Está en la página 1de 20

RESUMEN DE METRADO - VEREDAS

Proyecto “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO SANTA CLARA - DISTRITO DE HUAYLLABAMBA -
PROVINCIA DE SIHUAS - DEPARTAMENTO DE ANCASH” (CÓDIGO ÚNICO N° 2406912).

Subpresupuesto PISTAS Y VEREDAS


Componente VEREDAS, ESCALINATAS, SARDINELES Y AREAS VERDES
Cliente MUNICIPALIDAD DISTRITAL DE HUAYLLABAMBA
Lugar HUAYLLABAMBA - SIHUAS - ANCASH
ITEM DESCRIPCION METRADO UND
. VEREDAS, ESCALINATAS Y RAMPAS
04.02.01 MOVIMIENTO DE TIERRAS
04.02.01 MOVIMIENTO DE TIERRAS
04.02.01.01 CORTE DE MATERIAL SUELTO MANUAL 2,618.73 M3
04.02.01.02 RELLENO CON MATERIAL PROPIO Y COMPACTADO CON EQUIPO LIVIANO HASTA NIVEL DE SUBRASANTE 1,108.28 M3
04.02.01.03 PERFILADO Y COMPACTADO DE LA RASANTE EN VEREDAS 4,847.55 M3
04.02.01.04 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA HASTA D=8KM 2,039.11 M3
04.02.01.05 RELLENO Y COMPACTADO DE BASE CON MATERIAL GRANULAR E=0.10 M. 5,183.31 M2
04.02.02 CONCRETO EN VEREDAS
04.02.02.01 ENCOFRADO Y DESENCOFRADDO DE VEREDAS 1,462.16 M2
04.02.02.02 CONCRETO F'C=175 KG/CM2 EN SARDINEL SUMERGIDO PARA VEREDAS 194.96 M3
04.02.03.03 CONCRETO F'C=175 KG/CM2 EN VEREDAS, E=10 CM. ACABADO FROTACHADO 4,847.55 M2
04.02.03 CURADO
04.02.03.01 CURADO 4,847.55 M2
04.02.04 JUNTA EN VEREDAS
04.02.04.01 JUNTA ASFALTICA DE CONSTRUCCIÓN Y/O DILATACIÓN 1,219.00 M

04.03 SARDINELES REFORZADOS


04.03.01 MOVIMIENTO DE TIERRAS
04.03.01.01 CORTE DE MATERIAL SUELTO MANUAL 514.60 M3
04.03.01.02 PERFILADO Y COMPACTADO DE LA SUBRASANTE. 366.50 M2
04.03.01.03 RELLENO CON MATERIAL PROPIO Y COMPACTADO CON EQUIPO LIVIANO HASTA NIVEL DE SUBRASANTE 128.65 M3
04.03.01.04 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA HASTA D=8KM 694.71 M3
04.03.02 OBRAS DE CONCRETO ARMADO
04.03.02.01 ENCOFRADO Y DESENCOFRADO DE SARDINELES REFORZADOS 1,647.00 M2
04.03.02.02 ACERO CORRUGADO F'y=4200 kg/cm2 GRADO 60 5,036.22 KG
04.03.02.03 CONCRETO F'C=210 KG/CM2 EN SARDINELES REFORZADOS 138.30 M3
04.03.03 CURADO
04.03.03.01 CURADO 1,647.00 M2
04.03.04 JUNTAS
05.03.04.01 JUNTA ASFALTICA DE CONSTRUCCIÓN Y/O DILATACIÓN 20.75 M
PLANILLA DE METRADOS - VEREDAS

Proyecto “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO SANTA CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS - DEPARTAMENTO DE
ANCASH” (CÓDIGO ÚNICO N° 2406912).
SubpresupuesPISTAS Y VEREDAS
Componente VEREDAS, ESCALINATAS, SARDINELES Y AREAS VERDES
Cliente MUNICIPALIDAD DISTRITAL DE HUAYLLABAMBA
Lugar HUAYLLABAMBA - SIHUAS - ANCASH
ITEM DESCRIPCION METRADO UND
. VEREDAS, ESCALINATAS Y RAMPAS
04.02.01 MOVIMIENTO DE TIERRAS
04.02.01.01 CORTE DE MATERIAL SUELTO MANUAL 2,618.73 M3
EXCAVACION MANUAL PARA SARDINEL SUMERGIDO (UÑAS)
EXCAVACION MANUAL PARA SARDINEL SUMERGIDO (UÑAS)
MEDIDAS METRADO

FACTOR
Nº PARTIDAS UND. Nº BLOQUES Nº VECES
LARGO (m) ANCHO (m) ALTO (m) AREA (m2) PARCIAL TOTAL
1.00 M3 UÑA
VER HOJAS DE VEREDAS
V-01 1.00 69.50 0.04 1.00 2.78 2.78
V-02 1.00 1,051.45 0.04 1.00 42.06 42.06
V-03 1.00 36.03 0.04 1.00 1.44 1.44
V-04 1.00 82.47 0.04 1.00 3.30 3.30
V-05 1.00 1,706.20 0.04 1.00 68.25 68.25
V-06 1.00 199.90 0.04 1.00 8.00 8.00
V-07 1.00 245.02 0.04 1.00 9.80 9.80
V-08 1.00 198.68 0.04 1.00 7.95 7.95
V-09 1.00 237.65 0.04 1.00 9.51 9.51
V-10 1.00 517.14 0.04 1.00 20.69 20.69
V-11 1.00 529.84 0.04 1.00 21.19 21.19
194.96

CORTE MANUAL EN VEREDAS

CORTE MANUAL EN VEREDAS


MEDIDAS METRADO

FACTOR

Nº PARTIDAS UND. BLOQUES Nº VECES LARGO (m) ALTO
ANCHO (m) (m) AREA (m2) PARCIAL TOTAL
1.00 M3
VER HOJAS DE MOVIMIENTO DE TIERRAS EN VEREDAS
V-01 1.00 0.50 70.52 35.26 35.26
V-02 1.00 0.50 1,059.26 529.63 529.63
V-03 1.00 0.50 0.00 0.00 0.00
V-04 1.00 0.50 83.59 41.79 41.79
V-05 1.00 0.50 1,718.87 859.44 859.44
V-06 1.00 0.50 201.38 100.69 100.69
V-07 1.00 0.50 246.84 123.42 123.42
V-08 1.00 0.50 200.16 100.08 100.08
V-09 1.00 0.50 239.42 119.71 119.71
V-10 1.00 0.50 493.74 246.87 246.87
V-11 1.00 0.50 533.78 266.89 266.89
2,423.78

04.02.01.02 RELLENO CON MATERIAL PROPIO Y COMPACTADO CON EQUIPO LIVIANO HASTA NIVEL DE SUBRASANTE 1,108.28 M3

RELLENO CON MATERIAL PROPIO Y COMPACTADO CON EQUIPO LIVIANO HASTA NIVEL DE SUBRASANTE
MEDIDAS METRADO
FACTOR


Nº PARTIDAS UND. BLOQUES Nº VECES ALTO VOLUMEN
AREA (M2) ANCHO (m) (m) (m3) PARCIAL TOTAL

1.00 M3
VER HOJA DE MOVIMIENTO DE TIERRAS DE VEREDAS
V-01 1.00 0.00 0.00 0.00
V-02 1.00 314.03 314.03 314.03
V-03 1.00 0.00 0.00 0.00
V-04 1.00 0.20 0.20 0.20
V-05 1.00 338.17 338.17 338.17
V-06 1.00 31.82 31.82 31.82
V-07 1.00 20.81 20.81 20.81
V-08 1.00 116.25 116.25 116.25
V-09 1.00 65.04 65.04 65.04
V-10 1.00 59.40 59.40 59.40
V-11 1.00 121.87 121.87 121.87
1,108.28

04.02.01.03 PERFILADO Y COMPACTADO DE LA RASANTE EN VEREDAS 4,847.55 M2

PERFILADO Y COMPACTADO DE LA RASANTE EN VEREDAS


MEDIDAS METRADO
FACTOR


Nº PARTIDAS UND. BLOQUES Nº VECES LARGO (m) ALTO
ANCHO (m) (m) AREA (m2) PARCIAL TOTAL

1.00 M2
VER HOJAS DE VEREDAS 1.00 4,847.55 1.00 4,847.55 4,847.55
4,847.55
PLANILLA DE METRADOS - VEREDAS

Proyecto “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO SANTA CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS - DEPARTAMENTO DE
ANCASH” (CÓDIGO ÚNICO N° 2406912).
SubpresupuesPISTAS Y VEREDAS
Componente VEREDAS, ESCALINATAS, SARDINELES Y AREAS VERDES
Cliente MUNICIPALIDAD DISTRITAL DE HUAYLLABAMBA
Lugar HUAYLLABAMBA - SIHUAS - ANCASH
ITEM DESCRIPCION METRADO UND

04.02.01.04 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA HASTA D=8KM 2,039.11 M3

ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA HASTA D=8KM


MEDIDAS METRADO

FACTOR
Nº PARTIDAS UND. Nº Nº VECES
BLOQUES AREA (M2) ANCHO (m) ALTO VOLUMEN PARCIAL TOTAL
(m) (m3)
1.00 M3
CORTE DE MATERIAL SUELTO MANUAL 2,618.73
PROVENIENTE DE RELLENO 1,108.28
DIFERENCIA 1,510.46 1.35 2,039.11 2,039.11
2,039.11

04.02.01.05 RELLENO Y COMPACTADO DE BASE CON MATERIAL GRANULAR E=0.10 M. 5,183.31 M2

RELLENO Y COMPACTADO DE BASE CON MATERIAL GRANULAR E=0.10 M.


