PRESUPUESTO

PROYECTO: DEMOLICION Y CONSTRUCCION DE CAMPANARIO DE 4 PISOS

CLIENTE: COMUNIDAD CAMPESINA SAN MIGUEL DE VISO

UBICACION: SAN MIGUEL DE VISO - SAN MATEO DE HUANCHOR - HUAROCHIRI - LIMA

FECHA BASE: 20-08-2022 MONEDA: SOLES

ITEM PARTIDA UNIDAD METRADO PU PARCIAL

1 ESTRUCTURAS 157,264.96

1.1 OBRAS PRELIMINARES 12,484.23

1.1.1 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS VIAJES 2.00 2,500.00 5,000.00

1.1.2 CARTEL DE IDENTIFICACION DE OBRA 3.60M X 2.40M GLB 1.00 1,811.18 1,811.18

1.1.3 LIMPIEZA MANUAL DE TERRENO M2 25.00 6.20 155.00

1.1.4 CERCO PERIMETRICO DE MADERA, H=2.20 M. ML 12.28 328.91 4,039.01

1.1.5 TRAZO Y REPLANTEO M2 64.00 23.11 1,479.04

1.2 DEMOLICION DEL CAMPANARIO 29,873.37

DEMOLICION DE LOSA DE CONCRETO ARMADO, CON MARTILLO E: 15


1.2.1 M2 22.09 117.00 2,584.53
CM

1.2.2 DEMOLICION MANUAL DE COLUMNAS UND 12.00 393.18 4,718.16

1.2.3 DEMOLICION DE VIGA, CON MARTILLO NEUMATICO M3 6.78 626.83 4,249.91

1.2.4 DEMOLICION DE LOSA DE ALIGERADA E:20 CM M2 30.00 132.93 3,987.90

1.2.5 DEMOLICION DE MUROS DE LADRILLO KK-CABEZA, MANUAL M2 95.64 87.37 8,356.07

1.2.6 DEMOLICION MANUAL DE CIMIENTOS M3 6.75 463.98 3,131.87

1.2.7 DEMOLICION DE ESCALERA E: 15 CM DE 70 CM DE ANCHO ML 16.50 172.42 2,844.93

1.3 MOVIMIENTO DE TIERRA 7,798.49

1.3.1 EXCAVACION MANUAL H=1.00 EN TERRENO NORMAL M3 18.50 39.80 736.30

1.3.2 NIVELACION, REFINE Y COMPACTACION, PISÓN MANUAL M2 18.50 5.53 102.31

1.3.3 ACARREO DE MATERIAL POR ELIMINACION HORIZONTAL GLB 1.00 2,738.00 2,738.00

1.3.4 ELIMINACION DE MATERIAL A DME PARA D> 1 KM M3 68.85 61.32 4,221.88

1.4 OBRAS DE CONCRETO SIMPLE 16,447.28

1.4.1 CONCRETO PARA SOLADOS, E=0.10 M. C:H, 1:12 - M M2 18.55 66.19 1,227.82

1.4.2 CONCRETO PARA CIMIENTOS CICLÓPEO 1:10+30% PG - M M3 13.30 446.44 5,937.65

1.4.3 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO M2 28.60 86.07 2,461.60

1.4.4 CONCRETO F'C=210 KG/CM2 -PARA SOBRECIMIENTO M3 4.35 602.77 2,622.05

1.4.5 CONCRETO PARA FALSO PISO E=4" MEZCLA 1:8 C:H -M M2 18.00 70.38 1,266.84

1.4.6 CONCRETO PARA FALSO PISO E=2" MEZCLA 1:8 C:H -M - M2 58.00 50.54 2,931.32

1.5 OBRAS DE CONCRETO ARMADO 0.00

1.5.1 ZAPATAS 0.00

1.5.1.1 CONCRETO PARA ZAPATAS F´C=210 KG/CM2 M3 0.00 510.75 0.00

1.5.1.2 ENCOFRADO/ DESENCOFRADO NORMAL, ZAPATA M2 0.00 68.31 0.00

1.5.1.3 ACERO DE REFUERZO F´Y = 4200 KG/CM2 KG 0.00 8.13 0.00

1.6 VIGAS DE CIMENTACION 5,508.52

1.6.1 CONCRETO PARA VIGAS DE CIMENTACIÓN F¨C=210 KG/CM2 M3 3.33 523.91 1,744.62

https://presupuestos.pe 1/4
PRESUPUESTO
PROYECTO: DEMOLICION Y CONSTRUCCION DE CAMPANARIO DE 4 PISOS

