CÓMPUTOS MÉTRICOS
Unidad
Nº ACTIVIDADES
Veces
Nº de
descripcion eje de a Largo Ancho Alto
CÓMPUTOS MÉTRICOS
1.00 1.00
1.00 1.00
171.98 171.98
1.45 12.07
0.91
4.82
0.29
3.91
0.70
4.34 8.71
0.26
3.52
0.60
11.00 17.89
6.90
2.89 5.41
0.17
2.34
30.14 56.35
1.79
24.42
105.49 162.06
6.27
85.46
4.55
5.56
-6.30
-3.52 1.00
-28.00 1.00
-6.00 1.00
-1.44 12.07
21.35 21.35
14.00 14.00
15.32 15.32
4.80 4.80
12.70
32.79 32.79 5.41
56.35
1.36 2.54 164.94
0.08 32.79
1.11 3.04
206.68
124.33 206.68 77.04
82.35 35.67
16.21
16.21 16.21 11.48
92.49
0.44 8.20 71.45
2.79 65.06
0.34 49.98
2.50 352.50
1.58 9.82
0.55 32.56
197.95
48.00 87.67 4.00
30.00 2.00
4.82 2.00
4.85
15.00
8.89 72.25 282.71
56.60 352.50
6.77 1.00
16.00 65.02
12.00
5.88
5.84
3.30
10.00
12.00
30.42 49.98
12.56
7.00
229.06 346.74
13.60
185.56
4.55
5.56
-13.68
-7.04
-56.00
-12.00
-2.88
4.05 7.57
3.52
28.00 103.38
6.00
2.25
1.44 1.44
28.00 37.69
6.00
1.44
2.25
28.00 37.69
6.00
1.44
2.25
48.00 193.60
4.82
4.85
30.00
66.32
26.92
7.64
5.05
8.00 8.00
15.00 15.00
12.60 282.71
7.04
56.00
6.24
2.88
30.19
32.82
57.27
0.62
1.62
35.76
4.82
4.85
30.00
229.06 352.50
13.60
185.56
4.55
5.56
-13.68
-7.04
-56.00
-6.24
-2.88
1.00 1.00
PRESUPUESTO DE EJECUCION DE OBRA
ITE PRECIO
DESCRIPCION UND. CANTIDAD
M UNITARIO
1 Transporte de materiales Tprte 1.00 5,000.00
2 Letrero en Obras Pza. 1.00 795.64
3 Replanteo de obras m2 171.98 2.46
4 Excavación 0-2 M Terr. blando m3 12.07 47.52
5 Cimientos de ladrillo tubular m3 8.71 886.86
6 Cordon de acera ml. 17.89 64.03
7 Sobrecimientos de ladrillo tubular m3 5.41 886.86
8 Capa impermeabilizante ml 56.35 23.42
9 Muros de ladrillo tubular (soguilla) m2 152.06 129.06
10 Columnas de ladrillo vista A - 21 ml. 21.35 127.37
11 Elementos de sujeccion de serchas Pza. 14.00 12.08
12 Viga de madera incorruptible 4,00 " x 8.00 "(Tajibo) ml. 15.32 50.83
13 Pizarra de cemento inc. Marco y portatizas m2 4.80 262.93
14 Relleno y compactado inc. Material m3 32.79 27.42
15 Viga Cadena de Hº Aº m3 2.54 4,543.99
16 Cubierta de calamina de Zinc Nº 28 térmica m2 206.68 210.97
17 Cumbrera de calamina plana ml. 16.21 81.77
18 Contrapiso de cascote de ladrillo m3 8.20 66.37
19 Piso de ceramica esmaltada m2 87.67 181.83
20 Piso de ceramica roja m2 72.25 96.77
21 Zocalos de ceramica esmaltada ml. 65.02 43.81
22 Zocalos de ceramica roja ml. 49.98 43.81
23 Revoque de cemento arena m2 346.74 76.58
24 Prov. Y coloc. Puerta de mad. inc. marco (cuta) y quinc. m2 7.57 966.38
25 Marco p/ventanas (cuta) m2 103.38 465.88
26 Protectores de Fe Ø 1/2" m2 37.69 385.80
27 Prov. y coloc. de vidrio doble de 3,00 mm. m2 37.69 212.50
28 Cielo falso de machiembre de madera cedro m2 193.60 197.63
29 Luminaria fluorescente tipo espiral 40 Watts Pto. 8.00 313.00
30 Tomacorrientes placa doble Pto 15.00 207.00
31 Barniz en carpinteria de madera m2 282.71 33.88
32 Pintura latex m2 352.50 30.00
33 Limpieza general y retiro de escombros Glb 1.00 1,718.25
Total Bs.
