PRESUPUESTO

ITEM DESCRIPCION UNID CANT


MATERIALES M. DE .O
1 MODULO 4 (DESPLAZAMIENTO DE POSTE MT & BT)
1.1 LOCALIZACION Y REPLANTEO ML 6,826
1.2 DESMONTAR ESTRUCTURA MT UND 13 $ 37,300 $ 28,900
1.3 DESMONTAR LUMINARIAS DE AP UND 1 $ 37,300 $ 28,900
1.4 RETIRO DE POSTE MT UND 13 $ 125,600.00
1.5 RETIRO DE RETENIDA MT UND 11 $ 47,800.00
1.6 POSTE MT 12 X 510KGF UND 13 $ 1,668,849 $ 256,689
1.7 CIMENTACIÓN POSTE MT UND 13 $ 99,239 $ 72,795
1.8 MONTAR ESTRUCTURA ICEL EN H RH231 UND 1 $ 985,784.00 $ 115,167.00
1.9 MONTAR ESTRUCTURA ICEL 710 UND 2 $ 813,564 $ 306,256
1.10 MONTAR ESTRUCTURA ICEL 561 UND 10 $ 613,564 $ 206,256
1.11 RETENIDA MT UND 11 $ 173,268 $ 137,504
1.12 EMPALME Y TENDIDO DE RED KM 1.47 $ 1,653,767 $ 290,650
1.13 MONTAR LIMINARIA DE AP UND 23 $ 206,256
1.14 DESMONTAR Y MONTAR TRANSFORMADOR A ESTRUCTURA ICEL 710 UND 2 $ 190,000.00
1.15 RETIRO DE POSTE BT UND 5 $ 100,000.00
1.16 DESMONTAR ESTRUCTURA BT UND 5 $ 37,300 $ 28,900
SUBTOTAL MODULO 4

2 RED DE MEDIA TENSION


2.1 Transformador Trifasico Pad Mounted O Pedestal De 75 KVA UND 3 $ 16,135,000 $ 3,227,000.00
2.2 Transformador Trifasico Pad Mounted O Pedestal De 45 KVA UND 2 $ 14,300,000 $ 2,860,000.00
2.3 EMPALME DE TRANSFORMADOR cable desnudo de cobre calibre 4 AWG M 12 $ 8,200.00 $ 1,640.00
2.4 SUMINISTRO DE KIT PUESTA A TIERRA UND 4 $ 1,337,408.00 $ 267,481.60
2.5 Varilla puesta a tierra 2,4 m UND 5 $ 250,000.00 $ 50,000.00
2.6 Caja de maniobra UND 5 $ 6,000,000.00 $ 1,200,000.00
2.7 Cable de Aluminio Serie 8000 THHN 2 AWG M 2923.24 $ 2,950.00 $ 590.00
2.8 Transicion Media tension UND 5 #REF! #REF!
2.9 CAJA DE PASO NORMA CS 275 ODENSA (1,2 X0,7X1,3 M; CON MARCO Y TAPA EN CONCRETO) UND 14 $ 1,500,000.00 $ 90,000.00
2.10 Suministro e instalación de Cable ALUMINIO AISLADO 3X1/0 + 1 X 1/0 N + 1 X 4 T, RHW-2, SERIE 8000 ml 633.44 $ 43,000.00
2.11 CANALIZACION SUBTERRANEA INCLUYE EXCAVACION A=0,70 M H=1M Y SUMINISTRO TUBERIA PVC CONDUIT, 2 TUBOS DE 3" + 2 TU ML 633.44 $ 120,000.00
SUBTOTAL RED DE MEDIA TENSION

