1.1. Obra Por Contrata (Santiago Matos)
1.1. Obra Por Contrata (Santiago Matos)
FACULTAD DE INGENIERIA
VALORIZACION
CURSO : Planificación y Control de Proyectos
SECCIÓN : "B"
ESTAMOS TOMANDO COMO SI RESIEN ESTUVIERAMOS ENPESANDO LA OBRA POR ELLO SOLO EN (ANTERIOR) EL METRADO ES 0
ANTERIOR
PARTIDAS METRADO C.U PRESUPUESTO METRADO MONTO
S 109.00 S/ 29.00 S/ 3,161.00 21.80 S/ 632.20
A 1.00 S/ 101.00 S/ 101.00 0.10 S/ 10.10
N 79.00 S/ 49.00 S/ 3,871.00 9.48 S/ 464.52
T 115.00 S/ 25.00 S/ 2,875.00 11.50 S/ 287.50
I 49.00 S/ 69.00 S/ 3,381.00 7.35 S/ 507.15
A 1.00 S/ 101.00 S/ 101.00 0.10 S/ 10.10
G 37.00 S/ 77.00 S/ 2,849.00 5.55 S/ 427.35
O 85.00 S/ 45.00 S/ 3,825.00 7.65 S/ 344.25
M 73.00 S/ 53.00 S/ 3,869.00 9.49 S/ 502.97
A 1.00 S/ 101.00 S/ 101.00 0.10 S/ 10.10
T 115.00 S/ 25.00 S/ 2,875.00 11.50 S/ 287.50
O 85.00 S/ 45.00 S/ 3,825.00 7.65 S/ 344.25
S 109.00 S/ 29.00 S/ 3,161.00 21.80 S/ 632.20
COSTO DIR S/ - S/ 33,995.00 114.07 S/ 4,460.19
GG 15.00% S/ 5,099.25 S/ 669.03
UTIIDAD 8.00% S/ 2,719.60 S/ 356.82
SUB TOTAL 0 S/ 41,813.85 S/ 5,486.03
IGV 18.00% S/ 7,526.49 S/ 987.49
COSTO DE O 0 S/ 49,340.34 S/ 6,473.52
VALORIZACION SEGUNDO MES
LA OBRA NO A PEDIDO ADELANTO DILERECTO Y ADELANTO DE MATERIALES
DO DEL MES 1
LADO RESTANTE
% METRADO MONTO %
25.000% 81.75 S/ 2,370.75 75.00%
30.00% 0.70 S/ 70.70 70.00%
15.50% 66.76 S/ 3,271.00 84.50%
10.00% 103.50 S/ 2,587.50 90.00%
35.00% 31.85 S/ 2,197.65 65.00%
30.00% 0.70 S/ 70.70 70.00%
45.00% 20.35 S/ 1,566.95 55.00%
39.00% 51.85 S/ 2,333.25 61.00%
18.00% 59.86 S/ 3,172.58 82.00%
30.00% 0.70 S/ 70.70 70.00%
10.00% 103.50 S/ 2,587.50 90.00%
39.00% 51.85 S/ 2,333.25 61.00%
25.00% 81.75 S/ 2,370.75 75.00%
S/ 25,003.28
S/ 3,750.49
S/ 2,000.26
S/ 30,754.03
S/ 5,535.73
26.45% S/ 36,289.75 73.55%
ACUMULADO MES 2
ANTERIOR
PARTIDAS METRADO C.U PRESUPUESTO METRADO
S 109.00 S/ 29.00 S/ 3,161.00 27.25
A 1.00 S/ 101.00 S/ 101.00 0.30
N 79.00 S/ 49.00 S/ 3,871.00 12.25
T 115.00 S/ 25.00 S/ 2,875.00 11.50
I 49.00 S/ 69.00 S/ 3,381.00 17.15
A 1.00 S/ 101.00 S/ 101.00 0.30
G 37.00 S/ 77.00 S/ 2,849.00 16.65
O 85.00 S/ 45.00 S/ 3,825.00 33.15
M 73.00 S/ 53.00 S/ 3,869.00 13.14
A 1.00 S/ 101.00 S/ 101.00 0.30
T 115.00 S/ 25.00 S/ 2,875.00 11.50
O 85.00 S/ 45.00 S/ 3,825.00 33.15
S 109.00 S/ 29.00 S/ 3,161.00 27.25
COSTO DI S/ - S/ 33,995.00 203.89
GG 15.00% S/ 5,099.25
UTIIDAD 8.00% S/ 2,719.60
