METRADO COSTO
ITEM PARTIDA UNIDAD EXPEDIENTE METRADO META UNITARIO PPTO
12 SISTEMA DE ALCANTARILLADO
12.01 RED DE DESAGUE - COLECTORES PRIMARIOS
12.02.02 MOVIMIENTO DE TIERRAS
12.01.02.01 EXCAVACION C/EQUIPO T.NORMAL H=1.50M, P/TUB DN 200MM DESAGUE m 6,177.12 640.07 14.12 9,037.79
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.02.04 EXCAVACION C/EQUIPO T.NORMAL H=2.00M, P/TUB DN 200MM DESAGUE m 4,770.76 100.82 18.01 1,815.77
12.01.02.04 EXCAVACION C/EQUIPO T.NORMAL H=2.50M, P/TUB DN 200MM DESAGUE 108.36 19.21 2,081.60
TAMAÑA
BZ 406_25 @ BZ 406_24 25.77
BZ 406_24 @ BZ 406_23 41.27
12.01.02.10 EXCAVACION C/EQUIPO T.NORMAL H=3.00M, P/TUB DN 200MM DESAGUE m 1,507.77 161.58 20.60 3,328.55
TAMAÑA
BZ 406_12 @ BZ 406_13 13.70
ESCOBAYA - SAN FRANCISCO
BZ 840@ BZ 841 h=2.53, h=2.79 11.71
BZ 847@ BZ 848 h=2.36, h=2.65 34.97
BZ 848@ BZ 849 h=2.65, h=1.60 23.04
BZ _A_7@ BZ _A_9 h=1.80, h=2.51 28.34
BZ _A_9@ BZ _A_10 h=2.51, h=2.58 16.41
BZ _A_10@ BZ _A_11 h=2.58, h=2.70 22.65
BZ _A_11@ BZ _A_12 h=2.70, h=2.65 10.76
12.02.03.13 EXCAVACION C/EQUIPO T.NORMAL H=3.50M, P/TUB DN 200MM DESAGUE m 300.53 154.22 21.40 3,300.31
12.02.03.16 EXCAVACION C/EQUIPO T.NORMAL H=4.00M, P/TUB DN 200MM DESAGUE m 173.12 132.29 21.80 2,883.92
TAMAÑA
BZ 406_5 @ BZ 406_6 51.58
BZ 406_6 @ BZ 406_7 41.12
BZ 406_7 @ BZ 406_9 39.59
12.02.03.19 EXCAVACION C/EQUIPO T.NORMAL H=4.50M, P/TUB DN 200MM DESAGUE m 258.20 20.66 22.26 459.89
12.02.03.22 EXCAVACION C/EQUIPO T.NORMAL H=5.00M, P/TUB DN 200MM DESAGUE m 156.33 125.28 24.22 3,034.28
12.01.02.55 REFINE Y NIVELACION ZANJA T.NORMAL, P/DESAGUE m 17,490.58 1,500.44 2.79 4,186.23
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.02.58 CAMA DE ARENA EN ZANJA H=0.10M, A=0.60M m 18,219.35 1,500.44 7.09 10,638.12
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.02.59 RELLENO PROTECTOR C/MAT PROPIO P/TUB 200MM, H=0.30M m 18,219.35 1,500.44 5.35 8,027.35
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.02.60 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=1.50M m 6,434.50 640.07 3.81 2,438.67
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.02.61 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=2.00M m 4,969.54 100.82 6.25 630.13
12.01.02.62 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=2.50M m 4,969.54 108.36 7.25 785.61
TAMAÑA
BZ 406_25 @ BZ 406_24 25.77
BZ 406_24 @ BZ 406_23 41.27
12.01.02.63 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=3.00M m 1,570.59 161.58 7.25 1,171.46
TAMAÑA
BZ 406_12 @ BZ 406_13 13.70
12.01.02.64 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=3.50M m 1,570.59 154.22 5.84 900.64
12.01.02.65 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=4.00M m 463.77 57.16 7.80 445.85
TAMAÑA
12.01.02.66 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=4.50M m 403.04 20.66 0.00
ESCOBAYA - SAN FRANCISCO
BZ _A_17@ BZ _A_18 h=7.47, h=4.25 15.82
BZ _A_18@ BZ _A_19 h=4.25, h=3.33 4.84
12.01.02.67 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=5.00M m 123.78 125.28 8.87 1,111.23
ESCOBAYA - SAN FRANCISCO
BZ 859A@ BZ 859B h=3.86, h=4.53 43.76
BZ 859B @ BZ 860 h=4.53, h=4.55 19.09
BZ _A_15@ BZ _A_16 h=3.44, h=6.64 32.96
BZ _A_16@ BZ _A_17 h=6.64, h=7.47 29.47
12.01.03.02 INSTALACION DE TUBERIA ISO 4435 S-25 DN=200MM m 18,219.35 1,500.44 4.28 6,421.88
TAMAÑA
12.01.03.03 PRUEBA HIDRAULICA PARCIAL A ZANJA DESCUBIERTA DE TUBERIA PVC/ISO 4435 m 18,219.35 1,500.44 1.99 2,985.88
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.03.04 PRUEBA HIDRAULICA FINAL A ZANJA TAPADA DE TUBERIA PVC/ISO 4435 DN=200MM m 18,219.35 1,015.78 1.99 2,021.40
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.04.01 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=1.50M und 281.00 29.00 118.11 3,425.19
TAMAÑA
BZ - 406-B h =1.40 1.00
BZ - 407 h =1.40 1.00
BZ - 408 h =1.30 1.00
BZ - 409 h =1.30 1.00
BZ - 410 h =1.20 1.00
BZ - 411 h =1.20 1.00
BZ - 412-A h =1.50 1.00
BZ - 412 h =1.50 1.00
BZ - 413 h =1.30 1.00
BZ - 414 h =1.50 1.00
BZ - 415 h =1.30 1.00
BZ - 416 h =1.50 1.00
BZ - 417 h =1.50 1.00
BZ - 418 h =1.40 1.00
BZ - 419 h =1.25 1.00
BZ - 420 h =1.35 1.00
BZ - 406_19 h =1.20 1.00
BZ - 406_20 h =1.20 1.00
BZ - 406_21 h =1.20 1.00
BZ - 406_22 h =1.20 1.00
BZ - 406_23 h =1.21 1.00
BZ - 406_25 h =1.20 1.00
BZ - 406_26 h =1.20 1.00
BZ - 406_27 h =1.20 1.00
BZ - 406_28 h =1.20 1.00
12.01.04.02 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=2.00M und 108.00 3.00 128.83 386.49
12.01.04.03 EXCAVACION BUZON, Dexc.=2.01M, HASTA H=2.50M und 59.00 4.00 141.74 566.96
TAMAÑA
BZ - 406_24 h =2.20 1.00
12.01.04.04 EXCAVACION BUZON, Dexc.=2.50M, HASTA H=3.00M und 25.00 4.00 157.48 629.92
12.01.04.05 EXCAVACION BUZON, Dexc.=1.90M, HASTA H=3.50M und 20.00 8.00 3,543.40 28,347.20
12.01.04.06 EXCAVACION BUZON, Dexc.=1.90M, HASTA H=4.00M und 14.00 3.00 2,833.60 8,500.80
12.01.04.07 EXCAVACION BUZON, Dexc.=1.90M, HASTA H=4.50M und 11.00 5.00 2,598.42 12,992.10
TAMAÑA COGRI
BZ - 406-B h =1.40 1.00
BZ - 407 h =1.40 1.00
BZ - 408 h =1.30 1.00
BZ - 409 h =1.30 1.00
BZ - 410 h =1.20 1.00
BZ - 411 h =1.20 1.00
BZ - 412-A h =1.50 1.00
BZ - 412 h =1.50 1.00
BZ - 413 h =1.30 1.00
BZ - 414 h =1.50 1.00
BZ - 415 h =1.30 1.00
BZ - 416 h =1.50 1.00
BZ - 417 h =1.50 1.00
BZ - 418 h =1.40 1.00
BZ - 419 h =1.25 1.00
BZ - 420 h =1.35 1.00
BZ - 406_19 h =1.20 1.00
BZ - 406_20 h =1.20 1.00
BZ - 406_21 h =1.20 1.00
BZ - 406_22 h =1.20 1.00
BZ - 406_23 h =1.21 1.00
BZ - 406_25 h =1.20 1.00
BZ - 406_26 h =1.20 1.00
BZ - 406_27 h =1.20 1.00
BZ - 406_28 h =1.20 1.00
12.01.05.02 CONSTRUCCION DE BUZONES DN=1.20M, H=1.51 @2.00m und 108.00 3.00 1,669.55 5,008.65
12.01.05.03 CONSTRUCCION DE BUZONES DN=1.20M, H=2.01 @2.50m und 59.00 4.00 1,646.94 6,587.76
TAMAÑA
BZ - 406_24 h =2.20 1.00
12.01.05.04 CONSTRUCCION DE BUZONES DN=1.20M, H=2.51 @3.00m und 25.00 5.00 1,951.04 9,755.20
ESCOBAYA - SAN FRANCISCO
BZ - 840 h =2.53 1.00
BZ - 841 h =2.79 1.00
BZ - 848 h =2.65 1.00
BZ - 842 h =3.28 1.00
BZ A -12 h =2.88 1.00
12.01.05.05 CONSTRUCCION DE BUZONES DN=1.50M, H=3.01 @3.50m und 20.00 8.00 3,296.84 26,374.72
12.01.05.06 CONSTRUCCION DE BUZONES DN=1.50M, H=3.51 @4.00m und 14.00 3.00 3,526.15 10,578.45
12.01.05.07 CONSTRUCCION DE BUZONES DN=1.50M, H=4.01 @4.50m und 11.00 5.00 3,683.83 18,419.15
12.01.05.16 ANCLAJE O DADOS DE CONCRETO F´c=140KG/CM2 EN BUZONES und 1,104.00 #REF! 29.05 #REF!
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20 11.89
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20 14.39
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20 18.52
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20 23.92
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20 11.76
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40 8.57
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40 21.43
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20 11.08
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20 23.06
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20 13.74
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20 20.47
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20 10.29
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20 27.08
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20 16.70
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20 70.08
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20 26.16
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20 11.14
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20 43.67
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20 31.69
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20 37.29
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40 36.96
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 65.61
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 32.93
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.73
12.02.03.04 EXCAVACION C/EQUIPO T.NORMAL H=2.00M, P/TUB DN 200MM DESAGUE m 3,277.18 59.95 18.01 1,079.70
TAMAÑA
BZ_D @ BZ_E 24.89
BZ_C @ BZ_D 9.52
BZ_B @ BZ_C 25.54
12.02.03.07 EXCAVACION C/EQUIPO T.NORMAL H=2.50M, P/TUB DN 200MM DESAGUE m 1,795.40 0.00 19.21 0.00
12.02.03.10 EXCAVACION C/EQUIPO T.NORMAL H=3.00M, P/TUB DN 200MM DESAGUE m 1,085.93 237.23 20.60 4,886.94
TAMAÑA
BZ_G @ BZ_H 34.73
BZ_F @ BZ_G 26.69
BZ_E @ BZ_F 24.89
CHICHILIN
BZCHI 70 @ BZCHI 71 h=2.70, h=2.00 19.35
BZCHI 71 @ BZCHI 72 h=2.00, h=2.70 40.64
BZCHI 72 @ BZCHI 73 h=2.70, h=2.70 30.88
BZCHI 73 @ BZCHI 74 h=2.70, h=1.20 60.05
12.02.03.13 EXCAVACION C/EQUIPO T.NORMAL H=3.50M, P/TUB DN 200MM DESAGUE m 1,085.93 89.78 21.40 1,921.29
CHICHILIN
BZCHI 68 @ BZCHI 69 h=1.20, h=3.40 28.07
BZCHI 69 @ BZCHI 70 h=3.40, h=2.70 17.89
BZCHI 64A @ BZCHI 64 h=1.20, h=3.10 27.10
BZCHI 64 @ BZCHI 65 h=3.10, h=1.20 16.72
12.02.03.35 REFINE Y NIVELACION ZANJA T.NORMAL, P/DESAGUE m 20,074.25 1,655.76 2.79 4,619.57
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20 11.89
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20 14.39
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20 18.52
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20 23.92
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20 11.76
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40 8.57
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40 21.43
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20 11.08
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20 23.06
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20 13.74
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20 20.47
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20 10.29
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20 27.08
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20 16.70
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20 70.08
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20 26.16
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20 11.14
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20 43.67
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20 31.69
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20 37.29
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40 36.96
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 65.61
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 32.93
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.73
12.02.03.38 CAMA DE ARENA EN ZANJA H=0.10M, A=0.60M m 28,677.50 1,655.76 7.09 11,739.34
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20 11.89
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20 14.39
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20 18.52
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20 23.92
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20 11.76
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40 8.57
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40 21.43
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20 11.08
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20 23.06
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20 13.74
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20 20.47
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20 10.29
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20 27.08
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20 16.70
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20 70.08
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20 26.16
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20 11.14
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20 43.67
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20 31.69
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20 37.29
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40 36.96
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 65.61
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 32.93
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.73
12.02.03.39 RELLENO PROTECTOR C/MAT PROPIO P/TUB 200MM, H=0.30M m 28,677.50 1,655.76 5.35 8,858.32
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
BZ_D @ BZ_E 24.89
BZ_C @ BZ_D 9.52
BZ_B @ BZ_C 25.54
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20 11.89
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20 14.39
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20 18.52
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20 23.92
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20 11.76
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40 8.57
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40 21.43
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20 11.08
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20 23.06
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20 13.74
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20 20.47
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20 10.29
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20 27.08
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20 16.70
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20 70.08
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20 26.16
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20 11.14
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20 43.67
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20 31.69
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20 37.29
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40 36.96
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 65.61
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 32.93
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.73