MEDIDAS METRADO

FACTOR
Nº PARTIDAS UND. Nº
BLOQUES Nº VECES LARGO (m) ANCHO (m) ALTO AREA (m2) PARCIAL TOTAL
(m)
1.00 M3
VER HOJAS DE VEREDAS 1.00 4,847.55 1.00 4,847.55 4,847.55
VER HOJA DE MARTILLOS 1.00 36.32 1.00 36.32 36.32
VER HOJA DE RAMPAS 1.00 299.44 1.00 299.44 299.44
VER HOJA DE GRADAS 1.00 0.00 1.00 0.00 0.00
5,183.31

04.02.02 CONCRETO EN VEREDAS


04.02.02.01 ENCOFRADO Y DESENCOFRADDO DE VEREDAS 1,462.16 M3

ENCOFRADO Y DESENCOFRADDO DE VEREDAS


MEDIDAS METRADO
FACTOR

Nº PARTIDAS UND. Nº Nº VECES


BLOQUES LARGO (m) ANCHO (m) ALTO AREA (m2) PARCIAL TOTAL
(m)
1.00 M3 UÑA
V-01 1.00 69.50 0.30 1.00 20.85 20.85
V-02 1.00 1,051.45 0.30 1.00 315.44 315.44
V-03 1.00 36.03 0.30 1.00 10.81 10.81
V-04 1.00 82.47 0.30 1.00 24.74 24.74
V-05 1.00 1,706.20 0.30 1.00 511.86 511.86
V-06 1.00 199.90 0.30 1.00 59.97 59.97
V-07 1.00 245.02 0.30 1.00 73.51 73.51
V-08 1.00 198.68 0.30 1.00 59.60 59.60
V-09 1.00 237.65 0.30 1.00 71.30 71.30
V-10 1.00 517.14 0.30 1.00 155.14 155.14
V-11 1.00 529.84 0.30 1.00 158.95 158.95
1,462.16

04.02.02.02 CONCRETO F'C=175 KG/CM2 EN SARDINEL SUMERGIDO PARA VEREDAS 194.96 M3

CONCRETO F'C=175 KG/CM2 EN SARDINEL SUMERGIDO PARA VEREDAS


MEDIDAS METRADO
FACTOR

Nº PARTIDAS UND. Nº
BLOQUES Nº VECES LARGO (m) ANCHO (m) ALTO AREA (m2) PARCIAL TOTAL
(m)
1.00 M3 UÑA
VER HOJAS DE VEREDAS
V-01 1.00 69.50 0.04 1.00 2.78 2.78
V-02 1.00 1,051.45 0.04 1.00 42.06 42.06
V-03 1.00 36.03 0.04 1.00 1.44 1.44
V-04 1.00 82.47 0.04 1.00 3.30 3.30
V-05 1.00 1,706.20 0.04 1.00 68.25 68.25
V-06 1.00 199.90 0.04 1.00 8.00 8.00
V-07 1.00 245.02 0.04 1.00 9.80 9.80
V-08 1.00 198.68 0.04 1.00 7.95 7.95
V-09 1.00 237.65 0.04 1.00 9.51 9.51
V-10 1.00 517.14 0.04 1.00 20.69 20.69
V-11 1.00 529.84 0.04 1.00 21.19 21.19
194.96

04.02.03.03 CONCRETO F'C=175 KG/CM2 EN VEREDAS, E=10 CM. ACABADO FROTACHADO 4,847.55 M2

CONCRETO F'C=175 KG/CM2 EN VEREDAS, E=10 CM. ACABADO FROTACHADO


MEDIDAS METRADO
FACTOR


Nº PARTIDAS UND. BLOQUES Nº VECES LARGO (m) ALTO
ANCHO (m) (m) AREA (m2) PARCIAL TOTAL

1.00 M2
PLANILLA DE METRADOS - VEREDAS

Proyecto “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO SANTA CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS - DEPARTAMENTO DE
ANCASH” (CÓDIGO ÚNICO N° 2406912).
SubpresupuesPISTAS Y VEREDAS
Componente VEREDAS, ESCALINATAS, SARDINELES Y AREAS VERDES
Cliente MUNICIPALIDAD DISTRITAL DE HUAYLLABAMBA
Lugar HUAYLLABAMBA - SIHUAS - ANCASH
ITEM DESCRIPCION METRADO UND
VER HOJAS DE VEREDAS 1.00 4,847.55 1.00 4,847.55 4,847.55
4,847.55

04.02.03 CURADO
04.02.03.01 CURADO 4,847.55 M2

CURADO
MEDIDAS METRADO

FACTOR

Nº PARTIDAS UND. BLOQUES Nº VECES LARGO (m) ALTO
ANCHO (m) (m) AREA (m2) PARCIAL TOTAL

1.00 M2
VER HOJAS DE VEREDAS 1.00 4,847.55 1.00 4,847.55 4,847.55
4,847.55

04.02.04 JUNTA EN VEREDAS


04.02.04.01 JUNTA ASFALTICA DE CONSTRUCCIÓN Y/O DILATACIÓN 1,219.00 M

JUNTA ASFALTICA DE CONSTRUCCIÓN Y/O DILATACIÓN


MEDIDAS METRADO

FACTOR

Nº PARTIDAS UND. BLOQUES Nº VECES LARGO (m) ALTO
ANCHO (m) (m) AREA (m2) PARCIAL TOTAL

1.00 M PROM
TRANSVERSAL
VER HOJA DE VEREDAS 1,219.00 4,875.88 1.00 1.00 1,219.00 1,219.00
1,219.00

04.03 SARDINELES REFORZADOS


04.03.01 MOVIMIENTO DE TIERRAS
04.03.01.01 CORTE DE MATERIAL SUELTO MANUAL 514.60 M3

CORTE DE MATERIAL SUELTO MANUAL


MEDIDAS METRADO
FACTOR


Nº PARTIDAS UND. BLOQUES Nº VECES LARGO (m) ALTO VOLUMEN
ANCHO (m) (m) (m3) PARCIAL TOTAL
VER PLANO DE PERFIL
SR-01 1.00 10.00 1.20 1.50 18.00 1.00 18.00 18.00
SR-02 1.00 10.00 0.95 1.20 11.40 1.00 11.40 11.40
SR-03 1.00 10.00 0.95 1.20 11.40 1.00 11.40 11.40
SR-04 1.00 20.00 1.20 1.50 36.00 1.00 36.00 36.00
SR-05 1.00 20.00 1.20 1.50 36.00 1.00 36.00 36.00
SR-06 1.00 10.00 1.10 1.35 14.85 1.00 14.85 14.85
SR-07 1.00 20.00 0.95 1.20 22.80 1.00 22.80 22.80
SR-08 1.00 20.00 1.10 1.35 29.70 1.00 29.70 29.70
SR-09 1.00 20.00 0.95 1.20 22.80 1.00 22.80 22.80
SR-10 1.00 20.00 1.10 1.35 29.70 1.00 29.70 29.70
SR-11 1.00 10.00 0.95 1.20 11.40 1.00 11.40 11.40
SR-12 1.00 10.00 0.85 1.00 8.50 1.00 8.50 8.50
SR-13 1.00 10.00 1.10 1.35 14.85 1.00 14.85 14.85
SR-14 1.00 10.00 1.40 1.80 25.20 1.00 25.20 25.20
SR-15 1.00 10.00 1.20 1.50 18.00 1.00 18.00 18.00
SR-16 1.00 20.00 1.10 1.35 29.70 1.00 29.70 29.70
SR-17 1.00 10.00 1.20 1.50 18.00 1.00 18.00 18.00
SR-18 1.00 10.00 1.40 1.80 25.20 1.00 25.20 25.20
SR-19 1.00 50.00 1.20 1.50 90.00 1.00 90.00 90.00
SR-20 1.00 10.00 0.95 1.20 11.40 1.00 11.40 11.40
SR-21 1.00 20.00 1.10 1.35 29.70 1.00 29.70 29.70
514.60

04.03.01.02 PERFILADO Y COMPACTADO DE LA SUBRASANTE. 366.50 M2

PERFILADO Y COMPACTADO DE LA SUBRASANTE.


