERO
UNIDAD: MONEDA:Bs

A:MATERIALES unidad cantidad unitario total


arena m3 0.5 90.00 45
grava m3 0.8 110.00 88
cemento kg 350 1.16 406
fierro kg 180 7.15 1287
alambre kg 2 13.00 26
clavos kg 2 13.00 26
madera pie 2 70 8.70 609
agua m3 0.196 25.00 4.9
galleta pza 12 0.20 2.4
A= 2494.30

B: MANO DE OBRA rend jornal


albañil 22 120 330
peon 23 90 258.75
subtotal 588.75
cargas sociales (55-71,18) 60 588.75*60% = 353.25
iva (14,94) (353.25+588.75)*14.94% = 140.73
TO TOTAL MANO DE OBRA B= 588.75+353.25+140.73 = 1082.73

C : HERRAMIENTAS Y EQUIPO
herramientas(3-8) 5 54.14
equipo 10 108.27
OSTO TOTAL HERR. Y EQU C= 54.14+108.27 = 162.41

D: COSTO DIRECTO D= 2494.3+1082.73+162.41 = 3739.45

E: GASTOS GENERALES (5-15) E= 3739.45*10% = 373.94


10
F: UTILIDAD(5-15) F= (3739.45 + 373.94*10% = 411.34
10
G: PRECIO DEL ITEM G= 3739.45+373.94+411.34 = 4524.73

H: IT + ITF (3,09) H= 4524.73*3.09% = 139.81


3.09
I: PRECIO DE APLICACION I= 4524.73+139.81 = 4664.54

DOLARES #DIV/0!
CÓMPUTOS MÉTRICOS

PROYECTO CANAL BOVEDA DE TOMOYO Item: 1


ITEM HORMIGON H21 Unidad: M3

TOTAL
No. Item LARGO ANCHO ALTO CANT.
[M]
1 29.14
BASE 10.82
HORMIGON H21 29.14 M3
47.00 1.15 0.10 5.41 5.41
47.00 1.15 0.10 5.41 5.41
0.00
LADO IZQUIEEDO 3.20
47.00 0.40 0.02 0.38 0.19
47.00 0.40 0.15 2.82 2.82
47.00 0.40 0.02 0.38 0.19
LADO DERECHO 3.20
47.00 0.40 0.02 0.38 0.19
47.00 0.40 0.15 2.82 2.82
47.00 0.40 0.02 0.38 0.19
ARCO 10.55
47.00 1.00 1.00 22.70 22.70
47.00 1.00 1.00 12.15 12.15

Totales : 29.14
CÓMPUTOS MÉTRICOS

PROYECTO CANAL BOVEDA DE TOMOYO Item: 2


ITEM EXCAVACION Unidad: M3

TOTAL
No. Item LARGO ANCHO ALTO CANT.
[M]
2 EXCAVACION 186.12
EXCAVACION 186.12 M3
47.00 2.20 1.80 186.12 186.12

Totales : 186.12
CÓMPUTOS MÉTRICOS

PROYECTO CANAL BOVEDA DE TOMOYO Item: 3


ITEM CONFORMACION DE CAPA SUBBASE Unidad: M3

TOTAL
No. Item LARGO ANCHO ALTO CANT.
[M]
3 SUBBASE 103.40 CONFORMACION DE CAPA
103.40 M3
47.00 2.20 1.00 103.40 103.40 SUBBASE

Totales : 103.40
CÓMPUTOS MÉTRICOS

PROYECTO CANAL BOVEDA DE TOMOYO Item: 4


ITEM CONFORMACION DE CAPA BASE Unidad: M3

TOTAL
No. Item LARGO ANCHO ALTO CANT.
[M]
4 BASE 86.95
CONFORMACION DE CAPA BASE 86.95 M3
47.00 1.85 0,80 86.95 86.95

Totales : 86.95
CÓMPUTOS MÉTRICOS

PROYECTO CANAL BOVEDA DE TOMOYO Item: 6


ITEM EMPEDRADO Unidad: M3

TOTAL
No. Item LARGO ANCHO ALTO CANT.
[M]
6 EMPEDRADO 7.29
EMPEDRADO 7.29 M3
47.00 1.55 0.10 7.29 7.29

Totales : 7.29
CÓMPUTOS MÉTRICOS

PROYECTO CANAL BOVEDA DE TOMOYO Item: 6


ITEM EMBOQUILLADO Unidad: M3

TOTAL
No. Item LARGO ANCHO ALTO CANT.
[M]
6 EMBOQUILLADO 23.50
EMBOQUILLADO 23.50 M3
47.00 5.00 0.10 23.50 23.50

Totales : 23.50
CÓMPUTOS MÉTRICOS

PROYECTO CANAL BOVEDA DE TOMOYO Item: 6


ITEM RELLENO DE TIERRA SELECCIONADO Unidad: M3

TOTAL
No. Item LARGO ANCHO ALTO CANT.
[M]
6 EMBOQUILLADO 47.00 RELLENO DE TIERRA
47.00 M3
47.00 1.00 1.00 47.00 47.00 SELECCIONADO

Totales : 47.00
CÓMPUTOS MÉTRICOS

PROYECTO CANAL BOVEDA DE TOMOYO Item: 7


ITEM Unidad: M3

No. Item LARGO ANCHO ALTO CANT. TOTAL [M]


6 EMBOQUILLADO 47.00
0 47.00 M3
47.00 1.00 1.00 47.00 47.00

Totales : 47.00