TOTAL
5,000.00
795.64
423.06
573.70
7,724.55
1,145.50
4,797.22
1,319.62
19,625.32
2,719.35
169.12
778.72
1,262.06
899.18
11,541.73
43,602.75
1,325.49
544.23
15,941.04
6,991.63
2,848.53
2,189.62
26,553.35
7,315.50
48,162.67
14,540.80
8,009.13
38,261.17
2,504.00
3,105.00
9,578.38
10,575.05
1,718.25
282,081.69
C O M P U T O S M E T R I C
PROYECTO: CONSTRUCCION AULAS Y DIRECCION C. C
43.86
Unidad
Nº ACTIVIDADES
descripcion eje
3 Replanteo de obras m2
zapatas columnas
zapatas columnas
7 Capa impermeabilizante ml
Vanos de puertas
Vanos de ventanas
14 Viga Cadena de Hº Aº m3
columnas
Vanos de puertas
Vanos de ventanas
ventanas
cielo falso
29 Pintura latex m2
Vanos de puertas
Vanos de ventanas
CÓMPUTOS MÉTRICOS
Veces Cantidad
factor
Nº de
cantidad
de a Largo Ancho Alto total a
parcial
ejecutar
1 1.00 1.00
1 1.00 1.00
8 8.00 8.00
6 6.00 6.00
1 1.00 1.00
18 18.00 18.00
1 1.00 1.00
PRESUPUESTO DE EJECUCION DE OBRA
ITE PRECIO
DESCRIPCION UND. CANTIDAD
M UNITARIO
1 Transporte de materiales Tprte 1.00 5,000.00
2 Letrero en Obras Pza. 1.00 795.64
3 Replanteo de obras m2 208.15 2.46
4 Excavación 0-2 M Terr. blando m3 10.67 417.52
5 Cimientos de ladrillo tubular m3 14.96 886.86
6 Sobrecimientos de ladrillo tubular m3 6.99 886.86
7 Capa impermeabilizante ml 72.79 23.42
8 Muros de ladrillo tubular (soguilla) m2 209.54 129.06
9 Columnas de ladrillo vista A - 21 ml. 26.73 127.35
10 Elementos de sujeccion de serchas Pza. 18.00 12.08
11 Viga de madera incorruptible 4,00 " x 8.00 "(Tajibo) ml. 22.47 50.83
12 Pizarra de cemento arena m2 4.80 262.93
13 Relleno y compactado inc. Material m3 38.49 27.42
14 Viga Cadena de Hº Aº m3 3.93 4,543.99
15 Cubierta de calamina de Zinc Nº 28 térmica m2 310.46 210.97
16 Cumbrera de calamina plana ml. 24.35 81.77
17 Contrapiso de cascote de ladrillo m3 9.62 66.37
18 Piso de ceramica roja m2 192.44 96.77
19 Zocalos de ceramica roja ml. 79.97 43.81
20 Revoque de cemento arena m2 391.02 76.58
21 Prov. Y coloc. Puerta de mad. inc. marco (cuta) y quinc. m2 7.84 966.38
22 Marco p/ventanas c. barrotes Ø1/2" inc. malla milim. y criba m2 56.10 465.88
23 Prov. Y coloc. De vidrios dobles 3,00 mm m2 56.10 212.50
24 Cielo falso de machiembre de madera m2 339.13 187.20
25 Iluminacion Fluorescente (2 x 40 W) Pto. 8.00 414.07
26 Iluminacion Fluorescente (1 x 40 W) Pto. 6.00 325.93
27 Iluminacion Fluorescente (1 x 20 W) Pto. 1.00 207.00
28 Tomacorrientes placa doble Pto 18.00 123.75
29 Barniz en carpinteria de madera m2 466.99 33.88
30 Pintura latex m2 391.02 30.00
31 Limpieza general y retiro de escombros Glb 1.00 1,718.25
TOTAL
5,000.00
