DETALLE DE METRADOS - BUZONES

PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE


SUTOQ, DISTRITO DE CHECACUPE-CANCHIS-CUSCO"
EXCAVACION DE ZANJAS PARA BUZONES
ITEM BUZON Nº H DIAM. EXT. AREA VOLUMEN
1 BZ-1 1.70 1.60 2.01 3.417
2 BZ-2 3.01 1.60 2.01 6.050
3 BZ-3 3.40 1.60 2.01 6.834
4 BZ-4 3.81 1.60 2.01 7.658
5 BZ-5 2.85 1.90 2.84 8.094
6 BZ-6 2.61 1.60 2.01 5.246
7 BZ-7 2.70 1.90 2.84 7.668
8 BZ-8 2.30 1.90 2.84 6.532
9 BZ-9 1.90 1.60 2.01 3.819
10 BZ-10 2.20 1.60 2.01 4.422
11 BZ-11 1.60 1.60 2.01 3.216
12 BZ-12 1.40 1.60 2.01 2.814
13 BZ-13 2.00 1.60 2.01 4.020
14 BZ-14 1.40 1.60 2.01 2.814
15 BZ-15 1.40 1.60 2.01 2.814
16 BZ-16 1.70 1.60 2.01 3.417
17 BZ-17 1.40 1.60 2.01 2.814
18 BZ-18 1.80 1.60 2.01 3.618
19 BZ-19 1.40 1.60 2.01 2.814
20 BZ-20 1.40 1.60 2.01 2.814
21 BZ-21 1.70 1.60 2.01 3.417
22 BZ-22 1.71 1.60 2.01 3.437
23 BZ-23 1.40 1.60 2.01 2.814
24 BZ-24 1.70 1.60 2.01 3.417
25 BZ-25 1.41 1.60 2.01 2.834
26 BZ-26 1.40 1.60 2.01 2.814
27 BZ-27 1.71 1.60 2.01 3.437
28 BZ-28 1.40 1.60 2.01 2.814
29 BZ-29 1.80 1.60 2.01 3.618
30 BZ-30 1.40 1.60 2.01 2.814
31 BZ-31 1.40 1.60 2.01 2.814
32 BZ-32 1.71 1.60 2.01 3.437
33 BZ-33 2.47 1.60 2.01 4.965
34 BZ-34 1.40 1.60 2.01 2.814
35 BZ-35 1.40 1.60 2.01 2.814
36 BZ-36 1.40 1.60 2.01 2.814
37 BZ-37 1.41 1.60 2.01 2.834
38 BZ-38 1.40 1.60 2.01 2.814
39 BZ-39 1.41 1.60 2.01 2.834
40 BZ-40 1.40 1.60 2.01 2.814
41 BZ-41 1.70 1.60 2.01 3.417
42 BZ-42 2.82 1.60 2.01 5.668
43 BZ-43 2.20 1.60 2.01 4.422
44 BZ-44 1.70 1.60 2.01 3.417
45 BZ-45 1.40 1.60 2.01 2.814
VOLUMEN TOTAL 173.00
DETALLE DE METRADOS - BUZONES
PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE
SUTOQ, DISTRITO DE CHECACUPE-CANCHIS-CUSCO"
EXCAVACION DE ZANJAS PARA BUZONES
CONCRETO F'C=140 KG/CM2 + 30%P.G.LOSA FONDO
ITEM BUZON Nº H DIAM. INT. AREA VOLUMEN
1 BZ-1 0.20 1.60 2.01 0.402
2 BZ-2 0.20 1.60 2.01 0.402
3 BZ-3 0.20 1.60 2.01 0.402
4 BZ-4 0.20 1.60 2.01 0.402
5 BZ-5 0.20 1.90 2.84 0.568
6 BZ-6 0.20 1.60 2.01 0.402
7 BZ-7 0.20 1.90 2.84 0.568
8 BZ-8 0.20 1.90 2.84 0.568
9 BZ-9 0.20 1.60 2.01 0.402
10 BZ-10 0.20 1.60 2.01 0.402
11 BZ-11 0.20 1.60 2.01 0.402
12 BZ-12 0.20 1.60 2.01 0.402
13 BZ-13 0.20 1.60 2.01 0.402
14 BZ-14 0.20 1.60 2.01 0.402
15 BZ-15 0.20 1.60 2.01 0.402
16 BZ-16 0.20 1.60 2.01 0.402
17 BZ-17 0.20 1.60 2.01 0.402
18 BZ-18 0.20 1.60 2.01 0.402
19 BZ-19 0.20 1.60 2.01 0.402
20 BZ-20 0.20 1.60 2.01 0.402
21 BZ-21 0.20 1.60 2.01 0.402
22 BZ-22 0.20 1.60 2.01 0.402
23 BZ-23 0.20 1.60 2.01 0.402
24 BZ-24 0.20 1.60 2.01 0.402
25 BZ-25 0.20 1.60 2.01 0.402
26 BZ-26 0.20 1.60 2.01 0.402
27 BZ-27 0.20 1.60 2.01 0.402
28 BZ-28 0.20 1.60 2.01 0.402
29 BZ-29 0.20 1.60 2.01 0.402
30 BZ-30 0.20 1.60 2.01 0.402
31 BZ-31 0.20 1.60 2.01 0.402
32 BZ-32 0.20 1.60 2.01 0.402
33 BZ-33 0.20 1.60 2.01 0.402
34 BZ-34 0.20 1.60 2.01 0.402
35 BZ-35 0.20 1.60 2.01 0.402
36 BZ-36 0.20 1.60 2.01 0.402
37 BZ-37 0.20 1.60 2.01 0.402
38 BZ-38 0.20 1.60 2.01 0.402
39 BZ-39 0.20 1.60 2.01 0.402
40 BZ-40 0.20 1.60 2.01 0.402
41 BZ-41 0.20 1.60 2.01 0.402
42 BZ-42 0.20 1.60 2.01 0.402
43 BZ-43 0.20 1.60 2.01 0.402
44 BZ-44 0.20 1.60 2.01 0.402
45 BZ-45 0.20 1.60 2.01 0.402
VOLUMEN TOTAL 18.59
DETALLE DE METRADOS - BUZONES
PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE
SUTOQ, DISTRITO DE CHECACUPE-CANCHIS-CUSCO"
EXCAVACION DE ZANJAS PARA BUZONES

CONCRETO F'C=175 KG/CM2 PARA MUROS DE BUZON


ITEM BUZON Nº H DIAM. EXT. DIAM. INT. AREA 1 AREA 2 AREA VOL.
1 BZ-1 1.50 1.60 1.20 2.01 1.13 0.88 1.320
2 BZ-2 2.81 1.60 1.20 2.01 1.13 0.88 2.473
3 BZ-3 3.20 1.60 1.20 2.01 1.13 0.88 2.816
4 BZ-4 3.61 1.60 1.20 2.01 1.13 0.88 3.177
5 BZ-5 2.65 1.90 1.50 2.84 1.77 1.07 2.836
6 BZ-6 2.41 1.60 1.20 2.01 1.13 0.88 2.121
7 BZ-7 2.50 1.90 1.50 2.84 1.77 1.07 2.675
8 BZ-8 2.10 1.90 1.50 2.84 1.77 1.07 2.247
9 BZ-9 1.70 1.60 1.20 2.01 1.13 0.88 1.496
10 BZ-10 2.00 1.60 1.20 2.01 1.13 0.88 1.760
11 BZ-11 1.40 1.60 1.20 2.01 1.13 0.88 1.232
12 BZ-12 1.20 1.60 1.20 2.01 1.13 0.88 1.056
13 BZ-13 1.80 1.60 1.20 2.01 1.13 0.88 1.584
14 BZ-14 1.20 1.60 1.20 2.01 1.13 0.88 1.056
15 BZ-15 1.20 1.60 1.20 2.01 1.13 0.88 1.056
16 BZ-16 1.50 1.60 1.20 2.01 1.13 0.88 1.320
17 BZ-17 1.20 1.60 1.20 2.01 1.13 0.88 1.056
18 BZ-18 1.60 1.60 1.20 2.01 1.13 0.88 1.408
19 BZ-19 1.20 1.60 1.20 2.01 1.13 0.88 1.056
20 BZ-20 1.20 1.60 1.20 2.01 1.13 0.88 1.056
21 BZ-21 1.50 1.60 1.20 2.01 1.13 0.88 1.320
22 BZ-22 1.51 1.60 1.20 2.01 1.13 0.88 1.329
23 BZ-23 1.20 1.60 1.20 2.01 1.13 0.88 1.056
24 BZ-24 1.50 1.60 1.20 2.01 1.13 0.88 1.320
25 BZ-25 1.21 1.60 1.20 2.01 1.13 0.88 1.065
26 BZ-26 1.20 1.60 1.20 2.01 1.13 0.88 1.056
27 BZ-27 1.51 1.60 1.20 2.01 1.13 0.88 1.329
28 BZ-28 1.20 1.60 1.20 2.01 1.13 0.88 1.056
29 BZ-29 1.60 1.60 1.20 2.01 1.13 0.88 1.408
30 BZ-30 1.20 1.60 1.20 2.01 1.13 0.88 1.056
31 BZ-31 1.20 1.60 1.20 2.01 1.13 0.88 1.056
32 BZ-32 1.51 1.60 1.20 2.01 1.13 0.88 1.329
33 BZ-33 2.27 1.60 1.20 2.01 1.13 0.88 1.998
34 BZ-34 1.20 1.60 1.20 2.01 1.13 0.88 1.056
35 BZ-35 1.20 1.60 1.20 2.01 1.13 0.88 1.056
36 BZ-36 1.20 1.60 1.20 2.01 1.13 0.88 1.056
37 BZ-37 1.21 1.60 1.20 2.01 1.13 0.88 1.065
38 BZ-38 1.20 1.60 1.20 2.01 1.13 0.88 1.056
39 BZ-39 1.21 1.60 1.20 2.01 1.13 0.88 1.065
40 BZ-40 1.20 1.60 1.20 2.01 1.13 0.88 1.056
41 BZ-41 1.50 1.60 1.20 2.01 1.13 0.88 1.320
42 BZ-42 2.62 1.60 1.20 2.01 1.13 0.88 2.306
43 BZ-43 2.00 1.60 1.20 2.01 1.13 0.88 1.760
44 BZ-44 1.50 1.60 1.20 2.01 1.13 0.88 1.320
45 BZ-45 1.20 1.60 1.20 2.01 1.13 0.88 1.056
VOLUMEN TOTAL 66.35
DETALLE DE METRADOS - BUZONES
PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE
SUTOQ, DISTRITO DE CHECACUPE-CANCHIS-CUSCO"
EXCAVACION DE ZANJAS PARA BUZONES

CONCRETO F'C=210 KG/CM2. PARA LOSAS TECHO


ITEM BUZON Nº H DIAM. EXT. DIAM. INT. AREA 1 AREA 2 AREA VOLUMEN
1 BZ-1 0.20 1.60 0.50 2.01 0.20 1.81 0.362
2 BZ-2 0.20 1.60 0.50 2.01 0.20 1.81 0.362
3 BZ-3 0.20 1.60 0.50 2.01 0.20 1.81 0.362
4 BZ-4 0.20 1.60 0.50 2.01 0.20 1.81 0.362
5 BZ-5 0.20 1.90 0.50 2.84 0.20 2.64 0.528
6 BZ-6 0.20 1.60 0.50 2.01 0.20 1.81 0.362
7 BZ-7 0.20 1.90 0.50 2.84 0.20 2.64 0.528
8 BZ-8 0.20 1.90 0.50 2.84 0.20 2.64 0.528
9 BZ-9 0.20 1.60 0.50 2.01 0.20 1.81 0.362
10 BZ-10 0.20 1.60 0.50 2.01 0.20 1.81 0.362
11 BZ-11 0.20 1.60 0.50 2.01 0.20 1.81 0.362
12 BZ-12 0.20 1.60 0.50 2.01 0.20 1.81 0.362
13 BZ-13 0.20 1.60 0.50 2.01 0.20 1.81 0.362
14 BZ-14 0.20 1.60 0.50 2.01 0.20 1.81 0.362
15 BZ-15 0.20 1.60 0.50 2.01 0.20 1.81 0.362
16 BZ-16 0.20 1.60 0.50 2.01 0.20 1.81 0.362
17 BZ-17 0.20 1.60 0.50 2.01 0.20 1.81 0.362
18 BZ-18 0.20 1.60 0.50 2.01 0.20 1.81 0.362
19 BZ-19 0.20 1.60 0.50 2.01 0.20 1.81 0.362
20 BZ-20 0.20 1.60 0.50 2.01 0.20 1.81 0.362
21 BZ-21 0.20 1.60 0.50 2.01 0.20 1.81 0.362
22 BZ-22 0.20 1.60 0.50 2.01 0.20 1.81 0.362
23 BZ-23 0.20 1.60 0.50 2.01 0.20 1.81 0.362
24 BZ-24 0.20 1.60 0.50 2.01 0.20 1.81 0.362
25 BZ-25 0.20 1.60 0.50 2.01 0.20 1.81 0.362
26 BZ-26 0.20 1.60 0.50 2.01 0.20 1.81 0.362
27 BZ-27 0.20 1.60 0.50 2.01 0.20 1.81 0.362
28 BZ-28 0.20 1.60 0.50 2.01 0.20 1.81 0.362
29 BZ-29 0.20 1.60 0.50 2.01 0.20 1.81 0.362
30 BZ-30 0.20 1.60 0.50 2.01 0.20 1.81 0.362
31 BZ-31 0.20 1.60 0.50 2.01 0.20 1.81 0.362
32 BZ-32 0.20 1.60 0.50 2.01 0.20 1.81 0.362
33 BZ-33 0.20 1.60 0.50 2.01 0.20 1.81 0.362
34 BZ-34 0.20 1.60 0.50 2.01 0.20 1.81 0.362
35 BZ-35 0.20 1.60 0.50 2.01 0.20 1.81 0.362
36 BZ-36 0.20 1.60 0.50 2.01 0.20 1.81 0.362
37 BZ-37 0.20 1.60 0.50 2.01 0.20 1.81 0.362
38 BZ-38 0.20 1.60 0.50 2.01 0.20 1.81 0.362
39 BZ-39 0.20 1.60 0.50 2.01 0.20 1.81 0.362
40 BZ-40 0.20 1.60 0.50 2.01 0.20 1.81 0.362
41 BZ-41 0.20 1.60 0.50 2.01 0.20 1.81 0.362
42 BZ-42 0.20 1.60 0.50 2.01 0.20 1.81 0.362
43 BZ-43 0.20 1.60 0.50 2.01 0.20 1.81 0.362
44 BZ-44 0.20 1.60 0.50 2.01 0.20 1.81 0.362
45 BZ-45 0.20 1.60 0.50 2.01 0.20 1.81 0.362
VOLUMEN TOTAL 16.79
DETALLE DE METRADOS - BUZONES
PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE
SUTOQ, DISTRITO DE CHECACUPE-CANCHIS-CUSCO"
EXCAVACION DE ZANJAS PARA BUZONES

