PRESUPUESTO DE OBRAS PROVISIONALES Y SITIO

Proyecto : COLEGIO JOSE RAZURI


Colegio : ARCC 2353 - LOCAL ESCOLAR 413944 Ubicación : CURA MORI - PIURA

ACUMULADO PRESENTE VALORIZACION ACUMULADO


SALDO POR VALORIZAR
ESTRUCTURA DE PRESUPUESTO SEMANA ANTERIOR ACTUAL

Item Descripción U. Metrado PU PARCIAL METRADO MONTO S/.% AVANCE METRADO MONTO S/.% AVANCE METRADO MONTO S/.% AVANCE METRADO MONTO S/. % AVANCE
01.02 ESTRUCTURAS EXTERIORES COMUNES
01.02.03 CONCRETO SIMPLE
01.02.03.01 FALSA ZAPATA
01.02.03.01.01 CONCRETO EN FALSA ZAPATAS, C:H=1:10+30% P.G., f'c=120 kg/cm2. TIPO I m3 247.89 S/62.20 15,418.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 247.89 15,418.94 100.00%
01.02.03.01.05 CURADO DE CONCRETO m2 70.11 S/0.70 49.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 70.11 49.08 100.00%
01.02.03.02 SOLADO - - - 100.00%
01.02.03.02.01 CONCRETO f'c=100 kg/cm2 EN SOLADOS, e=5cm. TIPO I m2 3,514.49 S/12.80 44,985.43 0.00 0.00 0.00% 932.50 11,936.02 26.53% 932.50 11,936.02 26.53% 2,581.99 33,049.42 73.47%
01.02.04 CONCRETO ARMADO - - - 100.00%
01.02.04.02 ZAPATAS - - - 100.00%
01.02.04.02.01 CONCRETO PREMEZCLADO EN ZAPATAS f'c=280 Kg/cm2. TIPO I m3 110.58 S/53.80 5,949.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 110.58 5,949.20 100.00%
01.02.04.02.03 ENCOFRADO NORMAL Y DESENCOFRADO EN ZAPATAS m2 209.76 S/33.70 7,068.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 209.76 7,068.91 100.00%
01.02.04.02.05 CURADO DE CONCRETO m2 394.06 S/0.70 275.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 394.06 275.84 100.00%
01.02.04.03 VIGAS DE CIMENTACION - - - 100.00%
01.02.04.03.01 CONCRETO PREMEZCLADO EN VIGAS DE CIMENTACIÓN f'c=280 kg/cm2. TIPO I m3 159.29 S/35.00 5,575.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 159.29 5,575.03 100.00%
01.02.04.03.05 ENCOFRADO NORMAL Y DESENCOFRADO DE VIGAS DE CIMENTACIÓN m2 1,061.94 S/33.70 35,787.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,061.94 35,787.33 100.00%
01.02.04.03.07 CURADO DE CONCRETO m2 1,061.94 S/0.70 743.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,061.94 743.36 100.00%
01.02.04.04 PLATEA DE CIMENTACION - - - 100.00%
01.02.04.04.01 CONCRETO PREMEZCLADO EN PLATEAS DE CIMENTACION f'c=280 kg/cm2. TIPO I m3 1,741.29 S/27.00 47,014.91 0.00 0.00 0.00% 62.53 1,688.31 3.59% 62.53 1,688.31 3.59% 1,678.76 45,326.60 96.41%
01.02.04.04.05 ENCOFRADO NORMAL Y DESENCOFRADO DE PLATEA DE CIMENTACION m2 943.75 S/33.70 31,804.34 0.00 0.00 0.00% 20.92 705.00 2.22% 20.92 705.00 2.22% 922.83 31,099.34 97.78%
01.02.04.04.07 CURADO DE CONCRETO m2 4,236.31 S/0.70 2,965.41 0.00 0.00 0.00% 156.33 109.43 3.69% 156.33 109.43 3.69% 4,079.98 2,855.99 96.31%
01.02.04.05 SOBRECIMIENTO REFORZADO - - - 100.00%
01.02.04.05.01 CONCRETO PREMEZCLADO EN SOBRECIMIENTOS REFORZADOS f'c=280 kg/cm2.TIPO I m3 176.04 S/42.00 7,393.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 176.04 7,393.47 100.00%
01.02.04.05.05 ENCOFRADO NORMAL Y DESENCOFRADO DE SOBRECIMIENTOS m2 1,239.51 S/33.70 41,771.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,239.51 41,771.57 100.00%
01.02.04.05.07 CURADO DE CONCRETO m2 1,239.51 S/0.70 867.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,239.51 867.66 100.00%
01.02.04.07 MUROS DE CONTENCION - - - 100.00%
01.02.04.07.01 ZAPATAS - - - 100.00%
01.02.04.07.01.01 CONCRETO PREMEZCLADO EN ZAPATAS f'c=280 Kg/cm2. TIPO I m3 62.66 S/35.00 2,193.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 62.66 2,193.17 100.00%
01.02.04.07.01.02 ENCOFRADO NORMAL Y DESENCOFRADO EN ZAPATAS m2 365.86 S/33.70 12,329.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 365.86 12,329.62 100.00%
01.02.04.07.01.04 CURADO DE CONCRETO m2 365.86 S/0.70 256.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 365.86 256.10 100.00%
01.02.04.09 GRADAS - - - 100.00%
01.02.04.09.01 CONCRETO PREMEZCLADO EN GRADAS f'c=175 kg/cm2. TIPO I m3 40.57 S/65.00 2,636.73 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 40.57 2,636.73 100.00%
01.02.04.09.04 ENCOFRADO NORMAL Y DESENCOFRADO DE GRADAS m2 68.58 S/33.70 2,311.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 68.58 2,311.16 100.00%
01.02.04.09.06 CURADO DE CONCRETO m2 68.58 S/0.70 48.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 68.58 48.01 100.00%
01.02.04.10 RAMPAS - - - 100.00%
01.02.04.10.01 CONCRETO PREMEZCLADO EN RAMPAS f'c=175 kg/cm2. TIPO I m3 25.30 S/72.00 1,821.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 25.30 1,821.49 100.00%
01.02.04.10.04 ENCOFRADO NORMAL Y DESENCOFRADO EN RAMPAS m2 3.79 S/33.70 127.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.79 127.74 100.00%
01.02.04.10.06 CURADO DE CONCRETO m2 157.99 S/0.70 110.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 157.99 110.59 100.00%
01.07 CISTERNA Y TANQUE ELEVADO - - - 100.00%
01.07.01 ESTRUCTURAS CISTERNA Y TANQUE ELEVADO - - - 100.00%
01.07.01.02 CONCRETO SIMPLE CISTERNA Y TANQUE ELEVADO - - - 100.00%
01.07.01.02.01 CONCRETO f'c=100 kg/cm2 EN SOLADOS, e=5cm. TIPO I m2 89.76 S/12.00 1,077.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 89.76 1,077.07 100.00%
01.07.01.03 CONCRETO ARMADO CISTERNA Y TANQUE ELEVADO - - - 100.00%
01.07.01.03.01 CONCRETO ARMADO EN CISTERNA - - - 100.00%
01.07.01.03.01.01 PLATEA DE CIMENTACION - - - 100.00%
01.07.01.03.01.01.01 CONCRETO PREMEZCLADO EN PLATEAS DE CIMENTACION f'c =280 kg/cm2. TIPO I m3 89.76 S/35.00 3,141.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 89.76 3,141.46 100.00%
01.07.01.03.01.01.04 ENCOFRADO NORMAL Y DESENCOFRADO DE PLATEA DE CIMENTACION m2 26.29 S/33.70 885.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.29 885.86 100.00%
01.07.01.03.01.01.06 CURADO DE CONCRETO m2 116.04 S/0.70 81.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 116.04 81.23 100.00%
01.07.01.03.01.02 LOSA FONDO DE CISTERNA - - - 100.00%
01.07.01.03.01.02.01 CONCRETO PREMEZCLADO EN LOSAS MACIZAS f'c=280 kg/cm2 (h= var). TIPO I m3 2.41 S/53.80 129.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.41 129.82 100.00%
01.07.01.03.01.02.04 ENCOFRADO NORMAL Y DESENCOFRADO EN LOSA DE FONDO DE CISTERNA m2 0.76 S/33.70 25.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.76 25.61 100.00%
01.07.01.03.01.02.06 CURADO DE CONCRETO m2 9.66 S/0.70 6.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.66 6.76 100.00%
01.07.01.03.01.03 MUROS DE CISTERNA - - - 100.00%
01.07.01.03.01.03.01 CONCRETO PREMEZCLADO EN MUROS Y PANTALLAS f'c=280 kg/cm2. TIPO I m3 17.74 S/43.00 762.67 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.74 762.67 100.00%
01.07.01.03.01.03.04 ENCOFRADO NORMAL Y DESENCOFRADO DE MUROS Y PANTALLAS m2 118.98 S/42.00 4,997.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 118.98 4,997.08 100.00%
01.07.01.03.01.03.06 CURADO DE CONCRETO m2 118.98 S/0.70 83.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 118.98 83.28 100.00%
01.07.01.03.01.04 VIGAS - LOSA MACIZA DE CISTERNA - - - 100.00%
PRESUPUESTO DE OBRAS PROVISIONALES Y SITIO

Proyecto : COLEGIO JOSE RAZURI


Colegio : ARCC 2353 - LOCAL ESCOLAR 413944 Ubicación : CURA MORI - PIURA

ACUMULADO PRESENTE VALORIZACION ACUMULADO


SALDO POR VALORIZAR
ESTRUCTURA DE PRESUPUESTO SEMANA ANTERIOR ACTUAL

Item Descripción U. Metrado PU PARCIAL METRADO MONTO S/.% AVANCE METRADO MONTO S/.% AVANCE METRADO MONTO S/.% AVANCE METRADO MONTO S/. % AVANCE
01.07.01.03.01.04.01 CONCRETO PREMEZCLADO EN VIGAS f'c=280 kg/cm2. TIPO I m3 5.23 S/53.80 281.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.23 281.62 100.00%
01.07.01.03.01.04.04 ENCOFRADO NORMAL Y DESENCOFRADO DE VIGAS m2 26.16 S/58.00 1,517.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.16 1,517.45 100.00%
01.07.01.03.01.04.06 CURADO DE CONCRETO m2 26.16 S/0.70 18.31 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.16 18.31 100.00%
01.07.01.03.01.05 LOSA MACIZA - - - 100.00%
01.07.01.03.01.05.01 CONCRETO PREMEZCLADO EN LOSAS MACIZAS f'c=280 kg/cm2 (h= var). TIPO I m3 3.13 S/53.80 168.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.13 168.15 100.00%
01.07.01.03.01.05.04 ENCOFRADO NORMAL Y DESENCOFRADO DE LOSAS MACIZAS m2 20.84 S/33.70 702.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.84 702.41 100.00%
01.07.01.03.01.05.06 CURADO DE CONCRETO m2 20.84 S/0.70 14.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.84 14.59 100.00%
01.07.01.03.02 CONCRETO ARMADO EN SOPORTE DE TANQUE ELEVADO - - - 100.00%
01.07.01.03.02.01 COLUMNAS - - - 100.00%
01.07.01.03.02.01.01 CONCRETO PREMEZCLADO EN COLUMNAS f'c=280 kg/cm2. TIPO I m3 45.96 S/68.00 3,125.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 45.96 3,125.35 100.00%
01.07.01.03.02.01.04 ENCOFRADO NORMAL Y DESENCOFRADO DE COLUMNAS M2 229.82 S/48.80 11,215.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 229.82 11,215.41 100.00%
01.07.01.03.02.01.06 CURADO DE CONCRETO VERTICALES m2 229.82 S/0.70 160.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 229.82 160.88 100.00%
01.07.01.03.02.02 VIGAS - - - 100.00%
01.07.01.03.02.02.01 CONCRETO PREMEZCLADO EN VIGAS f'c=280 kg/cm2. TIPO I m3 9.88 S/53.80 531.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.88 531.54 100.00%
01.07.01.03.02.02.04 ENCOFRADO NORMAL Y DESENCOFRADO DE VIGAS m2 48.64 S/58.00 2,821.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 48.64 2,821.12 100.00%
01.07.01.03.02.02.06 CURADO DE CONCRETO m2 48.64 S/0.70 34.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 48.64 34.05 100.00%
01.07.01.03.02.03 LOSAS MACIZAS - - - 100.00%
01.07.01.03.02.03.01 CONCRETO PREMEZCLADO EN LOSAS MACIZAS f'c=280 kg/cm2 (h= var). TIPO I m3 1.62 S/84.00 135.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.62 135.66 100.00%
01.07.01.03.02.03.04 ENCOFRADO NORMAL Y DESENCOFRADO DE LOSAS MACIZAS m2 8.08 S/33.70 272.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.08 272.13 100.00%
01.07.01.03.02.03.06 CURADO DE CONCRETO m2 8.08 S/0.70 5.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.08 5.65 100.00%
01.07.01.03.03 CONCRETO ARMADO EN TANQUE ELEVADO - - - 100.00%
01.07.01.03.03.01 VIGAS - LOSA MACIZA INFERIOR - - - 100.00%
01.07.01.03.03.01.01 CONCRETO PREMEZCLADO EN VIGAS f'c=280 kg/cm2. TIPO I m3 5.34 S/53.80 287.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.34 287.24 100.00%
01.07.01.03.03.01.04 ENCOFRADO NORMAL Y DESENCOFRADO DE VIGAS m2 35.56 S/58.00 2,062.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.56 2,062.39 100.00%
01.07.01.03.03.01.06 CURADO DE CONCRETO m2 35.56 S/0.70 24.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.56 24.89 100.00%
01.07.01.03.03.02 LOSA MACIZA INFERIOR - - - 100.00%
01.07.01.03.03.02.01 CONCRETO PREMEZCLADO EN LOSAS MACIZAS f'c=280 kg/cm2 (h= var). TIPO I m3 1.62 S/84.00 135.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.62 135.66 100.00%
01.07.01.03.03.02.04 ENCOFRADO NORMAL Y DESENCOFRADO DE LOSAS MACIZAS m2 8.08 S/33.70 272.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.08 272.13 100.00%
01.07.01.03.03.02.06 CURADO DE CONCRETO m2 8.08 S/0.70 5.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.08 5.65 100.00%
01.07.01.03.03.03 MUROS DE TANQUE ELEVADO - - - 100.00%
01.07.01.03.03.03.01 CONCRETO PREMEZCLADO EN MUROS Y PANTALLAS f'c=280 kg/cm2. TIPO I m3 7.48 S/53.80 402.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.48 402.24 100.00%
01.07.01.03.03.03.04 ENCOFRADO NORMAL Y DESENCOFRADO DE MUROS Y PANTALLAS M2 49.84 S/42.00 2,093.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.84 2,093.15 100.00%
01.07.01.03.03.03.06 CURADO DE CONCRETO VERTICALES m2 49.84 S/0.70 34.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.84 34.89 100.00%
01.07.01.03.03.04 LOSA MACIZA SUPERIOR - - - 100.00%
01.07.01.03.03.04.01 CONCRETO PREMEZCLADO EN LOSAS MACIZAS f'c=280 kg/cm2 (h= var). TIPO I m3 2.82 S/84.00 237.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.82 237.01 100.00%
01.07.01.03.03.04.04 ENCOFRADO NORMAL Y DESENCOFRADO DE LOSAS MACIZAS m2 14.10 S/33.70 475.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.10 475.10 100.00%
01.07.01.03.03.04.06 CURADO DE CONCRETO m2 14.10 S/0.70 9.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.10 9.87 100.00%
01.07.01.04 ESTRUCTURAS COMPLEMENTARIAS CISTERNA - TANQUE ELEVADO - - - 100.00%
01.07.01.04.01 CISTERNA - - - 100.00%
01.07.01.04.01.01 WATER STOP 10'' PVC ml 15.77 S/1.20 18.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.77 18.92 100.00%
01.07.01.04.02 TANQUE ELEVADO - - - 100.00%
01.07.01.04.02.01 WATER STOP 10'' PVC ml 12.54 S/1.20 15.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.54 15.05 100.00%
01.07.01.04.03 BASE PARA EQUIPOS - - - 100.00%
01.07.01.04.03.01 CONCRETO PREMEZCLADO f'c=210 kg/cm2. TIPO I m3 0.10 S/53.80 5.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.10 5.11 100.00%
01.07.01.04.03.02 ENCOFRADO NORMAL Y DESENCOFRADO EN BASE PARA EQUIPOS m2 2.66 S/58.00 154.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.66 154.28 100.00%
01.07.01.04.03.04 CURADO DE CONCRETO m2 2.66 S/0.70 1.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.66 1.86 100.00%
01.07.01.04.04 CAJAS RECEPTORA PARA REBOSE - - - 100.00%
01.07.01.04.04.01 CONCRETO PREMEZCLADO f'c=210 kg/cm2. TIPO I m3 0.10 S/53.80 5.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.10 5.62 100.00%
01.07.01.04.04.02 ENCOFRADO DE CAJA RECEPTORA EN CAJA RECEPTORA PARA REBOSE m2 0.87 S/58.00 50.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.87 50.69 100.00%
01.07.01.04.04.04 CURADO DE CONCRETO m2 0.87 S/0.70 0.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.87 0.61 100.00%
01.08 CERCO INTERIOR Y PERIMETRICO - - - 100.00%
01.08.01 ESTRUCTURAS CERCO - - - 100.00%
01.08.01.02 CONCRETO SIMPLE - - - 100.00%
01.08.01.02.01 SOLADO - - - 100.00%
01.08.01.02.01.01 CONCRETO f'c=100 kg/cm2 EN SOLADOS, e=5cm. TIPO I m2 261.38 S/12.00 3,136.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 261.38 3,136.60 100.00%
01.08.01.03 CONCRETO ARMADO - - - 100.00%
PRESUPUESTO DE OBRAS PROVISIONALES Y SITIO

Proyecto : COLEGIO JOSE RAZURI


Colegio : ARCC 2353 - LOCAL ESCOLAR 413944 Ubicación : CURA MORI - PIURA

ACUMULADO PRESENTE VALORIZACION ACUMULADO


SALDO POR VALORIZAR
ESTRUCTURA DE PRESUPUESTO SEMANA ANTERIOR ACTUAL

Item Descripción U. Metrado PU PARCIAL METRADO MONTO S/.% AVANCE METRADO MONTO S/.% AVANCE METRADO MONTO S/.% AVANCE METRADO MONTO S/. % AVANCE
01.08.01.03.01 ZAPATAS - - - 100.00%
01.08.01.03.01.01 CONCRETO PREMEZCLADO EN ZAPATAS f'c=280 Kg/cm2. TIPO I m3 18.99 S/44.00 835.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.99 835.58 100.00%
01.08.01.03.01.05 ENCOFRADO NORMAL Y DESENCOFRADO EN ZAPATAS m2 85.73 S/33.70 2,889.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 85.73 2,889.03 100.00%
01.08.01.03.01.07 CURADO DE CONCRETO m2 120.23 S/0.70 84.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 120.23 84.16 100.00%
01.08.01.03.02 MUROS REFORZADOS - - - 100.00%
01.08.01.03.02.01 ZAPATAS CORRIDAS - - - 100.00%
01.08.01.03.02.01.01 CONCRETO PREMEZCLADO EN ZAPATAS f'c=280 Kg/cm2. TIPO I m3 160.81 S/44.00 7,075.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 160.81 7,075.49 100.00%
01.08.01.03.02.01.05 ENCOFRADO NORMAL Y DESENCOFRADO EN ZAPATAS m2 280.03 S/33.70 9,437.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 280.03 9,437.06 100.00%
01.08.01.03.02.01.07 CURADO DE CONCRETO m2 509.76 S/0.70 356.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 509.76 356.83 100.00%
01.08.01.03.02.02 PANTALLA - - - 100.00%
01.08.01.03.02.02.01 CONCRETO PREMEZCLADO EN MUROS Y PANTALLAS f'c=280 kg/cm2. TIPO I m3 100.02 S/44.00 4,400.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 100.02 4,400.70 100.00%
01.08.01.03.02.02.05 ENCOFRADO CARAVISTA Y DESENCOFRADO DE MUROS Y PANTALLAS m2 800.09 S/33.70 26,963.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 800.09 26,963.03 100.00%
01.08.01.03.02.02.07 CURADO DE CONCRETO VERTICALES m2 800.09 S/0.70 560.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 800.09 560.06 100.00%
01.08.01.03.04 PEDESTALES - - - - 100.00%
01.08.01.03.04.01 CONCRETO PREMEZCLADO EN PEDESTALES f'c=280 kg/cm2. TIPO I m3 8.21 S/53.80 441.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.21 441.59 100.00%
01.08.01.03.04.05 ENCOFRADO NORMAL Y DESENCOFRADO DE PEDESTALES m2 56.79 S/33.70 1,913.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 56.79 1,913.86 100.00%
01.08.01.03.04.07 CURADO DE CONCRETO m2 56.79 S/0.70 39.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 56.79 39.75 100.00%
02 ESTRUCTURAS - - 100.00%
02.03 CONCRETO SIMPLE - - 100.00%
02.03.03 FALSO PISO - - 100.00%
02.03.03.01 CONCRETO f'c=210 kg/cm2 EN FALSO PISO, e=0.10m. TIPO I m2 288.71 S/20.00 S/5,774.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 288.71 5,774.29 100.00%
02.03.03.04 ENCOFRADO NORMAL Y DESENCOFRADO EN LOSAS DE PISO m2 35.80 S/33.70 S/1,206.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.80 1,206.33 100.00%
02.03.03.05 CURADO DE CONCRETO m2 2,887.17 S/0.70 S/2,021.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,887.17 2,021.02 100.00%
02.04 CONCRETO ARMADO - - 100.00%
02.04.06 PLACAS - - 100.00%
02.04.06.01 CONCRETO PREMEZCLADO EN PLACAS f'c=280 kg/cm2. TIPO I m3 607.70 S/48.00 S/29,169.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 607.70 29,169.41 100.00%
02.04.06.05 ENCOFRADO NORMAL Y DESENCOFRADO DE PLACAS m2 4,414.40 S/42.00 S/185,404.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4,414.40 185,404.93 100.00%
02.04.06.07 CURADO DE CONCRETO VERTICALES m2 4,414.40 S/0.70 S/3,090.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4,414.40 3,090.08 100.00%
02.04.07 COLUMNAS - - 100.00%
02.04.07.01 CONCRETO PREMEZCLADO EN COLUMNAS f'c=280 kg/cm2. TIPO I m3 398.06 S/70.00 S/27,864.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 398.06 27,864.17 100.00%
02.04.07.05 ENCOFRADO NORMAL Y DESENCOFRADO DE COLUMNAS M2 3,308.04 S/42.00 S/138,937.79 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,308.04 138,937.79 100.00%
02.04.07.07 CURADO DE CONCRETO VERTICALES m2 3,308.04 S/0.70 S/2,315.63 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,308.04 2,315.63 100.00%
02.04.08 VIGAS - - 100.00%
02.04.08.01 CONCRETO PREMEZCLADO EN VIGAS f'c=280 kg/cm2. TIPO I m3 595.79 S/43.00 S/25,619.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 595.79 25,619.08 100.00%
02.04.08.05 ENCOFRADO NORMAL Y DESENCOFRADO DE VIGAS m2 3,936.76 S/48.00 S/188,964.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,936.76 188,964.58 100.00%
02.04.08.07 CURADO DE CONCRETO m2 3,936.76 S/0.70 S/2,755.73 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,936.76 2,755.73 100.00%
02.04.09 VIGA CANAL - - 100.00%
02.04.09.01 CONCRETO PREMEZCLADO EN VIGA CANAL f'c=280 kg/cm2. TIPO I m3 52.31 S/48.00 S/2,510.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 52.31 2,510.74 100.00%
02.04.09.05 ENCOFRADO NORMAL Y DESENCOFRADO DE VIGA CANAL m2 562.25 S/48.00 S/26,987.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 562.25 26,987.90 100.00%
02.04.09.07 CURADO DE CONCRETO m2 562.25 S/0.70 S/393.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 562.25 393.57 100.00%
02.04.10 LOSAS MACIZAS - - 100.00%
02.04.10.01 CONCRETO PREMEZCLADO EN LOSAS MACIZAS f'c=280 kg/cm2 (h= var). TIPO I m3 113.52 S/70.00 S/7,946.09 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 113.52 7,946.09 100.00%
02.04.10.05 ENCOFRADO NORMAL Y DESENCOFRADO DE LOSAS MACIZAS m2 517.11 S/33.70 S/17,426.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 517.11 17,426.72 100.00%
02.04.10.07 CURADO DE CONCRETO m2 517.11 S/0.70 S/361.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 517.11 361.98 100.00%
02.04.11 LOSAS ALIGERADAS - - 100.00%
02.04.11.01 CONCRETO PREMEZCLADO EN LOSAS ALIGERADAS f'c=280 kg/cm2 (h=22 cm). TIPO I m3 340.60 S/70.00 S/23,842.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 340.60 23,842.25 100.00%
02.04.11.05 ENCOFRADO NORMAL Y DESENCOFRADO DE LOSAS ALIGERADAS m2 4,622.90 S/26.00 S/120,195.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4,622.90 120,195.39 100.00%
02.04.11.07 BOVEDILLA DE CONCRETO 0.40x0.20x0.15m und 30,835.10 S/1.45 S/44,710.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 30,835.10 44,710.90 100.00%
02.04.11.09 CURADO DE CONCRETO m2 4,622.90 S/0.70 S/3,236.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4,622.90 3,236.03 100.00%
02.04.12 LOSA CON PLACA COLABORANTE - PUENTES - - 100.00%
02.04.12.01 PLACA COLABORANTE e=0.15m, CALIBRE 22 m2 15.20 S/54.00 S/820.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.20 820.80 100.00%
02.04.12.02 CONCRETO PREMEZCLADO EN LOSAS COLABORANTES f'c=280 kg/cm2 TIPO I m3 1.29 S/84.00 S/108.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.29 108.53 100.00%
02.04.12.04 CURADO DE CONCRETO m2 15.20 S/0.70 S/10.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.20 10.64 100.00%
02.04.13 ESCALERAS - - 100.00%
02.04.13.01 CONCRETO PREMEZCLADO EN ESCALERAS f'c=280 kg/cm2. TIPO I m3 83.89 S/53.80 S/4,513.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 83.89 4,513.01 100.00%
02.04.13.04 ENCOFRADO NORMAL Y DESENCOFRADO EN ESCALERAS m2 353.44 S/33.70 S/11,910.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 353.44 11,910.86 100.00%
02.04.13.06 CURADO DE CONCRETO m2 353.44 S/0.70 S/247.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 353.44 247.41 100.00%
02.04.15 LOSAS DEPORTIVA - - 100.00%
PRESUPUESTO DE OBRAS PROVISIONALES Y SITIO