12.02.03.40 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=1.50M m 18,342.37 1,268.80 3.81 4,834.13
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20 11.89
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20 14.39
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20 18.52
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20 23.92
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20 11.76
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40 8.57
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40 21.43
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20 11.08
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20 23.06
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20 13.74
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20 20.47
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20 10.29
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20 27.08
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20 16.70
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20 70.08
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20 26.16
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20 11.14
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20 43.67
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20 31.69
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20 37.29
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40 36.96
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 65.61
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 32.93
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.73
12.02.03.41 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=2.00M m 4,681.68 59.95 6.25 374.69
TAMAÑA
BZ_D @ BZ_E 24.89
BZ_C @ BZ_D 9.52
BZ_B @ BZ_C 25.54
12.02.03.42 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=2.50M m 2,564.85 0.00 7.25 0.00
12.02.03.43 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=3.00M m 1,551.33 237.23 7.25 1,719.92
TAMAÑA
BZ_G @ BZ_H 34.73
BZ_F @ BZ_G 26.69
BZ_E @ BZ_F 24.89
CHICHILIN
BZCHI 70 @ BZCHI 71 h=2.70, h=2.00 19.35
BZCHI 71 @ BZCHI 72 h=2.00, h=2.70 40.64
BZCHI 72 @ BZCHI 73 h=2.70, h=2.70 30.88
BZCHI 73 @ BZCHI 74 h=2.70, h=1.20 60.05
CHICHILIN
BZCHI 68 @ BZCHI 69 h=1.20, h=3.40 28.07
BZCHI 69 @ BZCHI 70 h=3.40, h=2.70 17.89
BZCHI 64A @ BZCHI 64 h=1.20, h=3.10 27.10
BZCHI 64 @ BZCHI 65 h=3.10, h=1.20 16.72
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20 11.89
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20 14.39
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20 18.52
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20 23.92
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20 11.76
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40 8.57
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40 21.43
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20 11.08
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20 23.06
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20 13.74
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20 20.47
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20 10.29
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20 27.08
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20 16.70
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20 70.08
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20 26.16
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20 11.14
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20 43.67
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20 31.69
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20 37.29
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40 36.96
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 65.61
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 32.93
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.73
12.02.04.02 INSTALACION DE TUBERIA ISO 4435 S-25 DN=200MM m 28,677.50 1,655.76 4.28 7,086.65
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20 11.89
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20 14.39
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20 18.52
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20 23.92
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20 11.76
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40 8.57
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40 21.43
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20 11.08
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20 23.06
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20 13.74
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20 20.47
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20 10.29
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20 27.08
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20 16.70
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20 70.08
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20 26.16
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20 11.14
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20 43.67
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20 31.69
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20 37.29
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40 36.96
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 65.61
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 32.93
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.73
12.02.04.03 PRUEBA HIDRAULICA PARCIAL A ZANJA DESCUBIERTA DE TUBERIA PVC/ISO 4435 m 28,677.50 1,655.76 1.99 3,294.96
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20 11.89
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20 14.39
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20 18.52
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20 23.92
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20 11.76
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40 8.57
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40 21.43
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20 11.08
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20 23.06
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20 13.74
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20 20.47
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20 10.29
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20 27.08
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20 16.70
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20 70.08
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20 26.16
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20 11.14
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20 43.67
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20 31.69
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20 37.29
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40 36.96
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 65.61
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 32.93
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.73
12.02.04.04 PRUEBA HIDRAULICA FINAL A ZANJA TAPADA DE TUBERIA PVC/ISO 4435 DN=200MM m 28,677.50 1,655.76 1.99 3,294.96
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20 11.89
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20 14.39
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20 18.52
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20 23.92
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20 11.76
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40 8.57
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40 21.43
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20 11.08
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20 23.06
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20 13.74
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20 20.47
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20 10.29
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20 27.08
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20 16.70
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20 70.08
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20 26.16
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20 11.14
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20 43.67
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20 31.69
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20 37.29
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40 36.96
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 65.61
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 32.93
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.73
TAMAÑA
BZ-459 h=1.38 1.00
BZ-458 h=1.25 1.00
BZ-457 h=1.50 1.00
BZ-456 h=1.40 1.00
BZ-H h=1.40 1.00
BZ-E h=1.40 1.00
BZ-B h=1.20 1.00
BZ-A h=1.20 1.00
COGRI
BZ-24 h=1.20 1.00
BZ-25 h=1.20 1.00
BZ-27 h=1.30 1.00
BZ-33 h=1.30 1.00
BZ-33A h=1.20 1.00
BZ-34 h=1.40 1.00
BZ-129 h=1.50 1.00
BZ-28 h=1.4 1.00
BZ-35A h=1.5 1.00
BZ-36 h=1.4 1.00
BZ-127 h=1.4 1.00
BZ-128 h=1.4 1.00
BZ-38 h=1.5 1.00
BZ-39 h=1.5 1.00
BZ-40 h=1.4 1.00
BZ-41 h=1.3 1.00
BZ-36 h=1.30 1.00
BZ-42 h=1.2 1.00
BZ-32 h=1.2 1.00
BZ-31 h=1.3 1.00
BZ-45 h=1.2 1.00
BZ-44 h=1.4 1.00
BZ-46 h=1.3 1.00
BZ-47 h=1.2 1.00
BZ-48 h=1.2 1.00
BZ-125 h=1.2 1.00
BZ-49 h=1.4 1.00
BZ-49A h=1.4 1.00
BZ-50 h=1.4 1.00
BZ-51 h=1.40 1.00
BZ-52 h=1.50 1.00
BZ-53 h=1.20 1.00
BZ-61 h=1.30 1.00
BZ-133 h=1.30 1.00
BZ-62 h=1.30 1.00
BZ-63 h=1.50 1.00
BZ-65 h=1.40 1.00
BZ-66A h=1.40 1.00
BZ-66 h=1.30 1.00
BZ-68A h=1.40 1.00
BZ-55 h=1.2 1.00
BZ-123 h=1.20 1.00
BZ-558 h=1.20 1.00
BZ-558A h=1.2 1.00
BZ-558B h=1.2 1.00
BZ-558C h=1.20 1.00
CHICHILIN
BZCHI 62A h=1.40 1.00
BZCHI 62 h=1.40 1.00
BZCHI 63B h=1.20 1.00
BZCHI 63A h=1.20 1.00
BZCHI 63 h=1.20 1.00
BZCHI 64B h=1.20 1.00
BZCHI 64A h=1.20 1.00
BZCHI 65A h=1.20 1.00
BZCHI 65 h=1.20 1.00
BZCHI 66 h=1.20 1.00
BZCHI 67 h=1.20 1.00
BZCHI 68 h=1.20 1.00
BZCHI 74 h=1.20 1.00
BZCHI 75 h=1.20 1.00
BZCHI 76 h=1.20 1.00
BZCHI 77 h=1.40 1.00
BZCHI 78 h=1.40 1.00
BZCHI 79 h=1.40 1.00
BZCHI 80 h=1.40 1.00
BZCHI 81 h=1.40 1.00
BZCHI 82 h=1.40 1.00
BZCHI 83 h=1.40 1.00
BZCHI 84 h=1.40 1.00
BZCHI 85 h=1.40 1.00
BZCHI 86 h=1.40 1.00
BZCHI 87 h=1.40 1.00
BZCHI 88 h=1.40 1.00
BZCHI 89 h=1.40 1.00
BZCHI 90 h=1.40 1.00
BZCHI 91 h=1.40 1.00
BZCHI 92 h=1.40 1.00
BZCHI 93 h=1.40 1.00
BZ 974 h=1.40 1.00
12.02.05.02 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=2.00M und 65.00 7.00 128.83 901.81
TAMAÑA
BZ_D h=1.65 1.00
BZ_C h=1.65 1.00
COGRI
BZ-35 h=1.60 1.00
BZ-134 h=1.60 1.00
BZ-67 h=1.60 1.00
BZ-68 h=1.80 1.00
CHICHILIN
BZCHI 71 h=2.00 1.00
12.02.05.03 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=2.50M und 31.00 1.00 141.74 141.74
COGRI
BZ - 30 H 2.43 1.00
12.02.05.04 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=3.00M und 30.00 6.00 157.48 944.88
TAMAÑA
BZ_G h=2.80 1.00
BZ_F h=2.65 1.00
COGRI
BZ-37 h=2.95 1.00
CHICHILIN
BZCHI 70 h=2.70 1.00
BZCHI 72 h=2.70 1.00
BZCHI 73 h=2.70 1.00
12.02.05.05 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=3.50M und 30.00 2.00 177.17 354.34
COGRI
BZ-69 h=3.20 1.00
CHICHILIN
BZCHI 69 h=3.40 1.00
TAMAÑA
BZ-459 h=1.38 1.00
BZ-458 h=1.25 1.00
BZ-457 h=1.50 1.00
BZ-456 h=1.40 1.00
BZ-H h=1.40 1.00
BZ-E h=1.40 1.00
BZ-B h=1.20 1.00
BZ-A h=1.20 1.00
COGRI
BZ-24 h=1.20 1.00
BZ-25 h=1.20 1.00
BZ-27 h=1.30 1.00
BZ-33 h=1.30 1.00
BZ-33A h=1.20 1.00
BZ-34 h=1.40 1.00
BZ-129 h=1.50 1.00
BZ-28 h=1.4 1.00
BZ-35A h=1.5 1.00
BZ-36 h=1.4 1.00
BZ-127 h=1.4 1.00
BZ-128 h=1.4 1.00
BZ-38 h=1.5 1.00
BZ-39 h=1.5 1.00
BZ-40 h=1.4 1.00
BZ-41 h=1.3 1.00
BZ-36 h=1.30 1.00
BZ-42 h=1.2 1.00
BZ-32 h=1.2 1.00
BZ-31 h=1.3 1.00
BZ-45 h=1.2 1.00
BZ-44 h=1.4 1.00
BZ-46 h=1.3 1.00
BZ-47 h=1.2 1.00
BZ-48 h=1.2 1.00
BZ-125 h=1.2 1.00
BZ-49 h=1.4 1.00
BZ-49A h=1.4 1.00
BZ-50 h=1.4 1.00
BZ-51 h=1.40 1.00
BZ-52 h=1.50 1.00
BZ-53 h=1.20 1.00
BZ-61 h=1.30 1.00
BZ-133 h=1.30 1.00
BZ-62 h=1.30 1.00
BZ-63 h=1.50 1.00
BZ-65 h=1.40 1.00
BZ-66A h=1.40 1.00
BZ-66 h=1.30 1.00
BZ-68A h=1.40 1.00
BZ-55 h=1.2 1.00
BZ-123 h=1.20 1.00
BZ-558 h=1.20 1.00
BZ-558A h=1.2 1.00
BZ-558B h=1.2 1.00
BZ-558C h=1.20 1.00
CHICHILIN
BZCHI 62A h=1.40 1.00
BZCHI 62 h=1.40 1.00
BZCHI 63B h=1.20 1.00
BZCHI 63A h=1.20 1.00
BZCHI 63 h=1.20 1.00
BZCHI 64B h=1.20 1.00
BZCHI 64A h=1.20 1.00
BZCHI 65A h=1.20 1.00
BZCHI 65 h=1.20 1.00
BZCHI 66 h=1.20 1.00
BZCHI 67 h=1.20 1.00
BZCHI 68 h=1.20 1.00
BZCHI 74 h=1.20 1.00
BZCHI 75 h=1.20 1.00
BZCHI 76 h=1.20 1.00
BZCHI 77 h=1.40 1.00
BZCHI 78 h=1.40 1.00
BZCHI 79 h=1.40 1.00
BZCHI 80 h=1.40 1.00
BZCHI 81 h=1.40 1.00
BZCHI 82 h=1.40 1.00
BZCHI 83 h=1.40 1.00
BZCHI 84 h=1.40 1.00
BZCHI 85 h=1.40 1.00
BZCHI 86 h=1.40 1.00
BZCHI 87 h=1.40 1.00
BZCHI 88 h=1.40 1.00
BZCHI 89 h=1.40 1.00
BZCHI 90 h=1.40 1.00
BZCHI 91 h=1.40 1.00
BZCHI 92 h=1.40 1.00
BZCHI 93 h=1.40 1.00
BZ 974 h=1.40 1.00
12.02.06.02 CONSTRUCCION DE BUZONES DN=1.20M, H=1.51 @2.00m Und 65.00 7.00 1,669.55 11,686.85
TAMAÑA
BZ_D h=1.65 1.00
BZ_C h=1.65 1.00
COGRI
BZ-35 h=1.60 1.00
BZ-134 h=1.60 1.00
BZ-67 h=1.60 1.00
BZ-68 h=1.80 1.00
CHICHILIN
BZCHI 71 h=2.00 1.00
12.02.06.03 CONSTRUCCION DE BUZONES DN=1.20M, H=2.01 @2.50m Und 30.00 3.00 1,646.94 4,940.82
COGRI
BZ - 30 H 2.43 1.00
CHICHILIN
BZCHI 50 h=2.30 1.00
BZCHI 98 h=2.40 1.00
12.02.06.04 CONSTRUCCION DE BUZONES DN=1.20M, H=2.51 @3.00m Und 30.00 6.00 1,951.04 11,706.24
TAMAÑA
BZ_G h=2.80 1.00
BZ_F h=2.65 1.00
COGRI
BZ-37 h=2.95 1.00
CHICHILIN
BZCHI 70 h=2.70 1.00
BZCHI 72 h=2.70 1.00
BZCHI 73 h=2.70 1.00
12.02.06.05 CONSTRUCCION DE BUZONES DN=1.20M, H=3.01 @3.50m Und 30.00 2.00 3,296.84 6,593.68
COGRI
BZ-69 h=3.20 1.00
CHICHILIN
BZCHI 69 h=3.40 1.00
PPTO - CHICHILIN (SISTEMA DE ALCANTARILLADO) S/. 162,401.74