ENCOFRADO Y DESENCOFRADO METALICO DE LOSA TECHO


ITEM BUZON Nº H DIAM. INT. CIRCUNF. AREA
1 0.2 1.6 5.03 1.006
2 0.2 0.6 1.88 0.376
45 1.382
TOTAL 62.190

ENCOFRADO Y DESENCOFRADO NORMAL PARA BUZONES


ITEM BUZON Nº H DIAM. INT. CIRCUNF. AREA
1 BZ-1 1.50 1.20 3.77 5.655
2 BZ-2 2.81 1.20 3.77 10.594
3 BZ-3 3.20 1.20 3.77 12.064
4 BZ-4 3.61 1.20 3.77 13.610
5 BZ-5 2.65 1.50 4.71 12.482
6 BZ-6 2.41 1.20 3.77 9.086
7 BZ-7 2.50 1.50 4.71 11.775
8 BZ-8 2.10 1.50 4.71 9.891
9 BZ-9 1.70 1.20 3.77 6.409
10 BZ-10 2.00 1.20 3.77 7.540
11 BZ-11 1.40 1.20 3.77 5.278
12 BZ-12 1.20 1.20 3.77 4.524
13 BZ-13 1.80 1.20 3.77 6.786
14 BZ-14 1.20 1.20 3.77 4.524
15 BZ-15 1.20 1.20 3.77 4.524
16 BZ-16 1.50 1.20 3.77 5.655
17 BZ-17 1.20 1.20 3.77 4.524
18 BZ-18 1.60 1.20 3.77 6.032
19 BZ-19 1.20 1.20 3.77 4.524
20 BZ-20 1.20 1.20 3.77 4.524
21 BZ-21 1.50 1.20 3.77 5.655
22 BZ-22 1.51 1.20 3.77 5.693
23 BZ-23 1.20 1.20 3.77 4.524
24 BZ-24 1.50 1.20 3.77 5.655
25 BZ-25 1.21 1.20 3.77 4.562
26 BZ-26 1.20 1.20 3.77 4.524
27 BZ-27 1.51 1.20 3.77 5.693
28 BZ-28 1.20 1.20 3.77 4.524
29 BZ-29 1.60 1.20 3.77 6.032
30 BZ-30 1.20 1.20 3.77 4.524
31 BZ-31 1.20 1.20 3.77 4.524
32 BZ-32 1.51 1.20 3.77 5.693
33 BZ-33 2.27 1.20 3.77 8.558
34 BZ-34 1.20 1.20 3.77 4.524
35 BZ-35 1.20 1.20 3.77 4.524
36 BZ-36 1.20 1.20 3.77 4.524
37 BZ-37 1.21 1.20 3.77 4.562
38 BZ-38 1.20 1.20 3.77 4.524
39 BZ-39 1.21 1.20 3.77 4.562
DETALLE DE METRADOS - BUZONES
PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE
SUTOQ, DISTRITO DE CHECACUPE-CANCHIS-CUSCO"
EXCAVACION DE ZANJAS PARA BUZONES
40 BZ-40 1.20 1.20 3.77 4.524
41 BZ-41 1.50 1.20 3.77 5.655
42 BZ-42 2.62 1.20 3.77 9.877
43 BZ-43 2.00 1.20 3.77 7.540
44 BZ-44 1.50 1.20 3.77 5.655
45 BZ-45 1.20 1.20 3.77 4.524
VOLUMEN TOTAL 347.34
1.641 409.53
DETALLE DE METRADOS - BUZONES
PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE
SUTOQ, DISTRITO DE CHECACUPE-CANCHIS-CUSCO"
EXCAVACION DE ZANJAS PARA BUZONES
ENCOFRADO Y DESENCOFRADO LOSA TECHO DE BUZON
ITEM BUZÓN Nº DIÁM. ÁREA
1 BZ-1 1.20 1.13
2 BZ-2 1.20 1.13
3 BZ-3 1.20 1.13
4 BZ-4 1.20 1.13
5 BZ-5 1.50 1.77
6 BZ-6 1.20 1.13
7 BZ-7 1.50 1.77
8 BZ-8 1.50 1.77
9 BZ-9 1.20 1.13
10 BZ-10 1.20 1.13
11 BZ-11 1.20 1.13
12 BZ-12 1.20 1.13
13 BZ-13 1.20 1.13
14 BZ-14 1.20 1.13
15 BZ-15 1.20 1.13
16 BZ-16 1.20 1.13
17 BZ-17 1.20 1.13
18 BZ-18 1.20 1.13
19 BZ-19 1.20 1.13
20 BZ-20 1.20 1.13
21 BZ-21 1.20 1.13
22 BZ-22 1.20 1.13
23 BZ-23 1.20 1.13
24 BZ-24 1.20 1.13
25 BZ-25 1.20 1.13
26 BZ-26 1.20 1.13
27 BZ-27 1.20 1.13
28 BZ-28 1.20 1.13
29 BZ-29 1.20 1.13
30 BZ-30 1.20 1.13
31 BZ-31 1.20 1.13
32 BZ-32 1.20 1.13
33 BZ-33 1.20 1.13
34 BZ-34 1.20 1.13
35 BZ-35 1.20 1.13
36 BZ-36 1.20 1.13
37 BZ-37 1.20 1.13
38 BZ-38 1.20 1.13
39 BZ-39 1.20 1.13
40 BZ-40 1.20 1.13
41 BZ-41 1.20 1.13
42 BZ-42 1.20 1.13
43 BZ-43 1.20 1.13
44 BZ-44 1.20 1.13
45 BZ-45 1.20 1.13
ÁREA TOTAL 52.77
DETALLE DE METRADOS - BUZONES
PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE
SUTOQ, DISTRITO DE CHECACUPE-CANCHIS-CUSCO"
EXCAVACION DE ZANJAS PARA BUZONES
ACERO DE REFUERZO BZ T-1
ÍTEM Ø LONG. CANT. L. TOTAL KG/M. P. TOTAL
LOSA FONDO
1 3/8" 1.70 4.00 6.80 0.56 3.808
2 3/8" 1.45 4.00 5.80 0.56 3.248
3 3/8" 4.25 1.00 4.25 0.56 2.380
LOSA TECHO
1 3/8" 0.60 16.00 9.60 0.56 5.376
2 3/8" 0.55 16.00 8.80 0.56 4.928
3 1/2" 2.40 2.00 4.80 1.02 4.896
4 1/2" 3.45 2.00 6.90 1.02 7.038
5 1/2" 2.90 1.00 2.90 1.02 2.958
KILOGRAMOS TOTAL 34.63
40.00 1385.280
ACERO DE REFUERZO TECHO LOSA BZ T-2
ÍTEM Ø LONG. CANT. L. TOTAL KG/M. P. TOTAL
LOSA FONDO
1 3/8" 1.70 4.00 6.80 0.56 3.808
2 3/8" 1.45 4.00 5.80 0.56 3.248
3 3/8" 4.25 1.00 4.25 0.56 2.380
MURO
1 3/8" 2.50 16.00 40.00 0.56 22.400
2 3/8" 4.25 9.00 38.25 0.56 21.420
LOSA TECHO
1 3/8" 0.60 16.00 9.60 0.56 5.376
2 3/8" 0.55 16.00 8.80 0.56 4.928
3 1/2" 2.40 2.00 4.80 1.02 4.896
4 1/2" 3.45 2.00 6.90 1.02 7.038
5 1/2" 2.90 1.00 2.90 1.02 2.958
KILOGRAMOS TOTAL 78.45
5.00 392.260
TOTAL ACERO 1777.540
DETALLE DE METRADOS TUBERÍAS ALCANTARILLADO

PROYECTO : "MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA


COMUNIDAD CAMPESINA DE SUTOQ, DISTRITO DE CHECACUPE-CANCHIS-CUSCO"

Nro. de DIAMETRO LONGITUD


TUBERIA (mm) (m) PENDIENTE
TUB-1 200 mm 78.27 158.40‰
TUB-2 200 mm 64.65 133.97‰
TUB-3 200 mm 64.95 129.28‰
TUB-4 200 mm 64.1 109.04‰
TUB-5 200 mm 64.22 123.65‰
TUB-6 200 mm 64.4 122.38‰
TUB-7 200 mm 29.54 114.17‰
TUB-8 200 mm 33.74 116.57‰
TUB-9 200 mm 64.56 133.77‰
TUB-10 200 mm 49.16 130.39‰
TUB-11 200 mm 15.51 129.71‰
TUB-12 200 mm 31.09 6.65‰
TUB-13 200 mm 32.48 172.00‰
TUB-14 200 mm 51.49 7.25‰
TUB-15 200 mm 52.57 108.58‰
TUB-16 200 mm 53.92 3.11‰
TUB-17 200 mm 28.5 38.94‰
TUB-18 200 mm 51.67 59.24‰
TUB-19 200 mm 71.77 2.66‰
TUB-20 200 mm 28.88 71.82‰
TUB-21 200 mm 51.23 14.51‰
TUB-22 200 mm 59.97 9.22‰
TUB-23 200 mm 43.61 35.23‰
TUB-24 200 mm 50.46 10.93‰
TUB-25 200 mm 76.47 5.53‰
TUB-26 200 mm 44.38 155.00‰
TUB-27 200 mm 13.81 11.03‰
TUB-28 200 mm 32.77 118.64‰
TUB-29 200 mm 35.2 7.93‰
TUB-30 200 mm 65.22 6.41‰
TUB-31 200 mm 31.03 9.47‰
TUB-32 200 mm 81.29 10.28‰
TUB-33 200 mm 85.84 9.00‰
TUB-34 200 mm 64.63 18.20‰
TUB-35 200 mm 64.55 29.77‰
TUB-36 200 mm 22.6 72.86‰
TUB-37 200 mm 42.11 11.90‰
TUB-38 200 mm 60.79 42.03‰
TUB-39 200 mm 37.32 21.66‰
TUB-40 200 mm 63.94 168.86‰
TUB-41 200 mm 63.76 149.37‰
TUB-42 200 mm 64.35 123.19‰
TUB-43 200 mm 30.39 130.25‰
TUB-44 200 mm 31.28 156.16‰
TUB-45 200 mm 29.9 134.27‰
TUB-46 200 mm 63.37 144.52‰
TUB-47 200 mm 38.82 195.00‰
TUB-48 200 mm 35.62 153.11‰
TUB-49 200 mm 64.2 81.82‰
TUB-50 200 mm 31.23 8.83‰
TUB-51 200 mm 22.64 350.95‰
TUB-52 200 mm 2.32 71.68‰
TOTAL 2500.57
(HOJA DE METRADOS DE CAMARA DE REJAS )
PROYECTO : "MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE
SUTOQ, DISTRITO DE CHECACUPE-CANCHIS-CUSCO"


DESCRIPCION UND LONG. ANCHO ALTO PARCIAL TOTAL
VECES

CAMARA DE REJAS, MEDIDOR DE CAUDAL Y DESARENADOR

TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL m2 1 6.30 1.15 7.25 7.25
TRAZO NIVELACION Y REPLANTEO m2 1 6.30 1.15 7.25 7.25
CINTA PLASTICA SEÑALIZADORA PARA LIMITE m 1 15.00 15.00 15.00
MOVIMIENTO DE TIERRAS
EXCAVACION C/I(MAQUINAS) TERRENO NORMAL m3 2.52
Losa de ingreso a la losa de transición 1 1.72 0.60 0.50 0.52
Losa de transición a las rejas 1 2.28 1.15 0.50 1.31
Losa de transición al desarenador 1 2.30 0.60 0.50 0.69

NIVELACION INTERIOR APISONADO MANUAL m2 5.03


1 1.72 0.60 1.03
1 2.28 1.15 2.62
1 2.30 0.60 1.38
Esponj. 20%
ELIMINACION DE MATERIAL EXCEDENTE CON MA m3 1 2.52 1.20 3.02 3.02