MEDIDAS METRADO
FACTOR


Nº PARTIDAS UND. BLOQUES Nº VECES LARGO (m) ALTO
ANCHO (m) (m) AREA (m2) PARCIAL TOTAL
VER PLANO DE PERFIL
SR-01 1.00 10.00 1.20 1.50 12.00 1.00 12.00 12.00
SR-02 1.00 10.00 0.95 1.20 9.50 1.00 9.50 9.50
SR-03 1.00 10.00 0.95 1.20 9.50 1.00 9.50 9.50
SR-04 1.00 20.00 1.20 1.50 24.00 1.00 24.00 24.00
SR-05 1.00 20.00 1.20 1.50 24.00 1.00 24.00 24.00
SR-06 1.00 10.00 1.10 1.35 11.00 1.00 11.00 11.00
SR-07 1.00 20.00 0.95 1.20 19.00 1.00 19.00 19.00
SR-08 1.00 20.00 1.10 1.35 22.00 1.00 22.00 22.00
SR-09 1.00 20.00 0.95 1.20 19.00 1.00 19.00 19.00
SR-10 1.00 20.00 1.10 1.35 22.00 1.00 22.00 22.00
PLANILLA DE METRADOS - VEREDAS

Proyecto “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO SANTA CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS - DEPARTAMENTO DE
ANCASH” (CÓDIGO ÚNICO N° 2406912).
SubpresupuesPISTAS Y VEREDAS
Componente VEREDAS, ESCALINATAS, SARDINELES Y AREAS VERDES
Cliente MUNICIPALIDAD DISTRITAL DE HUAYLLABAMBA
Lugar HUAYLLABAMBA - SIHUAS - ANCASH
ITEM DESCRIPCION METRADO UND
SR-11 1.00 10.00 0.95 1.20 9.50 1.00 9.50 9.50
SR-12 1.00 10.00 0.85 1.00 8.50 1.00 8.50 8.50
SR-13 1.00 10.00 1.10 1.35 11.00 1.00 11.00 11.00
SR-14 1.00 10.00 1.40 1.80 14.00 1.00 14.00 14.00
SR-15 1.00 10.00 1.20 1.50 12.00 1.00 12.00 12.00
SR-16 1.00 20.00 1.10 1.35 22.00 1.00 22.00 22.00
SR-17 1.00 10.00 1.20 1.50 12.00 1.00 12.00 12.00
SR-18 1.00 10.00 1.40 1.80 14.00 1.00 14.00 14.00
SR-19 1.00 50.00 1.20 1.50 60.00 1.00 60.00 60.00
SR-20 1.00 10.00 0.95 1.20 9.50 1.00 9.50 9.50
SR-21 1.00 20.00 1.10 1.35 22.00 1.00 22.00 22.00
366.50

04.03.01.03 RELLENO CON MATERIAL PROPIO Y COMPACTADO CON EQUIPO LIVIANO HASTA NIVEL DE SUBRASANTE 128.65 M3

RELLENO CON MATERIAL PROPIO Y COMPACTADO CON EQUIPO LIVIANO HASTA NIVEL DE SUBRASANTE
MEDIDAS METRADO

FACTOR
Nº PARTIDAS UND. Nº Nº VECES
BLOQUES LARGO (m) ANCHO (m) ALTO (m) VOL (m3) PARCIAL TOTAL
VER PLANO DE PERFIL
SR-01 1.00 10.00 1.20 1.50 18.00 0.25 4.50 4.50
SR-02 1.00 10.00 0.95 1.20 11.40 0.25 2.85 2.85
SR-03 1.00 10.00 0.95 1.20 11.40 0.25 2.85 2.85
SR-04 1.00 20.00 1.20 1.50 36.00 0.25 9.00 9.00
SR-05 1.00 20.00 1.20 1.50 36.00 0.25 9.00 9.00
SR-06 1.00 10.00 1.10 1.35 14.85 0.25 3.71 3.71
SR-07 1.00 20.00 0.95 1.20 22.80 0.25 5.70 5.70
SR-08 1.00 20.00 1.10 1.35 29.70 0.25 7.43 7.43
SR-09 1.00 20.00 0.95 1.20 22.80 0.25 5.70 5.70
SR-10 1.00 20.00 1.10 1.35 29.70 0.25 7.43 7.43
SR-11 1.00 10.00 0.95 1.20 11.40 0.25 2.85 2.85
SR-12 1.00 10.00 0.85 1.00 8.50 0.25 2.13 2.13
SR-13 1.00 10.00 1.10 1.35 14.85 0.25 3.71 3.71
SR-14 1.00 10.00 1.40 1.80 25.20 0.25 6.30 6.30
SR-15 1.00 10.00 1.20 1.50 18.00 0.25 4.50 4.50
SR-16 1.00 20.00 1.10 1.35 29.70 0.25 7.43 7.43
SR-17 1.00 10.00 1.20 1.50 18.00 0.25 4.50 4.50
SR-18 1.00 10.00 1.40 1.80 25.20 0.25 6.30 6.30
SR-19 1.00 50.00 1.20 1.50 90.00 0.25 22.50 22.50
SR-20 1.00 10.00 0.95 1.20 11.40 0.25 2.85 2.85
SR-21 1.00 20.00 1.10 1.35 29.70 0.25 7.43 7.43
128.65

04.03.01.04 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA HASTA D=8KM 694.71 M3

ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA HASTA D=8KM


MEDIDAS METRADO
FACTOR


Nº PARTIDAS UND. BLOQUES Nº VECES LARGO (m) ALTO VOLUMEN
ANCHO (m) (m) (m3) PARCIAL TOTAL
1.00 M3
DE CORTE 1.00 514.60 1.35 694.71 694.71

04.03.02 OBRAS DE CONCRETO ARMADO


04.03.02.01 ENCOFRADO Y DESENCOFRADO DE SARDINELES REFORZADOS 1,647.00 M2

ENCOFRADO Y DESENCOFRADO DE SARDINELES REFORZADOS


MEDIDAS METRADO
FACTOR


Nº PARTIDAS UND. BLOQUES Nº VECES LARGO (m) ALTO
ANCHO (m) (m) AREA (m2) PARCIAL TOTAL
ENCOFRADO DE MURO
SR-01 2.00 10.00 1.20 1.50 15.00 1.00 30.00 30.00
SR-02 2.00 10.00 0.95 1.20 12.00 1.00 24.00 24.00
SR-03 2.00 10.00 0.95 1.20 12.00 1.00 24.00 24.00
SR-04 2.00 20.00 1.20 1.50 30.00 1.00 60.00 60.00
SR-05 2.00 20.00 1.20 1.50 30.00 1.00 60.00 60.00
SR-06 2.00 10.00 1.10 1.35 13.50 1.00 27.00 27.00
SR-07 2.00 20.00 0.95 1.20 24.00 1.00 48.00 48.00
SR-08 2.00 20.00 1.10 1.35 27.00 1.00 54.00 54.00
SR-09 2.00 20.00 0.95 1.20 24.00 1.00 48.00 48.00
SR-10 2.00 20.00 1.10 1.35 27.00 1.00 54.00 54.00
SR-11 2.00 10.00 0.95 1.20 12.00 1.00 24.00 24.00
SR-12 2.00 10.00 0.85 1.00 10.00 1.00 20.00 20.00
SR-13 2.00 10.00 1.10 1.35 13.50 1.00 27.00 27.00
SR-14 2.00 10.00 1.40 1.80 18.00 1.00 36.00 36.00
SR-15 2.00 10.00 1.20 1.50 15.00 1.00 30.00 30.00
SR-16 2.00 20.00 1.10 1.35 27.00 1.00 54.00 54.00
PLANILLA DE METRADOS - VEREDAS

