Partida: Excavacion

Eje Tramo Tipo Largo Alto Ancho 30% Sub-total


A 1-6 6.00 0.80 0.80 1.1520 3.8400
C 1-2 2.60 0.80 0.80 0.4992 1.6640
C 4-6 2.50 0.80 0.80 0.4800 1.6000
D 4-6 2.50 0.80 0.80 0.4800 1.6000
F 1-2 0.75 0.80 0.80 0.1440 0.4800
G 1-3 3.05 0.80 0.80 0.5856 1.9520
1 A-C 2.98 0.80 0.80 0.5722 1.9072
1 C-F 2.88 0.80 0.80 0.5530 1.8432
1 F-H 3.45 0.80 0.80 0.6624 2.2080
2 C-E 1.40 0.80 0.80 0.2688 0.8960
3 F 0.15 0.80 0.80 0.0288 0.0960
3 G-H 0.45 0.80 0.80 0.0864 0.2880
4 C-D 0.17 0.80 0.80 0.0326 0.1088
6 A-C 2.98 0.80 0.80 0.5722 1.9072
6 C-D 0.97 0.80 0.80 0.1862 0.6208
6 D-G 4.91 0.80 0.80 0.9427 3.1424
TOTAL

Partida: Plantilla
Eje Tramo Tipo Largo Alto Ancho 30% Sub-total
A 1-6 6.00 0.05 0.80 0.0720 0.2400
C 1-2 2.60 0.05 0.80 0.0312 0.1040
C 4-6 2.50 0.05 0.80 0.0300 0.1000
D 4-6 2.50 0.05 0.80 0.0300 0.1000
F 1-2 0.75 0.05 0.80 0.0090 0.0300
G 1-3 3.05 0.05 0.80 0.0366 0.1220
1 A-C 2.98 0.05 0.80 0.0358 0.1192
1 C-F 2.88 0.05 0.80 0.0346 0.1152
1 F-H 3.45 0.05 0.80 0.0414 0.1380
2 C-E 1.40 0.05 0.80 0.0168 0.0560
3 F 0.15 0.05 0.80 0.0018 0.0060
3 G-H 0.45 0.05 0.80 0.0054 0.0180
4 C-D 0.17 0.05 0.80 0.0020 0.0068
6 A-C 2.98 0.05 0.80 0.0358 0.1192
6 C-D 0.97 0.05 0.80 0.0116 0.0388
6 D-G 4.91 0.05 0.80 0.0589 0.1964
Total

Partida: Cimentación
Eje Tramo Tipo Largo Alto-Ancho 30% Sub-total
A 1-6 2.10 6.00 0.35 0.3150 0.6300
C 1-2 0.91 2.60 0.35 0.1365 0.2730
C 4-6 0.88 2.50 0.35 0.1313 0.2625
D 4-6 0.88 2.50 0.35 0.1313 0.2625
F 1-2 0.26 0.75 0.35 0.0394 0.0788
G 1-3 1.07 3.05 0.35 0.1601 0.3203
1 A-C 1.04 2.98 0.35 0.1565 0.3129
1 C-F 1.01 2.88 0.35 0.1512 0.3024
1 F-H 1.21 3.45 0.35 0.1811 0.3623
2 C-E 0.49 1.40 0.35 0.0735 0.1470
3 F 0.05 0.15 0.35 0.0079 0.0158
3 G-H 0.16 0.45 0.35 0.0236 0.0473
4 C-D 0.06 0.17 0.35 0.0089 0.0179
6 A-C 1.04 2.98 0.35 0.1565 0.3129
6 C-D 0.34 0.97 0.35 0.0509 0.1019
6 D-G 1.72 4.91 0.35 0.2578 0.5156
Total

Partida: cadena de desplante varilla


Eje Tramo Tipo Largo Alto Ancho Cantidad Total
A 1-6 6.00 4 24.00
C 1-2 2.60 4 10.40
C 4-6 2.50 4 10.00
D 4-6 2.50 4 10.00
F 1-2 0.75 4 3.00
G 1-3 3.05 4 12.20
1 A-C 2.98 4 11.92
1 C-F 2.88 4 11.52
1 F-H 3.45 4 13.80
2 C-E 1.40 5 5.60
3 F 0.15 6 0.60
3 G-H 0.45 7 1.80
4 C-D 0.17 8 0.68
6 A-C 2.98 9 11.92
6 C-D 0.97 10 3.88
6 D-G 4.91 11 19.64
SUB-TOTAL 69.44

Partida: Cadena de desplante estribos


Eje Tramo Tipo Largo Alto Ancho Cantidad Total
A 1-6 6.00 0.80 5 24.00
C 1-2 2.60 0.80 5 10.40
C 4-6 2.50 0.80 5 10.00
D 4-6 2.50 0.80 5 10.00
F 1-2 0.75 0.80 5 3.00
G 1-3 3.05 0.80 5 12.20
1 A-C 2.98 0.80 5 11.92
1 C-F 2.88 0.80 5 11.52
1 F-H 3.45 0.80 5 13.80
2 C-E 1.40 0.80 5 5.60
3 F 0.15 0.80 5 0.60
3 G-H 0.45 0.80 5 1.80
4 C-D 0.17 0.80 5 0.68
6 A-C 2.98 0.80 5 11.92
6 C-D 0.97 0.80 5 3.88
6 D-G 4.91 0.80 5 19.64
TOTAL 150.96

Partida: Cadena de desplante alambre


Eje Tramo Tipo Largo Alto Ancho Cantidad Total
A 1-6 6.00 0.34 20 40.80
C 1-2 2.60 0.34 20 17.68
C 4-6 2.50 0.34 20 17.00
D 4-6 2.50 0.34 20 17.00
F 1-2 0.75 0.34 20 5.10
G 1-3 3.05 0.34 20 20.74
1 A-C 2.98 0.34 20 20.26
1 C-F 2.88 0.34 20 19.58
1 F-H 3.45 0.34 20 23.46
2 C-E 1.40 0.34 20 9.52
3 F 0.15 0.34 20 1.02
3 G-H 0.45 0.34 20 3.06
4 C-D 0.17 0.34 20 1.16
6 A-C 2.98 0.34 20 20.26
6 C-D 0.97 0.34 20 6.60
6 D-G 4.91 0.34 20 33.39
TOTAL 256.63

