CALENDARIO VALORIZADO REPROGRAMADO DE OBRA

: "MEJORAMIENTO DEL SERVICIO DE TROCHA CARROZABLE DESDE PUENTE SAN FELIPE - MIRAFLORES - VILLA ALTA DE HUANAS - SANTAROSA DE OLAYA - SAÑUILCA, DISTRITO DE SANTIAGO DE CHOCORVOS - HUAYTARA -
PROYECTO
HUANCAVELICA"

DISTRITO : SANTIAGO DE CHOCORVOS


PROVINCIA : HUAYTARA
DPTO : HUANCAVELICA
FECHA : MARZO 2021

MES 01

MES 02

MES 03

MES 04

MES 05

MES 06

MES 07
METRADO

PARCIAL
P. UNIT
UNID

ENE.

FEB.
PARTIDA DESCRIPCION

20 AL

MAR.

ABR.

MAY.
NOV.
OCT.

JUN.
DIC.
31

15

29
01 OBRAS GENERALES TROCHA CARROZABLE 1,996,645.52 67,203.31 263,010.02 215,430.03 312,716.68 385,072.60 444,064.81 309,148.07
01.01 OBRAS PRELIMINARES 346,374.27 67,203.31 65,987.07 47,035.92 17,748.96 38,591.43 38,591.43 71,216.15
01.01.01 MOVILIZACION Y DESMOVILIZACION. GLB 1.00 60,890.78 60,890.78 9,133.62 9,133.62 9,133.62 33,489.92
01.01.02 CAMPAMENTO DE OBRA Y ALMACÉN GLB 1.00 19,117.79 19,117.79 19,117.79
01.01.03 TRAZO Y REPLANTEO CAMINO KM 17.58 2,114.05 37,165.00 37,165.00
01.01.04 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL mes 6.00 37,902.30 227,413.80 56,853.45 37,902.30 17,748.96 38,591.43 38,591.43 37,726.23
01.01.05 CARTEL DE OBRA und 1.00 1,786.90 1,786.90 1,786.90
01.02 MOVIMIENTO DE TIERRAS 843,169.62 0.00 197,022.95 157,954.11 124,584.95 159,122.60 135,149.49 69,335.52
01.02.01 CORTE EN MATERIAL SUELTO m3 16,037.88 6.25 100,236.75 47,608.63 40,768.31 5,929.91 5,929.91
01.02.02 CORTE EN ROCA SUELTA m3 2,671.30 14.28 38,146.16 21,920.37 3,629.98 6,297.91 6,297.91
01.02.03 CORTE EN ROCA FIJA m3 1,976.37 26.12 51,622.78 26,586.76 10,324.56 10,324.556 4,386.908
01.02.04 RELLENO CON MATERIAL PROPIO CARRETERA m3 6,102.95 11.36 69,329.51 49,471.21 13,920.54 5,937.76
01.02.05 PERFILADO, NIVELACIÓN Y COMPAC. EN ZONAS DE CORTE Y RELLENO m2 70,320.00 4.93 346,677.60 69,335.52 104,003.28 104,003.28 69,335.52
01.02.06 ELIMINACION DE MATERIAL EXCEDENTE m3 18,957.38 12.51 237,156.82 78,022.74 73,048.52 26,759.31 32,566.95 26,759.31
01.03 EXTRACCION, APILAMIENTO Y TRANSPORTE 263,240.13 0.00 0.00 10,440.00 78,972.04 52,648.03 121,180.07 0.00
01.03.01 EXTRACCION Y APILAMIENTO MATERIAL GRANULAR. m3 11,406.38 10.44 119,082.61 10,440.00 35,724.78 23,816.522 49,101.305

