Está en la página 1de 8

A A-01

A-01

E2
2.65
1.55 1.10

0.15 1.25 0.15 0.50 0.60


0.15

B B
A-01 A-01

1.10
0.85

1.75
E1 A-01
2.70

2.40

0.65
BAÑO
2.93 m²
NPT+ 0.15
A=0.75
H=2.10
P-01

NPT+ 0.15
0.15

V-01 1.80
0.70 0.30

0.35 0.70 0.50

1.55

E3

A
A-01 A-01

PISO 1
1 1 : 25

2. CUADRO DE VANOS _PUERTAS 3. CUADRO DE VANO PARA VENTANAS


Tipo Ancho Alto Cantidad Marca Alfaizar Largo Alto Cantidad
P-01 0.75 2.10 1 V-01 1.80 0.70 0.30 1

PLANTA ARQUITECTONICA
BAÑO CON
DUCHA Project number BAÑO

VISCAS
Date Issue Date
A-01
Drawn by RHP
Checked by RHP Scale 1 : 25

4/07/2022 19:39:56
A
A-01
A-01

2.78
E2
0.23 1.55 1.00
0.20

B B
A-01 A-01

E1 A-01
15.84%
2.70
3.10

Canaleta pluvial
0.20

cobertura con plancha


aluzing TR5 x 0.30mm

2.65 0.15

2.80

A
A-01

TECHO
2 1 : 25

PLANTA ARQUITECTONICA
SS.HH CON (TECHO)
DUCHA Project number BAÑO
Date Issue Date
A-02
VISCAS Drawn by
Checked by
RHP
RHP Scale 1 : 25

4/07/2022 19:39:56
cobertura con plancha aluzing TR5 x 0.30mm B
sobre soleras metalicos con parantes de drywall A-01
cielo raso con fibrocemento de 4mm
3.10

0.20 0.15 2.40 0.15 0.20

0.63 0.61 0.61


0.74

0.20 0.20

0.30

0.90

1.85 1.85
2.10

1.80

1.20

SC 0.15 SC
N.T 0.40 N.T 0.40
0.15 0.15

Cimiento Cimiento
0.60 Corrido Corrido 0.60

0.40 2.15 0.40

CORTE A-A
A 1 : 25

PLANTA ARQUITECTONICA
SS.HH CON (CORTE A-A)
DUCHA Project number BAÑO
Date Issue Date
A-03
VISCAS Drawn by
Checked by
RHP
RHP Scale 1 : 25

4/07/2022 19:39:56
A
A-01 .13

0.24
2.70
2 Ø3/8"
1.57

0.90
15.84% .20
0.39

5 hiladas
0.51

3 hiladas
0.28
0.25
Viga Dintel 0.20
0.82

1.00 DINTEL-(15X20)
1 : 20
2Ø3/8"
ESTRIBOS Ø1/4
:2@0.05,2@0.10,2@0.15,
2.56 Rto. @0.20m.

2.20
0.35 2.10

0.30
1.20

Sobrecimiento
0.85

0.55
NPT+ 0.15
0.15
N.T 0.40
0.15 0.15

Cimiento Cimiento
0.60 Corrido Corrido 0.60

0.40 1.00 0.40

CORTE B-B
B 1 : 25

PLANTA ARQUITECTONICA
SS.HH CON (CORTE B-B)
DUCHA Project number BAÑO
Date Issue Date
A-04
VISCAS Drawn by
Checked by
RHP
RHP Scale 1 : 25

4/07/2022 19:39:56
FRONTAL
E1 1 : 25

Corte CIMIENTO
PLANTA ARQUITECTONICA
SS.HH CON (ELEVACION FRONTAL)
DUCHA Project number BAÑO
Date Issue Date
A-05
VISCAS Drawn by
Checked by
RHP
RHP Scale 1 : 25

4/07/2022 19:39:56
Contrazocalo
pulido h=0.25m

FRONTAL
E1 1 : 25

Corte CIMIENTO
PLANTA ARQUITECTONICA
SS.HH CON (ELEVACION FRONTAL)
DUCHA Project number BAÑO
Date Issue Date
A-05
VISCAS Drawn by
Checked by
RHP
RHP Scale 1 : 25

4/07/2022 19:39:56
cobertura con plancha aluzing TR5 x 0.30mm
sobre soleras metalicos con parantes de drywall
cielo raso con fibrocemento de 4mm

15.84%

Dintel revestido

Ladrillo
CARAVISTA

Contrazocalo PISO 1
pulido h=0.25m
NPT+0.15

LATERAL DERECHA
E2 1 : 25

PLANTA ARQUITECTONICA
SS.HH CON (ELEV.N LATERAL DERECHA)
DUCHA Project number BAÑO
Date Issue Date
A-06
VISCAS Drawn by
Checked by
RHP
RHP Scale 1 : 25

4/07/2022 19:39:56
15.84%

Dintel revestido

Contrazocalo PISO 1
pulido h=0.25m
NPT+0.15

LATERAL IZQUIERD
E3 1 : 25

PLANTA ARQUITECTONICA
SS.HH CON (ELEV. LATERAL IZQUIERDO)
DUCHA Project number BAÑO
Date Issue Date
A-07
VISCAS Drawn by
Checked by
RHP
RHP Scale 1 : 25

4/07/2022 19:39:56

También podría gustarte