Proyecto “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO SANTA CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS - DEPARTAMENTO DE
ANCASH” (CÓDIGO ÚNICO N° 2406912).
SubpresupuesPISTAS Y VEREDAS
Componente VEREDAS, ESCALINATAS, SARDINELES Y AREAS VERDES
Cliente MUNICIPALIDAD DISTRITAL DE HUAYLLABAMBA
Lugar HUAYLLABAMBA - SIHUAS - ANCASH
ITEM DESCRIPCION METRADO UND
SR-17 2.00 10.00 1.20 1.50 15.00 1.00 30.00 30.00
SR-18 2.00 10.00 1.40 1.80 18.00 1.00 36.00 36.00
SR-19 2.00 50.00 1.20 1.50 75.00 1.00 150.00 150.00
SR-20 2.00 10.00 0.95 1.20 12.00 1.00 24.00 24.00
SR-21 2.00 20.00 1.10 1.35 27.00 1.00 54.00 54.00
ENCOFRADO DE BASE
SR-01 2.00 10.00 1.20 1.50 12.00 1.00 24.00 24.00
SR-02 2.00 10.00 0.95 1.20 9.50 1.00 19.00 19.00
SR-03 2.00 10.00 0.95 1.20 9.50 1.00 19.00 19.00
SR-04 2.00 20.00 1.20 1.50 24.00 1.00 48.00 48.00
SR-05 2.00 20.00 1.20 1.50 24.00 1.00 48.00 48.00
SR-06 2.00 10.00 1.10 1.35 11.00 1.00 22.00 22.00
SR-07 2.00 20.00 0.95 1.20 19.00 1.00 38.00 38.00
SR-08 2.00 20.00 1.10 1.35 22.00 1.00 44.00 44.00
SR-09 2.00 20.00 0.95 1.20 19.00 1.00 38.00 38.00
SR-10 2.00 20.00 1.10 1.35 22.00 1.00 44.00 44.00
SR-11 2.00 10.00 0.95 1.20 9.50 1.00 19.00 19.00
SR-12 2.00 10.00 0.85 1.00 8.50 1.00 17.00 17.00
SR-13 2.00 10.00 1.10 1.35 11.00 1.00 22.00 22.00
SR-14 2.00 10.00 1.40 1.80 14.00 1.00 28.00 28.00
SR-15 2.00 10.00 1.20 1.50 12.00 1.00 24.00 24.00
SR-16 2.00 20.00 1.10 1.35 22.00 1.00 44.00 44.00
SR-17 2.00 10.00 1.20 1.50 12.00 1.00 24.00 24.00
SR-18 2.00 10.00 1.40 1.80 14.00 1.00 28.00 28.00
SR-19 2.00 50.00 1.20 1.50 60.00 1.00 120.00 120.00
SR-20 2.00 10.00 0.95 1.20 9.50 1.00 19.00 19.00
SR-21 2.00 20.00 1.10 1.35 22.00 1.00 44.00 44.00
1,647.00

04.03.02.02 ACERO CORRUGADO F'y=4200 kg/cm2 GRADO 60 5,036.22 KG

ACERO CORRUGADO F'y=4200 kg/cm2 GRADO 60


MEDIDAS
FACTOR

METRADO
Nº PARTIDAS UND. Nº
BLOQUES Nº VECES LARGO (m) 1/2" (Kg/ml) 3/8" 5/8" (Kg/ml) PARCIAL TOTAL
(Kg/ml)
1.00 KG 0.99 0.56 1.55
TRANSVERSAL LONGITUD (m)
SR-01 100.00 10.00 1.60 1.05 94.08 94.08
SR-02 100.00 10.00 1.30 1.05 76.44 76.44
SR-03 100.00 10.00 1.30 1.05 76.44 76.44
SR-04 200.00 20.00 1.60 1.05 188.16 188.16
SR-05 200.00 20.00 1.60 1.05 188.16 188.16
SR-06 100.00 10.00 1.45 1.05 85.26 85.26
SR-07 200.00 20.00 1.30 1.05 152.88 152.88
SR-08 200.00 20.00 1.45 1.05 170.52 170.52
SR-09 200.00 20.00 1.30 1.05 152.88 152.88
SR-10 200.00 20.00 1.45 1.05 170.52 170.52
SR-11 100.00 10.00 1.30 1.05 76.44 76.44
SR-12 100.00 10.00 1.10 1.05 64.68 64.68
SR-13 100.00 10.00 1.45 1.05 85.26 85.26
SR-14 100.00 10.00 1.90 1.05 111.72 111.72
SR-15 100.00 10.00 1.60 1.05 94.08 94.08
SR-16 200.00 20.00 1.45 1.05 170.52 170.52
SR-17 100.00 10.00 1.60 1.05 94.08 94.08
SR-18 100.00 10.00 1.90 1.05 111.72 111.72
SR-19 500.00 50.00 1.60 1.05 470.40 470.40
SR-20 100.00 10.00 1.30 1.05 76.44 76.44
SR-21 200.00 20.00 1.45 1.05 170.52 170.52
LONGITUDINAL
SR-01 100.00 10.00 1.20 1.05 70.56 70.56
SR-02 100.00 10.00 0.95 1.05 55.86 55.86
SR-03 100.00 10.00 0.95 1.05 55.86 55.86
SR-04 200.00 20.00 1.20 1.05 141.12 141.12
SR-05 200.00 20.00 1.20 1.05 141.12 141.12
SR-06 100.00 10.00 1.10 1.05 64.68 64.68
SR-07 200.00 20.00 0.95 1.05 111.72 111.72
SR-08 200.00 20.00 1.10 1.05 129.36 129.36
SR-09 200.00 20.00 0.95 1.05 111.72 111.72
SR-10 200.00 20.00 1.10 1.05 129.36 129.36
SR-11 100.00 10.00 0.95 1.05 55.86 55.86
SR-12 100.00 10.00 0.85 1.05 49.98 49.98
SR-13 100.00 10.00 1.10 1.05 64.68 64.68
SR-14 100.00 10.00 1.40 1.05 82.32 82.32
SR-15 100.00 10.00 1.20 1.05 70.56 70.56
SR-16 200.00 20.00 1.10 1.05 129.36 129.36
PLANILLA DE METRADOS - VEREDAS

Proyecto “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO SANTA CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS - DEPARTAMENTO DE
ANCASH” (CÓDIGO ÚNICO N° 2406912).
SubpresupuesPISTAS Y VEREDAS
Componente VEREDAS, ESCALINATAS, SARDINELES Y AREAS VERDES
Cliente MUNICIPALIDAD DISTRITAL DE HUAYLLABAMBA
Lugar HUAYLLABAMBA - SIHUAS - ANCASH
ITEM DESCRIPCION METRADO UND
SR-17 100.00 10.00 1.20 1.05 70.56 70.56
SR-18 100.00 10.00 1.40 1.05 82.32 82.32
SR-19 500.00 50.00 1.20 1.05 352.80 352.80
SR-20 100.00 10.00 0.95 1.05 55.86 55.86
SR-21 200.00 20.00 1.10 1.05 129.36 129.36
5,036.22

04.03.02.03 CONCRETO F'C=210 KG/CM2 EN SARDINELES REFORZADOS 138.30 M3

CONCRETO F'C=210 KG/CM2 EN SARDINELES REFORZADOS


MEDIDAS METRADO

FACTOR
Nº PARTIDAS UND. Nº
BLOQUES Nº VECES LARGO (m) ANCHO (m) ALTO VOL (m3) PARCIAL TOTAL
(m)
MURO
SR-01 1.00 10.00 0.20 1.30 2.60 1.00 2.60 2.60
SR-02 1.00 10.00 0.20 1.00 2.00 1.00 2.00 2.00
SR-03 1.00 10.00 0.20 1.00 2.00 1.00 2.00 2.00
SR-04 1.00 20.00 0.20 1.30 5.20 1.00 5.20 5.20
SR-05 1.00 20.00 0.20 1.30 5.20 1.00 5.20 5.20
SR-06 1.00 10.00 0.20 1.15 2.30 1.00 2.30 2.30
SR-07 1.00 20.00 0.20 1.00 4.00 1.00 4.00 4.00
SR-08 1.00 20.00 0.20 1.15 4.60 1.00 4.60 4.60
SR-09 1.00 20.00 0.20 1.00 4.00 1.00 4.00 4.00
SR-10 1.00 20.00 0.20 1.15 4.60 1.00 4.60 4.60
SR-11 1.00 10.00 0.20 1.00 2.00 1.00 2.00 2.00
SR-12 1.00 10.00 0.20 0.80 1.60 1.00 1.60 1.60
SR-13 1.00 10.00 0.20 1.15 2.30 1.00 2.30 2.30
SR-14 1.00 10.00 0.20 1.60 3.20 1.00 3.20 3.20
SR-15 1.00 10.00 0.20 1.30 2.60 1.00 2.60 2.60
SR-16 1.00 20.00 0.20 1.15 4.60 1.00 4.60 4.60
SR-17 1.00 10.00 0.20 1.30 2.60 1.00 2.60 2.60
SR-18 1.00 10.00 0.20 1.60 3.20 1.00 3.20 3.20
SR-19 1.00 50.00 0.20 1.30 13.00 1.00 13.00 13.00
SR-20 1.00 10.00 0.20 1.00 2.00 1.00 2.00 2.00
SR-21 1.00 20.00 0.20 1.15 4.60 1.00 4.60 4.60
BASE
SR-01 1.00 10.00 1.00 0.20 2.00 1.05 2.00 2.00
SR-02 1.00 10.00 0.75 0.20 1.50 1.05 1.50 1.50
SR-03 1.00 10.00 0.75 0.20 1.50 1.05 1.50 1.50
SR-04 1.00 20.00 1.00 0.20 4.00 1.05 4.00 4.00
SR-05 1.00 20.00 1.00 0.20 4.00 1.05 4.00 4.00
SR-06 1.00 10.00 0.90 0.20 1.80 1.05 1.80 1.80
SR-07 1.00 20.00 0.75 0.20 3.00 1.05 3.00 3.00
SR-08 1.00 20.00 0.90 0.20 3.60 1.05 3.60 3.60
SR-09 1.00 20.00 0.75 0.20 3.00 1.05 3.00 3.00
SR-10 1.00 20.00 0.90 0.20 3.60 1.05 3.60 3.60
SR-11 1.00 10.00 0.75 0.20 1.50 1.05 1.50 1.50
SR-12 1.00 10.00 0.65 0.20 1.30 1.05 1.30 1.30
SR-13 1.00 10.00 0.90 0.20 1.80 1.05 1.80 1.80
SR-14 1.00 10.00 1.20 0.20 2.40 1.05 2.40 2.40
SR-15 1.00 10.00 1.00 0.20 2.00 1.05 2.00 2.00
SR-16 1.00 20.00 0.90 0.20 3.60 1.05 3.60 3.60
SR-17 1.00 10.00 1.00 0.20 2.00 1.05 2.00 2.00
SR-18 1.00 10.00 1.20 0.20 2.40 1.05 2.40 2.40
SR-19 1.00 50.00 1.00 0.20 10.00 1.05 10.00 10.00
SR-20 1.00 10.00 0.75 0.20 1.50 1.05 1.50 1.50
SR-21 1.00 20.00 0.90 0.20 3.60 1.05 3.60 3.60
138.30

