Proyecto :
“VIVIENDAS SALUDABLES PARA EL SECTOR AYASH PICHIÚ"
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m u 1.00 909.89 909.89 136,625.89
01.02 ALMACENES Y GUARDIANIA m2 1.00 881.44 132,216.00
02 SEGURIDAD Y SALUD
02.01 ELABORACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJ u 1.00 1,636.94 1,636.94 23,198.79
02.02 IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD mes 3.00 1,283.69 3,851.07
02.07 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURID glb 1.00 2,358.00 2,358.00
03.05 NIVELACION INTERIOR Y APISONADO FINAL DEL TERRENO PREVIO m 1,244.08 1.51 1,878.56
03.07 RELLENO Y COMPACTADO ZANJA CON MATERIAL SELECCIONADO m3 298.58 37.38 11,160.92
03.08 RELLENO Y COMPACTADO ZANJA CON MATERIAL PROPIO SELE m3 597.16 23.32 13,925.77
03.10 TENDIDO DE TUBERIA PVC UF ISO 4435 160MM S-25 m 554.53 20.38 11,301.32
03.11 TENDIDO DE TUBERIA PVC UF ISO 4435 110MM S-25 m 689.65 16.11 11,110.26
03.12 DOBLE PRUEBA HIDRAULICA PARA TUBERIA DE DESAGUE m 1,244.08 0.58 721.57
04 BUZONES 29,930.46
04.01 TRAZO NIVELACION Y REPLANTEO m2 51.90 6.13 318.15
04.07 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 EN LOSA TECHO kg 223.15 4.60 1,026.49
Proyecto :
“VIVIENDAS SALUDABLES PARA EL SECTOR AYASH PICHIÚ"
05.03 NIVELACION INTERIOR Y APISONADO FINAL DEL TERRENO PREVIO m 260.00 1.51 392.60
05.04 CAMA DE APOYO EN ZANJAS PARA TUBERIA a=0.50M m 260.00 2.21 574.60
05.06 RELLENO Y COMPACTADO ZANJA CON MATERIAL SELECCIONADO m3 39.00 37.38 1,457.82
05.07 RELLENO Y COMPACTADO ZANJA CON MATERIAL PROPIO SELE m3 58.50 23.32 1,364.22
05.09 DOBLE PRUEBA HIDRAULICA PARA TUBERIA DE DESAGUE m 260.00 0.58 150.80
06.02.04.0 CONCRETO f'c=175 kg/cm2 PARA MUROS REFORZADOS m3 0.99 363.51 359.87
Proyecto :
“VIVIENDAS SALUDABLES PARA EL SECTOR AYASH PICHIÚ"
06.02.06.0 REJILLA SUMIDERO PLATINA 1 1/4"X1/4" @ 1/2" Y MARCO "L" 1 1 m2 0.43 120.58 51.85
06.03.04.0 CONCRETO f'c=210 kg/cm2 PARA MUROS REFORZADOS m3 5.39 380.05 2,048.47
06.03.04.0 ACERO ESTRUCTURAL TRABAJADO PARA LOSAS MACIZAS kg 98.40 4.79 471.34
06.03.06 ACCESORIOS
Proyecto :
“VIVIENDAS SALUDABLES PARA EL SECTOR AYASH PICHIÚ"
06.04.04.0 CONCRETO f'c=175 kg/cm2 PARA MUROS REFORZADOS m3 0.35 363.51 127.23
06.04.06 ACCESORIOS
06.05.04.0 CONCRETO f'c=175 kg/cm2 PARA MUROS REFORZADOS m3 0.76 363.51 276.27
Proyecto :
“VIVIENDAS SALUDABLES PARA EL SECTOR AYASH PICHIÚ"
06.06.03.0 CONCRETO f'c=140 kg/cm2 PARA SOLADOS Y/O SUB-BASES m3 0.16 284.41 45.51
06.06.04.0 CONCRETO f'c=175 kg/cm2 PARA MUROS REFORZADOS m3 0.02 363.51 7.27
06.07.04.0 CONCRETO f'c=175 kg/cm2 PARA MUROS REFORZADOS m3 3.84 363.51 1,395.88
06.07.06 ALBAÑILERIA
06.07.07 ACCESORIOS
06.07.07.0 SUMINISTRO DE CODO FIERRO FUNDIDO MAZZA DE 6" u 1.00 41.10 41.10
06.07.08.0 CONCRETO f'c= 140 kg/cm2 PARA DADOS m3 0.38 283.60 107.77
06.07.09 FILTROS
Proyecto :
“VIVIENDAS SALUDABLES PARA EL SECTOR AYASH PICHIÚ"
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2016 2017
TOTAL
MES 1 - DICIEMBRE MES 2 - ENERO MES 3 - FEBRERO MES 4 - MARZO
TOTAL TOTAL
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMAD
Item Descripción Und. Metrado Precio S/. Parcial S/. O EJECUTADO
01.02 CARTEL DE OBRA u 1.00 1,022.90 1,022.90 1,022.90 1,022.90 - - - - 1,022.90 1,022.90
01.04 ALMACEN Y OFICINAS mes 3.00 567.97 1,703.91 - - 1,703.91 567.97 - - 1,703.91 567.97
02.02 EQUIPOS DE PROTECCION INDIVIDUAL u 25.00 97.85 2,446.25 - - 2,446.25 2,446.25 - - 2,446.25 2,446.25
02.03 EQUIPOS DE PROTECCION COLECTIVA glb 1.00 1,101.70 1,101.70 - - 1,101.70 1,101.70 - - 1,101.70 1,101.70
02.04 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 2,458.00 2,458.00 - - 2,458.00 2,458.00 - - 2,458.00 2,458.00
02.05 CAPACITACION EN SEGURIDAD Y SALUD. mes 3.00 1,694.92 5,084.76 - - 5,084.76 1,694.92 - - 5,084.76 1,694.92
03.01.02 TRAZO NIVELACION Y REPLANTEO m2 6.21 1.24 7.70 - - 7.70 7.70 - - 7.70 7.70
03.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 15.15 35.35 535.55 - - 535.55 - - - 535.55 -
03.02.03 SUMINISTRO E INSTALACION DE PIEDRA SELECIONADA m3 5.18 184.81 957.32 - - 957.32 - - - 957.32 -
03.03.01 CONCRETO f'c= 140 kg/cm2 PARA SOLADOS Y/O DADOS m3 2.61 328.34 856.97 - - 856.97 - - - 856.97 -
03.04.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 82.96 4.60 381.62 - - 381.62 - - - 381.62 -
03.05.03 TARRAJEO CON IMPERMEABILIZANTES EN INTERIORES m2 5.61 29.90 167.74 - - 167.74 - - - 167.74 -
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2016 2017
TOTAL
MES 1 - DICIEMBRE MES 2 - ENERO MES 3 - FEBRERO MES 4 - MARZO
TOTAL TOTAL
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMAD
Item Descripción Und. Metrado Precio S/. Parcial S/. O EJECUTADO
03.06.01 REVESTIMIENTO DE PIEDRA ASENTADA EN CONCRETO F'C=100Kg/cm2 m2 0.50 74.87 37.44 - - 37.44 - - - 37.44 -
CRONOGRAMA VALORIZADO AL INICIO DEL PLAZO CONTRACTUAL
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2016 2017
TOTAL
MES 1 - DICIEMBRE MES 2 - ENERO MES 3 - FEBRERO MES 4 - MARZO
TOTAL TOTAL
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMAD
Item Descripción Und. Metrado Precio S/. Parcial S/. O EJECUTADO
03.07.01 TAPA METALICA 0.70X0.70 M SEGUN DISEÑO u 1.00 189.66 189.66 - - 189.66 - - - 189.66 -
03.07.02 TAPA METALICA 0.40X0.40 M SEGUN DISEÑO u 1.00 145.03 145.03 - - 145.03 - - - 145.03 -
03.08.01 PINTURA DE MURO EXTERIOR C/LATEX VINILICO m2 8.00 14.10 112.80 - - 112.80 - - - 112.80 -
03.09.01 SUM. E INST. TUBERIA PVC C-7.5 2" INC. PRUEBA m 10.00 5.97 59.70 - - 59.70 - - - 59.70 -
03.09.02 SUM. E INST. TUBERIA PVC C-10 2" m 4.00 6.59 26.36 - - 26.36 - - - 26.36 -
03.10.01 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC PARA CAPTACION C1. u 1.00 333.67 333.67 - - 333.67 - - - 333.67 -
03.11.01 SUMINISTRO E INSTALACION VALVULA COMPUERTA 2" u 1.00 36.67 36.67 - - 36.67 - - - 36.67 -
03.12.02 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 2.70 35.35 95.45 - - 95.45 - - - 95.45 -
03.12.03 CONCRETO f'c=100 kg/cm2 (CERCO DE SEGURIDAD) m3 2.70 276.20 745.74 - - 745.74 - - - 745.74 -
03.12.04 ANCLAJE DE ACERO CORRUGADO Fy=4200 KG/CM2 CON PLANCHA DE ACERO (CE u 3.00 40.86 122.58 - - 122.58 - - - 122.58 -
03.12.05 CERCO DE TUBO NEGRO Y MALLA OLIMPICA m2 29.40 77.75 2,285.85 - - 2,285.85 - - - 2,285.85 -
04.01.02 TRAZO NIVELACION Y REPLANTEO m2 5.00 1.24 6.20 - - 6.20 6.20 - - 6.20 6.20
04.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 6.90 35.35 243.92 - - 243.92 - - - 243.92 -
04.02.03 SUMINISTRO E INSTALACION DE PIEDRA SELECIONADA m3 1.08 184.81 199.59 - - 199.59 - - - 199.59 -
04.03.01 CONCRETO f'c= 140 kg/cm2 PARA SOLADOS Y/O DADOS m3 1.86 328.34 610.71 - - 610.71 - - - 610.71 -
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2016 2017
TOTAL
MES 1 - DICIEMBRE MES 2 - ENERO MES 3 - FEBRERO MES 4 - MARZO
TOTAL TOTAL
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMAD
