Proyecto: PU SISTEMA DE RIEGO LAZARETO
Módulo: (M00) - OBRAS PRELIMINARES Tipo de cambio: 6.96
1.14 1 1 0.43 0.47 0.23 Precio
Parcial (Bs)
Nº P. Insumo/Parámetro Und. Cant. Unit. (Bs) Parcial (Bs) RPC Divisa Bienes Locales RPC MOC RPC MOSC RPC MONCR RPC MONCU Productivo
A MATERIALES
1 - VARIOS MATERIALES INST CMDAD glb 1.00 10,000.00 10 000.0000 10,000.00 10,000.00 10,000.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
> D TOTAL MATERIALES (A) = 10 000.0000 (A) = 10,000.00
B MANO DE OBRA
1 - ALBAÑIL hr 50.00 18.75 937.50 18.75 18.75 937.50
2- AYUDANTE hr 60.00 15.00 900.00 6.45 6.45 387.00
3- PEON hr 80.00 10.00 800.00 4.70 4.70 376.00
0.00 0.00
0.00 0.00
> E SUBTOTAL MANO DE OBRA (B) = 2 637.5000 (B) = 1,700.50
F Cargas Sociales 65.00% de (E) = 1 714.3750 65.00% de (E) = 1,105.33
O Impuesto al Valor Agregado 14.94% de (E+F) = 650.17 0.00% de (E+F) = 0.00
> G TOTAL MANO DE OBRA (E+F+O) = 5 002.0451 (E+F+O) = 2,805.83
C EQUIPO, MAQUINARIA Y HERRAMIEN
1- VOLQUETA hr 30.00 200.00 6 000.0000 200.00 200.00 6,000.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
H Herramientas menores 5.00% de (G) = 250.10 5.00% de (G) = 140.29
> I TOTAL HERRAMIENTAS Y EQUIPO (C+H) = 6 250.1023 (C+H) = 6,140.29
> J SUB TOTAL (D+G+I) = 21 252.1474 (D+G+I) = 18,946.12
L Gastos grales. y administrativ 10.00% de (J) = 2 125.2147 10.00% de (J) = 1,894.61
M Utilidad 10.00% de (J+L) = 2 337.7362 10.00% de (J+L) = 2,084.07
> N PARCIAL (J+L+M) = 25 715.0983 (J+L+M) = 22,924.80
P Impuesto a las Transacciones 3.09% de (N) = 794.60 0.00% de (N) = 0.00