METRADO COSTO
ITEM PARTIDA UNIDAD EXPEDIENTE METRADO META UNITARIO PPTO
12 SISTEMA DE ALCANTARILLADO
12.01 RED DE DESAGUE - COLECTORES PRIMARIOS
12.02.02 MOVIMIENTO DE TIERRAS
12.01.02.01 EXCAVACION C/EQUIPO T.NORMAL H=1.50M, P/TUB DN 200MM DESAGUE m 6,177.12 271.63 14.12 3,835.42
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.02.04 EXCAVACION C/EQUIPO T.NORMAL H=2.00M, P/TUB DN 200MM DESAGUE m 4,770.76 0.00 18.01 0.00
12.01.02.04 EXCAVACION C/EQUIPO T.NORMAL H=2.50M, P/TUB DN 200MM DESAGUE 67.04 19.21 1,287.84
TAMAÑA
12.01.02.10 EXCAVACION C/EQUIPO T.NORMAL H=3.00M, P/TUB DN 200MM DESAGUE m 1,507.77 13.70 20.60 282.22
TAMAÑA
BZ 406_12 @ BZ 406_13 13.70
ESCOBAYA - SAN FRANCISCO
BZ 840 @ BZ 841
BZ 847 @ BZ 848
BZ 848 @ BZ 849
BZ A8 @ BZ A9
BZ A9 @ BZ A10
BZ A10 @ BZ A11
BZ A11 @ BZ A12
12.02.03.13 EXCAVACION C/EQUIPO T.NORMAL H=3.50M, P/TUB DN 200MM DESAGUE m 300.53 0.00 21.40 0.00
12.02.03.16 EXCAVACION C/EQUIPO T.NORMAL H=4.00M, P/TUB DN 200MM DESAGUE m 173.12 132.29 21.80 2,883.92
TAMAÑA
BZ 406_5 @ BZ 406_6 51.58
BZ 406_6 @ BZ 406_7 41.12
BZ 406_7 @ BZ 406_9 39.59
12.01.02.55 REFINE Y NIVELACION ZANJA T.NORMAL, P/DESAGUE m 17,490.58 484.66 2.79 1,352.20
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.02.58 CAMA DE ARENA EN ZANJA H=0.10M, A=0.60M m 18,219.35 484.66 7.09 3,436.24
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.02.59 RELLENO PROTECTOR C/MAT PROPIO P/TUB 200MM, H=0.30M m 18,219.35 484.66 5.35 2,592.93
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.02.60 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=1.50M m 6,434.50 271.63 3.81 1,034.91
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.02.61 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=2.00M m 4,969.54 0.00 6.25 0.00
12.01.02.62 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=2.50M m 4,969.54 67.04 7.25 486.04
TAMAÑA
BZ 406_25 @ BZ 406_24 25.77
BZ 406_24 @ BZ 406_23 41.27
12.01.02.63 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=3.00M m 1,570.59 13.70 7.25 99.33
TAMAÑA
BZ 406_12 @ BZ 406_13 13.70
12.01.02.64 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=3.50M m 1,570.59 0.00 5.84 0.00
12.01.02.65 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=4.00M m 463.77 132.29 7.80 1,031.86
TAMAÑA
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.03.02 INSTALACION DE TUBERIA ISO 4435 S-25 DN=200MM m 18,219.35 484.66 4.28 2,074.34
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.03.03 PRUEBA HIDRAULICA PARCIAL A ZANJA DESCUBIERTA DE TUBERIA PVC/ISO 4435 m 18,219.35 484.66 1.99 964.47
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.03.04 PRUEBA HIDRAULICA FINAL A ZANJA TAPADA DE TUBERIA PVC/ISO 4435 DN=200MM m 18,219.35 484.66 1.99 964.47
TAMAÑA
BZ 406 @ BZ 406_4 25.25
BZ 406_29 @ BZ 406_28 43.40
BZ 406_28 @ BZ 406_27 19.35
BZ 406_27 @ BZ 406_26 25.80
BZ 406_26 @ BZ 406_25 21.85
BZ 406_23 @ BZ 406_22 33.18
BZ 406_22 @ BZ 406_21 11.95
BZ 406_21 @ BZ 406_20 30.09
BZ 406_20 @ BZ 406_19 60.76
12.01.04.01 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=1.50M und 281.00 25.00 118.11 2,952.75
TAMAÑA
BZ - 406-B h =1.40 1.00
BZ - 407 h =1.40 1.00
BZ - 408 h =1.30 1.00
BZ - 409 h =1.30 1.00
BZ - 410 h =1.20 1.00
BZ - 411 h =1.20 1.00
BZ - 412-A h =1.50 1.00
BZ - 412 h =1.50 1.00
BZ - 413 h =1.30 1.00
BZ - 414 h =1.50 1.00
BZ - 415 h =1.30 1.00
BZ - 416 h =1.50 1.00
BZ - 417 h =1.50 1.00
BZ - 418 h =1.40 1.00
BZ - 419 h =1.25 1.00
BZ - 420 h =1.35 1.00
BZ - 406_19 h =1.20 1.00
BZ - 406_20 h =1.20 1.00
BZ - 406_21 h =1.20 1.00
BZ - 406_22 h =1.20 1.00
BZ - 406_23 h =1.21 1.00
BZ - 406_25 h =1.20 1.00
BZ - 406_26 h =1.20 1.00
BZ - 406_27 h =1.20 1.00
BZ - 406_28 h =1.20 1.00
12.01.04.02 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=2.00M und 108.00 0.00 128.83 0.00
12.01.04.03 EXCAVACION BUZON, Dexc.=2.01M, HASTA H=2.50M und 59.00 1.00 141.74 141.74
TAMAÑA
BZ - 406_24 h =2.20 1.00
12.01.04.04 EXCAVACION BUZON, Dexc.=2.50M, HASTA H=3.00M und 25.00 0.00 157.48 0.00
12.01.04.05 EXCAVACION BUZON, Dexc.=1.90M, HASTA H=3.50M und 20.00 0.00 3,543.40 0.00
12.01.04.06 EXCAVACION BUZON, Dexc.=1.90M, HASTA H=4.00M und 14.00 0.00 2,833.60 0.00
12.01.04.07 EXCAVACION BUZON, Dexc.=1.90M, HASTA H=4.50M und 11.00 0.00 2,598.42 0.00
TAMAÑA COGRI
BZ - 406-B h =1.40 1.00
BZ - 407 h =1.40 1.00
BZ - 408 h =1.30 1.00
BZ - 409 h =1.30 1.00
BZ - 410 h =1.20 1.00
BZ - 411 h =1.20 1.00
BZ - 412-A h =1.50 1.00
BZ - 412 h =1.50 1.00
BZ - 413 h =1.30 1.00
BZ - 414 h =1.50 1.00
BZ - 415 h =1.30 1.00
BZ - 416 h =1.50 1.00
BZ - 417 h =1.50 1.00
BZ - 418 h =1.40 1.00
BZ - 419 h =1.25 1.00
BZ - 420 h =1.35 1.00
BZ - 406_19 h =1.20 1.00
BZ - 406_20 h =1.20 1.00
BZ - 406_21 h =1.20 1.00
BZ - 406_22 h =1.20 1.00
BZ - 406_23 h =1.21 1.00
BZ - 406_25 h =1.20 1.00
BZ - 406_26 h =1.20 1.00
BZ - 406_27 h =1.20 1.00
BZ - 406_28 h =1.20 1.00
12.01.05.02 CONSTRUCCION DE BUZONES DN=1.20M, H=1.51 @2.00m und 108.00 0.00 1,669.55 0.00
TAMAÑA-COGRI
12.01.05.03 CONSTRUCCION DE BUZONES DN=1.20M, H=2.01 @2.50m und 59.00 1.00 1,646.94 1,646.94
TAMAÑA
BZ - 406_24 h =2.20 1.00
12.01.05.04 CONSTRUCCION DE BUZONES DN=1.20M, H=2.51 @3.00m und 25.00 0.00 1,951.04 0.00
12.01.05.05 CONSTRUCCION DE BUZONES DN=1.50M, H=3.01 @3.50m und 20.00 0.00 3,296.84 0.00
12.01.05.06 CONSTRUCCION DE BUZONES DN=1.50M, H=3.51 @4.00m und 14.00 0.00 3,526.15 0.00
12.01.05.07 CONSTRUCCION DE BUZONES DN=1.50M, H=4.01 @4.50m und 11.00 0.00 3,683.83 0.00
12.01.05.16 ANCLAJE O DADOS DE CONCRETO F´c=140KG/CM2 EN BUZONES und 1,104.00 29.05 0.00
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.03.04 EXCAVACION C/EQUIPO T.NORMAL H=2.00M, P/TUB DN 200MM DESAGUE m 3,277.18 59.95 18.01 1,079.70
TAMAÑA
BZ_D @ BZ_E 24.89
BZ_C @ BZ_D 9.52
BZ_B @ BZ_C 25.54
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20 h=1.65
BZCHI 51 @ BZCHI 52 h=1.60, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=2.00
BZCHI 76 @ BZCHI 77 h=2.00, h=1.40
12.02.03.07 EXCAVACION C/EQUIPO T.NORMAL H=2.50M, P/TUB DN 200MM DESAGUE m 1,795.40 0.00 19.21 0.00
CHICHILIN
12.02.03.10 EXCAVACION C/EQUIPO T.NORMAL H=3.00M, P/TUB DN 200MM DESAGUE m 1,085.93 86.31 20.60 1,777.99
TAMAÑA
BZ_G @ BZ_H 34.73
BZ_F @ BZ_G 26.69
BZ_E @ BZ_F 24.89
CHICHILIN
12.02.03.13 EXCAVACION C/EQUIPO T.NORMAL H=3.50M, P/TUB DN 200MM DESAGUE m 1,085.93 0.00 21.40 0.00
CHICHILIN
BZCHI 68 @ BZCHI 69 h=1.20, h=3.40
BZCHI 69 @ BZCHI 70 h=3.40, h=2.70
BZCHI 64A @ BZCHI 64 h=1.20, h=3.10
BZCHI 64 @ BZCHI 65 h=3.10, h=1.20
12.02.03.35 REFINE Y NIVELACION ZANJA T.NORMAL, P/DESAGUE m 20,074.25 276.54 2.79 771.55
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.03.38 CAMA DE ARENA EN ZANJA H=0.10M, A=0.60M m 28,677.50 276.54 7.09 1,960.67
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.03.39 RELLENO PROTECTOR C/MAT PROPIO P/TUB 200MM, H=0.30M m 28,677.50 276.54 5.35 1,479.49
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.03.40 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=1.50M m 18,342.37 130.28 3.81 496.37
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.03.41 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=2.00M m 4,681.68 59.95 6.25 374.69
TAMAÑA
BZ_D @ BZ_E 24.89
BZ_C @ BZ_D 9.52
BZ_B @ BZ_C 25.54
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20 h=1.65
CHICHILIN
12.02.03.42 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=2.50M m 2,564.85 0.00 7.25 0.00
12.02.03.43 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=3.00M m 1,551.33 86.31 7.25 625.75
TAMAÑA
BZ_G @ BZ_H 34.73
BZ_F @ BZ_G 26.69
BZ_E @ BZ_F 24.89
COLOHUACHE
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 70 @ BZCHI 71 h=2.70, h=2.00
BZCHI 71 @ BZCHI 72 h=2.00, h=2.70
BZCHI 72 @ BZCHI 73 h=2.70, h=2.70
BZCHI 73 @ BZCHI 74 h=2.70, h=1.20
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.04.02 INSTALACION DE TUBERIA ISO 4435 S-25 DN=200MM m 28,677.50 276.54 4.28 1,183.59
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.04.03 PRUEBA HIDRAULICA PARCIAL A ZANJA DESCUBIERTA DE TUBERIA PVC/ISO 4435 m 28,677.50 276.54 1.99 550.31
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.04.04 PRUEBA HIDRAULICA FINAL A ZANJA TAPADA DE TUBERIA PVC/ISO 4435 DN=200MM m 28,677.50 276.54 1.99 550.31
TAMAÑA
BZ 459 @ BZ 458 25.28
BZ 458 @ BZ 457 14.81
BZ 457 @ BZ 456 25.34
BZ H @ BZ 456 18.23
BZ_A @ BZ_B 46.62
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
TAMAÑA
BZ-459 h=1.38 1.00
BZ-458 h=1.25 1.00
BZ-457 h=1.50 1.00
BZ-456 h=1.40 1.00
BZ-H h=1.40 1.00
BZ-E h=1.40 1.00
BZ-B h=1.20 1.00
BZ-A h=1.20 1.00
CHICHILIN
BZCHI 62A h=1.40
BZCHI 62 h=1.40
BZCHI 63B h=1.20
BZCHI 63A h=1.20
BZCHI 63 h=1.20
BZCHI 64B h=1.20
BZCHI 64A h=1.20
BZCHI 65A h=1.20
BZCHI 65 h=1.20
BZCHI 66 h=1.20
BZCHI 67 h=1.20
BZCHI 68 h=1.20
BZCHI 74 h=1.20
BZCHI 75 h=1.20
BZCHI 76 h=1.20
BZCHI 77 h=1.40
BZCHI 78 h=1.40
BZCHI 79 h=1.40
BZCHI 80 h=1.40
BZCHI 81 h=1.40
BZCHI 82 h=1.40
BZCHI 83 h=1.40
BZCHI 84 h=1.40
BZCHI 85 h=1.40
BZCHI 86 h=1.40
BZCHI 87 h=1.40
BZCHI 88 h=1.40
BZCHI 89 h=1.40
BZCHI 90 h=1.40
BZCHI 91 h=1.40
BZCHI 92 h=1.40
BZCHI 93 h=1.40
BZ 974 h=1.40
12.02.05.02 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=2.00M und 65.00 2.00 128.83 257.66
TAMAÑA
BZ_D h=1.65 1.00
BZ_C h=1.65 1.00
CHICHILIN
BZCHI 71 h=2.00
12.02.05.03 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=2.50M und 31.00 0.00 141.74 0.00
COGRI
12.02.05.04 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=3.00M und 30.00 2.00 157.48 314.96
TAMAÑA
BZ_G h=2.80 1.00
BZ_F h=2.65 1.00
CHICHILIN
BZCHI 70 h=2.70
BZCHI 72 h=2.70
BZCHI 73 h=2.70
12.02.05.05 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=3.50M und 30.00 0.00 177.17 0.00
COGRI
CHICHILIN
BZCHI 69 h=3.40
TAMAÑA
BZ-459 h=1.38 1.00
BZ-458 h=1.25 1.00
BZ-457 h=1.50 1.00
BZ-456 h=1.40 1.00
BZ-H h=1.40 1.00
BZ-E h=1.40 1.00
BZ-B h=1.20 1.00
BZ-A h=1.20 1.00
CHICHILIN
BZCHI 62A h=1.40
BZCHI 62 h=1.40
BZCHI 63B h=1.20
BZCHI 63A h=1.20
BZCHI 63 h=1.20
BZCHI 64B h=1.20
BZCHI 64A h=1.20
BZCHI 65A h=1.20
BZCHI 65 h=1.20
BZCHI 66 h=1.20
BZCHI 67 h=1.20
BZCHI 68 h=1.20
BZCHI 74 h=1.20
BZCHI 75 h=1.20
BZCHI 76 h=1.20
BZCHI 77 h=1.40
BZCHI 78 h=1.40
BZCHI 79 h=1.40
BZCHI 80 h=1.40
BZCHI 81 h=1.40
BZCHI 82 h=1.40
BZCHI 83 h=1.40
BZCHI 84 h=1.40
BZCHI 85 h=1.40
BZCHI 86 h=1.40
BZCHI 87 h=1.40
BZCHI 88 h=1.40
BZCHI 89 h=1.40
BZCHI 90 h=1.40
BZCHI 91 h=1.40
BZCHI 92 h=1.40
BZCHI 93 h=1.40
BZ 974 h=1.40
12.02.06.02 CONSTRUCCION DE BUZONES DN=1.20M, H=1.51 @2.00m Und 65.00 2.00 1,669.55 3,339.10
TAMAÑA
BZ_D h=1.65 1.00
BZ_C h=1.65 1.00
CHICHILIN
BZCHI 71 h=2.00
12.02.06.03 CONSTRUCCION DE BUZONES DN=1.20M, H=2.01 @2.50m Und 30.00 0.00 1,646.94 0.00
COGRI
BZ - 30 H 2.43
CHICHILIN
BZCHI 50 h=2.30
BZCHI 98 h=2.40
12.02.06.04 CONSTRUCCION DE BUZONES DN=1.20M, H=2.51 @3.00m Und 30.00 2.00 1,951.04 3,902.08
TAMAÑA
BZ_G h=2.80 1.00
BZ_F h=2.65 1.00
CHICHILIN
BZCHI 70 h=2.70
BZCHI 72 h=2.70
BZCHI 73 h=2.70
12.02.06.05 CONSTRUCCION DE BUZONES DN=1.20M, H=3.01 @3.50m Und 30.00 0.00 3,296.84 0.00
COGRI
BZ-69 h=3.20
CHICHILIN
BZCHI 69 h=3.40
METRADO COSTO
ITEM PARTIDA UNIDAD EXPEDIENTE METRADO META UNITARIO PPTO
12 SISTEMA DE ALCANTARILLADO
12.01 RED DE DESAGUE - COLECTORES PRIMARIOS
12.02.02 MOVIMIENTO DE TIERRAS
12.01.02.01 EXCAVACION C/EQUIPO T.NORMAL H=1.50M, P/TUB DN 200MM DESAGUE m 6,177.12 233.00 14.12 3,289.96
12.01.02.04 EXCAVACION C/EQUIPO T.NORMAL H=2.00M, P/TUB DN 200MM DESAGUE m 4,770.76 18.01 0.00
12.01.02.04 EXCAVACION C/EQUIPO T.NORMAL H=2.50M, P/TUB DN 200MM DESAGUE 13.45 19.21 258.37
12.01.02.10 EXCAVACION C/EQUIPO T.NORMAL H=3.00M, P/TUB DN 200MM DESAGUE m 1,507.77 80.48 20.60 1,657.89
12.02.03.13 EXCAVACION C/EQUIPO T.NORMAL H=3.50M, P/TUB DN 200MM DESAGUE m 300.53 311.82 21.40 6,672.95
12.02.03.16 EXCAVACION C/EQUIPO T.NORMAL H=4.00M, P/TUB DN 200MM DESAGUE m 173.12 21.80 0.00
12.02.03.19 EXCAVACION C/EQUIPO T.NORMAL H=4.50M, P/TUB DN 200MM DESAGUE m 258.20 34.29 22.26 763.30
12.02.03.22 EXCAVACION C/EQUIPO T.NORMAL H=5.00M, P/TUB DN 200MM DESAGUE m 156.33 78.25 24.22 1,895.22
ESCOBAYA - SAN FRANCISCO
BZ _A_15@ BZ _A_16 h=3.44, h=6.64 32.96
BZ _A_16@ BZ _A_17 h=6.64, h=7.47 29.47
BZ _A_17@ BZ _A_18 h=7.47, h=4.25 15.82
12.01.02.55 REFINE Y NIVELACION ZANJA T.NORMAL, P/DESAGUE m 17,490.58 751.29 2.79 2,096.10
12.01.02.58 CAMA DE ARENA EN ZANJA H=0.10M, A=0.60M m 18,219.35 751.29 7.09 5,326.65
12.01.02.59 RELLENO PROTECTOR C/MAT PROPIO P/TUB 200MM, H=0.30M m 18,219.35 751.29 5.35 4,019.40
12.01.02.60 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=1.50M m 6,434.50 233.00 3.81 887.73
12.01.02.61 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=2.00M m 4,969.54 6.25 0.00
12.01.02.62 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=2.50M m 4,969.54 13.45 7.25 97.51
12.01.02.63 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=3.00M m 1,570.59 80.48 7.25 583.48
12.01.02.64 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=3.50M m 1,570.59 311.82 5.84 1,821.03
12.01.02.65 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=4.00M m 463.77 7.80 0.00
ESCOBAYA - SAN FRANCISCO
12.01.02.66 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=4.50M m 403.04 34.29 0.00
ESCOBAYA - SAN FRANCISCO
BZ _A_18@ BZ _A_19 h=4.25, h=3.33 4.84
BZ 776-Q @ BZ 776-52 h=4.24, h =2.83 29.45
12.01.02.67 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=5.00M m 123.78 78.25 8.87 694.08
ESCOBAYA - SAN FRANCISCO
BZ _A_15@ BZ _A_16 h=3.44, h=6.64 32.96
BZ _A_16@ BZ _A_17 h=6.64, h=7.47 29.47
BZ _A_17@ BZ _A_18 h=7.47, h=4.25 15.82
12.01.03.02 INSTALACION DE TUBERIA ISO 4435 S-25 DN=200MM m 18,219.35 751.29 4.28 3,215.52