Partida: Concreto en cadena


Eje Tramo Tipo Largo Alto Ancho Cantidad Total
A 1-6 6.00 0.20 0.15 0.180
C 1-2 2.60 0.20 0.15 0.078
C 4-6 2.50 0.20 0.15 0.075
D 4-6 2.50 0.20 0.15 0.075
F 1-2 0.75 0.20 0.15 0.023
G 1-3 3.05 0.20 0.15 0.092
1 A-C 2.98 0.20 0.15 0.089
1 C-F 2.88 0.20 0.15 0.086
1 F-H 3.45 0.20 0.15 0.104
2 C-E 1.40 0.20 0.15 0.042
3 F 0.15 0.20 0.15 0.005
3 G-H 0.45 0.20 0.15 0.014
4 C-D 0.17 0.20 0.15 0.005
6 A-C 2.98 0.20 0.15 0.089
6 C-D 0.97 0.20 0.15 0.029
6 D-G 4.91 0.20 0.15 0.147
TOTAL 1.132

Partida: Impermeabilizante en cadena


Eje Tramo Tipo Largo Alto Ancho Cantidad Total
A 1-6 6.00 0.55 3.30
C 1-2 2.60 0.55 1.43
C 4-6 2.50 0.55 1.38
D 4-6 2.50 0.55 1.38
F 1-2 0.75 0.55 0.41
G 1-3 3.05 0.55 1.68
1 A-C 2.98 0.55 1.64
1 C-F 2.88 0.55 1.58
1 F-H 3.45 0.55 1.90
2 C-E 1.40 1.55 0.77
3 F 0.15 2.55 0.08
3 G-H 0.45 3.55 0.25
4 C-D 0.17 4.55 0.09
6 A-C 2.98 5.55 1.64
6 C-D 0.97 6.55 0.53
6 D-G 4.91 7.55 2.70
TOTAL 20.76

Partida: Relleno de tepetate


cimentación 17.1717
Plantilla C. 1.9625
Cadena 1.132
Excavación 31.3997
TOTAL 10.9455 m3

Partida: Castillos varillas


Eje Tramo Cantidad Largo Alto Ancho Total
A 1-6 3 3.20 4 38.4
B 1 2 3.20 4 25.6
C 1-6 4 3.20 4 51.2
D 4-6 2 3.20 4 25.6
E 4-6 2 3.20 4 25.6
F 1-6 3 3.20 4 38.4
G 3-6 2 3.20 4 25.6
H 1-3 2 3.20 4 25.6
1 F-H 1 3.20 4 12.8
6 F-G 1 3.20 4 12.8
6 I 1 3.20 4 12.8
TOTAL 294.40

Partida: Castillos estribos


Eje Tramo Cantidad Largo Alto Total
A 1-6 3 0.80 3.20 5 38.4
B 1 2 0.80 3.20 5 25.6
C 1-6 4 0.80 3.20 5 51.2
D 4-6 2 0.80 3.20 5 25.6
E 1-2 2 0.80 3.20 5 25.6
F 1-6 3 0.80 3.20 5 38.4
G 3-6 2 0.80 3.20 5 25.6
H 1-3 2 0.80 3.20 5 25.6
1 F-H 1 0.80 3.20 5 12.8
6 F-G 1 0.80 3.20 5 12.8
6 I 1 0.80 3.20 5 12.8
TOTAL 294.40

Partida: Castillos alambre


Eje Tramo Cantidad Largo Alto Total
A 1-6 3 0.34 3.20 20 21.76
B 1 2 0.34 3.20 20 21.76
C 1-6 4 0.34 3.20 20 21.76
D 4-6 2 0.34 3.20 20 21.76
E 1-2 2 0.34 3.20 20 21.76
F 1-6 3 0.34 3.20 20 21.76
G 3-6 2 0.34 3.20 20 21.76
H 1-3 2 0.34 3.20 20 21.76
1 F-H 1 0.34 3.20 20 21.76
6 F-G 1 0.34 3.20 20 21.76
6 I 1 0.34 3.20 20 21.76
TOTAL 239.36

Partida: Castillos Cimbra


Eje Tramo Cantidad Alto Tablas Polín Tipo
A 1-6 2 2.50 4 2 A
1 2.50 2 - C
B 1 1 2.50 1 2 B
1 2.50 2 1 A
C 1-6 2 2.50 4 8 B
D 4-6 1 2.50 2 1 A
1 2.50 1 2 B
E 1-2 2 2.50 4 - C
F 1-6 3 2.50 3 6 B
G 3-6 2 2.50 2 4 B
H 1-3 2 2.50 4 2 A
1 F-H 1 2.50 2 - C
6 F-G 1 2.50 2 - C
6 I 1 2.50 2 1 A
TOTALES 35 29

Partida: Concreto en castillos


Eje Tramo Cantidad Alto TOTAL
A 1-6 2 2.50 0.20 0.15 0.150
1 2.50 0.20 0.15 0.075
B 1 1 2.50 0.20 0.15 0.075
1 2.50 0.20 0.15 0.075
C 1-6 2 2.50 0.20 0.15 0.150
D 4-6 1 2.50 0.20 0.15 0.075
1 2.50 0.20 0.15 0.075
E 1-2 2 2.50 0.20 0.15 0.150
F 1-6 3 2.50 0.20 0.15 0.225
G 3-6 2 2.50 0.20 0.15 0.150
H 1-3 2 2.50 0.20 0.15 0.150
1 F-H 1 2.50 0.20 0.15 0.075
6 F-G 1 2.50 0.20 0.15 0.075
6 I 1 2.50 0.20 0.15 0.075
TOTAL 1.575