795.64
512.05
4,454.21
13,265.57
6,197.24
1,704.74
27,044.14
3,404.07
217.44
1,142.15
1,262.06
1,055.36
17,860.88
65,498.27
1,991.10
638.62
18,622.71 77.04 14,825.81
3,503.49
29,944.59
7,571.59
26,133.54
11,921.25
63,486.03
3,312.56
1,955.58
207.00
2,227.50
15,821.78
11,730.60
1,718.25
350,200.00
C O M P U T O S M E T R I C O S
ACTIVIDAD : CONSTRUCCION OFICINAS ADULTO MAYOR B. CONAVI D3
CÓMPUTOS MÉTRICOS
Unidad
Nº ACTIVIDADES Cantidad
Veces
factor
Nº de
cantidad
descripcion Largo Ancho Alto total a
parcial
ejecutar
OBRAS INICIALES
1 LETRERO DE OBRAS (SEGUN DISEÑO) Pza 1 1.00 1.00
13 RELLENO Y COMPACTADO INCLUYE RIPIO m3 acera 1 35.47 2.00 0.20 14.19 66.26
sala de espera 1 6.13 5.14 0.20 6.30
archivo 1 3.64 5.14 0.20 3.74
oficina 1 3.64 5.14 0.20 3.74
baño 1 1 1.64 5.14 0.20 1.69
baño 2 1 2.64 2.04 0.20 1.08
dormitorio 1 1 5.14 4.14 0.20 4.26
dormitorio 2 1 5.14 4.10 0.20 4.22
salon de reuniones 1 2.50 2.04 0.20 1.02
salon de reuniones 1 10.32 7.53 0.20 15.54
cocina 1 5.14 4.14 0.20 4.26
comedor 1 4.14 7.53 0.20 6.23
21 PROV. Y COLOC. PUERTA TABLERO INC. MARCO (CUTA) m2 Vanos de puertas 10 0.90 2.50 22.50 33.43
1 2.50 3.00 7.50
2 0.78 2.20 3.43
22 PROV. Y COLOC. VENTANA DE MADERA m2 vanos de ventana 5 2.00 1.70 17.00 74.68
2 1.20 0.60 1.44
7 2.50 1.50 26.25
3 3.00 1.80 16.20
1 1.84 1.80 3.31
3 1.94 1.80 10.48
23 PROV. Y COLOC. DE MALLA MILIMETRICA m2 vanos de ventana 5 2.00 1.70 17.00 74.68
2 1.20 0.60 1.44
7 2.50 1.50 26.25
3 3.00 1.80 16.20
1 1.84 1.80 3.31
3 1.94 1.80 10.48
24 PROV. Y COLOC. DE MALLA ELECTROSOLDADA DE 3/8" m2 vanos de ventana 5 2.00 1.70 17.00 74.68
2 1.20 0.60 1.44
7 2.50 1.50 26.25
3 3.00 1.80 16.20
1 1.84 1.80 3.31
3 1.94 1.80 10.48
INSTALACION ELECTRICA
30 PROV. Y COL. DE TOMACORRIENTES DOBLE Pto. 40 40.00 40.00
INSTALACION SANITARIA
36 PROV. Y COLOC. DE JUEGO DE BAñO Jgo. 2 2.00 2.00
43 CAMARA DE INSPECCION PREF 60X60 H=80CM CON TAPA Pza. 7 7.00 7.00
NORIA
46 EXCAVACION CON AGOTAMIENTO m3 area 1,33 1 1.33 12.00 15.96 15.96
ITE PRECIO
DESCRIPCION UND. CANTIDAD
M UNITARIO
1 Letrero de Obras (según diseño) Pza. 1.00 795.64
2 Prov. Y coloc. Bancos Coloniales Pza. 3.00 1,152.81
3 Refaccion de bancos existentes (cambio de listones de mad.) ml. 616.00 34.42
4 Refaccion sube y baja (largueros con sillines) Pza 1.00 2,000.00
5 Prov. Y coloc. Caballito con resorte Pza 1.00 1,205.61
6 Retiro Prov. Y coloc. Tobogan Pza. 1.00 2,724.85
7 Retiro Prov. Y coloc. de columpio Pza. 1.00 3,169.91
9 Limpieza general ( Obras menores ) Glb 1.00 594.07
TOTAL
795.64
3,458.43
21,202.10 308.00
2,000.00
1,205.61
2,724.85
3,169.91
594.07