12.01.03.03 PRUEBA HIDRAULICA PARCIAL A ZANJA DESCUBIERTA DE TUBERIA PVC/ISO 4435 m 18,219.35 751.29 1.99 1,495.07
12.01.03.04 PRUEBA HIDRAULICA FINAL A ZANJA TAPADA DE TUBERIA PVC/ISO 4435 DN=200MM m 18,219.35 751.29 1.99 1,495.07
12.01.04.01 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=1.50M und 281.00 39.00 118.11 4,606.29
12.01.04.02 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=2.00M und 108.00 0.00 128.83 0.00
12.01.04.03 EXCAVACION BUZON, Dexc.=2.01M, HASTA H=2.50M und 59.00 2.00 141.74 283.48
12.01.04.04 EXCAVACION BUZON, Dexc.=2.50M, HASTA H=3.00M und 25.00 4.00 157.48 629.92
12.01.04.05 EXCAVACION BUZON, Dexc.=1.90M, HASTA H=3.50M und 20.00 6.00 177.17 1,063.02
12.01.04.06 EXCAVACION BUZON, Dexc.=1.90M, HASTA H=4.00M und 14.00 4.00 202.40 809.60
ESCOBAYA - SAN FRANCISCO
BZ A-19, h =3.72 1.00
BZ A-13, h=3.66 1.00
BZ A-14, h=3.69 1.00
BZ A-15, h =3.80 1.00
12.01.04.07 EXCAVACION BUZON, Dexc.=1.90M, HASTA H=4.50M und 11.00 4.00 236.22 944.88
12.01.05.02 CONSTRUCCION DE BUZONES DN=1.20M, H=1.51 @2.00m und 108.00 0.00 1,669.55 0.00
12.01.05.03 CONSTRUCCION DE BUZONES DN=1.20M, H=2.01 @2.50m und 59.00 2.00 1,646.94 3,293.88
12.01.05.04 CONSTRUCCION DE BUZONES DN=1.20M, H=2.51 @3.00m und 25.00 4.00 1,951.04 7,804.16
12.01.05.05 CONSTRUCCION DE BUZONES DN=1.50M, H=3.01 @3.50m und 20.00 6.00 3,296.84 19,781.04
ESCOBAYA - SAN FRANCISCO
BZ 842 h=3.28 1.00
BZ 843 h=3.31 1.00
BZ 844 h=3.30 1.00
BZ 845 h=3.37 1.00
BZ 781 h=3.08 1.00
BZ 780 h=3.32 1.00
12.01.05.06 CONSTRUCCION DE BUZONES DN=1.50M, H=3.51 @4.00m und 14.00 4.00 3,526.15 14,104.60
ESCOBAYA - SAN FRANCISCO
BZ A-19, h =3.72 1.00
BZ A-13, h=3.66 1.00
BZ A-14, h=3.69 1.00
BZ A-15, h =3.80 1.00
12.01.05.07 CONSTRUCCION DE BUZONES DN=1.50M, H=4.01 @4.50m und 11.00 4.00 3,683.83 14,735.32
ESCOBAYA - SAN FRANCISCO
BZ A-18, h =4.67 1.00
BZ A-16, h =6.99 1.00
BZ A-17, h =7.83 1.00
BZ 776- Q,h=4.24 1.00
12.01.05.16 ANCLAJE O DADOS DE CONCRETO F´c=140KG/CM2 EN BUZONES und 1,104.00 60.00 29.05 1,743.00
COLOHUACHE
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.03.04 EXCAVACION C/EQUIPO T.NORMAL H=2.00M, P/TUB DN 200MM DESAGUE m 3,277.18 0.00 18.01 0.00
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20 h=1.65
BZCHI 51 @ BZCHI 52 h=1.60, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=2.00
BZCHI 76 @ BZCHI 77 h=2.00, h=1.40
12.02.03.07 EXCAVACION C/EQUIPO T.NORMAL H=2.50M, P/TUB DN 200MM DESAGUE m 1,795.40 0.00 19.21 0.00
CHICHILIN
12.02.03.10 EXCAVACION C/EQUIPO T.NORMAL H=3.00M, P/TUB DN 200MM DESAGUE m 1,085.93 0.00 20.60 0.00
COLOHUACHE
CHICHILIN
BZCHI 70 @ BZCHI 71 h=2.70, h=2.00
BZCHI 71 @ BZCHI 72 h=2.00, h=2.70
BZCHI 72 @ BZCHI 73 h=2.70, h=2.70
BZCHI 73 @ BZCHI 74 h=2.70, h=1.20
12.02.03.13 EXCAVACION C/EQUIPO T.NORMAL H=3.50M, P/TUB DN 200MM DESAGUE m 1,085.93 0.00 21.40 0.00
CHICHILIN
BZCHI 68 @ BZCHI 69 h=1.20, h=3.40
BZCHI 69 @ BZCHI 70 h=3.40, h=2.70
BZCHI 64A @ BZCHI 64 h=1.20, h=3.10
BZCHI 64 @ BZCHI 65 h=3.10, h=1.20
12.02.03.35 REFINE Y NIVELACION ZANJA T.NORMAL, P/DESAGUE m 20,074.25 0.00 2.79 0.00
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.03.38 CAMA DE ARENA EN ZANJA H=0.10M, A=0.60M m 28,677.50 0.00 7.09 0.00
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.03.39 RELLENO PROTECTOR C/MAT PROPIO P/TUB 200MM, H=0.30M m 28,677.50 0.00 5.35 0.00
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.03.40 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=1.50M m 18,342.37 0.00 3.81 0.00
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.03.41 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=2.00M m 4,681.68 0.00 6.25 0.00
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20 h=1.65
CHICHILIN
12.02.03.42 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=2.50M m 2,564.85 0.00 7.25 0.00
12.02.03.43 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=3.00M m 1,551.33 0.00 7.25 0.00
COLOHUACHE
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 70 @ BZCHI 71 h=2.70, h=2.00
BZCHI 71 @ BZCHI 72 h=2.00, h=2.70
BZCHI 72 @ BZCHI 73 h=2.70, h=2.70
BZCHI 73 @ BZCHI 74 h=2.70, h=1.20
CHICHILIN
BZCHI 68 @ BZCHI 69 h=1.20, h=3.40
BZCHI 69 @ BZCHI 70 h=3.40, h=2.70
BZCHI 64A @ BZCHI 64 h=1.20, h=3.10
BZCHI 64 @ BZCHI 65 h=3.10, h=1.20
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.04.02 INSTALACION DE TUBERIA ISO 4435 S-25 DN=200MM m 28,677.50 0.00 4.28 0.00
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.04.03 PRUEBA HIDRAULICA PARCIAL A ZANJA DESCUBIERTA DE TUBERIA PVC/ISO 4435 m 28,677.50 0.00 1.99 0.00
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
12.02.04.04 PRUEBA HIDRAULICA FINAL A ZANJA TAPADA DE TUBERIA PVC/ISO 4435 DN=200MM m 28,677.50 0.00 1.99 0.00
COLOHUACHE
BZ 778 A @ BZ 778 B h=1.20
BZ 778 E @ BZ 778 G h=1.20, H=1.30
BZ 778 G@ BZ 778 H h=1.30, H=1.20
BZ 778 H @ BZ 778 K h=1.20, H=1.20
BZ 778 K@ BZ 778 L h=1.20, H=1.50
BZ 778 L@ BZ 776-23 h=1.50, H=1.20
BZ 778 B@ BZ 778 C h=1.20, h=2.65
BZ 778 C @ BZ 778 D h=2.65 h =1.60
BZ 778D @ BZ 778 D1 h=1.60 h =1.80
BZ 778D1 @ BZ 778 E h=1.80 h =1.20
CHICHILIN
BZCHI 60 @ BZCHI 61C h=1.20, h=1.20
BZCHI 61C@ BZCHI 61B h=1.20, h=1.20
BZCHI 61B @ BZCHI 61A h=1.20, h=1.20
BZCHI 61A @ BZCHI 61 h=1.20, h=1.20
BZCHI 61 @ BZCHI 62B h=1.20, h=1.20
BZCHI 62B @ BZCHI 62A h=1.20, h=1.40
BZCHI 62A @ BZCHI 62 h=1.40, h=1.40
BZCHI 62 @ BZCHI 63B h=1.40, h=1.20
BZCHI 63B @ BZCHI 63A h=1.20, h=1.20
BZCHI 63A @ BZCHI 63 h=1.20, h=1.20
BZCHI 63 @ BZCHI 64B h=1.20, h=1.20
BZCHI 64B @ BZCHI 64A h=1.20, h=1.20
BZCHI 64A @ BZCHI 65A h=1.20, h=1.20
BZCHI 65A @ BZCHI 65 h=1.20, h=1.20
BZCHI 65 @ BZCHI 66 h=1.20, h=1.20
BZCHI 66 @ BZCHI 67 h=1.20, h=1.20
BZCHI 67 @ BZCHI 68 h=1.20, h=1.20
BZCHI 74 @ BZCHI 75 h=1.20, h=1.20
BZCHI 75 @ BZCHI 76 h=1.20, h=1.20
BZCHI 76 @ BZCHI 77 h=1.20, h=1.20
BZCHI 77 @ BZCHI 78 h=1.40, h=1.40
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40
BZCHI 93 @ BZ 974 h=1.40, h=1.40
COGRI
BZ-24 h=1.20
BZ-25 h=1.20
BZ-27 h=1.30
BZ-33 h=1.30
BZ-33A h=1.20
BZ-34 h=1.40
BZ-129 h=1.50
BZ-28 h=1.4
BZ-35A h=1.5
BZ-36 h=1.4
BZ-127 h=1.4
BZ-128 h=1.4
BZ-38 h=1.5
BZ-39 h=1.5
BZ-40 h=1.4
BZ-41 h=1.3
BZ-36 h=1.30
BZ-42 h=1.2
BZ-32 h=1.2
BZ-31 h=1.3
BZ-45 h=1.2
BZ-44 h=1.4
BZ-46 h=1.3
BZ-47 h=1.2
BZ-48 h=1.2
BZ-125 h=1.2
BZ-49 h=1.4
BZ-49A h=1.4
BZ-50 h=1.4
BZ-51 h=1.40
BZ-52 h=1.50
BZ-53 h=1.20
BZ-61 h=1.30
BZ-133 h=1.30
BZ-62 h=1.30
BZ-63 h=1.50
BZ-65 h=1.40
BZ-66A h=1.40
BZ-66 h=1.30
BZ-68A h=1.40
BZ-55 h=1.2
BZ-123 h=1.20
BZ-558 h=1.20
BZ-558A h=1.2
BZ-558B h=1.2
BZ-558C h=1.20
CHICHILIN
BZCHI 62A h=1.40
BZCHI 62 h=1.40
BZCHI 63B h=1.20
BZCHI 63A h=1.20
BZCHI 63 h=1.20
BZCHI 64B h=1.20
BZCHI 64A h=1.20
BZCHI 65A h=1.20
BZCHI 65 h=1.20
BZCHI 66 h=1.20
BZCHI 67 h=1.20
BZCHI 68 h=1.20
BZCHI 74 h=1.20
BZCHI 75 h=1.20
BZCHI 76 h=1.20
BZCHI 77 h=1.40
BZCHI 78 h=1.40
BZCHI 79 h=1.40
BZCHI 80 h=1.40
BZCHI 81 h=1.40
BZCHI 82 h=1.40
BZCHI 83 h=1.40
BZCHI 84 h=1.40
BZCHI 85 h=1.40
BZCHI 86 h=1.40
BZCHI 87 h=1.40
BZCHI 88 h=1.40
BZCHI 89 h=1.40
BZCHI 90 h=1.40
BZCHI 91 h=1.40
BZCHI 92 h=1.40
BZCHI 93 h=1.40
BZ 974 h=1.40
12.02.05.02 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=2.00M und 65.00 0.00 128.83 0.00
COGRI
BZ-35 h=1.60
BZ-134 h=1.60
BZ-67 h=1.60
BZ-68 h=1.80
CHICHILIN
BZCHI 71 h=2.00
12.02.05.03 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=2.50M und 31.00 0.00 141.74 0.00
COGRI
BZ - 30 H 2.43
12.02.05.04 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=3.00M und 30.00 157.48 0.00
COGRI
BZ-37 h=2.95
CHICHILIN
BZCHI 70 h=2.70
BZCHI 72 h=2.70
BZCHI 73 h=2.70
12.02.05.05 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=3.50M und 30.00 0.00 177.17 0.00
COGRI
BZ-69 h=3.20
CHICHILIN
BZCHI 69 h=3.40
COGRI
BZ-24 h=1.20
BZ-25 h=1.20
BZ-27 h=1.30
BZ-33 h=1.30
BZ-33A h=1.20
BZ-34 h=1.40
BZ-129 h=1.50
BZ-28 h=1.4
BZ-35A h=1.5
BZ-36 h=1.4
BZ-127 h=1.4
BZ-128 h=1.4
BZ-38 h=1.5
BZ-39 h=1.5
BZ-40 h=1.4
BZ-41 h=1.3
BZ-36 h=1.30
BZ-42 h=1.2
BZ-32 h=1.2
BZ-31 h=1.3
BZ-45 h=1.2
BZ-44 h=1.4
BZ-46 h=1.3
BZ-47 h=1.2
BZ-48 h=1.2
BZ-125 h=1.2
BZ-49 h=1.4
BZ-49A h=1.4
BZ-50 h=1.4
BZ-51 h=1.40
BZ-52 h=1.50
BZ-53 h=1.20
BZ-61 h=1.30
BZ-133 h=1.30
BZ-62 h=1.30
BZ-63 h=1.50
BZ-65 h=1.40
BZ-66A h=1.40
BZ-66 h=1.30
BZ-68A h=1.40
BZ-55 h=1.2
BZ-123 h=1.20
BZ-558 h=1.20
BZ-558A h=1.2
BZ-558B h=1.2
BZ-558C h=1.20
CHICHILIN
BZCHI 62A h=1.40
BZCHI 62 h=1.40
BZCHI 63B h=1.20
BZCHI 63A h=1.20
BZCHI 63 h=1.20
BZCHI 64B h=1.20
BZCHI 64A h=1.20
BZCHI 65A h=1.20
BZCHI 65 h=1.20
BZCHI 66 h=1.20
BZCHI 67 h=1.20
BZCHI 68 h=1.20
BZCHI 74 h=1.20
BZCHI 75 h=1.20
BZCHI 76 h=1.20
BZCHI 77 h=1.40
BZCHI 78 h=1.40
BZCHI 79 h=1.40
BZCHI 80 h=1.40
BZCHI 81 h=1.40
BZCHI 82 h=1.40
BZCHI 83 h=1.40
BZCHI 84 h=1.40
BZCHI 85 h=1.40
BZCHI 86 h=1.40
BZCHI 87 h=1.40
BZCHI 88 h=1.40
BZCHI 89 h=1.40
BZCHI 90 h=1.40
BZCHI 91 h=1.40
BZCHI 92 h=1.40
BZCHI 93 h=1.40
BZ 974 h=1.40
12.02.06.02 CONSTRUCCION DE BUZONES DN=1.20M, H=1.51 @2.00m Und 65.00 0.00 1,669.55 0.00
COGRI
BZ-35 h=1.60
BZ-134 h=1.60
BZ-67 h=1.60
BZ-68 h=1.80
CHICHILIN
BZCHI 71 h=2.00
12.02.06.03 CONSTRUCCION DE BUZONES DN=1.20M, H=2.01 @2.50m Und 30.00 0.00 1,646.94 0.00
COGRI
BZ - 30 H 2.43
CHICHILIN
BZCHI 50 h=2.30
BZCHI 98 h=2.40
12.02.06.04 CONSTRUCCION DE BUZONES DN=1.20M, H=2.51 @3.00m Und 30.00 0.00 1,951.04 0.00
COGRI
BZ-37 h=2.95
BZ-778-C h=2.65
CHICHILIN
BZCHI 70 h=2.70
BZCHI 72 h=2.70
BZCHI 73 h=2.70
12.02.06.05 CONSTRUCCION DE BUZONES DN=1.20M, H=3.01 @3.50m Und 30.00 0.00 3,296.84 0.00
COGRI
BZ-69 h=3.20
CHICHILIN
BZCHI 69 h=3.40
12 SISTEMA DE ALCANTARILLADO
12.01 RED DE DESAGUE - COLECTORES PRIMARIOS
12.02.02 MOVIMIENTO DE TIERRAS
12.01.02.01 EXCAVACION C/EQUIPO T.NORMAL H=1.50M, P/TUB DN 200MM DESAGUE m 233.00 14.12 3,289.96
12.01.02.05 EXCAVACION C/EQUIPO T.NORMAL H=2.50M, P/TUB DN 200MM DESAGUE 13.45 19.21 258.37
12.01.02.10 EXCAVACION C/EQUIPO T.NORMAL H=3.00M, P/TUB DN 200MM DESAGUE m 80.48 20.60 1,657.89
12.02.03.13 EXCAVACION C/EQUIPO T.NORMAL H=3.50M, P/TUB DN 200MM DESAGUE m 311.82 21.40 6,672.95
12.02.03.19 EXCAVACION C/EQUIPO T.NORMAL H=4.50M, P/TUB DN 200MM DESAGUE m 34.29 22.26 763.30
ESCOBAYA - SAN FRANCISCO
BZ _A_18@ BZ _A_19 h=4.25, h=3.33 4.84
BZ 776-Q @ BZ 776-52 h=4.24, h =2.83 29.45
12.02.03.22 EXCAVACION C/EQUIPO T.NORMAL H=5.00M, P/TUB DN 200MM DESAGUE m 78.25 24.22 1,895.22
ESCOBAYA - SAN FRANCISCO
BZ _A_15@ BZ _A_16 h=3.44, h=6.64 32.96
BZ _A_16@ BZ _A_17 h=6.64, h=7.47 29.47
BZ _A_17@ BZ _A_18 h=7.47, h=4.25 15.82
12.01.02.59 RELLENO PROTECTOR C/MAT PROPIO P/TUB 200MM, H=0.30M m 751.29 5.35 4,019.40
12.01.02.60 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=1.50M m 233.00 3.81 887.73
12.01.02.62 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=2.50M m 13.45 7.25 97.51
12.01.02.63 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=3.00M m 80.48 7.25 583.48
12.01.02.64 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=3.50M m 311.82 5.84 1,821.03
12.01.02.67 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=5.00M m 78.25 8.87 694.08
ESCOBAYA - SAN FRANCISCO
BZ _A_15@ BZ _A_16 h=3.44, h=6.64 32.96
BZ _A_16@ BZ _A_17 h=6.64, h=7.47 29.47
BZ _A_17@ BZ _A_18 h=7.47, h=4.25 15.82
12.01.03.02 INSTALACION DE TUBERIA ISO 4435 S-25 DN=200MM m 751.29 4.28 3,215.52
12.01.03.03 PRUEBA HIDRAULICA PARCIAL A ZANJA DESCUBIERTA DE TUBERIA PVC/ISO 4435 m 751.29 1.99 1,495.07
12.01.03.04 PRUEBA HIDRAULICA FINAL A ZANJA TAPADA DE TUBERIA PVC/ISO 4435 DN=200M m 751.29 1.99 1,495.07
12.01.04.01 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=1.50M und 10.00 118.11 1,181.10
12.01.04.03 EXCAVACION BUZON, Dexc.=2.01M, HASTA H=2.50M und 2.00 141.74 283.48
12.01.04.04 EXCAVACION BUZON, Dexc.=2.50M, HASTA H=3.00M und 4.00 157.48 629.92
12.01.04.05 EXCAVACION BUZON, Dexc.=1.90M, HASTA H=3.50M und 6.00 177.17 1,063.02
12.01.04.06 EXCAVACION BUZON, Dexc.=1.90M, HASTA H=4.00M und 4.00 202.40 809.60
12.01.04.07 EXCAVACION BUZON, Dexc.=1.90M, HASTA H=4.50M und 4.00 236.22 944.88
12.01.05.03 CONSTRUCCION DE BUZONES DN=1.20M, H=2.01 @2.50m und 2.00 1,646.94 3,293.88
12.01.05.04 CONSTRUCCION DE BUZONES DN=1.20M, H=2.51 @3.00m und 4.00 1,951.04 7,804.16
12.01.05.05 CONSTRUCCION DE BUZONES DN=1.50M, H=3.01 @3.50m und 6.00 3,296.84 19,781.04
ESCOBAYA - SAN FRANCISCO
BZ 842 h=3.28 1.00
BZ 843 h=3.31 1.00
BZ 844 h=3.30 1.00
BZ 845 h=3.37 1.00
BZ 781 h=3.08 1.00
BZ 780 h=3.32 1.00
12.01.05.06 CONSTRUCCION DE BUZONES DN=1.50M, H=3.51 @4.00m und 4.00 3,526.15 14,104.60
ESCOBAYA - SAN FRANCISCO
BZ A-19, h =3.72 1.00
BZ A-13, h=3.66 1.00
BZ A-14, h=3.69 1.00
BZ A-15, h =3.80 1.00
12.01.05.07 CONSTRUCCION DE BUZONES DN=1.50M, H=4.01 @4.50m und 4.00 3,683.83 14,735.32
ESCOBAYA - SAN FRANCISCO
BZ A-18, h =4.67 1.00
BZ A-16, h =6.99 1.00
BZ A-17, h =7.83 1.00
BZ 776- Q,h=4.24 1.00
12.01.05.16 ANCLAJE O DADOS DE CONCRETO F´c=140KG/CM2 EN BUZONES und 8.00 29.05 232.40
COGRI
BZ 36@ BZ 127 h=1.40, H=1.40 63.10
BZ 127@ BZ 128 h=1.40, H=1.40 39.76
BZ 38@ BZ 39 h=1.50, H=1.50 68.54
BZ 39@ BZ 41 h=1.50, H=1.30 64.74
BZ 41@ BZ 36 h=1.30, H=1.30 50.62
BZ 36@ BZ 42 h=1.30, H=1.20 50.62
BZ42@ BZ 32 h=1.20, H=1.20 18.63
BZ 27 @ BZ 28 h=1.20, H=1.40 62.61
BZ 46 @ BZ 47 h=1.30, H=1.20 51.79
BZ 504@ BZ 49 h=1.30, H=1.40 14.35
BZ 49@ BZ 49A h=1.40, H=1.40 26.04
BZ 49A@ BZ 50 h=1.40, H=1.40 48.78
BZ 50@ BZ 51 h=1.40, H=1.40 47.37
BZ 61@ BZ 133 h=1.30, H=1.30 40.07
BZ 133@ BZ 62 h=1.30, H=1.30 39.19
BZ 62@ BZ 63 h=1.30, H=1.50 78.86
BZ 63@ BZ 66 h=1.50, H=1.30 60.08
BZ 65@ BZ 66A h=1.40, H=1.40 47.54
BZ 66A@ BZ 66 h=1.40, H=1.30 49.04
BZ 66@ BZ 55 h=1.30, H=1.20 18.92
ACHICARI - HUASALÓN
BZ_P1 @ BZ_P2 h=1.20, h=1.20 16.54
BZ_P2 @ BZ_P3 h=1.20, h=1.20 16.21
BZ_P3 @ BZ_P4 h=1.20, h=1.20 16.28
BZ_P4 @ BZ_P5 h=1.20, h=1.20 20.69
BZ_P5 @ BZ_P6 h=1.20, h=1.20 54.51
