WORKPLAN

Critical N PROJECT: San Marcos


Completed ü CLIENT:
In process / Scheduled 6 MADE BY: Carlos Garza
DATE: 3/11/2022

No. ACTIVITY DEADLINE ASSIGNED PROGRESS STATUS ACTION PLAN

1 Take measurements of the building 3/15/2022 Carlos/Zenovia 100% ü Go to San Marcos to take building measurements
2 Draw a sketch with measurements 3/16/2022 Carlos 100% ü
3 Drawing the Sketch in AutoCAD 3/18/2022 Carlos 100% ü
4 Check with the measurements and subtract the area 3/18/2022 Carlos 100% ü
5 Start redesigning the spaces 3/25/2022 Carlos 6 Make a list of questions, to review the scope and clarify doubts
about what is required in the project. Once the doubts have been
solved, proceed to design

6 Make a parametric cost budget 3/22/2022 Carlos 6 Review with Zenovia, the costs they use for parameterized costing.

7
8
9
10
NO. RISKS ASSIGNED ACTION PLAN
1 Not having complete information To make a list of the information to be handled
2
3
4
5
NO. AREAS OF OPPORTUNITY (WHAT CAN BE IMPROVED // STRATEGIES )
1
2
3
4
5
NO. LESSONS LEARNED
1
2
3
4
5
NO. MEETINGS LOCATION TOPICS OF IMPORTANCE
1
2
3
4
5

Página 1 de 4 CARATULA
LAST PLANNER SYSTEM
WEEKLY PLAN OF ACTIVITIES
PROGRESS STARTED QUALIFICATION
CODE ACTIVITY M T W T F S S RESPONSIBLE
% YES/NO 0 - 100 % (As P.A.C CAUSES OF NON-COMPLIANCE
WEEK FROM JUNE 14 TO JUNE 20

Progress)

GENERAL ACTIVITY
5% Y 1% 0.05%
0% N 0% 0.00%
10% Y 10% 1.00%
5%
5%

WEIGHTING: 25.00% TOTAL: 1.05%


PLAN DE EQUIPO Y PERSONAL
PLAN SEMANAL DE ACTIVIDADES:

No. NECESIDAD CANTIDAD CONTRATISTA Y/O CONCEPTO A EJECUTAR VOLUMEN FECHA DE


FECHA DE INICIO TERMINACION CAUSAS DE NO CUMPLIMIENTO
PROVEEDOR SEMANAL
PERSONAL DE OBRA
1 Almacenista
2 Velador
3 Seguridad
4 Mayordomo
5 Pareja de Albañileria (1 Oficial y 1 Ayudante)
6 Pareja de Carpintero (1 Oficial Caripintero y 1 Ayudante)
7 Pareja de Fierrero (1 Oficial fierrero y 1 Ayudante)
8 Pareja de Electrico (1 Oficial Electrico 1 Ayudante)
9 Pareja de plomero (1 Oficial Plomero 1 Ayudante)
10 Proveedor Hidrosanitario
11 Proveedor Electrico
12 Proveedor de Instaaciones (Electricas e Hidrosanitarias)
13 Cuadrilla de Topografia
14 Etc.
EQUIPO DE SERVICIOS
1 Caseta de obra
2 Sanitario Movil
3 Fosa septica
SEMANA DEL 08 DE JUNIO AL 20 DE JUNIO

4 Lavabo portatil
5 Contenedor de basura
6 Tambos de basura
7 CCTV
8 Internet
9 Luz
10 Agua
11 Ettc.
EQUIPO DE SEGURIDAD INTERNO DEMEX
1 Casco
2 Chaleco
3 Botas
4 Guantes
5 Gafas
6 Etc.
EQUIPO MENOR
1 Bailarina (modelo)
2 Revolvedora electrica (Modelo)
3 Rompedora
4 Vibrador electrico
5 Etc.
EQUIPO DE ELEVACION
1 Juego de Andamio
2 Ruedas para andamio
3 Barandal de proteccion
4 Andamios estructurales
5 Plataforma tipo tijera
6 plataforma articulada
7 Etc.
EQUIPO MAYOR
1 Retroexcavadora (Modelo)
2 Piloteadora
3 Excavadora
4 Cargador Frontal
5 Etc.
PLAN QUINCENAL DE MATERIALES
PLAN SEMANAL DE ACTIVIDADES:

No. MATERIALES UNIDAD CANTIDAD % DESPERDICIO CANTIDAD CONCEPTO A EJECUTAR FECHA DE


TOTAL REQUERIMIENTO
SEMANA DEL 08 DE JUNIO AL 20 DE JUNIO

MATERIALES
1 0
2 0
3 0
4 0
5 0
6 0
7 0
8 0
9 0
10 0
11 0
12 0
13 0