3 RED DE BAJA TENSION


3.1 CANALIZACION SUBTERRANEA TUBERIA PVC CONDUIT, 2 TUBOS DE 3" + 2 TUBOS DE 2" + 1 TUBO DE 1" ML 4048.773 $ 120,000.00
CANALIZACION SUBTERRANEA TUBERIA PVC CONDUIT, 2 TUBOS DE 1" (1 ACOMETIDA ELECTRICA + 1 ACOMETIDA
3.2 M 4160 $ 30,000.00
COMUNICACIONES POR LOTE, PROMEDIO 35 ML /LOTE)
3.3 CAJA DE PASO NORMA CS 275 CODENSA (1,2 X0,7X1,3 M; CON MARCO Y TAPA EN CONCRETO) UND 134 $ 1,500,000.00 $ 90,000.00
3.4 CAJAS DE INSPECCIÓN DE ACOMETIDA 40X40X40 CM UND 202 $ 310,000 $ 103,333.33
3.5 Suministro e instalación de Cable ALUMINIO AISLADO 3X2/0 + 1 X 2/0 N + 1 X 4 T, RHW-2, SERIE 8000 ML 4048.773 $ 55,000.00
3.6 Kit para cerca electrica ML 2844 $ 39,200.00 $ 3,000.00
3.7 Barraje cobre desnudo baja tension, para puesta a tierra, 200 A. 2,4 m UND 100 $ 70,000.00 $ 23,333.33

3.8 BARRAJE PREFORMADO DE 8 PUESTOS UND 100 $ 1,500,000.00

3.9 Suministro e instalación de Cable ALUMINIO AISLADO 2X6 + 1 X 6 N + 1 X 6 T, RHW-2, SERIE 8000 (ACOMETIDAS A LOTES; M 6060 $ 18,000.00
PROMEDIO 40ML/LOTE) OPCIONAL PUESTO SE REQUERIRIAN AL MONENTO DE CONSTRUCCION DE LAS VIVIENDAS

3.10 MEDIDORES UND 208 $ 550,000.00

SUBTOTAL RED BAJA TENSION

4 MODULO (ALUMBRADO)
4.1 SYLVANIA - LED STREET LIGHT 35W NW URBAN UND 137 $ 496,708.00 $ 165,569.33
4.2 SYLVANIA - KIT SOLAR STREET URBAN 35W NW UND 109 $ 2,484,039.00 $ 248,403.90
4.10 FEILO SYLVANIA START eco Bollard Rectangular L IP65 750lm 830 BLK /0 UND 345 $ 173,767.00 $ 206,256
4.11 POSTE 6M + BRAZO 1,5 M PARA LUMINARIAS AP UND 258 $ 850,000.00 $ 170,000.00
4.12 SECCIONADOR FUSIBLE UND 108 $ 25,589.00 $ 5,117.80
4.13 Suministro e instalación de Cable ALUMINIO AISLADO 1X6 + 1 X 6 N + 1 X 6 T, RHW-2, SERIE 8000. (RED IDEPENDIENTE DE ALUM M 4048.773 $ 18,000.00

CANALIZACION SUBTERRANEA TUBERIA PVC CONDUIT, 1 TUBO DE 3/4" (1 ACOMETIDA ELECTRICA DESDE CAJA PASO MAS
4.14 CERCANA A POSTE DE ALUMBRADO PUBLICO) M 2144.28 $ 20,000.00
4.17 REFLECTORES PARA ILUMINACIÓN DEPORTIVA LED PROYECTOR SYLVEO UND 16 $ 1,925,214.00 $ 385,042.80
4.18 POSTES 12 M PARA LOS REFLECTORES DE LAS CANCHAS UND 16 $ 1,668,849 $ 333,769.80
SUBTOTAL MODULO 3