SUB TOTAL 0 S/ 41,813.85
IGV 18.00% S/ 7,526.49
COSTO DE 0 S/ 49,340.34
PAGO DE VALORZACION 1 Y 2
3277
VALORIZACION TERCER MES
LA OBRA NO A PEDIDO ADELANTO DILERECTO Y ADELANTO DE MATERIALES
ACUMULADO MES 2
ACUMULADO RESTANTE
MONTO % METRADO MONTO %
S/ 2,212.70 70.00% 32.70 S/ 948.30 30.00%
S/ 55.55 55.00% 0.45 S/ 45.45 45.00%
S/ 2,438.73 63.00% 29.23 S/ 1,432.27 37.00%
S/ 1,581.25 55.00% 51.75 S/ 1,293.75 45.00%
S/ 1,690.50 50.00% 24.50 S/ 1,690.50 50.00%
S/ 55.55 55.00% 0.45 S/ 45.45 45.00%
S/ 1,851.85 65.00% 12.95 S/ 997.15 35.00%
S/ 2,830.50 74.00% 22.10 S/ 994.50 26.00%
S/ 2,282.71 59.00% 29.93 S/ 1,586.29 41.00%
S/ 55.55 55.00% 0.45 S/ 45.45 45.00%
S/ 1,581.25 55.00% 51.75 S/ 1,293.75 45.00%
S/ 2,830.50 74.00% 22.10 S/ 994.50 26.00%
S/ 2,212.70 70.00% 32.70 S/ 948.30 30.00%
S/ 21,679.34 S/ 12,315.66
S/ 3,251.90 S/ 1,847.35
S/ 1,734.35 S/ 985.25
S/ 26,665.59 S/ 15,148.26
S/ 4,799.81 S/ 2,726.69
S/ 31,465.39 63.8% S/ 17,874.95 36.23%
ACUMULADO MES 2
ANTERIOR
PARTIDAS METRADO C.U PRESUPUESTO METRADO
S 109.00 S/ 29.00 S/ 3,161.00 76.30
A 1.00 S/ 101.00 S/ 101.00 0.55
N 79.00 S/ 49.00 S/ 3,871.00 49.77
T 115.00 S/ 25.00 S/ 2,875.00 63.25
I 49.00 S/ 69.00 S/ 3,381.00 24.50
A 1.00 S/ 101.00 S/ 101.00 0.55
G 37.00 S/ 77.00 S/ 2,849.00 24.05
O 85.00 S/ 45.00 S/ 3,825.00 62.90
M 73.00 S/ 53.00 S/ 3,869.00 43.07
A 1.00 S/ 101.00 S/ 101.00 0.55
T 115.00 S/ 25.00 S/ 2,875.00 63.25
O 85.00 S/ 45.00 S/ 3,825.00 62.90
S 109.00 S/ 29.00 S/ 3,161.00 76.30
COSTO DI S/ - S/ 33,995.00 547.94
GG 15.00% S/ 5,099.25
UTIIDAD 8.00% S/ 2,719.60
SUB TOTAL 0 S/ 41,813.85
IGV 18.00% S/ 7,526.49
COSTO DE 0 S/ 49,340.34
PAGO DE VALORZACION 1 Y 2
VALORIZACION TERCER MES
LA OBRA NO A PEDIDO ADELANTO DILERECTO Y ADELANTO DE MATERIALES
ACUMULADO MES 2
ACUMULADO RESTANTE
MONTO % METRADO MONTO %
S/ 2,370.75 75.00% 27.25 S/ 790.25 25.00%
S/ 75.75 75.00% 0.25 S/ 25.25 25.00%
S/ 2,632.28 68.00% 25.28 S/ 1,238.72 32.00%
S/ 1,868.75 65.00% 40.25 S/ 1,006.25 35.00%
S/ 3,381.00 100.00% 0.00 S/ 0.00 0.00%
S/ 75.75 75.00% 0.25 S/ 25.25 25.00%
S/ 2,706.55 95.00% 1.85 S/ 142.45 5.00%
S/ 2,830.50 74.00% 22.10 S/ 994.50 26.00%
S/ 2,669.61 69.00% 22.63 S/ 1,199.39 31.00%
S/ 75.75 75.00% 0.25 S/ 25.25 25.00%
S/ 1,868.75 65.00% 40.25 S/ 1,006.25 35.00%
S/ 2,830.50 74.00% 22.10 S/ 994.50 26.00%
S/ 2,370.75 75.00% 27.25 S/ 790.25 25.00%
S/ 25,756.69 S/ 8,238.31
S/ 3,863.50 S/ 1,235.75
