Documentos de Académico
Documentos de Profesional
Documentos de Cultura
: MANTENIMIENTO PERIODICO RUTA JU-114 EMP. PE-24 A (CALABAZA) - APALLA CALABAZA - ULLIMARCA - BADOPAMPA - HUANCAMACHAY - UNION
PROYECTO PROGRESO - MANZANAYO - SAN IGNACIO - PUCACOCHA - EMP. JU-108 (MATAPA)
RUTA : JU - 114
ACTIVIDAD: 03.00 TRANSPORTE
FECHA: : NOVIEMBRE 2017
: MANTENIMIENTO PERIODICO RUTA JU-114 EMP. PE-24 A (CALABAZA) - APALLA CALABAZA - ULLIMARCA - BADOPAMPA - HUANCAMACHAY - UNION PROGRESO - MANZANAYO - SAN
PROYECTO
IGNACIO - PUCACOCHA - EMP. JU-108 (MATAPA)
RUTA : JU - 114
ACTIVIDAD: 03.00 TRANSPORTE
FECHA: NOVIEMBRE 2017
SUSTENTO DE METRADOS TRANSPORTE DE MATERIAL GRANULAR
52+355
0+000
13+000.00 14+000.00 C-3 16.919 100.00% 0.00 0.12 3.30 1,000.00 3.80 3,800.00 0.00 0.12 456.00 1,504.34 456.00 1,048.34
14+000.00 15+000.00 C-3 16.919 100.00% 0.00 0.12 2.30 1,000.00 4.50 4,500.00 0.00 0.12 540.00 1,241.46 540.00 701.46
15+000.00 16+000.00 C-3 16.919 100.00% 0.00 0.12 1.30 1,000.00 4.00 4,000.00 0.00 0.12 480.00 623.52 480.00 143.52
16+000.00 17+000.00 C-3 16.919 100.00% 0.00 0.12 0.30 1,000.00 4.50 4,500.00 0.00 0.12 540.00 161.46 161.46 -
17+000.00 18+000.00 C-3 16.919 100.00% 0.00 0.12 0.46 1,000.00 4.80 4,800.00 0.00 0.12 576.00 265.54 265.54 -
18+000.00 19+000.00 C-3 16.919 100.00% 0.00 0.12 1.46 1,000.00 4.00 4,000.00 0.00 0.12 480.00 701.28 480.00 221.28
19+000.00 20+000.00 C-3 16.919 100.00% 0.00 0.12 2.46 1,000.00 3.78 3,780.00 0.00 0.12 453.60 1,116.31 453.60 662.71
20+000.00 21+000.00 C-3 16.919 100.00% 0.00 0.12 3.46 1,000.00 4.50 4,500.00 0.00 0.12 540.00 1,868.94 540.00 1,328.94
21+000.00 22+000.00 C-3 16.919 100.00% 0.00 0.12 4.46 1,000.00 4.50 4,500.00 0.00 0.12 540.00 2,408.94 540.00 1,868.94
22+000.00 23+000.00 C-3 16.919 100.00% 0.00 0.12 5.46 1,000.00 3.80 3,800.00 0.00 0.12 456.00 2,490.22 456.00 2,034.22
23+000.00 24+000.00 C-3 16.919 100.00% 0.00 0.12 6.46 1,000.00 3.82 3,820.00 0.00 0.12 458.40 2,961.72 458.40 2,503.32
24+000.00 25+000.00 C-3 16.919 100.00% 0.00 0.12 7.46 1,000.00 4.20 4,200.00 0.00 0.12 504.00 3,760.34 504.00 3,256.34
25+000.00 26+000.00 C-3 16.919 100.00% 0.00 0.12 8.46 1,000.00 3.00 3,000.00 0.00 0.12 360.00 3,045.96 360.00 2,685.96
26+000.00 27+000.00 C-3 16.919 100.00% 0.00 0.12 9.46 1,000.00 4.00 4,000.00 0.00 0.12 480.00 4,541.28 480.00 4,061.28