5 MODULO 5 (AREAS COMUNES)


5.1 CANALIZACION SUBTERRANEA TUBERIA PVC CONDUIT, 2 TUBOS DE 3" + 2 TUBOS DE 2" + 1 TUBO DE 1" ML 629.83 $ 110,000.00
5.2 CANALIZACION SUBTERRANEA TUBERIA PVC CONDUIT, 1 TUBOS DE 1" (1 ACOMETIDA ELECTRICA ) ML 353.1 $ 30,000.00
5.3 CANALIZACION SUBTERRANEA TUBERIA PVC CONDUIT, 1 TUBO DE 1" ( ALUMBRADO PUBLICO CAJAS DE ALUMBRADO ) ML 208.65 $ 30,000.00
5.4 CAJA DE PASO NORMA CS 275 CODENSA (1,2 X0,7X1,3 M; CON MARCO Y TAPA EN CONCRETO) UND 19 $ 1,500,000.00 $ 90,000.00
5.5 CAJA DE PASO 40X40 ACOMETIDAS UND 11 $ 310,000 $ 103,333.33
5.6 CAJA DE INSPECCION ALUMBRADO PUBLICO UND 19 $ 310,000 $ 103,333.33
5.7 629.83 $ 43,000
5.8 BARRAJE PREFORMADO DE 4 PUESTOS UND 8 $ 700,000.00
5.9 Varilla puesta a tierra 2,4 m UND 5 $ 250,000.00
5.10 Medidores und 3 $ 550,000.00
Suministro e instalación de Cable ALUMINIO AISLADO 2X6 + 1 X 6 N + 1 X 6 T, RHW-2, SERIE 8000 (ACOMETIDAS ZONAS
5.11 COMUNES) ML 353.1 $ 18,000.00
5.12 SUMINISTRO E INSTALACION CABLE TTU DE ENTERRAMIENTO DIRECTO 12 AWG 7 HILOS ML 7383 $ 18,000.00
Suministro e instalación de Cable ALUMINIO AISLADO 2X6 + 1 X 6 N + 1 X 6 T, RHW-2, SERIE 8000 (ALUMBRADO JARDINERAS
5.13 ML 645.21 $ 18,000.00
ZONAS COMUNES)

SUBTOTAL MODULO 5

6 MODULO 6 (DISEÑO/DERECHOS/RETIE/MANIOBRAS)
6.1 Dirección técnica, datos básicos, elaboración de planos, aprobación de proyecto y gestión ante Operador de Red. UND 1
6.2 Derechos Operador de Red ( interventoría, conexiones en caliente y energización ) UND 1
6.3 Permiso Planeacion municipal extencion de Red aerea x vias UND 1
Certificación RETIE:
6.4 UND 1
• Uso final (se requieren planos eléctricos para justificar la carga solicitada + estudios de riesgo eléctrico, apantallamiento y sistema
de tierra)
SUBTOTAL MODULO 6

TOTAL COSTO DIRECTO

ADMINISTRACION 5%
IMPREVISTOS 5%
UTILIDAD 5%
IVA SOBRE UTILIDAD 19%
VALOR TOTAL DEL PRESUPUESTO
PRESUPUESTO
VR TOTAL
E&H TRANSPORTE INSTALACIÓN VR UNITARIO

$ 1,800 $ 12,286,800.00
$ 7,456 $ - $ 36,356.00 $ 73,656.00 $ 957,528.00
$ 7,456 $ - $ 36,356.00 $ 73,656.00 $ 73,656.00
$ 290,355.00 $ 283,955.00 $ 699,910.00 $ 699,910.00 $ 9,098,830.00
$ 45,300.00 $ 249.00 $ 93,349.00 $ 93,349.00 $ 1,026,839.00
$ 91,469 $ 280,355 $ 628,513.00 $ 2,297,362.00 $ 29,865,706.00
$ 43,229 $ 582,868 $ 698,892.00 $ 798,131.00 $ 10,375,703.00
$ 100,386.00 $ 565,429.00 $ 780,982.00 $ 1,766,766.00 $ 1,766,766.00
$ 28,193 $ 223,536 $ 557,985.00 #REF! #REF!
$ 28,193 $ 223,536 $ 457,985 $ 1,071,549.00 $ 10,715,490.00
$ 18,795 $ 163,540 $ 319,839.00 $ 493,107.00 $ 5,424,177.00
$ 76,800 $ 154,890 $ 522,340.00 $ 2,176,107.00 $ 3,198,877.29
$ 28,193 $ 223,536 $ 457,985.00 $ 457,985.00 $ 10,533,655.00
$ 170,000.00 $ 80,000.00 $ 440,000.00 $ 440,000.00 $ 880,000.00
$ 290,000.00 $ 390,000.00 $ 390,000.00 $ 1,950,000.00
$ 7,456 $ - $ 36,356.00 $ 73,656.00 $ 368,280.00
#REF!