Proyecto : COLEGIO JOSE RAZURI


Colegio : ARCC 2353 - LOCAL ESCOLAR 413944 Ubicación : CURA MORI - PIURA

ACUMULADO PRESENTE VALORIZACION ACUMULADO


SALDO POR VALORIZAR
ESTRUCTURA DE PRESUPUESTO SEMANA ANTERIOR ACTUAL

Item Descripción U. Metrado PU PARCIAL METRADO MONTO S/.% AVANCE METRADO MONTO S/.% AVANCE METRADO MONTO S/.% AVANCE METRADO MONTO S/. % AVANCE
02.04.15.01 CONCRETO PREMEZCLADO EN LOSA DEPORTIVA, f'c=280 Kg/cm2. TIPO I m3 284.02 S/40.00 S/11,360.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 284.02 11,360.86 100.00%
02.04.15.04 CURADO DE CONCRETO m2 1,420.12 S/0.70 S/994.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,420.12 994.08 100.00%
02.06 COMPLEMENTARIAS - - 100.00%
02.06.01 LOSAS ALIGERADAS - - 100.00%
02.06.01 Viguetas prefabricadas ALITEC ML 9,896.25 S/2.30 S/22,761.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9,896.25 22,761.36 100.00%
02.06.03 ENCOFRADO Y DESENCONFRADO m2 179.55 S/33.70 S/6,050.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 179.55 6,050.84 100.00%
03 ACERO - - 100.00%
3.01 ACERO ESTRUCTURAL F'Y=4200 KG/CM2, GRADO 60 P/ kg 109,000.00 S/1.05 S/114,450.00 0.00 0.00 0.00% 5,995.27 6,295.04 5.50% 5,995.27 6,295.04 5.50% 103,004.73 108,154.96 94.50%

COSTO DIRECTO (CD) 1,400,089.35 0.00 20,733.79 20,733.79 1,363,936.61


IGV (18%) 252,016.08 0.00 3,732.08 3,732.08 245,508.59
PRESUPUESTO TOTAL 1,652,105.44 0.00 24,465.88 24,465.88 1,609,445.21
% DE AVANCE 100.00% 0.00% 1.48% 1.48% 97.42%
PRESUPUESTO DE OBRAS PROVISIONALES Y SITIO

Proyecto : COLEGIO JOSE RAZURI


Colegio : ARCC 2353 - LOCAL ESCOLAR 413944 Ubicación : CURA MORI - PIURA

GRAFICO DEL PORCENTAJE DE AVANCE


PROGRAMADO VS EJECUTADO ACUMULADO 100%
100%

90%

80%
AVANCE MENSUAL ACUMULADO (%)

70%

60%

50%

40%

30%

20%

10%

0%
21/02/2022 - 25/02/2022 SEMANA 01

MONTOS VALORIZADOS PROGRAMADOS ACTUALIZADOS MONTOS VALORIZADOS EJECUTADOS


MONTOS TOTAL (Inc/ IGV) PORCENTAJES MONTOS TOTAL (Inc/ IGV) PORCENTAJES
SEMANA PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
21/02/2022 - 25/02/2022 0.00% 21/02/2022 - 25/02/2022 0.00 0.00%
SEMANA 01 24,000.00 1.45% 1.45% SEMANA 01 24,465.88 24,465.88 1.48% 1.48%
TOTAL 24,000.00 1.45% TOTAL 24,465.88 1.48%

SITUACION DE LA OBRA: ADELANTADA 0.03%


METRADO ACUMULADO DE VALORIZACION N 01 1
CONCRETO
HYF

SOLADO - CONCRETO
ITEM DESCRIPCCION Und Cant. L A AREA H M3 TOTAL

1.00 PABELLON 4.1.5 M2 170.52

1.01 TRAMO EJE 10-10 AL EJE 12-12 M2 1 17.4 9.80 170.52 0.05 8.53

2.00 PABELLON 4.3.1 - 4.3.3 451.36

2.01 TRAMO G-G AL P-P ENTRE LOS EJES10-10 AL 12-12 M2 1 36.4 12.40 451.36 0.05 22.57

2.00 PABELLON 4.3.1 - PAB 2.1.2 310.62

2.01 TRAMO Q"-Q" AL W-W ENTRE LOS EJES10-10 AL 12-12 M2 1 21.175 12.35 261.51 0.05 13.08
M2 1 8.025 2.10 16.85 0.05 0.84
M2 1 8.025 2.20 17.66 0.05 0.88
M2 1 2.45 4.95 12.13 0.05 0.61
M2 1 0.5 4.95 2.48
932.50

PLATEA DE CIMENTACION - CONCRETO


ITEM DESCRIPCCION Und Cant L A AREA H M3 TOTAL

1.00 PABELLON 4.1.5 M3 62.53

1.01 TRAMO EJE 10-10 AL EJE 12-12 ENTRE EL TRAMO A-A Y E-E M3 1 16.9 9.25 156.33 0.40 62.53
METRADO ACUMULADO DE VALORIZACION N 01 2
ACERO - PESOS
HYF
No. No. FE. FE. FE. FE. FE.
ITEM DESCRIPCCION Und LONG. TOTAL
PIEZAS VECES 3/8" 1/2" 3/4" 5/8" 1"

ESTRUCTURAS - ELEMENTOS ARMADOS 0.56 0.99 2.24 1.55 3.97

1.00 PLATEA DE CIMENTACION PABELLON 4.1.5 - MALLA INFERIOR 02 DIRECCIONES KG 5,995.27


1.00.01 MALLA INFERIOR 02 DIRECCIONES
1.00.01.01 LONGITUDINAL
EJE 1-1 AL EJE 3-3 KG 37 1.00 4.50 93.24
37 1.00 9.00 186.48
37 1.00 5.00 103.60
ACERO DE REFUERZO
37 3.00 2.90 180.26
1.00.01.02 TRANSVERSAL
EJE A-A AL C-C KG 67 1.00 9.00 337.68
67 1.00 1.50 56.28
ACERO DE REFUERZO
67 2.00 2.25 168.84
1.00.02 MALLA SUPERIOR 02 DIRECCIONES
1.00.02.01 LONGITUDINAL
EJE 1-1 AL EJE 3-3 KG 37 1.00 4.50 165.50
37 1.00 9.00 331.00
37 1.00 5.00 183.89
1.00.02.02 TRANSVERSAL
EJE A-A AL C-C KG 67 1.00 9.00 599.38
67 1.00 1.50 99.90
1.00.03 REFUERZO DE SOSTENIMIENTO ENTRE MALLA SUPERIOR E INFERIOR
KG 40 4.00 0.90 143.14

2.00 VIGAS DE CIMENTACION

2.00.01 ACERO LONGITUDINAL (0.30*0.80)

EJE A-A Y EJE E-E CORTE Y-Y

6 2.00 6.95 186.40

6 2.00 4.15 111.30

EJE B-B Y EJE D-D CORTE Z-Z

4 3.00 7.50 201.15


4 3.00 3.95 105.94

1 3.00 7.50 89.39

1 3.00 3.95 47.08

EJE 2-2 Y EJE 3-3 CORTE X-X

3 2.00 7.35 98.56

6 2.00 9.00 241.38

3 2.00 3.85 51.63

3 2.00 7.10 95.21

3 2.00 2.95 39.56

2.00.02 ESTRIBOS

EJE A-A Y EJE E-E CORTE Y-Y

32 2.00 1.90 68.10

EJE B-B Y EJE D-D CORTE Z-Z

42 3.00 1.90 134.06

EJE 2-2 Y EJE 3-3 CORTE X-X

62 2.00 1.90 131.94


2.00 COLUMNAS

2.01 PLACA

2.01.01 ACERO LONGITUDINAL

18 2.00 6.55 365.96

18 2.00 5.40 301.71

3 2.00 6.55

3 2.00 5.40

2.01.02 ESTRIBOS

SUNCHOS

3 4.00 0.85 5.71

3 4.00 1.95 13.10

3 4.00 3.35 22.51

3 4.00 0.35 2.35


2.02 C-01

02.02.01 LONGITUDINAL

16 3.00 6.55 487.95

4 3.00 6.55 44.02

16 3.00 5.40 402.28

4 3.00 5.40 36.29

2.02.02 ESTRIBOS

SUNCHOS

3 6.00 0.85 8.57

3 6.00 1.55 15.62

3 6.00 2.75 27.72

9 6.00 0.35 10.58

SUBTOTAL 1646.96 1522.81 1131.13 1557.90 136.47


METRADO ACUMULADO DE VALORIZACION N 01 3
ENCOFRADO
HYF

ENCOFRADO - PLATEA DE CIMENTACION


ITEM DESCRIPCCION Und Cant. L A H AREA TOTAL

1.00 PABELLON 4.1.5 M2 20.92

EJE A-A TRAMO 1-1 AL 3-3 M2 1 9.25 0.40 3.70


EJE E-E TRAMO 1-1 AL 3-3 M2 1 9.25 0.40 3.70
EJE 3-3 TRAMO A-A AL E-E M2 1 16.9 0.40 6.76
EJE 1-1 TRAMO A-A AL E-E M2 1 16.9 0.40 6.76
METRADO ACUMULADO DE VALORIZACION N 01 4
CURADO DEL CONCRETO

HYF

PLATEA DE CIMENTACION - CURADO


ITEM DESCRIPCCION Und Cant L A AREA TOTAL

1.00 PABELLON 4.1.5 M2 156.33

1.01 EJE 1-1 AL EJE 3-3 ENTRE EL TRAMO A-A Y TRAMO E-E M2 1 16.9 9.25 156.33
PABELLONES

I.E LUIS ALBERTO SANCHEZ


A.H SANTA ROSA
26 DE JULIO DEL 2021

Inm.
ITEM DESCRIPCCION Und Met. SAN SINCERADO
CAROS

ESTRUCTURAS
1.00.00 TRABAJOS PRELIMINARES

2.00.00 MOVIMIENTO DE TIERRAS


2.01 EXCAVACION DE ZANJAS -CUNETAS m3 20.00
EXCAVACION DE ZANJAS - ZAPATAS CORRIDAS - PLATEA 20.00
2.06 NIVELACION INT. CON EQUIPO P/ FALSO PISO Y VERED. m2

3.00.00 CONCRETO SIMPLE


3.01 CONCRETO CIMIENTOS CORRIDOS 1: 10 + 30%PG m3 60.00
3.02 SOLADO DE CONCRETO CICLOPEO 100KG/CM2 , E=10cm m2 10.00
3.03 FALSO PISO C:H 1:8, e=4" m2 12.00
3.04 VEREDAS DE CONCRETO Y BRUÑADO m2 25.00
3.05 CUNETA DE CONCRETO ml 40.00
4.00.00 CONCRETO ARMADO

4.02 VIGAS DE CIMENTACION


VIGAS DE CIMENTACION CONCRETO F´C=210 KG/CM2 m3 65.00
ENCOFRADO Y DESENCOFRADO P/ VIGA DE CIMENTACION m2 30.00
ACERO FY= 4,200 KG/CM2 kg

4.03 SOBRECIMIENTO ARMADO


SOBRECIMIENTO CONCRETO F´C=210KG/CM2 m3 65.00
ENCOFRADO Y DESENCOFRADO P/ SOBRECIMIENTO m2 30.00
ACERO FY= 4,200 KG/CM2 kg

4.04 COLUMNAS
COLUMNAS CONCRETO F´C=210KG/CM2 m3 75.00
ENCOFRADO Y DESENCOFRADO P/ COLUMNA m2 30.00
IZAJE DE COLUMNAS kg
ACERO FY= 4,200 KG/CM2 kg

4.05 VIGAS
VIGAS CONCRETO F´C=210 KG/CM2 m3 65.00
ENCOFRADO Y DESENCOFRADO P/ VIGAS m2 30.00
ACERO FY= 4,200 KG/CM2 kg

4.06 LOSA ALIGERADA


LOSA ALIGERADA FC=210KG/CM2 m3 80.00
ENCOFRADO Y DESENCOFRADO DE LOSA ALIGERADA m2 30.00
ACERO FY= 4,200 KG/CM2 kg
LADRILLO HUECO DE ARCILLA 15 X 30 X 30 PARA LOSA ALIGERADA und 0.40

4.07 ESCALERAS
CONCRETO F´C=210 KG/CM2 m3 80.00
ENCOFRADO Y DESENCOFRADO P/ VIGAS m2 30.00
ACERO FY= 4,200 KG/CM2 kg

* Los costos no incluyen Igv


PABELLONES

I.E LUIS ALBERTO SANCHEZ


A.H SANTA ROSA
26 DE JULIO DEL 2021

Inm.
ITEM DESCRIPCCION Und Met. SAN SINCERADO
CAROS

ARQUITECTURA
5.00 ALBAÑILERIA

5.01 MURO DE LADRILLO KK - SOGA. C.A , 1:4, j=5cm. m2 22.00


5.02 MURO DE LADRILLO KK - CABEZA C.A , 1:4, j=5cm. m2 28.00

6.00.00 REVOQUES Y ENLUCIDOS


6.01 TARRAJEO DE MUROS m2 16.00
6.02 TARRAJEO DE COLUMNAS m2 20.00
6.03 TARRAJEO DE VIGAS m2 20.00
6.04 TARRAJEO DE ESCALERAS m2 20.00
6.05 VESTIDURA DE DERRAMES ml 3.00
6.06 BRUÑAS ml

7.00.00 CIELO RASO


7.01 TARRAJEO CIELO RASO m2 20.00

8.00.00 PISOS Y PAVIMENTOS


8.01 CONTRAPISO m2 12.00
8.02 PISO DE CERAMICO m2 14.00
8.03 PISO DE CEMENTO PULIDO m2 15.00

9.00.00 ZOCALOS Y CONTRAZOCALOS


9.01 ZOCALO DE CERAMICA - BAÑOS m2 14.00
9.02 CONTRAZOCALO DE CERMICO H= 0.10 m. ml 10.00
9.03 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m. ml 10.00

10.00 CANALETA DE EVACUACION


10.01 EXCAVACION MANUAL PARA CANELETA ml
10.02 CONCRETO PARA CANALETA m3
10.03 ENCOFRADO PARA CANALETA ml

11.00 OTROS
10.01 CURADO DE SUPERFICIES m2

* Los costos no incluyen Igv


COSTO EXP. TECNICO
I.E LUIS ALBERTO SANCHEZ
22 DE DICIEMBRE DEL 2021

2.00 ESTRUCTURAS

2.03.00 CONCRETO ARMADO


2.03.10 ESTRUCTURA METALICA
ITEM DESCRIPCCION Und Met. Costo TOTAL

02.03.10.01 VIGAS
VIGA METALICA ARCO - PEFIL Kg 6,028.02 9.32 56,181.15

APOYO METALICO FIJO Und 20.00 418.67 8,373.40

APOYO METALICO MOBIL Und 20.00 319.95 6,399.00

02.03.10.02 VIGUETAS
VIGUETA METALICA - ARCO ACERO LISO Kg 4902.57 10.36 50,790.63

02.03.10.03 COBERTURA
CERAMICA DE COLOR 45X45 m2 1,836.00 60.10 110,343.60

SUBTOTAL 232,087.77
IGV 273,863.57
TOTAL 273,863.57

3.00 ARQUITECTURA
3.04.00 PISOS Y PAVIMENTOS
3.04.02 PISOS
ITEM DESCRIPCCION Und Met. Costo TOTAL

CERAMICOS
224000029 PISO CERAMICO DE 30 X 20 cm. m2 35.56 21.24 755.37

224000031 PISO CERAMICO DE 30 X 30 cm. ANTIDESLIZANTE m2 97.79 21.24 2,077.08

224000034 PISO CERAMICO DE 40 X 40 cm. m2 2621.59 21.24 55,682.52

229180008 FRAGUA Kg 34.67 6.70 232.30

240130054 CERAMICA DE COLOR 45X45 m2 425.46 20.46 8,704.91

* Nota: La Partida A TODO COSTO de Pisos es de : S/.145,850.66 SUBTOTAL 67,452.18


que incluye ceramica PISOS, ZOCALOS, CONTRAZOCALOS IGV 79,593.57
TOTAL 79,593.57

3.06.00 COBERTURAS
3.06.01 RECUBRIMIENTO CON PANEES TERMOACUSTICOS
ITEM DESCRIPCCION Und Met. Costo TOTAL

03.06.01.01 CUMBRERA TERMOACUSTICA TIPO TEJA m 177.30 106.37 18,859.40

03.06.01.02 PLANCHA TR4 COLOR NATURAL E=0.4 MM INC/CORREAS DE MADERA 2"X2" m2 2158.63 107.58 232,225.42

03.06.01.03 PLANCHA TR4 COLOR NATURAL E=0.4 MM INC/VIGAS METALICAS 2"X2" m2 31.57 106.41 3,359.36

03.06.01.04 BEBETALATERAL DE PLANCHA m 345.05 53.85 18,580.94

SUBTOTAL 273,025.12
IGV 322,169.64
TOTAL 322,169.64
3.07.00 CARPINTERIA DE MADERA
3.07.01 PUERTAS
ITEM DESCRIPCCION Und Met. Costo TOTAL

03.07.01.01 PUERTAS MACIZAS 91,309.73


PUERTAS CON TABLERO DE MADERA Y MARCO DE MADERA m2 211.37 431.99 91,309.73

SUBTOTAL 91,309.73
IGV 107,745.48
TOTAL 107,745.48

3.07.02 VENTANAS
ITEM DESCRIPCCION Und Met. Costo TOTAL

03.07.02.01 VENTANAS DE MADERA 1,091.27


VENTANA DE MADERA DE CEDRO C/SEG 1/2" m2 3.60 303.13 1,091.27

SUBTOTAL 1,091.27
IGV 1,287.70
TOTAL 1,287.70

3.08 CARPINTERIA METALICA Y HERRERIA


3.08.01 VENTANAS DE FIERRO
ITEM DESCRIPCCION Und Met. Costo TOTAL

VENTANA
203110005 VENTANA DE FIERRO PERFIL DE 1" X 1/8" FIJO MARCO "T" DE 1" C/SEG. 1/2" (T/REJA) Und 626.55 542.26 339,753.00