35,150.61
C O M P U T O S M E T R I C O S
PROYECTO: CONSTRUCCION AULAS Y DIRECCION C. C. BOLIVAR
CÓMPUT
Unidad
Nº ACTIVIDADES
descripci
eje de a
on
3 Replanteo de obras m2
Zapatas
Zapatas
7 Cordon de acera m2
8 Capa impermeabilizante ml
mojinetes
mojinetes
Vanos de puertas
Vanos de ventanas
15 Viga Cadena de Hº Aº m3
puertas
puertas
Vanos de puertas
Vanos de ventanas
24 Prov. Y coloc. Puerta de mad. inc. marco (cuta) y quinc. m2
31 Pintura latex m2
Vanos de puertas
Vanos de ventanas
CÓMPUTOS MÉTRICOS
Veces
Nº de
factor
3 3.00 3.00
1 1.00 1.00
14 14.00 14.00
13 13.00 13.00
1 1.00 1.00
PRESUPUESTO DE EJECUCION DE OBRA
PRECIO
ITEM DESCRIPCION UND. CANTIDAD TOTAL
UNITARIO
1 Transporte de materiales Tprte 3.00 1,058.09 3,174.27
2 Letrero en Obras Pza. 1.00 807.74 807.74
3 Replanteo de obras m2 191.25 2.46 470.48
4 Excavación 0-2 M Terr. blando m3 12.24 47.52 581.64
5 Cimientos de ladrillo tubular m3 9.25 886.86 8,203.46
6 Sobrecimientos de ladrillo tubular m3 3.11 886.86 2,758.13
7 Cordon de acera m2 7.94 64.03 508.40
8 Capa impermeabilizante ml 58.91 23.42 1,379.67
9 Muros de ladrillo tubular (soguilla) m2 165.16 129.06 21,315.55
10 Columnas de ladrillo vista A - 21 ml. 15.25 127.37 1,942.39
11 Elementos de sujeccion de serchas Pza. 18.00 12.08 217.44
12 Viga de madera incorruptible 4,00 " x 8.00 "(Tajibo) ml. 17.03 50.83 865.63
13 Pizarra de cemento arena m2 4.80 262.93 1,262.06
14 Relleno y compactado inc. Material m3 22.79 27.42 624.90
15 Viga Cadena de Hº Aº m3 3.18 3,859.58 12,273.46
16 Cubierta de calamina de Zinc Nº 28 térmica m2 220.32 197.84 43,588.11
17 Cumbrera de calamina plana ml. 17.28 81.77 1,412.99
18 Contrapiso de cascote de ladrillo m3 7.60 66.37 504.41
19 Piso de ceramica Nacional m2 94.93 181.83 17,261.12
20 Piso de ceramica roja m2 56.98 96.77 5,513.95
21 Zocalos de ceramica nacional ml. 67.38 43.81 2,951.92
22 Zocalos de ceramica roja ml. 19.62 35.67 699.85
23 Revoque de cemento arena m2 165.16 76.58 12,647.95
24 Prov. Y coloc. Puerta de mad. inc. marco (cuta) y quin m2 5.73 966.38 5,537.36
25 Marco p/ventanas c. barrotes Ø1/2" inc. Malla milim. Y m2 43.69 465.88 20,354.30
26 Prov. Y coloc de vidrios dibles 3,00 mm m2 43.69 212.50 9,284.13
27 Cielo falso de machiembre de madera cedro m2 183.78 197.63 36,320.44
28 Iluminacion Fluorescente (40 W) rosca Pto. 14.00 313.00 4,382.00
29 Tomacorrientes placa doble Pto 13.00 123.75 1,608.75
30 Barniz en carpinteria de madera m2 236.66 33.88 8,018.04
31 Pintura latex m2 165.30 30.00 4,959.00
32 Limpieza general y retiro de escombros Glb 1.00 477.36 477.36
TOTAL 231,906.91