Item Descripción Und. Metrado Precio S/. Parcial S/. O EJECUTADO
04.04.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 95.00 4.60 437.00 - - 437.00 - - - 437.00 -
04.05.03 TARRAJEO CON IMPERMEABILIZANTES EN INTERIORES m2 6.58 29.90 196.74 - - 196.74 - - - 196.74 -
04.06.01 REVESTIMIENTO DE PIEDRA ASENTADA EN CONCRETO F'C=100Kg/cm2 m2 1.00 74.87 74.87 - - 74.87 - - - 74.87 -
04.07.01 TAPA METALICA 0.70X0.70 M SEGUN DISEÑO u 2.00 189.66 379.32 - - 379.32 - - - 379.32 -
04.07.02 TAPA METALICA 0.40X0.40 M SEGUN DISEÑO u 2.00 145.03 290.06 - - 290.06 - - - 290.06 -
04.08.01 PINTURA DE MURO EXTERIOR C/LATEX VINILICO m2 13.24 14.10 186.68 - - 186.68 - - - 186.68 -
04.09.01 SUM. E INST. TUBERIA PVC C-7.5 2" INC. PRUEBA m 20.00 5.97 119.40 - - 119.40 - - - 119.40 -
04.09.02 SUM. E INST. TUBERIA PVC C-10 1" m 8.00 3.69 29.52 - - 29.52 - - - 29.52 -
04.10.01 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC PARA CAPTACION C1. u 2.00 184.07 368.14 - - 368.14 - - - 368.14 -
04.11.01 SUMINISTRO E INSTALACION VALVULA COMPUERTA 1" u 1.00 15.64 15.64 - - 15.64 - - - 15.64 -
04.12.02 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 9.00 35.35 318.15 - - 318.15 - - - 318.15 -
04.12.03 CONCRETO f'c=100 kg/cm2 (CERCO DE SEGURIDAD) m3 9.00 276.20 2,485.80 - - 2,485.80 - - - 2,485.80 -
04.12.04 ANCLAJE DE ACERO CORRUGADO Fy=4200 KG/CM2 CON PLANCHA DE ACERO (CE u 10.00 40.86 408.60 - - 408.60 - - - 408.60 -
04.12.05 CERCO DE TUBO NEGRO Y MALLA OLIMPICA m2 58.80 77.75 4,571.70 - - 4,571.70 - - - 4,571.70 -
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2016 2017
TOTAL
MES 1 - DICIEMBRE MES 2 - ENERO MES 3 - FEBRERO MES 4 - MARZO
TOTAL TOTAL
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMAD
Item Descripción Und. Metrado Precio S/. Parcial S/. O EJECUTADO
05.01.01 LIMPIEZA DE TERRENO MANUAL m2 245.68 1.76 432.40 - - 432.40 432.40 - - 432.40 432.40
05.01.02 TRAZO NIVELACION Y REPLANTEO m2 245.68 1.24 304.64 - - 304.64 304.64 - - 304.64 304.64
05.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 68.79 35.35 2,431.73 - - 2,431.73 - - - 2,431.73 -
05.02.02 EXCAVACION MANUAL EN ROCA SUELTA m3 29.48 102.10 3,009.91 - - 3,009.91 - - - 3,009.91 -
05.02.03 CAMA DE TIERRA ZARANDEADA E=0.10M. ZANJA P/TUBO m 307.10 1.09 334.74 - - 334.74 - - - 334.74 -
05.02.04 RELLENO Y COMPACTADO ZANJA CON MATERIAL SELECCIONADO EN CAPAS DE 0. m3 36.85 35.93 1,324.02 - - 1,324.02 - - - 1,324.02 -
05.02.05 RELLENO Y COMPACTADO ZANJA CON MATERIAL PROPIO SELECCIONADO m3 49.14 34.91 1,715.48 - - 1,715.48 - - - 1,715.48 -
05.03.01 SUM. E INST. TUBERIA PVC C-10 2" m 219.25 6.59 1,444.86 - - 1,444.86 - - - 1,444.86 -
05.03.02 SUM. E INST. TUBERIA PVC C-10 1" m 87.85 3.69 324.17 - - 324.17 - - - 324.17 -
05.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC u 1.00 88.71 88.71 - - 88.71 - - - 88.71 -
05.05.01 PRUEBA HIDRAULICA + DESINFECCION DE TUB. ZANJA TAPADA m 307.10 0.76 233.40 - - 233.40 - - - 233.40 -
06.01.01 LIMPIEZA DE TERRENO MANUAL m2 16.00 1.76 28.16 - - 28.16 28.16 - - 28.16 28.16
06.01.02 TRAZO NIVELACION Y REPLANTEO m2 16.00 1.24 19.84 - - 19.84 19.84 - - 19.84 19.84
06.02.01 EXCAVACION DE ZANJA EN MATERIAL CONGLOMERADO m3 9.60 36.04 345.98 - - 345.98 345.98 - - 345.98 345.98
06.02.02 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 11.52 45.45 523.58 - - 523.58 523.58 - - 523.58 523.58
06.03.01 CONCRETO f'c= 140 kg/cm2 PARA DADOS m3 1.60 328.34 525.34 - - 525.34 525.34 - - 525.34 525.34
06.04 OBRAS DE CONCRETO ARMADO 14,285.02 - - 10,419.86 12,667.39 3,865.16 - - - 14,285.02 12,667.39
06.04.01 CONCRETO F'C=210 KG/CM2 P/ PISO m3 4.32 383.82 1,658.10 - - 1,658.10 1,658.10 - - 1,658.10 1,658.10
06.04.02 ENCOFRADO Y DESENCOFRADO P/PISO m2 4.80 53.87 258.58 - - 258.58 258.58 - - 258.58 258.58
06.04.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 97.21 4.60 447.17 - - 447.17 447.17 - - 447.17 447.17
CRONOGRAMA VALORIZADO AL INICIO DEL PLAZO CONTRACTUAL
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2016 2017
TOTAL
MES 1 - DICIEMBRE MES 2 - ENERO MES 3 - FEBRERO MES 4 - MARZO
TOTAL TOTAL
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMAD
Item Descripción Und. Metrado Precio S/. Parcial S/. O EJECUTADO
06.04.04 CONCRETO F'C=210 KG/CM2 P/MUROS REFORZADO m3 6.26 425.94 2,666.38 - - 1,916.46 2,666.38 749.92 - 2,666.38 2,666.38
06.04.05 ENCOFRADO Y DESENCOFRADO P/MURO REFORZADO m2 62.56 53.87 3,370.11 - - 2,422.27 3,370.11 947.84 - 3,370.11 3,370.11
06.04.06 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 857.62 4.60 3,945.05 - - 3,057.41 3,945.05 887.64 - 3,945.05 3,945.05
06.04.07 CONCRETO F'C=210 KG/CM2 P/TECHO m3 1.44 457.15 658.30 - - 192.00 - 466.30 - 658.30 -
06.04.08 ENCOFRADO Y DESENCOFRADO P/TECHO m2 13.68 54.80 749.66 - - 218.65 - 531.01 - 749.66 -
06.04.09 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 115.58 4.60 531.67 - - 249.22 322.00 282.45 - 531.67 322.00
06.05.03 TARRAJEO CON IMPERMEABILIZANTES EN INTERIORES m2 39.68 29.90 1,186.43 - - - - 1,186.43 - 1,186.43 -
06.06.01 ESCALIN DE FIERRO CORRUGADO 3/4" (MOVIBLE) u 7.00 10.78 75.46 - - - - 75.46 - 75.46 -
06.06.02 TAPA METALICA TIPO T-1 SEGUN DISEÑO u 1.00 364.86 364.86 - - - - 364.86 - 364.86 -
06.06.03 VENTILACION C/TUBERIA DE ACERO S/DISEÑO DE 2" u 1.00 43.15 43.15 - - - - 43.15 - 43.15 -
06.07.01 PINTURA DE MURO EXTERIOR C/LATEX VINILICO m2 50.84 14.10 716.84 - - - - 716.84 - 716.84 -
06.08.01 PRUEBA HIDRAULICA CON EMPLEO DE LINEA DE INGRESO m3 20.00 0.90 18.00 - - - - 18.00 - 18.00 -
06.08.02 DESINFECCION DE RESERVORIO CON EMPLEO DE LINEA DE INGRESO m3 20.00 3.81 76.20 - - - - 76.20 - 76.20 -
06.08.03 EVACUACION DEL AGUA DE PRUEBA CON EMPLEO DE LINEA DE SALIDA m3 20.00 0.65 13.00 - - - - 13.00 - 13.00 -
06.09.02 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 9.00 35.35 318.15 - - - - 318.15 - 318.15 -
06.09.03 CONCRETO f'c=100 kg/cm2 (CERCO DE SEGURIDAD) m3 9.00 276.20 2,485.80 - - - - 2,485.80 - 2,485.80 -
06.09.04 ANCLAJE DE ACERO CORRUGADO Fy=4200 KG/CM2 CON PLANCHA DE ACERO (CE u 10.00 40.86 408.60 - - - - 408.60 - 408.60 -
06.09.05 CERCO DE TUBO NEGRO Y MALLA OLIMPICA m2 58.80 77.75 4,571.70 - - - - 4,571.70 - 4,571.70 -
07.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.68 1.76 2.96 - - - 2.96 2.96 - 2.96 2.96
CRONOGRAMA VALORIZADO AL INICIO DEL PLAZO CONTRACTUAL
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2016 2017
TOTAL
MES 1 - DICIEMBRE MES 2 - ENERO MES 3 - FEBRERO MES 4 - MARZO
TOTAL TOTAL
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMAD
Item Descripción Und. Metrado Precio S/. Parcial S/. O EJECUTADO
07.01.02 TRAZO NIVELACION Y REPLANTEO m2 1.68 1.24 2.08 - - - 2.08 2.08 - 2.08 2.08
07.02.01 EXCAVACION DE ZANJA EN MATERIAL CONGLOMERADO m3 0.34 36.04 12.25 - - - 12.25 12.25 - 12.25 12.25