BZ_P6 @ BZ_P7 h=1.20, h=1.20 39.96
BZ_P7 @ BZ_P8 h=1.20, h=1.20 22.62
BZ_P8 @ BZ_P9 h=1.20, h=1.20 11.74
BZ_P9 @ BZ_P10 h=1.20, h=1.20 31.57
BZ_P10 @ BZ_P11 h=1.20, h=1.20 12.36
BZ_P11 @ BZ_P12 h=1.20, h=1.20 14.37
BZ_P12 @ BZ_P13 h=1.20, h=1.20 23.58
BZ_P13 @ BZ_P14 h=1.20, h=1.20 47.82
BZ_P14 @ BZ_P15 h=1.20, h=1.20 17.13
BZ_P15 @ BZ_P16 h=1.20, h=1.20 35.88
BZ_P16 @ BZ_P17 h=1.20, h=1.20 23.51
BZ_P17 @ BZ_P18 h=1.20, h=1.20 9.13
BZ_P18 @ BZ_P19 h=1.20, h=1.20 10.09
BZ_P19 @ BZ_P20 h=1.20, h=1.20 35.04
BZ_P20 @ BZ_P21 h=1.20, h=1.20 43.61
BZ_P21 @ BZ_P22 h=1.20, h=1.20 38.07
BZ_P22 @ BZ_P23 h=1.20, h=1.20 33.98
BZ_P23 @ BZ_P24 h=1.20, h=1.20 34.81
CHICHILIN
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 76.06
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 22.61
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.75
12.02.03.04 EXCAVACION C/EQUIPO T.NORMAL H=2.00M, P/TUB DN 200MM DESAGUE m 286.39 18.01 5,157.88
COGRI
BZ 134@ BZ 65 h=1.60, H=1.40 77.83
BZ 35 @ BZ 36 h=1.60, H=1.40 68.28
BZ 67@ BZ 68 h=1.60, H=1.80 58.00
BZ 68@ BZ 68A h=1.80, H=1.40 50.59
CHICHILÍN
BZCHI 75 @ BZCHI 76 h=1.20, h=2.00 31.69
12.02.03.10 EXCAVACION C/EQUIPO T.NORMAL H=3.00M, P/TUB DN 200MM DESAGUE m 259.71 20.60 5,350.03
COGRI
BZ 37 @ BZ 30 h=2.95, H=2.43 23.86
BZ 30 @ BZ 31 h=2.43, H=2.60 21.63
BZ 28 @ BZ 37 h=1.40, H=2.95 68.03
BZ32@ BZ 31 h=1.20, H=2.60 10.88
BZ 128@ BZ 37 h=1.40, H=2.95 61.04
CHICHILIN
BZCHI 76 @ BZCHI 77 h=2.00, h=2.85 37.29
BZCHI 77 @ BZCHI 78 h=2.85, h=1.40 36.98
12.02.03.13 EXCAVACION C/EQUIPO T.NORMAL H=3.50M, P/TUB DN 200MM DESAGUE m 84.93 21.40 1,817.50
COGRI
BZ 55@ BZ 69 h=1.20, H=3.20 43.83
BZ 68A@ BZ 69 h=1.40, H=3.20 6.93
BZ 69@ BZ 8 h=3.20, H=1.40 34.17
COGRI
BZ 36@ BZ 127 h=1.40, H=1.40 63.10
BZ 127@ BZ 128 h=1.40, H=1.40 39.76
BZ 38@ BZ 39 h=1.50, H=1.50 68.54
BZ 39@ BZ 41 h=1.50, H=1.30 64.74
BZ 41@ BZ 36 h=1.30, H=1.30 50.62
BZ 36@ BZ 42 h=1.30, H=1.20 50.62
BZ42@ BZ 32 h=1.20, H=1.20 18.63
BZ 27 @ BZ 28 h=1.20, H=1.40 62.61
BZ 46 @ BZ 47 h=1.30, H=1.20 51.79
BZ 504@ BZ 49 h=1.30, H=1.40 14.35
BZ 49@ BZ 49A h=1.40, H=1.40 26.04
BZ 49A@ BZ 50 h=1.40, H=1.40 48.78
BZ 50@ BZ 51 h=1.40, H=1.40 47.37
BZ 61@ BZ 133 h=1.30, H=1.30 40.07
BZ 133@ BZ 62 h=1.30, H=1.30 39.19
BZ 62@ BZ 63 h=1.30, H=1.50 78.86
BZ 134@ BZ 65 h=1.60, H=1.40 77.83
BZ 35 @ BZ 36 h=1.60, H=1.40 68.28
BZ 37 @ BZ 30 h=2.95, H=2.43 23.86
BZ 30 @ BZ 31 h=2.43, H=2.60 21.63
BZ 28 @ BZ 37 h=1.40, H=2.95 68.03
BZ32@ BZ 31 h=1.20, H=2.60 10.88
BZ 128@ BZ 37 h=1.40, H=2.95 61.04
BZ 63@ BZ 66 h=1.50, H=1.30 60.08
BZ 65@ BZ 66A h=1.40, H=1.40 47.54
BZ 66A@ BZ 66 h=1.40, H=1.30 49.04
BZ 66@ BZ 55 h=1.30, H=1.20 18.92
BZ 55@ BZ 69 h=1.20, H=3.20 43.83
BZ 67@ BZ 68 h=1.60, H=1.80 58.00
BZ 68@ BZ 68A h=1.80, H=1.40 50.59
BZ 68A@ BZ 69 h=1.40, H=3.20 6.93
BZ 69@ BZ 8 h=3.20, H=1.40 34.17
ACHICARI - HUASALÓN
BZ_P1 @ BZ_P2 h=1.20, h=1.20 16.54
BZ_P2 @ BZ_P3 h=1.20, h=1.20 16.21
BZ_P3 @ BZ_P4 h=1.20, h=1.20 16.28
BZ_P4 @ BZ_P5 h=1.20, h=1.20 20.69
BZ_P5 @ BZ_P6 h=1.20, h=1.20 54.51
BZ_P6 @ BZ_P7 h=1.20, h=1.20 39.96
BZ_P7 @ BZ_P8 h=1.20, h=1.20 22.62
BZ_P8 @ BZ_P9 h=1.20, h=1.20 11.74
BZ_P9 @ BZ_P10 h=1.20, h=1.20 31.57
BZ_P10 @ BZ_P11 h=1.20, h=1.20 12.36
BZ_P11 @ BZ_P12 h=1.20, h=1.20 14.37
BZ_P12 @ BZ_P13 h=1.20, h=1.20 23.58
BZ_P13 @ BZ_P14 h=1.20, h=1.20 47.82
BZ_P14 @ BZ_P15 h=1.20, h=1.20 17.13
BZ_P15 @ BZ_P16 h=1.20, h=1.20 35.88
BZ_P16 @ BZ_P17 h=1.20, h=1.20 23.51
BZ_P17 @ BZ_P18 h=1.20, h=1.20 9.13
BZ_P18 @ BZ_P19 h=1.20, h=1.20 10.09
BZ_P19 @ BZ_P20 h=1.20, h=1.20 35.04
BZ_P20 @ BZ_P21 h=1.20, h=1.20 43.61
BZ_P21 @ BZ_P22 h=1.20, h=1.20 38.07
BZ_P22 @ BZ_P23 h=1.20, h=1.20 33.98
BZ_P23 @ BZ_P24 h=1.20, h=1.20 34.81
CHICHILIN
BZCHI 75 @ BZCHI 76 h=1.20, h=2.00 31.69
BZCHI 76 @ BZCHI 77 h=2.00, h=2.85 37.29
BZCHI 77 @ BZCHI 78 h=2.85, h=1.40 36.98
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 76.06
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 22.61
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.75
COGRI
BZ 36@ BZ 127 h=1.40, H=1.40 63.10
BZ 127@ BZ 128 h=1.40, H=1.40 39.76
BZ 38@ BZ 39 h=1.50, H=1.50 68.54
BZ 39@ BZ 41 h=1.50, H=1.30 64.74
BZ 41@ BZ 36 h=1.30, H=1.30 50.62
BZ 36@ BZ 42 h=1.30, H=1.20 50.62
BZ42@ BZ 32 h=1.20, H=1.20 18.63
BZ 27 @ BZ 28 h=1.20, H=1.40 62.61
BZ 46 @ BZ 47 h=1.30, H=1.20 51.79
BZ 504@ BZ 49 h=1.30, H=1.40 14.35
BZ 49@ BZ 49A h=1.40, H=1.40 26.04
BZ 49A@ BZ 50 h=1.40, H=1.40 48.78
BZ 50@ BZ 51 h=1.40, H=1.40 47.37
BZ 61@ BZ 133 h=1.30, H=1.30 40.07
BZ 133@ BZ 62 h=1.30, H=1.30 39.19
BZ 62@ BZ 63 h=1.30, H=1.50 78.86
BZ 134@ BZ 65 h=1.60, H=1.40 77.83
BZ 35 @ BZ 36 h=1.60, H=1.40 68.28
BZ 37 @ BZ 30 h=2.95, H=2.43 23.86
BZ 30 @ BZ 31 h=2.43, H=2.60 21.63
BZ 28 @ BZ 37 h=1.40, H=2.95 68.03
BZ32@ BZ 31 h=1.20, H=2.60 10.88
BZ 128@ BZ 37 h=1.40, H=2.95 61.04
BZ 63@ BZ 66 h=1.50, H=1.30 60.08
BZ 65@ BZ 66A h=1.40, H=1.40 47.54
BZ 66A@ BZ 66 h=1.40, H=1.30 49.04
BZ 66@ BZ 55 h=1.30, H=1.20 18.92
BZ 55@ BZ 69 h=1.20, H=3.20 43.83
BZ 67@ BZ 68 h=1.60, H=1.80 58.00
BZ 68@ BZ 68A h=1.80, H=1.40 50.59
BZ 68A@ BZ 69 h=1.40, H=3.20 6.93
BZ 69@ BZ 8 h=3.20, H=1.40 34.17
ACHICARI - HUASALÓN
BZ_P1 @ BZ_P2 h=1.20, h=1.20 16.54
BZ_P2 @ BZ_P3 h=1.20, h=1.20 16.21
BZ_P3 @ BZ_P4 h=1.20, h=1.20 16.28
BZ_P4 @ BZ_P5 h=1.20, h=1.20 20.69
BZ_P5 @ BZ_P6 h=1.20, h=1.20 54.51
BZ_P6 @ BZ_P7 h=1.20, h=1.20 39.96
BZ_P7 @ BZ_P8 h=1.20, h=1.20 22.62
BZ_P8 @ BZ_P9 h=1.20, h=1.20 11.74
BZ_P9 @ BZ_P10 h=1.20, h=1.20 31.57
BZ_P10 @ BZ_P11 h=1.20, h=1.20 12.36
BZ_P11 @ BZ_P12 h=1.20, h=1.20 14.37
BZ_P12 @ BZ_P13 h=1.20, h=1.20 23.58
BZ_P13 @ BZ_P14 h=1.20, h=1.20 47.82
BZ_P14 @ BZ_P15 h=1.20, h=1.20 17.13
BZ_P15 @ BZ_P16 h=1.20, h=1.20 35.88
BZ_P16 @ BZ_P17 h=1.20, h=1.20 23.51
BZ_P17 @ BZ_P18 h=1.20, h=1.20 9.13
BZ_P18 @ BZ_P19 h=1.20, h=1.20 10.09
BZ_P19 @ BZ_P20 h=1.20, h=1.20 35.04
BZ_P20 @ BZ_P21 h=1.20, h=1.20 43.61
BZ_P21 @ BZ_P22 h=1.20, h=1.20 38.07
BZ_P22 @ BZ_P23 h=1.20, h=1.20 33.98
BZ_P23 @ BZ_P24 h=1.20, h=1.20 34.81
CHICHILIN
BZCHI 75 @ BZCHI 76 h=1.20, h=2.00 31.69
BZCHI 76 @ BZCHI 77 h=2.00, h=2.85 37.29
BZCHI 77 @ BZCHI 78 h=2.85, h=1.40 36.98
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 76.06
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 22.61
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.75
12.02.03.39 RELLENO PROTECTOR C/MAT PROPIO P/TUB 200MM, H=0.30M m 2,829.96 5.35 15,140.29
COGRI
BZ 36@ BZ 127 h=1.40, H=1.40 63.10
BZ 127@ BZ 128 h=1.40, H=1.40 39.76
BZ 38@ BZ 39 h=1.50, H=1.50 68.54
BZ 39@ BZ 41 h=1.50, H=1.30 64.74
BZ 41@ BZ 36 h=1.30, H=1.30 50.62
BZ 36@ BZ 42 h=1.30, H=1.20 50.62
BZ42@ BZ 32 h=1.20, H=1.20 18.63
BZ 27 @ BZ 28 h=1.20, H=1.40 62.61
BZ 46 @ BZ 47 h=1.30, H=1.20 51.79
BZ 504@ BZ 49 h=1.30, H=1.40 14.35
BZ 49@ BZ 49A h=1.40, H=1.40 26.04
BZ 49A@ BZ 50 h=1.40, H=1.40 48.78
BZ 50@ BZ 51 h=1.40, H=1.40 47.37
BZ 61@ BZ 133 h=1.30, H=1.30 40.07
BZ 133@ BZ 62 h=1.30, H=1.30 39.19
BZ 62@ BZ 63 h=1.30, H=1.50 78.86
BZ 134@ BZ 65 h=1.60, H=1.40 77.83
BZ 35 @ BZ 36 h=1.60, H=1.40 68.28
BZ 37 @ BZ 30 h=2.95, H=2.43 23.86
BZ 30 @ BZ 31 h=2.43, H=2.60 21.63
BZ 28 @ BZ 37 h=1.40, H=2.95 68.03
BZ32@ BZ 31 h=1.20, H=2.60 10.88
BZ 128@ BZ 37 h=1.40, H=2.95 61.04
BZ 63@ BZ 66 h=1.50, H=1.30 60.08
BZ 65@ BZ 66A h=1.40, H=1.40 47.54
BZ 66A@ BZ 66 h=1.40, H=1.30 49.04
BZ 66@ BZ 55 h=1.30, H=1.20 18.92
BZ 55@ BZ 69 h=1.20, H=3.20 43.83
BZ 67@ BZ 68 h=1.60, H=1.80 58.00
BZ 68@ BZ 68A h=1.80, H=1.40 50.59
BZ 68A@ BZ 69 h=1.40, H=3.20 6.93
BZ 69@ BZ 8 h=3.20, H=1.40 34.17
ACHICARI - HUASALÓN
BZ_P1 @ BZ_P2 h=1.20, h=1.20 16.54
BZ_P2 @ BZ_P3 h=1.20, h=1.20 16.21
BZ_P3 @ BZ_P4 h=1.20, h=1.20 16.28
BZ_P4 @ BZ_P5 h=1.20, h=1.20 20.69
BZ_P5 @ BZ_P6 h=1.20, h=1.20 54.51
BZ_P6 @ BZ_P7 h=1.20, h=1.20 39.96
BZ_P7 @ BZ_P8 h=1.20, h=1.20 22.62
BZ_P8 @ BZ_P9 h=1.20, h=1.20 11.74
BZ_P9 @ BZ_P10 h=1.20, h=1.20 31.57
BZ_P10 @ BZ_P11 h=1.20, h=1.20 12.36
BZ_P11 @ BZ_P12 h=1.20, h=1.20 14.37
BZ_P12 @ BZ_P13 h=1.20, h=1.20 23.58
BZ_P13 @ BZ_P14 h=1.20, h=1.20 47.82
BZ_P14 @ BZ_P15 h=1.20, h=1.20 17.13
BZ_P15 @ BZ_P16 h=1.20, h=1.20 35.88
BZ_P16 @ BZ_P17 h=1.20, h=1.20 23.51
BZ_P17 @ BZ_P18 h=1.20, h=1.20 9.13
BZ_P18 @ BZ_P19 h=1.20, h=1.20 10.09
BZ_P19 @ BZ_P20 h=1.20, h=1.20 35.04
BZ_P20 @ BZ_P21 h=1.20, h=1.20 43.61
BZ_P21 @ BZ_P22 h=1.20, h=1.20 38.07
BZ_P22 @ BZ_P23 h=1.20, h=1.20 33.98
BZ_P23 @ BZ_P24 h=1.20, h=1.20 34.81
CHICHILIN
BZCHI 75 @ BZCHI 76 h=1.20, h=2.00 31.69
BZCHI 76 @ BZCHI 77 h=2.00, h=2.85 37.29
BZCHI 77 @ BZCHI 78 h=2.85, h=1.40 36.98
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 76.06
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 22.61
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.75
12.02.03.40 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=1.50M m 2,198.93 3.81 8,377.92
COGRI
BZ 36@ BZ 127 h=1.40, H=1.40 63.10
BZ 127@ BZ 128 h=1.40, H=1.40 39.76
BZ 38@ BZ 39 h=1.50, H=1.50 68.54
BZ 39@ BZ 41 h=1.50, H=1.30 64.74
BZ 41@ BZ 36 h=1.30, H=1.30 50.62
BZ 36@ BZ 42 h=1.30, H=1.20 50.62
BZ42@ BZ 32 h=1.20, H=1.20 18.63
BZ 27 @ BZ 28 h=1.20, H=1.40 62.61
BZ 46 @ BZ 47 h=1.30, H=1.20 51.79
BZ 504@ BZ 49 h=1.30, H=1.40 14.35
BZ 49@ BZ 49A h=1.40, H=1.40 26.04
BZ 49A@ BZ 50 h=1.40, H=1.40 48.78
BZ 50@ BZ 51 h=1.40, H=1.40 47.37
BZ 61@ BZ 133 h=1.30, H=1.30 40.07
BZ 133@ BZ 62 h=1.30, H=1.30 39.19
BZ 62@ BZ 63 h=1.30, H=1.50 78.86
BZ 63@ BZ 66 h=1.50, H=1.30 60.08
BZ 65@ BZ 66A h=1.40, H=1.40 47.54
BZ 66A@ BZ 66 h=1.40, H=1.30 49.04
BZ 66@ BZ 55 h=1.30, H=1.20 18.92
ACHICARI - HUASALÓN
BZ_P1 @ BZ_P2 h=1.20, h=1.20 16.54
BZ_P2 @ BZ_P3 h=1.20, h=1.20 16.21
BZ_P3 @ BZ_P4 h=1.20, h=1.20 16.28
BZ_P4 @ BZ_P5 h=1.20, h=1.20 20.69
BZ_P5 @ BZ_P6 h=1.20, h=1.20 54.51
BZ_P6 @ BZ_P7 h=1.20, h=1.20 39.96
BZ_P7 @ BZ_P8 h=1.20, h=1.20 22.62
BZ_P8 @ BZ_P9 h=1.20, h=1.20 11.74
BZ_P9 @ BZ_P10 h=1.20, h=1.20 31.57
BZ_P10 @ BZ_P11 h=1.20, h=1.20 12.36
BZ_P11 @ BZ_P12 h=1.20, h=1.20 14.37
BZ_P12 @ BZ_P13 h=1.20, h=1.20 23.58
BZ_P13 @ BZ_P14 h=1.20, h=1.20 47.82
BZ_P14 @ BZ_P15 h=1.20, h=1.20 17.13
BZ_P15 @ BZ_P16 h=1.20, h=1.20 35.88
BZ_P16 @ BZ_P17 h=1.20, h=1.20 23.51
BZ_P17 @ BZ_P18 h=1.20, h=1.20 9.13
BZ_P18 @ BZ_P19 h=1.20, h=1.20 10.09
BZ_P19 @ BZ_P20 h=1.20, h=1.20 35.04
BZ_P20 @ BZ_P21 h=1.20, h=1.20 43.61
BZ_P21 @ BZ_P22 h=1.20, h=1.20 38.07
BZ_P22 @ BZ_P23 h=1.20, h=1.20 33.98
BZ_P23 @ BZ_P24 h=1.20, h=1.20 34.81
CHICHILIN
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 76.06
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 22.61
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.75
12.02.03.41 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=2.00M m 286.39 6.25 1,789.94
COGRI
BZ 134@ BZ 65 h=1.60, H=1.40 77.83
BZ 35 @ BZ 36 h=1.60, H=1.40 68.28
BZ 67@ BZ 68 h=1.60, H=1.80 58.00
BZ 68@ BZ 68A h=1.80, H=1.40 50.59
CHICHILIN
12.02.03.43 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=3.00M m 259.71 7.25 1,882.90
COGRI
BZ 37 @ BZ 30 h=2.95, H=2.43 23.86
BZ 30 @ BZ 31 h=2.43, H=2.60 21.63
BZ 28 @ BZ 37 h=1.40, H=2.95 68.03
BZ32@ BZ 31 h=1.20, H=2.60 10.88
BZ 128@ BZ 37 h=1.40, H=2.95 61.04
CHICHILIN
12.02.03.44 RELLENO Y COMPACTADO C/MAT PROPIO, A=0.60M, H=3.50M m 84.93 5.84 495.99
COGRI
BZ 55@ BZ 69 h=1.20, H=3.20 43.83
BZ 68A@ BZ 69 h=1.40, H=3.20 6.93
BZ 69@ BZ 8 h=3.20, H=1.40 34.17
COGRI
BZ 36@ BZ 127 h=1.40, H=1.40 63.10
BZ 127@ BZ 128 h=1.40, H=1.40 39.76
BZ 38@ BZ 39 h=1.50, H=1.50 68.54
BZ 39@ BZ 41 h=1.50, H=1.30 64.74
BZ 41@ BZ 36 h=1.30, H=1.30 50.62
BZ 36@ BZ 42 h=1.30, H=1.20 50.62
BZ42@ BZ 32 h=1.20, H=1.20 18.63
BZ 27 @ BZ 28 h=1.20, H=1.40 62.61
BZ 46 @ BZ 47 h=1.30, H=1.20 51.79
BZ 504@ BZ 49 h=1.30, H=1.40 14.35
BZ 49@ BZ 49A h=1.40, H=1.40 26.04
BZ 49A@ BZ 50 h=1.40, H=1.40 48.78
BZ 50@ BZ 51 h=1.40, H=1.40 47.37
BZ 61@ BZ 133 h=1.30, H=1.30 40.07
BZ 133@ BZ 62 h=1.30, H=1.30 39.19
BZ 62@ BZ 63 h=1.30, H=1.50 78.86
BZ 134@ BZ 65 h=1.60, H=1.40 77.83
BZ 35 @ BZ 36 h=1.60, H=1.40 68.28
BZ 37 @ BZ 30 h=2.95, H=2.43 23.86
BZ 30 @ BZ 31 h=2.43, H=2.60 21.63
BZ 28 @ BZ 37 h=1.40, H=2.95 68.03
BZ32@ BZ 31 h=1.20, H=2.60 10.88
BZ 128@ BZ 37 h=1.40, H=2.95 61.04
BZ 63@ BZ 66 h=1.50, H=1.30 60.08
BZ 65@ BZ 66A h=1.40, H=1.40 47.54
BZ 66A@ BZ 66 h=1.40, H=1.30 49.04
BZ 66@ BZ 55 h=1.30, H=1.20 18.92
BZ 55@ BZ 69 h=1.20, H=3.20 43.83
BZ 67@ BZ 68 h=1.60, H=1.80 58.00
BZ 68@ BZ 68A h=1.80, H=1.40 50.59
BZ 68A@ BZ 69 h=1.40, H=3.20 6.93
BZ 69@ BZ 8 h=3.20, H=1.40 34.17
ACHICARI - HUASALÓN
BZ_P1 @ BZ_P2 h=1.20, h=1.20 16.54
BZ_P2 @ BZ_P3 h=1.20, h=1.20 16.21
BZ_P3 @ BZ_P4 h=1.20, h=1.20 16.28
BZ_P4 @ BZ_P5 h=1.20, h=1.20 20.69
BZ_P5 @ BZ_P6 h=1.20, h=1.20 54.51
BZ_P6 @ BZ_P7 h=1.20, h=1.20 39.96
BZ_P7 @ BZ_P8 h=1.20, h=1.20 22.62
BZ_P8 @ BZ_P9 h=1.20, h=1.20 11.74
BZ_P9 @ BZ_P10 h=1.20, h=1.20 31.57
BZ_P10 @ BZ_P11 h=1.20, h=1.20 12.36
BZ_P11 @ BZ_P12 h=1.20, h=1.20 14.37
BZ_P12 @ BZ_P13 h=1.20, h=1.20 23.58
BZ_P13 @ BZ_P14 h=1.20, h=1.20 47.82
BZ_P14 @ BZ_P15 h=1.20, h=1.20 17.13
BZ_P15 @ BZ_P16 h=1.20, h=1.20 35.88
BZ_P16 @ BZ_P17 h=1.20, h=1.20 23.51
BZ_P17 @ BZ_P18 h=1.20, h=1.20 9.13
BZ_P18 @ BZ_P19 h=1.20, h=1.20 10.09
BZ_P19 @ BZ_P20 h=1.20, h=1.20 35.04
BZ_P20 @ BZ_P21 h=1.20, h=1.20 43.61
BZ_P21 @ BZ_P22 h=1.20, h=1.20 38.07
BZ_P22 @ BZ_P23 h=1.20, h=1.20 33.98
BZ_P23 @ BZ_P24 h=1.20, h=1.20 34.81
CHICHILIN
BZCHI 75 @ BZCHI 76 h=1.20, h=2.00 31.69
BZCHI 76 @ BZCHI 77 h=2.00, h=2.85 37.29
BZCHI 77 @ BZCHI 78 h=2.85, h=1.40 36.98
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 76.06
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 22.61
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.75
12.02.04.02 INSTALACION DE TUBERIA ISO 4435 S-25 DN=200MM m 2,829.96 4.28 12,112.23
