CALCULO DE LA FORMULA POLINOMICA

OBRA:
"DESCOLMATACION E INSTALACION DE TUBERIAS PARA LA REHABILITACION DE LA
INFRAESTRUCTURA Y SISTEMA DE RIEGO DEL CANAL SECTOR MOLINO – CAMBI Y CANAL
SECTOR CHALLAGON – LAGUNA DEL DISTRITO DE LACABAMBA, PROVINCIA DE
PALLASCA, DEPARTAMENTO DE ANCASH, AFECTADOS POR LAS LLUVIAS DEL 03/04/2017"

FECH AGOSTO 2019


A:
COSTOS PRIVADOS = S/. 2,866,323.69

AGRUPAMIENTO PRELIMINAR

DESCRIPCION IND. UNIF. MONTO % % INCD.


MANO DE OBRA
Mano de Obra Inc.
47 S/. 1,452,324.16 50.669%
Leyes Sociales
Total S/. 1,452,324.16 50.669%

MATERIALES
Agregados 5 S/. 275,356.76 9.607%
Cemento 21 S/. 194,942.84 6.801%
Acero de construcción 3 S/. 31,678.21 1.105%
Madera para Carp. Nac. 43 S/. 148,643.92 5.186%
Tubería de PVC 72 S/. 21,931.07 0.765%
Total S/. 672,552.80 23.464%

MAQ. EQUIPO,
HERRAMIENTOS Y
FLETE.
Maq. Nacional 48 S/. 53,609.28 1.870%
Flete Terrestre 32 S/. 77,977.14 2.720%
Herr. Manual 37 S/. 31,678.21 1.105%
Total S/. 163,264.63 5.696%

INDICE GENERAL DE
PRECIOS AL
CONSUMIDOR
Ind. Gral. Precios 39.00 S/. 148,643.92 5.186%
Gastos Generales 39.00 S/. 258,963.19 9.035%
Utilidades 39.00 S/. 170,574.99 5.951%
S/. 578,182.09 20.172%
Total S/. 2,866,323.69 100.00%

FORMACION DE MONOMIOS

MONOMIO AGRUPAMIENTO I.U. % INC. SIMBOLO FACTOR


Agregados 5 40.942%
Cemento 21 28.986%
Agregados, Cemento, Acero 3 4.710% M 0.235
Tubería y Acero
Madera para Carp. Nac. 43 22.101%
Tubería de PVC 72 3.261%
Maq. Nacional 48 32.84%
Equipo y Herramientas Flete Terrestre 32 47.76% EH 0.057
Herr. Manual 37 19.40%
Ind. Gral. Precios
Gastos Generales Gastos Generales 39 100.00% GG 0.202
Utilidades
Mano de Obra Inc.
Jornales 47 100.00% J 0.506
Leyes Sociales

Coeficiente de Incidencia 1.000

K= 0.235 Mr/Mo + 0.057 EHr/EHo + 0.202 GGr/GGo + 0.506 Jr/Jo