07.02.02 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 1.64 45.45 74.54 - - - 74.54 74.54 - 74.54 74.54
07.03.01 CONCRETO f'c= 140 kg/cm2 PARA DADOS m3 0.15 328.34 49.25 - - - 49.25 49.25 - 49.25 49.25
07.04.01 CONCRETO F'C=210 KG/CM2 P/MUROS REFORZADO m3 0.32 425.94 136.30 - - - - 136.30 - 136.30 -
07.04.02 ENCOFRADO Y DESENCOFRADO P/MURO REFORZADO m2 6.40 53.87 344.77 - - - - 344.77 - 344.77 -
07.04.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 12.45 4.60 57.27 - - - 57.27 57.27 - 57.27 57.27
07.04.04 CONCRETO F'C=210 KG/CM2 P/TECHO m3 0.33 457.15 150.86 - - - - 150.86 - 150.86 -
07.04.06 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 9.85 4.60 45.31 - - - 23.00 45.31 - 45.31 23.00
07.06.01 REVESTIMIENTO DE PIEDRA ASENTADA EN CONCRETO F'C=100Kg/cm2 m2 0.50 74.87 37.44 - - - - 37.44 - 37.44 -
07.07.01 TAPA METALICA TIPO T-1 SEGUN DISEÑO u 1.00 364.86 364.86 - - - - 364.86 - 364.86 -
07.08.01 PINTURA DE MURO EXTERIOR C/LATEX VINILICO m2 5.34 14.10 75.29 - - - - 75.29 - 75.29 -
07.10.01 SUM. E INST. TUBERIA PVC C-10 4" INC. PRUEBA m 10.00 14.31 143.10 - - - - 143.10 - 143.10 -
07.10.02 SUM. E INST. TUBERIA PVC C-10 2" m 8.00 6.59 52.72 - - - - 52.72 - 52.72 -
07.11.01 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC u 1.00 347.16 347.16 - - - - 347.16 - 347.16 -
CRONOGRAMA VALORIZADO AL INICIO DEL PLAZO CONTRACTUAL
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2016 2017
TOTAL
MES 1 - DICIEMBRE MES 2 - ENERO MES 3 - FEBRERO MES 4 - MARZO
TOTAL TOTAL
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMAD
Item Descripción Und. Metrado Precio S/. Parcial S/. O EJECUTADO
07.12.01 SUMINISTRO E INSTALACION VALVULA COMPUERTA 2" u 3.00 36.67 110.01 - - - - 110.01 - 110.01 -
07.12.02 SUMINISTRO E INSTALACION VALVULA COMPUERTA 4" u 1.00 147.76 147.76 - - - - 147.76 - 147.76 -
08.01.01 LIMPIEZA DE TERRENO MANUAL m2 ### 1.76 2,238.76 - - - 2,238.76 2,238.76 - 2,238.76 2,238.76
08.01.02 TRAZO NIVELACION Y REPLANTEO m2 ### 1.24 1,577.30 - - - 1,577.30 1,577.30 - 1,577.30 1,577.30
08.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 712.33 35.35 25,180.87 - - - 25,180.87 25,180.87 - 25,180.87 25,180.87
08.02.02 EXCAVACION MANUAL EN ROCA SUELTA m3 305.28 102.10 31,169.09 - - - 31,169.09 31,169.09 - 31,169.09 31,169.09
08.02.03 CAMA DE TIERRA ZARANDEADA E=0.10M. ZANJA P/TUBO m ### 1.09 3,466.25 - - - 3,466.25 3,466.25 - 3,466.25 3,466.25
08.02.04 RELLENO Y COMPACTADO ZANJA CON MATERIAL SELECCIONADO EN CAPAS DE 0. m3 374.69 35.93 13,462.61 - - - 13,462.61 13,462.61 - 13,462.61 13,462.61
08.02.05 RELLENO Y COMPACTADO ZANJA CON MATERIAL PROPIO SELECCIONADO m3 508.81 34.91 17,762.56 - - - 17,762.56 17,762.56 - 17,762.56 17,762.56
08.02.06 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 147.98 45.45 6,725.69 - - - 6,725.69 6,725.69 - 6,725.69 6,725.69
08.03.01 SUM. E INST. TUBERIA PVC C-10 2 1/2" INC. PRUEBA m 413.79 7.95 3,289.63 - - - 3,289.63 3,289.63 - 3,289.63 3,289.63
08.03.02 SUM. E INST. TUBERIA PVC C-10 2" m 501.69 6.59 3,306.14 - - - 3,306.14 3,306.14 - 3,306.14 3,306.14
08.03.03 SUM. E INST. TUBERIA PVC C-10 1 1/2" INC. PRUEBA m 579.88 4.18 2,423.90 - - - 2,423.90 2,423.90 - 2,423.90 2,423.90
08.03.04 SUM. E INST. TUBERIA PVC C-10 1" m ### 3.69 4,157.38 - - - 4,157.38 4,157.38 - 4,157.38 4,157.38
08.03.05 SUM. E INST. TUBERIA PVC C-10 3/4" INC. PRUEBA m 556.00 2.28 1,267.68 - - - 1,267.68 1,267.68 - 1,267.68 1,267.68
08.04 SUMINISTRO E INSTALACION DE ACCESORIOS PARA RD 3,051.94 - - - 3,051.94 3,051.94 - - - 3,051.94 3,051.94
08.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC PARA REDES DE DISTRIBU u 1.00 3,051.94 3,051.94 - - - 3,051.94 3,051.94 - 3,051.94 3,051.94
08.05 PRUEBA HIDRAULICA Y DESINFECCION 2,416.84 - - - 2,416.84 2,316.14 - 100.70 - 2,416.84 2,416.84
08.05.01 PRUEBA HIDRAULICA + DESINFECCION DE TUB. ZANJA TAPADA m ### 0.76 2,416.84 - - - 2,416.84 2,316.14 100.70 2,416.84 2,416.84
09 CAMARA ROMPE PRESION TIPO CRP-7 (04 UND) 13,098.94 - - - 1,053.32 94.68 - 13,004.26 - 13,098.94 1,053.32
09.01.01 TRAZO NIVELACION Y REPLANTEO m2 6.60 1.24 8.18 - - - 8.18 8.18 - 8.18 8.18
09.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 5.22 35.35 184.53 - - - 184.53 86.50 98.03 184.53 184.53
CRONOGRAMA VALORIZADO AL INICIO DEL PLAZO CONTRACTUAL
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2016 2017
TOTAL
MES 1 - DICIEMBRE MES 2 - ENERO MES 3 - FEBRERO MES 4 - MARZO
TOTAL TOTAL
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMAD
Item Descripción Und. Metrado Precio S/. Parcial S/. O EJECUTADO
09.02.02 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 6.79 45.45 308.61 - - 308.61 308.61 308.61 308.61
09.03.01 CONCRETO f'c= 140 kg/cm2 PARA SOLADOS Y/O DADOS m3 0.05 328.34 16.42 - - - - - 16.42 16.42 -
09.04.01 CONCRETO ARMADO f'c=175 kg/cm2. m3 4.10 421.42 1,727.82 - - - - - 1,727.82 1,727.82 -
09.04.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 131.92 4.60 606.83 - - - 552.00 - 606.83 606.83 552.00
09.05.03 TARRAJEO CON IMPERMEABILIZANTES EN INTERIORES m2 13.92 29.90 416.21 - - - - - 416.21 416.21 -
CRONOGRAMA VALORIZADO AL INICIO DEL PLAZO CONTRACTUAL
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2016 2017
TOTAL
MES 1 - DICIEMBRE MES 2 - ENERO MES 3 - FEBRERO MES 4 - MARZO
TOTAL TOTAL
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMAD
Item Descripción Und. Metrado Precio S/. Parcial S/. O EJECUTADO
09.06.01 REVESTIMIENTO DE PIEDRA ASENTADA EN CONCRETO F'C=100Kg/cm2 m2 2.00 74.87 149.74 - - - - - 149.74 149.74 -
09.07.01 PINTURA DE MURO EXTERIOR C/LATEX VINILICO m2 28.52 14.10 402.13 - - - - - 402.13 402.13 -
09.08.01 TAPA METALICA 0.40X0.40 M SEGUN DISEÑO u 4.00 145.03 580.12 - - - - - 580.12 580.12 -
09.08.02 TAPA METALICA 0.60X0.60 M SEGUN DISEÑO u 4.00 172.72 690.88 - - - - - 690.88 690.88 -
09.08.03 VENTILACION C/TUBERIA DE Fo Go S/DISEÑO DE 2" u 4.00 43.88 175.52 - - - - - 175.52 175.52 -
09.09.01 SUM. E INST. TUBERIA PVC C-7.5 2" INC. PRUEBA m 40.00 5.97 238.80 - - - - - 238.80 238.80 -
09.09.02 SUM. E INST. TUBERIA PVC C-10 2 1/2" INC. PRUEBA m 4.00 7.95 31.80 - - - - - 31.80 31.80 -
09.09.03 SUM. E INST. TUBERIA PVC C-10 2" m 4.00 6.59 26.36 - - - - - 26.36 26.36 -
09.09.04 SUM. E INST. TUBERIA PVC C-10 1 1/2" INC. PRUEBA m 4.00 4.18 16.72 - - - - - 16.72 16.72 -
09.09.05 SUM. E INST. TUBERIA PVC C-10 1" m 4.00 3.69 14.76 - - - - - 14.76 14.76 -
09.10.01 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC PARA CRP-7.. u 1.00 4,170.19 4,170.19 - - - - - 4,170.19 4,170.19 -
09.11.01 SUMINISTRO E INSTALACION VALVULA COMPUERTA 2 1/2" u 1.00 40.32 40.32 - - - - - 40.32 40.32 -
09.11.02 SUMINISTRO E INSTALACION VALVULA FLOTADOR 2 1/2" u 1.00 71.01 71.01 - - - - - 71.01 71.01 -