COGRI
BZ 36@ BZ 127 h=1.40, H=1.40 63.10
BZ 127@ BZ 128 h=1.40, H=1.40 39.76
BZ 38@ BZ 39 h=1.50, H=1.50 68.54
BZ 39@ BZ 41 h=1.50, H=1.30 64.74
BZ 41@ BZ 36 h=1.30, H=1.30 50.62
BZ 36@ BZ 42 h=1.30, H=1.20 50.62
BZ42@ BZ 32 h=1.20, H=1.20 18.63
BZ 27 @ BZ 28 h=1.20, H=1.40 62.61
BZ 46 @ BZ 47 h=1.30, H=1.20 51.79
BZ 504@ BZ 49 h=1.30, H=1.40 14.35
BZ 49@ BZ 49A h=1.40, H=1.40 26.04
BZ 49A@ BZ 50 h=1.40, H=1.40 48.78
BZ 50@ BZ 51 h=1.40, H=1.40 47.37
BZ 61@ BZ 133 h=1.30, H=1.30 40.07
BZ 133@ BZ 62 h=1.30, H=1.30 39.19
BZ 62@ BZ 63 h=1.30, H=1.50 78.86
BZ 134@ BZ 65 h=1.60, H=1.40 77.83
BZ 35 @ BZ 36 h=1.60, H=1.40 68.28
BZ 37 @ BZ 30 h=2.95, H=2.43 23.86
BZ 30 @ BZ 31 h=2.43, H=2.60 21.63
BZ 28 @ BZ 37 h=1.40, H=2.95 68.03
BZ32@ BZ 31 h=1.20, H=2.60 10.88
BZ 128@ BZ 37 h=1.40, H=2.95 61.04
BZ 63@ BZ 66 h=1.50, H=1.30 60.08
BZ 65@ BZ 66A h=1.40, H=1.40 47.54
BZ 66A@ BZ 66 h=1.40, H=1.30 49.04
BZ 66@ BZ 55 h=1.30, H=1.20 18.92
BZ 55@ BZ 69 h=1.20, H=3.20 43.83
BZ 67@ BZ 68 h=1.60, H=1.80 58.00
BZ 68@ BZ 68A h=1.80, H=1.40 50.59
BZ 68A@ BZ 69 h=1.40, H=3.20 6.93
BZ 69@ BZ 8 h=3.20, H=1.40 34.17
ACHICARI - HUASALÓN
BZ_P1 @ BZ_P2 h=1.20, h=1.20 16.54
BZ_P2 @ BZ_P3 h=1.20, h=1.20 16.21
BZ_P3 @ BZ_P4 h=1.20, h=1.20 16.28
BZ_P4 @ BZ_P5 h=1.20, h=1.20 20.69
BZ_P5 @ BZ_P6 h=1.20, h=1.20 54.51
BZ_P6 @ BZ_P7 h=1.20, h=1.20 39.96
BZ_P7 @ BZ_P8 h=1.20, h=1.20 22.62
BZ_P8 @ BZ_P9 h=1.20, h=1.20 11.74
BZ_P9 @ BZ_P10 h=1.20, h=1.20 31.57
BZ_P10 @ BZ_P11 h=1.20, h=1.20 12.36
BZ_P11 @ BZ_P12 h=1.20, h=1.20 14.37
BZ_P12 @ BZ_P13 h=1.20, h=1.20 23.58
BZ_P13 @ BZ_P14 h=1.20, h=1.20 47.82
BZ_P14 @ BZ_P15 h=1.20, h=1.20 17.13
BZ_P15 @ BZ_P16 h=1.20, h=1.20 35.88
BZ_P16 @ BZ_P17 h=1.20, h=1.20 23.51
BZ_P17 @ BZ_P18 h=1.20, h=1.20 9.13
BZ_P18 @ BZ_P19 h=1.20, h=1.20 10.09
BZ_P19 @ BZ_P20 h=1.20, h=1.20 35.04
BZ_P20 @ BZ_P21 h=1.20, h=1.20 43.61
BZ_P21 @ BZ_P22 h=1.20, h=1.20 38.07
BZ_P22 @ BZ_P23 h=1.20, h=1.20 33.98
BZ_P23 @ BZ_P24 h=1.20, h=1.20 34.81
CHICHILIN
BZCHI 75 @ BZCHI 76 h=1.20, h=2.00 31.69
BZCHI 76 @ BZCHI 77 h=2.00, h=2.85 37.29
BZCHI 77 @ BZCHI 78 h=2.85, h=1.40 36.98
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 76.06
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 22.61
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.75
12.02.04.03 PRUEBA HIDRAULICA PARCIAL A ZANJA DESCUBIERTA DE TUBERIA PVC/ISO 4435 m 2,829.96 1.99 5,631.62
COGRI
BZ 36@ BZ 127 h=1.40, H=1.40 63.10
BZ 127@ BZ 128 h=1.40, H=1.40 39.76
BZ 38@ BZ 39 h=1.50, H=1.50 68.54
BZ 39@ BZ 41 h=1.50, H=1.30 64.74
BZ 41@ BZ 36 h=1.30, H=1.30 50.62
BZ 36@ BZ 42 h=1.30, H=1.20 50.62
BZ42@ BZ 32 h=1.20, H=1.20 18.63
BZ 27 @ BZ 28 h=1.20, H=1.40 62.61
BZ 46 @ BZ 47 h=1.30, H=1.20 51.79
BZ 504@ BZ 49 h=1.30, H=1.40 14.35
BZ 49@ BZ 49A h=1.40, H=1.40 26.04
BZ 49A@ BZ 50 h=1.40, H=1.40 48.78
BZ 50@ BZ 51 h=1.40, H=1.40 47.37
BZ 61@ BZ 133 h=1.30, H=1.30 40.07
BZ 133@ BZ 62 h=1.30, H=1.30 39.19
BZ 62@ BZ 63 h=1.30, H=1.50 78.86
BZ 134@ BZ 65 h=1.60, H=1.40 77.83
BZ 35 @ BZ 36 h=1.60, H=1.40 68.28
BZ 37 @ BZ 30 h=2.95, H=2.43 23.86
BZ 30 @ BZ 31 h=2.43, H=2.60 21.63
BZ 28 @ BZ 37 h=1.40, H=2.95 68.03
BZ32@ BZ 31 h=1.20, H=2.60 10.88
BZ 128@ BZ 37 h=1.40, H=2.95 61.04
BZ 63@ BZ 66 h=1.50, H=1.30 60.08
BZ 65@ BZ 66A h=1.40, H=1.40 47.54
BZ 66A@ BZ 66 h=1.40, H=1.30 49.04
BZ 66@ BZ 55 h=1.30, H=1.20 18.92
BZ 55@ BZ 69 h=1.20, H=3.20 43.83
BZ 67@ BZ 68 h=1.60, H=1.80 58.00
BZ 68@ BZ 68A h=1.80, H=1.40 50.59
BZ 68A@ BZ 69 h=1.40, H=3.20 6.93
BZ 69@ BZ 8 h=3.20, H=1.40 34.17
ACHICARI - HUASALÓN
BZ_P1 @ BZ_P2 h=1.20, h=1.20 16.54
BZ_P2 @ BZ_P3 h=1.20, h=1.20 16.21
BZ_P3 @ BZ_P4 h=1.20, h=1.20 16.28
BZ_P4 @ BZ_P5 h=1.20, h=1.20 20.69
BZ_P5 @ BZ_P6 h=1.20, h=1.20 54.51
BZ_P6 @ BZ_P7 h=1.20, h=1.20 39.96
BZ_P7 @ BZ_P8 h=1.20, h=1.20 22.62
BZ_P8 @ BZ_P9 h=1.20, h=1.20 11.74
BZ_P9 @ BZ_P10 h=1.20, h=1.20 31.57
BZ_P10 @ BZ_P11 h=1.20, h=1.20 12.36
BZ_P11 @ BZ_P12 h=1.20, h=1.20 14.37
BZ_P12 @ BZ_P13 h=1.20, h=1.20 23.58
BZ_P13 @ BZ_P14 h=1.20, h=1.20 47.82
BZ_P14 @ BZ_P15 h=1.20, h=1.20 17.13
BZ_P15 @ BZ_P16 h=1.20, h=1.20 35.88
BZ_P16 @ BZ_P17 h=1.20, h=1.20 23.51
BZ_P17 @ BZ_P18 h=1.20, h=1.20 9.13
BZ_P18 @ BZ_P19 h=1.20, h=1.20 10.09
BZ_P19 @ BZ_P20 h=1.20, h=1.20 35.04
BZ_P20 @ BZ_P21 h=1.20, h=1.20 43.61
BZ_P21 @ BZ_P22 h=1.20, h=1.20 38.07
BZ_P22 @ BZ_P23 h=1.20, h=1.20 33.98
BZ_P23 @ BZ_P24 h=1.20, h=1.20 34.81
CHICHILIN
BZCHI 75 @ BZCHI 76 h=1.20, h=2.00 31.69
BZCHI 76 @ BZCHI 77 h=2.00, h=2.85 37.29
BZCHI 77 @ BZCHI 78 h=2.85, h=1.40 36.98
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 76.06
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 22.61
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.75
12.02.04.04 PRUEBA HIDRAULICA FINAL A ZANJA TAPADA DE TUBERIA PVC/ISO 4435 DN=200M m 2,829.96 1.99 5,631.62
COGRI
BZ 36@ BZ 127 h=1.40, H=1.40 63.10
BZ 127@ BZ 128 h=1.40, H=1.40 39.76
BZ 38@ BZ 39 h=1.50, H=1.50 68.54
BZ 39@ BZ 41 h=1.50, H=1.30 64.74
BZ 41@ BZ 36 h=1.30, H=1.30 50.62
BZ 36@ BZ 42 h=1.30, H=1.20 50.62
BZ42@ BZ 32 h=1.20, H=1.20 18.63
BZ 27 @ BZ 28 h=1.20, H=1.40 62.61
BZ 46 @ BZ 47 h=1.30, H=1.20 51.79
BZ 504@ BZ 49 h=1.30, H=1.40 14.35
BZ 49@ BZ 49A h=1.40, H=1.40 26.04
BZ 49A@ BZ 50 h=1.40, H=1.40 48.78
BZ 50@ BZ 51 h=1.40, H=1.40 47.37
BZ 61@ BZ 133 h=1.30, H=1.30 40.07
BZ 133@ BZ 62 h=1.30, H=1.30 39.19
BZ 62@ BZ 63 h=1.30, H=1.50 78.86
BZ 134@ BZ 65 h=1.60, H=1.40 77.83
BZ 35 @ BZ 36 h=1.60, H=1.40 68.28
BZ 37 @ BZ 30 h=2.95, H=2.43 23.86
BZ 30 @ BZ 31 h=2.43, H=2.60 21.63
BZ 28 @ BZ 37 h=1.40, H=2.95 68.03
BZ32@ BZ 31 h=1.20, H=2.60 10.88
BZ 128@ BZ 37 h=1.40, H=2.95 61.04
BZ 63@ BZ 66 h=1.50, H=1.30 60.08
BZ 65@ BZ 66A h=1.40, H=1.40 47.54
BZ 66A@ BZ 66 h=1.40, H=1.30 49.04
BZ 66@ BZ 55 h=1.30, H=1.20 18.92
BZ 55@ BZ 69 h=1.20, H=3.20 43.83
BZ 67@ BZ 68 h=1.60, H=1.80 58.00
BZ 68@ BZ 68A h=1.80, H=1.40 50.59
BZ 68A@ BZ 69 h=1.40, H=3.20 6.93
BZ 69@ BZ 8 h=3.20, H=1.40 34.17
ACHICARI - HUASALÓN
BZ_P1 @ BZ_P2 h=1.20, h=1.20 16.54
BZ_P2 @ BZ_P3 h=1.20, h=1.20 16.21
BZ_P3 @ BZ_P4 h=1.20, h=1.20 16.28
BZ_P4 @ BZ_P5 h=1.20, h=1.20 20.69
BZ_P5 @ BZ_P6 h=1.20, h=1.20 54.51
BZ_P6 @ BZ_P7 h=1.20, h=1.20 39.96
BZ_P7 @ BZ_P8 h=1.20, h=1.20 22.62
BZ_P8 @ BZ_P9 h=1.20, h=1.20 11.74
BZ_P9 @ BZ_P10 h=1.20, h=1.20 31.57
BZ_P10 @ BZ_P11 h=1.20, h=1.20 12.36
BZ_P11 @ BZ_P12 h=1.20, h=1.20 14.37
BZ_P12 @ BZ_P13 h=1.20, h=1.20 23.58
BZ_P13 @ BZ_P14 h=1.20, h=1.20 47.82
BZ_P14 @ BZ_P15 h=1.20, h=1.20 17.13
BZ_P15 @ BZ_P16 h=1.20, h=1.20 35.88
BZ_P16 @ BZ_P17 h=1.20, h=1.20 23.51
BZ_P17 @ BZ_P18 h=1.20, h=1.20 9.13
BZ_P18 @ BZ_P19 h=1.20, h=1.20 10.09
BZ_P19 @ BZ_P20 h=1.20, h=1.20 35.04
BZ_P20 @ BZ_P21 h=1.20, h=1.20 43.61
BZ_P21 @ BZ_P22 h=1.20, h=1.20 38.07
BZ_P22 @ BZ_P23 h=1.20, h=1.20 33.98
BZ_P23 @ BZ_P24 h=1.20, h=1.20 34.81
CHICHILIN
BZCHI 75 @ BZCHI 76 h=1.20, h=2.00 31.69
BZCHI 76 @ BZCHI 77 h=2.00, h=2.85 37.29
BZCHI 77 @ BZCHI 78 h=2.85, h=1.40 36.98
BZCHI 78 @ BZCHI 79 h=1.40, h=1.40 74.85
BZCHI 79 @ BZCHI 80 h=1.40, h=1.40 74.30
BZCHI 80 @ BZCHI 81 h=1.40, h=1.40 24.69
BZCHI 81 @ BZCHI 82 h=1.40, h=1.40 20.24
BZCHI 82 @ BZCHI 83 h=1.40, h=1.40 76.06
BZCHI 83 @ BZCHI 84 h=1.40, h=1.40 22.61
BZCHI 84 @ BZCHI 85 h=1.40, h=1.40 47.48
BZCHI 85 @ BZCHI 86 h=1.40, h=1.40 22.91
BZCHI 86 @ BZCHI 87 h=1.40, h=1.40 60.93
BZCHI 87 @ BZCHI 88 h=1.40, h=1.40 43.00
BZCHI 88 @ BZCHI 89 h=1.40, h=1.40 44.51
BZCHI 89 @ BZCHI 90 h=1.40, h=1.40 15.79
BZCHI 90 @ BZCHI 91 h=1.40, h=1.40 26.07
BZCHI 91 @ BZCHI 92 h=1.40, h=1.40 16.23
BZCHI 92 @ BZCHI 93 h=1.40, h=1.40 45.36
BZCHI 93 @ BZ 974 h=1.40, h=1.40 33.75
COGRI
BZ-40 h=1.4 1.00
BZ-45 h=1.2 1.00
BZ-44 h=1.4 1.00
BZ-46 h=1.3 1.00
BZ-47 h=1.2 1.00
BZ-48 h=1.2 1.00
BZ-125 h=1.2 1.00
BZ-49 h=1.4 1.00
BZ-49A h=1.4 1.00
BZ-50 h=1.4 1.00
BZ-51 h=1.40 1.00
BZ-61 h=1.30 1.00
BZ-133 h=1.30 1.00
BZ-62 h=1.30 1.00
BZ-63 h=1.50 1.00
BZ-65 h=1.40 1.00
BZ-66A h=1.40 1.00
BZ-66 h=1.30 1.00
BZ-68A h=1.40 1.00
BZ-55 h=1.2 1.00
BZ-62 h=1.30 1.00
BZ-55 h=1.20 1.00
BZ-68A h=1.40 1.00
BZ-8 h=1.40 1.00
ACHICARI - HUASALÓN
BZ_P1 h=1.20 1.00
BZ_P2 h=1.20 1.00
BZ_P3 h=1.20 1.00
BZ_P4 h=1.20 1.00
BZ_P5 h=1.20 1.00
BZ_P6 h=1.20 1.00
BZ_P7 h=1.20 1.00
BZ_P8 h=1.20 1.00
BZ_P9 h=1.20 1.00
BZ_P10 h=1.20 1.00
BZ_P11 h=1.20 1.00
BZ_P12 h=1.20 1.00
BZ_P13 h=1.20 1.00
BZ_P14 h=1.20 1.00
BZ_P15 h=1.20 1.00
BZ_P16 h=1.20 1.00
BZ_P17 h=1.20 1.00
BZ_P18 h=1.20 1.00
BZ_P19 h=1.20 1.00
BZ_P20 h=1.20 1.00
BZ_P21 h=1.20 1.00
BZ_P22 h=1.20 1.00
BZ_P23 h=1.20 1.00
BZ_P24 h=1.20 1.00
CHICHILIN
BZCHI 78 h=1.40 1.00
BZCHI 79 h=1.40 1.00
BZCHI 80 h=1.40 1.00
BZCHI 81 h=1.40 1.00
BZCHI 82 h=1.40 1.00
BZCHI 83 h=1.40 1.00
BZCHI 84 h=1.40 1.00
BZCHI 85 h=1.40 1.00
BZCHI 86 h=1.40 1.00
BZCHI 87 h=1.40 1.00
BZCHI 88 h=1.40 1.00
BZCHI 89 h=1.40 1.00
BZCHI 90 h=1.40 1.00
BZCHI 91 h=1.40 1.00
BZCHI 92 h=1.40 1.00
BZCHI 93 h=1.40 1.00
BZ 974 h=1.40 1.00
12.02.05.02 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=2.00M und 4.00 128.83 515.32
COGRI
BZ-134 h=1.60 1.00
BZ-67 h=1.60 1.00
BZ-68 h=1.80 1.00
CHICHILIN
BZCHI 76 h=2.00 1.00
12.02.05.03 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=2.50M und 1.00 141.74 141.74
COGRI
BZ - 30 H 2.43 1.00
12.02.05.04 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=3.00M und 3.00 157.48 472.44
COGRI
BZ-31 h=2.60 1.00
BZ-37 h=2.95 1.00
CHICHILIN
BZCHI 77 h=2.85 1.00
12.02.05.05 EXCAVACION BUZON, Dexc.=1.60M, HASTA H=3.50M und 1.00 177.17 177.17
COGRI
BZ-69 h=3.20 1.00
COGRI
BZ-40 h=1.4 1.00
BZ-45 h=1.2 1.00
BZ-44 h=1.4 1.00
BZ-46 h=1.3 1.00
BZ-47 h=1.2 1.00
BZ-48 h=1.2 1.00
BZ-125 h=1.2 1.00
BZ-49 h=1.4 1.00
BZ-49A h=1.4 1.00
BZ-50 h=1.4 1.00
BZ-51 h=1.40 1.00
BZ-61 h=1.30 1.00
BZ-133 h=1.30 1.00
BZ-62 h=1.30 1.00
BZ-63 h=1.50 1.00
BZ-65 h=1.40 1.00
BZ-66A h=1.40 1.00
BZ-66 h=1.30 1.00
BZ-68A h=1.40 1.00
BZ-55 h=1.2 1.00
BZ-62 h=1.30 1.00
BZ-55 h=1.20 1.00
BZ-68A h=1.40 1.00
BZ-8 h=1.40 1.00
ACHICARI - HUASALÓN
BZ_P1 h=1.20 1.00
BZ_P2 h=1.20 1.00
BZ_P3 h=1.20 1.00
BZ_P4 h=1.20 1.00
BZ_P5 h=1.20 1.00
BZ_P6 h=1.20 1.00
BZ_P7 h=1.20 1.00
BZ_P8 h=1.20 1.00
BZ_P9 h=1.20 1.00
BZ_P10 h=1.20 1.00
BZ_P11 h=1.20 1.00
BZ_P12 h=1.20 1.00
BZ_P13 h=1.20 1.00
BZ_P14 h=1.20 1.00
BZ_P15 h=1.20 1.00
BZ_P16 h=1.20 1.00
BZ_P17 h=1.20 1.00
BZ_P18 h=1.20 1.00
BZ_P19 h=1.20 1.00
BZ_P20 h=1.20 1.00
BZ_P21 h=1.20 1.00
BZ_P22 h=1.20 1.00
BZ_P23 h=1.20 1.00
BZ_P24 h=1.20 1.00
CHICHILIN
BZCHI 78 h=1.40 1.00
BZCHI 79 h=1.40 1.00
BZCHI 80 h=1.40 1.00
BZCHI 81 h=1.40 1.00
BZCHI 82 h=1.40 1.00
BZCHI 83 h=1.40 1.00
BZCHI 84 h=1.40 1.00
BZCHI 85 h=1.40 1.00
BZCHI 86 h=1.40 1.00
BZCHI 87 h=1.40 1.00
BZCHI 88 h=1.40 1.00
BZCHI 89 h=1.40 1.00
BZCHI 90 h=1.40 1.00
BZCHI 91 h=1.40 1.00
BZCHI 92 h=1.40 1.00
BZCHI 93 h=1.40 1.00
BZ 974 h=1.40 1.00
12.02.06.02 CONSTRUCCION DE BUZONES DN=1.20M, H=1.51 @2.00m Und 4.00 1,669.55 6,678.20
COGRI
BZ-134 h=1.60 1.00
BZ-67 h=1.60 1.00
BZ-68 h=1.80 1.00
CHICHILIN
BZCHI 76 h=2.00 1.00
12.02.06.03 CONSTRUCCION DE BUZONES DN=1.20M, H=2.01 @2.50m Und 1.00 1,646.94 1,646.94
COGRI
BZ - 30 H 2.43 1.00
12.02.06.04 CONSTRUCCION DE BUZONES DN=1.20M, H=2.51 @3.00m Und 3.00 1,951.04 5,853.12
COGRI
BZ-31 h=2.60 1.00
BZ-37 h=2.95 1.00
CHICHILIN
BZCHI 77 h=2.85 1.00
12.02.06.05 CONSTRUCCION DE BUZONES DN=1.20M, H=3.01 @3.50m Und 1.00 3,296.84 3,296.84
COGRI
BZ-69 h=3.20 1.00
12.03.03 RELLENO COMPACTADO CON MAT PROPIO, P/DESAGUE m 6.00 10.15 9,987.60
12.03.04 SUMINISTRO DE TUBERIA ISO 4435 S-20 DN160MM U/F m 6.00 19.40 19,089.60
12.03.05 CONEXION DOMICILIARIA INC/TODOS LOS ACCESORIOS und 164.00 365.95 60,015.80
PPTO - COGRI (SISTEMA DE ALCANTARILLADO) S/. 262,795.89
2 3 3 3 3 3 4
1 EXCAVACION PARA BUZON UND
BZ 44, BZ 46 BZ 47, BZ 61, BZ 133 BZ 62, BZ 63, BZ 66 BZ 134, BZ 65, BZ 66A BZ 55, BZ 69, BZ 67 BZ 68, BZ 68A, BZ 8 BZ 49,BZ 49A, BZ 50, BZ 51
2 3 3 3 3 3 4
PERFILADO DE EXCAVACION PARA
2 UND
BUZON
BZ 44, BZ 46 BZ 47, BZ 61, BZ 133 BZ 62, BZ 63, BZ 66 BZ 134, BZ 65, BZ 66A BZ 55, BZ 69, BZ 67 BZ 68, BZ 68A, BZ 8 BZ 49,BZ 49A, BZ 50, BZ 51
2 3 3 3 3 3 4
3 VACIADO DE PISO PARA BUZON UND
BZ 44, BZ 46 BZ 47, BZ 61, BZ 133 BZ 62, BZ 63, BZ 66 BZ 134, BZ 65, BZ 66A BZ 55, BZ 69, BZ 67 BZ 68, BZ 68A, BZ 8 BZ 49,BZ 49A, BZ 50, BZ 51
1 1 2 1 2 3 3 3 3 3 4
4 ENCOFRADO DE CUERPO PARA BUZON UND
Bz 37 Bz 32 Bz 42, Bz 38 Bz 30 BZ 44, BZ 46 BZ 47, BZ 61, BZ 133 BZ 62, BZ 63, BZ 66 BZ 134, BZ 65, BZ 66A BZ 55, BZ 69, BZ 67 BZ 68, BZ 68A, BZ 8 BZ 49,BZ 49A, BZ 50, BZ 51
1 1 2 1 2 3 3 3 3 3 4
5 VACIADO DE CUERPO PARA BUZON UND
Bz 37 Bz 32 Bz 42, Bz 38 Bz 30 BZ 44, BZ 46 BZ 47, BZ 61, BZ 133 BZ 62, BZ 63, BZ 66 BZ 134, BZ 65, BZ 66A BZ 55, BZ 69, BZ 67 BZ 68, BZ 68A, BZ 8 BZ 49,BZ 49A, BZ 50, BZ 51
1 1 2 1 2 3 3 3 3 3 4
DESENCOFRADO DE CUERPO PARA
6 UND
BUZON Bz 37 Bz 32 Bz 42, Bz 38 Bz 30 BZ 44, BZ 46 BZ 47, BZ 61, BZ 133 BZ 62, BZ 63, BZ 66 BZ 134, BZ 65, BZ 66A BZ 55, BZ 69, BZ 67 BZ 68, BZ 68A, BZ 8 BZ 49,BZ 49A, BZ 50, BZ 51
1 1 2 1 2 3 3 3 3 3 4
7 SOLAQUEO DE CUERPO DE BUZON UND
Bz 37 Bz 32 Bz 42, Bz 38 Bz 30 BZ 44, BZ 46 BZ 47, BZ 61, BZ 133 BZ 62, BZ 63, BZ 66 BZ 134, BZ 65, BZ 66A BZ 55, BZ 69, BZ 67 BZ 68, BZ 68A, BZ 8 BZ 49,BZ 49A, BZ 50, BZ 51
103.75 129.58 115.36 130.64 93.11 105.92 127.06 118.05 137.91 115.5 101.83 106.04 122.19
EXCAVACIÓN DE ZANJA PARA TUBERIA
8 ML
200 MM BZ 36@BZ 42, BZ 37@BZ 30, BZ BZ 35@BZ 39, BZ 46@BZ 47, BZ
Bz 34@ Bz 28, Bz 127@ Bz 128 Bz 128@BZ 37, Bz 38@Bz 39 Bz 39@BZ 36 BZ 27@BZ 37 BZ 41@ BZ 127, BZ 127@BZ 34 BZ 133@BZ 63 BZ 63@ BZ 66, BZ 134@BZ65 BZ 66A@BZ 66, BZ 66@BZ 69 BZ 55@BZ 69, BZ 67@BZ 68 BZ 68@BZ 8, BZ 504@BZ 49 BZ49 @ BZ 51
42@ BZ 32 61@BZ 133
103.75 129.58 115.36 130.64 93.11 105.92 127.06 118.05 137.91 115.5 101.83 106.04 122.19
REFINE Y NIVELACIÓN DE ZANJA T.