$ 1,613,500.00 $ 1,613,500.00 $ 6,454,000.00 $ 22,589,000.00 $ 67,767,000.00


$ 1,430,000.00 $ 1,430,000.00 $ 5,720,000.00 $ 20,020,000.00 $ 40,040,000.00
$ 820.00 $ 820.00 $ 3,280.00 $ 11,480.00 $ 137,760.00
$ 133,740.80 $ 133,740.80 $ 534,963.20 $ 1,872,371.20 $ 7,489,484.80
$ 25,000.00 $ 25,000.00 $ 100,000.00 $ 350,000.00 $ 1,750,000.00
$ 600,000.00 $ 600,000.00 $ 2,400,000.00 $ 8,400,000.00 $ 42,000,000.00
$ 295.00 $ 295.00 $ 1,180.00 $ 4,130.00 $ 12,072,981.20
#REF! #REF! #REF! #REF! #REF!
$ 127,527.00 $ 217,527.00 $ 1,717,527.00 $ 24,045,378.00
$ - $ 43,000.00 $ 27,237,920.00
$ - $ 120,000.00 $ 76,012,800.00
#REF!

$ - $ 120,000.00 $ 485,852,760.00

$ - $ 30,000.00 $ 124,800,000.00
$ 127,527.00 $ 217,527.00 $ 1,717,527.00 $ 230,148,618.00
$ 77,500.00 $ 25,833.33 $ 206,666.67 $ 516,666.67 $ 104,366,666.67
$ - $ 55,000.00 $ 222,682,515.00
$ 2,500.00 $ 3,000.00 $ 8,500.00 $ 47,700.00 $ 135,658,800.00
$ 17,500.00 $ 5,833.33 $ 46,666.67 $ 116,666.67 $ 11,666,666.67

$ - $ 1,500,000.00 $ 150,000,000.00

$ - $ 18,000.00 $ 109,080,000.00

$ - $ 550,000.00 $ 114,400,000.00
$ - $ - $ -
$ 1,688,656,026.33

$ 124,177.00 $ 41,392.33 $ 331,138.67 $ 827,846.67 $ 113,414,993.33


$ 248,403.90 $ 248,403.90 $ 745,211.70 $ 3,229,250.70 $ 351,988,326.30
$ 28,193 $ 223,536 $ 457,985.00 $ 631,752.00 $ 217,954,440.00
$ 85,000.00 $ 85,000.00 $ 340,000.00 $ 1,190,000.00 $ 307,020,000.00
$ 2,558.90 $ 2,558.90 $ 10,235.60 $ 35,824.60 $ 3,869,056.80
$ - $ 18,000.00 $ 72,877,914.00

$ 20,000.00 $ 42,885,600.00
$ 192,521.40 $ 192,521.40 $ 770,085.60 $ 2,695,299.60 $ 43,124,793.60
$ 166,884.90 $ 166,884.90 $ 667,539.60 $ 2,336,388.60 $ 37,382,217.60
$ 1,190,517,341.63

$ - $ 110,000.00 $ 69,281,300.00
$ - $ 30,000.00 $ 10,593,000.00
$ - $ 30,000.00 $ 6,259,500.00
$ 127,527.00 $ 217,527.00 $ 1,717,527.00 $ 32,633,013.00
$ 77,500.00 $ 25,833.33 $ 206,666.67 $ 516,666.67 $ 5,683,333.33
$ 77,500.00 $ 25,833.33 $ 206,666.67 $ 516,666.67 $ 9,816,666.67
$ 43,000.00 $ 27,082,690.00
$ - $ 700,000.00 $ 5,600,000.00
$ 250,000.00 $ 250,000.00 $ 1,250,000.00
$ - $ 550,000.00 $ 1,650,000.00
$ - $ 18,000.00 $ 6,355,800.00
$ - $ 18,000.00 $ 132,894,000.00
$ - $ 18,000.00 $ 11,613,780.00

