Unit Hidrography

Runoff, Q (cfs/in of
Time (hr) Rainbfall excess)

0 0
1 10
2 100
3 200
4 150
5 100
6 50

Hyetograph (rain vs time)


Time(hr) 1 2 3 4
Precip(in) 0.5 1 1.5 0.5
Astraction (in) 0.3 0.3 0.3 0.3
Rainfall excess (in) 0.2 0.7 1.2 0.2

Resulting Runoff Hydrograph


What was the rainfall excess during hour…
1 2 3 4 SUM
Time (hr) 0.2 0.7 1.2 0.2 Runoff
0 0 0 0 0 0
1 2 0 0 0 2
2 20 7 0 0 27
3 40 70 12 0 122
4 30 140 120 2 292
5 20 105 240 20 385
6 10 70 180 40 300
7 0 35 120 30 185
8 0 0 60 20 80
9 0 0 0 10 10
10 0 0 0 0 0
FIGURA 7.2.5
TALA 7.4.1 pag 223

tabla 7.3.1
(graficicos tienes que salir asi)
TARRA 7.4.3

CLASE 19
FLUJO BASE 20 m3/s Calculo de Vd (m3) Calculo Rd (Vd/Area)
Area de drenaje 216 km2 15120000 m3 0.07 m
216000000 m2 (suma*tiempo*3600 seg)
HORA DIFERENCIA(Δt) 6 hrs
REFERENCIAS
PAG 223
PAG 140
HIETOGRAMA HIDROGRAMA DE
PERIODO DE LLUVIA LLUVIA CAUDAL TIEMPO (6 DE EXCESO DE ESCORRENTIA
SEIS HORAS (cm) (m) (m3/s) hr) LLUVIA (ERH) DIRECTA (DRH)
(m) (m3/s)
Columna 1 2 3 4 5 6
1 1.5 0.015 26 1 0.0100 6
2 3.5 0.035 71 2 0.0300 51
3 2.5 0.025 174 3 0.0200 154
4 1.5 0.015 226 4 0.0100 206
5 173 5 153
6 99 6 79 SUMA columna 6
7 49 7 29 700
8 33 8 13
9 26 9 6
10 22 10 2
11 21 11 1

Estimacion de tasa de atracciones de lluvia


Rd=Rm-Φ*Δt

1 M1 Φ*Δt
-0.00583333 -0.035

2 M2 Φ*Δt
-0.00083333 -0.005
HIDROGRAMA UNITARIO

3 M3 Φ*Δt
100
0.00027778 0.0016667

4 M4 Φ*Δt
0
0.00083333 0.005 1 2 3 4 5 6 7 8

HIDROGRAMA UNITARIO DEDUCIDO

R Ua (m3/s / cm)
1 6 4.8
2 33 31.8 Column C Column D
3 43 41.8
4 5 3.8
5 19 17.8
6 -31 0
7 79 0
8 -181 0

4.8 31.8 41.8 3.8 17.8 0 0 0


2 9.6 9.6 39.6
3 14.4 63.6 78 108
95.4 83.6 179 209
125.4 7.6 133 163
11.4 35.6 47 77
53.4 0 53.4 83.4
0 0 0 30
0 0 0 30
0 0 30
total 500 770