9 ML
NORMAL, P/ DESAGÜE BZ 36@BZ 42, BZ 37@BZ 30, BZ BZ 35@BZ 39, BZ 46@BZ 47, BZ
Bz 34@ Bz 28, Bz 127@ Bz 128 Bz 128@BZ 37, Bz 38@Bz 39 Bz 39@BZ 36 BZ 27@BZ 37 BZ 41@ BZ 127, BZ 127@BZ 34 BZ 133@BZ 63 BZ 63@ BZ 66, BZ 134@BZ65 BZ 66A@BZ 66, BZ 66@BZ 69 BZ 55@BZ 69, BZ 67@BZ 68 BZ 68@BZ 8, BZ 504@BZ 49 BZ49 @ BZ 51
42@ BZ 32 61@BZ 133
103.75 129.58 115.36 130.64 93.11 105.92 127.06 118.05 137.91 115.5 101.83 106.04 122.19
CAMA DE ARENA EN ZANJA H=0.10 A
10 ML
H=0.60 BZ 36@BZ 42, BZ 37@BZ 30, BZ BZ 35@BZ 39, BZ 46@BZ 47, BZ
Bz 34@ Bz 28, Bz 127@ Bz 128 Bz 128@BZ 37, Bz 38@Bz 39 Bz 39@BZ 36 BZ 27@BZ 37 BZ 41@ BZ 127, BZ 127@BZ 34 BZ 133@BZ 63 BZ 63@ BZ 66, BZ 134@BZ65 BZ 66A@BZ 66, BZ 66@BZ 69 BZ 55@BZ 69, BZ 67@BZ 68 BZ 68@BZ 8, BZ 504@BZ 49 BZ49 @ BZ 51
42@ BZ 32 61@BZ 133
103.75 129.58 115.36 130.64 93.11 105.92 127.06 118.05 137.91 115.5 101.83 106.04 122.19
103.75 129.58 115.36 130.64 93.11 105.92 127.06 118.05 137.91 115.5 101.83 106.04 122.19
3 3 3 3 2 3 3 3 3 3 3 3 3
14 EMBOQUILLADO UND
Bz 35A, Bz 33, Bz 33A Bz 36, Bz 127, Bz 34 BZ 129, BZ 28, BZ 27 BZ 24, Bz 25, Bz 37 BZ 36, BZ 128 BZ 39, BZ 38, BZ 35 BZ 30, BZ32, BZ 42 BZ 41, BZ 44, Bz 46 Bz 61, Bz 133, Bz 62 Bz 63, Bz 66, 134 Bz 65, Bz 65A, Bz 67 Bz 68, Bz 68A, Bz 69 Bz 49, Bz 61, Bz 50, Bz 51
3 3 3 3 2 3 3 3 3 3 3 3 3
13 VACIADO DE 1/2 CAÑA UND
Bz 35A, Bz 33, Bz 33A Bz 36, Bz 127, Bz 34 BZ 129, BZ 28, BZ 27 BZ 24, Bz 25, Bz 37 BZ 36, BZ 128 BZ 39, BZ 38, BZ 35 BZ 30, BZ32, BZ 42 BZ 41, BZ 44, Bz 46 Bz 61, Bz 133, Bz 62 Bz 63, Bz 66, 134 Bz 65, Bz 65A, Bz 67 Bz 68, Bz 68A, Bz 69 Bz 49, Bz 61, Bz 50, Bz 51
10 16 11 14 7 1 5 16 18 11 12 16 10 7 10
EXCAVACION DE ZANJA PARA
15 UND
CONEXIONES DOMICILIARIAS H10, G8, H9, G9, G7, G8, G9, G 10,G11, G12,G1, E8, E7, E6, E5, C5, C6, C7, C8, B5, B6, B7, B8, B9, B10, B11, B12, C11, A15,A14,A13,A12,B1,B2,B3,B4,
A19, A18, A17, A15, B20, B19, B18 E4 B17,B16,B15,B14,B13 A1,A2,A3
G2,G3,G4,G5,G6,E2,E3 H10,H9,H8,H7,H6,H5,H4,H3,H2 C13, C12 C10, C9, A23, A22, A21, A20 H14,H13,H12,11,C1,C2,C3,C4
10 16 11 14 7 1 5 16 18 11 12 16 10 7 10
REFINE DE ZANJA PARA CONEXIONES
16 UND
DOMICILIARIAS H10, G8, H9, G9, G7, G8, G9, G 10,G11, G12,G1, E8, E7, E6, E5, C5, C6, C7, C8, B5, B6, B7, B8, B9, B10, B11, B12, C11, A15,A14,A13,A12,B1,B2,B3,B4,
A19, A18, A17, A15, B20, B19, B18 E4 B17,B16,B15,B14,B13 A1,A2,A3 0 0 0 0 0 0
G2,G3,G4,G5,G6,E2,E3 H10,H9,H8,H7,H6,H5,H4,H3,H2 C13, C12 C10, C9, A23, A22, A21, A20 H14,H13,H12,11,C1,C2,C3,C4
10 16 11 14 7 1 5 16 18 11 12 16 10 7 10
10 16 11 14 7 1 5 16 18 11 12 16 10 7 10
SUMINISTRO DE TUBERIA PARA
18 UND
CONEXIONES DOMICILIARIAS H10, G8, H9, G9, G7, G8, G9, G 10,G11, G12,G1, E8, E7, E6, E5, C5, C6, C7, C8, B5, B6, B7, B8, B9, B10, B11, B12, C11, A15,A14,A13,A12,B1,B2,B3,B4,
A19, A18, A17, A15, B20, B19, B18 E4 B17,B16,B15,B14,B13 A1,A2,A3 0 0 0 0 0 0
G2,G3,G4,G5,G6,E2,E3 H10,H9,H8,H7,H6,H5,H4,H3,H2 C13, C12 C10, C9, A23, A22, A21, A20 H14,H13,H12,11,C1,C2,C3,C4
10 16 11 14 7 1 5 16 18 11 12 16 10 7 10
142.03 103.75 129.58 115.36 130.64 93.11 105.92 127.06 118.05 137.91 115.5 101.83 106.04 122.19
142.03 103.75 129.58 115.36 130.64 93.11 105.92 127.06 118.05 137.91 115.5 101.83 106.04 122.19
RELLENO PROTECTOR C/MAT. PROPIO
21 ML
P/TUB 200MM BZ 36@BZ 42, BZ 37@BZ 30, BZ BZ 35@BZ 39, BZ 46@BZ 47, BZ
Bz 35A@ Bz 34 Bz 34@ Bz 28, Bz 127@ Bz 128 Bz 128@BZ 37, Bz 38@Bz 39 Bz 39@BZ 36 BZ 27@BZ 37 BZ 41@ BZ 127, BZ 127@BZ 34 BZ 133@BZ 63 BZ 63@ BZ 66, BZ 134@BZ65 BZ 66A@BZ 66, BZ 66@BZ 69 BZ 55@BZ 69, BZ 67@BZ 68 BZ 68@BZ 8, BZ 504@BZ 49 BZ49 @ BZ 51
42@ BZ 32 61@BZ 133
11 14 7 1 5 16 18 11 12 16 10 7 10
142.03 103.75 129.58 115.36 130.64 93.11 105.92 127.06 118.05 137.91 115.5 101.83 106.04 122.19
10 16 11 14 7 1 5 16 18 11 12 16 10 7 10
3 3 3 3 2 3 3 3 3 3 3 3 3
26 ENCOFRADO DE TAPA DE BUZON UND
Bz 35A, Bz 33, Bz 33A Bz 36, Bz 127, Bz 34 BZ 129, BZ 28, BZ 27 BZ 24, Bz 25, Bz 37 BZ 36, BZ 128 BZ 39, BZ 38, BZ 35 BZ 30, BZ32, BZ 42 BZ 41, BZ 44, Bz 46 Bz 61, Bz 133, Bz 62 Bz 63, Bz 66, 134 Bz 65, Bz 65A, Bz 67 Bz 68, Bz 68A, Bz 69 Bz 49, Bz 61, Bz 50, Bz 51
3 3 3 3 2 3 3 3 3 3 3 3 3
27 VACIADO DE TAPA DE BUZON UND
Bz 35A, Bz 33, Bz 33A Bz 36, Bz 127, Bz 34 BZ 129, BZ 28, BZ 27 BZ 24, Bz 25, Bz 37 BZ 36, BZ 128 BZ 39, BZ 38, BZ 35 BZ 30, BZ32, BZ 42 BZ 41, BZ 44, Bz 46 Bz 61, Bz 133, Bz 62 Bz 63, Bz 66, 134 Bz 65, Bz 65A, Bz 67 Bz 68, Bz 68A, Bz 69 Bz 49, Bz 61, Bz 50, Bz 51
3 3 3 3 2 3 3 3 3 3 3 3 3
28 DESENCOFRADO DE TAPA DE BUZON UND
Bz 35A, Bz 33, Bz 33A Bz 36, Bz 127, Bz 34 BZ 129, BZ 28, BZ 27 BZ 24, Bz 25, Bz 37 BZ 36, BZ 128 BZ 39, BZ 38, BZ 35 BZ 30, BZ32, BZ 42 BZ 41, BZ 44, Bz 46 Bz 61, Bz 133, Bz 62 Bz 63, Bz 66, 134 Bz 65, Bz 65A, Bz 67 Bz 68, Bz 68A, Bz 69 Bz 49, Bz 61, Bz 50, Bz 51
10 16 11 14 7 1 5 16 18 11 12 16 10 7 10
10 16 11 14 7 1 5 16 18 11 12 16 10 7 10
10 16 11 14 7 1 5 16 18 11 12 16 10 7 10
10 16 11 14 7 1 5 16 18 11 12 16 10 7 10
10 16 11 14 7 1 5 16 18 11 12 16 10 7 10
DESENCOFRADO DE LOSA DE
33 UND
CONCRETO PARA CAJA DE DESAGUE H10, G8, H9, G9, G7, G8, G9, G 10,G11, G12,G1, E8, E7, E6, E5, C5, C6, C7, C8, B5, B6, B7, B8, B9, B10, B11, B12, C11, A15,A14,A13,A12,B1,B2,B3,B4,
A19, A18, A17, A15, B20, B19, B18 E4 B17,B16,B15,B14,B13 A1,A2,A3 0 0 0 0 0 0
G2,G3,G4,G5,G6,E2,E3 H10,H9,H8,H7,H6,H5,H4,H3,H2 C13, C12 C10, C9, A23, A22, A21, A20 H14,H13,H12,11,C1,C2,C3,C4
PLANIFICACION SETIEMBRE 2021
PROYECTO : "MEJORAMIENTO DE LOS SISTEMAS DE AGUA PARA CONSUMO HUMANO Y ALCANTARILLADO EN OMATE Y ANEXOS, DISTRITO DE OMATE, PROVINCIA GENERAL SANCHEZ CERRO - MOQUEGUA"
CUADRILLA : 05 OPERARIOS Y 09 PEONES
MONTO : S/. 162,401.74
SEMANA N°01 SEMANA N°02 SEMANA N°03 SEMANA N°04 SEMANA N°05
ITEM ACTIVIDADES UNIDAD
9/1/2021 9/2/2021 9/3/2021 9/4/2021 9/6/2021 9/7/2021 9/8/2021 9/9/2021 9/10/2021 9/11/2021 9/13/2021 9/14/2021 9/15/2021 9/16/2021 9/17/2021 9/18/2021 9/20/2021 9/21/2021 9/22/2021 9/23/2021 9/24/2021 9/25/2021 9/27/2021 9/28/2021 9/29/2021 9/30/2021
110 100.07 139.94 76.25 131.57 149.8 149.15 142.87 131.32 129.37 95.34
8 EXCAVACIÓN DE ZANJA PARA TUBERIA 200 MM ML
61C @ 62A 62A @ 64A 64A @ 67 67A @ 71 71A @ 74 74 @ 78 78 @ 80 80 @ 84 84 @ 87 87 @ 91 91 @ 974
110 100.07 139.94 76.25 131.57 149.8 149.15 142.87 131.32 129.37 95.34
9 REFINE Y NIVELACIÓN DE ZANJA T. NORMAL, P/ DESAGÜE ML
61C @ 62A 62A @ 64A 64A @ 67 67A @ 71 71A @ 74 74 @ 78 78 @ 80 80 @ 84 84 @ 87 87 @ 91 91 @ 974
110 100.07 139.94 76.25 131.57 149.8 149.15 142.87 131.32 129.37 95.34
10 CAMA DE ARENA EN ZANJA H=0.10 A H=0.60 ML
61C @ 62A 62A @ 64A 64A @ 67 67A @ 71 71A @ 74 74 @ 78 78 @ 80 80 @ 84 84 @ 87 87 @ 91 91 @ 974
110 100.07 139.94 76.25 131.57 149.8 149.15 142.87 131.32 129.37 95.34
11 SUMINISTRO DE TUBERÍA DN 200MM ML
61C @ 62A 62A @ 64A 64A @ 67 67A @ 71 71A @ 74 74 @ 78 78 @ 80 80 @ 84 84 @ 87 87 @ 91 91 @ 974
110 100.07 139.94 76.25 131.57 149.8 149.15 142.87 131.32 129.37 95.34
12 INSTALACIÓN DE TUBERÍA DN 200 MM ML
61C @ 62A 62A @ 64A 64A @ 67 67A @ 71 71A @ 74 74 @ 78 78 @ 80 80 @ 84 84 @ 87 87 @ 91 91 @ 974
8 8
13 VACIADO DE 1/2 CAÑA UND 4 4 4 4 4 4 4
8 8
14 EMBOQUILLADO UND 4 4 4 4 4 4 4
SEMANA N°01 SEMANA N°02 SEMANA N°03 SEMANA N°04 SEMANA N°05
ITEM ACTIVIDADES UNIDAD
9/1/2021 9/2/2021 9/3/2021 9/4/2021 9/6/2021 9/7/2021 9/8/2021 9/9/2021 9/10/2021 9/11/2021 9/13/2021 9/14/2021 9/15/2021 9/16/2021 9/17/2021 9/18/2021 9/20/2021 9/21/2021 9/22/2021 9/23/2021 9/24/2021 9/25/2021 9/27/2021 9/28/2021 9/29/2021 9/30/2021
8 8 6 6 10
1 EXCAVACION PARA BUZON UND
bz420 @ bz413 bz412 @ bz406-B bzA @ bzF bzG @ bz459 bz406_19 @ bz406_28
8 8 6 6 10
2 PERFILADO DE EXCAVACION PARA BUZON UND
bz420 @ bz413 bz412 @ bz406-B bzA @ bzF bzG @ bz459 bz406_19 @ bz406_28
4 4 4 4 6 6 10
3 VACIADO DE PISO PARA BUZON UND
bz420 @ bz417 bz417 @ bz413 bz412 @ bz409 bz409 @ bz406-B bzA @ bzF bzG @ bz459 bz406_19 @ bz406_28
4 4 4 4 4 2 6 5 5
4 ENCOFRADO DE CUERPO PARA BUZON UND
bz420 @ bz417 bz417 @ bz413 bz412 @ bz409 bz409 @ bz406-B bzA @ bzD bzD @ bzF bzG @ bz459 bz406_19 @ bz406_23 bz406_24 @ bz406_28
4 4 4 4 4 2 6 5 5
5 VACIADO DE CUERPO PARA BUZON UND
bz420 @ bz417 bz417 @ bz413 bz412 @ bz409 bz409 @ bz406-B bzA @ bzD bzD @ bzF bzG @ bz459 bz406_19 @ bz406_23 bz406_24 @ bz406_28
4 4 4 4 4 2 6 5 5
6 DESENCOFRADO DE CUERPO PARA BUZON UND
bz420 @ bz417 bz417 @ bz413 bz412 @ bz409 bz409 @ bz406-B bzA @ bzD bzD @ bzF bzG @ bz459 bz406_19 @ bz406_23 bz406_24 @ bz406_28
4 4 4 4 4 2 6 5 5
7 SOLAQUEO DE CUERPO DE BUZON UND
bz420 @ bz417 bz417 @ bz413 bz412 @ bz409 bz409 @ bz406-B bzA @ bzD bzD @ bzF bzG @ bz459 bz406_19 @ bz406_23 bz406_24 @ bz406_28
4 4 4 4 4 2 6 5 5
14 EMBOQUILLADO UND
bz420 @ bz417 bz417 @ bz413 bz412 @ bz409 bz409 @ bz406-B bzA @ bzD bzD @ bzF bzG @ bz459 bz406_19 @ bz406_23 bz406_24 @ bz406_28
5 4 2 2 4 2 4
15 EXCAVACION DE ZANJA PARA CONEXIONES DOMICILIARIAS UND
bz406_6 @ bz406_9 /
bz406_5 @ bz406_6 bzA @ bzD bzD @ bzF bzG @ bz459 bz406_19 @ bz406_23 bz406_24 @ bz406_28
bz406_13 @ bz406_12