Partida: Muros
Eje Tramo Alto Largo Subtotal Restar Total
A 1-6 2.50 5.70 14.25 14.25
C 1-6 2.50 5.70 14.25 V1/V2/P1 11.48
D 4-6 2.50 3.18 7.95 7.95
F 1-3 2.50 2.83 7.08 7.08
G 3-6 2.50 2.73 6.83 V3/P2 2.14
H 1-3 2.50 2.83 7.08 V3 4.61
1 F-H 2.50 3.45 8.63 8.63
2 C-E 2.50 2.96 7.40 7.40
3 G-H 2.50 0.45 1.13 1.13
4 C-D 2.50 1.00 2.50 P3 0.33
6 D-G 2.50 4.91 12.28 12.28
TOTAL 77.28
Partida: Cerramientos de acero (varillas)
Eje Tramo Largo Cantidad Total
C 1-6 1.00 4 4.00
0.30 4 1.20
0.75 4 3.00
G 3-6 1.30 4 5.20
1.00 4 4.00
H 1-3 1.30 4 5.20
4 C-D 0.80 4 3.20
Total 25.80

Partida: Cerramientos de alambron(estribos)


Eje Tramo Largo Cantidad Largo Total
C 1-6 1.00 5 0.80 4.00
0.30 1 0.80 0.24
0.75 3 0.80 1.80
G 3-6 1.30 6 0.80 6.24
1.00 5 0.80 4.00
H 1-3 1.30 6 0.80 6.24
4 C-D 0.80 4 0.80 2.56
TOTAL 25.08

Partida: Cerramiento para alambre


Eje Tramo Largo Largo2 Cantidad Total
C 1-6 0.34 2.05 8 5.58
G 3-6 0.34 2.30 11 8.60
H 1-3 0.34 1.30 6 2.65
4 C-D 0.34 0.80 4 1.09
Total 17.92
Partida: Cerramiento para concreto
Eje Tramo Tipo Largo
A 1-6 1.40 0.20 0.15
B 1 1.40 0.20 0.15
C 1-6 1.40 0.20 0.15
D 4-6 1.40 0.20 0.15
E 1-2 1.40 0.20 0.15
F 1-3 1.40 0.20 0.15
G 3-6 1.40 0.20 0.15
H 1-3 1.40 0.20 0.15
1 F-H 1.40 0.20 0.15
2 C-E 1.40 0.20 0.15
3 G-H 1.40 0.20 0.15
6 D-G 1.40 0.20 0.15
6 I 1.40 0.20 0.15

Partida: Cimbra en cerramientos


Eje Tramo Largo Tablas
C 1-6 1.00 3
0.30 3
0.75 3
G 3-6 1.30 3
1.00 3
H 1-3 1.30 3
4 C-D 0.80 3
Total 21

Partida: Cimbra perimetral en losa


Eje Tramo Largo Tablas (2.50)
B 1-4 3.50 2
C 4-6 2.50 2
H 1-3 2.95 2
I 3-6 3.05 2
1 B-I 9.90 2
6 C-I 8.40 2
Total 30.30 12

Partida: Cimbra apuntalamiento en losa


Eje Tramo Puntales Vigas Largo Ancho
1-2 C-F 12 4 2.94 2.38
1-3 F-H 15 4 3.40 2.83
2-6 C-D 6 1 1.20 3.18
2-6 D-F 9 2 1.84 2.88
3-6 F-G 16 4 3.08 2.73
Total 58 15

Partida: Vigueta
Eje Tramo Cantidad Largo Total
1-2 C-F 4 2.89 11.56
1-3 F-H 4 3.45 13.80
2-6 C-D 1 1.04 1.04
2-6 D-F 2 1.91 3.82
3-6 F-G 4 3.08 12.32
TOTAL 42.54

Partida: Bovedilla
Eje Tramo Espacios Largo Ancho de bo.Bovedilla to.
1-2 C-F 5 2.89 0.20 72
1-3 F-H 5 3.45 0.20 86
2-6 C-D 2 1.04 0.20 10
2-6 D-F 3 1.91 0.20 29
3-6 F-G 5 3.08 0.20 77
TOTAL 275

Partida: Acero en losa (malla electrosoldada


Eje Tramo Largo Ancho Total
1-2 C-F 2.94 2.38 7.00
1-3 F-H 3.40 2.83 9.62
2-6 C-D 1.20 3.18 3.82
2-6 D-F 1.84 2.88 5.30
3-6 F-G 3.08 2.73 8.41
TOTAL 34.14

Partida: Concreto en losa


Eje Tramo Viguetas Largo Ancho Alto
1-2 C-F 4 3.22 2.53 0.5
1.40 0.01
0.60 0.01
1-3 F-H 4 3.75 0.60 0.5
2.98 0.01
0.45 0.01
2-6 C-D 1 1.28 3.33 0.5
0.18 0.01
2-6 D-F 2 1.91 3.18 0.5
3-6 F-G 4 3.23 2.80 0.5

Partida: Charola Sanitaria Varilla


Eje Tramo Largo Alto Varillas Total
4-6 C-C 2.50 0.07 16 40.00
1.20 0.07 8 9.60
Total 49.60

Partida: Charola Sanitaria alambre


Eje Tramo T. varillas Total
4-6 C-C 16 8 0.34 20 8.70
16 8 0.34 20 8.70
Total 17.40