PARALIZADO POR LLUVIAS

PARALIZADO POR LLUVIAS


01.03.02 TRANSPORTE DE MATERIAL GRANULAR DE CANTERA D > 1KM M3K 33,340.56 3.38 112,691.09 33,807.33 22,538.218 56,345.545
01.03.03 TRANSPORTE DE MATERIAL GRANULAR DE CANTERA D < 1KM M3K 10,150.46 3.10 31,466.43 9,439.93 6,293.286 15,733.215
01.04 PAVIMENTOS 457,053.65 0.00 0.00 0.00 91,410.73 134,710.55 149,143.82 81,788.55
01.04.01 CONFORMACION DE BASE 0.15 M C/MATERIAL DE APORTE DE 0.15 M m3 11,406.38 40.07 457,053.65 91,410.73 134,710.55 149,143.82 81,788.55
01.05 SEÑALIZACION 86,807.85 0.00 0.00 0.00 0.00 0.00 0.00 86,807.85
01.05.01 SEÑAL INFORMATIVA CARRT. und 4.00 1,443.40 5,773.60 5,773.60
01.05.02 SEÑALES PREVENTIVAS DE 0.60 X 0.60 M und 123.00 504.95 62,108.85 62,108.85
01.05.03 SEÑALES REGLAMENTARIAS DE 0.90 X 0.60 M und 14.00 734.35 10,280.90 10,280.90
01.05.04 POSTE DE KILOMETRAJE und 17.00 508.50 8,644.50 8,644.50
02 OBRAS DE ARTE Y DRENAJE 700,629.90 0.00 9,410.63 0.00 34,458.03 243,035.64 241,848.65 171,876.96
02.01 CONSTRUCCION DE ALCANTARILLAS TMC 184,638.49 0.00 0.00 0.00 9,620.34 94,866.11 52,170.51 27,981.54
02.01.01 OBRAS PRELIMINARES 2,696.75 0.00 0.00 0.00 0.00 1,348.38 1,348.38 0.00
02.01.01.01 TRAZO Y REPLANTEO m2 431.48 6.25 2,696.75 1,348.38 1,348.38
02.01.02 MOVIMIENTO DE TIERRAS 32,834.23 0.00 0.00 0.00 0.00 32,834.23 0.00 0.00
02.01.02.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL SUELTO MANUAL m3 608.78 28.60 17,411.11 17,411.11
02.01.02.02 EXCAVACION EN ROCA FIJA m3 39.42 50.57 1,993.47 1,993.47
02.01.02.03 RELLENO EN ESTRUCTURAS C/MATERIAL PROPIO m3 200.32 33.88 6,786.84 6,786.84
02.01.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 531.00 12.51 6,642.81 6,642.81
02.01.03 ALCANTARILLA TMC 53,364.27 0.00 0.00 0.00 9,620.34 24,050.85 14,430.51 5,262.57
02.01.03.01 ALCANTARILLA TMC DIAM.= 24", E=1.8 mm m 109.00 441.30 48,101.70 9,620.34 24,050.85 14,430.51
02.01.03.02 ALIVIADERO Y EMBOQUILLADO DE PIEDRA (E=0.20M) m2 80.10 65.70 5,262.57 5,262.57
02.01.04 CONCRETO SIMPLE 4,729.80 0.00 0.00 0.00 0.00 4,729.80 0.00 0.00
02.01.04.01 ENCOFRADO Y DESENCOFRADO m2 18.36 41.47 761.39 761.39
02.01.04.02 CONCRETO CICLOPEO FC=175KG/CM2 + 30 % PM. m3 14.18 279.86 3,968.41 3,968.41
02.01.05 CONCRETO ARMADO 91,013.44 0.00 0.00 0.00 0.00 31,902.85 36,391.62 22,718.97
02.01.05.01 CABEZAL DE ENTRADA 45,575.50 0.00 0.00 0.00 0.00 31,902.85 13,672.65 0.00
02.01.05.01.01 CONCRETO FC=175 KG/CM2 m3 57.97 293.52 17,015.35 11,910.75 5,104.61
02.01.05.01.02 ENCOFRADO Y DESENCOFRADO m2 311.56 41.47 12,920.39 9,044.27 3,876.12
02.01.05.01.03 ACERO DE REFUERZO Fy=4200 kg/cm2 kg 2,691.87 5.81 15,639.76 10,947.83 4,691.93

DO POR LLUVIAS

DO POR LLUVIAS
02.01.05.02 CABEZAL DE SALIDA 45,437.94 0.00 0.00 0.00 0.00 0.00 22,718.97 22,718.97
02.01.05.02.01 CONCRETO FC=175 KG/CM2 m3 56.14 293.52 16,478.21 8,239.11 8,239.11
02.01.05.02.02 ENCOFRADO Y DESENCOFRADO m2 318.04 41.47 13,189.12 6,594.56 6,594.56
02.01.05.02.03 ACERO DE REFUERZO Fy=4200 kg/cm2 kg 2,714.39 5.81 15,770.61 7,885.31 7,885.31
PARALIZADO POR LLUVIAS

