CALCULO DE TRANSPORTE DE MATERIALES

1- DATOS GENERALES

A-POR PESO

MATERIALES UNIDAD CANTIDAD PESO.UNIT. PESO.TOTAL


CEMENTO BL. 906.38 42.50 38,521.15
FIERRO, CLAV. ETC KG 1,373.00 1.00 1,373.00
YESO BL 34.00 25.00 850.00
MADERA EUCALIPTO UND 0.00 15.00 0.00
MADERA PARA ENCOFRADO P2 2,865.00 1.50 4,297.50
TAPA METALICA 3/16", 0.60X0.60 M.UND 0.00 10.00 0.00
ASFALTO RC-250 GL. 386.00 4.00 1,544.00
PINTURA ESMALTE GL 5.00 4.00 20.00
GASOLINA Y PETROLEO GL. 840.56 4.00 3,362.23
ADITIVOS, ACELER. IMPERM. GL. 250.00 4.00 1,000.00
OTROS 1,500.00 1.00 1,500.00

PESO TOTAL 52,467.88

B-POR VOLUMEN

EN AGREGADOS
DESCRIPC. UNIDAD AFECTOS IGV SIN IGV
ARENA FINA M3 0.00
ARENA GRUESA M3 0.00
PIEDRA MEDIANA M3 0.00
FILTRO DE GRAVA M3 0.00
HORMIGÓN M3 0.00

VOLUMEN TOTAL
CAPACIDAD DEL CAMION (M3) 12.00
NUMERO DE VIAJES
REDONDEO POR VIAJE POR TIPO DE AGREGADO 0.00

EN TUBERIA UNIDAD DE (2.20 M. x 6.00 M.) DE CARROCERIA, CON H= 1.50 M.


CAPACIDAD DEL CAMION EN TUBOS / VIAJE ML No de tubos No VIAJES
Tub, 1/2" 5,050.00 U - 0.00 0.00
Tub, 3/4" 4,200.00 U - 0.00 0.00
Tub, 1" 3,360.00 U - 0.00 0.00
Tub,1 1/2" 1,690.00 U - 0.00 0.00
Tub 2:" 994.00 U - 0.00 0.00
Tub, 3" 470.00 U 997.00 167.56 0.36
Tub 4": 259.00 U 217.00 36.47 0.14
Tub 6:" U-PVC 110.00 U - 0.00 0.00
Tub 8" U-PVC 65.00 U
Tub 6'; CSN 160.00 U - 0.00 0.00
Tub 8'; CSN 80.00 U
NUMERO TOTAL DE VIAJES 0.50
REDONDEO 1.00
TUBERIA EN VOLUMEN 8

2- FLETE TERRESTRE

UNIDAD DE TRANSPORTE
UNIDAD QUE DA COMPROBANTE UNIDAD QUE NO DA COMPROBANTE
CAPACIDAD DEL CAMION ( TN ) 12.00 CAPACIDAD DEL VOLQUETE ( M3 ) 12.00
COSTO POR VIAJE S/. 1,300.00 COSTO POR VIAJE S/. 0.00
CAPACIDAD DEL CAMION (KG) 12,000.00
FLETE POR KG 0.17 FLETE POR M3 0.00

AFECTO IGV SIN IGV FLETE POR PESO =Peso Total * Flete por peso
FLETE POR PESO 10,219.54 FLETE POR VOLUMEN=No viajes*costo por viaje
FLETE POR VOLUMEN
AGREGADOS 0.00
TUBERIA 280.46
COSTO TOTAL FLETE TERR. 10,500.00 0.00

RESUMEN FLETE TOTAL

AFECTO IGV SIN IGV


FLETE TERRESTRE 10,500.00
FLETE MANUAL 0.00
FLETE EN ACEMILA 0.00
FLETES TOTALES S/. 10,500.00 0.00
CALCULO DE FLETE RURAL

1- DATOS GENERALES

A-POR PESO

COSTO
CANTIDAD Nº DE POR PESO.TOT
MATERIALES UNIDAD CANTIDAD POR VIAJE VIAJES VIAJE AL
CEMENTO BL. 906.38 18.00 50.35 30.00 1,510.63
FIERRO, CLAV. ETC KG 1,373.00 65.00 21.12 30.00 633.69
MADERA PARA ENCOFRADO P2 369.00 50.00 7.38 30.00 221.40
0.00
Tub 2" UND 613.00 2.00 58.00 30.00 1,740.00
Tub 3/4" UND 52.00 1.00 85.00 30.00 2,550.00
45.75

PESO TOTAL 4,401.48

B-POR VOLUMEN

EN AGREGADOS
CANTIDAD Nº VIAJES COSTO COSTO
DESCRIPC. UNIDAD (M3) DISTRIB POR VIAJE TOTAL
ARENA FINA M3 6.57 13.14 30.00 394.16
ARENA GRUESA M3 41.14 20.57 30.00 617.16
HORMIGON M3 31.48 15.74 30.00 472.20
PIEDRA ZARANDEADA DE 1/2" M3 61.00 30.50 30.00 915.00

VOLUMEN TOTAL 140.19 79.95 2,398.52


CAPACIDAD DEL VIAJE 1.00
NUMERO 79.95

RESUMEN FLETE TOTAL

AFECTO IGV
FLETE DISTRIBUCION DE MATERIALES 4,401.48
FLETE DE DISTRIBUCION DE AGREGADOS 2,398.52
FLETES TOTALES S/. 6,800.00

El traslado de materiales y agregados sera realizada hasta pie de obra, según la ubicación en planos
sera trasladado en camion 4 toneladas de capacidad