HOJA DE METRADO

ACERO - KG/M

OBRA : "COSTRUCCION DE UNA VIVIENDA UNIFAMILIAR" 1/4"


3/8"
1/2"
5/8"
FECHA : ABRIL DE 2014 HECHO POR : ING. HOJA N° 1 3/4"
1"

MEDIDAS Nº SUB TOTAL


Nº DESCRIPCION UNID DE
LARGO ANCHO ALTO LONG. AREA VOL. KG.
VECES

01 OBRAS DE CONCRETO SIMPLE


01.01 CIMIENTOS
01.01.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA GRANDE
Eje 1 y 1 M3 10.00 0.50 1.000 2.00 10.00
Eje 2 y 2 M3 11.50 0.50 1.000 1.00 5.75
Eje 3-3,4-4,5-5,6-6 M3 9.50 0.50 1.000 4.00 19.00
Eje A-A y C-C M3 15.65 0.50 1.000 2.00 15.65
Eje B-B M3 13.10 0.50 1.000 1.00 6.55
56.95
1.02 SOBRECIMIENTOS
01.02.01 CONCRETO EN SOBRECIMIENTO F'c=175 KG/CM2+ 25% PIEDRA MEDIANA
Eje 1 y 1 M3 9.10 0.15 0.45 1.00 0.61
Eje 2 y 2 M3 10.30 0.15 0.45 1.00 0.70
Eje Ay A M3 13.85 0.15 0.45 1.00 0.93
Eje C y -C M3 12.45 0.15 0.45 1.00 0.84
3.08
ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO HASTA 0.40 M.
Eje 1 y 1 M2 9.10 0.45 2.00 8.19
Eje 2 y 2 M2 10.30 0.45 2.00 9.27
Eje Ay A M2 13.45 0.45 2.00 12.11
Eje C y -C M2 12.45 0.45 2.00 11.21
40.77
FALSO PISO
00.00.01 CONCRETO EN FALSO PISO DE 4" CEM:HOR 1:8 PARA PISO PULI M2
PARA PISO DE CEMENTO
salon de billar M2 13.50 9.70 1.00 130.95
tienda M2 4.70 2.00 1.00 9.40
ss.HH. M2 5.00 1.00 1.00 5.00
pasadiso M2 5.00 0.80 1.00 4.00
149.35
ZAPATA
COCRETO EN ZAPATA FC = 210 KG/CM2 M3
Z1 M3 1.20 1.20 0.60 6.00 5.18
Z2 M3 1.00 1.00 0.60 12.00 7.20
ZOLADO EN ZAPATA E = 10 CM M2 12.38
Z1 M2 1.20 1.20 0.10 6.00 0.86
OBZ2 M2 1.00 1.00 0.10 12.00 1.20
2.06
CONCRETO ARMADO
ZAPATA
COCRETO EN ZAPATA FC = 210 KG/CM2 M3 PESO N° F°
Z1 D= 1/2" M3 2.20 6.00 1.02 8.00 107.71
Z2 D= 1/2" M3 2.00 12.00 1.02 8.00 195.84
303.55

COLUMNAS
HOJA DE METRADO
ACERO - KG/M

OBRA : "COSTRUCCION DE UNA VIVIENDA UNIFAMILIAR" 1/4"


3/8"
1/2"
5/8"
FECHA : ABRIL DE 2014 HECHO POR : ING. HOJA N° 1 3/4"
1"

MEDIDAS Nº SUB TOTAL


Nº DESCRIPCION UNID DE
LARGO ANCHO ALTO LONG. AREA VOL. KG.
VECES
CONCRETO EN COLUMNAS f'c=175 kg/cm2
-
C1 M3 0.30 0.30 3.00 5.00 1.35
C2 M3 0.30 0.15 3.00 4.00 0.54
C3 M3 0.60 0.15 3.00 2.00 0.54
- C-4 M3 0.30 0.20 3.00 7.00 1.26
3.69
ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS

C-1 M2 1.20 3.00 4.00 14.40


C2 M2 0.90 3.00 4.00 10.80
C3 M2 1.20 3.00 4.00 14.40
C4 M2 1.00 3.00 4.00 12.00
51.60

00.00.01 ACERO EN COLUMNAS FY=4200 KG/CM2 KG


KG CANT COLMPESO N° F°
C-1 5/8" KG 4.20 5.00 1.60 6.00 201.60
ESTRIBO Ø 3/8" KG 1.32 0.58 150.00 114.84
C2 5/8" KG 4.00 4.00 1.60 12.00 307.20
ESTRIBO Ø 3/8" 1.02 0.58 120.00 70.99
C3 5/8" KG 4.10 4.00 1.60 4.00 104.96
ESTRIBO Ø 3/8" 1.42 0.58 60.00 49.42
C 4 5/8" KG 4.15 7.00 1.60 6.00 278.88
ESTRIBO Ø 3/8" 1.12 0.58 210.00 1,127.89

00.01 VIGAS
00.01.01 CONCRETO EN VIGAS F'C=175 KG/CM2
- Eje 1-1, 6-6 M3 9.10 0.15 0.30 2.00 0.82
- Eje 2-2 M3 4.55 0.15 0.30 1.00 0.20
- Eje 2" M3 4.65 0.30 0.30 1.00 0.42
- Eje 3 - 3, 4-4, 5-5 M3 10.20 0.30 0.30 3.00 2.75
- Eje A - A M3 13.85 0.20 0.30 1.00 0.83
- Eje C-C M3 14.44 0.20 0.30 1.00 0.87
- Eje B-B M3 14.00 0.30 0.30 1.00 1.26
7.15