PARALIZADO POR LLUVIAS


02.02 BADENES 361,032.87 0.00 9,410.63 0.00 0.00 99,346.52 147,861.50 104,414.23
02.02.01 OBRAS PRELIMINARES 7,875.00 0.00 7,875.00 0.00 0.00 0.00 0.00 0.00
02.02.01.01 TRAZO Y REPLANTEO m2 1,260.00 6.25 7,875.00 7,875.00
02.02.02 MOVIMIENTO DE TIERRAS 31,471.84 0.00 0.00 0.00 0.00 9,441.55 12,588.74 9,441.55
02.02.02.01 EXCAVACION PARA ESTRUCTURAS MATERIA SUELTO (MAQUINARIA) m3 183.53 8.42 1,545.32 463.60 618.13 463.60
02.02.02.02 EXCAVACION PARA ESTRUCTURAS MATERIAL SUELTO (MANUAL) m3 85.05 26.73 2,273.39 682.02 909.36 682.02
02.02.02.03 EXCAVACION EN ROCA SUELTA m3 76.63 32.54 2,493.54 748.06 997.42 748.06
02.02.02.04 EXCAVACION EN ROCA FIJA m3 68.97 50.57 3,487.81 1,046.34 1,395.12 1,046.34
02.02.02.05 RELLENO EN ESTRUCTURAS C/MATERIAL PROPIO m3 73.58 33.88 2,492.89 747.87 997.16 747.87
02.02.02.06 ELIMINACION DE MATERIAL EXCEDENTE m3 486.51 12.51 6,086.24 1,825.87 2,434.50 1,825.87
02.02.02.07 BASE PARA EMBOQUILLADOS C/ MATERIAL GRANULAR m2 1,071.00 11.15 11,941.65 3,582.50 4,776.66 3,582.50
02.02.02.08 LIMPIEZA DE CURSO DE AGUA m2 100.00 11.51 1,151.00 345.30 460.40 345.30
02.02.03 EMBOQUILLADO DE PIEDRA (PLATAFORMA Y BASE ANTISOCAVACION) 212,803.31 0.00 0.00 0.00 0.00 66,436.74 92,333.92 54,032.64
02.02.03.01 ENCOFRADO Y DESENCOFRADO m2 964.60 41.47 40,001.96 12,000.59 16,000.78 12,000.59
02.02.03.02 EMBOQUILLADO DE PIEDRA CON CONCRETO FC=175KG/CM2 +30% DE P.M. m3 433.55 275.27 119,343.31 35,802.99 47,737.32 35,802.99
02.02.03.03 PIEDRA PROPIA DE LA QUEBRADA ASENTADA CON MEZCLA FC=175KG/CM2+70% PG. m3 56.70 366.20 20,763.54 6,229.06 8,305.42 6,229.06
02.02.03.04 JUNTAS ASFALTICAS LONGITUDINAL m 594.50 9.81 5,832.05 5,832.05
02.02.03.05 SARDINEL DE CONCRETO F´C=175 Kg/cm2 m3 30.00 378.27 11,348.10 11,348.10
02.02.03.06 ENCOFRADO Y DESENCOFRADO m2 120.00 41.47 4,976.40 1,866.15 3,110.25
02.02.03.07 ACERO DE REFUERZO Fy=4200 kg/cm2 kg 1,813.76 5.81 10,537.95 10,537.95
02.02.04 MURO DE PIE 108,882.72 0.00 1,535.63 0.00 0.00 23,468.22 42,938.84 40,940.03
02.02.04.01 OBRAS PRELIMINARES 1,535.63 0.00 1,535.63 0.00 0.00 0.00 0.00 0.00
02.02.04.01.01 TRAZO Y REPLANTEO m2 245.70 6.25 1,535.63 1,535.63
02.02.04.02 MOVIMIENTO DE TIERRAS 4,997.01 0.00 0.00 0.00 0.00 2,998.21 1,998.80 0.00

