MUNICIPALIDAD DISTRITAL DE ILAVE

ILAVE - COLLAO - PUNO

CALENDARIO DE UTILIZACION DE EQUIPOS


OBRA: CREACION DEL SERVICIO DE ESPACIOS PUBLICOS DE RECREACION PASIVA EN EL CENTRO POBLADO DE ANCOAMAYA DEL DISTRITO DE ILAVE PROVINCIA DE EL COLLAO DEPARTAMENTO DE PUNO
Ubicación: LOCALIDAD ANCOAMAYA - Departamento : PUNO - Provincia : COLLAO - Distrito : ILAVE
UNIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE AJOYANI
PLAZO DE EJECUCION : 90 DIAS CALENDARIOS (3.0 MESES)
FECHA :
PRESUPUESTO DE OBRA PRIMER MES SEGUNDO MES TERCER MES

ITEM PARTIDAS COSTO COSTO PARCIAL PARCIAL PARCIAL PARCIAL


UND CANT. CANT. % CANT. % CANT. %
UNITARIO S/. S/.
S/. S/. S/.
EQUIPOS Y/O HERRAMIENTAS 47,118.93 10,780.57 22.88% 23,920.86 50.77% 12,417.49 26.35%
HERRAMIENTAS MANUALES %mo 3,635.76 3,635.76 100.00% 0.00 0.00% 0.00 0.00%
NIVEL TOPOGRAFICO C/TRIPODE Y MIRA hm 89.635 10 896.35 29.00 290.00 32.35% 35.00 350.00 39.05% 25.64 256.35 28.60%
TEODOLITO C/TRIPODE Y MIRA hm 89.635 10 896.35 29.00 290.00 32.35% 35.00 350.00 39.05% 25.64 256.35 28.60%
MEDIDOR DE AGUA und 1.000 203 203.00 0.00 0.00% 0.00 0.00% 1.00 203.00 100.00%
CONO DE ABRAMS jgo 1.724 80 137.92 1.72 137.92 100.00% 0.00 0.00% 0.00 0.00%
COMPACTADOR VIBR. TIPO PLANCHA 4 HP hm 1242.136 12.5 15,526.70 0.00 0.00% 1242.136 15,526.70 100.00% 0.00 0.00%
CARGADOR S/LLANTAS DE 80-95 HP 1.5-1.75 YD3 hm 26.842 180 4,831.58 6.860 1,234.80 25.56% 10.00 1,800.00 37.25% 9.98 1,796.78 37.19%
TRACTOR DE ORUGAS DE 140-160 HP hm 12.347 245 3,024.97 8.000 1,960.00 64.79% 4.35 1,064.97 35.21% 0.00 0.00%
CAMION VOLQUETE 6x4 340 HP 12 M3 hm 69.212 120 8,305.43 12.00 1,440.00 17.34% 12.00 1,440.00 17.34% 45.21 5,425.43 65.32%
VIBRADOR DE 3/4'' - 2'' CONCRETO hm 133.079 15 1,996.19 10.00 150.00 7.51% 46.00 690.00 34.57% 77.08 1,156.19 57.92%
MEZCLADORA DE CONCRETO 11 P3 (23 HP) hm 282.332 12.5 3,529.15 50.00 625.00 17.71% 46.00 575.00 16.29% 186.33 2,329.15 66.00%
CIZALLA hm 5.075 4.5 22.84 5.075 22.84 99.99% 0.00 0.00% 0.00 0.00%
ANDAMIO DE MADERA p2 33.924 4 135.69 0.00 0.00% 33.924 135.69 100.00% 0.00 0.00%
FLETE ton 2.000 1988.5 3,977.00 0.50 994.25 25.00% 1.00 1,988.50 50.00% 0.50 994.25 25.00%

TOTAL DE PRESUPUESTO DE COSTO DIRECTO S/. 47,118.93 S/. 10,780.57 S/. 23,920.86 S/. 12,417.49

% AVANCE FÍSICO EJECUTADO DE COSTO DIRECTO 100% 22.88% 50.77% 26.35%


% AVANCE FÍSICO ACUMULADO DE COSTO DIRECTO 100% 22.88% 73.65% 100.00%