$ 320,713,083.00

11,590,000 $ 11,590,000.00
12,585,868 $ 12,585,868.00
3,000,000 $ 3,000,000.00
21,050,000 $ 21,050,000.00

$ 48,225,868.00

#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
ITEM DESCRIPCION UNID CANT VR TOTAL
VR UNITARIO
1 OBRAS PRELIMINARES
1.1 LOCALIZACION Y REPLANTEO ML 6,826 $ 1,800 $ 12,286,800.00
1.2 DESMONTAR ESTRUCTURA MT UND 13 $ 73,656 $ 957,528.00
1.3 DESMONTAR LUMINARIAS DE AP UND 1 $ 73,656 $ 73,656.00
1.4 RETIRO DE POSTE MT UND 13 $ 699,910 $ 9,098,830.00
1.5 RETIRO DE RETENIDA MT UND 11 $ 93,349 $ 1,026,839.00
1.6 POSTE MT 12 X 510KGF UND 13 $ 2,297,362 $ 29,865,706.00
1.7 CIMENTACIÓN POSTE MT UND 13 $ 798,131 $ 10,375,703.00
1.8 MONTAR ESTRUCTURA ICEL EN H RH231 UND 1 $ 1,766,766 $ 1,766,766.00
1.9 MONTAR ESTRUCTURA ICEL 710 UND 2 $ 1,474,415 $ 2,948,830.35
1.10 MONTAR ESTRUCTURA ICEL 561 UND 10 $ 1,071,549 $ 10,715,490.00
1.11 RETENIDA MT UND 11 $ 493,107 $ 5,424,177.00
1.12 EMPALME Y TENDIDO DE RED KM 1 $ 2,176,107 $ 3,198,877.29
1.13 MONTAR LIMINARIA DE AP UND 23 $ 457,985 $ 10,533,655.00
1.14 DESMONTAR Y MONTAR TRANSFORMADOR A ESTRUCTURA ICEL 710 UND 2 $ 440,000 $ 880,000.00
1.15 RETIRO DE POSTE BT UND 5 $ 390,000 $ 1,950,000.00
1.16 DESMONTAR ESTRUCTURA BT UND 5 $ 73,656 $ 368,280.00
SUBTOTAL OBRAS PRELIMINARES $ 101,471,137.64

2 RED DE MEDIA TENSION


2.1 Transformador Trifasico Pad Mounted O Pedestal De 75 KVA UND 3 $ 22,589,000 $ 67,767,000.00
2.2 Transformador Trifasico Pad Mounted O Pedestal De 45 KVA UND 2 $ 20,020,000 $ 40,040,000.00
2.3 EMPALME DE TRANSFORMADOR cable desnudo de cobre calibre 4 AWG M 12 $ 11,480 $ 137,760.00
2.4 SUMINISTRO DE KIT PUESTA A TIERRA UND 4 $ 1,872,371 $ 7,489,484.80
2.5 Varilla puesta a tierra 2,4 m UND 5 $ 350,000 $ 1,750,000.00
2.6 Caja de maniobra UND 5 $ 8,400,000 $ 42,000,000.00
2.7 Cable de Aluminio Serie 8000 THHN 2 AWG M 2,923 $ 4,130 $ 12,072,981.20
2.8 Transicion Media tension UND 5 $ 7,476,463 $ 37,382,317.00
2.9 CAJA DE PASO NORMA CS 275 ODENSA (1,2 X0,7X1,3 M; CON MARCO Y TAPA EN UND 14 $ 1,717,527 $ 24,045,378.00
CONCRETO)
Suministro e instalación de Cable ALUMINIO AISLADO 3X1/0 + 1 X 1/0 N + 1 X 4 T,
2.10 ml 633 $ 43,000 $ 27,237,920.00
RHW-2, SERIE 8000

2.11 CANALIZACION SUBTERRANEA INCLUYE EXCAVACION A=0,70 M H=1M Y SUMINISTRO ML 633 $ 120,000 $ 76,012,800.00
TUBERIA PVC CONDUIT, 2 TUBOS DE 3" + 2 TUBOS DE 2" + 1 TUBO DE 1"