04.03.03 CURADO
04.03.03.01 CURADO 1,647.00 M2

CURADO
MEDIDAS METRADO
FACTOR

Nº PARTIDAS UND. Nº
BLOQUES Nº VECES LARGO (m) ANCHO (m) ALTO AREA (m2) PARCIAL TOTAL
(m)
VER PLANO DE PERFIL
SR-01 2.00 10.00 1.20 1.50 15.00 1.00 30.00 30.00
SR-02 2.00 10.00 0.95 1.20 12.00 1.00 24.00 24.00
SR-03 2.00 10.00 0.95 1.20 12.00 1.00 24.00 24.00
SR-04 2.00 20.00 1.20 1.50 30.00 1.00 60.00 60.00
SR-05 2.00 20.00 1.20 1.50 30.00 1.00 60.00 60.00
SR-06 2.00 10.00 1.10 1.35 13.50 1.00 27.00 27.00
SR-07 2.00 20.00 0.95 1.20 24.00 1.00 48.00 48.00
SR-08 2.00 20.00 1.10 1.35 27.00 1.00 54.00 54.00
SR-09 2.00 20.00 0.95 1.20 24.00 1.00 48.00 48.00
SR-10 2.00 20.00 1.10 1.35 27.00 1.00 54.00 54.00
SR-11 2.00 10.00 0.95 1.20 12.00 1.00 24.00 24.00
PLANILLA DE METRADOS - VEREDAS

Proyecto “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO SANTA CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS - DEPARTAMENTO DE
ANCASH” (CÓDIGO ÚNICO N° 2406912).
SubpresupuesPISTAS Y VEREDAS
Componente VEREDAS, ESCALINATAS, SARDINELES Y AREAS VERDES
Cliente MUNICIPALIDAD DISTRITAL DE HUAYLLABAMBA
Lugar HUAYLLABAMBA - SIHUAS - ANCASH
ITEM DESCRIPCION METRADO UND
SR-12 2.00 10.00 0.85 1.00 10.00 1.00 20.00 20.00
SR-13 2.00 10.00 1.10 1.35 13.50 1.00 27.00 27.00
SR-14 2.00 10.00 1.40 1.80 18.00 1.00 36.00 36.00
SR-15 2.00 10.00 1.20 1.50 15.00 1.00 30.00 30.00
SR-16 2.00 20.00 1.10 1.35 27.00 1.00 54.00 54.00
SR-17 2.00 10.00 1.20 1.50 15.00 1.00 30.00 30.00
SR-18 2.00 10.00 1.40 1.80 18.00 1.00 36.00 36.00
SR-19 2.00 50.00 1.20 1.50 75.00 1.00 150.00 150.00
SR-20 2.00 10.00 0.95 1.20 12.00 1.00 24.00 24.00
SR-21 2.00 20.00 1.10 1.35 27.00 1.00 54.00 54.00
ENCOFRADO DE BASE
SR-01 2.00 10.00 1.20 1.50 12.00 1.00 24.00 24.00
SR-02 2.00 10.00 0.95 1.20 9.50 1.00 19.00 19.00
SR-03 2.00 10.00 0.95 1.20 9.50 1.00 19.00 19.00
SR-04 2.00 20.00 1.20 1.50 24.00 1.00 48.00 48.00
SR-05 2.00 20.00 1.20 1.50 24.00 1.00 48.00 48.00
SR-06 2.00 10.00 1.10 1.35 11.00 1.00 22.00 22.00
SR-07 2.00 20.00 0.95 1.20 19.00 1.00 38.00 38.00
SR-08 2.00 20.00 1.10 1.35 22.00 1.00 44.00 44.00
SR-09 2.00 20.00 0.95 1.20 19.00 1.00 38.00 38.00
SR-10 2.00 20.00 1.10 1.35 22.00 1.00 44.00 44.00
SR-11 2.00 10.00 0.95 1.20 9.50 1.00 19.00 19.00
SR-12 2.00 10.00 0.85 1.00 8.50 1.00 17.00 17.00
SR-13 2.00 10.00 1.10 1.35 11.00 1.00 22.00 22.00
SR-14 2.00 10.00 1.40 1.80 14.00 1.00 28.00 28.00
SR-15 2.00 10.00 1.20 1.50 12.00 1.00 24.00 24.00
SR-16 2.00 20.00 1.10 1.35 22.00 1.00 44.00 44.00
SR-17 2.00 10.00 1.20 1.50 12.00 1.00 24.00 24.00
SR-18 2.00 10.00 1.40 1.80 14.00 1.00 28.00 28.00
SR-19 2.00 50.00 1.20 1.50 60.00 1.00 120.00 120.00
SR-20 2.00 10.00 0.95 1.20 9.50 1.00 19.00 19.00
SR-21 2.00 20.00 1.10 1.35 22.00 1.00 44.00 44.00
1,647.00

04.03.04 JUNTAS
05.03.04.01 JUNTA ASFALTICA DE CONSTRUCCIÓN Y/O DILATACIÓN 20.75 M

JUNTA ASFALTICA DE CONSTRUCCIÓN Y/O DILATACIÓN


MEDIDAS METRADO
FACTOR


Nº PARTIDAS UND. BLOQUES Nº VECES LARGO (m) ALTO AREA CAD
ANCHO (m) (m) (m2) PARCIAL TOTAL
VER PLANO DE PERFIL
83.00 330.00 0.25 1.00 20.75 20.75
20.75
METRADO AREA DE VEREDAS

PROYECTO “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO SANTA


CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS - DEPARTAMENTO DE ANCASH”
(CÓDIGO ÚNICO N° 2406912).

ANCHO (M) ANCHO (M)


LONGITUD
DESCRIPCION MZA TRAMO AREA (M2) PERIMETRO VEREDA VEREDA
PARA UÑA (M)
IZQUIERDA DERECHA
AV. VIRGEN BENDITA CLARA 1 V-01 70.52 141.00 70.00 1.00 0.00
AV. VIRGEN BENDITA CLARA 2 V-02 1059.26 2104.90 1051.45 1.00 1.00
AV. JOSE CARLOS MARIATEGUI 1 V-03 0.00 74.06 37.03 0.00 0.00
AV. JOSE CARLOS MARIATEGUI 2 V-04 83.59 166.94 82.97 1.00 0.00
AV. JOSE CARLOS MARIATEGUI 2 V-05 1718.87 3414.40 1706.20 1.00 1.00
JR. JOSE OLAYA V-06 201.38 401.80 199.90 1.00 1.00
JR. CONCHUCOS V-07 246.84 492.04 245.02 1.00 1.00
JR. PLAZA DE ARMAS 1 V-08 200.16 399.36 198.68 1.00 1.00
JR. PLAZA DE ARMAS 2 V-09 239.42 477.30 237.65 1.00 1.00
JR. CARLOS MARX V-10 493.74 1036.27 517.14 1.00 1.00
JR. CONFRATERNIDAD 1 V-11 533.78 1061.68 529.84 1.00 1.00
TOTAL 4,847.55 9,769.75 4,875.88
METRADO AREA DE VEREDAS ADICIONALES

PROYECTO “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO


SANTA CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS -
DEPARTAMENTO DE ANCASH” (CÓDIGO ÚNICO N° 2406912).