OBRAS DE CONCRETO SIMPLE


CONCRETO FC=175 KG/CM2 PARA SOLADOS m3 1 5.03 0.10 0.50 0.50
(CONCRETO P/SOLADO F'c=140 KG/CM2, CEMENTO TIPO I)
OBRAS DE CONCRETO ARMADO
CONCRETO PARA MUROS FC=210 KG/CM2 m3 2.31
Muro longitudinal de ingreso a la transición 2 1.72 0.15 0.50 0.26
Muro longitudinal de transición 2 2.28 0.15 0.55 0.38
Muro longitudinal de la camara de rejas 2 1.18 0.15 0.55 0.19
Muro longitudinal de la camara de rejas 2 0.40 0.15 0.55 0.07
Muro longitudinal de transición al desarenador 2 2.30 0.15 0.85 0.59
Muro longitudinal del desarenador 1 0.30 0.15 0.85 0.04
Muro longitudinal del desarenador 2 0.30 0.15 0.40 0.04
Losa de ingreso a la losa de transición 1 1.72 0.60 0.15 0.15
Losa de transición a las rejas 1 2.28 1.15 0.15 0.39
Losa de transición al desarenador 1 2.30 0.60 0.15 0.21
ENCOFRADO Y DESENCOFRADO MUROS m2 21.252
Muro longitudinal de ingreso a la transición 4 1.72 0.50 3.44
Muro longitudinal de transición 4 2.28 0.55 5.02
Muro longitudinal de la camara de rejas 4 1.18 0.55 2.60
Muro longitudinal de la camara de rejas 4 0.4 0.55 0.88
Muro longitudinal de transición al desarenador 4 2.3 0.85 7.82
Muro longitudinal del desarenador 4 0.3 0.85 1.02
Muro longitudinal del desarenador 4 0.3 0.40 0.48

REVOQUES ENLUCIDOS Y MOLDURAS


TARRAJEO CON IMPERMEABILIZANTES P/MUROS m2 1 21.25 21.25 21.25
REJILLA FIERRO 1/2" ESPACIAMIENTO DE 1" und 1 1.00 1.00 1.00
COMPUERTAS Y VERTEDORES
COMPUERTA METALICA TIPO TARJETA DE 0.40 X 0 und 1 1.00 1.00 1.00
(METRADOS DE ACEROS EN CAMARA DE REJAS )
"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DISTRITO DE CHECACUPE-CANCHIS-CUSCO"
PROYECTO :

Armadura 1/4¨ 3/8¨ 1/2¨ 5/8¨ 3/4¨ Parcial N° de


Item Concepto @ Sub Total
cant. long. ф¨ total. 0.25 0.56 0.994 1.6 2.24 kg Obras
CAMARA DE REJAS
Losa fondo 4 8.25 3/8" 33.00 @ 0.20 18.48 18.48 1 18.48
36 1.30 3/8" 46.80 @ 0.20 26.21 26.208 2 52.42
Pared 6 6.90 3/8" 41.40 @ 0.20 23.18 23.184 2 46.37
Bypass losa fondo 4 3.30 3/8" 13.20 @ 0.20 7.39 7.392 1 7.39
18 1.00 3/8" 18.00 @ 0.20 10.08 10.08 1 10.08
Bypass pared 4 4.50 3/8" 18.00 @ 0.20 10.08 85.344 1 85.34
TOTAL 170.69 220.08
(HOJA DE METRADOS DE TANQUE IMHOFF )
PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DISTRITO DE
CHECACUPE-CANCHIS-CUSCO"

descripcion Unid. cant. Largo Ancho Alto Perim. Area Parcial Sub Total
TANQUE IMHOFF
TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL m2 1 6.00 8.20 49.20 49.20
TRAZO NIVELACION Y REPLANTEO m2 1 6.00 8.20 49.20 49.20
CINTA PLASTICA SEÑALIZADORA PARA LIMITE DE SEGURIDAD DE OBRA m 1 27.32 27.32 27.32

MOVIMIENTO DE TIERRAS
EXCAVACION C/I(MAQUINAS) TERRENO NORMAL-ESTRUCTURAS m3 1 6.00 8.20 5.45 268.14 268.14
NIVELACION INTERIOR APISONADO MANUAL m2 1 6.00 8.20 49.20 49.20
Esponj. 20%
ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=5 KM m3 1 268.14 1.20 321.77 321.77
OBRAS DE CONCRETO SIMPLE
CONCRETO FC=175 KG/CM2 PARA SOLADOS m3 1 6.60 10.00 0.10 6.60 6.60
OBRAS DE CONCRETO ARMADO
CONCRETO PARA LOSA DE CIMENTACION FC=210 KG/CM2 m3 1 6.60 10.00 0.30 19.80 19.80
CONCRETO PARA MUROS FC=210 KG/CM2 m3 51.76 51.76
FRENTE Y FONDO 2 6.00 0.45 4.05 21.87
LATERALES 2 8.20 0.45 4.05 29.89
ENCOFRADO Y DESENCOFRADO MUROS m2 230.04 230.04
FRENTE Y FONDO 4 6.00 4.05 97.20
LATERALES 4 8.20 4.05 132.84
CONCRETO PARA MUROS DEL SEDIMENTADOR FC=210 KG/CM2 m3 7.01 7.01
1 6.40 0.20 2.40 3.07
1 6.40 0.20 3.08 3.94
ENCOFRADO Y DESENCOFRADO MUROS DE SEDIMENTADOR m2 37.63 37.63
1 6.40 2.60 16.64
1 6.40 3.28 20.99
CONCRETO PARA CAJA DE SALIDA DE LODOS FC=210 KG/CM2 m3 1.25 1.25
1 1.00 1.00 0.20 0.20
2 1.00 0.20 1.55 0.62
2 0.70 0.20 1.55 0.43
ENCOFRADO Y DESENCOFRADO CAJA DE SALIDA DE LODOS m2 4.34 4.34
2 0.70 1.55 2.17
2 0.70 1.55 2.17
CONCRETO PARA CAJA DE SALIDA FC=210 KG/CM2 m3 0.29 0.29
2 0.30 0.20 0.50 0.06
1 1.40 0.15 0.50 0.11
1 1.40 0.45 0.20 0.13
ENCOFRADO Y DESENCOFRADO CAJA DE SALIDA m2 1.70 1.70
4 0.30 0.50 0.60
2 1.10 0.50 1.10
WATER STOP DE NEOPRENE DE 8". PROVISION Y COLOCADO DE JUNTA m
2 22.40 44.80 44.80
REVOQUES ENLUCIDOS Y MOLDURAS
TARRAJEO CON IMPERMEABILIZANTES P/MUROS m2 124.26 124.26
LOSA DE FONDO 1 8.00 4.80 38.4
MURO 2 6.40 4.05 51.84
2 4.20 4.05 34.02
INSTALACIONES HIDRAULICAS
SUMINISTRO E INST. DE TUBERIA PVC NTP ISO 4435 UF. DE 200 MM INC/ m 1 9.00 9.00 9.00
SUMINISTRO E INST.DE CODO PVC NTP ISO 4435 UF. DE 200 MM X 45° INC und 1 1.00 1.00 1.00
SUMINISTRO E INST. DE YEE PVC NTP ISO 4435 UF. DE 200 X 200MM. INC und 1 1.00 1.00 1.00
SUMINISTRO E INST. DE VALVULA F°F° DE 200 MM UF. INC/ANILLOS TIPO m 1 1.00 1.00 1.00
BAFLE DE PVC DE 1.00 X 1.20 *1/2" und 2 2.00 2.00 2.00
CONTROL DE CALIDAD DE CONCRETO
PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 1 3.00 3.00 3.00
(HOJA DE METRADOS ACEROS - TANQUE IMHOFF )

PROYECTO : "MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DISTR
CANCHIS-CUSCO"
Armadura 1/4¨ 3/8¨ 1/2¨ 5/8¨ 3/4¨
Concepto @
cant. long. ф¨ total. 0.25 0.56 0.994 1.6 2.24
Tanque imhoff
Losa fondo transversal 31 7.50 3/4" 232.50 @ 0.25 520.80
31 7.20 1/2" 223.20 @ 0.25 221.86
31 0.45 3/8" 13.95 @ 0.50 7.81
Losa fondo longitudinal 23 5.30 3/4" 121.90 @ 0.25 273.06
23 5.30 1/2" 121.90 @ 0.25 121.17
18 4.20 3/4" 75.60 @ 0.25 169.34
18 4.20 1/2" 75.60 @ 0.25 75.15
21 0.45 3/8" 9.45 @ 0.50 5.29

Pared fondo y frente vertical 31 2.60 3/4" 80.60 @ 0.25 180.54


30 5.10 3/4" 153.00 @ 0.25 342.72
31 2.60 1/2" 80.60 @ 0.25 80.12
23 5.10 1/2" 117.30 @ 0.25 116.60
23 0.45 3/8" 10.35 @ 1.00 5.80
Pared lateral vertical 30 2.60 3/4" 78.00 @ 0.25 174.72
30 5.10 3/4" 153.00 @ 0.25 342.72
30 2.60 1/2" 78.00 @ 0.25 77.53
30 5.10 1/2" 153.00 @ 0.25 152.08
30 0.45 3/8" 13.50 @ 1.00 7.56
Pared horizontal fondo y frente 33 6.70 1/2" 221.10 @ 0.15 219.77
33 7.10 1/2" 234.30 @ 0.15 232.89
Pared horizontal costados 33 10.70 1/2" 353.10 @ 0.15 350.98
33 9.00 1/2" 297.00 @ 0.15 295.22

Tabique vertical 45 2.8 1/2" 126.00 @ 0.15 125.24


45 3.4 1/2" 153.00 @ 0.15 152.08
Tabique horizontal 15 9 1/2" 135.00 @ 0.15 134.19
19 9 1/2" 171.00 @ 0.15 169.97

buferrs vertical 11 1.20 1/4" 13.20 @ 0.10 3.30


buferrs horizontal 13 0.95 1/4" 12.35 @ 0.10 3.09

Rebose vertical 8 1.75 3/8" 14.00 @ 0.15 7.84


Rebose horizontal 4 2.60 3/8" 10.40 @ 0.15 5.82
4 3.30 3/8" 13.20 @ 0.15 7.39

Caja de valvulas losa fondo 7 0.8 1/2" 5.60 @ 0.15 5.57


7 0.8 1/2" 5.60 @ 0.15 5.57
Caja de valvulas paredes 7 1.3 1/2" 9.10 @ 0.15 9.05
Caja de valvulas losa tapa 10 0.8 1/2" 8.00 @ 0.10 7.95
10 0.8 1/2" 8.00 @ 0.11 7.95
TOTAL
HOFF )

MPESINA DE SUTOQ, DISTRITO DE CHECACUPE-

Parcial kg N° de Sub Total


Obras

520.80 1.00 520.80


221.86 1.00 221.86
7.81 8.00 62.50
273.06 1.00 273.06
121.17 1.00 121.17
169.34 2.00 338.69
75.15 2.00 150.29
5.29 8.00 42.34

180.54 2.00 361.09


342.72 2.00 685.44
80.12 2.00 160.23
116.60 2.00 233.19
5.80 7.00 40.57
174.72 2.00 349.44
342.72 2.00 685.44
77.53 2.00 155.06
152.08 2.00 304.16
7.56 7.00 52.92
219.77 2.00 439.55
232.89 2.00 465.79
350.98 2.00 701.96
295.22 2.00 590.44

125.24 2.00 250.49


152.08 2.00 304.16
134.19 2.00 268.38
169.97 2.00 339.95

3.30 2.00 6.60


3.09 2.00 6.18

7.84 1.00 7.84


5.82 1.00 5.82
7.39 1.00 7.39

5.57 1.00 5.57


5.57 1.00 5.57
9.05 4.00 36.18
7.95 1.00 7.95
7.95 1.00 7.95
4,618.75 8,216.01
(HOJA DE METRADOS DE FITRO BIOLOGICO )
PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE
SUTOQ, DISTRITO DE CHECACUPE-CANCHIS-CUSCO"

descripcion Unid. cant. Largo Ancho Alto Parcial


FILTRO BIOLOGICO
TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL m2 1 7.50 5.90 44.25
TRAZO NIVELACION Y REPLANTEO m2 1 7.50 5.90 44.25
MOVIMIENTO DE TIERRAS
EXCAVACION C/I(MAQUINAS) TERRENO NORMAL-ESTRUCTURAS m3 1 7.50 5.90 2.55 112.84
NIVELACION INTERIOR APISONADO MANUAL m2 1 7.50 5.90 44.25
ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=5 KM m3 1 112.84 1.20 135.41
OBRAS DE CONCRETO SIMPLE
CONCRETO FC=175 KG/CM2 PARA SOLADOS m3 1 7.50 5.90 0.10 4.43
OBRAS DE CONCRETO ARMADO
CONCRETO PARA LOSA DE CIMENTACION FC=210 KG/CM2 m3 1 7.90 5.90 0.25 11.65
CONCRETO PARA MUROS FC=210 KG/CM2 m3 14.30
2 7.50 0.25 2.20 8.25
2 5.50 0.25 2.20 6.05
ENCOFRADO Y DESENCOFRADO MUROS m2 114.40
4 7.50 2.20 66.00
4 5.50 2.20 48.40
CONCRETO PARA CANAL CENTRAL FC=210 KG/CM2 m3 1 5.90 0.26 1.50
ENCOFRADO Y DESENCOFRADO CANAL CENTRAL m2 2 5.90 0.10 1.18
REVOQUES ENLUCIDOS Y MOLDURAS
TARRAJEO CON IMPERMEABILIZANTES 1:2 e=1.5 cm. m2 98.45
2 7.50 2.20 33.00
2 5.50 2.20 24.20
VARIOS 1 7.50 5.50 41.25
ENCOFRADO Y DESENCOFRADO m2 26 0.80 0.20 4.16
DADO DE SOPORTE CONCRETO FC=210 KG/CM2 m3 26 0.20 0.20 0.20 0.21
LOSA PRE FABRICADA C° A° CON ORIFICIOS und 24 24.00
FILTRO DE CANTO RODADO DE 6" m3 1 7.00 5.00 0.80 28.00
FILTRO DE CANTO RODADO DE 3" m3 1 7.00 5.00 0.40 14.00
FILTRO DE CANTO RODADO DE 1" m3 1 7.00 5.00 0.15 5.25
TUBERIA PVC SAP DN: 4" C-10 PERFORADA PARA RIEGO m 11 5.50 60.50
SUMINISTRO E INST. DE VALVULA F°F° DE 200 MM UF. INC/ANILLOS und 1 1.00
CAJA DE INGRESO Y SALIDA
CONCRETO PARA CAJA DE ENTRADA/SALIDA FC=210 KG/CM2 m3 1.62
ENTRADA 1 1.30 1.00 0.15 0.20
ENTRADA 2 0.90 0.15 0.70 0.19
ENTRADA 2 0.80 0.15 0.70 0.17
SALIDA 1 1.50 1.25 0.15 0.28
SALIDA 2 1.15 0.15 1.55 0.53
SALIDA 1 1.00 0.15 1.55 0.23
SALIDA 1 0.40 0.40 0.15 0.02
ENCOFRADO Y DESENCOFRADO CAJAS m2 16.47
ENTRADA 1 2.90 0.70 2.03
ENTRADA 1 2.80 0.70 1.96
SALIDA 1 3.60 1.70 6.12
SALIDA 1 4.00 1.55 6.20
SALIDA 1 0.40 0.40 0.16
TARRAJEO CON IMPERMEABILIZANTES 1:2 e=1.5 cm. m2 16.47
CONCRETO PARA CANAL DE DIST. FC=210 KG/CM2 m3 0.32
1 7.00 0.25 0.10 0.18
1 7.00 0.10 0.20 0.14
ENCOFRADO Y DESENCOFRADO CANAL DE DIST. m2 1 7.00 0.75 5.25
TAPA PRE FABRICADA DE C° A° INGRESO Y SALIDA und 2 2.00
MADERA TRATADA PARA VERTEDERO e=2" m2 11 0.15 0.22 0.36
CONTROL DE CALIDAD DE CONCRETO
PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 3 3.00
D CAMPESINA DE