S/ 2,060.54 S/ 659.06
S/ 31,680.73 S/ 10,133.12
S/ 5,702.53 S/ 1,823.96
S/ 37,383.26 75.8% S/ 11,957.08 24.23%
ACUMULADO MES 2
ANTERIOR
PARTIDAS METRADO C.U PRESUPUESTO METRADO
S 109.00 S/ 29.00 S/ 3,161.00 81.75
A 1.00 S/ 101.00 S/ 101.00 0.75
N 79.00 S/ 49.00 S/ 3,871.00 53.72
T 115.00 S/ 25.00 S/ 2,875.00 74.75
I 49.00 S/ 69.00 S/ 3,381.00 49.00
A 1.00 S/ 101.00 S/ 101.00 0.75
G 37.00 S/ 77.00 S/ 2,849.00 35.15
O 85.00 S/ 45.00 S/ 3,825.00 62.90
M 73.00 S/ 53.00 S/ 3,869.00 50.37
A 1.00 S/ 101.00 S/ 101.00 0.75
T 115.00 S/ 25.00 S/ 2,875.00 74.75
O 85.00 S/ 45.00 S/ 3,825.00 62.90
S 109.00 S/ 29.00 S/ 3,161.00 81.75
COSTO DI S/ - S/ 33,995.00 629.29
GG 15.00% S/ 5,099.25
UTIIDAD 8.00% S/ 2,719.60
SUB TOTAL 0 S/ 41,813.85
IGV 18.00% S/ 7,526.49
COSTO DE 0 S/ 49,340.34
PAGO DE VALORZACION 1 Y 2
VALORIZACION TERCER MES
LA OBRA NO A PEDIDO ADELANTO DILERECTO Y ADELANTO DE MATERIALES
ACUMULADO MES 2
ACUMULADO RESTANTE
MONTO % METRADO MONTO %
S/ 3,161.00 100.00% 0.00 S/ 0.00 0.00%
S/ 101.00 100.00% 0.00 S/ 0.00 0.00%
S/ 3,871.00 100.00% 0.00 S/ 0.00 0.00%
S/ 2,875.00 100.00% 0.00 S/ 0.00 0.00%
S/ 3,381.00 100.00% 0.00 S/ 0.00 0.00%
S/ 101.00 100.00% 0.00 S/ 0.00 0.00%
S/ 2,849.00 100.00% 0.00 S/ 0.00 0.00%
S/ 3,825.00 100.00% 0.00 S/ 0.00 0.00%
S/ 3,869.00 100.00% 0.00 S/ 0.00 0.00%
S/ 101.00 100.00% 0.00 S/ 0.00 0.00%
S/ 2,875.00 100.00% 0.00 S/ 0.00 0.00%
S/ 3,825.00 100.00% 0.00 S/ 0.00 0.00%
S/ 3,161.00 100.00% 0.00 S/ 0.00 0.00%
S/ 33,995.00 S/ 0.00
S/ 5,099.25 S/ 0.00
S/ 2,719.60 S/ 0.00
S/ 41,813.85 S/ 0.00
S/ 7,526.49 S/ 0.00
S/ 49,340.34 100.0% S/ 0.00 0.00%
CURVA S
120.00%
100.00%
100.00%
80.00%
75.77%
80.00%
PORCENTAJE
63.77%
60.00%
60.00%
40.00% 26.45%
20.00%
20.00% 13.12%
5.00%
0.00%
0.5 1 1.5 2 2.5 3 3.5 4 4.5 5
VALORIZACIÓN
expediente tecnico
EJECUTADO cronograma
AVANCE ACUMULADO
MONTO % MONTO % DE AVANCE
S/ 6,473.52 13.12% S/ 6,473.52 262.40% comprobacion
S/ 6,577.07 26.45% ### 132.25% 26.45%
### 63.77% ### 106.29% 63.77%
S/ 5,917.87 75.77% ### 94.71% 75.77%
### 100.00% ### 100.00% 100.00%
RVA S
100.00%
80.00%
75.77%
PROGRAMADO
EJECUTADO
S/ 4,531.46 pagado
S/ 4,603.95 en tramite esc conveniente cabiar los montos totales que teniamos en la curva s
### en tramite por los nuevos montos calculados con la resta de adelanto y materiales?
S/ 4,142.51 en tramite
S/ 8,369.96 en tramite
os en la curva s
anto y materiales?