Partida: Charola Sanitaria cimbra


Eje Tramo Largo Alto Varillas Total

Total

Partida: Concreto Charola Sanitaria


Eje Tramo Largo Alto Varillas Total

Total

Partida: Firmes
Eje Tramo Largo Ancho Alto Total
1-2 C-F 2.88 2.37 0.07 0.47
1-3 F-H 3.45 2.82 0.07 0.68
2-6 C-D 0.97 3.17 0.07 0.21
2-6 D-F 1.91 3.17 0.07 0.42
3-6 F-G 3.07 2.80 0.07 0.60
Total 2.38
Total
4.9920
2.1632
2.0800
2.0800
0.6240
2.5376
2.4794
2.3962
2.8704
1.1648
0.1248
0.3744
0.1414
2.4794
0.8070
4.0851
31.3997

Total
0.3120
0.1352
0.1300
0.1300
0.0390
0.1586
0.1550
0.1498
0.1794
0.0728
0.0078
0.0234
0.0088
0.1550
0.0504
0.2553
1.9625

Total
2.7300
1.1830
1.1375
1.1375
0.3413
1.3878
1.3559
1.3104
1.5698
0.6370
0.0683
0.2048
0.0774
1.3559
0.4414
2.2341
17.1717

TOTAL 5.787
Partida: Cadena de desplante cimbraperimetro
Eje Tramo Largo Alto Tablas
A 1-6 6.00 0.25 2
C 1-6 6.00 0.25 2
D 2-6 3.40 0.25 2
F 1-1 0.60 0.25 2
G 5-6 3.05 0.25 2
H 1-3 2.95 0.25 2
1 A-C 3.62 0.25 2
1 C-F 3.11 0.25 2
1 F-H 4.00 0.25 2
2 G-E 1.56 0.25 2
4 C-D 1.20 0.25 2
6 A-C 3.62 0.25 2
6 C-D 1.20 0.25 2
6 D-G 5.06 0.25 2
TOTAL
TOTAL TABLAS
Total
12.00
12.00
6.80
1.20
6.10
5.90
7.24
6.22
8.00
3.12
2.40
7.24
2.40
10.12
90.74
36.30
Partida: Castillos varillas
Eje Tramo Cantidad Alto Varillas Total
B 1-4 2 3.20 4 25.6
C 4-6 2 3.20 4 25.6
D 4-6 2 3.20 4 25.6
E 1-2 2 3.20 4 25.6
F 1-6 3 3.20 4 38.4
G 1-6 2 3.20 4 25.6
1 F-G 1 3.20 4 12.8
6 G-I 1 3.20 4 12.8
Total 192.00

Partida: Castillos estribos


Eje Tramo Cantidad Largo Alto Total
B 1-4 2 0.80 3.20 5 16
C 4-6 2 0.80 3.20 5 16
D 4-6 2 0.80 3.20 5 16
E 1-2 2 0.80 3.20 5 16
F 1-6 3 0.80 3.20 5 16
G 1-6 2 0.80 3.20 5 16
1 F-G 1 0.80 3.20 5 16
6 G-I 1 0.80 3.20 5 16
TOTAL 128

Partida: Castillos amarre


Eje Tramo Cantidad Largo Alto Total
B 1-4 2 0.34 3.20 20 21.76
C 4-6 2 0.34 3.20 20 21.76
D 4-6 2 0.34 3.20 20 21.76
E 1-2 2 0.34 3.20 20 21.76
F 1-6 3 0.34 3.20 20 21.76
G 1-6 2 0.34 3.20 20 21.76
1 F-G 1 0.34 3.20 20 21.76
6 G-I 1 0.34 3.20 20 21.76
TOTAL 174.08

Partida: Castillos Cimbra


Eje Tramo Cantidad Alto Tablas Polín Tipo
B 1-4 1 2.50 1 2 B
1 2.50 2 1 A
C 4-6 2 2.50 2 4 B
D 4-6 1 2.50 1 2 B
1 2.50 3 - D
E 1-2 1 2.50 1 2 B
1 2.50 2 1 A
F 1-6 1 2.50 2 - C
1 2.50 3 - D
1 2.50 2 1 A
G 1-6 2 2.50 4 - C
1 F-G 1 2.50 2 - C
6 G-I 1 2.50 3 - D
TOTALES 28 13

Partida: Colado (Concreto en castillos)


Eje Tramo Cantidad Alto TOTAL
B 1-4 1 2.50 0.20 0.15 0.075
1 2.50 0.20 0.15 0.075
C 4-6 2 2.50 0.20 0.15 0.150
D 4-6 1 2.50 0.20 0.15 0.075
1 2.50 0.20 0.15 0.075
E 1-2 1 2.50 0.20 0.15 0.075
1 2.50 0.20 0.15 0.075
F 1-6 1 2.50 0.20 0.15 0.075
1 2.50 0.20 0.15 0.075
1 2.50 0.20 0.15 0.075
G 1-6 2 2.50 0.20 0.15 0.150
1 F-G 1 2.50 0.20 0.15 0.075
6 G-I 1 2.50 0.20 0.15 0.075
TOTAL 1.125

Partida: Muros
Eje Tramo Alto Largo Sub-total Restar Total
B 1-4 2.50 3.28 8.20 V3/V2 5.61
C 4-6 2.50 2.28 5.70 5.70
D 4-6 2.50 1.51 3.78 P5 2.11
E 1-2 2.50 2.83 7.08 7.08
F 3-6 2.50 2.73 6.83 P4 4.79
H 1-3 2.50 2.83 7.08 V3 4.61
I 3-6 2.50 2.73 6.83 V1 5.83
3 C-I 2.50 6.58 16.45 P3/P3 12.05
4 B-D 2.50 0.88 2.20 2.20
5 F-G 2.50 0.59 1.48 1.48
Total 51.46

Partida: cerramientos varilla


Eje Tramo Largo Cantidad Total
B 1-4 1.30 4 5.20
0.30 4 1.20
D 4-6 0.76 4 3.04
F 3-6 0.93 4 3.72
H 1-3 1.30 4 5.20
I 3-6 1.00 4 4.00
3 C-I 0.80 4 3.20
0.80 4 3.20
Total 28.76