Sub Total

44.25
44.25

112.84
44.25
135.41

4.43

11.65
14.30

114.40

1.50
1.18

98.45

4.16
0.21
24.00
28.00
14.00
5.25
60.50
1.00

1.62

16.47
16.47
0.32

5.25
2.00
0.36

3.00
(HOJA DE METRADOS DE ACERO FILTRO BIOLOGICO)
PROYECTO : "MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DI
CUSCO"

Armadura 1/4¨ 3/8¨ 1/2¨


Concepto @
cant. long. ф¨ total. 0.25 0.56 0.994
FILTRO BIOLOGICO
Losa fondo 41 4.15 3/8" 170.15 @ 0.15 95.28
41 4.00 3/8" 164.00 @ 0.15 91.84
41 0.70 3/8" 28.70 @ 0.15 16.07
41 1.20 3/8" 49.20 @ 0.15 27.55
51 6.30 3/8" 321.30 @ 0.15 179.93
51 6.00 3/8" 306.00 @ 0.15 171.36
Pared frente y fondo vertical 48 2.70 3/8" 129.60 @ 0.20 72.58
39 2.90 1/2" 113.10 @ 0.25 112.42
Pared frente y fondo horizontal 13 8.00 3/8" 104.00 @ 0.20 58.24
11 7.80 1/2" 85.80 @ 0.25 85.29
Pared lateral vertical 33 2.70 3/8" 89.10 @ 0.20 49.90
27 2.90 1/2" 78.30 @ 0.25 77.83
Pared lateral horizontal 13 5.80 3/8" 75.40 @ 0.20 42.22
11 5.30 1/2" 58.30 @ 0.25 57.95

Caja inspeccion losa 10 2.15 3/8" 21.50 @ 0.15 12.04


Pared vertical 7 2.20 3/8" 15.40 @ 0.15 8.62
Pared horizontal 13 1.65 3/8" 21.45 @ 0.15 12.01
13 1.70 3/8" 22.10 @ 0.15 12.38

Canaleta losa fondo 3 9.00 1/2" 27.00 @ 0.15 26.84


Canaleta pared 61 1.00 1/2" 61.00 @ 0.15 60.63
3 9.00 1/2" 27.00 @ 0.15 26.84
Losa tapa 10 1.10 1/2" 11.00 @ 0.15 10.93
9 1.25 1/2" 11.25 @ 0.15 11.18

Caja valvula losa fondo 5 1.45 1/2" 7.25 @ 0.15 7.21


5 0.8 1/2" 4.00 @ 0.15 3.98
6 0.8 1/2" 4.80 @ 0.15 4.77
7 1.5 1/2" 10.50 @ 0.15 10.44
7 1.3 1/2" 9.10 @ 0.15 9.05
Losa tapa 7 0.90 1/2" 6.30 @ 0.15 6.26
7 0.80 1/2" 5.60 @ 0.15 5.57
O BIOLOGICO)
CAMPESINA DE SUTOQ, DISTRITO DE CHECACUPE-CANCHIS-

5/8¨ 3/4¨ N° de
Parcial kg Obras Sub Total
1.6 2.24

95.284 2 190.57
91.84 2 183.68
16.072 1 16.07
27.552 1 27.55
179.928 1 179.93
171.36 1 171.36
72.576 2 145.15
112.4214 2 224.84
58.24 2 116.48
85.2852 2 170.57
49.896 2 99.79
77.8302 2 155.66
42.224 2 84.45
57.9502 2 115.90
1,882.01

12.04 2 24.08
8.624 3 25.87
12.012 2 24.02
12.376 1 12.38

26.838 1 26.84
60.634 1 60.63
26.838 1 26.84
10.934 1 10.93
11.1825 1 11.18

7.2065 1 7.21
3.976 2 7.95
4.7712 1 4.77
10.437 2 20.87
9.0454 1 9.05
6.2622 1 6.26
5.5664 1 5.57

TOTAL 1,164.01 284.46


(HOJA DE METRADOS DE LECHO DE SECADOS )
PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DISTRITO
DE CHECACUPE-CANCHIS-CUSCO"
descripcion Unid. cant. Largo Ancho Alto Parcial Sub Total
LECHO DE SECADO
TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL m2 1 8.85 5.35 47.35 47.35
TRAZO NIVELACION Y REPLANTEO m2 1 8.85 5.35 47.35 47.35
MOVIMIENTO DE TIERRAS
EXCAVACION C/I(MAQUINAS) TERRENO NORMAL-ESTRUCTURAS m3 50.85 50.85
1 8.85 5.35 3.00 47.35
1 7.00 0.50 0.35 3.50
NIVELACION INTERIOR APISONADO MANUAL m2 1 8.85 5.35 47.35 47.35
ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=5 KM m3 1 50.85 1.20 61.02 61.02
OBRAS DE CONCRETO SIMPLE
CONCRETO FC=175 KG/CM2 PARA SOLADOS m3 1 9.50 6.85 0.10 6.51 6.51
OBRAS DE CONCRETO ARMADO
CONCRETO PARA MUROS FC=210 KG/CM2 m3 22.00 22.00
LOSA DE FONDO 4 9.50 0.98 0.15 5.59
FROTAL 1 5.35 0.15 2.54 2.04
FONDO 1 5.35 0.15 3.20 2.57
LATERALES 2 8.00 0.15 3.20 7.68
CENTRAL 1 8.00 0.15 1.60 1.92
CANAL DE DISTRIBUCION 1 3.90 0.15 0.55 0.32
1 3.90 0.55 0.15 0.32
SALIDA 1 5.05 0.15 2.06 1.56
ENCOFRADO Y DESENCOFRADO MUROS m2 235.35 235.35
FROTAL 2 5.35 2.54 27.18
FONDO 2 5.35 3.20 34.24
LATERALES 4 8.85 3.20 113.28
CENTRAL 2 8.00 1.60 25.60
CANAL DE DISTRIBUCION 1 3.90 1.65 6.44
4 0.55 0.55 1.21
CANAL CENTRAL 4 6.60 0.25 6.60
SALIDA 2 5.05 2.06 20.81
TARRAJEO CON IMPERMEABILIZANTES P/MUROS m2 235.35 235.35
CONCRETO PARA PARED SALPICADORA FC=210 KG/CM2 m3 2 1.20 0.60 0.10 0.14 0.14
ENCOFRADO Y DESENCOFRADO PARED SALPICADORA m2 2.71 2.71
2 1.20 0.60 1.44
2 3.00 0.10 0.60
CONCRETO PARA CANAL CENTRAL FC=210 KG/CM2 m3 2 6.60 0.16 2.11 2.11
TAPA PRE FABRICADA DE C° A° DE 0.35 X 0.35 m. P/CANALCENTRAL und 20 20.00 20.00
ARCILLA PARA LOSA DE FONDO
ARCILLA P/LECHO DE SECADOS (LOSA DE FONDO) m3 1 9.50 6.85 0.10 6.51 6.51
VARIOS
SUMINISTRO E INST. DE TUBERIA PVC NTP ISO 4435 UF. DE 200 MM IN m 1 5.00 5.00 5.00
SUMINISTRO E INST.DE CODO PVC NTP ISO 4435 UF. DE 200 MM X 90° und 2 2.00 2.00
TUBERIA PVC NTP ISO 4422 UF DE 110 mm. C-10 INC/ANILLOS m 1 2.50 2.50 2.50
GRAVA P/LECHO DE SECADOS D=3/4" - 2" m3 2 8.00 2.45 0.20 7.84 7.84
GRAVA P/LECHO DE SECADOS D=1/4" m3 2 8.00 2.45 0.15 5.88 5.88
GRAVA P/LECHO DE SECADOS D=1/16" m3 2 8.00 2.45 0.10 3.92 3.92
COBERTURA DE LADRILLO KK P/LECHO DE SECADOS m2 2 8.00 2.45 39.20 39.20
CONTROL DE CALIDAD DE CONCRETO
PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 3 3.00 3.00
(HOJA DE METRADOS DE ACERO LECHO DE SECADOS)
PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DISTRI
CANCHIS-CUSCO"
Armadura 1/4¨ 3/8¨ 1/2¨ 5/8¨ 3/4¨
Concepto @
cant. long. ф¨ total. 0.25 0.56 0.994 1.6 2.24
CAMARA LECHO DE SECADO
Losa fondo transversal 33 1.65 1/2" 54.45 @ 0.25 54.12
33 1.10 3/8" 36.3 @ 0.25 20.33
Losa fondo Longitudinal 6 7.90 1/2" 47.4 @ 0.25 47.12
6 4.70 1/2" 28.2 @ 0.25 28.03
Paredes fondo vertical 27 3.50 1/2" 94.5 @ 0.20 93.93
27 2.20 1/2" 59.4 @ 0.20 59.04
Paredes fondo horizontl 15 5.85 1/2" 87.75 @ 0.20 87.22
10 5.85 1/2" 58.5 @ 0.20 58.15
Paredes laterales 39 3.20 1/2" 124.8 @ 0.25 124.05
12 9.4 1/2" 112.8 @ 0.25 112.12
39 2.15 3/8" 83.85 @ 0.25 46.96
12 9.4 3/8" 112.8 @ 0.25 63.17
Pared frente 27 4.70 1/2" 126.9 @ 0.20 126.14
27 6.45 1/2" 174.15 @ 0.20 173.11
27 1.5 1/2" 40.5 @ 0.20 40.26
Caja rebose vertical 7 1.4 1/2" 9.8 @ 0.10 9.74
27 1.45 3/8" 39.15 @ 0.15 21.92
Caja rebose horizontal 4 4.9 3/8" 19.6 @ 0.15 10.98
Salpicadero 13 0.55 1/2" 7.15 @ 0.10 7.11
Losa dren 109 0.3 3/8" 32.7 @ 0.10 18.31
5 10.8 3/8" 54 @ 0.10 30.24
ADOS)
SINA DE SUTOQ, DISTRITO DE CHECACUPE-