SUBTOTAL 339,753.00
IGV 400,908.54
TOTAL 400,908.54

3.08 CARPINTERIA METALICA Y HERRERIA


3.08.02 PUERTAS DE FIERRO
ITEM DESCRIPCCION Und Met. Costo TOTAL

03.08.02.01 PUERTA DE INGRESO PRINCIPAL C/PERFILES 3/16" m2 33.80 1,501.11 50,737.52

3.08.03 BARANDAS METALICAS

03.08.03.01 PASAMNO DE TUBO DE 2" Y 1 1/2" F°G° m 127.70 63.48 8,106.40

3.08.04 PASAMANOS AISLADOS

03.08.04.01 PASAMNO DE TUBO DE F°G° 2" EN ESCALERA m 80.28 63.48 5,096.17

3.08.05 CERCO DE FIERRO

03.08.05.01 CERCO REJA METALICA m 36.00 264.00 9,504.00

3.08.06 ELEMENTOS METALICOS


03.08.06.01 CANTONERA DE FIERRO EN ESCALERA m 230.25 18.53 4,266.53

03.08.06.02 MARCO Y TAPA DE FIERRO D=0.60 m Und 36.00 264.00 9,504.00

3.08.07 ELEMENTOS METALICOS


03.08.07.01 PUERTA METALICA ENRROLLABLE m2 8.14 512.00 4,167.68
03.08.07.02 PUERTA CON PERFILES METALICOS m2 4.80 450.00 2,160.00
03.08.07.03 VENTNA METALICA m2 1.62 536.46 869.07
03.08.07.04 MALLA METALICA PORTECTORA CON ALAMBRE N° 12 X COCADAS DE 1" m2 65.00 88.63 5,760.95

03.08.06.02 BARANDA DE TUBO DE 2" F°G° H=1.00 m 8.00 130.11 1,040.88


SUBTOTAL 91,709.20
IGV 108,216.85
TOTAL 108,216.85
VAL. 01 - ENCOFRADOS 1
ENCOFRADOS GENERALES
EDGAR VILCHEZ NAVARRO
26 DE AGOSTO DEL 2021

PLATEA - VC
ITEM DESCRIPCCION Und ML H M2 TOTAL

1.00 PABELLON 09 M2 43.34

1.01 CAJON 1 - INT. m2 14.78 0.70 10.35


1.02 CAJON 2 - INT. m2 14.53 0.70 10.17
1.03 CARAS - EXT. m2 32.60 0.70 22.82

2.00 PABELLON 01 110.66

2.01 CAJON 1 - INT. m2 14.50 0.70 10.15


2.02 CAJON 2 - INT. m2 16.03 0.70 11.22
3.02 CAJON 3 - INT. m2 15.95 0.70 11.17
4.02 CAJON 4 - INT. m2 15.95 0.70 11.17
5.02 CAJON 5 - INT. m2 16.03 0.70 11.22
6.02 CAJON 6 - INT. m2 14.53 0.70 10.17
2.03 CARAS - EXT. m2 65.10 0.70 45.57

3.00 ESCALERA 31.01

2.01 CAJON 1 - INT. m2 10.55 0.70 7.39


3.01 CAJON 1 - INT. m2 10.55 0.70 7.39
2.02 CARA - EXT. m2 23.20 0.70 16.24

185.01 185.01
M2

PLATEA - VC
ITEM DESCRIPCCION Und CANT. ML H M2 TOTAL

4.00 SS-HH PRIMARIA M2 37.79

4.01 CAJON 1 - INT. m2 10.77 0.70 7.54


4.02 CAJON 2 - INT. m2 11.95 0.70 8.37
4.03 CAJON 2 - INT. m2 10.77 0.70 7.54
4.04 CARAS - EXT. m2 20.50 0.70 14.35

5.00 PABELLON 02 60.76

5.01 CAJON 1 - INT. m2 14.60 0.70 10.22


5.02 CAJON 2 - INT. m2 15.95 0.70 11.17
5.03 CAJON 3 - INT. m2 15.95 0.70 11.17
5.04 CAJON 4 - INT. m2 14.60 0.70 10.22
5.05 CARAS - EXT. m2 25.70 0.70 17.99

98.55 98.55
M2

COLUMNAS
ITEM DESCRIPCCION Und CANT. ML H M2 TOTAL
6.00 PABELLON 9 M2 66.41

6.01 C -1 m2 2 1.00 3.10 6.20


6.02 C-2 m2 4 2.20 4.14 36.43
6.03 C-3 m2 2 2.90 4.10 23.78

7.00 PABELLON 1 168.89

7.01 C-1 m2 4 1.00 3.10 12.40


7.02 C-2 m2 4 2.20 4.14 36.43
7.03 C-3 m2 10 2.90 4.14 120.06

235.30 235.30
M2

SOBRECIMIENTOS
ITEM DESCRIPCCION Und CANT. L H M2 TOTAL

8.00 PABELLON 9 M2 55.35

8.1 EJE 3-3 m2 2 6.51 1.10 14.32


8.02 EJE 1-1 m2 2 6.51 1.10 14.32
8.03 EJE A-A m2 2 5.58 1.10 12.28
8.03 EJE C-C m2 2 6.56 1.10 14.43

9.00 PABELLON 1 50.13

9.01 EJE 1-1 m2 1 6.51 1.10 7.16


9.02 EJE 3-3 m2 2 6.51 1.10 14.32
9.03 EJE 5-5 m2 2 6.51 1.10 14.32
9.04 EJE 7-7 m2 2 6.51 1.10 14.32

105.48 105.48
M2

VAL 01
Platea - Vigas Pab.9 43.34 21,852.11
Platea - Vigas Pab.1 110.66
Platea - Vigas Escalera 31.01
Platea - Vigas SS.hh 37.79
Platea - Vigas Pab. 2 60.76
Columnas Pab. 9 66.41
Columnas Pab. 1 168.89
Sobrec. Pab. 9 55.35
Sobrec. Pab. 1 50.13
Metrado total 624.35 S/ 35.00

con Igv

VAL. 02 - ENCOFRADOS 2
ENCOFRADOS GENERALES
EDGAR VILCHEZ NAVARRO
15 DE AGOSTO DEL 2021

PLATEA - VC
ITEM DESCRIPCCION Und ML H M2 TOTAL

1.00 PABELLON 04 m2 112.67

1.01 CAJON 1 - INT. - Pab. Administrativo m2 1 25.80 0.70 18.06


1.02 CAJON 1 - INT. - Pab. 4 Aulas m2 1 17.10 0.70 11.97
1.03 CAJON 2 - INT. - Pab. 4 Aulas m2 1 17.96 0.70 12.57
1.04 CAJON 3 - INT. - Pab. 4 Aulas m2 1 18.11 0.70 12.68
1.05 CAJON 4 - INT. - Pab. 4 Aulas m2 1 12.62 0.70 8.83
1.06 CARAS - EXT. m2 1 69.36 0.70 48.55

2.00 PABELLON 05 84.53

2.01 CAJON 1 - INT. - Escalera m2 2 10.55 0.70 14.77


2.02 CAJON 1 - INT. m2 1 16.23 0.70 11.36
2.03 CAJON 2 - INT. m2 1 17.80 0.70 12.46
2.04 CAJON 3 - INT. m2 1 14.80 0.70 10.36
2.05 CARAS - EXT. m2 1 50.83 0.70 35.58

197.20 197.20

COLUMNAS
ITEM DESCRIPCCION Und CANT. ML H M2 TOTAL

1.00 SS.HH PRIMARIA M2 78.72

1.01 C -1 m2 2 1.50 4.10 12.30


1.02 C-2 m2 2 1.50 4.10 12.30
1.03 C-3 m2 6 2.20 4.10 54.12

2.00 PABELLON 2 117.77

2.01 C-1 m2 3 1.00 3.10 9.30


2.02 C-2 m2 4 2.20 4.14 36.43
2.03 C-3 m2 6 2.90 4.14 72.04

3.00 PABELLON 4 - ADMINISTRATIVO 72.04

3.01 C-3 m2 6 2.90 4.14 72.04

268.52 268.52
M2

SOBRECIMIENTOS
ITEM DESCRIPCCION Und CANT. L H M2 TOTAL

1.00 PABELLON 1 78.89

1.1 EJE C-C m2 2 19.34 1.10 42.55


1.2 EJE A-A m2 2 16.52 1.10 36.34

2.00 SS-HH - PRIMARIA 103.36

2.1 EJE 1-1 m2 2 4.16 1.10 9.15


2.2 EJE 2-2 m2 2 3.11 1.10 6.84
2.3 EJE 3-3 m2 2 3.11 1.10 6.84
2.4 EJE 4-4 m2 2 4.16 1.10 9.15
2.5 EJE 2-3 m2 2 3.45 1.10 7.59
2.6 EJE A-A m3 2 7.16 1.10 15.75
2.7 EJE B-B m2 2 10.69 1.10 23.52
2.8 EJE C-C m5 2 11.14 1.10 24.51

3.00 PABELLON 2 - PRIMARIA 96.25

3.1 EJE 8-8 m2 2 6.51 1.10 14.32


3.2 EJE 10-10 m2 2 6.51 1.10 14.32
3.3 EJE 12-12 m2 2 6.51 1.10 14.32
3.4 EJE A-A m2 2 11.12 1.10 24.46
3.5 EJE C-C m2 2 13.10 1.10 28.82

278.50 278.50
M2

ALIGERADO - VIGAS
ITEM DESCRIPCCION Und ML H M2 TOTAL

1.00 PABELLON 09 m2 145.55

1.01 CAJON 1 m2 1 28.34


1.02 CAJON 2 m2 1 27.38
1.03 CAJON 3 m2 1 9.43
1.04 CAJON 4 m2 1 9.11
1.05 CAJON 5 m2 1 4.78
1.06 FRISOS m2 1 38.77 0.20 7.75

2.1 EJE A-A m2 1 8.53 0.85 7.25


2.2 EJE C-C m2 1 8.53 0.85 7.25
2.3 EJE A-A m2 1 8.53 0.35 2.99
2.4 EJE 1-1 m2 1 10.86 0.80 8.69
2.5 EJE 3-3 m2 1 10.86 0.80 8.69
2.6 EJE 2-2 m2 2 10.86 1.10 23.89

145.55 145.55
M2
VAL 02
Platea - Vigas Pab.4 112.67 30,285.62
Platea - Vigas Pab.5 84.53
Columnas Ss.hh Prim. 78.72
Columnas Pab. 2 117.77
Columnas Pab. 4 72.04
Sobrec. Pab. 1 78.89
Sobrec. Ss.hh. Prim. 78.89
Sobrec. Pab. 2 96.25
Aligerado y Vigas Pab. 9 145.55

Metrado total 865.30 S/ 35.00

con Igv 30,285.62


VAL. 03 - ENCOFRADOS 3
ENCOFRADOS GENERALES
EDGAR VILCHEZ NAVARRO
30 DE SEPTIEMBRE DEL 2021

PLATEA - VC
ITEM DESCRIPCCION Und ML H M2 TOTAL

1.00 SS.HH SECUNDARIA m2 57.32

1.01 CAJON 1 - INT. - Ss.hh m2 1 8.87 0.70 6.21


1.02 CAJON 2 - INT. - Ss.hh m2 1 14.17 0.70 9.92
1.03 CAJON 3 - INT. - Ss.hh m2 1 12.39 0.70 8.67
1.04 CARAS - EXT. m2 1 46.45 0.70 32.52

2.00 PABELLON 03 77.22

2.01 CAJON 1 - INT. - Pab. 3 m2 1 14.60 0.70 10.22


2.02 CAJON 2 - INT. Pab. 3 m2 1 15.95 0.70 11.17
2.03 CAJON 3 - INT. Pab. 3 m2 1 8.70 0.70 6.09
2.04 CAJON 4 - INT. Pab. 3 m2 1 8.83 0.70 6.18
2.05 CAJON 5 - INT. Pab. 3 m2 1 13.18 0.70 9.23
2.06 CARAS - EXT. m2 1 49.05 0.70 34.34

3.00 PABELLON 08 43.26

3.01 CAJON 1 - INT. - Pab.8 m2 1 14.53 0.70 10.17


3.02 CAJON 2 - INT. - Pab.8 m2 1 14.78 0.70 10.35
3.03 CARAS - EXT. m2 1 32.49 0.70 22.74

4.00 PABELLON 07 43.26

4.01 CAJON 1 - INT. - Pab. 7 m2 1 14.53 0.70 10.17


4.02 CAJON 2 - Pab. 7 m2 1 14.78 0.70 10.35
2.05 CARAS - EXT. m2 1 32.49 0.70 22.74

221.05 243.37

COLUMNAS
ITEM DESCRIPCCION Und CANT. ML H M2 TOTAL

1.00 PABELLON 4 M2 222.63

1.01 C -1 m2 2 1.00 4.10 8.20


1.02 C-2 m2 7 2.20 4.10 63.14
1.03 C-3 m2 8 2.90 4.10 95.12
1.04 C-4 m2 1 1.70 4.10 6.97
1.05 C-5 m2 8 1.50 4.10 49.20

2.00 PABELLON 5 91.84

2.01 C-1 m2 2 1.00 4.10 8.20


2.02 C-2 m2 4 2.20 4.10 36.08
2.03 C-3 m2 4 2.90 4.10 47.56

314.47 314.47

SOBRECIMIENTOS
ITEM DESCRIPCCION Und CANT. L H M2 TOTAL

1.00 PABELLON 4 132.46

1.1 EJE F-F m2 2 19.50 1.10 42.90


1.2 EJE A-A m2 2 10.47 1.10 23.03
1.3 EJE 1-1 m2 2 6.78 1.10 14.92
1.4 EJE B-B m2 2 4.95 1.10 10.89
1.5 EJE 5-5 m2 2 5.83 1.10 12.83
1.6 EJE 10-10 m2 2 3.96 1.10 8.71
1.7 EJE INT. m2 2 8.72 1.10 19.18

2.00 PABELLON 5 44.37

2.1 EJE C-C m2 2 10.48 1.10 23.06


2.2 EJE 1-1 m2 1 6.46 1.10 7.11
2.3 EJE 4-4 m2 2 6.46 1.10 14.21

3.00 ESCALERAS 24.56

3.1 EJE 5-5 m2 2 5.01 1.10 11.02


3.2 EJE 6-6 m2 1 5.01 1.10 5.51
3.3 EJE C-C m2 2 3.65 1.10 8.03

4.00 SS.HH SECUNDARIA 66.55


3.1 EJE C-C m2 2 6.66 1.10 14.65
3.2 EJE B-B m2 2 3.58 1.10 7.88
3.3 EJE 4-4 m2 2 3.41 1.10 7.50
3.4 EJE D-D m2 1 3.78 1.10 4.16
3.5 EJE B-B m2 2 4.05 1.10 8.91
3.6 EJE 1-1 m2 2 4.51 1.10 9.92
3.7 EJE 2-2 m2 2 3.70 1.10 8.14
3.8 EJE 3-3 m2 2 2.45 1.10 5.39

5.00 PABELLON 8 27.76

5.1 EJE 1-1 m2 2 6.26 1.10 13.77


5.2 EJE 3-3 m2 2 6.36 1.10 13.99

6.00 PABELLON 3 50.89

6.1 EJE 5-5 m2 2 6.26 1.10 13.77


6.2 EJE 3-3 m2 2 6.36 1.10 13.99
6.3 EJE 1-1 m3 2 4.10 1.10 9.02
6.4 EJE B-B m4 2 6.41 1.10 14.10

346.60 346.60

ALIGERADO - VIGAS
ITEM DESCRIPCCION Und ML H M2 TOTAL

1.00 PABELLON 01 m2 339.37

1.01 CAJON 1 m2 1 27.43


1.02 CAJON 2 m2 1 28.15
1.03 CAJON 3 m2 1 27.88
1.04 CAJON 4 m2 1 27.88
1.05 CAJON 5 m2 1 28.15
1.06 CAJON 6 m2 1 27.43

1.07 CAJON 7 m2 1 9.13


1.08 CAJON 8 m2 1 9.37
1.09 CAJON 9 m2 1 9.28
1.1 CAJON 10 m2 1 9.28
1.11 CAJON 11 m2 1 9.37
1.12 CAJON 12 m3 1 9.13
1.13 FRISOS m2 1 70.82 0.20 14.16

2.1 EJE 2-4-6 m2 3 10.00 1.10 33.00


2.2 EJE 1-3-5-7 m2 4 10.00 0.80 32.00
2.3 EJE C-A m2 2 25.15 0.60 30.18
2.4 EJE 1-1 m2 2 25.15 0.15 7.55

339.37 339.37
M2

2.00 PABELLON 02 m2 226.37

1.01 CAJON 1 m2 1 27.70


1.02 CAJON 2 m2 1 27.88
1.03 CAJON 3 m2 1 27.88
1.04 CAJON 4 m2 1 27.70

1.07 CAJON 7 m2 1 9.22


1.08 CAJON 8 m2 1 9.28
1.09 CAJON 9 m2 1 9.28
1.1 CAJON 10 m2 1 9.22
1.13 FRISOS m2 1 54.15 0.20 10.83

2.1 EJE 9-11 m2 2 10.26 1.10 22.57


2.2 EJE 1-3-5-7 m2 3 10.26 0.80 24.62
2.3 EJE C-A m2 2 16.82 0.60 20.18

226.37 226.37
M2

VAL 03 - ENCOFRADOS
Platea - Ss.hh Secund. 57.32 50,675.14
Platea - Vigas Pab.3 77.22
Platea - Vigas Pab.8 43.26
Platea - Vigas Pab.7 43.26
Columnas - Pab. 4 222.63
Columnas - Pab. 5 91.84
Sobrec. Pab. 4 132.46
Sobrec. Pab. 5 44.37
Sobrec. Escalera 24.56
Sobrec. Sa.hh Secund. 66.55
Sobrec. Pab. 8 27.76
Sobrec. Pab. 3 50.89
Aligerado y Vigas Pab. 1 339.37
Aligerado y Vigas Pab. 2 226.37

Metrado total 1,447.86 S/ 35.00

con Igv 50,675.14

VAL. 04 - ENCOFRADOS 4

PLATEA - VC
ITEM DESCRIPCCION Und ML H M2 TOTAL

2.00 PABELLON 06 43.26

2.01 CAJON 1 - INT. - Pab. 6 m2 1 14.78 0.70 10.35


2.02 CAJON 2 - INT. Pab. 6 m2 1 14.53 0.70 10.17
2.06 CARAS - EXT. m2 1 32.49 0.70 22.74

2.00 ADICIONALES 49.20

2.01 ZAPATA ESCALERA PAB- 9-1 / PAB. 4-5 m2 2 15.94 0.70 22.32

ZAPATA S.H SECUNDARIA m2 1 18.32 0.70 12.82

ZAPATA S.H PRIMARIA m2 1 20.08 0.70 14.06

0.00 92.46
M2

COLUMNAS
ITEM DESCRIPCCION Und CANT. ML H M2 TOTAL

2.00 SS.HH SECUNDARIA 85.28

2.01 C-1 m2 12 1.50 4.10 73.80


2.02 C-2 m2 2 1.40 4.10 11.48
2.00 PABELLON 8 62.96

C1 m2 2 0.50 3.10 3.10


C2 m2 4 2.20 4.10 36.08
C3 m2 2 2.90 4.10 23.78

2.00 PABELLON 7 63.96

C1 m2 2 0.50 4.10 4.1


C2 m2 4 2.20 4.10 36.08
C3 m2 2 2.90 4.10 23.78

2.00 PABELLON 3 107.42

C1 m2 3 0.5 3.10 4.65


C2 m2 4 2.2 4.10 36.08
C3 m2 6 2.9 4.10 71.34

2.00 PABELLON 1 SEGUNDO PISO 119.40

C1 m2 4 0.50 3.0 6.00


C2 m2 4 2.20 3.0 26.40
C3 m2 10 2.90 3.0 87.00

2.00 PABELLON 2 SEGUNDO PISO 83.10

C1 m2 3 0.50 3.0 4.50


C2 m2 4 2.20 3.0 26.40
C3 m2 6 2.90 3.0 52.20

2.00 PABELLON 6 26.58

C1 m2 2 0.50 2.80 2.80


C3 m2 2 2.90 4.10 23.78

0.00 548.70
M2

SOBRECIMIENTOS
ITEM DESCRIPCCION Und CANT. L H M2 TOTAL

2.00 PABELLON 5 84.06

2.1 EJE A-A m2 2 8.51 1.10 18.72


2.2 EJE ESCALERA m2 2 3.00 1.10 6.60
2.3 SOBRECIMIENTOS INTERNOS m2 2 6.53 1.10 14.37

2.1 EJE C-C m2 2 10.48 1.10 23.06


2.2 EJE 1-1 m2 1 6.46 1.10 7.11
2.3 EJE 4-4 m2 2 6.46 1.10 14.21

1.00 SS.HH SECUNDARIA 79.31

1.1 EJE A-A m2 2 7.91 1.10 17.40


1.2 EJE 6-6 m2 2 7.06 1.10 15.53
1.3 EJE 2-2 m2 2 1.49 1.10 3.28

3.1 EJE C-C m2 2 6.66 1.10 14.65


3.2 EJE B-B m2 2 3.58 1.10 7.88
3.3 EJE 4-4 m2 2 3.41 1.10 7.50
3.4 EJE D-D m2 1 3.78 1.10 4.16
3.5 EJE E-E m2 2 4.05 1.10 8.91

2.00 PABELLON 8 26.97

2.1 EJE C-C m2 2 6.63 1.10 14.59


2.2 EJE A-A m2 2 5.63 1.10 12.39

2.00 PABELLON 7 55.62

3.1 EJE 1-1 m2 2 6.51 1.10 14.32


3.1 EJE 3-3 m2 2 6.51 1.10 14.32
3.1 EJE C-C m2 2 6.63 1.10 14.59
3.1 EJE A-A m2 2 5.63 1.10 12.39

2.00 PABELLON 3 63.49

2.1 EJE A-A m2 2 10.11 1.10 22.24


2.2 EJE C-C m2 2 13.11 1.10 28.84
2.4 EJE 2-2 m2 2 3.00 1.10 6.60
2.3 EJE 1-1 FALTANTE m2 2 2.64 1.10 5.81

2.00 PABELLON 6 21.48

2.1 EJE 1-1 m2 2 6.51 1.10 14.32


2.2 EJE 3-3 m2 1 6.51 1.10 7.16

0.00 330.94
M2

ALIGERADO - VIGAS
ITEM DESCRIPCCION Und ML H M2 TOTAL

2.00 PABELLON 04 m2 352.833

1.01 CAJON 1 m2 1 35.79


1.02 CAJON 2 m2 1 27.25
1.03 CAJON 3 m2 1 27.86
1.04 CAJON 4 m2 1 15.72
1.05 CAJON 5 m2 1 14.32
1.06 CAJON 6 m2 1 26.34
1.07 CAJON 7 m2 1 10.07
1.08 CAJON 8 m2 1 13.32
1.09 CAJON 9 m2 1 5.11
1.1 CAJON 10 m2 1 9.41
1.11 CAJON 11 m2 1 3.59
1.12 FRISOS m2 1 88.69 0.20 17.74
1.13
1.14 EJE 1-5= VP-101 m2 17.63 1.25 22.04
1.15 EJE 2-3-4 =VP-102 m2 25.89 1.30 33.66
1.16 EJE 6-9-10 =V-103 m2 24.73 1.05 25.97
1.17 EJE 7 = V-104 m2 9.76 1.10 10.74
1.18 EJE 8= V-105 m2 9.76 1.05 10.25
1.19 EJE F-A-D-B = V-P m2 43.67 1.00 43.67