LONGITUD
DESCRIPCION MZA TRAMO AREA (M2) PERIMETRO ANCHO (M)
PARA UÑA (M)

JR. CARLOS MARX - PACHAVILCA V-12 264.94 565.23 281.61 1.00


JR. CONFRATERNIDAD 2 V-13 54.74 118.36 58.18 1.00
CALLE SANTIAGO ANTUNEZ DE MAYOLO V-14 135.29 289.60 143.80 1.00
TOTAL 454.97 973.19 483.59
METRADO AREA DE SARDINEL REFORZADO
PROYECTO “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO SANTA
CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS - DEPARTAMENTO DE ANCASH”
(CÓDIGO ÚNICO N° 2406912).
LONGITUD PROGRESIVA PROGRESIVA AREA PERIMETRO LONGITUD
DESCRIPCION SARDINEL ALTURA ANCHO
BASE (M) INICIO FIN (M2) (M) (M)
AV. VIRGEN BENDITA CLARA SR-01 1.50 1.20 0+000.00 0+010.00 2.00 20.40 0.20 10.00
AV. VIRGEN BENDITA CLARA SR-02 1.20 0.95 0+010.00 0+020.00 2.00 20.40 0.20 10.00
AV. VIRGEN BENDITA CLARA SR-03 1.20 0.95 0+050.00 0+060.00 2.00 20.40 0.20 10.00
AV. VIRGEN BENDITA CLARA SR-04 1.50 1.20 0+060.00 0+080.00 4.00 40.40 0.20 20.00
AV. JOSE CARLOS MARIATEGUI SR-05 1.50 1.20 0+040.00 0+060.00 4.00 40.40 0.20 20.00
AV. JOSE CARLOS MARIATEGUI SR-06 1.35 1.10 0+060.00 0+070.00 2.00 20.40 0.20 10.00
AV. JOSE CARLOS MARIATEGUI SR-07 1.20 0.95 0+070.00 0+090.00 4.00 40.40 0.20 20.00
AV. JOSE CARLOS MARIATEGUI SR-08 1.35 1.10 0+090.00 0+110.00 4.00 40.40 0.20 20.00
AV. JOSE CARLOS MARIATEGUI SR-09 1.20 0.95 0+110.00 0+130.00 4.00 40.40 0.20 20.00
AV. JOSE CARLOS MARIATEGUI SR-10 1.35 1.10 0+210.00 0+230.00 4.00 40.40 0.20 20.00
AV. JOSE CARLOS MARIATEGUI SR-11 1.20 0.95 0+240.00 0+250.00 2.00 20.40 0.20 10.00
AV. JOSE CARLOS MARIATEGUI SR-12 1.00 0.85 0+300.00 0+310.00 2.00 20.40 0.20 10.00
AV. JOSE CARLOS MARIATEGUI SR-13 1.35 1.10 0+310.00 0+320.00 2.00 20.40 0.20 10.00
AV. JOSE CARLOS MARIATEGUI SR-14 1.80 1.40 0+320.00 0+330.00 2.00 20.40 0.20 10.00
AV. JOSE CARLOS MARIATEGUI SR-15 1.50 1.20 0+330.00 0+340.00 2.00 20.40 0.20 10.00
AV. JOSE CARLOS MARIATEGUI SR-16 1.35 1.10 0+580.00 0+600.00 4.00 40.40 0.20 20.00
AV. JOSE CARLOS MARIATEGUI SR-17 1.50 1.20 0+720.00 0+730.00 2.00 20.40 0.20 10.00
AV. JOSE CARLOS MARIATEGUI SR-18 1.80 1.40 0+750.00 0+760.00 2.00 20.40 0.20 10.00
AV. JOSE CARLOS MARIATEGUI SR-19 1.50 1.20 0+760.00 0+810.00 10.00 100.40 0.20 50.00
AV. JOSE CARLOS MARIATEGUI SR-20 1.20 0.95 0+810.00 0+820.00 2.00 20.40 0.20 10.00
AV. JOSE CARLOS MARIATEGUI SR-21 1.35 1.10 0+820.00 0+840.00 4.00 40.40 0.20 20.00
TOTAL 66.00 668.40 330.00
METRADO AREA DE RAMPAS
PROYECTO “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO
POBLADO SANTA CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS
- DEPARTAMENTO DE ANCASH” (CÓDIGO ÚNICO N° 2406912).

PERIMETRO
DESCRIPCION CANTIDAD TRAMO AREA (M2) LONGITUD (M) ANCHO (M)
(M)
AV. VIRGEN BENDITA CLARA 26 R01 4.40 9.65 3.60 1.20
AV. JOSE CARLOS MAREATEGUI 27 R02 4.32 9.60 3.60 1.20
JR CONCHUCOS 4 R03 3.72 9.28 3.60 1.05
JR. S/N 8 R04 4.53 9.72 3.60 1.20
JR. CONFRATERNIDAD 2 R05 4.32 9.60 3.60 1.20
JR. CARLOS MARK 2 R06 4.32 9.60 3.60 1.20
TOTAL 299.44 663.38 248.40 82.20
METRADO AREA DE VEREDAS DE ÁREAS LIBRES

PROYECTO “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO


POBLADO SANTA CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE
SIHUAS - DEPARTAMENTO DE ANCASH” (CÓDIGO ÚNICO N° 2406912).

LONGITUD ANCHO (M)


DESCRIPCION MZA TRAMO AREA (M2) PERIMETRO
PARA UÑA (M) VEREDA

BERMA TRIANGULAR E-01 73.55 95.07 1.20


ÁREA PÚBLICA N°01 E-02 51.72 47.53 1.20
ÁREA PÚBLICA N°03 E-03 101.03 222.19 1.20
TOTAL 226.30 0.00 364.79
METRADO AREA DE CUNETAS

PROYECTO “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO


SANTA CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS -
DEPARTAMENTO DE ANCASH” (CÓDIGO ÚNICO N° 2406912).

LONGITUD PARA
DESCRIPCION MZA TRAMO AREA (M2) PERIMETRO JUNTA DE ANCHO (M)
ASILAMIENTO (M)
AV. VIRGEN BENDITA CLARA CU-01 110.28 1103.17 551.38 0.20
AV. JOSE CARLOS MARIATEGUI CU-02 170.74 1707.80 853.70 0.20
JR. CARLOS MARX CU-03 50.64 506.77 253.18 0.20
JR. JOSE OLAYA CU-04 19.14 191.80 95.70 0.20
JR. CONCHUCOS CU-05 23.47 235.07 117.34 0.20
JR. PLAZA DE ARMAS 1 CU-06 16.92 169.63 84.62 0.20
JR. PLAZA DE ARMAS 2 CU-07 22.02 220.61 110.11 0.20
JR. CONFRATERNIDAD 1 CU-08 75.54 755.81 377.71 0.20
TOTAL 488.75 4,890.66 2,443.73
PLANILLA DE METRADOS - CUNETAS

Proyecto “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO SANTA CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS - DEPARTAMENTO
DE ANCASH” (CÓDIGO ÚNICO N° 2406912).
SubpresupuesPISTAS Y VEREDAS
Componente CUNETAS
Cliente MUNICIPALIDAD DISTRITAL DE HUAYLLABAMBA
Lugar HUAYLLABAMBA - SIHUAS - ANCASH
ITEM DESCRIPCION METRADO UND
CUNETAS
TRABAJOS PRELIMINARES
TRAZO, NIVELACIÓN Y REPLANTEO 488.75 M2
TRAZO, NIVELACIÓN Y REPLANTEO
MEDIDAS METRADO

FACTOR
Nº PARTIDAS UND. Nº BLOQUES Nº VECES ANCHO
LARGO (m) ALTO (m) AREA (m2) PARCIAL TOTAL
(m)
1.00 M2
VER HOJAS DE CUNETAS
CU-01 1.00 110.28 1.00 110.28 110.28
CU-02 1.00 170.74 1.00 170.74 170.74
CU-03 1.00 50.64 1.00 50.64 50.64
CU-04 1.00 19.14 1.00 19.14 19.14
CU-05 1.00 23.47 1.00 23.47 23.47
CU-06 1.00 16.92 1.00 16.92 16.92
CU-07 1.00 22.02 1.00 22.02 22.02
CU-08 1.00 75.54 1.00 75.54 75.54
488.75