MANTENIMIENTO PERIODICO RUTA JU-114 EMP. PE-24 A (CALABAZA) - APALLA CALABAZA - ULLIMARCA - BADOPAMPA - HUANCAMACHAY - UNION PROGRESO - MANZANAYO - SAN IGNACIO -
PUCACOCHA - EMP. JU-108 (MATAPA)
: MANTENIMIENTO PERIODICO RUTA JU-114 EMP. PE-24 A (CALABAZA) - APALLA CALABAZA - ULLIMARCA - BADOPAMPA - HUANCAMACHAY - UNION PROGRESO - MANZANAYO - SAN
PROYECTO
IGNACIO - PUCACOCHA - EMP. JU-108 (MATAPA)
RUTA : JU - 114
ACTIVIDAD: 03.00 TRANSPORTE
FECHA: NOVIEMBRE 2017
SUSTENTO DE METRADOS TRANSPORTE DE MATERIAL GRANULAR
52+355
0+000
: MANTENIMIENTO PERIODICO RUTA JU-114 EMP. PE-24 A (CALABAZA) - APALLA CALABAZA - ULLIMARCA - BADOPAMPA - HUANCAMACHAY - UNION PROGRESO - MANZANAYO - SAN IGNACIO -
PROYECTO
PUCACOCHA - EMP. JU-108 (MATAPA)
RUTA : JU - 114
ACTIVIDAD: : 03.00 TRANSPORTE
FECHA: : NOVIEMBRE 2017
Sustento de metrados de transporte de Agua
Calculo de la Distancia Media de Transporte FUENTE AGUA ACCESO
Fuente 1: 0.00
27+511.05
50+903.20
43+083.81
0
17+518.8
28+282.00
52+355
Fuente 2: 0.00
0+000
FUENTE DE AGUA N°1 FUENTE DE AGUA N°2 FUENTE DE AGUA N°3 FUENTE DE AGUA N°4 FUENTE DE AGUA N°6 Fuente 3: 0.00
E
c Fuente 4: 0.00
u
a Fuente 5: 0.00
o c
i tramo
Tram ó
Inicio n PAVIMENTOS Fin de
E Código Fte. Ubicación de Fte. Participación D.L.P. 120.00 Espesor Momento D<=1km (m3- D>1km (m3-
INICIO (km) FIN (km) Acceso (km) Distancia (km) Longitud (m) Ancho (m) Área (m2) SA (m2) Volumen (m3)
m Agua agua (km) % m (km) (m) (m3-km) km) km)
p
a
l
0+000.00 1+000.00 m F-1 17.518 100.00% 0.00 0.00 17.02 1,000.00 3.15 3,150.00 63.00 0.12 385.56 6,561.46 385.56 6,175.90
1+000.00 2+000.00 e F-1 17.518 100.00% 0.00 0.00 16.02 1,000.00 4.20 4,200.00 84.00 0.12 514.08 8,234.53 514.08 7,720.45
2+000.00 3+000.00 F-1 17.518 100.00% 0.00 0.00 15.02 1,000.00 2.90 2,900.00 58.00 0.12 354.96 5,330.79 354.96 4,975.83
(
3+000.00 4+000.00 m F-1 17.518 100.00% 0.00 0.00 14.02 1,000.00 4.20 4,200.00 84.00 0.12 514.08 7,206.37 514.08 6,692.29
4+000.00 5+000.00 ) F-1 17.518 100.00% 0.00 0.00 13.02 1,000.00 3.50 3,500.00 70.00 0.12 428.40 5,576.91 428.40 5,148.51
5+000.00 6+000.00 F-1 17.518 100.00% 0.00 0.00 12.02 1,000.00 4.50 4,500.00 90.00 0.12 550.80 6,619.51 550.80 6,068.71
6+000.00 7+000.00 F-1 17.518 100.00% 0.00 0.00 11.02 1,000.00 4.00 4,000.00 80.00 0.12 489.60 5,394.41 489.60 4,904.81
7+000.00 8+000.00 F-1 17.518 100.00% 0.00 0.00 10.02 1,000.00 3.80 3,800.00 76.00 0.12 465.12 4,659.57 465.12 4,194.45