M2 352.83

VAL 04 - ENCOFRADOS
Platea - Pab. 6 92.46 46,372.34
Columnas - Pab. 4 548.70
Sobrec. Pab. 4 330.94
Aligerado y Vigas Pab. 1 352.83

Metrado total 1,324.92 S/ 35.00

con Igv 46,372.34


VAL. 05 - ENCOFRADOS 5
EDGARD VILCHEZ NAVARRO
I.E LAS - 26 Octubre
31 OCTUBRE DEL 2021

PLATEA - VC
ITEM DESCRIPCCION Und ML H M2 TOTAL

1.00 CORREDOR - PRIMARIA 34.94

1.01 CAJON 1 - INT. - Corredor m2 1 10.85 0.70 7.60


1.02 CAJON 2 - INT. Corredor m2 1 11.61 0.70 8.13
1.03 CARAS - EXT. m2 1 27.46 0.70 19.22

COLUMNAS
ITEM DESCRIPCCION Und CANT. ML H M2 TOTAL

2.00 PABELLON 4 - Segundo Nivel 159.90

2.01 C-1 m2 2 0.50 3.00 3.00


2.02 C-2 m2 7 2.20 3.00 46.20
2.03 C-3 m2 8 2.90 3.00 69.60
2.04 C-4 m2 1 1.70 3.00 5.10
2.05 C-5 m2 8 1.50 3.00 36.00

3.00 PABELLON 6 - Primer nivel 26.40

C2 m2 4 2.20 3.00 26.40

SOBRECIMIENTOS
ITEM DESCRIPCCION Und CANT. L H M2 TOTAL

2.00 PABELLON 5 44.37

2.1 EJE C-C m2 2 10.48 1.10 23.06


2.2 EJE 1-1 m2 1 6.46 1.10 7.11
2.3 EJE 4-4 m2 2 6.46 1.10 14.21

1.00 SS.HH SECUNDARIA 43.10

3.1 EJE C-C m2 2 6.66 1.10 14.65


3.2 EJE B-B m2 2 3.58 1.10 7.88
3.3 EJE 4-4 m2 2 3.41 1.10 7.50
3.4 EJE D-D m2 1 3.78 1.10 4.16
3.5 EJE E-E m2 2 4.05 1.10 8.91

2.00 PABELLON 8 26.97

2.1 EJE C-C m2 2 6.63 1.10 14.59


2.2 EJE A-A m2 2 5.63 1.10 12.39

2.00 PABELLON 7 55.62

3.1 EJE 1-1 m2 2 6.51 1.10 14.32


3.1 EJE 3-3 m2 2 6.51 1.10 14.32
3.1 EJE C-C m2 2 6.63 1.10 14.59
3.1 EJE A-A m2 2 5.63 1.10 12.39

2.00 PABELLON 3 63.49

2.1 EJE A-A m2 2 10.11 1.10 22.24


2.2 EJE C-C m2 2 13.11 1.10 28.84
2.4 EJE 2-2 m2 2 3.00 1.10 6.60
2.3 EJE 1-1 FALTANTE m2 2 2.64 1.10 5.81

2.00 PABELLON 6 21.48

2.1 EJE 1-1 m2 2 6.51 1.10 14.32


2.2 EJE 3-3 m2 1 6.51 1.10 7.16

ALIGERADO - VIGAS
ITEM DESCRIPCCION Und ML H M2 TOTAL

4.00 PABELLON 01 Segundo Nivel m2 417.619

4.01 CAJON 1 m2 1 27.43


4.02 CAJON 2 m2 1 28.15
4.03 CAJON 3 m2 1 27.88
4.04 CAJON 4 m2 1 27.88
4.05 CAJON 5 m2 1 28.15
4.06 CAJON 6 m2 1 27.43
4.07 CAJON 7 m2 1 9.13
4.08 CAJON 8 m2 1 9.37
4.09 CAJON 9 m2 1 9.28
4.1 CAJON 10 m2 1 9.28
4.11 CAJON 11 m2 1 9.37
4.12 CAJON 12 m2 1 9.13
4.13 CAJON 13 m2 1 13.85
4.14 FRISOS m2 1 72.02 0.20 14.40

4.15 EJE 2-4-6 m2 3 10.60 1.10 34.98


4.16 EJE 1-3-5-7 m2 4 10.60 0.80 33.92
4.17 EJE C-A m2 2 25.75 0.60 30.90
4.18 EJE 1-1 m2 2 25.75 0.15 7.73
4.19 EJE F-A-D-B = V-P m2 44.27 1.00 44.27
4.20 Tarima LOSA MACIZA m2 1.00 25.15 0.60 15.09
5.00 PABELLON 02 - Segundo Nivel m2 249.422

5.01 CAJON 1 m2 1 27.70


5.02 CAJON 2 m2 1 27.88
5.03 CAJON 3 m2 1 27.88
5.04 CAJON 4 m2 1 27.70
5.05 CAJON 5 m2 1 9.22
5.06 CAJON 6 m2 1 9.28
5.07 CAJON 7 m2 1 9.28
5.08 CAJON 8 m2 1 9.22
5.09 CAJON 9 m2 1 9.24
5.10 FRISOS m2 1 55.35 0.20 11.07
5.11 EJE 9-11 m2 2 10.86 1.10 23.89

5.12 EJE 1-3-5-7 m2 3 10.86 0.80 26.06

5.13 EJE C-A m2 2 17.42 0.60 20.90


5.14 Tarima LOSA MACIZA m2 1.00 16.82 0.60 10.09

6.00 PABELLON 05 m2 224.649

6.01 CAJON 1 m2 1 33.05


6.02 CAJON 2 m2 1 29.62
6.03 CAJON 3 m2 1 27.76
6.04 CAJON 4 m2 1 11.38
6.05 CAJON 5 m2 1 10.20
6.06 CAJON 6 m2 1 9.55
6.07 FRISOS m2 1 47.53 0.20 9.51

6.08 EJE 1-4= VP-101 m2 2 10.46 1.20 25.10


6.09 EJE 2-3 =VP-102 m2 2 9.96 1.50 29.88
6.10 EJE C-A = VP m2 2 13.31 1.45 38.60

7.00 PABELLON 08 m2 147.681

7.01 CAJON 1 m2 1 28.34


7.02 CAJON 2 m2 1 27.38
7.03 CAJON 3 m2 1 9.43
7.04 CAJON 4 m2 1 9.11
7.05 CAJON 5 m2 1 4.78
7.06 FRISOS m2 1 38.77 0.20 7.75

7.07 EJE A-A m2 1 8.53 0.85 7.25


7.08 EJE C-C m2 1 8.53 0.85 7.25
7.09 EJE A-A m2 1 8.53 0.60 5.12
7.1 EJE 1-1 m2 1 10.86 0.80 8.69
7.11 EJE 3-3 m2 1 10.86 0.80 8.69
7.12 EJE 2-2 m2 2 10.86 1.10 23.89

ESCALERAS
2.00 ESCALERA PABELLON 1 - Ss.hh Primaria m2 60.195

1.01 CAJON 1 m2 1 8.75


1.02 CAJON 2 m2 1 5.25
1.03 CAJON 3 m2 1 7.30
1.04 CAJON 4 m2 1 5.25

2.1 EJE 7-8 m2 2 9.00 1.20 21.60


2.2 EJE A-C m2 2 3.65 1.45 10.59
2.3 V-B m2 1 3.65 0.40 1.46

VAL 05 - ENCOFRADOS
Platea - Corred. Prim. 34.94 55,154.58
Colum. - Pab. 4 / Pab.6 186.30
Sobrec. - 255.04
Aligdo.- Pab 1-2-5 -8-7 1,039.37
Escalera - Pab. 1 y Ss.hh 60.20

Metrado total 1,575.85 S/ 35.00

con Igv 55,154.58


VAL. 06 - ENCOFRADOS 6
EDGARD VILCHEZ NAVARRO
I.E LAS - 26 Octubre
15 NOVIEMBRE DEL 2021

ZAPATAS
ITEM DESCRIPCCION Und ML H M2 TOTAL

1.00 ARCO TECHO - PRIMARIA 30.00

1.01 CAJON 1 - INT. - Arco Techo m2 1 12.00 0.50 6.00


1.02 CAJON 2 - INT. - Arco Techo m2 1 12.00 0.50 6.00
1.03 CAJON 3 - INT. - Arco Techo m2 1 12.00 0.50 6.00
1.04 CAJON 4 - INT. - Arco Techo m2 1 12.00 0.50 6.00
1.05 CAJON 5 - INT. - Arco Techo m2 1 12.00 0.50 6.00

COLUMNAS
ITEM DESCRIPCCION Und CANT. ML H M2 TOTAL

2.00 PABELLON 5 - Segundo Nivel 64.20

2.01 C-1 m2 2 0.50 3.00 3.00


2.02 C-2 m2 4 2.20 3.00 26.40
2.03 C-3 m2 4 2.90 3.00 34.80

3.00 CORREDOR 34.44

3.01 C-1 m2 6 1.40 4.10 34.44

4.00 PABELLON 7 17.40

4.01 C-3 m2 2 2.90 3.00 17.40

COLUMNETAS
ITEM DESCRIPCCION Und CANT. ML H M2 TOTAL

5.00 PABELLON 9 6.52

5.01 EJE C-C m2 4 0.50 1.00 2.00


5.02 EJE A-A m2 3 0.50 2.10 3.15
5.03 EJE A-A m2 1 0.65 2.10 1.37

6.00 PABELLON 1 19.55

6.01 EJE C-C m2 12 0.50 1.00 6.00


6.02 EJE A-A m2 9 0.50 2.10 9.45
6.03 EJE A-A m2 3 0.65 2.10 4.10

7.00 PABELLON 2 13.03

7.01 EJE C-C m2 8 0.50 1.00 4.00


7.02 EJE A-A m2 6 0.50 2.10 6.30
7.03 EJE A-A m2 2 0.65 2.10 2.73

VIGUETAS
ITEM DESCRIPCCION Und CANT. ML H M2 TOTAL
ITEM DESCRIPCCION Und CANT. ML H M2 TOTAL

8.00 PABELLON 9 2.02

8.01 VIGUETA EJE C-C m2 5.53 0.20 1.11


8.02 VIGUETA EJE A-A m2 4.55 0.20 0.91

9.00 PABELLON 1 5.96

9.01 VIGUETA EJE C-C m2 16.34 0.20 3.27

9.02 VIGUETA EJE A-A m2 13.48 0.20 2.70

10.00 PABELLON 2 3.98

10.01 VIGUETA EJE C-C m2 10.92 0.20 2.18

10.02 VIGUETA EJE A-A m2 8.97 0.20 1.79

ALIGERADO - VIGAS
ITEM DESCRIPCCION Und CANT. ML H M2 TOTAL

11.00 PABELLON 07 m2 137.543

11.01 CAJON 1 m2 1 28.34


11.02 CAJON 2 m2 1 27.38
11.03 CAJON 3 m2 1 9.43
11.04 CAJON 4 m2 1 9.11
11.05 FRISOS m2 1 37.57 0.20 7.51

11.06 EJE A-A m2 1 8.53 0.85 7.25


11.07 EJE C-C m2 1 8.53 0.85 7.25
11.08 EJE 1-1 m2 1 10.86 0.80 8.69
11.09 EJE 3-3 m2 1 10.86 0.80 8.69
11.1 EJE 2-2 m2 2 10.86 1.10 23.89
11.11 Tarima LOSA MACIZA m2 1.00 9.00 1.00 9.00

12.00 PABELLON 06 m2 146.535

12.01 CAJON 1 m2 1 28.34


12.02 CAJON 2 m2 1 27.38
12.03 CAJON 3 m2 1 9.43
12.04 CAJON 4 m2 1 9.11
12.05 FRISOS m2 1 37.53 0.20 7.51

12.06 EJE A-A m2 1 8.53 0.85 7.25


12.07 EJE C-C m2 1 8.53 0.85 7.25
12.08 EJE 1-1 m2 1 10.86 0.80 8.69
12.09 EJE 3-3 m2 1 10.86 0.80 8.69
12.1 EJE 2-2 m2 2 10.86 1.10 23.89
12.11 Tarima LOSA MACIZA m2 1.00 9.00 1.00 9.00

13.00 PABELLON 03 m2 303.676

13.01 CAJON 1 m2 1 27.66


13.02 CAJON 2 m2 1 27.84
13.03 CAJON 3 m2 1 28.15
13.04 CAJON 4 m2 1 27.39
13.05 CAJON 5 m2 1 9.79
13.06 CAJON 6 m2 1 9.86
13.07 CAJON 7 m2 1 9.95
13.08 CAJON 8 m2 1 9.70
13.09 FRISOS m2 1 54.15 0.20 10.83

13.10 EJE A-A VP m2 1 16.82 1.25 21.03


13.11 EJE C-C VP m2 1 16.82 1.25 21.03
13.12 EJE 1-5 V-101 m2 2 10.26 1.20 24.62
13.13 EJE 2-4 V-103 m2 2 9.94 1.50 29.82
13.14 EJE 5 V-102 m2 1 10.01 1.20 12.01
13.15 Tarima LOSA MACIZA y escalera m2 1.00 34.00 1.00 34.00

14.00 PABELLON 05 m2 289.885

14.01 CAJON 1 m2 1 33.05


14.02 CAJON 2 m2 1 29.62
14.03 CAJON 3 m2 1 27.76
14.04 CAJON 4 m2 1 11.38
14.05 CAJON 5 m2 1 10.20
14.06 CAJON 6 m2 1 9.55
14.07 CAJON 7 m2 1 7.31
14.08 FRISOS m2 1 147.16 0.20 29.43

14.09 EJE 1-4= VP-101 m2 2 10.46 1.20 25.10


14.10 EJE 2-3 =VP-102 m2 2 9.96 1.50 29.88
14.11 EJE C-A = VP m2 2 13.31 1.45 38.60
14.12 Tarima LOSA MACIZA y escalera m2 1.00 38.00 1.00 38.00

VAL 06 - ENCOFRADOS
Zapatas - Arco Techo 30.00 37,615.45
Colum. - Pab. 5 -7 corr. 116.04
Columtas. - Pab. 9-1-2 39.09
Viguetas - Pab. 9 -1 -2 11.96
Aligdo.- Pab 7-6-3 -5 877.64
Escalera - 0.00

Metrado total 1,074.73 S/ 35.00

con Igv 37,615.45


VAL. 07 - ENCOFRADOS 7
EDGARD VILCHEZ NAVARRO
I.E LAS - 26 Octubre
30 NOVIEMBRE DEL 2021

ZAPATAS
ITEM DESCRIPCCION Und ML H M2 TOTAL

1.00 ARCO TECHO - PRIMARIA 30.00

1.01 CAJON 6 - INT. - Arco Techo m2 1 12.00 0.50 6.00


1.02 CAJON 7 - INT. - Arco Techo m2 1 12.00 0.50 6.00
1.03 CAJON 8 - INT. - Arco Techo m2 1 12.00 0.50 6.00
1.04 CAJON 9 - INT. - Arco Techo m2 1 12.00 0.50 6.00
1.05 CAJON 10 - INT. - Arco Techo m2 1 12.00 0.50 6.00

COLUMNAS
2.00 PABELLON 3 - Segundo Nivel 83.10

2.01 C-1 m2 3 0.50 3.00 4.50


2.02 C-2 m2 4 2.20 3.00 26.40
2.03 C-3 m2 6 2.90 3.00 52.20

3.00 PABELLON 6- Segundo Nivel 46.80

3.01 C-1 m2 2 0.50 3.00 3.00


3.02 C-2 m2 4 2.20 3.00 26.40
3.03 C-3 m2 2 2.90 3.00 17.40

4.00 PABELLON 7- Segundo Nivel 29.40

4.01 C-1 m2 2 0.50 3.00 3.00


4.02 C-2 m2 4 2.2 3.00 26.40

COLUMNETAS
5.00 PABELLON 4 10.30

5.01 EJE F-F m2 8 0.50 1.00 4.00


5.02 EJE A-A m2 6 0.50 2.10 6.30

6.00 PABELLON 1 PARAPETO 5.60

6.01 EJE COMPLETO m2 14 0.40 1.00 5.60

VIGUETAS
7.00 PABELLON 4 3.16

7.01 VIGUETA EJE F-F m2 8.27 0.20 1.65


7.02 VIGUETA EJE A-A m2 7.54 0.20 1.51

SOBRECIMIENTOS
8.00 CORREDOR 2.86

8.1 EJE C-C m2 1 1.19 1.07 1.27


8.2 EJE 1-1 m2 1 1.48 1.07 1.58

ALIGERADO - VIGAS
9.00 PABELLON 04-Segundo Nivel m2 384.665

9.01 CAJON 1 m2 1 35.79


9.02 CAJON 2 m2 1 27.25
9.03 CAJON 3 m2 1 27.86
9.04 CAJON 4 m2 1 15.72
9.05 CAJON 5 m2 1 14.32
9.06 CAJON 6 m2 1 26.34
9.07 CAJON 7 m2 1 10.07
9.08 CAJON 8 m2 1 13.32
9.09 CAJON 9 m2 1 5.11
9.1 CAJON 10 m2 1 9.41
9.11 CAJON 11 m2 1 3.59
9.12 CAJON 12-LOSA MACIZA m2 1 12.15
9.13 FRISOS m2 1 66.60 0.20 13.32

9.15 EJE 1-5= VP-101 m2 17.63 1.25 22.04


9.16 EJE 2-3-4 =VP-102 m2 25.89 1.30 33.66
9.17 EJE 6-9 =V-103 m2 19.52 1.05 20.50
9.18 EJE 7 = V-104 m2 9.76 1.10 10.74
9.19 EJE 8= V-105 m2 9.76 1.05 10.25
9.2 EJE F-A-D-B = V-P m2 37.51 1.00 37.51
9.21 Tarima LOSA MACIZA y escalera m2 1.00 22.93 1.00 22.93
9.22 Ramfla de acceso m2 1.00 16.00 0.80 12.80

10.00 PABELLON 07-Segundo Nivel m2 185.833

10.01 CAJON 1 m2 1 38.34


10.02 CAJON 2 m2 1 37.38
10.03 CAJON 3 m2 1 9.43
10.04 CAJON 4 m2 1 9.11
10.05 CAJON 5-LOSA MACIZA m2 1 4.59
10.06 FRISOS m2 1 38.77 0.20 7.75

10.07 EJE A-A m2 1 8.53 0.85 7.25


10.08 EJE C-C m2 1 8.53 0.85 7.25
10.09 EJE 1-1 m2 1 10.86 0.80 8.69
10.1 EJE 3-3 m2 1 10.86 0.80 8.69
10.11 EJE 2-2 m2 2 10.86 1.10 23.89
10.12 Tarima LOSA MACIZA y escalera m2 2.00 8.53 1.00 17.06
10.13 Ramfla de acceso m2 1.00 8.00 0.80 6.40

12.00 PABELLON 06-Segundo Nivel m2 185.833

12.01 CAJON 1 m2 1 38.34


12.02 CAJON 2 m2 1 37.38
12.03 CAJON 3 m2 1 9.43
12.04 CAJON 4 m2 1 9.11
12.05 CAJON 5-LOSA MACIZA m2 1 4.59
12.06 FRISOS m2 1 38.77 0.20 7.75

12.07 EJE A-A m2 1 8.53 0.85 7.25


12.08 EJE C-C m2 1 8.53 0.85 7.25
12.09 EJE 1-1 m2 1 10.86 0.80 8.69
12.1 EJE 3-3 m2 1 10.86 0.80 8.69
12.11 EJE 2-2 m2 2 10.86 1.10 23.89
12.12 Tarima LOSA MACIZA y escalera m2 2.00 8.53 1.00 17.06
9.22 Ramfla de acceso m2 1.00 8.00 0.80 6.40

VAL 07 - ENCOFRADOS
Zapatas - Arco Techo 30.00 33,864.23
Colum. - Pab. 3-7-6 corr. 159.30
Colmtas. - Pab. 4 15.90
Vigueta. - Pab. 4 3.16
Sobrec. - Corr. 2.86
Algdo.- Pab 4-7-6 756.33
Metrado total 967.55 S/ 35.00

Inc. Igv 33,864.23

VAL. 08 - ENCOFRADOS 8
EDGARD VILCHEZ NAVARRO
I.E LAS - 26 Octubre
15 DICIEMBRE DEL 2021

ITEM DESCRIPCCION Und ML H M2 TOTAL

ZAPATAS
1.00 ARCO TECHO - Secundaria 30.00

1.01 CAJON 1 - INT. - Arco Techo m2 1 12.00 0.50 6.00


1.02 CAJON 2 - INT. - Arco Techo m2 1 12.00 0.50 6.00
1.03 CAJON 3 - INT. - Arco Techo m2 1 12.00 0.50 6.00
1.04 CAJON 4 - INT. - Arco Techo m2 1 12.00 0.50 6.00

