¤ Item Descripción Und.

0 01 ESTRUCTURAS
0 01.01 MOVIMIENTO DE TIERRAS
0 01.01.01 LIMPIEZA DE TERRENO MANUAL m2
0 01.01.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 m TERRENO NORMAL m3
0 01.01.03 ELIMINACION CON TRANSPORTE (CARGUIO A MANO) R=25 m3/día m3
0 01.02 CONCRETO SIMPLE
0 01.02.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA m3
0 01.02.02 CONCRETO EN FALSOPISO MEZCLA 1:8 CEMENTO-HORMIGON E=4" m2
0 01.03 CONCRETO ARMADO
0 01.03.01 ZAPATAS
0 01.03.01.01 ACERO Fy=4200 kg/cm2, PARA ZAPATAS kg
0 01.03.01.02 CONCRETO PARA ZAPATAS f'c=210 kg/cm2 m3
0 01.03.02 COLUMNAS
0 01.03.02.01 ACERO Fy=4200 kg/cm2, PARA COLUMNAS kg
0 01.03.02.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2
0 01.03.02.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3
0 02 ARQUITECTURA
0 02.01 CARPINTERIA METALICA
0 02.01.01 PUERTA METALICA und
0 02.02 COBERTURA METÁLICA
0 02.02.01 COBERTURA CON CALAMINA GALVANIZADA DE 0.25mm x 0.83m x 3.60 m m2
Metrado Precio (S/.) Parcial (S/.)
24,551.40
1,009.99
400.00 0.49 196.00
52.38 6.45 337.85
31.10 15.31 476.14
3,703.40
21.06 104.34 2,197.40
120.00 12.55 1,506.00
19,838.01
4,225.38
107.52 3.05 327.94
16.00 243.59 3,897.44
15,612.63
2,051.24 2.99 6,133.21
187.40 27.56 5,164.74
18.23 236.68 4,314.68
9,092.00
450.00
1.00 450.00 450.00
8,642.00
580.00 14.90 8,642.00
01.01.01 LIMPIEZA DE TERRENO MANUAL
CANTIDAD LARGO ANCHO ALTO PARCIAL
1.00 40.00 10.00 400.00 m2

01.01.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 m TERRENO NORMAL 37.06 m3


ZAPATAS
CANTIDAD LARGO ANCHO ALTO PARCIAL
20.00 1.00 1.00 0.80 16.00 m3

CIMINETOS CORRIDOS
CANTIDAD LARGO ANCHO ALTO PARCIAL
20.00 3.90 0.45 0.60 21.06 m3

01.01.03 ELIMINACION CON TRANSPORTE (CARGUIO A MANO) R=25 m3/día

01.02.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA


CANTIDAD LARGO ANCHO ALTO PARCIAL
20.00 3.90 0.45 0.60 21.06 m3

01.02.02 CONCRETO EN FALSOPISO MEZCLA 1:8 CEMENTO-HORMIGON E=4"


CANTIDAD LARGO ANCHO ALTO PARCIAL
20.00 1.00 1.00 0.80 16.00 m3

01.03.02.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS 81.00


CANTIDAD N° veces LARGO ANCHO ALTO PARCIAL
20.00 2 0.15 4.50 27.00 m2
20.00 2 0.30 4.50 54.00 m2

01.03.02.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2


CANTIDAD LARGO ANCHO ALTO PARCIAL
20.00 0.15 0.10 4.50 1.35 m3

02.02.01 COBERTURA CON CALAMINA GALVANIZADA DE 0.25mm x 0.83m x 3.60 m

MUROS DE LADRILLO 158.10

CANTIDAD LARGO ANCHO ALTO PARCIAL


16.00 4.75 1.70 129.20 m2
4.00 4.25 1.70 28.90 m2