CLIENTE: COMUNIDAD CAMPESINA SAN MIGUEL DE VISO

UBICACION: SAN MIGUEL DE VISO - SAN MATEO DE HUANCHOR - HUAROCHIRI - LIMA

FECHA BASE: 20-08-2022 MONEDA: SOLES

ITEM PARTIDA UNIDAD METRADO PU PARCIAL

1.6.2 ENCOFRADO/ DESENCOFRADO NORMAL, VIGAS DE CIMENTACIÓN M2 20.00 80.83 1,616.60

1.6.3 ACERO DE REFUERZO F´Y = 4200 KG/CM2 KG 264.12 8.13 2,147.30

1.7 COLUMNAS 14,627.10

1.7.1 CONCRETO PARA COLUMNAS F´C=210 KG/CM2 M3 4.55 638.61 2,905.68

1.7.2 ENCOFRADO Y DESENCOFRADO NORMAL PARA COLUMNAS M2 64.25 83.58 5,370.02

1.7.3 ACERO DE REFUERZO F´Y = 4200 KG/CM2 KG 781.23 8.13 6,351.40

1.8 VIGAS 24,771.07

1.8.1 CONCRETO PARA VIGAS F'C=210 KG/CM2 M3 11.28 577.67 6,516.12

1.8.2 ENCOFRADO Y DESENCOFRADO NORMAL PARA VIGAS M2 96.00 72.80 6,988.80

1.8.3 ACERO DE REFUERZO F´Y = 4200 KG/CM2 KG 1,385.75 8.13 11,266.15

1.9 LOSAS ALIGERADAS 15,487.16

1.9.1 CONCRETO PARA LOSAS ALIGERADAS F´C=210 KG/CM2 M3 7.84 614.23 4,815.56

1.9.2 ENCOFRADO Y DESENCOFRADO NORMAL PARA LOSAS ALIGERADAS M2 31.27 70.59 2,207.35

1.9.3 ACERO DE REFUERZO F´Y = 4200 KG/CM2 KG 914.78 8.13 7,437.16

1.9.4 LADRILLO HUECO DE ARCILLA H = 15 CM PARA LOSA ALIGERADA PZA 271.00 3.79 1,027.09

1.10 LOSAS MACIZA 7,965.47

1.10.1 CONCRETO LOSA MACIZA F'C=210 KG/CM2 - M M3 5.25 603.46 3,168.17

1.10.2 ENCOFRADO Y DESENCOFRADO NORMAL PARA LOSAS MACIZA M2 30.25 81.79 2,474.15

1.10.3 ACERO DE REFUERZO F´Y = 4200 KG/CM2 KG 285.75 8.13 2,323.15

1.11 ESCALERAS 22,302.27

1.11.1 CONCRETO PARA ESCALERAS F´C=210 KG/CM2 M3 9.56 638.61 6,105.11

1.11.2 ENCOFRADO Y DESENCOFRADO NORMAL PARA ESCALERAS M2 36.85 92.06 3,392.41

1.11.3 ACERO DE REFUERZO F´Y = 4200 KG/CM2 KG 1,575.00 8.13 12,804.75

2 ARQUITECTURA 91,629.04

2.1 ALBAÑILERIA 28,876.73

2.1.1 MURO DE LADRILLO KK DE ARCILLA, CABEZA. MEZCLA 1:4 M2 156.76 176.40 27,652.46

MURO DE LADRILLO KK DE ARCILLA, CV-SOG. MEZCLA 1:4 ZONA


2.1.2 M2 12.25 99.94 1,224.27
BALCON

2.2 REVOQUES, ENLUCIDOS Y MOLDURAS 18,341.35

2.2.1 TARRAJEO FROTACHADO, MUROS INT. E=1.5CM, MEZCLA 1:4 M2 195.25 45.83 8,948.31

2.2.2 TARRAJEO FROTACHADO, MUROS EXT. E=1.5CM, MEZCLA 1:4 M2 156.19 52.15 8,145.31

2.2.3 VESTIDURA DE DERRAMES, A=0.10, E=1.5CM, MEZCLA 1:5 ML 44.85 27.82 1,247.73

2.3 CIELORASOS 3,738.21

2.3.1 TARRAJEO DE CIELORASO E=1.5CM, MEZCLA 1:4 M2 61.85 60.44 3,738.21

2.4 PISOS Y PAVIMENTOS 6,148.58

https://presupuestos.pe 2/4
PRESUPUESTO
PROYECTO: DEMOLICION Y CONSTRUCCION DE CAMPANARIO DE 4 PISOS