5 4 2 2 4 2 4
16 REFINE DE ZANJA PARA CONEXIONES DOMICILIARIAS UND
bz406_6 @ bz406_9 /
bz406_5 @ bz406_6 bzA @ bzD bzD @ bzF bzG @ bz459 bz406_19 @ bz406_23 bz406_24 @ bz406_28
bz406_13 @ bz406_12
5 4 2 2 4 2 4
17 CAMA DE ARENA PARA CONEXIONES DOMICILIARIAS UND
bz406_6 @ bz406_9 /
bz406_5 @ bz406_6 bzA @ bzD bzD @ bzF bzG @ bz459 bz406_19 @ bz406_23 bz406_24 @ bz406_28
bz406_13 @ bz406_12
5 4 2 2 4 2 4
SUMINISTRO DE TUBERIA PARA CONEXIONES
18 UND
DOMICILIARIAS bz406_6 @ bz406_9 /
bz406_5 @ bz406_6 bzA @ bzD bzD @ bzF bzG @ bz459 bz406_19 @ bz406_23 bz406_24 @ bz406_28
bz406_13 @ bz406_12
5 4 2 2 4 2 4
INSTALACION DE TUBERIA PARA CONEXIONES
19 UND
DOMICILIARIAS bz406_6 @ bz406_9 /
bz406_5 @ bz406_6 bzA @ bzD bzD @ bzF bzG @ bz459 bz406_19 @ bz406_23 bz406_24 @ bz406_28
bz406_13 @ bz406_12
76.83 94.41 131.46 118.39 269.9
20 PRUEBA HIDRÁULICA A ZANJA ABIERTA UND
bz406_4 @ bz406 / bz406_6 @ bz406_9 /
bzA @ bzF bzG @ bz459 bz406_19 @ bz406_28
bz406_5 @ bz406_6 bz406_13 @ bz406_12
76.83 94.41 131.46 118.39 269.9
21 RELLENO PROTECTOR C/MAT. PROPIO P/TUB 200MM ML
bz406_4 @ bz406 / bz406_6 @ bz406_9 /
bzA @ bzF bzG @ bz459 bz406_19 @ bz406_28
bz406_5 @ bz406_6 bz406_13 @ bz406_12
5 4 6 4 6
22 RELLENO PROTECTOR PARA CONEXIONES DOMICILIARIAS UND
bz406_4 @ bz406 / bz406_6 @ bz406_9 /
bzA @ bzF bzG @ bz459 bz406_19 @ bz406_28
bz406_5 @ bz406_6 bz406_13 @ bz406_12
76.83 94.41 131.46 118.39 269.9
24 RELLENO Y COMPACTADO C/MAT PROPIO ML
bz406_4 @ bz406 / bz406_6 @ bz406_9 /
bzA @ bzF bzG @ bz459 bz406_19 @ bz406_28
bz406_5 @ bz406_6 bz406_13 @ bz406_12
5 4 6 4 6
RELLENO Y COMPACTADO C/MAT PROPIO CONEXIONES
25 UND
DOMICILIARIAS bz406_4 @ bz406 / bz406_6 @ bz406_9 /
bzA @ bzF bzG @ bz459 bz406_19 @ bz406_28
bz406_5 @ bz406_6 bz406_13 @ bz406_12
4 4 4 4 4 2 6 5 5
26 ENCOFRADO DE TAPA DE BUZON UND
bz420 @ bz417 bz417 @ bz413 bz412 @ bz409 bz409 @ bz406-B bzA @ bzD bzD @ bzF bzG @ bz459 bz406_19 @ bz406_23 bz406_24 @ bz406_28
4 4 4 4 4 2 6 5 5
27 VACIADO DE TAPA DE BUZON UND
bz420 @ bz417 bz417 @ bz413 bz412 @ bz409 bz409 @ bz406-B bzA @ bzD bzD @ bzF bzG @ bz459 bz406_19 @ bz406_23 bz406_24 @ bz406_28
4 4 4 4 6 6 5 5
28 DESENCOFRADO DE TAPA DE BUZON UND
bz420 @ bz417 bz417 @ bz413 bz412 @ bz409 bz409 @ bz406-B bzA @ bzD bzG @ bz459 bz406_19 @ bz406_23 bz406_24 @ bz406_28
5 4 4 4 6
29 EXCAVACION PARA CAJA DE DESAGUE UND
bz406_6 @ bz406_9 /
bz406_5 @ bz406_6 bzA @ bzF bzG @ bz459 bz406_19 @ bz406_28
bz406_13 @ bz406_12
5 4 4 4 6
30 INSTALACION DE CAJA DE DESAGUE UND
bz406_6 @ bz406_9 /
bz406_5 @ bz406_6 bzA @ bzF bzG @ bz459 bz406_19 @ bz406_28
bz406_13 @ bz406_12
5 4 4 4 6
31 ENCOFRADO PARA CAJA DE DESAGUE UND
bz406_6 @ bz406_9 /
bz406_5 @ bz406_6 bzA @ bzF bzG @ bz459 bz406_19 @ bz406_28
bz406_13 @ bz406_12
5 4 4 4 6
32 VACIADO DE LOSA DE CONCRETO PARA CAJA DE DESAGUE UND
bz406_6 @ bz406_9 /
bz406_5 @ bz406_6 bzA @ bzF bzG @ bz459 bz406_19 @ bz406_28
bz406_13 @ bz406_12
5 4 4 4 6
DESENCOFRADO DE LOSA DE CONCRETO PARA CAJA DE
33 UND
DESAGUE bz406_6 @ bz406_9 /
bz406_5 @ bz406_6 bzA @ bzF bzG @ bz459 bz406_19 @ bz406_28
bz406_13 @ bz406_12
PLANIFICACION OCTUBRE 2021
PROYECTO : "MEJORAMIENTO DE LOS SISTEMAS DE AGUA PARA CONSUMO HUMANO Y ALCANTARILLADO EN OMATE Y ANEXOS, DISTRITO DE OMATE, PROVINCIA GENERAL SANCHEZ CERRO - MOQUEGUA"
CUADRILLA : 05 OPERARIO +05 PEONES
MONTO : S/. 140,773.74
SEMANA N°01 SEMANA N°02 SEMANA N°03 SEMANA N°04 SEMANA N°05
ITEM ACTIVIDADES UNIDAD
10/1/2021 10/2/2021 10/4/2021 10/5/2021 10/6/2021 10/7/2021 10/11/2021 10/12/2021 10/13/2021 10/14/2021 10/15/2021 10/16/2021 10/18/2021 10/19/2021 10/20/2021 10/21/2021 10/22/2021 10/23/2021 10/25/2021 10/26/2021 10/27/2021 10/28/2021 10/29/2021 10/30/2021
2 2 2 3 2 3 2 2 2 2 1 2 1 1 1 2
1 EXCAVACION PARA BUZON UND
BZ 784, BZ 783, BZ BZ 780, BZ 781, BZ
BZ 790, BZ 789 BZ 788, BZ 787 BZ 786, BZ 785 BZ 776-Q, BZ 776-52 BZ 840, BZ 841 BZ 842, BZ 843 BZ 844, BZ 845 BZ 846, BZ 847 BZ 848 BZ A-13, BZ A-14 BZ A-15 BZ 16 BZ 17 BZ 18, BZ 19
782 777-11A
2 2 2 3 2 3 2 2 2 2 1 2 1 1 1 2
2 PERFILADO DE EXCAVACION PARA BUZON UND
BZ 784, BZ 783, BZ BZ 780, BZ 781, BZ
BZ 790, BZ 789 BZ 788, BZ 787 BZ 786, BZ 785 BZ 776-Q, BZ 776-52 BZ 840, BZ 841 BZ 842, BZ 843 BZ 844, BZ 845 BZ 846, BZ 847 BZ 848 BZ A-13, BZ A-14 BZ A-15 BZ 16 BZ 17 BZ 18, BZ 19
782 777-11A
2 2 2 3 2 3 2 2 2 2 1 2 1 1 1 2
3 VACIADO DE PISO PARA BUZON UND
BZ 784, BZ 783, BZ BZ 780, BZ 781, BZ
BZ 790, BZ 789 BZ 788, BZ 787 BZ 786, BZ 785 BZ 776-Q, BZ 776-52 BZ 840, BZ 841 BZ 842, BZ 843 BZ 844, BZ 845 BZ 846, BZ 847 BZ 848 BZ A-13, BZ A-14 BZ A-15 BZ 16 BZ 17 BZ 18, BZ 19
782 777-11A
2 2 2 3 2 3 2 2 2 2 1 2 1 1 1 2
2 2 2 3 2 3 2 2 2 2 1 2 1 1 1 2
5 VACIADO DE CUERPO PARA BUZON UND
BZ 784, BZ 783, BZ BZ 780, BZ 781, BZ
BZ 790, BZ 789 BZ 788, BZ 787 BZ 786, BZ 785 BZ 776-Q, BZ 776-52 BZ 840, BZ 841 BZ 842, BZ 843 BZ 844, BZ 845 BZ 846, BZ 847 BZ 848 BZ A-13, BZ A-14 BZ A-15 BZ 16 BZ 17 BZ 18, BZ 19
782 777-11A
2 2 2 3 2 3 2 2 2 2 1 2 1 1 1 2
2 2 2 3 2 3 2 2 2 2 1 2 1 1 1 2
28.36 37.43 30.17 34.67 93.27 93.78 96.23 92.01 73.09 61.54
EXCAVACIÓN DE ZANJA PARA TUBERIA 200
8 ML
MM BZ 790@ BZ 789 BZ 789 @ BZ 787 BZ 787@ BZ 785 BZ 785@ BZ 784 BZ 776-Q @ BZ 780 BZ 780@ BZ 782 BZ 840 @ BZ 845 BZ 845 @ BZ 849 BZ A-12@ BZ A-15 BZ A-15 @BZ A-20
28.36 37.43 30.17 34.67 93.27 93.78 96.23 92.01 73.09 61.54
REFINE Y NIVELACIÓN DE ZANJA T.
9 ML
NORMAL, P/ DESAGÜE BZ 790@ BZ 789 BZ 789 @ BZ 787 BZ 787@ BZ 785 BZ 785@ BZ 784 BZ 776-Q @ BZ 780 BZ 780@ BZ 782 BZ 840 @ BZ 845 BZ 845 @ BZ 849 BZ A-12@ BZ A-15 BZ A-15 @BZ A-20
28.36 37.43 30.17 34.67 93.27 93.78 96.23 92.01 73.09 61.54
28.36 37.43 30.17 34.67 93.27 93.78 96.23 92.01 73.09 61.54
28.36 37.43 30.17 34.67 93.27 93.78 96.23 92.01 73.09 61.54
3 2 2 2 2 2 2 2 3 3 3 5
6 5 2 6 5 9
BZ A12, BZ A13, BZ
19 ENCOFRADO DE TECHO DE BUZON UND
BZ 790, 788, 787, BZ 783, 782, 781, BZ 840, 841, BZ 845, 846, 847, A14, A 15, A 16, A
BZ 776-52, BZ 11A
786, 785, BZ 784 780, 776-Q 842,842, 843, 844 848, 849 17, BZ A18, BZ A 19,
BZ A20
6 5 2 6 5 9
BZ A12, BZ A13, BZ
20 VACIADO DE TAPA DE BUZON UND
BZ 790, 788, 787, BZ 783, 782, 781, BZ 840, 841, BZ 845, 846, 847, A14, A 15, A 16, A
BZ 776-52, BZ 11A
786, 785, BZ 784 780, 776-Q 842,842, 843, 844 848, 849 17, BZ A18, BZ A 19,
BZ A20
CHICHILIN COGRI ESCOBAYA - SAN FRANCISCO TAMAÑA
TUBERIA (m) BUZONES = 38 UND TUBERIA (m) BUZONES = 53 UND TUBERIA (m) BUZONES = 30 UND TUBERIA (m) BUZONES = 38 UND
BZCHI 62A h=1.40 BZ-24 h=1.20 BZ - 850 h =1.20 BZ-459 h=1.38
BZCHI 62 h=1.40 BZ-25 h=1.20 BZ - 851 h =1.40 BZ-458 h=1.25
BZCHI 63B h=1.20 BZ-27 h=1.30 BZ - 852 h =1.30 BZ-457 h=1.50 3,168.25
BZCHI 63A h=1.20 BZ-33 h=1.30 BZ - 855 h =1.20 BZ-456 h=1.40
BZCHI 63 h=1.20 BZ-33A h=1.20 BZ - 849 h =1.60 BZ-H h=1.40
BZCHI 64B h=1.20 BZ-34 h=1.40 BZ - 853 h =1.95 BZ-E h=1.40
BZCHI 64A h=1.20 BZ-129 h=1.50 BZ - 854 h =1.60 BZ-B h=1.20
BZCHI 65A h=1.20 BZ-28 h=1.4 BZ - 846 h =2.35 BZ-A h=1.20
BZCHI 65 h=1.20 BZ-35A h=1.5 BZ - 847 h =2.36 BZ_D h=1.65
BZCHI 66 h=1.20 BZ-36 h=1.4 BZ - 856 h =2.44 BZ_C h=1.65
BZCHI 67 h=1.20 BZ-127 h=1.4 BZ - 840 h =2.53 BZ_G h=2.80
BZCHI 68 h=1.20 BZ-128 h=1.4 BZ - 841 h =2.79 BZ_F h=2.65
BZCHI 74 h=1.20 BZ-38 h=1.5 BZ - 848 h =2.65 BZ - 406-B h =1.40
BZCHI 75 h=1.20 BZ-39 h=1.5 BZ - 842 h =3.28 BZ - 407 h =1.40
BZCHI 76 h=1.20 BZ-40 h=1.4 BZ - 843 h =3.31 BZ - 408 h =1.30
751.29
BZCHI 77 h=1.40 BZ-41 h=1.3 BZ - 844 h =3.30 BZ - 409 h =1.30
BZCHI 78 h=1.40 BZ-36 h=1.30 BZ - 845 h =3.37 BZ - 410 h =1.20
BZCHI 79 h=1.40 BZ-42 h=1.2 BZ - 857 h =3.47 BZ - 411 h =1.20
BZCHI 80 h=1.40 BZ-32 h=1.2 BZ - A-13 h =3.39 BZ - 412-A h =1.50
1,655.76 761.2
BZCHI 81 h=1.40 BZ-31 h=1.3 BZ - A-14 h =3.41 BZ - 412 h =1.50
BZCHI 82 h=1.40 BZ-45 h=1.2 BZ - A-15 h =3.44 BZ - 413 h =1.30
BZCHI 83 h=1.40 BZ-44 h=1.4 BZ - A-19 h =3.33 BZ - 414 h =1.50
BZCHI 84 h=1.40 BZ-46 h=1.3 BZ - 858 h =3.98 BZ - 415 h =1.30
BZCHI 85 h=1.40 BZ-47 h=1.2 BZ - 859 h =3.71 BZ - 416 h =1.50
BZCHI 86 h=1.40 BZ-48 h=1.2 BZ - 859A h =3.86 BZ - 417 h =1.50
BZCHI 87 h=1.40 BZ-125 h=1.2 BZ - 860 h =4.55 BZ - 418 h =1.40
BZCHI 88 h=1.40 0 BZ-49 h=1.4 BZ - A-16 h =6.64 BZ - 419 h =1.25
BZCHI 89 h=1.40 BZ-49A h=1.4 BZ - A-17 h =7.47 BZ - 420 h =1.35
BZCHI 90 h=1.40 BZ-50 h=1.4 BZ - A-18 h =4.25 BZ - 406_19 h =1.20
BZCHI 91 h=1.40 BZ-51 h=1.40 BZ - 859B h =4.53 BZ - 406_20 h =1.20
BZCHI 92 h=1.40 BZ-52 h=1.50 BZ - 406_21 h =1.20
BZCHI 93 h=1.40 BZ-53 h=1.20 BZ - 406_22 h =1.20
BZ 974 h=1.40 BZ-61 h=1.30 BZ - 406_23 h =1.21
BZCHI 71 h=2.00 BZ-133 h=1.30 BZ - 406_25 h =1.20
BZCHI 70 h=2.70 BZ-62 h=1.30 BZ - 406_26 h =1.20
BZCHI 72 h=2.70 BZ-63 h=1.50 BZ - 406_27 h =1.20
BZCHI 73 h=2.70 BZ-65 h=1.40 BZ - 406_28 h =1.20
BZCHI 69 h=3.40 BZ-66A h=1.40 BZ - 406_24 h =2.20
BZ-66 h=1.30
BZ-68A h=1.40
BZ-55 h=1.2
BZ-123 h=1.20
BZ-558 h=1.20
BZ-558A h=1.2
BZ-558B h=1.2
BZ-558C h=1.20
BZ-35 h=1.60
BZ-134 h=1.60
BZ-67 h=1.60
BZ-68 h=1.80
BZ - 30 H 2.43
BZ-37 h=2.95
BZ-69 h=3.20