SUBTOTAL RED DE MEDIA TENSION $ 335,935,641.00

3 RED DE BAJA TENSION


CANALIZACION SUBTERRANEA INCLUYE EXCAVACION Y RELLENO SUMINISTRO TUBERIA
3.1 PVC CONDUIT 2 TUBOS DE 3" + 2 TUBOS DE 2" + 1 TUBO DE 1" ML 4,049 $ 120,000 $ 485,852,760.00

3.2 CANALIZACION SUBTERRANEA TUBERIA PVC CONDUIT, 2 TUBOS DE 1" (1 ACOMETIDA M 4,160 $ 30,000 $ 124,800,000.00
ELECTRICA + 1 ACOMETIDA COMUNICACIONES POR LOTE, PROMEDIO 35 ML /LOTE)

3.3 CAJA DE PASO NORMA CS 275 CODENSA (1,2 X0,7X1,3 M; CON MARCO Y TAPA EN UND 134 $ 1,717,527 $ 230,148,618.00
CONCRETO)
3.4 CAJAS DE INSPECCIÓN DE ACOMETIDA 40X40X40 CM UND 202 $ 516,667 $ 104,366,666.67
Suministro e instalación de Cable ALUMINIO AISLADO 3X2/0 + 1 X 2/0 N + 1 X 4 T,
3.5 RHW-2, SERIE 8000 ML 4,049 $ 55,000 $ 222,682,515.00
3.6 Kit para cerca electrica ML 2,844 $ 47,700 $ 135,658,800.00
3.7 Barraje cobre desnudo baja tension, para puesta a tierra, 200 A. 2,4 m UND 100 $ 116,667 $ 11,666,666.67
3.8 BARRAJE PREFORMADO DE 8 PUESTOS UND 100 $ 1,500,000 $ 150,000,000.00
Suministro e instalación de Cable ALUMINIO AISLADO 2X6 + 1 X 6 N + 1 X 6 T, RHW-2,
3.9 SERIE 8000 (ACOMETIDAS A LOTES; PROMEDIO 40ML/LOTE) OPCIONAL PUESTO SE M 6,060 $ 18,000 $ 109,080,000.00
REQUERIRIAN AL MONENTO DE CONSTRUCCION DE LAS VIVIENDAS
3.10 MEDIDORES UND 208 $ 550,000 $ 114,400,000.00
SUBTOTAL RED BAJA TENSION $ 1,688,656,026.33

4 MODULO 3 (ALUMBRADO)
4.1 SYLVANIA - LED STREET LIGHT 35W NW URBAN UND 137 $ 827,847 $ 113,414,993.33
4.2 SYLVANIA - KIT SOLAR STREET URBAN 35W NW UND 109 $ 3,229,251 $ 351,988,326.30
4.3 FEILO SYLVANIA START eco Bollard Rectangular L IP65 750lm 830 BLK /0 UND 345 $ 631,752 $ 217,954,440.00
4.4 POSTE 6M + BRAZO 1,5 M PARA LUMINARIAS AP UND 258 $ 1,190,000 $ 307,020,000.00
4.5 SECCIONADOR FUSIBLE UND 108 $ 35,825 $ 3,869,056.80
4.6 Suministro e instalación de Cable ALUMINIO AISLADO 1X6 + 1 X 6 N + 1 X 6 T, RHW-2 M 4,049 $ 18,000 $ 72,877,914.00

CANALIZACION SUBTERRANEA TUBERIA PVC CONDUIT, 1 TUBO DE 3/4" (1 ACOMETIDA


4.7 ELECTRICA DESDE CAJA PASO MAS CERCANA A POSTE DE ALUMBRADO PUBLICO) M 2,144 $ 20,000 $ 42,885,600.00

4.8 REFLECTORES PARA ILUMINACIÓN DEPORTIVA LED PROYECTOR SYLVEO UND 16 $ 2,695,300 $ 43,124,793.60
4.9 POSTES 12 M PARA LOS REFLECTORES DE LAS CANCHAS UND 16 $ 2,336,389 $ 37,382,217.60
SUBTOTAL MODULO ALUMBRADO $ 1,190,517,341.63