Parcial kg N° de Sub Total


Obras

54.12 4 216.49
20.33 2 40.66
47.12 2 94.23
28.03 2 56.06
93.93 1 93.93
59.04 1 59.04
87.22 1 87.22
58.15 1 58.15
124.05 2 248.10
112.12 2 224.25
46.96 1 46.96
63.17 1 63.17
126.14 2 252.28
173.11 2 346.21
40.26 1 40.26
9.74 1 9.74
21.92 1 21.92
10.98 1 10.98
7.11 1 7.11
18.31 1 18.31
30.24 1 30.24
1,232.05 2,025.31
(HOJA DE METRADOS DE CAMARA DE CONTACTO Y CLORACION )
PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ,
DISTRITO DE CHECACUPE-CANCHIS-CUSCO"

descripcion Unid. cant. Largo Ancho Alto Parcial Sub Total


CAMARA DE CONTACTO Y CLORAACION
TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL m2 7.27 7.27
1 5.30 1.10 5.83
1 1.20 1.20 1.44
TRAZO NIVELACION Y REPLANTEO m2 7.27 7.27
1 5.30 1.10 5.83
1 1.20 1.20 1.44
MOVIMIENTO DE TIERRAS
EXCAVACION C/I(MAQUINAS) TERRENO NORMAL-ESTRUCTURAS m3 9.32 9.32
1 5.30 1.10 1.55 9.04
1 1.20 1.20 0.20 0.29
NIVELACION INTERIOR APISONADO MANUAL m2 1 7.27 7.27
ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=5 KM m3 1 9.32 1.20 11.19 11.19
OBRAS DE CONCRETO SIMPLE
CONCRETO FC=175 KG/CM2 PARA SOLADOS m3 1 5.30 1.10 0.10 0.58 0.58
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO m2 21.04 21.04
MURO FRENTE Y FONDO 4 1.10 1.40 6.16
LATERALES 4 2.40 1.40 13.44
BUZONETA 1 2.40 0.60 1.44
ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 1 143.66 143.66 143.66
CONCRETO FC=210 KG/CM2 m3 2.18 2.18
LOSA DE FONDO 1 2.50 1.10 0.15 0.41
MURO FRENTE Y FONDO 2 1.10 0.15 1.40 0.46
LATERALES 2 2.40 0.15 1.40 1.01
BUZONETA 2 0.80 0.10 0.60 0.10
2 0.60 0.10 0.60 0.07
1 0.80 0.80 0.10 0.06
1 0.80 0.80 0.10 0.06
REVOQUES ENLUCIDOS Y MOLDURAS
TARRAJEO CON IMPERMEABILIZANTES P/MUROS m2 14.87 14.87
LOSA DE FONDO 1 2.50 1.10 2.75
MURO FRENTE Y FONDO 2 1.10 1.40 3.08
LATERALES 2 2.40 1.40 6.72
BUZONETA 2 0.80 0.60 0.96
2 0.60 0.60 0.72
1 0.80 0.80 0.64
VARIOS
ACCESORIOS AL COSTO CAMARA DE CONTACTO Y CLORACION GLB 1 1.00 1.00
CONTROL DE CALIDAD DE CONCRETO
PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 1 1.00 1.00
(HOJA DE METRADOS ACERO DE CAMARA DE CONTACTO Y CLORACION )
PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DIST
CANCHIS-CUSCO"
Armadura 1/4¨ 3/8¨ 1/2¨ 5/8¨
Concepto @
cant. long. ф¨ total. 0.25 0.56 0.994 1.6
CAMARA CONTACTO
Losa Fondo 6 3.15 3/8" 18.9 @ 0.20 10.58
14 1.50 3/8" 21 @ 0.20 11.76
Pared Horizontal 8 3.20 3/8" 25.6 @ 0.20 14.34
8 1.60 3/8" 12.8 @ 0.20 7.17
Pared Vertical 6 1.80 3/8" 10.8 @ 0.20 6.05
14 1.80 3/8" 25.2 @ 0.20 14.11
Placas balfers 6 1.05 1/4" 6.3 @ 0.10 1.58
12 0.40 1/4" 4.8 @ 0.11 1.20
BUZONETA
Pared y losas 7 2.1 3/8" 14.7 @ 0.10 8.23
7 2.1 3/8" 14.7 @ 0.10 8.23
Losa tapa 7 0.55 1/2" 3.85 @ 0.10 3.83
7 0.55 1/2" 3.85 @ 0.10 3.83
ACTO Y CLORACION )
CAMPESINA DE SUTOQ, DISTRITO DE CHECACUPE-

3/4¨ N° de
Parcial kg Obras Sub Total
2.24

10.58 1.00 10.58


11.76 1.00 11.76
14.34 2.00 28.67
7.17 2.00 14.34
6.05 2.00 12.10
14.11 2.00 28.22
1.58 5.00 7.88
1.20 5.00 6.00

8.23 1.00 8.23


8.23 1.00 8.23
3.83 1.00 3.83
3.83 1.00 3.83
90.90 143.66
(HOJA DE METRADOS DE MUROS Y TECHO TANQUE IMHOFF Y FILTRO BIOLOGICO)
PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DIS
DE CHECACUPE-CANCHIS-CUSCO"

descripcion Unid. cant. Largo Ancho Alto


MUROS Y TECHOS
TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL m2 1 184.93
TRAZO NIVELACION Y REPLANTEO m2 1 184.93
MOVIMIENTO DE TIERRAS
RELLENO CON MATERIAL PROPIO m3 1 57.68 2 2.5
CONCRETO SIMPLE
SUB ZAPATA
CONCRETO 1:10 +30% P.G. EN SUB ZAPATAS m3 12 1.50 1.50 0.80
SOBRE CIMIENTOS
CONCRETO FC=175 KG/CM2 m3
6 4.15 0.25 0.30
2 2.25 0.25 0.30
2 3.35 0.25 0.30
2 4.30 0.25 0.30
ENCOFRADO Y DESENCOFRADO m2
12 4.15 0.30
4 2.25 0.30
4 3.35 0.30
4 4.30 0.30
GRADAS Y RAMPA
CONCRETO FC=175 KG/CM2 m3 1 0.58 AREA 0.70
1 0.45 AREA 0.70
1 0.33 AREA 0.70
1 0.27 AREA 0.70
ENCOFRADO Y DESENCOFRADO m2 1 1.05 AREA
1 0.95 AREA
1 0.53 AREA
1 0.6 AREA
CONCRETO ARMADO
VIGA DE CIMENTACION
ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg LONG. COEF.
4 60.564 242.26 1.60
372 1.89 703.08 0.56
CONCRETO FC=210 KG/CM2 m3
6 4.15 0.60 0.40
2 2.25 0.60 0.40
2 3.35 0.60 0.40
2 4.30 0.60 0.40
ZAPATAS
ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg LONG. COEF.
72 1.15 82.80 1.60
60 0.95 57.00 1.60
CONCRETO FC=210 KG/CM2 m3 12 1.20 1.00 0.60

COLUMNAS
ENCOFRADO Y DESENCOFRADO m2 12 1.20 1.45
ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg LONG. COEF.
48 6.5 312.00 0.99
348 1.2 417.60 0.56
CONCRETO FC=210 KG/CM2 m3 12 0.35 0.25 1.85
VIGAS
ENCOFRADO Y DESENCOFRADO m2 2 57.68 0.35
ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg LONG. COEF.
4 60.564 242.26 0.99
372 1.89 703.08 0.56
CONCRETO FC=210 KG/CM2 m3 1 57.68 0.25 0.35
MUROS Y TABIQUES
MURO DE LADRILLO K.K. (ARC. MACIZO. MAN.) - CABEZA m2
6 4.15 1.15
2 2.25 1.15
2 3.35 1.15
2 4.30 1.15
1 18.50
15.75
REVOQUES ENLUCIDOS Y MOLDURAS
TARRAJEO EN EXTERIORES CON CEMENTO-ARENA m2
6 4.15 1.15
2 2.25 1.15
2 3.35 1.15
2 4.30 1.15
1 18.50
1 15.75
4 0.6 1.15
6 0.35 1.15
2 0.25 1.15
1 57.68 0.3
1 57.68 0.35
TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA m2
6 4.15 1.15
2 2.25 1.15
2 3.35 1.15
2 4.30 1.15
1 18.50
1 15.75
6 0.35 1.15
2 0.25 1.15
1 57.68 0.3
1 57.68 0.35
PINTURAS
PINTADO DE MURO EXTERIOR E INTERIOR C/LATEX ACRILICO m2
CARPINTERIA DE MADERA
PUERTA METAL LAC 1/16" C/MARCO 1.14"X1/8" Y REFUERZOS und 1
COBERTURA DE POLICARBONATO DE 10 mm. m2
TRAMO 01 1 9.33 11.30
TRAMO 02 1 4.50 12.20
TRAMO 03 1 4.80 13.10
CORREAS DE TUBO RECTAANGULO DE 60X40X3mm. ML.
TRAMO 01 10 9.70
4 11.30
TRAMO 02 8 4.30
2 3.10
2 4.30
2 12.20
TRAMO 03 12 5.05
2 13.10
TIJERALES DE TUBO RECTANGULAR 100X50X3mm. L=9.25 ML. und 3
TIJERALES DE TUBO RECTANGULAR 100X50X3mm. L=11.45 ML. und 2
PISOS Y PAVIMENTOS
CONCRETO FC=175 KG/CM2 m3 96.5 0.10
VARIOS
PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRES und 3
TRO BIOLOGICO)
AMPESINA DE SUTOQ, DISTRITO

Parcial Sub Total

184.93
184.93

288.40 288.40

21.60 21.60

3.35 3.35
1.87
0.34
0.50
0.65
26.82 26.82
14.94
2.70
4.02
5.16

0.41 1.14
0.32
0.23
0.19
1.05 3.13
0.95
0.53
0.60

781.33 781.33
387.61
393.72
10.73 10.728
5.98
1.08
1.61
2.06

223.68 223.68
132.48
91.20
8.64 8.64

20.88 20.88
543.98 543.98
310.13
233.86
1.94 1.94

40.38 40.38
634.53 634.53
240.80
393.72
20.19 20.188

85.66 85.66
28.64
5.18
7.71
9.89
18.50
15.75

128.90 128.90
28.64
5.18
7.71
9.89
18.50
15.75
2.76
2.42
0.58
17.30
20.19
126.14 126.14
28.64
5.18
7.71
9.89
18.50
15.75
2.42
0.58
17.30
20.19

255.03 255.03

1.00 1.00
223.21 223.21
105.43
54.90
62.88
302.60 302.60
97.00
45.20
34.40
6.20
8.60
24.40
60.60
26.20
3.00 3.00
2.00 2.00

9.65 9.65

3.00 3.00
(HOJA DE METRADOS DE MUROS Y TECHO SECADO DE LODOS)
PROYECTO : "MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DI
DE CHECACUPE-CANCHIS-CUSCO"

descripcion Unid. cant. Largo Ancho Alto


MUROS Y TECHOS
TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL m2 1 11.15 7.35
TRAZO NIVELACION Y REPLANTEO m2 1 11.15 7.35
MOVIMIENTO DE TIERRAS
RELLENO CON MATERIAL PROPIO m3 1 37 1.5 2
CONCRETO SIMPLE
SUB ZAPATA
CONCRETO 1:10 +30% P.G. EN SUB ZAPATAS m3 10 1.50 1.50 0.80
SOBRE CIMIENTOS
CONCRETO FC=175 KG/CM2 m3
6 3.30 0.25 0.30
4 3.35 0.25 0.30
ENCOFRADO Y DESENCOFRADO m2
6 3.30 0.30
4 3.35 0.30
GRADAS Y RAMPA
CONCRETO FC=175 KG/CM2 m3 1 0.58 AREA 0.70
1 0.45 AREA 0.70
1 0.33 AREA 0.70
1 0.27 AREA 0.70
ENCOFRADO Y DESENCOFRADO m2 1 1.05 AREA
1 0.95 AREA
1 0.53 AREA
1 0.6 AREA
CONCRETO ARMADO
VIGA DE CIMENTACION
ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg LONG. COEF.
4 27.85 111.40 1.60
221 1.89 417.69 0.56
CONCRETO FC=210 KG/CM2 m3
6 3.30 0.35 0.40
4 3.35 0.35 0.40
ZAPATAS
ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg LONG. COEF.
60 1.15 69.00 1.60
50 0.95 47.50 1.60
CONCRETO FC=210 KG/CM2 m3 10 1.20 1.00 0.60

COLUMNAS
ENCOFRADO Y DESENCOFRADO m2 10 1.20 1.45
ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg LONG. COEF.
40 3.65 146.00 0.99
207 1.2 248.40 0.56

CONCRETO FC=210 KG/CM2 m3 10 0.35 0.25 1.85


VIGAS
ENCOFRADO Y DESENCOFRADO m2 2 37.8 0.35
ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg LONG. COEF.
4 40.11 160.44 0.99
221 1.89 417.69 0.56
CONCRETO FC=210 KG/CM2 m3 1 37.8 0.25 0.35
MUROS Y TABIQUES
MURO DE LADRILLO K.K. (ARC. MACIZO. MAN.) - CABEZA m2
6 3.30 1.50
3 3.35 1.50
1 2.45 1.50
2 5.20
REVOQUES ENLUCIDOS Y MOLDURAS
TARRAJEO EN EXTERIORES CON CEMENTO-ARENA m2
6 3.30 0.35
4 3.35 0.35
14 0.35 1.50
6 3.30 0.35
4 3.35 0.35
TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA m2
6 3.30 0.35
4 3.35 0.35
10 0.35 1.50
6 3.30 0.35
4 3.35 0.35
PINTURAS
PINTADO DE MURO EXTERIOR E INTERIOR C/LATEX ACRILICO m2
CARPINTERIA DE MADERA
PUERTA METAL LAC 1/16" C/MARCO 1.14"X1/8" Y REFUERZOS und 1
COBERTURA DE POLICARBONATO DE 10 mm. m2
TRAMO 01 1 11.75 9.35
CORREAS DE TUBO RECTAANGULO DE 60X40X3mm. ML.
TRAMO 01 10 11.75
3 9.35
TIJERALES DE TUBO RECTANGULAR 100X50X3mm. L=8.80 ML. und 4
PISOS Y PAVIMENTOS
CONCRETO FC=175 KG/CM2 m3 96.5 0.10
VARIOS
PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRES und 3
LODOS)
AMPESINA DE SUTOQ, DISTRITO