1.05 CAJON 5 - INT. - Arco Techo m2 1 12.00 0.50 6.00

COLUMNAS ARCO TECHO


2.00 ARCO TECHO- Primaria 73.73

2.01 C-1 m2 4 2.40 7.68 73.73

TARIMA-COLUMNAS ARCO TECHO


2.00 TARIMAS 40.00

2.01 TARIMAS PARA COLUMNAS ARCO TECHO m2 4 10.00 40.00

COLUMNETAS
3.00 PABELLON 1 - Segundo Nivel 19.55

3.00 EJE C-C m2 12 0.50 1.00 6.00


3.10 EJE A-A m2 9 0.50 2.10 9.45
3.20 EJE A-A m2 3 0.65 2.10 4.10

4.00 PABELLON 2- Segundo Nivel 13.03

4.10 EJE C-C m2 8 0.50 1.00 4.00


4.20 EJE A-A m2 6 0.50 2.10 6.30
4.30 EJE A-A m2 2 0.65 2.10 2.73

VIGUETAS
5.00 PABELLON 1 -Segundo Nivel 11.93

5.10 VIGUETA EJE C-C m2 16.34 0.40 6.54


5.20 VIGUETA EJE A-A m2 13.48 0.40 5.39

6.00 PABELLON 2- Segundo Nivel 7.96

6.10 VIGUETA EJE C-C m2 10.92 0.40 4.37


6.20 VIGUETA EJE A-A m2 8.97 0.40 3.59

7.00 PABELLON 1 - Parapeto Completo 26.29

7.10 VIGUETA EJE C-C m2 25.15 0.40 10.06


7.20 VIGUETA EJE A-A m2 25.15 0.40 10.06
7.30 VIGUETA EJE 1-1 m2 7.71 0.40 3.08
7.40 VIGUETA EJE 7-7 m2 7.71 0.40 3.08

ALIGERADO - VIGAS
8.00 PABELLON 03 Segundo Nivel m2 297.636

8.10 CAJON 1 m2 1 27.66


8.20 CAJON 2 m2 1 27.84
8.30 CAJON 3 m2 1 28.15
8.40 CAJON 4 m2 1 27.39
8.00 CAJON 5 m2 1 9.79
8.00 CAJON 6 m2 1 9.86
8.60 CAJON 7 m2 1 9.95
8.70 CAJON 8 m2 1 9.70
8.80 CAJON 9 LOSA MACIZA m2 1 9.24
8.90 FRISOS m2 1 55.35 0.20 11.07

8.10 EJE A-A VP m2 1 16.82 1.25 21.03


8.11 EJE C-C VP m2 1 16.82 1.25 21.03
8.12 EJE 1-5 V-101 m2 2 10.26 1.20 24.62
8.13 EJE 2-4 V-103 m2 2 9.94 1.50 29.82
8.14 EJE 5 V-102 m2 1 10.01 1.20 12.01
8.15 Tarima LOSA MACIZA y escalera m2 2.00 9.24 1.00 18.48

RAMPA - ALIGERADO
2.00 RAMPA 24.91

2.01 PABELLON 6-Segundo Nivel m2 2 0.73 8.53 12.45


PABELLON 3-Segundo Nivel m2 2 0.73 8.53 12.45

VAL 08 - ENCOFRADOS
Zapatas. Colum. Techo-Prim. 30.00 19,075.65
Colum. Arco Techo-Prim. 73.73
Colmtas. - Pab.1-2 Seg.Nivel 32.58
Vigueta. - Pab. 1-2 Seg. Nivel 46.17
Algdo.- Pab 3.seg.Nivel 297.64

Rampa -Aligerado 24.91


Tarima-Arco Techo 40.00
Metrado total 545.02 S/ 35.00

Inc. Igv 19,075.65


VAL. 09 - ENCOFRADOS 9

EDGARD VILCHEZ NAVARRO


I.E LAS - 26 Octubre
28 DICIEMBRE DEL 2021

ITEM DESCRIPCCION Und ML H M2 TOTAL

ZAPATAS
1.00 ARCO TECHO - Secundaria 12.00

1.01 CAJON 6 - INT. - Arco Techo m2 1 12.00 0.50 6.00


1.02 CAJON 7 - INT. - Arco Techo m2 1 12.00 0.50 6.00

COLUMNAS
2.00 ESCALERAS - Primer Descanso 10.03

C-4 -EJE 7-8 m2 2 1.70 2.95 10.03

3.00 CORREDOR m2 3.927

C-c m2 1 1.10 3.57 3.93

COLUMNAS ARCO TECHO


2.00 ARCO TECHO- Primaria 184.32

2.01 C-1 (6 Primaria-4 Secundaria) m2 10 2.40 7.68 184.32

TARIMA-COLUMNAS ARCO TECHO


3.00 TARIMAS 100.00

3.01 TARIMAS PARA COLUMNAS ARCO TECHO m2 10 10.00 100.00

COLUMNETAS
4.00 PABELLON 7 - Primer Nivel 6.52

4.01 EJE C-C m2 4 0.50 1.00 2.00


4.02 EJE A-A m2 3 0.50 2.10 3.15
4.03 EJE A-A m2 1 0.65 2.10 1.37

5.00 PABELLON 2- Parapeto Completo 6.05


5
5.01 EJE C-C m2 5 0.40 1.08 2.16
5.02 EJE A-A m2 5 0.40 1.08 2.16
5.03 EJE 8-8 m2 2 0.40 1.08 0.86
5.04 EJE 12-12 m2 2 0.40 1.08 0.86
VIGUETAS
7.00 PABELLON 7 - Primer Nivel 4.03

7.01 VIGUETA EJE C-C m2 5.53 0.40 2.21


7.02 VIGUETA EJE A-A m2 4.55 0.40 1.82

8.00 PABELLON 2- Parapeto Completo 22.14

8.01 VIGUETA EJE C-C m2 16.82 0.40 6.73


8.02 VIGUETA EJE A-A m2 16.82 0.40 6.73
8.03 VIGUETA EJE 8-8 m2 10.86 0.40 4.34
8.04 VIGUETA EJE 12-12 m2 10.86 0.40 4.34

ESCALERAS
2.00 ESCALERA PABELLON 4-Pimer Nivel m2 60.195

1.01 CAJON 1 m2 1 8.75


1.02 CAJON 2 m2 1 5.25
1.03 CAJON 3 m2 1 7.30
1.04 CAJON 4 m2 1 5.25

2.1 EJE 7-8 m2 2 9.00 1.20 21.60


2.2 EJE A-C m2 2 3.65 1.45 10.59
2.3 V-B m2 1 3.65 0.40 1.46

ARCOTECHO VIGAS
2.00 ARCO TECHO (viga eje 2)-PRIMARIA m2 21.460

1.01 CAJON 1 m2 1 5.81


1.02 CAJON 2 m2 1 4.92
1.03 CAJON 3 m2 1 4.92
1.04 CAJON 4 m2 1 5.81

2.00 TARIMA PARA VIGA (viga eje 2)-PRIMARIA m2 21.460

1.01 CAJON 1 m2 1 5.81


1.02 CAJON 2 m2 1 4.92
1.03 CAJON 3 m2 1 4.92
1.04 CAJON 4 m2 1 5.81

TARIMA TARRAJEO
2.00 PABELLÓN 2 - FACHADA LATERAL m2 19.548

1.01 Madera m2 1 10.86 1.80 19.55

VAL 09 - ENCOFRADOS
Zapatas. Arcot. - secund 12.00
Columnas. Escalera 13.96

Columnas. Arco Techo 184.32

Tarima Columnas 100.00


Columnetas. - Pab.7-1
Nivel, Pab.2 - Parapeto 12.56
16,508.77
Viguetas. - Pab.7-1 Nivel,
Pab.2 - Parapeto 26.18

Escaleras. Pabellón 4 -
Primer Nivel 60.20

Arcotecho Vigas y
Tarima. Eje 2-Primaria 42.92
Tarimas para Tarrajeo 19.55
Metrado total 471.68 S/ 35.00

Inc. Igv 16,508.77


VAL. 01 - ENCOFRADOS 1
Horly Percy Michilot Garcia
I.E LAS - 26 Octubre
16 DICIEMBRE DEL 2021

ITEM DESCRIPCCION Und ML H M2 TOTAL

ZAPATAS- CERCO
1.00 Cerco 36.260

1.01 CAJON 1 - INT. Cerco m2 1 6.00 0.70 4.20


1.02 CAJON 2 - INT. Cerco m2 1 4.40 0.70 3.08
1.03 CAJON 3 - INT. Cerco m2 1 5.00 0.70 3.50
1.04 CAJON 4 - INT. Cerco m2 1 4.40 0.70 3.08
1.05 CAJON 5 - INT. Cerco m2 1 4.40 0.70 3.08
1.06 CAJON 6 - INT. Cerco m3 1 4.40 0.70 3.08
1.07 CAJON 7 - INT. Cerco m4 1 4.40 0.70 3.08
1.08 CAJON 8 - INT. Cerco m5 1 5.00 0.70 3.50
1.09 CAJON 9 - INT. Cerco m6 1 4.40 0.70 3.08
1.10 CAJON 10 - INT. Cerco m7 1 4.40 0.70 3.08
1.11 CAJON 11 - INT. Cerco m8 1 5.00 0.70 3.50

CIMIENTO -CORRIDO
1.00 Cimiento Corrido-Cerco 22.652

1.01 Cimiento 1 - INT. Cerco m2 2 1.70 0.70 2.38


1.02 Cimiento 2 - INT. Cerco m2 2 1.64 0.70 2.30
1.03 Cimiento 3 - INT. Cerco m2 2 1.68 0.70 2.35
1.04 Cimiento 4 - INT. Cerco m2 2 1.65 0.70 2.31
1.05 Cimiento 5 - INT. Cerco m2 2 1.68 0.70 2.35
1.06 Cimiento 6 - INT. Cerco m3 2 1.68 0.70 2.35
1.07 Cimiento 7 - INT. Cerco m4 2 2.70 0.70 3.78
1.08 Cimiento 8 - INT. Cerco m5 2 1.65 0.70 2.31
1.09 Cimiento 9 - INT. Cerco m6 2 0.80 0.70 1.12
1.10 Cimiento 10 - INT. Cerco m7 2 1.00 0.70 1.40

VAL 01 - ENCOFRADOS
ZAPATAS- CERCO 36.26 2,061.92
CIMIENTO -CORRIDO 22.65

Metrado total 58.91 S/ 35.00

Con. Igv 2,061.92


VAL. 02 - ENCOFRADOS 2

Horly Percy Michilot Garcia


I.E LAS - 26 Octubre
29 DICIEMBRE DEL 2021

ITEM DESCRIPCCION Und ML H M2 TOTAL

ZAPATAS- CERCO
1.00 Cerco 35.140

1.01 CAJON 12 - INT. Cerco m2 1 4.40 0.70 3.08


1.02 CAJON 13 - INT. Cerco m2 1 4.40 0.70 3.08
1.03 CAJON 14 - INT. Cerco m3 1 5.00 0.70 3.50
1.04 CAJON 15 - INT. Cerco m2 1 4.40 0.70 3.08
1.05 CAJON 16 - INT. Cerco m2 1 4.40 0.70 3.08
1.06 CAJON 17 - INT. Cerco m2 1 5.00 0.70 3.50
1.07 CAJON 18 - INT. Cerco m2 1 4.40 0.70 3.08
1.08 CAJON 19 - INT. Cerco m2 1 4.40 0.70 3.08
1.09 CAJON 20 - INT. Cerco m2 1 5.00 0.70 3.50
1.1 CAJON 21 - INT. Cerco m2 1 4.40 0.70 3.08
1.11 CAJON 22 - INT. Cerco m2 1 4.40 0.70 3.08

COLUMNAS- CERCO
2.00 Cerco 15.925

2.01 Columna C-1 m2 1 0.85 1.30 1.11


2.02 Columna C-1 m2 1 0.70 1.30 0.91
2.03 Columna C-1 m2 1 1.20 1.30 1.56
2.04 Columna C-1 m2 1 0.70 1.30 0.91
2.05 Columna C-1 m2 1 1.35 1.30 1.76
2.06 Columna C-1 m2 1 0.70 1.30 0.91
2.07 Columna C-1 m2 1 0.70 1.30 0.91
2.08 Columna C-1 m2 1 1.20 1.30 1.56
2.09 Columna C-1 m2 1 0.70 1.30 0.91
2.10 Columna C-1 m2 1 0.70 1.30 0.91
2.11 Columna C-1 m2 1 1.20 1.30 1.56
2.12 Columna C-1 m2 1 0.70 1.30 0.91
2.13 Columna C-1 m2 1 0.70 1.30 0.91
2.14 Columna C-1 m2 1 0.85 1.30 1.11

CIMIENTO -CORRIDO
3.00 Cimiento Corrido-Cerco 21.336

3.01 Cimiento 1 - INT. Cerco m2 2 1.69 0.70 2.37


3.02 Cimiento 2 - INT. Cerco m2 2 1.70 0.70 2.38
3.03 Cimiento 3 - INT. Cerco m2 2 1.69 0.70 2.37
3.04 Cimiento 4 - INT. Cerco m2 2 1.69 0.70 2.37
3.05 Cimiento 4 - INT. Cerco m3 2 1.70 0.70 2.38
3.06 Cimiento 4 - INT. Cerco m4 2 1.69 0.70 2.37
3.07 Cimiento 4 - INT. Cerco m5 2 1.69 0.70 2.37
3.08 Cimiento 4 - INT. Cerco m6 2 1.70 0.70 2.38
3.09 Cimiento 4 - INT. Cerco m7 2 1.69 0.70 2.37

SOBRECIMIENTO
4.00 Sobrecimiento-Cerco 90.818

4.01 Sobrecimiento 1 - INT. Cerco m2 2 3.66 1.30 9.52


4.02 Sobrecimiento 2 - INT. Cerco m2 2 2.75 1.30 7.15
4.03 Sobrecimiento 3 - INT. Cerco m2 2 1.90 1.30 4.94
4.04 Sobrecimiento 4 - INT. Cerco m2 2 1.87 1.30 4.86
4.05 Sobrecimiento 5 - INT. Cerco m2 2 2.75 1.30 7.15
4.06 Sobrecimiento 6 - INT. Cerco m2 2 2.75 1.30 7.15
4.07 Sobrecimiento 7 - INT. Cerco m2 2 2.75 1.30 7.15
4.08 Sobrecimiento 8 - INT. Cerco m2 2 2.75 1.30 7.15
4.09 Sobrecimiento 9 - INT. Cerco m2 2 2.75 1.30 7.15
4.10 Sobrecimiento 10 - INT. Cerco m2 2 2.75 1.30 7.15
4.11 Sobrecimiento 11 - INT. Cerco m2 2 2.75 1.30 7.15
4.10 Sobrecimiento 12 - INT. Cerco m2 2 2.75 1.30 7.15
4.13 Sobrecimiento 13 - INT. Cerco m2 2 2.75 1.30 7.15

VAL 02 - ENCOFRADOS
ZAPATAS 35.14 5,712.67
COLUMNAS 15.93
CIMIENTO CORRIDO 21.34
SOBRECIMIENTO 90.82

Metrado total 163.22 S/ 35.00

Con. Igv 5,712.67


VAL. 03 - ENCOFRADOS 3

Horly Percy Michilot Garcia


I.E LAS - 26 Octubre
15 ENERO DEL 2022

ITEM DESCRIPCCION Und ML H M2 TOTAL

CIMIENTO -CORRIDO
2.00 Cimiento Corrido-Cerco 4.760

3.01 Cimiento 1 - INT. Cerco m2 2 1.70 0.70 2.38


3.02 Cimiento 2 - INT. Cerco m2 2 1.70 0.70 2.38

COLUMNAS- CERCO
3.00 Cerco 55.26

2.01 Columna C-1 m2 1 0.60 1.30 0.78


2.02 Columna C-1 m2 1 0.70 1.30 0.91
2.03 Columna C-1 m2 1 0.70 1.30 0.91
2.04 Columna C-1 m2 1 0.85 1.30 1.11
2.05 Columna C-1 m2 1 0.60 1.30 0.78
2.06 Columna C-1 m2 1 0.70 1.30 0.91
2.07 Columna C-1 m2 1 0.70 1.30 0.91
2.08 Columna C-1 m2 1 0.85 1.30 1.11
2.09 Columna C-1 Completa m2 1 0.85 3.00 2.55
2.10 Columna C-1 Completa m2 1 0.70 3.00 2.10
2.11 Columna C-1 Completa m2 1 0.85 3.00 2.55
2.12 Columna C-1 Completa m2 1 0.60 3.00 1.80
2.13 Columna C-1 Completa m2 1 0.70 3.00 2.10
2.14 Columna C-1 Completa m2 1 0.85 3.00 2.55
2.15 Columna C-1 Completa m2 1 0.60 3.00 1.80
2.16 Columna C-1 Completa m2 1 0.70 3.00 2.10
2.17 Columna C-1 Completa m2 1 0.70 3.00 2.10
2.18 Columna C-1 Completa m2 1 0.85 3.00 2.55
2.19 Columna C-1 Completa m2 1 0.60 3.00 1.80
2.20 Columna C-1 Completa m2 1 0.70 3.00 2.10
2.21 Columna C-1 Completa m2 1 0.70 3.00 2.10
2.22 Columna C-1 Completa m2 1 0.85 3.00 2.55
2.23 Columna C-1 Completa m2 1 0.60 3.00 1.80
2.24 Columna C-1 Completa m2 1 0.70 3.00 2.10
2.25 Columna C-1 Completa m2 1 0.70 3.00 2.10
2.26 Columna C-1 Completa m2 1 0.85 3.00 2.55
2.27 Columna C-1 Completa m2 1 0.60 3.00 1.80
2.28 Columna C-1 Completa m2 1 0.70 3.00 2.10
2.29 Columna C-1 Completa m2 1 0.70 3.00 2.10
2.30 Columna C-1 Completa m2 1 0.85 3.00 2.55

SOBRECIMIENTO
4.00 Sobrecimiento-Cerco 42.900

4.01 Sobrecimiento 1 - INT. Cerco m2 2 2.75 1.30 7.15


4.02 Sobrecimiento 2 - INT. Cerco m2 2 2.75 1.30 7.15
4.03 Sobrecimiento 3 - INT. Cerco m2 2 2.75 1.30 7.15
4.04 Sobrecimiento 4 - INT. Cerco m2 2 2.75 1.30 7.15
4.05 Sobrecimiento 5 - INT. Cerco m2 2 2.75 1.30 7.15
4.06 Sobrecimiento 13 - INT. Cerco m2 2 2.75 1.30 7.15

VAL 03 - ENCOFRADOS
CIMIENTO CORRIDO 4.76
COLUMNAS 55.26
SOBRECIMIENTO 42.90

Metrado total 102.92 S/ 35.00

Sin. Igv 3,602.20


VAL. 04 - ENCOFRADOS 4
Horly Percy Michilot Garcia
I.E LAS - 26 Octubre
31 ENERO DEL 2022

ITEM DESCRIPCCION Und ML H M2 TOTAL

ZAPATAS- CERCO
1.00 Cerco 64.54

1.01 CAJON 23 - INT. Cerco m2 1 5.00 0.70 3.50


1.02 CAJON 24 - INT. Cerco m2 1 4.40 0.70 3.08
1.03 CAJON 25 - INT. Cerco m2 1 4.40 0.70 3.08
1.04 CAJON 26 - INT. Cerco m2 1 5.00 0.70 3.50
1.05 CAJON 27 - INT. Cerco m2 1 4.40 0.70 3.08
1.06 CAJON 28 - INT. Cerco m2 1 4.40 0.70 3.08
1.07 CAJON 29 - INT. Cerco m2 1 4.40 0.70 3.08
1.08 CAJON 30 - INT. Cerco m2 1 5.00 0.70 3.50
1.09 CAJON 31 - INT. Cerco m2 1 4.40 0.70 3.08
1.10 CAJON 32 - INT. Cerco m2 1 4.40 0.70 3.08
1.11 CAJON 33 - INT. Cerco m2 1 5.00 0.70 3.50
1.12 CAJON 34 - INT. Cerco m2 1 4.40 0.70 3.08
1.13 CAJON 35 - INT. Cerco m2 1 4.40 0.70 3.08
1.14 CAJON 36 - INT. Cerco m2 1 5.00 0.70 3.50
1.15 CAJON 36 - INT. Cerco m2 1 4.40 0.70 3.08
1.16 CAJON 36 - INT. Cerco m2 1 4.40 0.70 3.08
1.17 CAJON 36 - INT. Cerco m2 1 5.00 0.70 3.50
1.18 CAJON 36 - INT. Cerco m2 1 4.40 0.70 3.08
1.19 CAJON 36 - INT. Cerco m2 1 4.40 0.70 3.08
1.20 CAJON 36 - INT. Cerco m2 1 5.00 0.70 3.50

CIMIENTO -CORRIDO
2.00 Cimiento Corrido-Cerco 39.27

2.01 Cimiento 22 - INT. Cerco m2 2 1.70 0.70 2.38


2.02 Cimiento 23 - INT. Cerco m2 2 1.70 0.70 2.38
2.03 Cimiento 24 - INT. Cerco m2 2 1.70 0.70 2.38
2.04 Cimiento 25 - INT. Cerco m2 2 1.70 0.70 2.38
2.05 Cimiento 26 - INT. Cerco m2 2 1.00 0.70 1.40
2.06 Cimiento 27 - INT. Cerco m2 2 1.55 0.70 2.17
2.07 Cimiento 28 - INT. Cerco m2 2 1.70 0.70 2.38
2.08 Cimiento 29 - INT. Cerco m2 2 1.70 0.70 2.38
2.09 Cimiento 30 - INT. Cerco m2 2 1.70 0.70 2.38
2.1 Cimiento 31 - INT. Cerco m2 2 1.70 0.70 2.38
2.11 Cimiento 32 - INT. Cerco m2 2 1.70 0.70 2.38
2.12 Cimiento 33 - INT. Cerco m2 2 1.70 0.70 2.38
2.13 Cimiento 34 - INT. Cerco m2 2 1.70 0.70 2.38
2.14 Cimiento 35 - INT. Cerco m2 2 1.70 0.70 2.38
2.15 Cimiento 36 - INT. Cerco m2 2 1.70 0.70 2.38
2.16 Cimiento 37 - INT. Cerco m2 2 1.70 0.70 2.38
2.17 Cimiento 38 - INT. Cerco m2 2 1.70 0.70 2.38