Partida: cerramientos estribos


Eje Tramo Largo Cantidad Largo Total
B 1-4 1.30 6 0.80 6.24
0.30 2 0.80 0.48
D 4-6 0.76 3 0.80 1.82
F 3-6 0.93 4 0.80 2.98
H 1-3 1.30 6 0.80 6.24
I 3-6 1.00 5 0.80 4.00
3 C-I 0.80 4 0.80 2.56
0.80 4 0.80 2.56
Total 26.88

Partida: cerramientos alambre


Eje Tramo Largo Largo Cantidad Total
B 1-4 0.34 1.60 8 4.35
D 4-6 0.34 0.76 3 0.78
F 3-6 0.34 0.93 4 1.26
H 1-3 0.34 1.30 6 2.65
I 3-6 0.34 1.00 5 1.70
3 C-I 0.34 1.60 8 4.35
Total 15.10

Partida: cimbra en cerramientos


Eje Tramo Largo Tablas
B 1-4 1.30 3
0.30 3
D 4-6 0.76 3
F 3-6 0.93 3
H 1-3 1.30 3
I 3-6 1.00 3
3 C-I 0.80 3
0.80 3
Total 24

Partida: Cimbra perimetral en losa


Eje Tramo Largo Tablas (2.50)
1 A-H 8.74 4
6 A-I 7.80 3
B 1-4 3.50 2
C 4-6 2.50 1
H 1-3 2.95 2
H 3-6 3.05 4
Total 28.54 16

Partida: Cimbra apuntalamiento en losa


Eje Tramo Puntales Vigas Largo Ancho
1-4 B-E 16 4 2.89 3.28
1-3 E-H 24 7 5.00 2.83
4-6 C-D 9 2 1.47 2.28
3-6 D-F 12 2 1.75 2.73
3-6 F-I 20 5 3.86 2.73
Total 81 20

Partida: Acero en losa (malla electrosoldada)


Eje Tramo Largo Ancho Total
1-4 B-E 2.89 3.28 9.48
1-3 E-H 5.00 2.83 14.15
4-6 C-D 1.47 2.28 3.35
3-6 D-F 1.75 2.73 4.78
3-6 F-I 3.86 2.73 10.54
Total 42.30

Partida: Concreto en losa


Eje Tramo Viguetas Largo Ancho Alto
1-4 B-E 4 2.89 3.28 0.5
1.94 0.01
0.45 0.01
2.98 0.01
1-3 E-H 7 5.00 2.82 0.5
0.59 0.01
3.61 0.01
2.82 0.01
4-6 C-D 2 1.03 2.28 0.5
1.47 0.01
1.66 0.01
3-6 D-F 2 0.74 1.66 0.5
1.75 0.01
1.80 0.01
3-6 F-I 5 4.01 1.65 0.5
0.59 0.01
3.86 0.01
2.73 0.01
Partida: Vigueta
Eje Tramo Cantidad Largo Total
1-4 B-E 4 2.89 11.56
1-3 E-H 7 5.00 35.00
4-6 C-D 2 1.47 2.94
3-6 D-F 2 1.75 3.50
3-6 F-I 5 3.86 19.30
TOTAL 72.30

Partida: Bovedilla
Eje Tramo Espacios Largo Ancho de bo.Bovedilla to.
1-4 B-E 5 2.89 0.20 72
1-3 E-H 8 5.00 0.20 200
4-6 C-D 3 1.47 0.20 22
3-6 D-F 3 1.75 0.20 26
3-6 F-I 6 3.86 0.20 116
TOTAL 436
Partida: Pretil en losa de azotea
Eje Tramo Alto Largo Total
B 1-4 1.20 3.28 3.94
C 4-6 1.20 2.28 2.74
H 1-3 1.20 2.83 3.40
I 3-6 1.20 2.73 3.28
1 B-H 1.20 8.04 9.65
3 H-I 1.20 0.25 0.30
4 B-C 1.20 0.91 1.09
6 C-I 1.20 0.91 1.09
TOTAL 25.48

Partida: Pretil castillos varillas


Eje Tramo Cantidad Alto Varillas Total
B 1-6 2 1.20 4 9.60
I 1-6 2 1.20 4 9.60
1 B-I 3 1.20 4 14.40
3 H-I 2 1.20 4 9.60
4 B-C 2 1.20 4 9.60
6 C-I 2 1.20 4 9.60
TOTAL 62.40

Partida: Pretil castillos estribos


Eje Tramo Cantidad Largo Alto Estribos Total
B 1-6 2 0.80 1.20 5 9.60
I 1-6 2 0.80 1.20 5 9.60
1 B-I 3 0.80 1.20 5 14.40
3 H-I 2 0.80 1.20 5 9.60
4 B-C 2 0.80 1.20 5 9.60
6 C-I 2 0.80 1.20 5 9.60
TOTAL 62.40

Partida: Pretil castillos alambre


Eje Tramo Cantidad Largo Alto Alambre Total
B 1-6 2 0.34 1.20 20 16.32
I 1-6 2 0.34 1.20 20 16.32
1 B-I 3 0.34 1.20 20 24.48
3 H-I 2 0.34 1.20 20 16.32
4 B-C 2 0.34 1.20 20 16.32
6 C-I 2 0.34 1.20 20 16.32
TOTAL 106.08
Partida: Colado (Concreto en castillos)
Eje Tramo Cantidad Alto TOTAL
B 1-6 2 1.20 0.20 0.15 0.072
I 1-6 2 1.20 0.20 0.15 0.072
1 B-I 2 1.20 0.20 0.15 0.072
1 1.20 0.20 0.15 0.036
3 H-I 2 1.20 0.20 0.15 0.072
4 B-C 2 1.20 0.20 0.15 0.072
6 C-I 2 1.20 0.20 0.15 0.072
1 1.20 0.20 0.15 0.036
TOTAL 0.504

Partida: Base de tinaco (muros)