09.11.03 SUMINISTRO E INSTALACION VALVULA COMPUERTA 2" u 1.00 36.67 36.67 - - - - - 36.67 36.67 -
09.11.04 SUMINISTRO E INSTALACION VALVULA FLOTADOR 2" u 1.00 60.58 60.58 - - - - - 60.58 60.58 -
09.11.05 SUMINISTRO E INSTALACION VALVULA COMPUERTA 11/2" u 1.00 20.83 20.83 - - - - - 20.83 20.83 -
09.11.06 SUMINISTRO E INSTALACION VALVULA FLOTADOR 11/2" u 1.00 37.78 37.78 - - - - - 37.78 37.78 -
09.11.07 SUMINISTRO E INSTALACION VALVULA COMPUERTA 1" u 1.00 15.64 15.64 - - - - - 15.64 15.64 -
09.11.08 SUMINISTRO E INSTALACION VALVULA FLOTADOR 1" u 1.00 36.97 36.97 - - - - - 36.97 36.97 -
10.01 CAMARA P/VALVULA DE PURGA EN MATRIZ (03 UND 1", 03 UND 1 1/2" Y 01 UND 3/4") 2,735.43 - - - 138.00 - - 2,735.43 - 2,735.43 138.00
10.01.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 1.75 35.35 61.86 - - - - - 61.86 61.86 -
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2016 2017
TOTAL
MES 1 - DICIEMBRE MES 2 - ENERO MES 3 - FEBRERO MES 4 - MARZO
TOTAL TOTAL
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMAD
Item Descripción Und. Metrado Precio S/. Parcial S/. O EJECUTADO
10.01.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 45.68 4.60 210.13 - - - 138.00 - 210.13 210.13 138.00
10.01.05 SUM. E INST. DE TUBERIA Fo Go STAND. ISO-I 1 1/2" m 4.50 24.81 111.65 - - - - - 111.65 111.65 -
10.01.06 SUM. E INST. TUBERIA PVC C-10 1 1/2" INC. PRUEBA m 6.00 4.18 25.08 - - - - - 25.08 25.08 -
10.01.07 SUM. E INST. DE TUBERIA Fo Go STAND. ISO-I 1" m 4.50 12.91 58.10 - - - - - 58.10 58.10 -
10.01.08 SUM. E INST. TUBERIA PVC C-10 1" m 6.00 3.69 22.14 - - - - - 22.14 22.14 -
10.01.09 SUM. E INST. DE TUBERIA Fo Go STAND. ISO-I 3/4" m 4.50 10.93 49.19 - - - - - 49.19 49.19 -
10.01.10 SUM. E INST. TUBERIA PVC C-10 3/4" INC. PRUEBA m 6.00 2.28 13.68 - - - - - 13.68 13.68 -
10.01.11 SUMINISTRO E INSTALACION VALVULA COMPUERTA 11/2" u 3.00 20.83 62.49 - - - - - 62.49 62.49 -
10.01.12 SUMINISTRO E INSTALACION VALVULA COMPUERTA 3/4" u 3.00 12.62 37.86 - - - - - 37.86 37.86 -
10.01.13 SUMINISTRO E INSTALACION VALVULA COMPUERTA 1" u 1.00 15.64 15.64 - - - - - 15.64 15.64 -
10.02 CAMARA P/VALVULA DE CONTROL EN MATRIZ (02 UND 1 1/2", 01 UND 1") 1,699.75 - - - 55.20 - - 1,699.75 - 1,699.75 55.20
10.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 0.75 35.35 26.51 - - - - - 26.51 26.51 -
10.02.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 18.45 4.60 84.87 - - - 55.20 - 84.87 84.87 55.20
10.02.06 SUMINISTRO E INSTALACION VALVULA COMPUERTA 11/2" u 2.00 20.83 41.66 - - - - - 41.66 41.66 -
10.02.07 SUMINISTRO E INSTALACION VALVULA COMPUERTA 2" u 1.00 36.67 36.67 - - - - - 36.67 36.67 -
11.01 TRAZO NIVELACION Y REPLANTEO m ### 0.76 820.80 - - - 820.80 - 820.80 820.80 820.80
11.03 CAMA DE TIERRA ZARANDEADA E=0.10M. ZANJA P/TUBO m ### 1.09 1,177.20 - - - - - 1,177.20 1,177.20 -
11.04 SUM. E INST. TUBERIA PVC C-10 1/2" INC. PRUEBA m ### 1.82 1,965.60 - - - - - 1,965.60 1,965.60 -
11.05 RELLENO Y COMPACTADO ZANJA CON MATERIAL SELECCIONADO EN CAPAS DE 0.1 m3 172.80 35.93 6,208.70 - - - - - 6,208.70 6,208.70 -
11.06 RELLENO Y COMPACTADO ZANJA CON MATERIAL PROPIO SELECCIONADO m3 86.40 34.91 3,016.22 - - - - - 3,016.22 3,016.22 -
11.07 ELIMINACION DE MATERIAL EXCEDENTE EN CARRETILLA (50.00M) m3 172.80 75.75 13,089.60 - - - - - 13,089.60 13,089.60 -
11.08 CONEXIONES DOMICILIARIAS DE R.D. Ø 2 1/2" u 8.00 97.92 783.36 - - - - - 783.36 783.36 -
CRONOGRAMA VALORIZADO AL INICIO DEL PLAZO CONTRACTUAL
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2016 2017
TOTAL
MES 1 - DICIEMBRE MES 2 - ENERO MES 3 - FEBRERO MES 4 - MARZO
TOTAL TOTAL
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMAD
Item Descripción Und. Metrado Precio S/. Parcial S/. O EJECUTADO
11.09 CONEXIONES DOMICILIARIAS DE R.D. Ø 2 " u 21.00 87.41 1,835.61 - - - - - 1,835.61 1,835.61 -
11.10 CONEXIONES DOMICILIARIAS DE R.D. Ø 1 1/2 " u 27.00 80.80 2,181.60 - - - - - 2,181.60 2,181.60 -
11.11 CONEXIONES DOMICILIARIAS DE R.D. Ø 1" u 39.00 76.52 2,984.28 - - - - - 2,984.28 2,984.28 -
11.12 CONEXIONES DOMICILIARIAS DE R.D. Ø 3/4" u 13.00 70.28 913.64 - - - - - 913.64 913.64 -
12.01 INFORMACION A LA POBLACION DE LAS ACTIVIDADES DEL PROYECTO 2,661.50 - - - - - - 2,661.50 - 2,661.50 -
12.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 3.00 35.35 106.05 - - - - - 106.05 106.05 -
12.02.03 CLAUSURA MANUAL DE FOSA DE BASURA m3 3.00 39.30 117.90 - - - - 117.90 117.90 -
12.03.01 EXCAVACION MANUAL PARA HOYO m3 34.00 26.51 901.34 - - - - - 901.34 901.34 -
13.01.01.01 ELABORACION Y REPRODUCCION DEL MATERIAL DE CAPACITACION EN EDUCAC glb 1.00 3,237.28 3,237.28 - - - - - 3,237.28 3,237.28 -
13.01.02.01 CAPACITACION EN EDUCACION SANITARIA glb 1.00 2,945.88 2,945.88 - - - - - 2,945.88 2,945.88 -
13.01.03 CONSTITUCION Y REGISTRO DE LA UNIDAD DE GESTION SANITARIA (UGS) 5,385.93 - - - - - - 5,385.93 - 5,385.93 -
13.01.03.01.01 CONSTITUCION Y REGISTRO DE LA UGS glb 1.00 2,118.64 2,118.64 - - - - - 2,118.64 2,118.64 -
CRONOGRAMA VALORIZADO AL INICIO DEL PLAZO CONTRACTUAL
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2016 2017
TOTAL
MES 1 - DICIEMBRE MES 2 - ENERO MES 3 - FEBRERO MES 4 - MARZO
TOTAL TOTAL
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMAD
Item Descripción Und. Metrado Precio S/. Parcial S/. O EJECUTADO
13.02.01.01 ELABORACION Y REPRODUCCION DEL MATERIAL DE CAPACITACION DE LA UGS glb 1.00 3,237.28 3,237.28 - - - - - 3,237.28 3,237.28 -
CRONOGRAMA VALORIZADO AL INICIO DEL PLAZO CONTRACTUAL
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2016 2017
TOTAL
MES 1 - DICIEMBRE MES 2 - ENERO MES 3 - FEBRERO MES 4 - MARZO
TOTAL TOTAL
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMAD
Item Descripción Und. Metrado Precio S/. Parcial S/. O EJECUTADO
14.01 FLETE TERRESTRE glb 1.00 7,061.20 7,061.20 - - 7,061.20 3,530.60 - - 7,061.20 3,530.60
14.02 FLETE RURAL glb 1.00 ### 24,814.08 - - - 12,407.04 24,814.08 - 24,814.08 12,407.04
COSTO DIRECTO S/. 331,272.54 1,022.90 1,022.90 75,854.66 167,541.14 164,534.01 0.00 89,860.97 0.00 331,272.54 168,564.04
GASTOS GENERALES 16.26% 53,879.30 166.37 166.37 12,337.26 27,249.46 26,760.37 0.00 14,615.30 0.00 53,879.30 27,415.83
UTILIDADES 10.00% 33,127.25 102.29 102.29 7,585.47 16,754.11 16,453.40 0.00 8,986.10 0.00 33,127.25 16,856.40
SUB TOTAL 418,279.09 1,291.56 1,291.56 95,777.39 211,544.71 207,747.79 0.00 113,462.36 0.00 418,279.09 212,836.28
RELACION 1.00 418,279.09 1,291.56 1,291.56 95,777.39 211,544.71 207,747.79 0.00 113,462.36 0.00 418,279.09 212,836.28
UTILIDADES 18.00% 75,290.24 232.48 232.48 17,239.93 38,078.05 37,394.60 0.00 20,423.23 0.00 75,290.24 38,310.53
TOTAL PRESUPUESTO 493,569.33 1,524.04 1,524.04 113,017.32 249,622.76 245,142.39 0.00 133,885.59 0.00 493,569.33 251,146.81
MONTO PROGRAMADO 1,524.04 ### ### ###