SOBRECIMIENTO
3.00 Sobrecimiento-Cerco 157.46

3.01 Sobrecimiento 20 - INT. Cerco m2 2 2.75 1.30 7.15


3.02 Sobrecimiento 21 - INT. Cerco m2 2 2.75 1.30 7.15
3.03 Sobrecimiento 22 - INT. Cerco m2 2 2.75 1.30 7.15
3.04 Sobrecimiento 23 - INT. Cerco m2 2 2.75 1.30 7.15
3.05 Sobrecimiento 24 - INT. Cerco m2 2 2.75 1.30 7.15
3.06 Sobrecimiento 25 - INT. Cerco m2 2 2.75 1.30 7.15
3.07 Sobrecimiento 26 - INT. Cerco m2 2 2.70 1.30 7.02
3.08 Sobrecimiento 27 - INT. Cerco m2 2 2.86 1.30 7.44
3.09 Sobrecimiento 28 - INT. Cerco m2 2 2.75 1.30 7.15
3.10 Sobrecimiento 29 - INT. Cerco m2 2 2.75 1.30 7.15
3.11 Sobrecimiento 30 - INT. Cerco m2 2 2.75 1.30 7.15
3.12 Sobrecimiento 31 - INT. Cerco m2 2 2.75 1.30 7.15
3.13 Sobrecimiento 32 - INT. Cerco m2 2 2.75 1.30 7.15
3.14 Sobrecimiento 33 - INT. Cerco m2 2 2.75 1.30 7.15
3.15 Sobrecimiento 34 - INT. Cerco m2 2 2.75 1.30 7.15
3.16 Sobrecimiento 35 - INT. Cerco m2 2 2.75 1.30 7.15
3.17 Sobrecimiento 36 - INT. Cerco m2 2 2.75 1.30 7.15
3.18 Sobrecimiento 37 - INT. Cerco m2 2 2.75 1.30 7.15
3.19 Sobrecimiento 38 - INT. Cerco m2 2 2.75 1.30 7.15
3.20 Sobrecimiento 39 - INT. Cerco m2 2 2.75 1.30 7.15
3.21 Sobrecimiento 40 - INT. Cerco m2 2 2.75 1.30 7.15
3.22 Sobrecimiento 41 - INT. Cerco m2 2 2.75 1.30 7.15

COLUMNAS- CERCO
4.00 Cerco 27.82

4.01 Columna C-1 m2 1 0.60 1.30 0.78


4.02 Columna C-1 m2 1 0.70 1.30 0.91
4.03 Columna C-1 m2 1 0.70 1.30 0.91
4.04 Columna C-1 m2 1 0.85 1.30 1.11
4.05 Columna C-1 m2 1 0.60 1.30 0.78
4.06 Columna C-1 m2 1 0.70 1.30 0.91
4.07 Columna C-1 m2 1 0.70 1.30 0.91
4.08 Columna C-1 m2 1 0.85 1.30 1.11
4.09 Columna C-1 m2 1 0.60 1.30 0.78
4.10 Columna C-1 m2 1 0.85 1.30 1.11
4.11 Columna C-1 m2 1 0.60 1.30 0.78
4.12 Columna C-1 m2 1 0.70 1.30 0.91
4.13 Columna C-1 m2 1 0.70 1.30 0.91
4.14 Columna C-1 m2 1 0.85 1.30 1.11
4.15 Columna C-1 m2 1 0.60 1.30 0.78
4.16 Columna C-1 m2 1 0.70 1.30 0.91
4.17 Columna C-1 m2 1 0.70 1.30 0.91
4.18 Columna C-1 m2 1 0.85 1.30 1.11
4.19 Columna C-1 m2 1 0.60 1.30 0.78
4.20 Columna C-1 m2 1 0.70 1.30 0.91
4.21 Columna C-1 m2 1 0.70 1.30 0.91
4.22 Columna C-1 m2 1 0.85 1.30 1.11
4.23 Columna C-1 m2 1 0.60 1.30 0.78
4.24 Columna C-1 m2 1 0.70 1.30 0.91
4.25 Columna C-1 m2 1 0.70 1.30 0.91
4.26 Columna C-1 m2 1 0.85 1.30 1.11
4.27 Columna C-1 m2 1 0.60 1.30 0.78
4.28 Columna C-1 m2 1 0.70 1.30 0.91
4.29 Columna C-1 m2 1 0.70 1.30 0.91
4.30 Columna C-1 m2 1 0.85 1.30 1.11

VIGAS- CERCO
5.00 Cerco 21.20

5.01 VIGA VS (0,15X0,20) m2 1 51.10 0.20 10.22


5.02 VIGA VS (0,15X0,20) con pinto m2 1 54.90 0.20 10.98

VAL 03 - ENCOFRADOS
ZAPATAS 64.54
CIMIENTO CORRIDO 39.27
COLUMNAS 27.82
SOBRECIMIENTO 157.46
VIGAS 21.20

Metrado total 310.29 S/ 35.00

Sin. Igv 10,860.01


VAL. 01 - EJECUCION
VACIADOS DE CONCRETO
Horly Percy Michilot Garcia
16 DE DICIEMBRE DEL 2021

ZAPATAS- CONCRETO
1.00 ZAPATAS-Cerco=fc 210 M3

1.00 ZAPATAS-Cerco=fc 210 m3 1 2.10 0.70 0.90 1.32


1.2 ZAPATAS-Cerco=fc 210 m3 1 1.30 0.70 0.90 0.82
1.3 ZAPATAS-Cerco=fc 210 m4 1 1.60 0.70 0.90 1.01
1.4 ZAPATAS-Cerco=fc 210 m5 1 1.30 0.70 0.90 0.82
1.5 ZAPATAS-Cerco=fc 210 m6 1 1.00 1.20 0.70 0.84
1.6 ZAPATAS-Cerco=fc 210 m7 1 1.30 0.70 0.90 0.82
1.7 ZAPATAS-Cerco=fc 210 m8 1 1.30 0.70 0.90 0.82
1.8 ZAPATAS-Cerco=fc 210 m9 1 1.60 0.70 0.90 1.01
1.9 ZAPATAS-Cerco=fc 210 m10 1 1.30 0.70 0.90 0.82
1.10 ZAPATAS-Cerco=fc 210 m11 1 1.30 0.70 0.90 0.82
1.11 ZAPATAS-Cerco=fc 210 m12 1 1.60 0.70 0.90 1.01

CIMIENTO CORRIDO- CONCRETO


1.00 Cimiento Corrido-Cerco=fc 110 M3

1.00 Cimiento Corrido-Cerco=fc 110 m3 1 1.70 0.70 0.60 0.71


1.2 Cimiento Corrido-Cerco=fc 111 m3 1 1.64 0.70 0.60 0.69
1.3 Cimiento Corrido-Cerco=fc 112 m4 1 1.68 0.70 0.60 0.71
1.4 Cimiento Corrido-Cerco=fc 113 m5 1 1.65 0.70 0.60 0.69
1.5 Cimiento Corrido-Cerco=fc 114 m6 1 1.68 0.70 0.60 0.71
1.6 Cimiento Corrido-Cerco=fc 115 m7 1 1.68 0.70 0.60 0.71
1.7 Cimiento Corrido-Cerco=fc 116 m8 1 2.70 0.70 0.60 1.13
1.8 Cimiento Corrido-Cerco=fc 117 m9 1 1.65 0.70 0.60 0.69
1.9 Cimiento Corrido-Cerco=fc 118 m10 1 0.80 0.70 0.60 0.34
1.10 Cimiento Corrido-Cerco=fc 119 m11 1 1.00 0.70 0.60 0.42

VAL 01 - EJECUCION
ZAPATAS 10.10 65.00
CIMIENTO CORRIDO 6.80 60.00

Con. Igv
VAL. 02 - EJECUCION
VACIADOS DE CONCRETO
Horly Percy Michilot Garcia
29 DE DICIEMBRE DEL 2021

ZAPATAS- CONCRETO
ITEM DESCRIPCCION Und L A H M3

1.00 ZAPATAS-Cerco=fc 210 M3

1.00 ZAPATAS-Cerco=fc 210 m3 1 1.30 0.90 0.70 0.82


1.2 ZAPATAS-Cerco=fc 210 m3 1 1.30 0.90 0.70 0.82
1.3 ZAPATAS-Cerco=fc 210 m3 1 1.60 0.90 0.70 1.01
1.4 ZAPATAS-Cerco=fc 210 m3 1 1.30 0.90 0.70 0.82
1.5 ZAPATAS-Cerco=fc 210 m3 1 1.30 0.90 0.70 0.82
1.6 ZAPATAS-Cerco=fc 210 m3 1 1.60 0.90 0.70 1.01
1.7 ZAPATAS-Cerco=fc 210 m3 1 1.30 0.90 0.70 0.82
1.8 ZAPATAS-Cerco=fc 210 m3 1 1.30 0.90 0.70 0.82

COLUMNA- CONCRETO
2.00 Cerco

2.01 Columna C-1 m2 1 0.25 0.25 1.30 0.08


2.02 Columna C-1 m2 1 0.25 0.25 1.30 0.08
2.03 Columna C-1 m2 1 0.25 0.50 1.30 0.16
2.04 Columna C-1 m2 1 0.25 0.25 1.30 0.08
2.05 Columna C-1 m2 1 0.25 0.50 1.30 0.16
2.06 Columna C-1 m2 1 0.25 0.25 1.30 0.08
2.07 Columna C-1 m2 1 0.25 0.25 1.30 0.08
2.08 Columna C-1 m2 1 0.25 0.50 1.30 0.16
2.09 Columna C-1 m2 1 0.25 0.25 1.30 0.08
2.10 Columna C-1 m3 1 0.25 0.25 1.30 0.08
2.11 Columna C-1 m3 1 0.25 0.50 1.30 0.16
2.12 Columna C-1 m3 1 0.25 0.25 1.30 0.08
2.13 Columna C-1 m3 1 0.25 0.25 1.30 0.08
2.14 Columna C-1 m3 1 0.25 0.25 1.30 0.08

CIMIENTO CORRIDO- CONCRETO


3.00 Cimiento Corrido-Cerco=fc 110 M3

3.1 Cimiento Corrido-Cerco=fc 110 m3 1 1.70 0.70 0.60 0.71


3.2 Cimiento Corrido-Cerco=fc 110 m3 1 1.70 0.70 0.60 0.71
3.3 Cimiento Corrido-Cerco=fc 110 m3 1 1.70 0.70 0.60 0.71
3.4 Cimiento Corrido-Cerco=fc 110 m3 1 1.70 0.70 0.60 0.71
3.5 Cimiento Corrido-Cerco=fc 110 m3 1 1.70 0.70 0.60 0.71
3.6 Cimiento Corrido-Cerco=fc 110 m3 1 1.70 0.70 0.60 0.71
3.7 Cimiento Corrido-Cerco=fc 110 m3 1 1.70 0.70 0.60 0.71
3.8 Cimiento Corrido-Cerco=fc 110 m3 1 1.70 0.70 0.60 0.71
3.9 Cimiento Corrido-Cerco=fc 110 m3 1 1.70 0.70 0.60 0.71

SOBRECIMIENTO - CONCRETO
4.00 Sobrecimiento-Cerco=fc 100 M3

4.1 Sobrecimiento 1 - INT. Cerco m3 1 3.66 1.30 0.13 0.62


4.2 Sobrecimiento 2 - INT. Cerco m3 1 2.75 1.30 0.13 0.46
4.3 Sobrecimiento 3 - INT. Cerco m3 1 1.90 1.30 0.13 0.32
4.4 Sobrecimiento 4 - INT. Cerco m3 1 1.87 1.30 0.13 0.32
4.5 Sobrecimiento 5 - INT. Cerco m3 1 2.75 1.30 0.13 0.46
4.6 Sobrecimiento 6 - INT. Cerco m3 1 2.75 1.30 0.13 0.46
4.7 Sobrecimiento 7 - INT. Cerco m3 1 2.75 1.30 0.13 0.46
4.8 Sobrecimiento 8 - INT. Cerco m3 1 2.75 1.30 0.13 0.46
4.9 Sobrecimiento 9 - INT. Cerco m3 1 2.75 1.30 0.13 0.46
4.10 Sobrecimiento 10 - INT. Cerco m3 1 2.75 1.30 0.13 0.46
4.11 Sobrecimiento 11 - INT. Cerco m3 1 2.75 1.30 0.13 0.46
4.12 Sobrecimiento 12 - INT. Cerco m3 1 2.75 1.30 0.13 0.46
4.13 Sobrecimiento 13 - INT. Cerco m3 1 2.75 1.30 0.13 0.46

VAL 02 - EJECUCION
ZAPATAS 6.93 65.00
COLUMNAS 1.46 75.00
CIMIENTO CORRIDO 6.43 60.00
SOBRECIMIENTO 5.90 65.00

Con. Igv
VAL. 03 - EJECUCION
VACIADOS DE CONCRETO
Horly Percy Michilot Garcia
15 DE ENERO DEL 2022

COLUMNA- CONCRETO
2.00 Cerco

2.01 Columna C-1 m3 8 0.25 0.25 1.30 0.65


2.02 Columna C-1 m3 22 0.25 0.25 3.00 4.13

CIMIENTO CORRIDO- CONCRETO


1.00 Cimiento Corrido-Cerco=fc 110 M3

1.10 Cimiento Corrido-Cerco=fc 110 m3 1 1.70 0.70 0.60 0.71


1.2 Cimiento Corrido-Cerco=fc 110 m3 1 1.70 0.70 0.60 0.71

SOBRECIMIENTO - CONCRETO
1.00 Sobrecimiento-Cerco=fc 100 M3

1.01 Sobrecimiento 1 - INT. Cerco m3 1 2.75 1.30 0.13 0.46


1.02 Sobrecimiento 2 - INT. Cerco m3 1 2.75 1.30 0.13 0.46
1.03 Sobrecimiento 3 - INT. Cerco m3 1 2.75 1.30 0.13 0.46
1.04 Sobrecimiento 4 - INT. Cerco m3 1 2.75 1.30 0.13 0.46
1.05 Sobrecimiento 5 - INT. Cerco m3 1 2.75 1.30 0.13 0.46
2.05 Sobrecimiento 5 - INT. Cerco m4 1 2.75 1.30 0.13 0.46

VAL 03 - EJECUCIÓN
COLUMNAS 4.78 75.00 358.13
CIMIENTO CORRIDO 1.43 60.00 85.68
SOBRECIMIENTO 2.79 65.00 181.25
VAL. 04 - EJECUCION
VACIADOS DE CONCRETO
Horly Percy Michilot Garcia
31 DE ENERO DEL 2022

ITEM DESCRIPCCION Und L A H M3

ZAPATAS- CERCO
1.00 ZAPATAS-Cerco=fc 210 M3

1.01 ZAPATAS-Cerco=fc 210 m3 7 1.60 0.90 0.70 7.06


1.02 ZAPATAS-Cerco=fc 210 m3 12 1.30 0.90 0.70 9.83
1.05 ZAPATAS-Cerco=fc 210 m3 1 1.20 1.00 0.70 0.84

CIMIENTO CORRIDO- CONCRETO


2.00 Cimiento Corrido-Cerco=fc 210 M3

2.01 Cimiento Corrido-Cerco=fc 210 m3 17 1.70 0.70 0.60 12.14


2.02 Cimiento Corrido-Cerco=fc 210 m3 1 1.55 0.70 0.60 0.65
2.03 Cimiento Corrido-Cerco=fc 210 m3 1 1.00 0.70 0.60 0.42

SOBRECIMIENTO - CONCRETO
3.00 Sobrecimiento-Cerco=fc 100 M3

3.01 Sobrecimiento - INT. Cerco m3 20 2.75 1.30 0.13 9.30


3.02 Sobrecimiento - INT. Cerco m3 1 2.70 1.30 0.13 0.46
3.03 Sobrecimiento - INT. Cerco m3 1 2.86 1.30 0.13 0.48
COLUMNA- CONCRETO

4.00 Cerco

4.01 Columna C-1 m3 30 0.23 0.23 1.30 2.06

VIGAS- CONCRETO
5.00 Cerco

5.01 VIGA VS (0,15X0,20) m3 1 51.10 0.15 0.18 1.38


5.02 VIGA VS (0,15X0,20) pinto m3 23 0.23 0.10 0.18 0.10

ALBAÑILERIA
6.00 Cerco

6.01 Paño 1 m2 1 2.75 3.00 8.25


6.02 Paño 2 m2 1 2.75 3.00 8.25
6.03 Paño 3 m2 1 2.75 3.00 8.25
6.04 Paño 4 m2 1 2.75 3.00 8.25
6.05 Paño 5 m2 1 2.75 3.00 8.25
6.06 Paño 6 m2 1 2.75 3.00 8.25

VAL 03 - EJECUCIÓN
ZAPATAS 17.72 65.00 1152.06
COLUMNAS 2.06 75.00 154.73
CIMIENTO CORRIDO 13.21 60.00 792.54
SOBRECIMIENTO 10.23 65.00 665.25
VIGAS 1.47 60.00 88.50
ALBAÑILERIA 49.50 30.00 1485.00

Sin. Igv
1

10.10

6.80

1,064.38
656.57
407.81

1,255.96
2

TOTAL

6.93

1.46

6.43
5.90

1,329.40
450.45
109.69
385.56
383.71

1,568.70
3

4.78

1.43

2.79

625.06
4

TOTAL

17.72

13.21

10.23
2.06

1.47

49.50

4,338.08

4,338.08
VAL. 01 - ENCOFRADOS 1
FERNANDO ARCE
I.E LAS - 26 Octubre
07 DICIEMBRE DEL 2021

ALIGERADO - VIGAS
ITEM DESCRIPCCION Und ML H M2 TOTAL

2.00 SS.HH-PRIMARIA m2 81.518

1.01 CAJON 1 m2 1 19.20


1.02 CAJON 2 m2 1 17.87
1.03 CAJON 3 m2 1 19.19
1.12 FRISOS m2 1 37.37 0.20 7.47

1.14 EJE C-C= VP(25X40) m2 1 12.96 0.40 5.18


1.15 EJE A-A =VP(15X40) m2 1 12.96 0.40 5.18
1.16 EJE 1-1 =VP(25X40) m2 1 4.76 0.40 1.90
1.17 EJE 4-4 =VP(25X40) m2 1 4.76 0.40 1.90
1.18 EJE 2-2= VP(25X40) m2 1 4.51 0.40 1.80
1.19 EJE 3-3 = VP(25X40) m2 1 4.51 0.40 1.80

VAL 07 - ENCOFRADOS
Aligerado Sshh. - 81.52 2,445.54
Metrado total 81.52 S/ 30.00

Sin. Igv 2,445.54


VAL. 02 - ENCOFRADOS 2
FERNANDO ARCE
I.E LAS - 26 Octubre
29 DICIEMBRE DEL 2021

ALIGERADO - VIGAS
ITEM DESCRIPCCION Und ML H M2 TOTAL

1.00 SS.HH-Secundaria m2 125.50

1.01 CAJON 1 m2 1 6.48


1.02 CAJON 2 m2 1 6.85
1.03 CAJON 3 m2 1 16.04
1.03 CAJON 4 m2 1 19.28
1.03 CAJON 5 m2 1 9.70
1.03 CAJON 6 m2 1 18.81
1.12 FRISOS m2 1 46.45 0.20 9.29

1.14 EJE D-D= VP(25X50) m2 1 12.96 0.60 7.78


1.15 EJE C-C= VP(25X50) m2 1 3.95 0.60 2.37
1.16 EJE B-B= VP(25X50) m2 1 8.26 0.60 4.96
1.17 EJE A-A= VP(25X50) m2 1 8.66 0.60 5.20
1.18 EJE 1-1= VP(25X50) m2 1 5.26 0.60 3.16
1.19 EJE 2-2= VP(25X50) m2 1 4.76 0.60 2.86
1.19 EJE 4-4= VP(25X50) m2 1 7 0.60 4.20
1.19 EJE 5-5= VP(25X50) m2 1 3.01 0.60 1.81
1.19 EJE 6-6= VP(25X50) m2 1 10.26 0.60 6.16
1.19 EJE E-E= VP(30X20) m2 1 2.89 0.20 0.58

2.00 CORREDOR Primaria m2 67.15

2.01 CAJON 1 m2 1 17.02


2.02 CAJON 2 m2 1 18.71
2.03 FRISOS m2 1 27.46 0.20 5.49
2.04 EJE B-B= VP(25X50) m2 1 8.78 0.80 7.02
2.05 EJE A-A= VP(25X50) m2 1 8.78 0.80 7.02
2.06 EJE 1-1= VP(25X50) m2 1 4.95 0.80 3.96
2.07 EJE 2-2= VP(25X50) m2 1 4.95 0.80 3.96
2.08 EJE 3-3= VP(25X50) m2 1 4.95 0.80 3.96

VAL 02 - ENCOFRADOS
SS.HH-Secundaria 125.50 5,779.50
CORREDOR Primaria 67.15

Metrado total 192.65 S/ 30.00

Sin. Igv 5,779.50


* No presenta Factura
VAL. 1 - ENCOFRADOS 1
GREGORIO COVEÑAS RAMOS
I.E LAS - 26 Octubre
15 DE ENERO DEL 2022

ITEM DESCRIPCCION Und H M2 TOTAL

COLUMNETAS
1.00 PABELLON 8- Primer Nivel N° H 6.30

3.00 EJE C-C m2 4 0.50 1.00 2.00


3.10 EJE A-A m2 3 0.50 2.00 3.00
3.20 EJE A-A m2 1 0.65 2.00 1.30

1.00 PABELLON 7- Segundo Nivel 23.47

3.00 EJE C-C m2 4 0.50 1.00 2.00


3.00 EJE A-A m2 3 0.50 1.82 2.73
3.00 EJE A-A m2 1 0.65 1.82 1.18

1.00 PABELLON 6- Segundo Nivel 4.00

3.00 EJE A-A m2 4 0.50 2.00 4.00

1.00 PABELLON 5- Segundo Nivel 13.56

3.00 EJE A-A (Tramo 1-2) m2 6 0.50 2.92 8.76


3.01 PARAPETO TERCER NIVEL m2 10 0.20 2.40 4.80

VIGUETAS
2.00 PABELLON 8- Primer Nivel N° Lados L H 2.42

3.00 EJE A-A (tramo 1-2) m2 2 3.20 0.10 0.64


3.00 EJE A-A (tramo 2-3) m2 2 2.35 0.10 0.47
3.10 EJE C-C (tramo 1-2) m2 2 3.20 0.10 0.64
3.10 EJE C-C (tramo 2-3) m2 2 3.33 0.10 0.67

2.00 PABELLON 8- Parapeto N° Lados L H 7.76

3.00 EJE A-A m2 2 8.53 0.10 1.71


3.10 EJE C-C m2 2 8.53 0.10 1.71
3.00 EJE 1-1 m2 2 10.86 0.10 2.17
3.10 EJE 3-3 m2 2 10.86 0.10 2.17

2.00 PABELLON 7- Segundo Nivel N° Lados L H 2.42

3.00 EJE A (tramo 1-2) m2 2 3.20 0.10 0.64


3.10 EJE A (tramo 2-3) m2 2 2.35 0.10 0.47
3.00 EJE C (tramo 1-2) m2 2 3.20 0.10 0.64
3.10 EJE C (tramo 2-3) m2 2 3.33 0.10 0.67