MOVIMIENTO DE TIERRAS
CORTE HASTA NIVEL DE SUB RASANTE 342.12 M3

CORTE HASTA NIVEL DE SUB RASANTE


MEDIDAS METRADO

FACTOR

Nº PARTIDAS UND. BLOQUES Nº VECES LARGO (m) ANCHO ALTO
(m) (m) AREA (m2) PARCIAL TOTAL
1.00 M3
VER HOJAS DE MOVIMIENTO DE TIERRAS EN CUNETAS
VEREDAS
CU-01 1.00 0.70 110.28 77.19 77.19
CU-02 1.00 0.70 170.74 119.52 119.52
CU-03 1.00 0.70 50.64 35.45 35.45
CU-04 1.00 0.70 19.14 13.40 13.40
CU-05 1.00 0.70 23.47 16.43 16.43
CU-06 1.00 0.70 16.92 11.85 11.85
CU-07 1.00 0.70 22.02 15.41 15.41
CU-08 1.00 0.70 75.54 52.88 52.88
342.12

NIVELACIÓN, PERFILADO Y COMPACTADO EN SUB RASANTE EN ZONAS DE CORTE 488.75 M2

NIVELACIÓN, PERFILADO Y COMPACTADO EN SUB RASANTE EN ZONAS DE CORTE


MEDIDAS METRADO
FACTOR

Nº PARTIDAS UND. Nº
BLOQUES Nº VECES LARGO (m) ANCHO ALTO AREA (m2) PARCIAL TOTAL
(m) (m)
1.00 M2
VER HOJAS DE CUNETAS 1.00 488.75 1.00 488.75 488.75
488.75

SUMINISTRO Y COLOCACIÓN DE BASE COMPACTADO CON RODILLO #NAME? M3

SUMINISTRO Y COLOCACIÓN DE BASE COMPACTADO CON RODILLO


MEDIDAS METRADO
FACTOR

Nº PARTIDAS UND. Nº
BLOQUES Nº VECES LARGO (m) ANCHO ALTO AREA (m2) PARCIAL TOTAL
(m) (m)
1.00 M3
CUNETAS
CU-01 1.00 551.38 0.20 0.25 0.00 27.57 27.57
CU-02 1.00 853.70 0.20 0.25 0.00 42.69 42.69
CU-03 1.00 253.18 0.20 0.25 0.00 12.66 12.66
CU-04 1.00 95.70 0.20 0.25 0.00 4.78 4.78
CU-05 1.00 117.34 0.20 0.25 0.00 5.87 5.87
CU-06 1.00 84.62 0.20 0.25 0.00 4.23 4.23
CU-07 1.00 110.11 0.20 0.25 0.00 5.51 5.51
CU-08 1.00 377.71 0.20 0.25 0.00 18.89 18.89
#NAME?

BASE GRANULAR E=0.25 m #NAME? M2

BASE GRANULAR E=0.25 m


MEDIDAS METRADO
FACTOR

Nº PARTIDAS UND. Nº Nº VECES


BLOQUES ANCHO ALTO
LARGO (m) (m) (m) AREA (m2) PARCIAL TOTAL
1.00 M3
CUNETAS
CU-01 1.00 551.38 0.20 0.25 0.00 110.28 110.28
CU-02 1.00 853.70 0.20 0.25 0.00 170.74 170.74
CU-03 1.00 253.18 0.20 0.25 0.00 50.64 50.64
CU-04 1.00 95.70 0.20 0.25 0.00 19.14 19.14
CU-05 1.00 117.34 0.20 0.25 0.00 23.47 23.47
CU-06 1.00 84.62 0.20 0.25 0.00 16.92 16.92
CU-07 1.00 110.11 0.20 0.25 0.00 22.02 22.02
CU-08 1.00 377.71 0.20 0.25 0.00 75.54 75.54
#NAME?

ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA HASTA D=8KM 427.65 M3

ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA HASTA D=8KM


MEDIDAS METRADO

FACTOR

Nº PARTIDAS UND. BLOQUES Nº VECES AREA (M2) ANCHO ALTO VOLUMEN PARCIAL TOTAL
(m) (m) (m3)
1.00 M3
CORTE DE MATERIAL SUELTO MANUAL 1.00 342.12 1.25 427.65 427.65
427.65

OBRAS DE CONCRETO
ENCOFRADO Y DESENCOFRADO DE CUNETAS #NAME? M2

ENCOFRADO Y DESENCOFRADO DE CUNETAS


MEDIDAS METRADO

FACTOR
Nº PARTIDAS UND. Nº
BLOQUES Nº VECES LARGO (m) ANCHO ALTO AREA (m2) PARCIAL TOTAL
(m) (m)
1.00 M3
CU-01 1.00 551.38 0.20 1.00 110.28 110.28
CU-02 1.00 853.70 0.20 1.00 170.74 170.74
CU-03 1.00 253.18 0.20 1.00 50.64 50.64
CU-04 1.00 95.70 0.20 1.00 19.14 19.14
CU-05 1.00 117.34 0.20 1.00 23.47 23.47
CU-06 1.00 84.62 0.20 1.00 16.92 16.92
CU-07 1.00 110.11 0.20 1.00 22.02 22.02
CU-08 1.00 377.71 0.20 1.00 75.54 75.54
#NAME?

CONCRETO F'C=210 KG/CM2 EN CUNETAS #NAME? M3

CONCRETO F'C=210 KG/CM2 EN CUNETAS


MEDIDAS METRADO
FACTOR

Nº PARTIDAS UND. Nº Nº VECES


BLOQUES LARGO (m) ANCHO
(m)
ALTO
(m) AREA (m2) PARCIAL TOTAL
1.00 M3
VER HOJAS DE CUNETAS
CU-01 1.00 551.38 0.02 1.00 11.03 11.03
CU-02 1.00 853.70 0.02 1.00 17.07 17.07
CU-03 1.00 253.18 0.02 1.00 5.06 5.06
CU-04 1.00 95.70 0.02 1.00 1.91 1.91
CU-05 1.00 117.34 0.02 1.00 2.35 2.35
CU-06 1.00 84.62 0.02 1.00 1.69 1.69
CU-07 1.00 110.11 0.02 1.00 2.20 2.20
CU-08 1.00 377.71 0.02 1.00 7.55 7.55
#NAME?

CURADO
CURADO 488.75 M2

CURADO
MEDIDAS METRADO
FACTOR

Nº PARTIDAS UND. Nº Nº VECES


BLOQUES LARGO (m) ANCHO ALTO AREA (m2) PARCIAL TOTAL
(m) (m)

1.00 M2
VER HOJAS DE CUNETAS 1.00 488.75 1.00 488.75 488.75
488.75

JUNTAS
SELLADO DE JUNTAS EN SUPERFICIE HORIZONTALES CON POLIURETANO AUTONIVELANTE 2,444.00 M

SELLADO DE JUNTAS EN SUPERFICIE HORIZONTALES CON POLIURETANO AUTONIVELANTE


MEDIDAS METRADO
FACTOR

Nº PARTIDAS UND. Nº Nº VECES


BLOQUES ANCHO ALTO
LARGO (m) AREA (m2) PARCIAL TOTAL
(m) (m)
1.00 M PROM
VER HOJA DE CUNETAS 2,444.00 2,443.73 1.00 1.00 2,444.00 2,444.00
2,444.00
METRADO AREA DE SARDINEL DE CUNETA

PROYECTO “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO SANTA


CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS - DEPARTAMENTO DE ANCASH”
(CÓDIGO ÚNICO N° 2406912).

DESCRIPCION MZA TRAMO AREA (M2) PERIMETRO LONGITUD (M) ALTURA (M) ANCHO (M)

AV. VIRGEN BENDITA CLARA SS-01 86.58 1154.66 577.18 0.55 0.15
AV. JOSE CARLOS MARIATEGUI SS-02 134.05 1787.58 893.64 0.55 0.15
JR. CARLOS MARX SS-03 38.12 508.59 254.14 0.55 0.15
JR. JOSE OLAYA SS-04 15.03 200.65 100.17 0.55 0.15
JR. CONCHUCOS SS-05 18.42 245.95 122.83 0.55 0.15
JR. PLAZA DE ARMAS 1 SS-06 13.29 177.45 88.57 0.55 0.15
JR. PLAZA DE ARMAS 2 SS-07 17.29 230.81 115.26 0.55 0.15
JR. CONFRATERNIDAD 1 SS-08 59.31 791.05 395.38 0.55 0.15
TOTAL 382.08 5,096.74 2,547.17
PLANILLA DE METRADOS - SARDINEL DE CUNETA

Proyecto “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANO DEL CENTRO POBLADO SANTA CLARA - DISTRITO DE HUAYLLABAMBA - PROVINCIA DE SIHUAS - DEPARTAMENTO DE ANCASH”
(CÓDIGO ÚNICO N° 2406912).
SubpresupuesPISTAS Y VEREDAS
Componente SARDINEL SIMPLE
Cliente MUNICIPALIDAD DISTRITAL DE HUAYLLABAMBA
Lugar HUAYLLABAMBA - SIHUAS - ANCASH
ITEM DESCRIPCION METRADO UND
SARDINEL
TRABAJOS PRELIMINARES
TRAZO, NIVELACIÓN Y REPLANTEO 382.08 M2
TRAZO, NIVELACIÓN Y REPLANTEO
MEDIDAS METRADO

