Documentos de Académico
Documentos de Profesional
Documentos de Cultura
MANO DE OBRA
47 00002 CAPATAZ HH 3,168.72 28.15 89,199.47 3,925.68 6,937.49 20,049.79 32,276.37 16,279.53 6,213.22 3,517.39 89,199.47
47 00004 TOPOGRAFO HH 703.26 23.46 16,498.48 - 4,879.10 9,647.92 - 1,971.46 - - 16,498.48
47 00006 OPERARIO HH 21,428.55 23.46 502,713.78 53,898.21 8,448.05 23,924.10 122,443.59 218,206.53 63,161.62 12,631.68 502,713.78
47 00036 OFICIAL HH 13,318.76 18.55 247,063.00 2,736.82 6,280.27 28,801.46 96,756.52 89,493.19 21,549.83 1,444.91 247,063.00
47 00003 PEON HH 46,802.96 16.77 784,885.64 14,397.69 42,859.18 107,676.55 267,587.78 253,314.43 73,525.49 25,524.52 784,885.64
MATERIALES
02 00047 ALAMBRE NEGRO # 8 kg 1,373.62 3.81 5,233.49 152.15 - 680.26 2,611.18 1,771.73 18.17 - 5,233.49
02 00046 ALAMBRE NEGRO # 16 kg 41.29 3.81 157.31 60.72 - - - - 96.59 - 157.31
02 00040 CLAVOS PARA MADERA kg 970.72 3.81 3,698.44 162.82 586.01 746.06 1,306.34 886.37 10.84 - 3,698.44
02 00136 PERNO 3/8" X 5" C/TUERCA Y VOLANDAS und 158.01 4.00 632.04 - 442.43 189.61 - - - - 632.04
02 00169 PERNO DE ANCLAJE 1/2" C/TUERCA Y VOLANDA pza 0.22 6.82 1.50 - - - - - 1.50 - 1.50
03 00123 ACERO CORRUGADO FY=4200 kg/cm2 GRADO 60 kg 1,068.94 2.54 2,715.11 - 189.64 1,117.59 259.08 - 1,148.80 - 2,715.11
04 00098 ARENA FINA m3 234.99 38.14 8,962.52 - - - 1,083.15 6,871.37 1,006.85 1.15 8,962.52
04 00099 ARENA GRUESA m3 3,343.16 29.66 99,158.13 - 73.82 76.01 74,005.71 20,706.89 4,196.23 99.47 99,158.13
04 00177 TIERRA DE CHACRA m3 9.00 25.42 228.78 - - - - - - 228.78 228.78
05 00100 CONFITILLO m3 166.32 27.30 4,540.54 - - - - 3,602.64 937.90 - 4,540.54
05 00101 PIEDRA DE 1/2" m3 865.89 29.66 25,682.30 - 75.46 80.74 2,680.84 18,137.78 4,707.48 - 25,682.30
05 00119 PIEDRA CHANCADA DE 1/2" m3 811.12 50.85 41,245.45 - - - 40,869.13 - 376.32 - 41,245.45
05 00144 PIEDRA MEDIANA m3 4.11 29.66 121.90 - - - 78.77 43.13 - - 121.90
07 00167 CONDUCTOR 2-1X10mm2 NYY m 85.52 8.90 761.13 - - - - - 761.13 - 761.13
07 00166 CONDUCTOR 2X10mm2 NYY m 566.86 8.90 5,045.05 - - - - - 5,045.05 - 5,045.05
07 00165 CONDUCTOR THW 4.0 MM2 m 652.77 1.53 998.74 - - - - - 998.74 - 998.74
07 00162 CONDUCTOR TIPO CCT-B7X14 AWG m 1,575.26 12.71 20,021.55 - - - - - 20,021.55 - 20,021.55
07 00164 CONDUCTOR TIPO NLT 4X16 AWG m 945.22 5.42 5,123.09 - - - - - 5,123.09 - 5,123.09
07 00178 CONECTOR ANDERSON DE COBRE PARA CONDUCTOR 10mm2 pza 6.00 4.24 25.44 - - - - - - 25.44 25.44
Página 1 de 7
MUNICIPALIDAD DISTRITAL GREGORIO ALBARRACIN LANCHIPA GERENCIA DE DESARROLLO URBANO
30 00062 CHALECO DE SEGURIDAD NARANJA CON CINTA REFLECTIVA und 100.00 25.42 2,542.00 2,542.00 - - - - - - 2,542.00
Página 2 de 7
MUNICIPALIDAD DISTRITAL GREGORIO ALBARRACIN LANCHIPA GERENCIA DE DESARROLLO URBANO
30 00061 PANTALON DE SEGURIDAD NARANJA CON CINTA REFLECTIVA und 100.00 29.66 2,966.00 2,966.00 - - - - - - 2,966.00
Página 3 de 7
MUNICIPALIDAD DISTRITAL GREGORIO ALBARRACIN LANCHIPA GERENCIA DE DESARROLLO URBANO
Página 4 de 7
MUNICIPALIDAD DISTRITAL GREGORIO ALBARRACIN LANCHIPA GERENCIA DE DESARROLLO URBANO
50 00125 TAPA DE F°F° DIAM.=0.60mts. C/MARCO PARA BUZON DE 1.20M und 34.00 296.61 10,084.74 - - 8,067.79 2,016.95 - - - 10,084.74
Página 5 de 7
MUNICIPALIDAD DISTRITAL GREGORIO ALBARRACIN LANCHIPA GERENCIA DE DESARROLLO URBANO
COSTO DIRECTO 5,541,409.24 405,445.94 154,138.74 556,947.34 2,669,921.28 1,180,521.82 455,444.31 118,989.81 5,541,409.24
GASTOS GENERALES 10 % 554,140.92 40,544.59 15,413.87 55,694.73 266,992.13 118,052.18 45,544.43 11,898.99 554,140.92
UTILIDAD 8% 443,312.74 32,435.68 12,331.10 44,555.79 213,593.70 94,441.75 36,435.54 9,519.18 443,312.74
SUB TOTAL 6,538,862.90 478,426.21 181,883.71 657,197.86 3,150,507.11 1,393,015.75 537,424.29 140,407.97 6,538,862.90
IGV. 18 % 1,176,995.32 86,116.72 32,739.07 118,295.61 567,091.28 250,742.83 96,736.37 25,273.44 1,176,995.32
PRESUPUESTO TOTAL 7,715,858.22 564,542.93 214,622.78 775,493.48 3,717,598.39 1,643,758.58 634,160.66 165,681.40 7,715,858.22
TOTAL ACUMULADO 564,542.93 779,165.71 1,554,659.19 5,272,257.58 6,916,016.16 7,550,176.82 7,715,858.22
PORCENTAJE DE AVANCE 7.32% 2.78% 10.05% 48.18% 21.30% 8.22% 2.15%
PORCENTAJE ACUMULADO 7.32% 10.10% 20.15% 68.33% 89.63% 97.85% 100.00%
M1 M2 M3 M4 M5 M6 M7
Página 6 de 7
MUNICIPALIDAD DISTRITAL GREGORIO ALBARRACIN LANCHIPA GERENCIA DE DESARROLLO URBANO
771,585.82
Página 7 de 7