2.00 PABELLON 5- Segundo Nivel N° Lados L H 11.77

3.00 EJE A m2 2 8.09 0.10 1.62


3.10 EJE C (tramo tabique-2) m2 2 1.52 0.10 0.30
3.10 EJE C (tramo 3-4) m2 2 3.20 0.10 0.64
3.20 PARAPETO TERCER NIVEL M2 2 0.10 46.04 9.21

ZAPATAS
3.00 Zapatas Cerco 30.80

5 Zapatas - Secundaria m2 10 4.40 0.70 30.80

SOBRECIMIENTO
3.00 Sobrecimiento Cerco 7.15

Sobrecimiento 1 - INT. Cerco m2 2 2.75 1.30 7.15

COLUMNAS
3.00 SS.HH. SECUNDARIA - Segundo Nivel 15.40

4 Columnas - Eje D (Tramo 2-3) m2 8 0.50 3.08 12.32


1 Columna - Eje 1-B m2 2 0.50 3.08 3.08

3.00 Cerco 4.03

Columna C-1 m2 1 0.85 1.30 1.11


Columna C-2 m2 1 0.70 1.30 0.91
Columna C-3 m2 1 0.70 1.30 0.91
Columna C-4 m2 1 0.85 1.30 1.11

VAL 01 - ENCOFRADOS
Pab.7 Seg. Nivel, Pab.6 Seg.
Nivel, Pab.5 Seg. Nivel 47.33
Parapeto, Pab. 7 Seg. Nivel,
Pab.5 Seg. Nivel 24.36

Zapatas. Cerco 30.80 3,872.13


Sobrecimiento. Cerco 7.15
Columnas.SSHH Secundaria,
Seg. Nivel 19.43
Metrado total 129.07 S/ 30.00

Inc. Igv 3,872.13


VAL. 2 - ENCOFRADOS 2
GREGORIO COVEÑAS RAMOS
I.E LAS - 26 Octubre
31 DE ENERO DEL 2022

ITEM DESCRIPCCION Und M2 TOTAL

VIGUETAS
1.00 PABELLON 5 - Primer Nivel N° de Lados H L 2.88

EJE A m2 2 0.10 8.41 1.68


EJE C (Tramo 1-3) m2 2 0.10 5.99 1.20
2.00 PABELLON 6 - Primer Nivel N° de Lados H L 2.42

EJE A m2 2 0.10 5.55 1.11


EJE C m2 2 0.10 6.53 1.31
3.00 PABELLON 7 - Segundo Nivel N° de Lados H L 1.94

PARAPETO m2 2 0.10 9.71 1.94

3.00 PABELLON 7 - Parapeto N° de Lados H L 7.76

m2 1 0.20 38.78 7.76

COLUMNETAS
4.00 PABELLON 5 - Primer Nivel N° de Columnetas H 14.16

Columneta de Tabique Interno (Área de Profesores) m3 2 0.40 3.30 2.64


Ca (EJE A) m3 6 0.50 2.00 6.00
Ca - Baja (EJE C) m3 3 0.50 0.90 1.35
Ca - Alta (EJE C) m3 3 0.50 2.78 4.17
19.00 PABELLON 5 - Segundo Nivel N° de Columnetas H 4.31

Columneta de Tabique Interno (Centro de Carga) m3 1 0.44 3.37 1.48


Columneta de Tabique Interno (Centro de Carga) m3 1 0.54 3.37 1.82
Columneta de Tabique Interno (Centro de Carga) m3 1 0.30 3.37 1.01
20.00 PABELLON 6 - Parapeto N° de Columnetas H 4.90

Ca (EJE A) m3 4 0.50 1.50 3.00


Ca (EJEC) m3 4 0.50 0.95 1.90
21.00 PABELLON 7 - Segundo Nivel N° de Columnetas H 1.21

Ca (PARAPETO) m3 4 0.30 1.01 1.21


21.00 PABELLON 7 - Parapeto N° de Columnetas H 4.04

Ca m3 10 0.40 1.01 4.04


22.00 SS.HH. SECUNDARIA - Segundo Nivel N° de Columnetas H 5.78
Ca (EJE 4) m3 1 0.65 3.30 2.15
Cp (EJE C) m3 1 0.30 3.30 0.99
Cc (EJE D) m3 1 0.80 3.30 2.64

COLUMNAS
23.00 SS.HH. SECUNDARIA - Segundo Nivel N° de Columnas H 66.59

C1- EJE 2 m3 3 1.00 3.30 9.90


C1- EJE 3 m3 2 1.92 3.30 12.67
C1- EJE 4 m3 2 1.92 3.30 12.67
C1- EJE 5 m3 2 1.90 3.30 12.54
C1- EJE 6 m3 3 1.90 3.30 18.81

23.00 SS.HH. SECUNDARIA - Primer Nivel N° de Columnas H 14.52

C1- EJE 5 m3 2 2.20 3.30 14.52

ALIGERADO - VIGAS
ITEM DESCRIPCCION Und ML H M2 TOTAL

1.00 SS.HH-Secundaria m2 139.71

1.03 CAJON 3 m2 1 19.04


1.03 CAJON 4 m2 1 19.28
1.03 CAJON 5 m2 1 14.70
1.03 CAJON 6 m2 1 18.81
1.12 FRISOS m2 1 46.45 0.50 23.23

1.14 EJE D-D= VP(25X50) m2 1 13.96 0.60 8.38


1.15 EJE C-C= VP(25X50) m2 1 4.95 0.60 2.97
1.16 EJE B-B= VP(25X50) m2 1 9.26 0.60 5.56
1.17 EJE A-A= VP(25X50) m2 1 9.66 0.60 5.80
1.18 EJE 1-1= VP(25X50) m2 1 6.26 0.60 3.76
1.19 EJE 2-2= VP(25X50) m2 1 5.76 0.60 3.46
1.19 EJE 4-4= VP(25X50) m2 1 8 0.60 4.80
1.19 EJE 5-5= VP(25X50) m2 1 4.01 0.60 2.41
1.19 EJE 6-6= VP(25X50) m2 1 11.26 0.60 6.76
1.19 EJE E-E= VP(30X20) m2 1 3.89 0.20 0.78

CIMIENTO CORRIDO-CERCO
2.00 Cimiento Corrido-Cerco 11.90

2.01 Cimiento 22 - INT. Cerco m2 2 1.70 0.70 2.38


2.02 Cimiento 23 - INT. Cerco m2 2 1.70 0.70 2.38
2.03 Cimiento 24 - INT. Cerco m2 2 1.70 0.70 2.38
2.04 Cimiento 25 - INT. Cerco m2 2 1.70 0.70 2.38
2.05 Cimiento 26 - INT. Cerco m2 2 1.70 0.70 2.38
SOLADO-CERCO
2.00 SOLADO-Cerco 4.14

2.01 SOLADO 1.60 X 0.90 m2 3 5.00 0.10 1.50


2.02 SOLADO 1.30 X 0.90 m2 6 4.40 0.10 2.64

VAL 02 - ENCOFRADOS 8,587.61


VIGUETAS 14.99
Pab. 5,6,7 -Parap. Pab.7

COLUMNETAS 34.40
Pab. 5 1° y 2°, Pab. 6, s.h

COLUMNAS 81.11
Ss.hh Secund y Prima.

ALIGERADO - VIGAS 139.71

CIMIENTO CORRIDO-CERCO 11.90

SOLADO-CERCO 4.14
Metrado total 286.25 S/ 30.00

Sin. Igv 8,587.61


VAL. 1 - ACERO 1
GREGORIO COVEÑAS RAMOS
I.E LAS - 26 Octubre
15 DE ENERO DEL 2022

COLUMNETAS
1.00 PABELLON 5 - Segundo nivel KG Varillas Estribos 46.40

Estribos de 4 columnetas (Eje 1-Tabique) kg 29.57 29.57

2 Columnetas Eje A (Tamo 1-2) kg 6.54 10.29 16.83

2.00 PABELLON 8 - Primer nivel KG Varillas Estribos 29.60

EJE A kg 15.23 2.83 18.06

EJE C kg 5.37 6.17 11.54

3.00 PABELLON 8 - Parapeto KG Nº L Peso 26.61

Estribos kg 72 0.66 0.56 26.61

4.00 PABELLON 7 - Segundo nivel KG Varillas Estribos 28.34

4 COLUMNETAS - EJE A kg 17.02 11.32 28.34

5.00 SS.HH. SECUNDARIA - Segundo nivel KG Varillas Estribos 52.12

13 Ca kg 29.12 23.00 52.12

VIGUETAS
6.00 PABELLON 8 - Primer nivel KG Varillas Estribos 16.51

EJE A kg 6.21 1.40 7.61

EJE C kg 7.30 1.60 8.90

7.00 PABELLON 8 - Parapeto KG Varillas Estribos 53.02

EJE A kg 9.55 2.11 11.66

EJE C kg 9.55 2.11 11.66

EJE 1 kg 12.16 2.69 14.85

EJE 3 kg 12.16 2.69 14.85

8.00 PABELLON 5 - Segundo nivel KG Varillas Estribos 25.18

EJE C (tramo 1-tabique) kg 2.45 0.55 3.00

EJE C (tramo tabique-2) kg 1.7 0.35 2.05

EJE C (tramo 2-3) kg 3.75 0.80 4.55

EJE C (tramo 3-4) kg 3.58 0.80 4.38

EJE A (tramo 1-2) kg 2.07 0.45 2.52

EJE A (tramo 2-3) kg 3.75 1.00 4.75

EJE A (tramo 3-4) kg 3.23 0.70 3.93

9.00 PABELLON 7 - Segundo nivel KG Varillas Estribos 7.71

EJE A (tramo 1-2) kg 3.58 0.90 4.48

EJE A (tramo 2-3) kg 2.63 0.60 3.23

10.00 PABELLON 6 - Segundo nivel KG Varillas Estribos 7.61

EJE A kg 6.21 1.40 7.61

COLUMNAS
11.00 SS.HH. SECUNDARIA - Segundo nivel KG 1,342.76

9 COLUMNAS C1 kg 17 45.96 781.32


11.00 CERCO PERIMETRICO - Secundaria KG Varillas Estribos 577.12

Columnas kg 9 343.72 217.72 561.44

SOBRECIMIENTO
12.00 SOBRECIMIENTO CERCO PERIMETRICO - SECUNDARIA ML 129.36

Sobrecimiento kg 8.25 15.68 129.36

ZAPATAS
12.00 ZAPATA CERCO PERIMETRICO - SECUNDARIA N° 89.67

Malla de zapata (0.90*1.30) kg 4 17.25 69


Malla de zapata (0.90*1.60) kg 1 20.67 20.67

VAL 01 - ACERO
COLUMNETAS 183.07 2,302.65
Pab.8 Prim. Nivel, Parapeto - Pab. 5
Seg. Nivel - Pab.7 Seg. Nivel - Pab. 5
Seg. Nivel

VIGUETAS 110.03
Pab.8 Prim. Nivel, Parapeto - Pab. 5
Seg. Nivel - Pab.7 Seg. Nivel - Pab. 6
Seg. Nivel

COLUMNAS 1,919.88
SSHH Secundaria
ZAPATAS 89.67
Cerco Secundaria
SOBRECIMIENTO 129.36
Cerco Secundaria
Metrado total 2,302.65 S/ 1.00

VAL. 2 - ACERO 2
GREGORIO COVEÑAS RAMOS
I.E LAS - 26 Octubre
31 DE ENERO DEL 2022

COLUMNETAS
1.00 PABELLON 5 - Primer nivel KG Varillas Estribos 197.27

6 Columnetas Eje A kg 26.88 58.07 84.95

3 Columnetas Bajas Eje C kg 6.04 13.66 19.70

3 Columnetas Altas Eje C kg 18.68 37.58 56.26

2 Columnetas Tabique Interno kg 12.45 23.91 36.36

2.00 PABELLON 6 - Primer nivel KG Varillas Estribos 56.77

4 Columnetas Eje A kg 16.39 20.49 36.88

4 Columnetas Eje C kg 8.51 11.38 19.89

3.00 PABELLON 6 - Parapeto KG Varillas Estribos 32.26

3 Columnetas Eje A kg 7.25 2.43 9.68

3 Columnetas Eje C kg 7.25 2.43 9.68

2 Columnetas Eje 1 kg 4.83 1.62 6.45

2 Columnetas Eje 3 kg 4.83 1.62 6.45

4.00 PABELLON 7 - Segundo nivel KG Varillas Estribos 10.86

4 Columnetas Parapeto kg 9.04 1.82 10.86


5.00 PABELLON 7 - Parapeto KG Varillas Estribos 32.26

3 Columnetas Eje A kg 7.25 2.43 9.68

3 Columnetas Eje C kg 7.25 2.43 9.68

2 Columnetas Eje 1 kg 4.83 1.62 6.45

2 Columnetas Eje 3 kg 4.83 1.62 6.45

6.00 SS.HH. SECUNDARIA - Segundo nivel KG Varillas Estribos 150.62

13 Ca (agregado de varillas y estribos) kg 60.56 46.00 106.56

1 Ca Eje D kg 19.60 24.46 44.06

7.00 SS.HH. SECUNDARIA - Primer nivel KG Varillas Estribos 12.69

1 Ca Eje C kg 7.39 5.30 12.69

VIGUETAS
8.00 PABELLON 5 - Primer nivel KG Varillas Estribos 19.35
3 Viguetas Eje A kg 9.41 1.89 11.30

2 Viguetas Eje C kg 6.70 1.35 8.05

9.00 PABELLON 6 - Primer nivel KG Varillas Estribos 16.82

2 Viguetas Eje A kg 6.21 1.55 7.76

2 Viguetas Eje C kg 7.31 1.75 9.06

10.00 PABELLON 7 - Segundo nivel KG Varillas Estribos 13.30

Viguetas Parapeto kg 10.20 3.10 13.30

11.00 PABELLON 7 - Parapeto KG Varillas Estribos 52.82

Viguetas Eje A kg 9.55 2.06 11.61

Viguetas Eje C kg 9.55 2.06 11.61

Viguetas Eje 1 kg 12.16 2.64 14.80

Viguetas Eje 3 kg 12.16 2.64 14.80

COLUMNAS
13.00 SS.HH. SECUNDARIA - Primer nivel KG Varillas Estribos 65.11

1 Ca Eje 5 kg 40.92 24.19 65.11

VIGAS sshh. Segundo nivel


6.00 SS.HH-Secondaria-SEGUNDO Nivel UND 1,022.80

V-P EJE D-D Und 1 162.47 162.47


V-P EJE C-C Und 1 56.50 56.50
V-P 58.76
V-P EJE
EJE B-B
A-A Und
Und 11
108.80
58.76
108.80
V-P EJE 1-1 Und 1 63.98 63.98
V-P EJE 2-2 Und 1 93.55 93.55
V-P EJE 4-4 Und 1 90.32 90.32
V-P EJE 6-6 Und 1 126.91 126.91
V-P EJE E-E Und 1 127.36 127.36
V-P EJE 5-5 Und 1 134.15 134.15

SOBRECIMIENTO- CERCO
6.00 SOBRECIMIENTO-Cerco ML 318.46

EJE A-A ml 20.31 15.68 318.4608

VAL 02 - ACERO
COLUMNETAS 492.73 2,001.39
Pab.5 -1°. Nivel, Pab. 6- 2° nivel
/Pab. 6 Parapeto /Pab. 7-
2°nivel/Pab. 7 parpto/Ss.hh secund.
1°nivel
VIGUETASy 2°nivel 102.29
Pab.5 - 1° nivel/ Pab. 6 -1° nivel/
Pab.7 - 2° nivel /Pab.7 Parpto.

COLUMNAS 65.11
SSHH Secund-1° nivel

vigas sshh segundo nivel 1,022.80


SOBRECIMIENTO - CERCO 318.46

Metrado total 2,001.39 S/ 1.00

Sin Igv
2,001.39
VAL. 1 - EJECUCION 1
VACIADOS DE CONCRETO
GREGORIO COVEÑAS RAMOS
15 DE ENERO DEL 2022

ALBAÑILERIA
1.00 PABELLON 5- Segundo Nivel M2 SOGA L H 14.07

1.01 TABIQUE (tramo 1) m2 1 3.00 2.19 6.57

1.02 TABIQUE (tramo 2) m2 1 3.15 2.38 7.50

2.00 PABELLON 5- Parapeto M2 SOGA L H 40.78

2.01 EJE A m2 1 12.71 1.08 13.73

2.02 EJE C m2 1 4.15 1.08 4.48

2.03 EJE 1 m2 1 10.45 1.08 11.29

2.04 EJE 5 m2 1 10.45 1.08 11.29

3.00 PABELLON 7- Segundo Nivel M2 SOGA L H 8.94

3.01 EJE A (tramo 1-2) m2 1 2.67 1.66 4.42

3.02 EJE A (tramo 2-3) m2 1 1.77 1.66 2.93

EJE C m2 1 1.77 0.90 1.59

4.00 PABELLON 6- Primer Nivel M2 SOGA L H 1.70

4.01 EJE A m2 1 4.43 0.11 0.49

4.02 EJE C m2 1 5.53 0.22 1.22

4.00 PABELLON 6- Segundo Nivel M2 SOGA L H 12.78

4.01 EJE A m2 1 4.43 1.70 7.53

4.02 EJE C m2 1 5.53 0.95 5.25

5.00 SS.HH. SECUNDARIA - Segundo Nivel M2 SOGA L H 44.49

3.01 EJE 6 (tramo A-D) m2 1 5.75 3.08 17.71

3.01 EJE 2 (tramo A-B) m2 1 1.49 3.08 4.59

3.01 EJE 1 (tramo B-D) m2 1 4.03 3.08 9.71

3.01 EJE B (tramo 1-2) m2 1 4.05 3.08 12.47

TARRAJEO
6.00 VIGAS M2 L 42.83

6.01 PABELLON 7- Segundo Nivel

V201= EJE 1-3 m2 2 0.40 7.20 5.76

ADICIONAR V201 m2 2 0.65 2.55 3.32

V203= EJE 2 m2 1 1.10 9.76 17.06

V-P= EJE A m2 1 0.85 6.63 5.64

6.02 PABELLON 5- Segundo Nivel

V201= EJE 4 - Parte externa (cara interior y abajo) m2 1 0.65 2.55 1.66

V202= EJE 2-3 - Parte externo m2 2 1.10 2.55 5.61

V-P= EJE A (cara externa) m2 1 0.30 10.51 3.15

6.03 PABELLON 6- Segundo Nivel

V201= EJE 3 - Parte externa (cara abajo) m2 1 0.25 2.55 0.64


7.00 MUROS M2 L H 188.81

7.01 PABELLON 7- Segundo Nivel

EJE 1 m2 1 6.26 2.92 18.28

EJE A (tramo 1-2) m2 2 2.67 1.66 8.86

EJE A (tramo 2-3) m2 2 1.77 1.66 5.88

EJE C m2 1 5.53 0.90 4.98

7.02 PABELLON 8- Primer Nivel

EJE A m2 2 4.55 1.70 15.47

EJE C m2 1 5.53 0.60 3.32

7.02 PABELLON 8- Parapeto

EJES A-C (interno) m2 2 8.08 1.08 17.45

EJES 1-3 (interno) m2 2 10.26 1.08 22.16

7.03 PABELLON 5- Parapeto m2 36.14 1.20 43.37

7.03 PABELLON 5- Segundo Nivel

EJE A (Tramo 2-4) (Interno y externo) m2 2 5.52 2.00 22.08

EJE C (Tramo 3-4) (Interno) m2 1 2.70 0.90 2.43

EJE C (Tramo 2-3) (Interno) m2 1 2.85 0.90 2.57

EJE C (Tramo Tabique-2) (Interno) m2 1 1.02 0.90 0.92

7.04 PABELLON 6- Segundo Nivel

EJE A (Interno y externo) m2 2 4.55 1.73 15.74

EJE C (Interno) m2 1 5.53 0.96 5.31

8.00 COLUMNAS M2 H 36.79

8.01 PABELLON 7-Segundo Nivel


C-3 m2 1 2.90 2.92 8.47
C-2 m2 2 1.35 2.92 7.88
8.02 PABELLON 8-Primer Nivel
C-2 m2 2 0.50 2.92 2.92
C-3 m2 1 0.90 2.92 2.63
8.03 PABELLON 5-Segundo Nivel
C-3 (cara frontal) Eje 2-4 m2 4 0.90 2.92 10.51
C-2 (cara frontal) Eje 3 m2 2 0.50 2.92 2.92
8.04 PABELLON 6-Segundo Nivel
C-2 (cara frontal) Eje 1 m2 1 0.50 2.92 1.46

9.00 COLUMNETAS M2 H 16.25

8.01 PABELLON 8-Primer Nivel


Ca (EJE A) m2 2 0.50 1.70 1.70
Ca (EJE C) m2 2 0.50 0.60 0.60
PABELLON 8-Parapeto
Ca (EJE A-C) m2 6 0.15 1.08 0.97
Ca (EJE 1-3) m2 4 0.15 1.08 0.65
8.02 PABELLON 7-Segundo Nivel
Ca (EJE A) m2 2 0.50 1.66 1.66
Ca (EJE C) m2 2 0.50 0.90 0.90
8.03 PABELLON 5-Segundo Nivel
Ca (EJE A - Tramo 2-4) (Interno y externo) m2 4 0.50 2.00 4.00
Ca (EJE C - Tramo Tabique-2) (Interno) m2 2 0.25 0.90 0.45
Ca (EJE C - Tramo 2-3) (Interno) 2 0.25 0.90 0.45
Ca (EJE C - Tramo 3-4) (Interno) m2 2 0.25 0.90 0.45
8.04 PABELLON 6-Segundo Nivel
Ca (EJE A) (Interno y externo) m2 4 0.50 1.73 3.46
Ca (EJE C) (Interno) m2 4 0.25 0.96 0.96
10.00 VIGUETAS M2 L 9.50

9.01 PABELLON 8-Primer Nivel


Eje A-C (Interno y externo) m2 5.55 0.20 1.11
Eje 1-3 (Interno y externo) m2 6.53 0.20 1.31
PABELLON 8-Parapeto
Eje A-C (Interno) m2 8.08 0.10 0.81
Eje 1-3 (Interno) m2 10.26 0.10 1.03
9.02 PABELLON 5-Segundo Nivel
Eje A (Tramo 2-4) (Interno y externo) m2 6.24 0.20 1.25
Eje C (Tramo Tabique-2) (Interno) 1.52 0.10 0.15
Eje C (Tramo 3-4) (Interno) m2 3.20 0.10 0.32
9.01 PABELLON 6-Segundo Nivel
Eje A (Interno y externo) m2 5.55 0.20 1.11
Eje C (Interno) m2 6.53 0.10 0.65
9.01 PABELLON 7-Segundo Nivel
Eje A (Interno y externo) m2 5.55 0.20 1.11
Eje C (Interno) m2 6.53 0.10 0.65