MONTO PROGRAMADO ACUMULADO 1,524.04 ### ### ###
% PROGRAMADO 0.31% 22.90% 49.67% 27.13%
% PROGRAMADO ACUMULADO 0.31% 23.21% 72.87% 100.00%
MONTO EJECUTADO 1,524.04 ### - -
MONTO EJECUTADO ACUMULADO 1,524.04 ### - -
% EJECUTADO 0.31% 50.58% 0.00% 0.00%
% EJECUTADO ACUMULADO 0.31% 50.88% 0.00% 0.00%
CRONOGRAMA VALORIZADO AL INICIO DEL PLAZO CONTRACTUAL
Proyecto : "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE EN EL CASERIO DE CHUYO, DISTRITO DE SAN MARCOS - HUARI - ANCASH"
2017
01.01 MOVILIZACION DE EQUIPOS Y HERRAMIENTAS est 2.00 1,298.29 2,596.58 2,596.58 2,596.58 0.00
01.04 ALMACEN Y OFICINAS mes 3.00 567.97 1,703.91 1,703.91 1,703.91 0.00
02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE S glb 1.00 3,389.83 3,389.83 3,389.83 3,389.83 0.00
02.02 EQUIPOS DE PROTECCION INDIVIDUAL u 25.00 97.85 2,446.25 2,446.25 2,446.25 0.00
02.03 EQUIPOS DE PROTECCION COLECTIVA glb 1.00 1,101.70 1,101.70 1,101.70 1,101.70 0.00
02.04 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 2,458.00 2,458.00 2,458.00 2,458.00 0.00
02.05 CAPACITACION EN SEGURIDAD Y SALUD. mes 3.00 1,694.92 5,084.76 5,084.76 5,084.76 0.00
03.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.21 1.76 10.93 10.93 10.93 0.00
03.01.02 TRAZO NIVELACION Y REPLANTEO m2 6.21 1.24 7.70 7.70 7.70 0.00
03.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 15.15 35.35 535.55 535.55 535.55 0.00
03.02.02 ELIMINACION DE MATERIAL EXCEDENTE 50 M m3 16.66 46.34 772.02 772.02 772.02 0.00
03.02.03 SUMINISTRO E INSTALACION DE PIEDRA SELECIONADA m3 5.18 184.81 957.32 957.32 957.32 0.00
03.03.01 CONCRETO f'c= 140 kg/cm2 PARA SOLADOS Y/O DADOS m3 2.61 328.34 856.97 856.97 856.97 0.00
03.04.01 CONCRETO F'C=210 KG/CM2 m3 3.63 422.16 1,532.44 1,532.44 1,532.44 0.00
03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 24.40 47.59 1,161.20 1,161.20 1,161.20 0.00
03.04.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 82.96 4.60 381.62 381.62 381.62 0.00
03.05.03 TARRAJEO CON IMPERMEABILIZANTES EN INTERIORES m2 5.61 29.90 167.74 167.74 167.74 0.00
03.06.01 REVESTIMIENTO DE PIEDRA ASENTADA EN CONCRETO F'C=100Kg/cm m2 0.50 74.87 37.44 37.44 37.44 0.00
03.07.01 TAPA METALICA 0.70X0.70 M SEGUN DISEÑO u 1.00 189.66 189.66 189.66 189.66 0.00
03.07.02 TAPA METALICA 0.40X0.40 M SEGUN DISEÑO u 1.00 145.03 145.03 145.03 145.03 0.00
03.08.01 PINTURA DE MURO EXTERIOR C/LATEX VINILICO m2 8.00 14.10 112.80 112.80 112.80 0.00
03.09.01 SUM. E INST. TUBERIA PVC C-7.5 2" INC. PRUEBA m 10.00 5.97 59.70 59.70 59.70 0.00
03.09.02 SUM. E INST. TUBERIA PVC C-10 2" m 4.00 6.59 26.36 26.36 26.36 0.00
03.10.01 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC PARA CAPTAC u 1.00 333.67 333.67 333.67 333.67 0.00
03.12.01 TRAZO NIVELACION Y REPLANTEO m2 1.08 1.24 1.34 1.34 1.34 0.00
03.12.02 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 2.70 35.35 95.45 95.45 95.45 0.00
03.12.03 CONCRETO f'c=100 kg/cm2 (CERCO DE SEGURIDAD) m3 2.70 276.20 745.74 745.74 745.74 0.00
03.12.04 ANCLAJE DE ACERO CORRUGADO Fy=4200 KG/CM2 CON PLANCHA D u 3.00 40.86 122.58 122.58 122.58 0.00
03.12.05 CERCO DE TUBO NEGRO Y MALLA OLIMPICA m2 29.40 77.75 2,285.85 2,285.85 2,285.85 0.00
04.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 1.76 8.80 8.80 8.80 0.00
04.01.02 TRAZO NIVELACION Y REPLANTEO m2 5.00 1.24 6.20 6.20 6.20 0.00
04.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 6.90 35.35 243.92 243.92 243.92 0.00
04.02.02 ELIMINACION DE MATERIAL EXCEDENTE 50 M m3 7.59 46.34 351.72 351.72 351.72 0.00
04.02.03 SUMINISTRO E INSTALACION DE PIEDRA SELECIONADA m3 1.08 184.81 199.59 199.59 199.59 0.00
04.03.01 CONCRETO f'c= 140 kg/cm2 PARA SOLADOS Y/O DADOS m3 1.86 328.34 610.71 610.71 610.71 0.00
04.04.01 CONCRETO F'C=210 KG/CM2 m3 3.39 422.16 1,431.12 1,431.12 1,431.12 0.00
04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 35.10 47.59 1,670.41 1,670.41 1,670.41 0.00
04.04.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 95.00 4.60 437.00 437.00 437.00 0.00
04.05.03 TARRAJEO CON IMPERMEABILIZANTES EN INTERIORES m2 6.58 29.90 196.74 196.74 196.74 0.00
04.06.01 REVESTIMIENTO DE PIEDRA ASENTADA EN CONCRETO F'C=100Kg/cm m2 1.00 74.87 74.87 74.87 74.87 0.00
04.07.01 TAPA METALICA 0.70X0.70 M SEGUN DISEÑO u 2.00 189.66 379.32 379.32 379.32 0.00
04.07.02 TAPA METALICA 0.40X0.40 M SEGUN DISEÑO u 2.00 145.03 290.06 290.06 290.06 0.00
04.08.01 PINTURA DE MURO EXTERIOR C/LATEX VINILICO m2 13.24 14.10 186.68 186.68 186.68 0.00
04.09.01 SUM. E INST. TUBERIA PVC C-7.5 2" INC. PRUEBA m 20.00 5.97 119.40 119.40 119.40 0.00
04.09.02 SUM. E INST. TUBERIA PVC C-10 1" m 8.00 3.69 29.52 29.52 29.52 0.00
04.10.01 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC PARA CAPTAC u 2.00 184.07 368.14 368.14 368.14 0.00
04.11.01 SUMINISTRO E INSTALACION VALVULA COMPUERTA 1" u 1.00 15.64 15.64 15.64 15.64 0.00
04.12.01 TRAZO NIVELACION Y REPLANTEO m2 14.40 1.24 17.86 17.86 17.86 0.00
04.12.02 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 9.00 35.35 318.15 318.15 318.15 0.00
04.12.03 CONCRETO f'c=100 kg/cm2 (CERCO DE SEGURIDAD) m3 9.00 276.20 2,485.80 2,485.80 2,485.80 0.00
04.12.04 ANCLAJE DE ACERO CORRUGADO Fy=4200 KG/CM2 CON PLANCHA D u 10.00 40.86 408.60 408.60 408.60 0.00
04.12.05 CERCO DE TUBO NEGRO Y MALLA OLIMPICA m2 58.80 77.75 4,571.70 4,571.70 4,571.70 0.00
05.01.01 LIMPIEZA DE TERRENO MANUAL m2 245.68 1.76 432.40 432.40 432.40 0.00
05.01.02 TRAZO NIVELACION Y REPLANTEO m2 245.68 1.24 304.64 304.64 304.64 0.00
05.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 68.79 35.35 2,431.73 2,431.73 2,431.73 0.00
05.02.02 EXCAVACION MANUAL EN ROCA SUELTA m3 29.48 102.10 3,009.91 3,009.91 3,009.91 0.00
05.02.03 CAMA DE TIERRA ZARANDEADA E=0.10M. ZANJA P/TUBO m 307.10 1.09 334.74 334.74 334.74 0.00
05.02.04 RELLENO Y COMPACTADO ZANJA CON MATERIAL SELECCIONADO EN m3 36.85 35.93 1,324.02 1,324.02 1,324.02 0.00
05.02.05 RELLENO Y COMPACTADO ZANJA CON MATERIAL PROPIO SELECCI m3 49.14 34.91 1,715.48 1,715.48 1,715.48 0.00
05.02.06 ELIMINACION DE MATERIAL EXCEDENTE 50 M m3 17.04 46.34 789.63 789.63 789.63 0.00
05.03.01 SUM. E INST. TUBERIA PVC C-10 2" m 219.25 6.59 1,444.86 1,444.86 1,444.86 0.00
05.03.02 SUM. E INST. TUBERIA PVC C-10 1" m 87.85 3.69 324.17 324.17 324.17 0.00
05.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC u 1.00 88.71 88.71 88.71 88.71 0.00
05.05.01 PRUEBA HIDRAULICA + DESINFECCION DE TUB. ZANJA TAPADA m 307.10 0.76 233.40 233.40 233.40 0.00
06.01.01 LIMPIEZA DE TERRENO MANUAL m2 16.00 1.76 28.16 28.16 28.16 0.00
06.01.02 TRAZO NIVELACION Y REPLANTEO m2 16.00 1.24 19.84 19.84 19.84 0.00
06.02.01 EXCAVACION DE ZANJA EN MATERIAL CONGLOMERADO m3 9.60 36.04 345.98 345.98 345.98 0.00
06.02.02 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 11.52 45.45 523.58 523.58 523.58 0.00