8+000.00 9+000.00 F-1 17.518 100.00% 0.00 0.00 9.02 1,000.00 4.59 4,590.00 91.80 0.12 561.82 5,066.46 561.82 4,504.64
9+000.00 10+000.00 F-1 17.518 100.00% 0.00 0.00 8.02 1,000.00 4.90 4,900.00 98.00 0.12 599.76 4,808.88 599.76 4,209.12
10+000.00 11+000.00 F-1 17.518 100.00% 0.00 0.00 7.02 1,000.00 4.50 4,500.00 90.00 0.12 550.80 3,865.51 550.80 3,314.71
11+000.00 12+000.00 F-1 17.518 100.00% 0.00 0.00 6.02 1,000.00 3.20 3,200.00 64.00 0.12 391.68 2,357.13 391.68 1,965.45
12+000.00 13+000.00 F-1 17.518 100.00% 0.00 0.00 5.02 1,000.00 4.00 4,000.00 80.00 0.12 489.60 2,456.81 489.60 1,967.21
13+000.00 14+000.00 F-1 17.518 100.00% 0.00 0.00 4.02 1,000.00 3.80 3,800.00 76.00 0.12 465.12 1,868.85 465.12 1,403.73
14+000.00 15+000.00 F-1 17.518 100.00% 0.00 0.00 3.02 1,000.00 4.50 4,500.00 90.00 0.12 550.80 1,662.31 550.80 1,111.51
15+000.00 16+000.00 F-1 17.518 100.00% 0.00 0.00 2.02 1,000.00 4.00 4,000.00 80.00 0.12 489.60 988.01 489.60 498.41
16+000.00 17+000.00 F-1 17.518 100.00% 0.00 0.00 1.02 1,000.00 4.50 4,500.00 90.00 0.12 550.80 560.71 550.80 9.91
17+000.00 18+000.00 F-1 17.518 100.00% 0.00 0.00 0.02 1,000.00 4.80 4,800.00 96.00 0.12 587.52 10.58 10.58 -
18+000.00 19+000.00 F-1 17.518 100.00% 0.00 0.00 0.98 1,000.00 4.00 4,000.00 80.00 0.12 489.60 480.79 480.79 -
19+000.00 20+000.00 F-1 17.518 100.00% 0.00 0.00 1.98 1,000.00 3.78 3,780.00 75.60 0.12 462.67 917.02 462.67 454.34
20+000.00 21+000.00 F-1 17.518 100.00% 0.00 0.00 2.98 1,000.00 4.50 4,500.00 90.00 0.12 550.80 1,642.49 550.80 1,091.69
21+000.00 22+000.00 F-1 17.518 100.00% 0.00 0.00 3.98 1,000.00 4.50 4,500.00 90.00 0.12 550.80 2,193.29 550.80 1,642.49
22+000.00 23+000.00 F-1 17.518 100.00% 0.00 0.00 4.98 1,000.00 3.80 3,800.00 76.00 0.12 465.12 2,317.23 465.12 1,852.11
23+000.00 24+000.00 F-2 27.511 100.00% 0.00 0.00 4.01 1,000.00 3.82 3,820.00 76.40 0.12 467.57 1,875.42 467.57 1,407.85
24+000.00 25+000.00 F-2 27.511 100.00% 0.00 0.00 3.01 1,000.00 4.20 4,200.00 84.00 0.12 514.08 1,547.89 514.08 1,033.81
25+000.00 26+000.00 F-2 27.511 100.00% 0.00 0.00 2.01 1,000.00 3.00 3,000.00 60.00 0.12 367.20 738.44 367.20 371.24
26+000.00 27+000.00 F-2 27.511 100.00% 0.00 0.00 1.01 1,000.00 4.00 4,000.00 80.00 0.12 489.60 494.99 489.60 5.39
27+000.00 28+000.00 F-2 27.511 100.00% 0.00 0.00 0.01 1,000.00 3.20 3,200.00 64.00 0.12 391.68 4.31 4.31 -
28+000.00 29+000.00 F-3 28.282 100.00% 0.00 0.00 0.22 1,000.00 3.50 3,500.00 70.00 0.12 428.40 93.39 93.39 -