FACTOR
Nº PARTIDAS UND. Nº BLOQUES Nº VECES ANCHO
LARGO (m) ALTO (m) AREA (m2) PARCIAL TOTAL
(m)
1.00 M2
VER HOJAS DE SARDINEL SIMPLE
SS-01 1.00 86.58 1.00 86.58 86.58
SS-02 1.00 134.05 1.00 134.05 134.05
SS-03 1.00 38.12 1.00 38.12 38.12
SS-04 1.00 15.03 1.00 15.03 15.03
SS-05 1.00 18.42 1.00 18.42 18.42
SS-06 1.00 13.29 1.00 13.29 13.29
SS-07 1.00 17.29 1.00 17.29 17.29
SS-08 1.00 59.31 1.00 59.31 59.31
382.08

MOVIMIENTO DE TIERRAS
CORTE HASTA NIVEL DE SUB RASANTE 210.14 M3

CORTE HASTA NIVEL DE SUB RASANTE


MEDIDAS METRADO

FACTOR
Nº PARTIDAS UND. Nº Nº VECES
BLOQUES ANCHO ALTO
LARGO (m) (m) (m) AREA (m2) PARCIAL TOTAL
1.00 M3
VER HOJAS DE MOVIMIENTO DE TIERRAS EN SARDINEL SIMPLE
SARDINEL SIMPLE
SS-01 1.00 0.55 86.58 47.62 47.62
SS-02 1.00 0.55 134.05 73.73 73.73
SS-03 1.00 0.55 38.12 20.97 20.97
SS-04 1.00 0.55 15.03 8.26 8.26
SS-05 1.00 0.55 18.42 10.13 10.13
SS-06 1.00 0.55 13.29 7.31 7.31
SS-07 1.00 0.55 17.29 9.51 9.51
SS-08 1.00 0.55 59.31 32.62 32.62
210.14

NIVELACIÓN, PERFILADO Y COMPACTADO EN SUB RASANTE EN ZONAS DE CORTE 382.08 M2

NIVELACIÓN, PERFILADO Y COMPACTADO EN SUB RASANTE EN ZONAS DE CORTE


MEDIDAS METRADO
FACTOR


Nº PARTIDAS UND. BLOQUES Nº VECES LARGO (m) ANCHO ALTO
(m) (m) AREA (m2) PARCIAL TOTAL

1.00 M2
VER HOJAS DE SARDINEL SIMPLE 1.00 382.08 1.00 382.08 382.08
382.08

ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA HASTA D=8KM 262.68 M3

ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA HASTA D=8KM


MEDIDAS METRADO
FACTOR

Nº PARTIDAS UND. Nº Nº VECES


BLOQUES ANCHO ALTO VOLUMEN
AREA (M2) (m) (m) (m3) PARCIAL TOTAL

1.00 M3
CORTE DE MATERIAL SUELTO MANUAL 1.00 210.14 1.25 262.68 262.68
262.68

OBRAS DE CONCRETO
ENCOFRADO Y DESENCOFRADDO DE VEREDAS 382.08 M2

ENCOFRADO Y DESENCOFRADDO DE VEREDAS


MEDIDAS METRADO
FACTOR

Nº PARTIDAS UND. Nº Nº VECES


BLOQUES
FACTOR

Nº PARTIDAS UND. BLOQUES Nº VECES LARGO (m) ANCHO ALTO
(m) (m) AREA (m2) PARCIAL TOTAL

1.00 M3
SS-01 1.00 577.18 0.15 1.00 86.58 86.58
SS-02 1.00 893.64 0.15 1.00 134.05 134.05
SS-03 1.00 254.14 0.15 1.00 38.12 38.12
SS-04 1.00 100.17 0.15 1.00 15.03 15.03
SS-05 1.00 122.83 0.15 1.00 18.42 18.42
SS-06 1.00 88.57 0.15 1.00 13.29 13.29
SS-07 1.00 115.26 0.15 1.00 17.29 17.29
SS-08 1.00 395.38 0.15 1.00 59.31 59.31
382.08

ACERO CORRUGADO F'y=4200 kg/cm2 GRADO 60 4,204.70 KG

ACERO CORRUGADO F'y=4200 kg/cm2 GRADO 60


MEDIDAS

FACTOR
METRADO
Nº PARTIDAS UND. Nº Nº VECES
BLOQUES LARGO (m) 1/2" 3/8" 5/8" (Kg/ml) PARCIAL TOTAL
(Kg/ml) (Kg/ml)
1.00 KG 0.99 0.56 1.55
TRANSVERSAL LONGITUD (m)
SS-01 2,309.00 577.18 0.45 1.05 610.96 610.96
SS-02 3,575.00 893.64 0.45 1.05 945.95 945.95
SS-03 1,017.00 254.14 0.45 1.05 269.10 269.10
SS-04 401.00 100.17 0.45 1.05 106.10 106.10
SS-05 492.00 122.83 0.45 1.05 130.18 130.18
SS-06 355.00 88.57 0.45 1.05 93.93 93.93
SS-07 462.00 115.26 0.45 1.05 122.25 122.25
SS-08 1,582.00 395.38 0.45 1.05 418.60 418.60
LONGITUDINAL
SS-01 145.00 577.18 4.00 1.05 341.04 341.04
SS-02 224.00 893.64 4.00 1.05 526.85 526.85
SS-03 64.00 254.14 4.00 1.05 150.53 150.53
SS-04 26.00 100.17 4.00 1.05 61.15 61.15
SS-05 31.00 122.83 4.00 1.05 72.91 72.91
SS-06 23.00 88.57 4.00 1.05 54.10 54.10
SS-07 29.00 115.26 4.00 1.05 68.21 68.21
SS-08 99.00 395.38 4.00 1.05 232.85 232.85
4,204.70

CONCRETO F'C=210 KG/CM2 EN SARDINEL SIMPLE 210.14 M3

CONCRETO F'C=210 KG/CM2 EN SARDINEL SIMPLE


MEDIDAS METRADO
FACTOR
Nº PARTIDAS UND. Nº
BLOQUES Nº VECES LARGO (m) ANCHO ALTO AREA (m2) PARCIAL TOTAL
(m) (m)
1.00 M3
VER HOJAS DE SARDINEL SIMPLE
SS-01 1.00 577.18 0.15 0.55 1.00 47.62 47.62
SS-02 1.00 893.64 0.15 0.55 1.00 73.73 73.73
SS-03 1.00 254.14 0.15 0.55 1.00 20.97 20.97
SS-04 1.00 100.17 0.15 0.55 1.00 8.26 8.26
SS-05 1.00 122.83 0.15 0.55 1.00 10.13 10.13
SS-06 1.00 88.57 0.15 0.55 1.00 7.31 7.31
SS-07 1.00 115.26 0.15 0.55 1.00 9.51 9.51
SS-08 1.00 395.38 0.15 0.55 1.00 32.62 32.62
210.14

CURADO
CURADO DE CONCRETO 382.08 M2

CURADO DE CONCRETO
MEDIDAS METRADO
FACTOR

Nº PARTIDAS UND. Nº Nº VECES


BLOQUES ANCHO ALTO
LARGO (m) (m) (m) AREA (m2) PARCIAL TOTAL

1.00 M2
VER HOJAS DE SARDINEL SIMPLE
SS-01 1.00 577.18 0.15 1.00 86.58 86.58
SS-02 1.00 893.64 0.15 1.00 134.05 134.05
SS-03 1.00 254.14 0.15 1.00 38.12 38.12
SS-04 1.00 100.17 0.15 1.00 15.03 15.03
SS-05 1.00 122.83 0.15 1.00 18.42 18.42
SS-06 1.00 88.57 0.15 1.00 13.29 13.29
SS-07 1.00 115.26 0.15 1.00 17.29 17.29
SS-08 1.00 395.38 0.15 1.00 59.31 59.31
382.08
JUNTAS
JUNTA ASFALTICA DE CONSTRUCCIÓN Y/O DILATACIÓN 95.55 M

JUNTA ASFALTICA DE CONSTRUCCIÓN Y/O DILATACIÓN


MEDIDAS METRADO

FACTOR
Nº PARTIDAS UND. Nº Nº VECES
BLOQUES ANCHO ALTO AREA CAD
LARGO (m) (m) (m) (m2) PARCIAL TOTAL
VER PLANO DE PERFIL
637.00 2,547.17 0.15 1.00 95.55 95.55
95.55

También podría gustarte