Eje Tramo Alto Largo Total
6 C-I 1.00 1.70 1.70
4 C-I 1.00 1.70 1.70
Total 3.40

Partida: Castillos varillas


Eje Tramo Cantidad Largo Ancho C/D 0.15 Total
6 C-I 2 1.7 1.7 12 24.4
4 C-I 2 1.7 1.7 12 24.4 40.80
24 VARILLAS 1.70

Partida: Castillos amarre


Eje Tramo Cantidad Largo Alto AMARRES Total
6 C-I 2 1.7 1.7 12(12) 144*.34*.20=179
4 C-I 2 1.7 1.7 12(12)

Partida: Castillos Cimbra


Eje Tramo Cantidad Alto Tablas Polín Tipo
6 C-I 2 1.00 - 2 C
4 C-I 2 1.00 - 2 C
Totales 0 4
Partida: Excavacion Cisterna
Eje Tramo Tipo Largo Alto Ancho 30% Sub-total
I 3-6 2.00 2.00 2.00 2.40 8.00
J 3-6 2.00 2.00 2.00 2.40 8.00
3 I-J 2.00 2.00 2.00 2.40 8.00
6 I-J 2.00 2.00 2.00 2.40 8.00
Total

Partida: Cadena de desplante varilla


Eje Tramo Largo Cantidad Total
I 3-6 2.00 4 8.00
J 3-7 2.00 4 8.00
3 I-J 2.00 4 8.00
6 I-J 2.00 4 8.00
Total 32.00

Partida: Cadena de desplante estribos


Eje Tramo Largo Ancho Cantidad Total
I 3-6 2.00 0.80 5 8.00
J 3-7 2.00 0.80 5 8.00
3 I-J 2.00 0.80 5 8.00
6 I-J 2.00 0.80 5 8.00
Total 32.00

Partida: Cadena de desplante alambre


Eje Tramo Largo Ancho Cantidad Total
I 3-6 2.00 0.34 20 13.60
J 3-7 2.00 0.34 20 13.60
3 I-J 2.00 0.34 20 13.60
6 I-J 2.00 0.34 20 13.60
Total 54.40

Partida: Cadena de desplante cimbraperimetro


Eje Tramo Largo Alto Tablas
I 3-6 2.00 0.20 2
J 3-7 2.00 0.20 2
3 I-J 2.00 0.20 2
6 I-J 2.00 0.20 2
Total 8

Partida: Losa base para cisterna varilla


Eje Tramo Largo Varilla Total
1 3-6 2.00 12 24.00
3 I-J 2.00 12 24.00
Total 48.00

Partida: Losa base para cisterna alambre


Eje Tramo Largo Alambre Cantidad Total
I 3-6 2.00 0.34 12.00 8.16
3 I-J 2.00 0.34 12.00 8.16
Total 16.32

Partida: Concreto para losa base para cisterna


Eje Tramo Largo Alto Ancho Total
I-J 3-6 2.00 0.05 2.00 0.20
Total 0.20
Total
10.40
10.40
10.40
10.40
41.60
Partida: Rebocado aplanado exterior
Eje Tramo Alto Largo Subtotal Restar Total
C 1-6 2.70 5.70 15.39 V1/V2/P1 12.07
G 3-6 2.70 2.73 7.37 V3/P2 2.72
H 1-3 2.70 2.83 7.64 V3 5.17
B 1-4 2.70 3.28 8.86 V3/V2 6.51
C 4-6 2.70 2.28 6.16 6.16
H 1-3 2.70 2.83 7.64 V3 5.17
I 3-6 2.70 2.73 7.37 V1 6.37
Total 44.17

Partida: Pasta en exterior


Eje Tramo Alto Largo Subtotal Restar Total
C 1-6 2.70 5.70 15.39 V1/V2/P1 12.07
G 3-6 2.70 2.73 7.37 V3/P2 2.72
H 1-3 2.70 2.83 7.64 V3 5.17
B 1-4 2.70 3.28 8.86 V3/V2 6.51
C 4-6 2.70 2.28 6.16 6.16
H 1-3 2.70 2.83 7.64 V3 5.17
I 3-6 2.70 2.73 7.37 V1 6.37
Total 44.17

Partida: Aplanado interior pb


Eje Tramo Alto Largo Subtotal Restar Total
A 1-6 2.50 5.70 14.25 14.25
C 1-6 2.50 5.70 14.25 V1/V2/P1 11.48
D 4-6 2.50 3.18 7.95 7.95
F 1-3 2.50 2.83 7.08 7.08
G 3-6 2.50 2.73 6.83 V3/P2 2.14
H 1-3 2.50 2.83 7.08 V3 4.61
1 F-H 2.50 3.45 8.63 8.63
2 C-E 2.50 2.96 7.40 7.40
3 G-H 2.50 0.45 1.13 1.13
4 C-D 2.50 1.00 2.50 P3 0.33
6 D-G 2.50 4.91 12.28 12.28
TOTAL 77.28

Partida: Pasta interior pb


Eje Tramo Alto Largo Subtotal Restar Total
A 1-6 2.50 5.70 14.25 14.25
C 1-6 2.50 5.70 14.25 V1/V2/P1 11.48
D 4-6 2.50 3.18 7.95 7.95
F 1-3 2.50 2.83 7.08 7.08
G 3-6 2.50 2.73 6.83 V3/P2 2.14
H 1-3 2.50 2.83 7.08 V3 4.61
1 F-H 2.50 3.45 8.63 8.63
2 C-E 2.50 2.96 7.40 7.40
3 G-H 2.50 0.45 1.13 1.13
4 C-D 2.50 1.00 2.50 P3 0.33
6 D-G 2.50 4.91 12.28 12.28
TOTAL 77.28