29+000.00 30+000.00 F-3 28.282 100.00% 0.00 0.00 1.22 1,000.00 3.20 3,200.00 64.00 0.12 391.68 477.07 391.68 85.39
30+000.00 31+000.00 F-3 28.282 100.00% 0.00 0.00 2.22 1,000.00 3.00 3,000.00 60.00 0.12 367.20 814.45 367.20 447.25
31+000.00 32+000.00 F-3 28.282 100.00% 0.00 0.00 3.22 1,000.00 3.00 3,000.00 60.00 0.12 367.20 1,181.65 367.20 814.45
32+000.00 33+000.00 F-3 28.282 100.00% 0.00 0.00 4.22 1,000.00 3.00 3,000.00 60.00 0.12 367.20 1,548.85 367.20 1,181.65
33+000.00 34+000.00 F-3 28.282 100.00% 0.00 0.00 5.22 1,000.00 3.40 3,400.00 68.00 0.12 416.16 2,171.52 416.16 1,755.36
34+000.00 35+000.00 F-3 28.282 100.00% 0.00 0.00 6.22 1,000.00 3.40 3,400.00 68.00 0.12 416.16 2,587.68 416.16 2,171.52
35+000.00 36+000.00 F-3 28.282 100.00% 0.00 0.00 7.22 1,000.00 3.00 3,000.00 60.00 0.12 367.20 2,650.45 367.20 2,283.25
MANTENIMIENTO PERIODICO RUTA JU-114 EMP. PE-24 A (CALABAZA) - APALLA CALABAZA - ULLIMARCA - BADOPAMPA - HUANCAMACHAY - UNION PROGRESO - MANZANAYO - SAN IGNACIO - PUCACOCHA -
EMP. JU-108 (MATAPA)
: MANTENIMIENTO PERIODICO RUTA JU-114 EMP. PE-24 A (CALABAZA) - APALLA CALABAZA - ULLIMARCA - BADOPAMPA - HUANCAMACHAY - UNION PROGRESO - MANZANAYO - SAN IGNACIO -
PROYECTO
PUCACOCHA - EMP. JU-108 (MATAPA)
RUTA : JU - 114
ACTIVIDAD: : 03.00 TRANSPORTE
FECHA: : NOVIEMBRE 2017
Sustento de metrados de transporte de Agua
Calculo de la Distancia Media de Transporte FUENTE AGUA ACCESO
Fuente 1: 0.00
27+511.05
50+903.20
43+083.81
0
17+518.8
28+282.00
52+355
Fuente 2: 0.00
0+000
FUENTE DE AGUA N°1 FUENTE DE AGUA N°2 FUENTE DE AGUA N°3 FUENTE DE AGUA N°4 FUENTE DE AGUA N°6 Fuente 3: 0.00
E
c Fuente 4: 0.00
u
a Fuente 5: 0.00
o c
i tramo
Tram ó
Inicio n PAVIMENTOS Fin de
E Código Fte. Ubicación de Fte. Participación D.L.P. 120.00 Espesor Momento D<=1km (m3- D>1km (m3-
INICIO (km) FIN (km) Acceso (km) Distancia (km) Longitud (m) Ancho (m) Área (m2) SA (m2) Volumen (m3)
m Agua agua (km) % m (km) (m) (m3-km) km) km)
p
36+000.00 37+000.00 a F-4 43.083 100.00% 0.00 0.00 6.58 1,000.00 3.00 3,000.00 60.00 0.12 367.20 2,417.28 367.20 2,050.08
l
37+000.00 38+000.00 m F-4 43.083 100.00% 0.00 0.00 5.58 1,000.00 3.00 3,000.00 60.00 0.12 367.20 2,050.08 367.20 1,682.88
38+000.00 39+000.00 e F-4 43.083 100.00% 0.00 0.00 4.58 1,000.00 3.20 3,200.00 64.00 0.12 391.68 1,795.07 391.68 1,403.39