Parcial Sub Total

81.9525 81.95
81.9525 81.95

111.00 111.00

18.00 18.00

2.49 2.49
1.49
1.01
9.96 9.96
5.94
4.02

0.41 1.14
0.32
0.23
0.19
1.05 3.13
0.95
0.53
0.60

412.15 412.15
178.24
233.91
4.65 4.648
2.77
1.88

186.40 186.4
110.40
76.00
7.20 7.2

17.40 17.40
284.23 284.23
145.12
139.10

1.62 1.62

26.46 26.46
393.38 393.38
159.48
233.91
13.23 13.23

53.65 53.65
29.70
15.08
3.68
5.20

30.59 30.59
6.93
4.69
7.35
6.93
4.69
28.49 28.49
6.93
4.69
5.25
6.93
4.69

59.08 59.08

1.00 1.00
109.86 109.86
109.86
145.55 145.55
117.50
28.05
4.00 4.00

9.65 9.65

3.00 3.00
RESUMEN DE HOJA DE METRADOS ALCANTARILLADO
1.- NOMBRE DEL PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DISTRITO DE CHECACUPE-
CANCHIS-CUSCO"
2.- COMUNIDAD: SUTOQ
3.- DISTRITO: CHECACUPE
4.- PROVINCIA: CANCHIS
Nº Medidas Nº DE
Item Descripción Und Vece Cantidad OBRAS
Total
s Largo Ancho Alto
02 SISTEMA DE ALCANTARILLADO
02.01 RED DE DISTRIBUCION
02.01.01 TRABAJOS PROVISIONALES
02.01.01.01 CINTA PLASTICA SEÑALIZADORA PARA LIMITE DE SEGURIDAD DE OBRA m 1 2500.57 2500.57 1.00 2500.57
02.01.01.02 PUENTE DE MADERA PARA PASE PEATONAL DE ZANJAS DURANTE LA EJECU und 1 10.00 10.00 1.00 10.00
02.01.02 TRABAJOS PRELIMINARES
02.01.02.01 LIMPIEZA DE TERRENO MANUAL m2 1 2500.57 0.80 2000.46 1.00 2000.46
02.01.02.02 TRAZO, NIVELES Y REPLANTEO PRELIMINAR KM 1 2.50 2.50 1.00 2.50
02.01.02.03 TRAZO NIVELACION Y REPLANTEO DURANTE LA OBRA KM 1 2.50 2.50 1.00 2.50
02.01.03 MOVIMIENTO DE TIERRAS
02.01.03.01 EXCAVACION DE ZANJAS C/I(MAQ.) TN P/TUB. 8"-12" m3 1 2500.57 0.80 1.64 3282.75 1.00 3282.75
02.01.03.02 EXCAVACION DE ZANJAS PARA BUZONES m3 1 173.00 173.00 1.00 173.00
02.01.03.03 CAMA DE APOYO PARA TUBERIAS 8" A 12" m 1 2500.57 2500.57 1.00 2500.57
02.01.03.04 REFINE DE ZANJA Y CONFORMACION DE FONDOS m 1 2500.57 2500.57 1.00 2500.57
02.01.03.05 RELLENO COMP.ZANJA TERR.NORMAL-P/TUB. 8"-12" m3 1 2970.12 2970.12 1.00 2970.12
02.01.03.06 ENTIBADO DE ZANJAS m 1 750.17 750.17 1.00 750.17
02.01.03.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 1 2500.57 0.04 260.52 1.20 312.63
02.01.04 TENDIDO DE TUBERIAS
02.01.04.01 SUMINISTRO E INST. DE TUBERIA PVC NTP ISO 4435 UF. DE 200 MM INC/ANIL m 1 2500.57 2500.57 1.00 2500.57
02.01.05 CONSTRUCCION DE BUZONES
02.01.05.01 CONCRETO F'C=140 KG/CM2 + 30%P.G.LOSA FONDO m3 1 18.59 18.59 1.00 18.59
02.01.05.02 CONCRETO F'C=175 KG/CM2 PARA MUROS DE BUZON m3 1 66.35 66.35 1.00 66.35
02.01.05.03 CONCRETO F'C=210 KG/CM2. PARA LOSAS TECHO m3 1 16.79 16.79 1.30 21.82
02.01.05.04 CONCRETO F'C=175 KG/CM2 PARA DADO DE ANCLAJE m3 1 0.50 0.40 0.40 0.08 104.00 8.32
02.01.05.05 ACERO DE REFUERZO kg 1777.54 1777.54 1.00 1777.54
02.01.05.06 TAPA DE CONCRETO ARMADO PARA BUZON INC/ANILLO und 1 45.00 45.00 1.00 45.00
02.01.05.07 ENCOFRADO Y DESENCOFRADO NORMAL PARA BUZONES m2 1 409.53 409.53 1.00 409.53
02.01.05.08 ENCOFRADO Y DESENCOFRADO LOSA TECHO DE BUZON m2 1 52.77 52.77 1.00 52.77
02.01.06 PRUEBA HIDRAULICA
02.01.06.01 PRUEBA HIDRAULICA AZANJA ABIERTA m 1 2500.57 2500.57 1.00 2500.57
02.01.06.02 PRUEBA HIDRAULICA AZANJA TAPADA m 1 2500.57 2500.57 1.00 2500.57
02.01.07 INSTALACIONES DOMICILIARIAS ALCANTARILLADO
02.01.07.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR KM 1 6.00 0.006 91.00 0.55
02.01.07.02 EXCAVACION DE ZANJAS PARA TUBERÍAS m3 1 6.00 0.80 1.20 5.76 91.00 524.16
02.01.07.03 INSTALACIONES DOMICILIARIAS - ALCANTARILLADO und 1 1.00 1.00 91.00 91.00
02.01.07.04 CAMA DE APOYO PARA TUBERIAS 8" A 12" m 1 6.00 6.00 91.00 546.00
02.01.07.05 RELLENO COMP.ZANJA TERR.NORMAL-P/TUB. 8"-10" m3 1 6.00 0.80 1.20 5.76 91.00 524.16
02.01.07.06 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 1 6.00 0.02 0.12 91.00 10.92
02.01.08 CONTROL DE CALIDAD DE CONCRETO
02.01.08.01 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 6 6.00 1.00 6.00
02.01.08.02 DISEÑO DE MEZCLA und 3 3.00 1.00 3.00
02.02 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES
02.02.01 CAMARA DE REJAS, MEDIDORDE CAUDAL Y DESARENADOR
02.02.01.01 TRABAJOS PRELIMINARES
02.02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 1 7.25 1.00 7.25
02.02.01.01.02 TRAZO NIVELACION Y REPLANTEO m2 1 7.25 1.00 7.25
02.02.01.01.03 CINTA PLASTICA SEÑALIZADORA PARA LIMITE DE SEGURIDAD DE OBRA m 15.00 1.00 15.00
02.02.01.02 MOVIMIENTO DE TIERRAS
02.02.01.02.01 EXCAVACION C/I(MAQUINAS) TERRENO NORMAL-ESTRUCTURAS m3 1 2.52 1.00 2.52
02.02.01.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 1 5.03 1.00 5.03
02.02.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=5 KM m3 1 3.02 1.00 3.02
02.02.01.03 OBRAS DE CONCRETO SIMPLE
02.02.01.03.01 CONCRETO FC=175 KG/CM2 PARA SOLADOS m3 1 0.50 1.00 0.50
02.02.01.04 OBRAS DE CONCRETO ARMADO
02.02.01.04.01 CONCRETO PARA MUROS FC=210 KG/CM2 m3 1 2.31 1.00 2.31
02.02.01.04.02 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 1 220.08 1.00 220.08
02.02.01.04.03 ENCOFRADO Y DESENCOFRADO MUROS m2 1 21.25 1.00 21.25
02.02.01.05 REVOQUES ENLUCIDOS Y MOLDURAS
02.02.01.05.01 TARRAJEO CON IMPERMEABILIZANTES P/MUROS m2 1 21.25 1.00 21.25
02.02.01.05.02 REJILLA FIERRO 1/2" ESPACIAMIENTO DE 1" und 1 1.00 1.00 1.00
02.02.01.06 COMPUERTAS Y VERTEDORES
02.02.01.06.01 COMPUERTA METALICA TIPO TARJETA DE 0.40 X 0.25 m. und 1 1.00 1.00 1.00
02.02.01.07 CONTROL DE CALIDAD DE CONCRETO
02.02.01.07.01 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 1 1.00 1.00 1.00 1.00
RESUMEN DE HOJA DE METRADOS ALCANTARILLADO
1.- NOMBRE DEL PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DISTRITO DE CHECACUPE-
CANCHIS-CUSCO"
2.- COMUNIDAD: SUTOQ
3.- DISTRITO: CHECACUPE
4.- PROVINCIA: CANCHIS
Nº Medidas Nº DE
Item Descripción Und Vece Cantidad OBRAS
Total
s Largo Ancho Alto
02.02.02 TANQUE IMHOFF
02.02.02.01 TRABAJOS PRELIMINARES
02.02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 1 49.20 1.00 49.20
02.02.02.01.02 TRAZO NIVELACION Y REPLANTEO m2 1 49.20 1.00 49.20
02.02.02.01.03 CINTA PLASTICA SEÑALIZADORA PARA LIMITE DE SEGURIDAD DE OBRA m 1 27.32 1.00 27.32
02.02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.02.01 EXCAVACION C/I(MAQUINAS) TERRENO NORMAL-ESTRUCTURAS m3 1 268.14 1.00 268.14
02.02.02.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 1 49.20 1.00 49.20
02.02.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=5 KM m3 1 321.77 1.00 321.77
02.02.02.03 OBRAS DE CONCRETO SIMPLE
02.02.02.03.01 CONCRETO FC=175 KG/CM2 PARA SOLADOS m3 1 6.60 1.00 6.60
02.02.02.04 OBRAS DE CONCRETO ARMADO
02.02.02.04.01 CONCRETO PARA LOSA DE CIMENTACION FC=210 KG/CM2 m3 1 19.80 1.00 19.80
02.02.02.04.02 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 1 8216.01 1.00 8216.01
02.02.02.04.03 CONCRETO PARA MUROS FC=210 KG/CM2 m3 1 51.76 1.00 51.76
02.02.02.04.04 ENCOFRADO Y DESENCOFRADO MUROS m2 1 230.04 1.00 230.04
02.02.02.04.05 CONCRETO PARA MUROS DEL SEDIMENTADOR FC=210 KG/CM2 m3 1 7.01 1.00 7.01
02.02.02.04.06 ENCOFRADO Y DESENCOFRADO MUROS DE SEDIMENTADOR m2 37.63 1.00 37.63
02.02.02.04.07 CONCRETO PARA CAJA DE SALIDA DE LODOS FC=210 KG/CM2 m3 1 1.25 1.00 1.25
02.02.02.04.08 ENCOFRADO Y DESENCOFRADO CAJA DE SALIDA DE LODOS m2 1 4.34 1.00 4.34
02.02.02.04.09 CONCRETO PARA CAJA DE SALIDA FC=210 KG/CM2 m3 1 0.29 1.00 0.29
02.02.02.04.10 ENCOFRADO Y DESENCOFRADO CAJA DE SALIDA m2 1 1.70 1.00 1.70
02.02.02.04.11 WATER STOP DE NEOPRENE DE 8". PROVISION Y COLOCADO DE JUNTA m 1 44.80 1.00 44.80
02.02.02.05 REVOQUES ENLUCIDOS Y MOLDURAS
02.02.02.05.01 TARRAJEO CON IMPERMEABILIZANTES P/MUROS m2 1 124.26 1.00 124.26
02.02.02.06 INSTALACIONES HIDRAULICAS
02.02.02.06.01 SUMINISTRO E INST. DE TUBERIA PVC NTP ISO 4435 UF. DE 200 MM INC/AN m 1 9.00 1.00 9.00
02.02.02.06.02 SUMINISTRO E INST.DE CODO PVC NTP ISO 4435 UF. DE 200 MM X 45° INC/ und 1 1.00 1.00 1.00
02.02.02.06.03 SUMINISTRO E INST. DE YEE PVC NTP ISO 4435 UF. DE 200 X 200MM. INC/A und 1 1.00 1.00 1.00
02.02.02.06.04 SUMINISTRO E INST. DE VALVULA F°F° DE 200 MM UF. INC/ANILLOS TIPO M m 1 1.00 1.00 1.00
02.02.02.06.05 BAFLE DE PVC DE 1.00 X 1.20 *1/2" und 1 2.00 1.00 2.00
02.02.02.07 CONTROL DE CALIDAD DE CONCRETO
02.02.02.07.01 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 1 3.00 1.00 3.00
02.02.03 FILTRO BIOLOGICO
02.02.03.01 TRABAJOS PRELIMINARES
02.02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 1 44.25 1.00 44.25
02.02.03.01.02 TRAZO NIVELACION Y REPLANTEO m2 1 44.25 1.00 44.25
02.02.03.02 MOVIMIENTO DE TIERRAS
02.02.03.02.01 EXCAVACION C/I(MAQUINAS) TERRENO NORMAL-ESTRUCTURAS m3 1 112.84 1.00 112.84
02.02.03.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 1 44.25 1.00 44.25
02.02.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=5 KM m3 1 135.41 1.00 135.41
02.02.03.03 OBRAS DE CONCRETO SIMPLE
02.02.03.03.01 CONCRETO FC=175 KG/CM2 PARA SOLADOS m3 1 4.43 1.00 4.43
02.02.03.04 OBRAS DE CONCRETO ARMADO
02.02.03.04.01 CONCRETO PARA LOSA DE CIMENTACION FC=210 KG/CM2 m3 1 11.65 1.00 11.65
02.02.03.04.02 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 1 1882.01 1.00 1882.01
02.02.03.04.03 CONCRETO PARA MUROS FC=210 KG/CM2 m3 1 14.30 1.00 14.30