Partida: Aplanado interior Pa


Eje Tramo Alto Largo Sub-total Restar Total
B 1-4 2.50 3.28 8.20 V3/V2 5.61
C 4-6 2.50 2.28 5.70 5.70
D 4-6 2.50 1.51 3.78 P5 2.11
E 1-2 2.50 2.83 7.08 7.08
F 3-6 2.50 2.73 6.83 P4 4.79
H 1-3 2.50 2.83 7.08 V3 4.61
I 3-6 2.50 2.73 6.83 V1 5.83
3 C-I 2.50 6.58 16.45 P3/P3 12.05
4 B-D 2.50 0.88 2.20 2.20
5 F-G 2.50 0.59 1.48 1.48
Total 51.46

Partida: Pasta interior Pa


Eje Tramo Alto Largo Sub-total Restar Total
B 1-4 2.50 3.28 8.20 V3/V2 5.61
C 4-6 2.50 2.28 5.70 5.70
D 4-6 2.50 1.51 3.78 P5 2.11
E 1-2 2.50 2.83 7.08 7.08
F 3-6 2.50 2.73 6.83 P4 4.79
H 1-3 2.50 2.83 7.08 V3 4.61
I 3-6 2.50 2.73 6.83 V1 5.83
3 C-I 2.50 6.58 16.45 P3/P3 12.05
4 B-D 2.50 0.88 2.20 2.20
5 F-G 2.50 0.59 1.48 1.48
Total 51.46

Partida: Pisos pb
Eje Tramo Largo Ancho Total
1-2 C-F 2.60 3.10 8.06
1-2 F-H 3.60 2.95 10.62
2-4 C-D 0.90 1.20 1.08
2-6 B-F 3.40 1.90 6.46
3-6 F-G 3.15 3.05 9.61
Total 35.83
Partida: Pisos pa
Eje Tramo Largo Ancho Total
1-4 B-E 3.58 3.50 9.51
1-3 E-H 5.15 2.95 15.19
3-6 D-F 1.90 3.05 5.80
3-6 F-I 3.01 3.05 10.56
Total 41.06

Partida: Azulejo cocina


Eje Tramo Largo Alto Total
1 C-F 3.11 2.50 9.51
C 1-2 2.60 2.50 6.50
Total 16.01

Partida: Azulejo en baño p


Eje Tramo Alto Ancho Total
6 C-D 2.50 1.20 3.00
6 C-D 2.50 0.20 0.50
C 4-6 2.50 2.50 6.25
D 4-6 2.50 2.50 6.25
4-6 C-D 2.50 1.20 3.00
Total 19.00

Partida: Azulejo en baño pa


Eje Tramo Alto Ancho Total
6 C-D 2.50 1.62 4.05
4 C-D 2.50 1.62 4.05
C 4-6 2.50 2.50 6.25
D 4-6 2.50 2.50 6.25
C-D 4-6 2.5 1.62 4.05
Total 24.65

Partida: Impermeabilizante carpeta azotea


Eje Tramo Largo Ancho Total
1-6 B-I 8.74 6.00 52.44
Total 52.44

Partida: Pasto
Eje Tramo Largo Ancho Total
1-6 A-C 3.20 6.00 12.01
Total 12.01
Partida: Poliducto 3/4
Eje Tramo Largo Alto 30% Total
1-2 B-C 1.48 1.60 0.92 4.04
1-2 C-D 1.98 - 0.59 2.57
1.25 1.60 1.73 3.06
1.25 1.60 1.73 3.06
1.25 1.60 1.73 3.06
1-2 E-G 2.70 - 0.81 3.51
1.30 1.60 0.87 3.77
3-5 F-G 3.00 - 0.90 3.90
1.60 1.60 0.96 4.16
1.60 1.60 0.96 4.16
1.60 1.60 0.96 4.16
H-E 4-6 2.80 - 0.84 3.64
E-C 4-6 1.20 - 0.36 1.56
1.60 1.60 0.96 4.16
1.60 1.60 0.96 4.16
1-2 B-D 1.30 - 0.39 1.69
1.60 1.60 0.36 3.56
1.30 1.60 1.78 4.68
2-6 B-D 2.00 - 0.06 2.06
0.60 1.60 0.36 2.56
C-F 4-6 1.20 - 0.36 1.56
0.60 1.60 0.66 2.86
F-I 3-6 1.87 - 0.56 2.43
1.87 1.60 0.56 3.43
0.45 1.60 1.04 3.09
1.50 - 0.45 1.95
1.29 - 1.38 2.67
F-I 1-3 0.80 - 0.24 1.04
2.30 - 0.69 2.99
0.45 1.60 0.61 2.66
2.00 1.60 1.00 4.60
1.30 - 0.39 1.69
Total 98.50

Partida: Chalupas
Eje Tramo Cantidad
1-2 B-C 1
1-2 C-F 1
1-3 F-H 1
2-6 D-F 1
3-6 F-G 1
1-4 B-E 1
1-3 E-H 1
4-6 C-D 1
3-6 D-F 1
3-6 F-I 1
1-2 B-C 1
1-2 C-F 3
1-3 F-H 1
2-6 D-F 1
1-4 B-E 2
1-3 E-H 3
4-6 C-D 1
3-6 F-I 2
3-6 D-F 1
3-6 F-G 1
Total 26

Partida: Cajas registro 3/4


Eje Tramo Cantidad
1-2 B-C 1
1-2 C-F 1
1-3 F-H 1
2-6 D-F 1
3-6 F-G 1
1-4 B-E 1
1-3 E-H 2
4-6 C-D 1
3-6 D-F 1
3-6 F-I 2
5-6 G-H 1
1-3 D-F 1
Total 14

Partida: Cable thw #12


Poliducto 3/4 = Cable Thw #12
98.50 = 98.50 +6.40
Total = 104.9
Partida: Cable thw #10
Cable Thw #12 = Cable Thw #10
98.5
32 * 0.20 = 6.40
98.50 + 6.40= 104.9 * 2
Total= 209.8