5 MODULO 5 (AREAS COMUNES)

CANALIZACION SUBTERRANEA TUBERIA PVC CONDUIT, 2 TUBOS DE 3" + 2 TUBOS DE 2"


5.1 + 1 TUBO DE 1" ML 630 $ 110,000 $ 69,281,300.00

5.2 CANALIZACION SUBTERRANEA TUBERIA PVC CONDUIT, 1 TUBOS DE 1" (1 ACOMETIDA ML 353 $ 30,000 $ 10,593,000.00
ELECTRICA )

CANALIZACION SUBTERRANEA TUBERIA PVC CONDUIT, 1 TUBO DE 1" ( ALUMBRADO


5.3 ML 209 $ 30,000 $ 6,259,500.00
PUBLICO CAJAS DE ALUMBRADO )

CAJA DE PASO NORMA CS 275 CODENSA (1,2 X0,7X1,3 M; CON MARCO Y TAPA EN
5.4 UND 19 $ 1,717,527 $ 32,633,013.00
CONCRETO)
5.5 CAJA DE PASO 40X40 ACOMETIDAS UND 11 $ 516,667 $ 5,683,333.33
5.6 CAJA DE INSPECCION ALUMBRADO PUBLICO UND 19 $ 516,667 $ 9,816,666.67
5.7 Suministro e instalación de Cable ALUMINIO AISLADO 3X1/0 + 1 X 1/0 N + 1 X 4 T, RHW- ML 630 $ 43,000 $ 27,082,690.00
5.8 BARRAJE PREFORMADO DE 4 PUESTOS UND 8 $ 700,000 $ 5,600,000.00
5.9 Varilla puesta a tierra 2,4 m UND 5 $ 250,000 $ 1,250,000.00
5.10 Medidores und 3 $ 550,000 $ 1,650,000.00
Suministro e instalación de Cable ALUMINIO AISLADO 2X6 + 1 X 6 N + 1 X 6 T, RHW-2,
5.11 SERIE 8000 (ACOMETIDAS ZONAS COMUNES) ML 353 $ 18,000 $ 6,355,800.00
5.12 SUMINISTRO E INSTALACION CABLE TTU DE ENTERRAMIENTO DIRECTO 12 AWG 7 HILOS ML 7,383 $ 18,000 $ 132,894,000.00
Suministro e instalación de Cable ALUMINIO AISLADO 2X6 + 1 X 6 N + 1 X 6 T, RHW-2,
5.13 SERIE 8000 (ALUMBRADO JARDINERAS ZONAS COMUNES) ML 645 $ 18,000 $ 11,613,780.00

SUBTOTAL MODULO 5 AREAS COMUNES $ 320,713,083.00

6 MODULO 6 (DISEÑO/DERECHOS/RETIE/MANIOBRAS)
Dirección técnica, datos básicos, elaboración de planos, aprobación de proyecto y
6.1 gestión ante Operador de Red. UND 1 $ 11,590,000 $ 11,590,000.00
6.2 Derechos Operador de Red ( interventoría, conexiones en caliente y energización ) UND 1 $ 12,585,868 $ 12,585,868.00
6.3 Permiso Planeacion municipal extencion de Red aerea x vias UND 1 $ 3,000,000 $ 3,000,000.00
Certificación RETIE:
6.4 • Uso final (se requieren planos eléctricos para justificar la carga solicitada + estudios de UND 1 $ 21,050,000 $ 21,050,000.00
riesgo eléctrico, apantallamiento y sistema de tierra)
SUBTOTAL MODULO 6 $ 48,225,868.00
TOTAL COSTO DIRECTO $ 3,685,519,098
ADMINISTRACION 5% $ 184,275,955
IMPREVISTOS 5% $ 184,275,955
UTILIDAD 5% $ 184,275,955
IVA SOBRE UTILIDAD 19% $ 35,012,431