10.00 CIELO RASO M2 A L 75.44

10.01 PABELLON 6-Segundo Nivel


Tramo 1-2 m2 1 3.93 9.76 38.36
Tramo 2-3 m2 1 3.80 9.76 37.09

10.00 DERRAMES ML 49.48

10.01 PABELLON 6-Segundo Nivel


VENTANAS ml 12.08
PUERTAS ml 1.00
10.01 PABELLON 5-Segundo Nivel
VENTANAS ml 10.24
10.01 PABELLON 7-Segundo Nivel
VENTANAS ml 12.08
PUERTAS ml 1.00
10.01 PABELLON 8-Primer Nivel
VENTANAS ml 12.08
PUERTAS ml 1.00

BRUÑADO INTERNO Y EXTERNO


11.00 PABELLONES ML 253.61

PABELLON 8 - Primer Nivel - Eje A (Interno y externo) ml 25.34

PABELLON 8 - Primer Nivel - Eje C (Interno) ml 9.37

PABELLON 7 - Segundo Nivel - Eje A (Interno y externo) ml 31.04

PABELLON 7 - Segundo Nivel - Eje C (Interno) ml 14.66

PABELLON 5 - Segundo Nivel - Eje A - Tramo 2-4 (Interno y externo)


ml 38.08

PABELLON 5 - Segundo Nivel - Eje C - Tramo 3-4 (Interno) ml 7.20

PABELLON 5 - Segundo Nivel - Eje C - Tramo Tabique-2 (Interno)


ml 3.84

PABELLON 5- PARAPETO ML 78.14

PABELLON 6 - Segundo Nivel - Eje A (Interno y externo) ml 32.04

PABELLON 6 - Segundo Nivel - Eje C (Interno) ml 13.90

ZOCALO
12.00 PABELLONES M M 15.76

PABELLON 8 - Primer Nivel (Eje A) ml 7.53


PABELLON 8 - Parapeto (Eje A-C) ml 8.23

ZAPATAS
13.00 ZAPATAS CERCO PERIMETRICO - Secundaria N° H 4.28

Zapata (0.90*1.30) m3 4 0.90 1.30 0.70 3.28


Zapata (0.90*1.60) m3 1 0.90 1.60 0.70 1.01

SOBRECIMIENTOS
14.00 Sobrecimienos Cerco N° H 1.51

Secundaria m3 3 0.16 2.42 1.30 1.51

VIGUETAS
15.00 PABELLON 8 - Primer Nivel Fondo H L 0.18

Eje A m3 0.15 0.10 5.55 0.08


Eje c m3 0.15 0.10 6.53 0.10

16.00 PABELLON 8 - Parapeto 0.58

Eje A m3 0.15 0.10 8.53 0.13


Eje C m3 0.15 0.10 8.53 0.13
Eje 1 m3 0.15 0.10 10.86 0.16
Eje 3 m3 0.15 0.10 10.86 0.16

17.00 PABELLON 5 - Segundo Nivel 0.97

Eje A m3 0.15 0.10 8.09 0.12


Eje C (Tramo 1-Tabique) m3 0.15 0.10 2.19 0.03
Eje C (Tramo Tabique-2) m3 0.15 0.10 1.52 0.02
Eje C (Tramo 2-3) m3 0.15 0.10 3.35 0.05
Eje C (Tramo 3-4) m3 0.15 0.10 3.20 0.05
PARAPETO M3 0.15 0.10 46.04 0.69

COLUMNETAS
18.00 PABELLON 8 - Primer Nivel N° H 0.26

Eje A m3 4 0.15 0.15 2.00 0.18


Eje C m3 4 0.15 0.15 0.90 0.08

19.00 PABELLON 8 - Parapeto N° H 0.24

Eje A m3 3 0.15 0.15 1.08 0.07


Eje C m3 3 0.15 0.15 1.08 0.07
Eje 1 m3 2 0.15 0.15 1.08 0.05
Eje 3 m3 2 0.15 0.15 1.08 0.05

18.00 PABELLON 5 - Segundo Nivel N° H 11.55

Eje A (Tramo 2-4) m3 4 0.15 0.15 2.00 0.18


Eje A (1-2) m3 1 0.15 0.15 2.92 0.07
PARAPETO M3 10 0.15 0.15 1.00 11.30

COLUMNAS
18.00 SSHH SECUNDARIA - Segundo Nivel N° H 1.93
C1- Eje D m3 4 0.25 0.50 3.08 1.54
C1- Eje B-1 m3 1 0.25 0.50 3.08 0.39

18.00 PABELLON 5 - Segundo Nivel N° H 0.37

C1- Eje 2 m3 1 0.25 0.50 2.92 0.37

2.00 CERCO SECUNDARIA 0.33

2.01 Columna C-1 m3 1 0.25 0.25 1.30 0.08


2.02 Columna C-1 m3 1 0.25 0.25 1.30 0.08
2.03 Columna C-1 m3 1 0.25 0.25 1.30 0.08
2.04 Columna C-1 m3 1 0.25 0.25 1.30 0.08

CIMIENTO CORRIDO
18.00 CIMIENTO CORRIDO CERCO PERIMETRICO - Secundaria N° H 1.37

Secundaria m3 3 0.60 1.69 0.45 1.37

VAL 1 - EJECUCION 14,913.40

ALBAÑILERIA 122.76 28.00 3,437.39


Pab.5 Seg. Nivel, Parapeto - Pab. 7 Seg.
Nivel - Pab.6 Prim y Seg. Nivel - SSHH
Secundaria Seg. Nivel

COLUMNAS-CONCRETO 2.62 75.00 196.13


SSHH SECUNDARIA - Pab. 5 Seg. Nivel

ZAPATAS-CONCRETO 4.28 75.00 321.30


Cerco perímetrico

SOBRECIMIENTO-CONCRETO 1.51 75.00 113.26


Cerco perímetrico Secundaria

VIGUETAS CONFINAMIENTO 1.73 75.00 129.66


Pab.8 Prim. Nivel, Parapeto Pab.5 Seg. Nivel

COLUMNETAS CONFINAMIENTO 12.05 75.00 903.73


Pab.8 Prim. Nivel, Parapeto Pab.5 Seg. Nivel

TARRAJEO
VIGAS 42.83 25.00 1,070.71
COLUMNAS 36.79 25.00 919.80
MUROS 214.56 18.00 3,862.05
CIELO RASO 75.44 25.00 1,886.12
DERRAMES 49.48 3.00 148.44

COLUMNETAS 12.05 75.00 903.73


Pab.8 Prim. Nivel, Parapeto Pab.5 Seg. Nivel

CONTRAPISO 0.00 12.00 0.00


Pab.3 Primer Piso Aula 1

CIMIENTO CORRIDO - CONCRETO 1.37 75.00 102.67


Cerco Perimétrico Secundaria
BRUÑADO INTERNO Y EXTERNO 253.61 3.00 760.83

Pab. 8 Prim. Nivel, Pab.7 Seg. Nivel, Pab.5


Seg. Nivel, Pab.6 Seg. Nivel

ZOCALO 15.76 10.00 157.60


Pab.8 Prim. Nivel, Parapeto

VAL. 2 - EJECUCION 2

VACIADOS DE CONCRETO
GREGORIO COVEÑAS RAMOS
31 DE ENERO DEL 2022

ALBAÑILERIA
1.00 PABELLON 5 - Primer Nivel M2 SOGA L H 54.16

1.01 EJE A m2 1 8.91 2.00 17.82


1.02 EJE C m2 1 7.80 0.90 7.02
1.03 EJE C (Muro alto) m2 1 0.53 2.78 1.47
1.04 Tabique interno (Área de profesores) m2 1 5.53 3.08 17.03
1.05 Tabique interno m2 1 3.51 3.08 10.81

2.00 PABELLON 5 - Escalera M2 CABEZA L H 2.25

2.01 EJE 6 m2 1 4.25 0.53 2.25

3.00 PABELLON 6 - Parapeto M2 SOGA L H 44.75

3.01 EJE A m2 1 9.08 1.10 9.99


3.02 EJE C m2 1 9.08 1.10 9.99
3.03 EJE 1 m2 1 11.26 1.10 12.39
3.04 EJE 3 m2 1 11.26 1.10 12.39

4.00 PABELLON 7- Segundo Nivel M2 SOGA L H 10.02

4.01 Parapeto m2 1 9.11 1.10 10.02

5.00 PABELLON 7- Parapeto M2 SOGA L H 44.75

5.01 EJE A m2 1 9.08 1.10 9.99


5.02 EJE C m2 1 9.08 1.10 9.99
5.03 EJE 1 m2 1 11.26 1.10 12.39
5.04 EJE 3 m2 1 11.26 1.10 12.39

6.00 SS.HH. SECUNDARIA - Segundo Nivel M2 SOGA L H 55.64


6.01 EJE 2 m2 1 3.55 3.30 11.72
6.02 EJE 4 m2 1 6.51 3.30 21.48
6.03 EJE B m2 1 3.25 3.30 10.73
6.04 EJE C m2 1 3.55 3.30 11.72

TARRAJEO
7.00 VIGAS M2 L 84.24

7.01 PABELLON 5 - Primer Nivel


V102 = EJES 2-3 m2 2 1.10 9.35 20.57
V101 = EJES 1-4 m2 2 1.10 9.35 20.57
VP = EJE A m2 1 1.10 10.51 11.56
VP = EJE C m2 2 1.10 10.51 23.12
7.02 PABELLON 6- Primer Nivel
V101= EJES 1-3 - m2 2 1.10 2.55 5.61

V103 = EJE 2 - m2 1 1.10 2.55 2.81

8.00 MUROS M2 L H 227.36

8.01 PABELLON 5 - Primer Nivel

EJE A (Interno y externo) m2 2 7.91 2.00 31.64

EJE C - Muro bajo (Interno) m2 2 7.80 0.90 14.04

Tabique Área de Profesores (Interno y externo) m2 2 3.96 2.78 22.02

8.02 PABELLON 5 - Segundo Nivel

Tabique Interno (Centro de carga) m2 2 7.16 3.37 48.26

8.03 PABELLON 5 - Parapeto

EJE A (Interno) m2 1 12.71 1.10 13.98

EJE C (Interno) m2 1 12.71 1.10 13.98

EJE 1 (Interno) m2 1 7.83 1.10 8.61

EJE 3 (Interno) m2 1 7.83 1.10 8.61

8.04 PABELLON 6 - Primer Nivel

EJE A-A m2 2 4.43 1.83 16.21

EJE C-C m2 1 5.53 0.95 5.25

8.05 PABELLON 7 - Parapeto

EJE A (Interno) m2 1 9.08 1.10 9.99

EJE C (Interno) m2 1 9.08 1.10 9.99

EJE 1 (Interno) m2 1 11.26 1.10 12.39

EJE 3 (Interno) m2 1 11.26 1.10 12.39


9.00 COLUMNAS M2 H 49.84

9.01 PABELLON 5 - Primer Nivel


C-3 (EJE A-2) m2 2 2.60 3.08 16.02
C-3 (EJE A-3) m2 2 2.30 3.08 14.17
C-3 (EJE C-3) m2 2 0.30 3.08 1.85
9.02 PABELLON 5 - Segundo Nivel
COLUMNA (EJE A) m2 3 1.00 3.37 10.11
9.03 PABELLON 6 - Primer Nivel
C-2 (EJE A) m2 2 0.50 2.75 2.75

C-3 (EJE A) m2 2 0.90 2.75 4.95


10.00 COLUMNETAS M2 H 37.47

10.01 PABELLON 5 - Primer Nivel


Ca (EJE A) (Interno y externo) m2 6 0.50 2.00 6.00
Ca Baja (EJE C) (Interno) m2 4 0.25 0.90 0.90
Ca Alta (EJE C) (Interno) m2 4 0.25 2.78 2.78
10.02 PABELLON 5 - Seguno Nivel
Ca (Tabique interno Centro de Carga) m2 2 0.56 3.37 3.77
Ca (Tabique interno Centro de Carga) m2 2 0.54 3.37 3.64
Ca (Tabique interno Centro de Carga) m2 2 0.60 3.37 4.04
Ca (Eje A) m3 4 0.60 3.37 8.09
10.03 PABELLON 5 - Parapeto
Ca (EJE A) (Interno) m2 4 0.15 1.10 0.66
Ca (EJE C) (Interno) m2 4 0.15 1.10 0.66
Ca (EJE 1) (Interno) m2 4 0.15 1.10 0.66
Ca (EJE 3) (Interno) m2 4 0.15 1.10 0.66
10.04 PABELLON 6 - Primer Nivel
Ca (EJE A) (Interno y externo) m2 4 0.50 1.50 3.00
Ca (EJE C) (Interno) m2 4 0.25 0.95 0.95
10.05 PABELLON 7 - Parapeto
Ca (EJE A) (Interno) m2 3 0.15 1.10 0.50
Ca (EJE C) (Interno) m2 3 0.15 1.10 0.50
Ca (EJE 1) (Interno) m2 2 0.15 1.10 0.33

Ca (EJE 3) (Interno) m2 2 0.15 1.10 0.33


11.00 VIGUETAS M2 L 13.70

11.01 PABELLON 5 - Primer Nivel


EJE A (Interno y externo) m2 10.41 0.20 2.08
EJE C (Tramo 1-3) (Interno) m2 6.99 0.10 0.70
11.02 PABELLON 5 - Parapeto
EJE A (Interno) m2 13.31 0.10 1.33
EJE C (Interno) m2 13.31 0.10 1.33
EJE 1 (Interno) m2 11.06 0.10 1.11
EJE 4 (Interno) m2 11.06 0.10 1.11
11.03 PABELLON 6 - Primer Nivel
EJE A (Interno y externo) m2 5.55 0.20 1.11
EJE C (Interno) m2 6.53 0.10 0.65
11.04 PABELLON 7 - Parapeto
EJE A (Interno) m2 9.53 0.10 0.95
EJE C (Interno) m2 9.53 0.10 0.95
EJE C (Interno) m2 11.86 0.10 1.19

EJE C (Interno) m2 11.86 0.10 1.19


12.00 DERRAMES ML 46.61

12.01 PABELLON 5 - Primer Nivel


VENTANAS (EJE A) ml 11.41
VENTANAS (EJE C) (Tramo 2-3) ml 10.28
12.02 PABELLON 5 - Segundo Nivel
PUERTA (EJE A) ml 5.42
12.03 PABELLON 6 - Primer Nivel
VENTANAS (EJES A-C) ml 14.08
PUERTA ml 5.42

BRUÑADO INTERNO Y EXTERNO


13.00 PABELLONES ML N° 343.85

PABELLON 5 - Primer Nivel - Eje A (Interno y externo) ml 2 34.46 68.92

PABELLON 5 - Primer Nivel - Eje C - Tramo 1-3 (Interno) ml 2 32.92 65.84

PABELLON 5 - Primer Nivel - Tabique Área Profesores (Internoml


y externo) 2 3.08 6.16

PABELLON 5 - Segundo Nivel - Tabique (Interno y externo) ml 2 10.99 21.98

PABELLON 6 - Primer Nivel - Eje A (Interno y externo) ml 2 38.15 76.30

PABELLON 6 - Primer Nivel - Eje C (Interno) ml 1 33.25 33.25

PABELLON 7 - Parapeto - Ejes A-C (Interno) ml 1 38.16 38.16

PABELLON 7 - Parapeto - Ejes 1-3 (Interno) ml 1 33.24 33.24

ZOCALO
14.00 PABELLONES M M 35.61
PABELLON 5 - Primer Nivel (Eje A) ml 10.31

PABELLON 6 - Primer Nivel (Eje A) ml 7.51

PABELLON 7 - Parapeto (Ejes A-C) ml 17.79

VIGUETAS
15.00 PABELLON 5 - Primer Nivel Fondo H L 0.22

EJE A m3 0.15 0.10 8.41 0.13


EJE C (Tramo 1-3) m3 0.15 0.10 5.99 0.09
16.00 PABELLON 6 - Primer Nivel Fondo H L 0.08

EJE A m3 0.15 0.10 5.55 0.08


17.00 PABELLON 7 - Segundo Nivel Fondo H L 0.15

PARAPETO m3 0.15 0.10 9.71 0.15

18.00 PABELLON 7 - Parapeto Fondo H L 0.58

EJE A m3 0.15 0.10 8.53 0.13


EJE C m3 0.15 0.10 8.53 0.13
EJE 1 m3 0.15 0.10 10.86 0.16
EJE 3 m3 0.15 0.10 10.86 0.16

COLUMNETAS
19.00 PABELLON 5 - Primer Nivel N° H 1.05

Columneta de Tabique Interno (Área de Profesores) m3 2 0.15 0.20 3.08 0.18


Ca (EJE A) m3 6 0.15 0.25 2.00 0.45
Ca - Baja (EJE C) m3 3 0.15 0.25 0.90 0.10
Ca - Alta (EJE C) m3 3 0.15 0.25 2.78 0.31
20.00 PABELLON 5 - Segundo Nivel N° H 0.55

Columneta de Tabique Interno (Centro de Carga) m3 1 0.15 0.22 3.37 0.11


Columneta de Tabique Interno (Centro de Carga) m3 1 0.15 0.27 3.37 0.14
Columneta de Tabique Interno (Centro de Carga) m3 1 0.15 0.30 3.37 0.15
Columneta (Eje A) m3 1 0.15 0.30 3.37 0.15
21.00 PABELLON 6 - Primer Nivel N° H 0.37

Ca (EJE A) m3 4 0.15 0.25 1.50 0.23


Ca (EJEC) m3 4 0.15 0.25 0.95 0.14
22.00 PABELLON 7 - Parapeto N° H 1.62

Ca (EJE A) m3 3 0.15 0.15 1.08 0.49


Ca (EJE C) m3 3 0.15 0.15 1.08 0.49
Ca (EJE 1) m3 2 0.15 0.15 1.08 0.32
Ca (EJE 3) m3 2 0.15 0.15 1.08 0.32
23.00 PABELLON 7 - Segundo Nivel N° H 0.09

4 Ca (PARAPETO) m3 4 0.15 0.15 1.01 0.09


24.00 SS.HH. SECUNDARIA - Segundo Nivel N° H 0.40

Ca (EJE 4) m3 1 0.15 0.25 3.30 0.12


Cp (EJE C) m3 1 0.15 0.15 3.30 0.07
Cc (EJE D) m3 1 0.15 0.40 3.30 0.20

COLUMNAS
25.00 SS.HH. SECUNDARIA - Segundo Nivel N° H 8.48

C1- EJE 1 m3 2 0.25 0.50 3.30 0.83


C1- EJE 2 m3 3 0.25 0.50 3.30 1.24
C1- EJE 3 m3 3 0.25 0.96 3.30 2.38
C1- EJE 4 m3 3 0.25 0.50 3.30 1.24
C1- EJE 5 m3 2 0.25 0.95 3.30 1.57
C1- EJE 6 m3 3 0.25 0.50 3.30 1.24

CONTRAPISO
26.00 PABELLONES 236.82

PABELLON 6 - Primer Nivel m2 59.18


PABELLON 6 - Segundo Nivel m2 59.18
PABELLON 7 - Segundo Nivel m2 59.23
PABELLON 8 - Primer Nivel m2 59.23

CERAMICO
27.00 PABELLONES 217.46

PABELLON 6 - Segunbdo Nivel m2 59.03


PABELLON 6 - Primer Nivel 40.27
PABELLON 7 - Segundo Nivel m2 59.08
PABELLON 8 - Primer Nivel m2 59.08

ZOCALO CERAMICO
28.00 PABELLONES 94.45

PABELLON 6 - Primer Nivel ml 31.47


PABELLON 7 - Segundo Nivel ml 31.49
PABELLON 8 - Primer Nivel ml 31.49

CIMIENTO CORRIDO- CONCRETO


2.00 Cimiento Corrido-Cerco=fc 210 M3 3.57

2.01 Cimiento Corrido-Cerco=fc 210 m3 5 1.70 0.70 0.60 3.57

SOLADOS-CERCO
2.00 SOLADOS-Cerco=fc 210 M3 1.22

2.01 SOLADO-Cerco=fc 210 m3 6 1.60 0.90 0.10 0.86


2.01 SOLADO-Cerco=fc 211 m3 3 1.30 0.90 0.10 0.35

AFIRMADO PARA CERCO(COLOCACION-COMPACTACION)

2.00 AFIRMADO M3 37.44

2.01 AFIRMADO -Cerco m3 41.60 0.90 37.44

VAL 2 - EJECUCION 25,541.30


ALBAÑILERIA 211.56 28.00 5,923.79
Pab.5 -1° nivel y escalera/ Pab. 6 - parpto./
Pab.7 - 2° nivel Prim y parpto./Ss.hh Secund.
- 2°nivel
TARRAJEO
VIGAS - Pab 5. y Pab 6. 84.24 25.00 2,105.95
MUROS - Pab. 5 /Pab. 6 /Pab. 7 227.36 18.00 4,092.47
COLUMNAS - Pab. 5 /Pab.6 49.84 26.00 1,295.89
COLUMNETAS . Pab.5/Pab.6/Pab.7 37.47 25.00 936.65
VIGUETAS - Pab.5/Pab. 6 /Pab.7 13.70 25.00 342.40
DERRAMES - Pab. 5 /Pab.6 46.61 3.00 139.83
BRUÑADO 343.85 3.00 1,031.55
Pab.5 -1° nivel y 2° nivel
Pab.6 -1° nivel
Pab.7 -Parapeto
ZOCALO 35.61 10.00 356.10
Pab.5 /Pab.6 / Pab. 7
VIGUETAS 1.03 75.00 77.00
Pab.5 /Pab.6 / Pab. 7
COLUMNETAS 4.07 75.00 305.56
Pab.5/Pab.6 /Pab.7/ S.hh 2° nivel
COLUMNAS 8.48 75.00 636.08
Ss.hh Secundd. 2° nivel
CONTRAPISO 236.82 12.00 2,841.84
Pab 6 . 1° y 2° nivel / Pab. 7-2° nivel / Pab. 8 1° nivel
CERAMICO 217.46 14.00 3,044.44
Pab.6 /Pab. 7 / Pab.8
ZOCALO CERAMICO 94.45 14.00 1322.30
Pab.8 Prim. Nivel, Parapeto
CIMIENTO CORRIDO 3.57 75.00 267.75
SOLADOS 1.22 60.00 72.90
AFIRMADO 37.44 20.00 748.80
Sin Igv 25,541.30