Partida: Apagadores
Eje Tramo Cantidad
1-2 B-C 1
1-2 C-F 1
1-3 F-H 1
2-6 D-F 1
3-6 F-G 1
1-4 B-E 1
1-3 E-H 1
4-6 C-D 1
3-6 D-F 1
3-6 F-I 1
Total 10

Partida: Contactos
Eje Tramo Cantidad
1-2 B-C 1
1-2 C-F 3
1-3 F-H 1
2-6 D-F 1
1-4 B-E 2
1-3 E-H 3
4-6 C-D 1
3-6 F-I 2
3-6 D-F 1
3-6 F-G 1
Total 16

Partida: Bases para foco


Eje Tramo Cantidad
1-2 B-C 1
1-2 C-F 1
1-3 F-H 1
2-6 D-F 1
3-6 F-G 1
1-4 B-E 1
1-3 E-H 2
4-6 C-D 1
3-6 D-F 1
3-6 F-I 2
5-6 G-H 1
1-3 D-F 1
Total 14

Partida: Focos o lamparas


Eje Tramo Cantidad
1-2 B-C 1
1-2 C-F 1
1-3 F-H 1
2-6 D-F 1
3-6 F-G 1
1-4 B-E 1
1-3 E-H 2
4-6 C-D 1
3-6 D-F 1
3-6 F-I 2
5-6 G-H 1
1-3 D-F 1
Total 14

Partida: Centro de carga QO8


Eje Tramo Cantidad
1-2 B-C 1
Total 1

Partida: Breakers
Eje Tramo Cantidad
1-2 B-C 2
Total 2

Partida: Base para medidor


Eje Tramo Cantidad
5-6 G-H 1
Total 1
Partida: Mufa y tubo
Eje Tramo Cantidad
5-6 G-H 1
Total 1
Partida: Regaderas
Eje Tramo Piezas Total
4-6 C-D 1 1
4-6 C-D 1 1
Total 2

Partida: Llaves de empotrar regadera


Eje Tramo Piezas Total
4-6 C-D 2 2
4-6 C-D 2 2
Total 4

Partida: Llaves angulares


Eje Tramo Piezas Total
4-6 C-D 1 1
1-2 C-F 1 1
4-6 C-D 1 1
Total 3

Partida: Coflex lavamanos


Eje Tramo Piezas Total
4-6 C-D 1 1
1-2 C-F 1 1
4-6 C-D 1 1
Total 3

Partida: Coflex WC
Eje Tramo Piezas Total
4-6 C-D 1 1
4-6 C-D 1 1
Total 2

Partida: Tubo CU 3/4


Concepto Cantidad
Planta baja 14.22
Planta Alta 5.65
Azotea 21.82
Total 41.69
Partida: Codos CU 90
Concepto Piezas
Baño pb 2
Baño pa 4
Jardin principal 1
Cocina 2
Azotea 17
Total 26

Partida: Coples Cree


Eje Tramo Piezas
1-2 C-C 1
Total 1

Partida: Tee CU 3/4


Pieza Cantidad
Baño pb 4
Baño pa 4
Azotea 1
Total 9

Partida: Tapon CU 3/4


Eje Tramo Piezas
1-2 C-C 1
Total 1

Partida: Llaves de nariz


Eje Tramo Piezas
1-2 C-C 1
Total 1
Partida: Cuadro medidor
Eje Tramo Piezas
1-2 H-I 1
Total 1

Partida: Pinchacha
Eje Tramo Piezas
3-6 I-J 1
Total 1

Partida: Flotador cisterna


Eje Tramo Piezas
3-6 I-J 1
Total 1

Partida: Bomba 3/4 hp BONASA


Eje Tramo Piezas
3-6 I-J 1
Total 1

Partida: Tubo CU 1"


Planta baja 14.22
Planta Alta 5.65
Azotea 21.82
Total 41.69

Partida: Tinaco 1100 LTS


Eje Tramo Piezas
4-6 C-I 1
Total 1

Partida: Calentador solar


Eje Tramo Piezas
1-4 B-H 1
Total 1

Partida: Valvula Check


Eje Tramo Piezas
1-2 C-C 1
Total 1
Partida: Llave de globo
Eje Tramo Piezas
1-2 C-C 1
Total 1
Partida: Tubo 4"
Cantidad
Pb 24.47
Pa 6.6
Total 31.07

Partida: Tubo 2"


Cantidad
Pb 7.02
Pa 1.2
Total 8.22

Partida: Reducción de 4" a 2"


Cantidad
Pb 3
Pa 3
Total 6

Partida: Codos de 4" por 90


Cantidad
Pb 1
Pa 1
Total 2

Partida: Yee de 4"


Cantidad
Pb 3
Pa 3
Total 6

Partida: Yee de 2"


Cantidad
Pb 1
Pa -
Total 1
Partida: Codo de 2" por 90
Cantidad
Pb 2
Pa 2
Total 4

Partida: Codo de 2" por 45


Cantidad
Pb
Pa
Total

Partida: Coples de 4"


Cantidad
Pb 4
Pa 2
Total 6

Partida: Coples de 2"


Cantidad
Pb 3
Pa 2
Total 5

Partida: Bote cespol


Eje Tramo Piezas Total
4-6 C-D 1 1
4-6 C-D 1 1
Total 2
Partida: Bote cespol para lavamanos
Eje Tramo Piezas Total
4-6 C-D 1 1
4-6 C-D 1 1
Total 2

Partida: Bote cespol para tarja


Eje Tramo Piezas Total
1-2 C-F 1 1
Total 1

Partida: Coladeras para exterior


Eje Tramo Piezas Total
I-J 1-3 1 1
Total 1

Partida: Tarja
Eje Tramo Piezas Total
1-2 C-F 1 1
Total 1

Partida: Juego de baño


Eje Tramo Piezas Total
4-6 C-D 1 1
4-6 C-D 1 1
Total 2