02.02.03.04.04 ENCOFRADO Y DESENCOFRADO MUROS m2 1 114.40 1.00 114.40
02.02.03.04.05 CONCRETO PARA CANAL CENTRAL FC=210 KG/CM2 m3 1 1.50 1.00 1.50
02.02.03.04.06 ENCOFRADO Y DESENCOFRADO CANAL CENTRAL m2 1 1.18 1.00 1.18
02.02.03.05 REVOQUES ENLUCIDOS Y MOLDURAS
02.02.03.05.01 TARRAJEO CON IMPERMEABILIZANTES 1:2 e=1.5 cm. m2 1 98.45 1.00 98.45
02.02.03.06 VARIOS
02.02.03.06.01 ENCOFRADO Y DESENCOFRADO m2 1 4.16 1.00 4.16
02.02.03.06.02 DADO DE SOPORTE CONCRETO FC=210 KG/CM2 m3 1 0.21 1.00 0.21
02.02.03.06.03 LOSA PRE FABRICADA C° A° CON ORIFICIOS und 1 24.00 1.00 24.00
02.02.03.06.04 FILTRO DE CANTO RODADO DE 6" m3 1 28.00 1.00 28.00
02.02.03.06.05 FILTRO DE CANTO RODADO DE 3" m3 1 14.00 1.00 14.00
02.02.03.06.06 FILTRO DE CANTO RODADO DE 1" m3 1 5.25 1.00 5.25
02.02.03.06.07 TUBERIA PVC SAP DN: 4" C-10 PERFORADA PARA RIEGO m 1 60.50 1.00 60.50
02.02.03.06.08 SUMINISTRO E INST. DE VALVULA F°F° DE 200 MM UF. INC/ANILLOS TIPO M und 1 1.00 1.00 1.00
RESUMEN DE HOJA DE METRADOS ALCANTARILLADO
1.- NOMBRE DEL PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DISTRITO DE CHECACUPE-
CANCHIS-CUSCO"
2.- COMUNIDAD: SUTOQ
3.- DISTRITO: CHECACUPE
4.- PROVINCIA: CANCHIS
Nº Medidas Nº DE
Item Descripción Und Vece Cantidad OBRAS
Total
s Largo Ancho Alto
02.02.03.07 CAJA DE INGRESO Y SALIDA
02.02.03.07.01 CONCRETO PARA CAJA DE ENTRADA/SALIDA FC=210 KG/CM2 m3 1 1.62 1.00 1.62
02.02.03.07.02 ENCOFRADO Y DESENCOFRADO CAJAS m2 1 16.47 1.00 16.47
02.02.03.07.03 TARRAJEO CON IMPERMEABILIZANTES 1:2 e=1.5 cm. m2 1 16.47 1.00 16.47
02.02.03.07.04 CONCRETO PARA CANAL DE DIST. FC=210 KG/CM2 m3 1 0.32 1.00 0.32
02.02.03.07.05 ENCOFRADO Y DESENCOFRADO CANAL DE DIST. m2 1 5.25 1.00 5.25
02.02.03.07.06 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 1 284.46 1.00 284.46
02.02.03.07.07 TAPA PRE FABRICADA DE C° A° INGRESO Y SALIDA und 1 2.00 1.00 2.00
02.02.03.07.08 MADERA TRATADA PARA VERTEDERO e=2" m2 1 0.36 1.00 0.36
02.02.03.08 CONTROL DE CALIDAD DE CONCRETO
02.02.03.08.01 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 1 3.00 1.00 3.00
02.02.04 LECHO DE SECADOS
02.02.04.01 TRABAJOS PRELIMINARES
02.02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 1 47.35 1.00 47.35
02.02.04.01.02 TRAZO NIVELACION Y REPLANTEO m2 1 47.35 1.00 47.35
02.02.04.02 MOVIMIENTO DE TIERRAS
02.02.04.02.01 EXCAVACION C/I(MAQUINAS) TERRENO NORMAL-ESTRUCTURAS m3 1 50.85 1.00 50.85
02.02.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 1 47.35 1.00 47.35
02.02.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=5 KM m3 1 61.02 1.00 61.02
02.02.04.03 OBRAS DE CONCRETO SIMPLE
02.02.04.03.01 CONCRETO FC=175 KG/CM2 PARA SOLADOS m3 1 6.51 1.00 6.51
02.02.04.04 OBRAS DE CONCRETO ARMADO
02.02.04.04.01 CONCRETO PARA MUROS FC=210 KG/CM2 m3 1 22.00 1.00 22.00
02.02.04.04.02 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 1 2025.31 1.00 2025.31
02.02.04.04.03 ENCOFRADO Y DESENCOFRADO MUROS m2 1 235.35 1.00 235.35
02.02.04.04.04 TARRAJEO CON IMPERMEABILIZANTES P/MUROS m2 1 235.35 1.00 235.35
02.02.04.04.05 CONCRETO PARA PARED SALPICADORA FC=210 KG/CM2 m3 1 0.14 1.00 0.14
02.02.04.04.06 ENCOFRADO Y DESENCOFRADO PARED SALPICADORA m2 1 2.71 1.00 2.71
02.02.04.04.07 CONCRETO PARA CANAL CENTRAL FC=210 KG/CM2 m3 1 2.11 1.00 2.11
02.02.04.04.08 TAPA PRE FABRICADA DE C° A° DE 0.35 X 0.35 m. P/CANALCENTRAL und 1 20.00 1.00 20.00
02.02.04.05 ARCILLA PARA LOSA DE FONDO
02.02.04.05.01 ARCILLA P/LECHO DE SECADOS (LOSA DE FONDO) m3 1 6.51 1.00 6.51
02.02.04.06 VARIOS
02.02.04.06.01 SUMINISTRO E INST. DE TUBERIA PVC NTP ISO 4435 UF. DE 200 MM INC/AN m 1 5.00 1.00 5.00
02.02.04.06.02 SUMINISTRO E INST.DE CODO PVC NTP ISO 4435 UF. DE 200 MM X 90° INC/ und 1 2.00 1.00 2.00
02.02.04.06.03 TUBERIA PVC NTP ISO 4422 UF. DE 110 MM. C-10 INC/ANILLOS ML 1 2.50 1.00 2.50
02.02.04.06.04 GRAVA P/LECHO DE SECADOS D=3/4" - 2" m3 1 7.84 1.00 7.84
02.02.04.06.05 GRAVA P/LECHO DE SECADOS D=1/4" m3 1 5.88 1.00 5.88
02.02.04.06.06 GRAVA P/LECHO DE SECADOS D=1/16" m3 1 3.92 1.00 3.92
02.02.04.06.07 COBERTURA DE LADRILLO KK P/LECHO DE SECADOS m2 1 39.20 1.00 39.20
02.02.04.07 CONTROL DE CALIDAD DE CONCRETO
02.02.04.07.01 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 1 3.00 1.00 3.00
02.02.05 CAMARA DE CONTACTO Y CLORACION
02.02.05.01 TRABAJOS PRELIMINARES
02.02.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1 7.27 1.00 7.27
02.02.05.01.02 TRAZO NIVELACION Y REPLANTEO m2 1 7.27 1.00 7.27
02.02.05.02 MOVIMIENTO DE TIERRAS
02.02.05.02.01 EXCAVACION C/I(MAQUINAS) TERRENO NORMAL-ESTRUCTURAS m3 1 9.32 1.00 9.32
02.02.05.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 1 7.27 1.00 7.27
02.02.05.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=5 KM m3 1 11.19 1.00 11.19
02.02.05.03 OBRAS DE CONCRETO SIMPLE
02.02.05.03.01 CONCRETO FC=175 KG/CM2 PARA SOLADOS m3 1 0.58 1.00 0.58
02.02.05.04 OBRAS DE CONCRETO ARMADO
02.02.05.04.01 ENCOFRADO Y DESENCOFRADO m2 1 21.04 1.00 21.04
02.02.05.04.02 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 1 143.66 1.00 143.66
02.02.05.04.03 CONCRETO FC=210 KG/CM2 m3 1 2.18 1.00 2.18
02.02.05.05 REVOQUES ENLUCIDOS Y MOLDURAS
02.02.05.05.01 TARRAJEO CON IMPERMEABILIZANTES P/MUROS m2 1 14.87 1.00 14.87
02.02.05.06 VARIOS
02.02.05.06.01 ACCESORIOS AL COSTO CAMARA DE CONTACTO Y CLORACION GLB 1 1.00 1.00 1.00
02.02.05.07 CONTROL DE CALIDAD DE CONCRETO
02.02.05.07.01 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 1 1.00 1.00 1.00
02.02.06 TUBERIA DE INTERCONEXION Y EVACUACION
02.02.06.01 TRABAJOS PRELIMINARES
02.02.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 1 49.50 1.00 49.50 1.00 49.50
02.02.06.01.02 TRAZO, NIVELES Y REPLANTEO PRELIMINAR KM 1 0.05 1.00 0.05
RESUMEN DE HOJA DE METRADOS ALCANTARILLADO
1.- NOMBRE DEL PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DISTRITO DE CHECACUPE-
CANCHIS-CUSCO"
2.- COMUNIDAD: SUTOQ
3.- DISTRITO: CHECACUPE
4.- PROVINCIA: CANCHIS
Nº Medidas Nº DE
Item Descripción Und Vece Cantidad OBRAS
Total
s Largo Ancho Alto
02.02.06.01.03 TRAZO NIVELACION Y REPLANTEO DURANTE LA OBRA KM 1 0.05 1.00 0.05
02.02.06.02 MOVIMIENTO DE TIERRAS
02.02.06.02.01 EXCAVACION DE ZANJAS TERRENO NORMAL TUBERÍA MENORES 8" - 10" m3 1 49.50 0.80 1.20 47.52 1.00 47.52
02.02.06.02.02 REFINE DE ZANJA Y CONFORMACION DE FONDOS m 1 49.50 49.50 1.00 49.50
02.02.06.02.03 CAMA DE APOYO PARA TUBERIAS 8" A 12" m 1 49.50 49.50 1.00 49.50
02.02.06.02.04 RELLENO COMP.ZANJA TERR.NORMAL-P/TUB. 8"-10" m3 1 49.50 0.80 1.20 47.52 1.00 47.52
02.02.06.03 TENDIDO DE TUBERIAS
02.02.06.03.01 SUMINISTRO E INST. DE TUBERIA PVC NTP ISO 4435 UF. DE 200 MM INC/AN m 1 49.50 49.50 1.00 49.50
02.02.06.04 CAJA DE REPARTICION
02.02.06.04.01 LIMPIEZA DE TERRENO MANUAL m2 2 1.00 1.00 2.00 1.00 2.00
02.02.06.04.02 TRAZO NIVELACION Y REPLANTEO m2 2 1.00 1.00 2.00 1.00 2.00
02.02.06.04.03 EXCAVACION C/I(MAQUINAS) TERRENO NORMAL-ESTRUCTURAS m3 2 1.00 1.00 1.20 2.40 1.00 2.40
02.02.06.04.04 NIVELACION INTERIOR APISONADO MANUAL m2 2 1.00 1.00 2.00 1.00 2.00
02.02.06.04.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=5 KM m3 1 2.40 1.20 2.88 1.00 2.88
02.02.06.04.06 CONCRETO FC=175 KG/CM2 PARA SOLADOS m3 1 1.00 1.00 0.10 0.10 2.00 0.20
02.02.06.04.07 ENCOFRADO Y DESENCOFRADO m2 1 4.34 2.00 8.68
02.02.06.04.08 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 1 63.22 1.00 63.22
02.02.06.04.09 CONCRETO FC=210 KG/CM2 m3 1 1.25 2.00 2.51
02.02.06.04.10 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 1 1.00 1.00 1.00
02.02.07 ZANJA DE PERCOLACION
02.02.07.01 LIMPIEZA DE TERRENO MANUAL m2 1 7.50 1.00 7.50 1.00 7.50
02.02.07.02 TRAZO, NIVELES Y REPLANTEO PRELIMINAR KM 1 0.01 1.00 0.01
02.02.07.03 EXCAVACION DE ZANJAS TERRENO NORMAL TUBERÍA MENORES 8" - 10" m3 1 7.50 0.90 1.20 8.10 1.00 8.10
02.02.07.04 REFINE DE ZANJA Y CONFORMACION DE FONDOS m 1 7.50 7.50 1.00 7.50
02.02.07.05 SUMINISTRO E INST. DE TUBERIA PVC NTP ISO 4422 UF. DE 110 MM. C-10 INC ML 1 7.50 7.50 1.00 7.50
02.02.07.06 RELLENO CON GRAVA FINA m3 1 1 7.50 0.90 0.70 4.73 3.31
02.02.07.07 RELLENO COMP.ZANJA TERR.NORMAL-P/TUB. 8"-10" m3 1 1 7.50 0.90 0.50 3.38 1.69
02.02.08 CERCO PERIMETRICO DE MALLA OLIMPICA
02.02.08.01 TRABAJOS PRELIMINARES
02.02.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 1 102.00 1.20 122.40 1.00 122.40
02.02.08.01.02 TRAZO NIVELACION Y REPLANTEO m2 1 102.00 1.20 122.40 1.00 122.40
02.02.08.02 MOVIMIENTO DE TIERRAS
02.02.08.02.01 EXCAVACION PARA ESTRUCTURAS A MANO m3 1 102.00 0.40 0.50 20.40 1.00 20.40
02.02.08.03 CONTROL DE CALIDAD DE CONCRETO
02.02.08.03.01 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 1 1.00 1.00 1.00
02.02.08.04 OBRAS DE CONCRETO SIMPLE
02.02.08.04.01 CONCRETO FC=175 KG/CM2 + 30% PG. PARA CIMIENTO CORRIDO m3 1 102.00 0.40 0.50 20.40 1.00 20.40
02.02.08.04.02 CONCRETO FC=175 KG/CM2 PARA SARDINELES m3 1 99.00 0.20 0.20 3.96 1.00 3.96
02.02.08.04.03 ENCOFRADO Y DESENCOFRADO m2 2 99.00 0.20 39.60 1.00 39.60
02.02.08.04.04 TARRAJEO EN EXTERIORES CON CEMENTO-ARENA m2 2 99.00 0.20 39.60 1.00 39.60
