CRONOGRAMA DE ADQUISICIÓN DE MATERIALES

N° Recurso Unidad Parcial S/. MES 01 MES 02

1 ALAMBRE NEGRO RECOCIDO # 16 kg 487.45 487.45


2 ALAMBRE NEGRO RECOCIDO # 8 kg 209.23 209.23
3 CLAVOS PARA MADERA CON CABEZA DE 1" kg 3.65 3.65
4 CLAVOS PARA MADERA CON CABEZA DE 2" kg 4.98 4.98
5 CLAVOS PARA MADERA CON CABEZA DE 3" kg 141.32 141.32
6 CLAVOS PARA MADERA CON CABEZA DE 4" kg 39.01 39.01
7 PERNO DE ANCLAJE 5/8"x5.0m pza 642.12 642.12
8 GIGANTOGRAFIA A COLOR 3.60X2.40m u 136.12 136.12
9 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 7,085.08 7,085.08
10 PIEDRA CHANCADA DE 3/4" m3 9,577.02 9,577.02
11 PIEDRA GRANDE TM 10" m3 3,101.54 3,101.54
12 ARENA GRUESA m3 5,980.64 5,980.64
13 AFIRMADO PUESTO A OBRA m3 18,450.02 18,450.02
14 EMULSION ASFALTICA gal 10.44 10.44
15 CEMENTO PORTLAND TIPO I (42.5 kg) bls 34,464.35 34,464.35
16 CERROJO DE 4" u 25.98 25.98
17 BISAGRA ALUMINIZADA 4" X 4" u 39.00 39.00
18 YESO EN BOLSAS DE 25 kg bls 117.68 117.68
19 SOLDADURA CELLOCORD kg 9.84 9.84
20 LACA DESMOLDEADORA gal 412.57 412.57
21 SILICONA u 7.80 7.80
22 PEGAMENTO DE ADHERENCIA kg 146.28 146.28
23 LAMINA REFLECTIVA DE 0.20X0.30 M. u 144.56 144.56
24 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 816.74 816.74
25 TRANSPORTE DE ESTRUCTURA METALICA (LIMA - PUENTE) t 7,133.72 7,133.72
26 MOVILIZACION Y DESMOVILIZACION DE EQUIPO glb 40,673.66 40,673.66
27 HORMIGON (PUESTO EN OBRA) m3 7,901.71 7,901.71
28 COSTALILLOS pza 241.04 241.04
29 SEÑAL VERTICAL INFORMATIVA u 6,200.32 6,200.32
30 SEÑAL VERTICAL PREVENTINA 0.60x0.60 M. u 1,104.60 1,104.60
31 MADERA TORNILLO p2 10,150.58 10,150.58
32 TACOS DE MADERA TORNILLO 48"x12"x4" p2 1,975.15 1,975.15
33 MADERA EUCALIPTO ROLLIZO 4" X 6 m pza 78.78 78.78
34 TRIPLAY DE 4' X 8' X 4 mm pl 1,104.00 1,104.00
35 TRIPLAY DE 18 mm PARA ENCOFRADO pl 317.03 317.03
36 GEOTEXTIL NO TEGIDO TIPO I m2 112.36 112.36
37 GAVION CAJA ZN-10% AL 10x12cm 2.7x3.4mm 5.0x1.0x1.0 u 1,915.62 1,915.62
38 GAVION CAJA ZN-10% AL 10x12cm 2.7x3.4mm 5.0x1.0x2.0 u 2,813.51 2,813.51
39 GAVION CAJA ZN-10% AL 10x12cm 2.7x3.4mm 5.0x1.0x1.5 u 7,071.50 7,071.50
40 GAVION TIPO COLCHON DE 5.0x2.0x0.30m 10x12cm/3.4mm 3Zn+Al u 2,224.38 2,224.38
41 ANGULO DE ACERO PESADO DE 4" X 4" X 1/4" X 6 m pza 1,734.44 1,734.44
42 PINTURA DE TRAFICO REFLECTIVO NEGRO gal 49.77 49.77
43 PINTURA DE TRAFICO REFLECTIVO AMARILLO gal 49.77 49.77
44 PINTURA ESMALTE gal 470.36 470.36
45 CALAMINA GALVANIZADA 3.60 X 0.80m X 0.6 mm pl 898.08 898.08
46 PLANCHA DE TECKNOPOR DE 1/2" pl 5.97 5.97
47 VIDRIO CORRIENTE m2 64.80 64.80

COSTO DIRECTO 176,344.57 175,774.67 569.90


IGV (18%) 31,742.02 31,639.44 102.58

TOTAL 208,086.59 207,414.11 672.48

EXPEDIENTE TECNICO: “INSTALACIÓN DE PUENTE MODULAR COLPA – PACLLÓN - BOLOGNESI – ANCASH”