Está en la página 1de 1

CORTES DE OBRA CONSTRUCTORA INFANTE VIVES S.A.

Contrato: 08-22 BARCELONA


Contratista: PERFEKOM SAS

CONCEPTO: CONTRATO CIVIL MANO DE OBRA MAMPOSTERÍA PISOS


8 AL 16

VALOR ANTICIPO $0

CONTRATO INICIAL CORTE 15 CORTE 16


VALOR FINAL CONTRATADO ACUMULADO SALDO
CODIGO ACTIVIDAD UN 8 DE MAYO DE 2015 11 de noviembre de 2022 25 de noviembre de 2022 %
CANT VR UNIT. VR. TOTAL CANT VR UNIT. VR. TOTAL CANT. VR. TOTAL CANT. VR. TOTAL CANT. VR. TOTAL CANT, VR. TOTAL

1.0 MAMPOSTERÍA

1.1 DINTELES EN CONCRETO 15X20 ML 92.13 $ 24.287.11 $ 2.237.449.76 92.13 $ 24.287.11 $ 2.237.449.76 24.23 $ 588.476.61 $ - 104.33 $ 2.533.873.90 113.25% -12.21 -296.424.14

1.2 MURO EN BLOQUE DE CEMENTO 0.15 M2 2300.00 $ 18.595.34 $ 42.769.281.81 2300.00 $ 18.595.34 $ 42.769.281.81 232.87 $ 4.330.296.81 177.44 $ 3.299.557.11 2.397.46 $ 44.581.583.64 104.24% -97.46 -1.812.301.83

1.4 DESCOLGADOS EN CONCRETO ML 319.00 $ 33.499.46 $ 10.686.327.19 319.00 $ 33.499.46 $ 10.686.327.19 28.12 $ 942.004.77 28.12 $ 942.004.77 346.40 $ 11.604.128.59 108.59% -27.40 -917.801.40

1.5 VIGA SOBRE MURO Y DINTEL ASCENSOR UND 6.00 $ 799.119.11 $ 4.794.714.65 6.00 $ 799.119.11 $ 4.794.714.65 $ - $ - 6.00 $ 4.794.714.65 100.00% 0.00 0.00

1.7 TRAZADO SOBRE PLACA M2 3500.00 $ 2.272 $ 7.950.887.05 3500.00 $ 2.271.68 $ 7.950.887.05 $ - $ - 2.599.25 $ 5.904.669.48 74.26% 900.75 2.046.217.57

1.8 POYO BALCONES 0.20 ML 88.22 $ 23.816 $ 2.101.049.38 88.22 $ 23.816.02 $ 2.101.049.38 $ - $ - 174.78 $ 4.162.564.17 198.12% -86.56 -2.061.514.79

1.9 MURO EN BLOQUE 0.20 M2 557.50 $ 19.525.11 $ 10.885.247.10 557.50 $ 19.525.11 $ 10.885.247.10 40.00 $ 781.004.28 69.59 $ 1.358.752.19 465.50 $ 9.088.937.27 83.50% 92.00 1.796.309.84

1.10 MURO EN BLOQUE 0.12 M2 3446.00 $ 16.931.88 $ 58.347.266.90 3446.00 $ 16.931.88 $ 58.347.266.90 204.15 $ 3.456.643.80 170.12 $ 2.880.451.84 3.372.94 $ 57.110.223.57 97.88% 73.06 1.237.043.33

1.12 BASE GABINETES C. INCENDIO UND 6.00 $ 52.343 $ 314.057.42 6.00 $ 52.342.90 $ 314.057.42 $ - $ - - $ - 0.00% 6.00 314.057.42

1.13 BASE MEDIDORES AGUA UND 6.00 $ 83.749 $ 502.491.87 6.00 $ 83.748.65 $ 502.491.87 $ - $ - - $ - 0.00% 6.00 502.491.87

1.14 MO. OBRA CIVIL SHUT UND 6.00 $ 104.686 $ 628.114.84 6.00 $ 104.685.81 $ 628.114.84 $ - $ - - $ - 0.00% 6.00 628.114.84

1.15 MO. CHAFLAN ASCENSORES UND 6.00 $ 188.434 $ 1.130.606.72 6.00 $ 188.434.45 $ 1.130.606.72 $ - $ - - $ - 0.00% 6.00 1.130.606.72

1.16 COLUMNETA 0.15 X 0.20 X 3.10 UND 935.00 $ 41.874 $ 39.152.491.86 935.00 $ 41.874.32 $ 39.152.491.86 97.00 $ 4.061.809.32 100.00 $ 4.187.432.28 890.00 $ 37.268.147.33 95.19% 45.00 1.884.344.53
$ - $ - -
COSTO DIRECTO $ 181.499.986.56 $ 181.499.987 $ 14.160.236 $ 12.668.198 $ 177.048.843 $ 4.451.144
Administracion 3.0% $ 5.445.000 $ 5.445.000 $ 424.807 $ 380.046 $ 5.311.465 $ 133.534
Imprevistos 3.0% $ 5.445.000 $ 5.445.000 $ 424.807 $ 380.046 $ 5.311.465 $ 133.534
Utilidad 4.0% $ 7.259.999 $ 7.259.999 $ 566.409 $ 506.728 $ 7.081.954 $ 178.046
SUBTOTAL ANTES DE IVA $ 199.649.985 $ 199.649.985.21 $ 15.576.259.13 $ 13.935.018.02 $ 194.753.726.85 $ 4.896.258
I.V.A. 19% / UTILIDAD 19.0% $ 1.379.400 $ 1.379.400 $ 107.618 $ 96.278 $ 1.345.571 $ 33.829
VALOR TOTAL $ 201.029.385 $ 201.029.385.11 $ 15.683.877 $ 14.031.296 $ 196.099.298 $ 4.930.087
DESCUENTOS
VARIOS $ 520.000
PRESTAMOS $0 $0
MATERIALES $0
SUBTOTAL DESCUENTOS $0 $0
AMORTIZACION ANTICIPO 0.0% $0 $0 $0 $0
RETEFUENTE 0.0% $0 $0 $0
RETEICA 0.0% $0 $0 $0
RETEIVA 15.0% $ 16.143 $ 14.442 $ 201.836
RETENCION EN GARANTIA 10.0% $ 1.557.626 $ 1.393.502 $ 19.475.373
TOTAL DESCUENTOS $ 1.573.769 $ 1.407.944 20.197.208.37
VALOR TOTAL (DESPUES DE DESCUENTOS) $ 14.110.108 $ 12.623.353 $ 175.902.090

FIRMA RESIDENTE DE OBRA


ING. ENRIQUE OROZCO

FIRMA CONTRATISTA
PERFEKOM S.A.S.

Vo.Bo. DIRECTOR DE OBRA


ING. HIDUARTE SALCEDO MOLINA

Vo.Bo. GERENCIA
ING. FRANCISCO INFANTE VIVES