02.02.08.05 CARPINTERIA METALICA
02.02.08.05.01 COLOCADO DE TUBO GALVANIZADO DE 3" PARA COLUMNAS und 36 36.00 1.00 36.00
02.02.08.05.02 MALLA OLIMPICA m2 1 102.00 2.00 204.00 1.00 204.00
02.02.08.05.03 ANGULAR DE 2 X 2 X 3/16" m 36 10.00 360.00 1.00 360.00
02.02.08.05.04 ALAMBRE DE PUAS m 2 102.00 204.00 1.00 204.00
02.02.09 ENROCADO PARA PROTECCION
02.02.09.01 TRABAJOS PRELIMINARES
02.02.09.01.01 LIMPIEZA DE TERRENO MANUAL m2 1 65.00 3.00 195.00 1.00 195.00
02.02.09.01.02 TRAZO NIVELACION Y REPLANTEO m2 1 65.00 3.00 195.00 1.00 195.00
02.02.09.02 MOVIMIENTO DE TIERRAS
02.02.09.02.01 EXCAVACION PARA ESTRUCTURAS A MANO m3 1 65.00 1.50 1.20 117.00 1.00 117.00
02.02.09.02.02 ELIMINACION DE MAT. EXCED. CARGUIO MANUAL DMAX. 50 M. m3 1 117.00 1.20 140.40 1.00 140.40
02.02.09.03 CONCRETO SIMPLE
02.02.09.03.01 MANPOSTERIA DE PIEDRA m3 1 65.00 1.00 1.50 97.50 1.00 97.50
02.02.10 AREA VERDE EN LA PTAR
02.02.10.01 SEMBRIO DE GRASS m2 1 26.00 12.00 312.00 1.00 312.00
02.02.10.02 CERCO VIVO m 1 99.00 99.00 1.00 99.00
02.02.11 EMISOR
02.02.11.01 LINEA EMISORA
02.02.11.01.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR KM 1 100.00 0.10 1.00 0.10
02.02.11.01.02 EXCAVACION DE ZANJAS PARA TUBERÍAS m3 1 100.00 0.80 1.20 96.00 1.00 96.00
02.02.11.01.03 REFINE DE ZANJA Y CONFORMACION DE FONDOS m 1 100.00 100.00 1.00 100.00
02.02.11.01.04 CAMA DE APOYO PARA TUBERIAS 8" A 12" m 1 100.00 100.00 1.00 100.00
02.02.11.01.05 SUMINISTRO E INST. DE TUBERIA PVC NTP ISO 4435 UF. DE 200 MM INC/AN m 1 100.00 100.00 1.00 100.00
02.02.11.01.06 RELLENO COMP.ZANJA TERR.NORMAL-P/TUB. 8"-10" m3 1 100.00 0.80 1.20 96.00 1.00 96.00
02.02.11.01.07 PRUEBA HIDRAULICA AZANJA ABIERTA m 1 100.00 100.00 1.00 100.00
RESUMEN DE HOJA DE METRADOS ALCANTARILLADO
1.- NOMBRE DEL PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DISTRITO DE CHECACUPE-
CANCHIS-CUSCO"
2.- COMUNIDAD: SUTOQ
3.- DISTRITO: CHECACUPE
4.- PROVINCIA: CANCHIS
Nº Medidas Nº DE
Item Descripción Und Vece Cantidad OBRAS
Total
s Largo Ancho Alto
02.02.11.01.08 PRUEBA HIDRAULICA AZANJA TAPADA m 1 100.00 100.00 1.00 100.00
02.02.11.02 CONSTRUCCION DE BUZONES
02.02.11.02.01 EXCAVACION DE ZANJAS PARA BUZONES m3 1 2.81 3.00 8.43
02.02.11.02.02 CONCRETO F'C=140 KG/CM2 + 30%P.G.LOSA FONDO m3 1 0.40 3.00 1.21
02.02.11.02.03 CONCRETO F'C=175 KG/CM2 PARA MUROS DE BUZON m3 1 1.05 3.00 3.15
02.02.11.02.04 CONCRETO F'C=210 KG/CM2. PARA LOSAS TECHO m3 1 0.36 3.00 1.08
02.02.11.02.05 CONCRETO F'C=175 KG/CM2 PARA DADO DE ANCLAJE m3 1 0.16 3.00 0.48
02.02.11.02.06 ACERO DE REFUERZO kg 1 36.64 3.00 109.92
02.02.11.02.07 TAPA DE CONCRETO ARMADO PARA BUZON INC/ANILLO und 1 1.00 3.00 3.00
02.02.11.02.08 ENCOFRADO Y DESENCOFRADO NORMAL PARA BUZONES m2 1 4.52 3.00 13.56
02.02.11.02.09 ENCOFRADO Y DESENCOFRADO LOSA TECHO DE BUZON m2 1 1.13 3.00 3.39
02.02.12 MUROS Y TECHOS TANQUE IMHOFF Y FITRO BIOLOGICO
02.02.12.01 TRABAJOS PRELIMINARES
02.02.12.01.01 LIMPIEZA DE TERRENO MANUAL m2 184.93 1 184.93
02.02.12.01.02 TRAZO NIVELACION Y REPLANTEO m2 184.93 1 184.93
02.02.12.02 MOVIMIENTO DE TIERRAS
02.02.12.02.01 RELLENO CON MATERIAL PROPIO m3 288.40 1 288.40
02.02.12.03 CONCRETO SIMPLE
02.02.12.03.01 SUB ZAPATA
02.02.12.03.01.01 CONCRETO 1:10 +30% P.G. EN SUB ZAPATAS m3 21.60 1 21.60
02.02.12.03.02 SOBRE CIMIENTOS
02.02.12.03.02.01 CONCRETO FC=175 KG/CM2 m3 3.35 1 3.35
02.02.12.03.02.02 ENCOFRADO Y DESENCOFRADO m2 26.82 1 26.82
02.02.12.03.03 GRADAS Y RAMPA
02.02.12.03.03.01 CONCRETO FC=175 KG/CM2 m3 1.14 1 1.14
02.02.12.03.03.02 ENCOFRADO Y DESENCOFRADO m2 3.13 1 3.13
02.02.12.04 CONCRETO ARMADO
02.02.12.04.01 VIGA DE CIMENTACION
02.02.12.04.01.01 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 781.33 1 781.33
02.02.12.04.01.02 CONCRETO FC=210 KG/CM2 m3 8.64 1 8.64
02.02.12.04.02 ZAPATAS
02.02.12.04.03 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 223.68 1 223.68
02.02.12.04.04 CONCRETO FC=210 KG/CM2 m3 8.64 1 8.64
02.02.12.04.05 COLUMNAS
02.02.12.04.06 ENCOFRADO Y DESENCOFRADO m2 20.88 1 20.88
02.02.12.04.07 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 543.98 1 543.98
02.02.12.04.08 CONCRETO FC=210 KG/CM2 m3 1.94 1 1.94
02.02.12.04.09 VIGAS
02.02.12.04.10 ENCOFRADO Y DESENCOFRADO m2 40.38 1 40.38
02.02.12.04.11 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 634.53 1 634.53
02.02.12.04.12 CONCRETO FC=210 KG/CM2 m3 20.19 1 20.19
02.02.12.05 MUROS Y TABIQUES
02.02.12.05.01 MURO DE LADRILLO K.K. (ARC. MACIZO. MAN.) - CABEZA m2 85.66 1 85.66
02.02.12.06 REVOQUES ENLUCIDOS Y MOLDURAS
02.02.12.06.01 TARRAJEO EN EXTERIORES CON CEMENTO-ARENA m2 128.90 1 128.90
02.02.12.06.02 TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA m2 126.14 1 126.14
02.02.12.07 PINTURAS
02.02.12.07.01 PINTADO DE MURO EXTERIOR E INTERIOR C/LATEX ACRILICO (SUPERLATEXm2 255.03 1 255.03
02.02.12.08 CARPINTERIA METALICA
02.02.12.08.01 PUERTA METAL LAC 1/16" C/MARCO 1.14"X1/8" Y REFUERZOS und 1.00 1 1.00
02.02.12.08.02 COBERTURA DE POLICARBONATO DE 10 mm. m2 223.21 1 223.21
02.02.12.08.03 CORREAS DE TUBO RECTAANGULO DE 60X40X3mm. ML. 302.60 1 302.60
02.02.12.08.04 TIJERALES DE TUBO RECTANGULAR 100X50X3mm. L=11.45 ML. und 3.00 1 3.00
02.02.12.08.05 TIJERALES DE TUBO RECTANGULAR 100X50X3mm. L=11.45 ML. und 2.00 1 2.00
02.02.12.09 PISOS Y PAVIMENTOS
02.02.12.09.01 CONCRETO FC=175 KG/CM2 m3 9.65 1 9.65
02.02.12.10 VARIOS
02.02.12.10.01 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 3.00 1 3.00
02.02.13 MUROS Y TECHOS SECADO DE LODOS
02.02.13.01 TRABAJOS PRELIMINARES
02.02.13.01.01 LIMPIEZA DE TERRENO MANUAL m2 81.95 1 81.95
02.02.13.01.02 TRAZO NIVELACION Y REPLANTEO m2 81.95 1 81.95
02.02.13.02 MOVIMIENTO DE TIERRAS
02.02.13.02.01 RELLENO CON MATERIAL PROPIO m3 111.00 1 111.00
02.02.13.03 CONCRETO SIMPLE
02.02.13.03.01 SUB ZAPATA
RESUMEN DE HOJA DE METRADOS ALCANTARILLADO
1.- NOMBRE DEL PROYECTO :"MEJORAMIENTO Y AMPLIACION DEL SANEAMIENTO BASICO DE LA COMUNIDAD CAMPESINA DE SUTOQ, DISTRITO DE CHECACUPE-
CANCHIS-CUSCO"
2.- COMUNIDAD: SUTOQ
3.- DISTRITO: CHECACUPE
4.- PROVINCIA: CANCHIS
Nº Medidas Nº DE
Item Descripción Und Vece Cantidad OBRAS
Total
s Largo Ancho Alto
02.02.13.03.01.01 CONCRETO 1:10 +30% P.G. EN SUB ZAPATAS m3 18.00 1 18.00
02.02.13.03.02 SOBRE CIMIENTOS 1 0.00
02.02.13.03.02.01 CONCRETO FC=175 KG/CM2 m3 2.49 1 2.49
02.02.13.03.02.02 ENCOFRADO Y DESENCOFRADO m2 9.96 1 9.96
02.02.13.03.03 GRADAS Y RAMPA
02.02.13.03.03.01 CONCRETO FC=175 KG/CM2 m3 1.14 1 1.14
02.02.13.03.03.02 ENCOFRADO Y DESENCOFRADO m2 3.13 1 3.13
02.02.13.04 CONCRETO ARMADO
02.02.13.04.01 VIGA DE CIMENTACION
02.02.13.04.01.01 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 412.15 1 412.15
02.02.13.04.01.02 CONCRETO FC=210 KG/CM2 m3 4.65 1 4.65
02.02.13.04.02 ZAPATAS
02.02.13.04.02.01 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 186.40 1 186.40
02.02.13.04.02.02 CONCRETO FC=210 KG/CM2 m3 7.20 1 7.20
02.02.13.04.03 COLUMNAS
02.02.13.04.03.01 ENCOFRADO Y DESENCOFRADO m2 17.40 1 17.40
02.02.13.04.03.02 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 284.23 1 284.23
02.02.13.04.03.03 CONCRETO FC=210 KG/CM2 m3 1.62 1 1.62
02.02.13.04.04 VIGAS
02.02.13.04.04.01 ENCOFRADO Y DESENCOFRADO m2 26.46 1 26.46
02.02.13.04.04.02 ACERO DE REFUERZO F`Y = 4200 Kg/Cm2 kg 393.38 1 393.38
02.02.13.04.04.03 CONCRETO FC=210 KG/CM2 m3 13.23 1 13.23
02.02.13.05 MUROS Y TABIQUES
02.02.13.05.01 MURO DE LADRILLO K.K. (ARC. MACIZO. MAN.) - CABEZA m2 53.65 1 53.65
02.02.13.06 REVOQUES ENLUCIDOS Y MOLDURAS
02.02.13.06.01 TARRAJEO EN EXTERIORES CON CEMENTO-ARENA m2 30.59 1 30.59
02.02.13.06.02 TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA m2 28.49 1 28.49
02.02.13.07 PINTURAS
02.02.13.07.01 PINTADO DE MURO EXTERIOR E INTERIOR C/LATEX ACRILICO (SUPERLATEXm2 59.08 1 59.08
02.02.13.08 CARPINTERIA METALICA
02.02.13.08.01 PUERTA METAL LAC 1/16" C/MARCO 1.14"X1/8" Y REFUERZOS und 1.00 1 1.00
02.02.13.08.02 COBERTURA DE POLICARBONATO DE 10 mm. m2 109.86 1 109.86
02.02.13.08.03 CORREAS DE TUBO RECTAANGULO DE 60X40X3mm. ML. 145.55 1 145.55
02.02.13.08.04 TIJERALES DE TUBO RECTANGULAR 100X50X3mm. L=8.80 ML. und 4.00 1 4.00
02.02.13.09 PISOS Y PAVIMENTOS
02.02.13.09.01 CONCRETO FC=175 KG/CM2 m3 9.65 1 9.65
02.02.13.10 VARIOS
02.02.13.01.01 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 3.00 1 3.00
02.03 FLETE TERRESTRE ALCANTARILLADO
02.03.01 FLETE TERRESTRE ALCANTARILLADO GLB 1 1.00 1.00 1.00
02.03.02 FLETE RURAL ALCANTARILLADO GLB 1 1.00 1.00 1.00
02.03.03 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA PESADA GLB 1 1.00 1.00 1.00
02.04 ACTIVIDADES DE MITIGACION Y DE CAPACITACION
02.04.01 MITIGACION DE IMPACTO AMBIENTAL
02.04.01.01 PERFILADO Y NIVELACION EN ZONA DE TRABAJO m2 1 2500.57 5.00 1.20 15003.42 1.00 15003.42
02.04.01.02 LIMPIEZA FINAL DE OBRA m2 1 35.00 25.00 875.00 1.00 875.00
02.04.02 CAPACITACION
02.04.02.01 CAPACITACION GLB 1 1.00 1.00 1.00
02.04.03 PLAN DE MONITOREO ARQUEOLOGICO
02.04.03.01 MONITOREO ARQUEOLOGICO GLB 1 1.00 1.00 1.00