Untitled Gantt Project Oct 5, 2021

http://

Project manager
Project dates Oct 5, 2021 - Oct 6, 2021

Completion 0%
Tasks 61
Resources 0
Untitled Gantt Project Oct 5, 2021
2
Tasks
Name Begin date End date
1.TRABAJOS PRELIMINARES 10/5/21 10/5/21
1.01 Limpieza del terreno y replanteo 10/5/21 10/5/21

2. MOVIMIENTO DE TIERRA 10/5/21 10/5/21


2.01 Excavación para zapata de muros 10/5/21 10/5/21
2.02 Excavación para zapata de columnas 10/5/21 10/5/21
2.03 Relleno del terreno con material producto de 10/5/21 10/5/21
excavaciones
2.04 Bote de material 10/5/21 10/5/21

3. HORMIGÓN ARMADO 10/5/21 10/5/21


3.01 Zapata de muros 10/5/21 10/5/21
3.02 Zapata de columnas 10/5/21 10/5/21
3.03 Columnas 10/5/21 10/5/21
3.04 Vigas 10/5/21 10/5/21
3.05 Losa de techo plana 10/5/21 10/5/21

4. MUROS DE BLOQUES 10/5/21 10/5/21


4.01 Muros de 6" 10/5/21 10/5/21

5. TECHOS DE ZINC 10/5/21 10/5/21


5.01 Planchas de zinc para techos acanalados 10/5/21 10/5/21

6. TERMINACIÓN DE SUPERFICIES 10/5/21 10/5/21


6.01 Fraguado de hormigón 10/5/21 10/5/21
6.02 Pañete de muros 10/5/21 10/5/21
6.03 Pañete de columnas 10/5/21 10/5/21
6.04 Antepecho 10/5/21 10/5/21
6.05 Fino de techo 10/5/21 10/5/21
6.06 Marco de ventanas 10/5/21 10/5/21
6.07 Desague de techo 10/5/21 10/5/21

7. TERMINACIÓN DE PISO 10/5/21 10/5/21


7.01 Cerámica para baños 10/5/21 10/5/21
7.02 Pisos de hormigon pulido 10/5/21 10/5/21

8. REVESTIMIENTO 10/5/21 10/5/21


8.01 Cerámicas para revestimiento en baños 10/5/21 10/5/21

9. INSTALACIONES SANITARIAS 10/5/21 10/5/21


9.01 Suministro e instalacion de inodoros economicos 10/5/21 10/5/21
blancos
Untitled Gantt Project Oct 5, 2021
3
Tasks
Name Begin date End date
9.02 Suministro e instalacion de lavamanos 10/5/21 10/5/21
9.03 Suminsitro e instalacion de lavadero 10/5/21 10/5/21
9.04 Suministro e instalacion de fregadero 10/5/21 10/5/21
9.05 Duchas 10/5/21 10/5/21
9.06 Desagues de piso 10/5/21 10/5/21
9.07 Septico 10/5/21 10/5/21
9.08 Tramos de grasa 10/5/21 10/5/21

10. INSTALACIONES ELÉCTRICAS 10/5/21 10/5/21


10.01 Luces cenitales 10/5/21 10/5/21
10.02 Tomacorrientes dobles 110v 10/5/21 10/5/21
10.02 Interruptores simples blancos 10/5/21 10/5/21
10.03 Interruptores simples blancos 10/5/21 10/5/21
10.04 Interruptores dobles blancos 10/5/21 10/5/21
10.05 Panel de distribución 10/5/21 10/5/21
10.06 Salida para telefonos 10/5/21 10/5/21
10.07 Salida para cable o antena 10/5/21 10/5/21
10.08 Panel de conexión para elestricidad de la calle 10/5/21 10/5/21

11. TERMINACIÓN DE COCINA 10/5/21 10/5/21


11.01 Obtención e Instalación de topes en marmolite 10/5/21 10/5/21
11.02 Hormigonado de base para meseta 10/5/21 10/5/21
11.03 Gabinetes de cristal y aluminio 10/5/21 10/5/21

12. PUERTAS Y VENTANAS 10/5/21 10/5/21


12.01 Puerta económica color Blanco(1.00x 2.10m) 10/5/21 10/5/21
12.02 Puerta económica color blanco (0.80 x 2.10m) 10/5/21 10/5/21
12.03 Ventanas de celocías en aluminio blancas 10/5/21 10/5/21

13. TERMINACIÓN DE PINTURA 10/5/21 10/5/21


13.01 Pintura Acrílica para interior y exterior 10/5/21 10/5/21

14. LIMPIEZA FINAL 10/5/21 10/5/21


14.01 Limpieza durante y completada la obra 10/5/21 10/5/21
Untitled Gantt Project Oct 5, 2021
4
Gantt Chart
October 2021 November 2021

5 6 7 8 11 12 13 14 15 18 19 20 21 22 25 26 27 28 29 1 2 3 4 5 8 9 10 11 12
Name Begin date End date
1.TRABAJOS PRELIMIN... 10/5/21 10/5/21
2. MOVIMIENTO DE TI... 10/5/21 10/5/21
3. HORMIGÓN ARMA... 10/5/21 10/5/21
4. MUROS DE BLOQUES 10/5/21 10/5/21
5. TECHOS DE ZINC 10/5/21 10/5/21
6. TERMINACIÓN DE S... 10/5/21 10/5/21
7. TERMINACIÓN DE P... 10/5/21 10/5/21
8. REVESTIMIENTO 10/5/21 10/5/21
9. INSTALACIONES SA... 10/5/21 10/5/21
10. INSTALACIONES EL... 10/5/21 10/5/21
11. TERMINACIÓN DE ... 10/5/21 10/5/21
12. PUERTAS Y VENTA... 10/5/21 10/5/21
13. TERMINACIÓN DE ... 10/5/21 10/5/21
14. LIMPIEZA FINAL 10/5/21 10/5/21
Untitled Gantt Project Oct 5, 2021
5
Resources Chart
October 2021 November 2021

5 6 7 8 11 12 13 14 15 18 19 20 21 22 25 26 27 28 29 1 2 3 4 5 8 9 10 11 12
Name Default role

También podría gustarte