06.03.01 CONCRETO f'c= 140 kg/cm2 PARA DADOS m3 1.60 328.34 525.34 525.34 525.34 0.00
06.04.01 CONCRETO F'C=210 KG/CM2 P/ PISO m3 4.32 383.82 1,658.10 1,658.10 1,658.10 0.00
06.04.02 ENCOFRADO Y DESENCOFRADO P/PISO m2 4.80 53.87 258.58 258.58 258.58 0.00
06.04.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 97.21 4.60 447.17 447.17 447.17 0.00
06.04.04 CONCRETO F'C=210 KG/CM2 P/MUROS REFORZADO m3 6.26 425.94 2,666.38 1,916.46 1,916.46 749.92 749.92 0.00
06.04.05 ENCOFRADO Y DESENCOFRADO P/MURO REFORZADO m2 62.56 53.87 3,370.11 2,422.27 2,422.27 947.84 947.84 0.00
06.04.06 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 857.62 4.60 3,945.05 3,057.41 3,057.41 887.64 887.64 0.00
06.04.07 CONCRETO F'C=210 KG/CM2 P/TECHO m3 1.44 457.15 658.30 192.00 192.00 466.30 466.30 0.00
06.04.08 ENCOFRADO Y DESENCOFRADO P/TECHO m2 13.68 54.80 749.66 218.65 218.65 531.01 531.01 0.00
06.04.09 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 115.58 4.60 531.67 249.22 249.22 282.45 282.45 0.00
06.05.03 TARRAJEO CON IMPERMEABILIZANTES EN INTERIORES m2 39.68 29.90 1,186.43 1,186.43 1186.43 0.00
06.06.01 ESCALIN DE FIERRO CORRUGADO 3/4" (MOVIBLE) u 7.00 10.78 75.46 75.46 75.46 0.00
06.06.02 TAPA METALICA TIPO T-1 SEGUN DISEÑO u 1.00 364.86 364.86 364.86 364.86 0.00
06.06.03 VENTILACION C/TUBERIA DE ACERO S/DISEÑO DE 2" u 1.00 43.15 43.15 43.15 43.15 0.00
06.07.01 PINTURA DE MURO EXTERIOR C/LATEX VINILICO m2 50.84 14.10 716.84 716.84 716.84 0.00
06.08.01 PRUEBA HIDRAULICA CON EMPLEO DE LINEA DE INGRESO m3 20.00 0.90 18.00 18.00 18.00 0.00
06.08.02 DESINFECCION DE RESERVORIO CON EMPLEO DE LINEA DE INGRES m3 20.00 3.81 76.20 76.20 76.20 0.00
06.08.03 EVACUACION DEL AGUA DE PRUEBA CON EMPLEO DE LINEA DE SALI m3 20.00 0.65 13.00 13.00 13.00 0.00
06.09 CERCO DE SEGURIDAD 7,802.11
06.09.01 TRAZO NIVELACION Y REPLANTEO m2 14.40 1.24 17.86 17.86 17.86 0.00
06.09.02 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 9.00 35.35 318.15 318.15 318.15 0.00
06.09.03 CONCRETO f'c=100 kg/cm2 (CERCO DE SEGURIDAD) m3 9.00 276.20 2,485.80 2485.80 2485.80 0.00
06.09.04 ANCLAJE DE ACERO CORRUGADO Fy=4200 KG/CM2 CON PLANCHA D u 10.00 40.86 408.60 408.60 408.60 0.00
06.09.05 CERCO DE TUBO NEGRO Y MALLA OLIMPICA m2 58.80 77.75 4,571.70 4571.70 4571.70 0.00
07.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.68 1.76 2.96 2.96 2.96 0.00
07.01.02 TRAZO NIVELACION Y REPLANTEO m2 1.68 1.24 2.08 2.08 2.08 0.00
07.02.01 EXCAVACION DE ZANJA EN MATERIAL CONGLOMERADO m3 0.34 36.04 12.25 12.25 12.25 0.00
07.02.02 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 1.64 45.45 74.54 74.54 74.54 0.00
07.03.01 CONCRETO f'c= 140 kg/cm2 PARA DADOS m3 0.15 328.34 49.25 49.25 49.25 0.00
07.04.01 CONCRETO F'C=210 KG/CM2 P/MUROS REFORZADO m3 0.32 425.94 136.30 136.30 136.30 0.00
07.04.02 ENCOFRADO Y DESENCOFRADO P/MURO REFORZADO m2 6.40 53.87 344.77 344.77 344.77 0.00
07.04.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 12.45 4.60 57.27 57.27 57.27 0.00
07.04.04 CONCRETO F'C=210 KG/CM2 P/TECHO m3 0.33 457.15 150.86 150.86 150.86 0.00
07.04.05 ENCOFRADO Y DESENCOFRADO P/TECHO m2 2.29 54.80 125.49 125.49 125.49 0.00
07.04.06 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 9.85 4.60 45.31 45.31 45.31 0.00
07.06.01 REVESTIMIENTO DE PIEDRA ASENTADA EN CONCRETO F'C=100Kg/cm m2 0.50 74.87 37.44 37.44 37.44 0.00
07.07.01 TAPA METALICA TIPO T-1 SEGUN DISEÑO u 1.00 364.86 364.86 364.86 364.86 0.00
07.08.01 PINTURA DE MURO EXTERIOR C/LATEX VINILICO m2 5.34 14.10 75.29 75.29 75.29 0.00
07.09.01 HIPOCLORADOR DE FLUJO DIFUSION u 1.00 71.25 71.25 71.25 71.25 0.00
07.10.01 SUM. E INST. TUBERIA PVC C-10 4" INC. PRUEBA m 10.00 14.31 143.10 143.10 143.10 0.00
07.10.02 SUM. E INST. TUBERIA PVC C-10 2" m 8.00 6.59 52.72 52.72 52.72 0.00
07.11.01 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC u 1.00 347.16 347.16 347.16 347.16 0.00
07.12.01 SUMINISTRO E INSTALACION VALVULA COMPUERTA 2" u 3.00 36.67 110.01 110.01 110.01 0.00
07.12.02 SUMINISTRO E INSTALACION VALVULA COMPUERTA 4" u 1.00 147.76 147.76 147.76 147.76 0.00
08.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,272.02 1.76 2,238.76 2238.76 2238.76 0.00
08.01.02 TRAZO NIVELACION Y REPLANTEO m2 1,272.02 1.24 1,577.30 1577.30 1577.30 0.00
08.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 712.33 35.35 25,180.87 25180.87 25180.87 0.00
08.02.02 EXCAVACION MANUAL EN ROCA SUELTA m3 305.28 102.10 31,169.09 31169.09 31169.09 0.00
08.02.03 CAMA DE TIERRA ZARANDEADA E=0.10M. ZANJA P/TUBO m 3,180.05 1.09 3,466.25 3466.25 3466.25 0.00
08.02.04 RELLENO Y COMPACTADO ZANJA CON MATERIAL SELECCIONADO EN m3 374.69 35.93 13,462.61 13462.61 13462.61 0.00
08.02.05 RELLENO Y COMPACTADO ZANJA CON MATERIAL PROPIO SELECCI m3 508.81 34.91 17,762.56 17762.56 17762.56 0.00
08.02.06 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 147.98 45.45 6,725.69 6725.69 6725.69 0.00
08.03.01 SUM. E INST. TUBERIA PVC C-10 2 1/2" INC. PRUEBA m 413.79 7.95 3,289.63 3289.63 3289.63 0.00
08.03.02 SUM. E INST. TUBERIA PVC C-10 2" m 501.69 6.59 3,306.14 3306.14 3306.14 0.00
08.03.03 SUM. E INST. TUBERIA PVC C-10 1 1/2" INC. PRUEBA m 579.88 4.18 2,423.90 2423.90 2423.90 0.00
08.03.04 SUM. E INST. TUBERIA PVC C-10 1" m 1,126.66 3.69 4,157.38 4157.38 4157.38 0.00
08.03.05 SUM. E INST. TUBERIA PVC C-10 3/4" INC. PRUEBA m 556.00 2.28 1,267.68 1267.68 1267.68 0.00
08.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC PARA REDES u 1.00 3,051.94 3,051.94 3051.94 3051.94 0.00
08.05.01 PRUEBA HIDRAULICA + DESINFECCION DE TUB. ZANJA TAPADA m 3,180.05 0.76 2,416.84 2316.14 2416.84 100.70 0.00
09.01.01 TRAZO NIVELACION Y REPLANTEO m2 6.60 1.24 8.18 8.18 8.18 0.00
09.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 5.22 35.35 184.53 86.50 184.53 98.03 0.00
09.02.02 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 6.79 45.45 308.61 308.61 308.61 0.00
09.03.01 CONCRETO f'c= 140 kg/cm2 PARA SOLADOS Y/O DADOS m3 0.05 328.34 16.42 16.42 16.42 0.00
09.04.01 CONCRETO ARMADO f'c=175 kg/cm2. m3 4.10 421.42 1,727.82 1727.82 1727.82 0.00
09.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 45.28 47.59 2,154.88 2154.88 2154.88 0.00
09.04.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 131.92 4.60 606.83 606.83 606.83 0.00
09.05.03 TARRAJEO CON IMPERMEABILIZANTES EN INTERIORES m2 13.92 29.90 416.21 416.21 416.21 0.00
09.06.01 REVESTIMIENTO DE PIEDRA ASENTADA EN CONCRETO F'C=100Kg/cm m2 2.00 74.87 149.74 149.74 149.74 0.00
09.07.01 PINTURA DE MURO EXTERIOR C/LATEX VINILICO m2 28.52 14.10 402.13 402.13 402.13 0.00
09.08.01 TAPA METALICA 0.40X0.40 M SEGUN DISEÑO u 4.00 145.03 580.12 580.12 580.12 0.00
09.08.02 TAPA METALICA 0.60X0.60 M SEGUN DISEÑO u 4.00 172.72 690.88 690.88 690.88 0.00
09.08.03 VENTILACION C/TUBERIA DE Fo Go S/DISEÑO DE 2" u 4.00 43.88 175.52 175.52 175.52 0.00