39+000.00 40+000.00 F-4 43.083 100.00% 0.00 0.00 3.58 1,000.00 3.50 3,500.00 70.00 0.12 428.40 1,534.96 428.40 1,106.56
(
40+000.00 41+000.00 m F-4 43.083 100.00% 0.00 0.00 2.58 1,000.00 3.00 3,000.00 60.00 0.12 367.20 948.48 367.20 581.28
41+000.00 42+000.00 ) F-4 43.083 100.00% 0.00 0.00 1.58 1,000.00 4.43 4,430.00 88.60 0.12 542.23 858.35 542.23 316.12
42+000.00 43+000.00 F-4 43.083 100.00% 0.00 0.00 0.58 1,000.00 3.63 3,630.00 72.60 0.12 444.31 259.03 259.03 -
43+000.00 44+000.00 F-4 43.083 100.00% 0.00 0.00 0.42 1,000.00 3.80 3,800.00 76.00 0.12 465.12 193.96 193.96 -
44+000.00 45+000.00 F-4 43.083 100.00% 0.00 0.00 1.42 1,000.00 4.00 4,000.00 80.00 0.12 489.60 693.76 489.60 204.16
45+000.00 46+000.00 F-4 43.083 100.00% 0.00 0.00 2.42 1,000.00 3.20 3,200.00 64.00 0.12 391.68 946.69 391.68 555.01
46+000.00 47+000.00 F-4 43.083 100.00% 0.00 0.00 3.42 1,000.00 2.80 2,800.00 56.00 0.12 342.72 1,171.07 342.72 828.35
47+000.00 48+000.00 F-5 50.903 100.00% 0.00 0.00 3.40 1,000.00 4.00 4,000.00 80.00 0.12 489.60 1,666.11 489.60 1,176.51
48+000.00 49+000.00 F-5 50.903 100.00% 0.00 0.00 2.40 1,000.00 3.80 3,800.00 76.00 0.12 465.12 1,117.68 465.12 652.56
49+000.00 50+000.00 F-5 50.903 100.00% 0.00 0.00 1.40 1,000.00 4.50 4,500.00 90.00 0.12 550.80 772.77 550.80 221.97
50+000.00 51+000.00 F-5 50.903 100.00% 0.00 0.00 0.40 1,000.00 4.50 4,500.00 90.00 0.12 550.80 221.97 221.97 -
51+000.00 52+000.00 F-5 50.903 100.00% 0.00 0.00 0.60 1,000.00 4.00 4,000.00 80.00 0.12 489.60 292.29 292.29 -
52+000.00 52+355.00 F-5 50.903 100.00% 0.00 0.00 1.27 355.00 4.50 1,597.50 31.95 0.12 195.53 249.21 195.53 53.67
LONGITUD TOTAL DE AFIRMADO 52,355.00 24,149.21 114,154.49 21,858.50 92,295.97
MANTENIMIENTO PERIODICO RUTA JU-114 EMP. PE-24 A (CALABAZA) - APALLA CALABAZA - ULLIMARCA - BADOPAMPA - HUANCAMACHAY - UNION
PROGRESO - MANZANAYO - SAN IGNACIO - PUCACOCHA - EMP. JU-108 (MATAPA)
CALCULO DE RENDIMIENTOS
Tiempo de Carguío al Volquete Tcv 8.57 min
Tiempo de Descarga del Volquete Tdv 2.00 min
Tiempo Útil : 8 hrs. x 90.00% (b) 432 min
CALCULO DE RENDIMIENTOS
Tiempo de Llenado Tcv 10.00 min
Tiempo de Vaciado Tdv 25.00 min
Tiempo Útil : 8 hrs. x 90.00% (b) 432 min
Tiempo de Ciclo del Volquete Tciclo = Tcv+Tdv+Tc+Td 35 + 3.21 x d
Para d = 4.73 Km, Ciclo = (c) 50.19 min
Numero de ciclos (d) = (b) / (c) 8.61
Volumen Transportado por la Cisterna (e) = (a) x (d) 65.18 m3/dia
Rendimiento = 65.18 m3