00.01.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS


Eje 1-1, 6-6 M2 9.10 0.90 4.00 32.76
Eje 2-2 M2 4.55 0.60 4.00 10.92
Eje 2" M2 4.65 0.60 2.00 11.16
Eje 3 - 3, 4-4, 5-5 M2 10.20 0.60 2.00 24.48
Eje A - A M2 13.85 0.60 2.00 33.24
Eje C-C M2 14.44 0.60 2.00 34.66
Eje B-B M2 14.00 0.60 2.00 147.22

00.01.03 ACERO EN VIGAS FY=4200 KG/CM2 KG Lag PESO N° F°


EJE 1-1 VS-1 (.15 X Ø 1/2" KG 10.34 1.02 4.00 42.19
EJE 6 - 6 S- 1(.15 X .30) Ø = 1/2" KG 10.34 1.02 4.00 42.19
ESTRBOS DE Ø = 1/4" KG 1.02 0.25 146.00 37.23
EJE 2-2 VS - 2 ( .30 X .30) Ø = 1/2" KG 10.34 1.02 4.00 4.00 168.75
ESTRBOS DE Ø = 1/4" KG 1.32 0.25 292.00 96.36
EJE A- A , C- C V S - 1 (.20X.30) Ø = 1/2" KG 15.80 1.02 4.00 4.00 257.86
ESTRBOS DE Ø = 1/4" KG 1.12 0.25 242.00 67.76
EJE V CH B-B (.30X.40) Ø = 1/2" KG 15.80 1.02 4.00 64.46
ESTRBOS DE Ø = 1/4" KG 1.40 0.25 242.00 84.70
861.49

#REF! MUROS Y TABIQUES DE ALBAÑILERIA


#REF! MURO DE CABEZA LADRILLO KING KONG 18 HUECOS DE ARCILLA - MEZCLA CEMENTO ARENA 1:5
HOJA DE METRADO
ACERO - KG/M

OBRA : "COSTRUCCION DE UNA VIVIENDA UNIFAMILIAR" 1/4"


3/8"
1/2"
5/8"
FECHA : ABRIL DE 2014 HECHO POR : ING. HOJA N° 1 3/4"
1"

MEDIDAS Nº SUB TOTAL


Nº DESCRIPCION UNID DE
LARGO ANCHO ALTO LONG. AREA VOL. KG.
VECES
EJE A-A MLL 13.85 2.80 38.78
EJE C-C MLL 13.85 2.80 38.78
EJE 1-1 MLL 9.20 2.80 25.76
EJE 6-6 MLL 9.20 2.80 25.76
EJE 2-2 MLL 9.20 2.80 25.76
EJE DE E MLL 3.50 2.40 8.40
163.24
HOJA DE METRADO
ACERO - KG/ML

.25
.58
1.02
1.60
2.26
4.04

TOTAL
HOJA DE METRADO
ACERO - KG/ML

.25
.58
1.02
1.60
2.26
4.04

TOTAL
HOJA DE METRADO
ACERO - KG/ML

.25
.58
1.02
1.60
2.26
4.04

TOTAL
CALCULO DE PESO DE MATERIALES EN OBRA
PROY. : CONSTRUCCION DE UNA VIVIEN UNIFAMILIAR

PESO
ITEM DESCRIPCION CANTIDAD UNIDAD
EN KG
1.00 ACERO CORRUGADO D=5/8" 1,155.57 Kg. 1.00
2.00 ALAMBRES NEGRO RECOCIDON N° 16 200.50 Kg. 1.00
ALAMBRES NEGRO RECOCIDON N° 8 40.10 KG 1.00
3.00 CEMENTO PORTLAND TIPO I DE 42.5KG 200.50 Bolsa 42.50
4.00 CLAVOS CON CAVEZA DE 3" 110.00 Kg. 1.00
5.00 LADRILLO K.K. 18 HUECOS 6,366.36 Und. 2.70
6.00 MADERA 1,300.50 P2 1.50
7.00 HORMIGON 210.50 M3 1.00
8.00 ACERO CORRUGADO D=1/2" 750.50 Kg 1.00
9.00 ACERO CORRUGADO D=1/4" 300.10 Kg 1.00
10.00 ACERO CORRUGADO D=3/8" 250.50 Kg 1.00

CANTIDAD DE PESO TOTAL DE LOS MATERIALES EN KG.


ACERO CORRUGADO CANTIDA EN KG UND N° VECES
ACERO CORRUGADO D=5/8" 1,155.57 KG 1.00
ACERO CORRUGADO D=3/8" 250.50 KG 1.00
ACERO CORRUGADO D=1/4" 300.10 KG 1.00
ACERO CORRUGADO D= 1/2" 861.49 KG 1.00
HORMIGON
CANTIDA UND N° VECES
PIEDRA MEDINA PARA CIMIENTO 2.61 M3 1.00
HORMIGON 257.89 M3 1.00

N° DE VOLQUETE
BRA

PARCIAL
PESO EN KG
1,155.57
160.40
40.10
8,521.25
110.00
17,189.17
1,950.75
210.50
750.50
300.10
250.50

30,638.84
N° DE VARILLA
80.25
47.99
133.38
93.84

2.61
257.89

14.03