09.09.01 SUM. E INST. TUBERIA PVC C-7.5 2" INC. PRUEBA m 40.00 5.97 238.80 238.80 238.80 0.00
09.09.02 SUM. E INST. TUBERIA PVC C-10 2 1/2" INC. PRUEBA m 4.00 7.95 31.80 31.80 31.80 0.00
09.09.03 SUM. E INST. TUBERIA PVC C-10 2" m 4.00 6.59 26.36 26.36 26.36 0.00
09.09.04 SUM. E INST. TUBERIA PVC C-10 1 1/2" INC. PRUEBA m 4.00 4.18 16.72 16.72 16.72 0.00
09.09.05 SUM. E INST. TUBERIA PVC C-10 1" m 4.00 3.69 14.76 14.76 14.76 0.00
09.10.01 SUMINISTRO E INSTALACION DE ACCESORIOS DE PVC PARA CRP-7.. u 1.00 4,170.19 4,170.19 4170.19 4170.19 0.00
09.11.01 SUMINISTRO E INSTALACION VALVULA COMPUERTA 2 1/2" u 1.00 40.32 40.32 40.32 40.32 0.00
09.11.02 SUMINISTRO E INSTALACION VALVULA FLOTADOR 2 1/2" u 1.00 71.01 71.01 71.01 71.01 0.00
09.11.03 SUMINISTRO E INSTALACION VALVULA COMPUERTA 2" u 1.00 36.67 36.67 36.67 36.67 0.00
09.11.04 SUMINISTRO E INSTALACION VALVULA FLOTADOR 2" u 1.00 60.58 60.58 60.58 60.58 0.00
09.11.05 SUMINISTRO E INSTALACION VALVULA COMPUERTA 11/2" u 1.00 20.83 20.83 20.83 20.83 0.00
09.11.06 SUMINISTRO E INSTALACION VALVULA FLOTADOR 11/2" u 1.00 37.78 37.78 37.78 37.78 0.00
09.11.07 SUMINISTRO E INSTALACION VALVULA COMPUERTA 1" u 1.00 15.64 15.64 15.64 15.64 0.00
09.11.08 SUMINISTRO E INSTALACION VALVULA FLOTADOR 1" u 1.00 36.97 36.97 36.97 36.97 0.00
10.01 CAMARA P/VALVULA DE PURGA EN MATRIZ (03 UND 1", 03 UND 1 1/2" Y 01 UND 3/4") 2,735.43
10.01.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 1.75 35.35 61.86 61.86 61.86 0.00
10.01.02 CONCRETO F'C=210 KG/CM2 m3 1.49 422.16 629.02 629.02 629.02 0.00
10.01.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 45.68 4.60 210.13 210.13 210.13 0.00
10.01.04 ENCOFRADO Y DESENCOFRADO NORMAL m2 22.40 47.59 1,066.02 1066.02 1066.02 0.00
10.01.05 SUM. E INST. DE TUBERIA Fo Go STAND. ISO-I 1 1/2" m 4.50 24.81 111.65 111.65 111.65 0.00
10.01.06 SUM. E INST. TUBERIA PVC C-10 1 1/2" INC. PRUEBA m 6.00 4.18 25.08 25.08 25.08 0.00
10.01.07 SUM. E INST. DE TUBERIA Fo Go STAND. ISO-I 1" m 4.50 12.91 58.10 58.10 58.10 0.00
10.01.08 SUM. E INST. TUBERIA PVC C-10 1" m 6.00 3.69 22.14 22.14 22.14 0.00
10.01.09 SUM. E INST. DE TUBERIA Fo Go STAND. ISO-I 3/4" m 4.50 10.93 49.19 49.19 49.19 0.00
10.01.10 SUM. E INST. TUBERIA PVC C-10 3/4" INC. PRUEBA m 6.00 2.28 13.68 13.68 13.68 0.00
10.01.11 SUMINISTRO E INSTALACION VALVULA COMPUERTA 11/2" u 3.00 20.83 62.49 62.49 62.49 0.00
10.01.12 SUMINISTRO E INSTALACION VALVULA COMPUERTA 3/4" u 3.00 12.62 37.86 37.86 37.86 0.00
10.01.13 SUMINISTRO E INSTALACION VALVULA COMPUERTA 1" u 1.00 15.64 15.64 15.64 15.64 0.00
10.01.14 SUMINISTRO E INSTALACION DE ACCESORIOS u 1.00 372.57 372.57 372.57 372.57 0.00
10.02 CAMARA P/VALVULA DE CONTROL EN MATRIZ (02 UND 1 1/2", 01 UND 1") 1,699.75
10.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 0.75 35.35 26.51 26.51 26.51 0.00
10.02.02 CONCRETO F'C=210 KG/CM2 m3 0.53 422.16 223.74 223.74 223.74 0.00
10.02.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 18.45 4.60 84.87 84.87 84.87 0.00
10.02.04 ENCOFRADO Y DESENCOFRADO NORMAL m2 19.20 47.59 913.73 913.73 913.73 0.00
10.02.05 SUMINISTRO E INSTALACION DE ACCESORIOS u 1.00 372.57 372.57 372.57 372.57 0.00
10.02.06 SUMINISTRO E INSTALACION VALVULA COMPUERTA 11/2" u 2.00 20.83 41.66 41.66 41.66 0.00
10.02.07 SUMINISTRO E INSTALACION VALVULA COMPUERTA 2" u 1.00 36.67 36.67 36.67 36.67 0.00
11.01 TRAZO NIVELACION Y REPLANTEO m 1,080.00 0.76 820.80 820.80 820.80 0.00
11.02 EXCAVACION MANUAL DE ZANJA m 1,080.00 7.27 7,851.60 7851.60 7851.60 0.00
11.03 CAMA DE TIERRA ZARANDEADA E=0.10M. ZANJA P/TUBO m 1,080.00 1.09 1,177.20 1177.20 1177.20 0.00
11.04 SUM. E INST. TUBERIA PVC C-10 1/2" INC. PRUEBA m 1,080.00 1.82 1,965.60 1965.60 1965.60 0.00
11.05 RELLENO Y COMPACTADO ZANJA CON MATERIAL SELECCIONADO EN C m3 172.80 35.93 6,208.70 6208.70 6208.70 0.00
11.06 RELLENO Y COMPACTADO ZANJA CON MATERIAL PROPIO SELECCIO m3 86.40 34.91 3,016.22 3016.22 3016.22 0.00
11.07 ELIMINACION DE MATERIAL EXCEDENTE EN CARRETILLA (50.00M) m3 172.80 75.75 13,089.60 13089.60 13089.60 0.00
11.08 CONEXIONES DOMICILIARIAS DE R.D. Ø 2 1/2" u 8.00 97.92 783.36 783.36 783.36 0.00
11.09 CONEXIONES DOMICILIARIAS DE R.D. Ø 2 " u 21.00 87.41 1,835.61 1835.61 1835.61 0.00
11.10 CONEXIONES DOMICILIARIAS DE R.D. Ø 1 1/2 " u 27.00 80.80 2,181.60 2181.60 2181.60 0.00
11.11 CONEXIONES DOMICILIARIAS DE R.D. Ø 1" u 39.00 76.52 2,984.28 2984.28 2984.28 0.00
11.12 CONEXIONES DOMICILIARIAS DE R.D. Ø 3/4" u 13.00 70.28 913.64 913.64 913.64 0.00
12.01.01 DIFUSION RADIAL glb 5.00 211.86 1,059.30 1059.30 1059.30 0.00
12.01.02 PERIFONEO Y VOLANTEO glb 5.00 320.44 1,602.20 1602.20 1602.20 0.00
12.02 POZO DE BASURA (03 Und.) 405.03
12.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 3.00 35.35 106.05 106.05 106.05 0.00
12.02.03 CLAUSURA MANUAL DE FOSA DE BASURA m3 3.00 39.30 117.90 117.90 117.90 0.00
12.03.01 EXCAVACION MANUAL PARA HOYO m3 34.00 26.51 901.34 901.34 901.34 0.00
12.04.03 MANTENIMIENTO DE SIEMBRA mes 1.00 1,700.00 1,700.00 1700.00 1700.00 0.00
13 CAPACITACION 17,752.25
13.01.01.01 ELABORACION Y REPRODUCCION DEL MATERIAL DE CAPACITACIO glb 1.00 3,237.28 3,237.28 3237.28 0.00 3237.28
13.01.02 EJECUCION DE LA CAPACITACION 2,945.88
13.01.02.01 CAPACITACION EN EDUCACION SANITARIA glb 1.00 2,945.88 2,945.88 2945.88 0.00 2945.88
13.01.03 CONSTITUCION Y REGISTRO DE LA UNIDAD DE GESTION SANITARIA (UGS) 5,385.93
13.01.03.01.0 CONSTITUCION Y REGISTRO DE LA UGS glb 1.00 2,118.64 2,118.64 2118.64 0.00 2118.64
13.01.03.02 IMPLEMENTACION DE LA UGS 3,267.29
13.01.03.02.0 IMPLEMENTACION DE LA UGS glb 1.00 3,267.29 3,267.29 3267.29 0.00 3267.29
13.02 CAPACITACION DE LA UGS 6,183.16
13.02.01.01 ELABORACION Y REPRODUCCION DEL MATERIAL DE CAPACITACIO glb 1.00 3,237.28 3,237.28 3237.28 0.00 3237.28
13.02.02 EJECUCION DE LA CAPACITACION 2,945.88
13.02.02.01 CAPACITACION DE LA UGS glb 1.00 2,945.88 2,945.88 2945.88 0.00 2945.88
14 FLETE 31,875.28
14.01 FLETE TERRESTRE glb 1.00 7,061.20 7,061.20 7061.20 7061.20 0.00
14.02 FLETE RURAL glb 1.00 24,814.08 24,814.08 20,000.00 24814.08 4814.08 0.00
S/. 331,272.54 76,877.56 100,004.85 164,534.01 154,511.68 89,860.97 59,003.76 0.00 17,752.25
COSTO DIRECTO
% 100.00% 23.21% 30.19% 49.67% 46.64% 27.13% 17.81% 0.00% 5.36%
ACUMULADO PROGRAMADO 23.21% 72.87% 100.00% 100.00%
ACUMULADO EJECUTADO 30.19% 76.83% 94.64% 100.00%
CURVA "S"
12
AVANCE DE OBRA (%)
10
0
0 2 4 6 8 10 12
TIEMPO (MES)
EXPERIENCIA EN OBRAS EN GENERAL
PROYECTO: "VIVIENDAS SALUDABLES PARA EL SECTOR AYASH PICHIU, DISTRITO DE HUACHIS PROVINCIA DE HUARI, REGION ANCASH"
NOMBRE
FECHA FECHA DE LA % DE
NOMBRE DEL PROYECTO DESCRIPCION DETALLADA DEL PROYECTO UBICACIÓN NOMBRE DEL CLIENTE
INICIO TERMINO EMPRESA PARTICIPACION
ASOCIADA
MUNICIPALIDAD