CLIENTE: COMUNIDAD CAMPESINA SAN MIGUEL DE VISO

UBICACION: SAN MIGUEL DE VISO - SAN MATEO DE HUANCHOR - HUAROCHIRI - LIMA

FECHA BASE: 20-08-2022 MONEDA: SOLES

ITEM PARTIDA UNIDAD METRADO PU PARCIAL

2.4.1 CONTRAPISO DE 2" M2 58.00 56.84 3,296.72

2.4.2 PISO DE CEMENTO SEMIPULIDO Y GRUÑADO M2 58.00 49.17 2,851.86

2.5 REVESTIMIENTOS 5,885.88

2.5.1 REVESTIMIENTO DE GRADAS DE ESCALERA ML 98.00 60.06 5,885.88

2.6 CUBIERTAS 3,002.40

2.6.1 CUBIERTA DE TEJA ARCILLA 36X16 CM M2 30.26 99.22 3,002.40

2.7 CERRAJERIA 14,007.55

2.7.1 BISAGRA TIPO CAPUCHINA ALUMINIZADA 3 1/2" PZA 6.00 43.28 259.68

2.7.2 MANTENIMIENTO DE CERRADURA PUERTA PRINCIPAL PESADA PZA 1.00 437.10 437.10

2.7.3 PASAMANOS DE TUBO GALVANIZADO DE 2" ML 16.00 365.29 5,844.64

2.7.4 VENTANA METALICA MODELO COLONIAL UND 9.00 829.57 7,466.13

2.8 PINTURA 11,628.34

2.8.1 PINTURA DE CIELORASOS AL TEMPLE M2 61.85 25.06 1,549.96

2.8.2 PINTURA INT. INC. ANDAMIOS M2 245.98 25.06 6,164.26

2.8.3 PINTURA EXT. INC. ANDAMIOS M2 156.19 25.06 3,914.12

3 INSTALACIONES ELECTRICAS 9,863.67

3.1 SALIDA PARA ALUMBRADO, TOMACORRIENTE 9,863.67

3.1.1 SALIDA PARA CENTRO DE LUZ PTO 14.00 214.17 2,998.38

3.1.2 SALIDA PARA TOMACORRIENTES PTO 2.00 178.16 356.32

3.1.3 SUMINISTRO E INSTALACION DE LUMINARIAS UND 14.00 400.84 5,611.76

3.1.4 TABLERO ELECTRICO DE POLICARBONATO DE 12 POLOS UND 1.00 897.21 897.21

4 SISTEMA DE DESAGÜE 10,468.89

4.1 SALIDA DE DESAGUE PVC-SAL 2" PTO 18.00 155.35 2,796.30

4.2 SALIDA DE DESAGUE PVC-SAL 4" PTO 18.00 162.77 2,929.86

4.3 SALIDA DE VENTILACION PVC-SAL 2" PTO 36.00 111.02 3,996.72

4.4 REGISTRO DE BRONCE 4" UND 9.00 52.88 475.92

4.5 CAJA REGISTRO DE DESAGÜE 12" X 24" UND 3.00 90.03 270.09

5 SISTEMA DE AGUA FRIA 13,731.37

5.1 SALIDA DE AGUA FRIA TUBERIA PVC CLASE 10, D = 1/2" PTO 45.00 109.04 4,906.80

RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC CLASE 10 DE


5.2 M 76.00 26.01 1,976.76
1/2"

RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC CLASE 10 DE


5.3 M 98.00 26.41 2,588.18
3/4"

5.4 VALVULA COMPUERTA Y ACCESORIOS DE 1/2" UND 5.00 76.32 381.60

5.5 VALVULA COMPUERTA Y ACCESORIOS DE 3/4" UND 2.00 80.92 161.84

https://presupuestos.pe 3/4
PRESUPUESTO
PROYECTO: DEMOLICION Y CONSTRUCCION DE CAMPANARIO DE 4 PISOS

CLIENTE: COMUNIDAD CAMPESINA SAN MIGUEL DE VISO

UBICACION: SAN MIGUEL DE VISO - SAN MATEO DE HUANCHOR - HUAROCHIRI - LIMA

FECHA BASE: 20-08-2022 MONEDA: SOLES

ITEM PARTIDA UNIDAD METRADO PU PARCIAL

5.6 TANQUE DE AGUA 1000 LITROS UND 3.00 1,238.73 3,716.19

COSTO DIRECTO 282,957.93

GASTOS GENERALES 12.6967% 35,926.32

UTILIDAD 10% 28,295.79

SUB TOTAL 347,180.04

IGV 18% 62,492.41

TOTAL PRESUPUESTO 409,672.45

SON: CUATROCIENTOS NUEVE MIL SEISCIENTOS SETENTA Y DOS CON 45/100 SOLES