CONSTRUCCION DE AULAS CONSTRUCCION DE 03 AULAS, ZONA DE SUPE
DISTRITAL DE SUPE 11/27/2006 12/31/2006 100%
PRONOEI DE LLAMAHUACA RECREACION PUEBLO
PUERTO
EXPERIENCIA EN OBRAS EN GENERAL
PROYECTO: "VIVIENDAS SALUDABLES PARA EL SECTOR AYASH PICHIU, DISTRITO DE HUACHIS PROVINCIA DE HUARI, REGION ANCASH"
NOMBRE
FECHA FECHA DE LA % DE
NOMBRE DEL PROYECTO DESCRIPCION DETALLADA DEL PROYECTO UBICACIÓN NOMBRE DEL CLIENTE
INICIO TERMINO EMPRESA PARTICIPACION
ASOCIADA
Proyecto : "VIVIENDAS SALUDABLES PARA EL SECTOR AYASH PICHIU, DISTRITO DE HUACHIS PROVINCIA DE HUARI, REGION ANCASH"
NOMBRE DE
NOMBRE DEL FECHA % DE
NOMBRE DEL PROYECTO DESCRIPCION DETALLADA DEL PROYECTO UBICACIÓN FECHA INICIO LA EMPRESA OBSERVACION
CLIENTE TERMINO PARTICIPACION
ASOCIADA
MUNICIPALIDAD
CONSTRUCCION DE AULAS CONSTRUCCION DE 03 AULAS, ZONA DE
SUPE PUEBLO DISTRITAL DE 11/27/2006 12/31/2006 100% CULMINADO
PRONOEI DE LLAMAHUACA RECREACION
SUPE PUERTO
MUNICIPALIDAD
CONSTRUCCION DE PRONOEI DE CONSTRUCCION DE 02 AULAS Y LOSA
SUPE PUEBLO DISTRITAL DE 12/4/2006 12/31/2006 100% CULMINADO
LIMAC SUPE DEPORTIVA
SUPE PUEBLO
FORMATO N° 01
Proyecto:
"VIVIENDAS SALUDABLES PARA EL SECTOR AYASH PICHIU, DISTRITO DE HUACHIS PROVINCIA DE HUARI, REGION ANCASH"
Su funcion es de manejo del personal de obra, en coordinacion con el Ing. Residente para
6 MAESTRO DE OBRA JACINTO VARGAS RAMIREZ cumplir las metas y objetivos del proyecto, cumpliendo los planos y dentro del marco de
las Especificaciones Tecnicas
Presupuesto
VIVIENDAS SALUDABLES PARA EL SECTOR AYASH PICHIU
1 MIRAS Y JALONES U 4
2 NIVEL TOPOGRAFICO U 1
3 WINCHA DE 5 MTRS. U 5
4 WINCHA DE 50 MTRS. U 2
5 ALQUILER DE ANDAMIO LAYHER U 2
ANALISIS DE COSTOS UNITARIOS -PARA EL PRESUPUESTO DE SEGURIDAD
1.1 Desarrollo deL Plan de seguridad y Salud en el Trabajo
Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. Tiempo(dias) Parcial S/.
Personal
Gerente hh 0.1 0.8 25 1 20.00
Prevencionista de Seguridad hh 0.2 1.6 12.50 3.00 60.00
Residente de Obra hh 0.2 1.6 16.67 3.00 80.00
Asistente Tecnico hh 0.5 4 12.50 3.00 150.00
Maestro de Obra hh 0.2 1.6 10.42 3.00 50.00
Asistente de Administracion y Logistica hh 0.5 4 8.33 3.00 100.00
Asistente de Prevencion de Riesgo hh 1 8 8.33 1.00 66.67
SUB TOTAL 526.67
Materiales
Utiles de Oficina Gbl 1 100 1.00 100
Reproduccion del Plan Gbl 1 100 1.00 100
SUB TOTAL 200
Equipos
Proyector Multimedia Gbl 0.2 1.6 20 1 32
SUB TOTAL 32
Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. Tiempo(mes) Parcial S/.
Mano de Obra
Gerente hh 0.1 0.8 25 1 20.00
Prevencionista de Seguridad hh 1 8 12.5 1 100.00
Asistente de Prevencion de Riesgo hh 1 8 8.33 1 66.67
SUB TOTAL 186.67
Materiales
Utiles de Oficina Gbl 1 200 1 200
Reproduccion del Plan Gbl 1 50 1 50
SUB TOTAL 250
Equipos
Proyector Multimedia Gbl 0.1 0.8 20 1 16
SUB TOTAL 16
Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. Coef. Incide Parcial S/.
Mano de Obra
RESIDENTE hh 0.1 0.8 16.67 0.5 6.67
Prevencionista de Seguridad hh 0.1 0.8 12.50 0.7 7.00
Asistente de Prevencion de Riesgo hh 0.1 0.8 8.33 1 6.67
Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. incid (mes) Parcial S/.
Personal
Jefe de Prevencion de Riesgos hh 0.1 0.8 12.50 1 10.00
Asistente de Seguridad hh 0.5 4 8.33 1 33.33
Capataz hh 0.1 0.8 13.6 1 10.88
SUB TOTAL 54.21
Materiales
Baranda de madera und 10 30 0.5 150
Acordamiento para limitacion und 2 50 1 100
Tapas de aberturas und 10 40 0.1 40
Lineas de vida horizontales und 5 100 0.2 100
Lineas de vida Verticales und 1 50 1 50
Puntos de Anclaje und 20 6 1 120
Sistema de mallas antiacidas und 500 0.5 0
Sistema de Entibados und 2 100 0.4 80
Sistema de Extraccion de aire und 0 500 0.2 0
Sistema de Bloqueo (Tarjeta, Candado) und 2 20 1 40
Interruptor Diferencial para Tablero und 2 20 1 40
Alarmas audibles und 0 200 1 0
Luces estroboscopicas en maquinaria pesada und 0 350 1 0
Andamios und 5 10 1 50
SUB TOTAL 770
Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. incid (mes) Parcial S/.
Personal
Jefe de Prevencion de Riesgos hh 0.1 0.8 12.50 0.2 2.00
Asistente de Seguridad hh 0.2 1.6 8.33 0.2 2.67
Capataz hh 0.5 4 8.33 0.2 6.67
Operario hh 1 8 13.6 0.2 21.76
SUB TOTAL 33.09
Materiales
Señales de advertencia und 10 30 0.3 90
Señales de prohibicion und 10 30 0.3 90
Señales de informacion und 10 30 0.3 90
Señales de obligacion und 10 30 0.3 90
Señales de lucha contra incendios und 10 20 0.1 20
Rotulos en areas de trabajo und 10 20 0.1 20
Señales en las instalaciones de la Obra und 10 20 0.1 20
Conos reflectivos und 10 20 0.1 20
Luces estroboscopicas en maquinaria pesada und 10 20 0.1 20
Alarmas audibles und 10 20 0.1 20
Señales de conservacion del ambiente und 10 30 0.1 30
SUB TOTAL 510
Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. incid (mes) Parcial S/.
Personal
Jefe de Prevencion de Riesgos hh 1 8 12.50 0.2 20.00
Asistente de Seguridad hh 1 8 8.33 0.2 13.33
chofer hh 1 8 10.60 0.2 16.96
Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. Incid(mes) Parcial S/.
Personal
Jefe de Prevencion de Riesgos hh 0.1 0.8 30.00 1 24.00
Asistente de Seguridad hh 0.1 0.8 15.00 1 12.00
Chofer hh 1 8 12.20 1 97.60
OBRA:
“VIVIENDAS SALUDABLES PARA EL SECTOR AYASH PICHIÚ"
COSTO DIRECTO DE OBRA S/. = 0.00
TIEMPO DE EJECUCION = 3 MESES
S/Mes (Programacion)
OE.1.2.1 ELABORACIÓN, IMPLEMENTACIÓN Y ADMINISTRACIÓN DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO (GLB) 1,661.47
TOTAL 19,726.79
TOTAL 1,044.52
Costo Unitario que incluye Flete desde Lima a Pichiu - Según el Expediente Tecnico S/. 1,044.52
Según el Expediente Tecnico Costo de la partida a Ejecutar sera= S/. 97,140.00
Por lo que actualizamos nuestra cotizacion según el Expediente Tecni und 93 980.00 S/. 91,140.00
NOTA: Al respecto según el Reglamento de Metrados CONSIDERA las seis (06) partidas, los cuales estan concordante y vinculado al Plan de
Seguridad en el Trabajo (PST) según NORMA G-050, representado en los Planes de Seguridad Industrial y Salud Ocupacional (PSST,EPP,
EPC, Señalizacion,Capacitaciones), Manejo Ambiental (capacitaciones, residuos solidos), Plan de Responsabilidad Social (Comunidades),
estos planes se han adjuntado por lo que nuestro compromiso organizacional es de cumplimiento de los Planes (PSST)
Asimismo se indica que cada Partida desde el 10.01,…….,10.06, se han calculado coherentemente, ajustandose a los Planes que se
adjuntan, con los costos unitarios que son relativamente variables, pero que son costos del Mercado
Para lo cual se adjunta el calculo de cada uno de las partidas.
Finalmente, lo Presupuesta en el Expediente Tecnico no es Completo según EL REGLAMENTO NACIONAL DE METRADOS y la NORMA
G-050 DE SEGURIDAD EN LA CONSTRUCCION.
por lo que aparentemente es incrementado, sin embargo no sobrepasa los niveles del Techo Presupuestal del
Expediente Tecnico