PARALIZADO POR LLUVIAS

PARALIZADO POR LLUVIAS


02.02.04.02.01 EXCAVACION PARA ESTRUCTURAS MATERIA SUELTO (MAQUINARIA) m3 54.60 8.42 459.73 275.84 183.89
02.02.04.02.02 EXCAVACION PARA ESTRUCTURAS MATERIAL SUELTO (MANUAL) m3 23.40 33.41 781.79 469.07 312.72
02.02.04.02.03 EXCAVACION EN ROCA SUELTA m3 24.05 32.54 782.59 469.55 313.04
02.02.04.02.04 EXCAVACION EN ROCA FIJA m3 20.80 50.57 1,051.86 631.12 420.74
02.02.04.02.05 ELIMINACION DE MATERIAL EXCEDENTE m3 153.56 12.51 1,921.04 1,152.62 768.42
02.02.04.03 CONCRETO SIMPLE 102,350.08 0.00 0.00 0.00 0.00 20,470.02 40,940.03 40,940.03
02.02.04.03.01 CONCRETO CICLOPEO FC=175KG/CM2 + 30 % PM. m3 292.95 279.86 81,984.99 16,397.00 32,794.00 32,794.00
02.02.04.03.02 ENCOFRADO Y DESENCOFRADO m2 491.08 41.47 20,365.09 4,073.02 8,146.04 8,146.04
02.03 CUNETAS LONGITUDINALES 154,958.54 0.00 0.00 0.00 24,837.69 48,823.02 41,816.65 39,481.19
02.03.01 TRABAJOS PRELIMINARES 23,354.58 0.00 0.00 0.00 11,677.29 9,341.83 2,335.46 0.00
02.03.01.01 TRAZO Y REPLANTEO CUNETAS KM 17.36 1,345.31 23,354.58 11,677.29 9,341.83 2,335.46
02.03.02 MOVIMIENTO DE TIERRAS 131,603.96 0.00 0.00 0.00 13,160.40 39,481.19 39,481.19 39,481.19
02.03.02.01 CONFORMACION Y PERFILADO DE CUNETAS LONGITUDINALES m 17,362.00 7.58 131,603.96 13,160.40 39,481.19 39,481.19 39,481.19
03 MITIGACIÓN DE IMPACTO AMBIENTAL 23,715.00 0.00 0.00 0.00 0.00 0.00 0.00 23,715.00
03.01 TRATAMIENTO DE CANTERA m2 3,500.00 1.09 3,815.00 3,815.00
03.02 RESTAURACION DE PATIO DE MAQUINAS Y CAMPAMENTO m2 2,000.00 1.45 2,900.00 2,900.00
03.03 ACONDICIONAMIENTO DE BOTADERO m2 12,500.00 1.36 17,000.00 17,000.00
04 FLETE TERRESTRE 159,618.47 47,885.53 63,847.39 0.00 7,980.92 12,769.48 12,769.48 14,365.67
04.01 FLETE TERRESTRE DE ICA - PIE DE OBRA GLB 1.00 102,064.09 102,064.09 30,619.23 40,825.64 5,103.20 8,165.13 8,165.127 9,185.766
04.02 FLETE TERRESTRE DE LIMA - PIE DE OBRA GLB 1.00 57,554.38 57,554.38 17,266.31 23,021.75 2,877.72 4,604.35 4,604.350 5,179.905
05 CAPACITACION EN MANTENIMIENTO RUTINARIO Y PERIODICO AL COMITE VIAL 12,500.00 0.00 0.00 0.00 0.00 0.00 0.00 12,500.00
05.01 CAPACITACION EN MANTENIMIENTO RUTINARIO Y PERIODICO AL COMITE VIAL GLB 1.00 12,500.00 12,500.00 12,500.00
06 MONITOREO ARQUEOLOGICO 37,955.07 0.00 17,719.62 5,781.56 3,856.25 3,856.25 3,271.42 3,469.97
06.01 ELABORACION DEL PLAN DE MONITOREO ARQUEOLOGICO GLB 1.00 9,047.29 9,047.29 9,047.29
6.02 IMPLEMENTACION DEL MONITOREO ARQUEOLOGICO EN OBRA GLB 1.00 28,907.78 28,907.78 8,672.33 5,781.56 3,856.25 3,856.25 3,271.42 3,469.97
07 IMPLEMENTACION DEL PLAN DE VIGILANCIA Y PREVENCION CONTRA EL COVID 19 19,822.08 1,982.22 2,977.79 3,964.42 3,413.80 3,083.43 3,083.43 1,316.99
7.01 IMPLEMENTACION DEL PLAN DE VIGILANCIA Y PREVENCION CONTRA EL COVID 19 GLB 1.00 19,822.08 19,822.08 1,982.22 2,977.79 3,964.42 3,413.80 3,083.43 3,083.43 1,316.99

COSTO DIRECTO 2,950,886.04 117,071.06 356,965.45 225,176.01 362,425.68 647,817.40 705,037.78 536,392.66
GASTOS GENERALES 399,254.88 15,839.71 48,297.42 30,466.31 49,036.19 87,649.69 95,391.61 72,573.93
UTILIDADES 236,070.88 9,365.68 28,557.24 18,014.08 28,994.05 51,825.39 56,403.02 42,911.41
SUB TOTAL 3,586,211.80 142,276.46 433,820.11 273,656.40 440,455.93 787,292.49 856,832.42 651,878.00
I.G.V. (18%) 645,518.12 25,609.762 78,087.62 49,258.15 79,282.07 141,712.65 154,229.84 117,338.04
PRESUPUESTO TOTAL 4,231,729.92 167,886.21 511,907.73 322,914.55 519,738.00 929,005.14 1,011,062.25 769,216.05
AVANCE VALORIZADO
100.00% 3.97% 12.10% 7.63% 12.28% 21.95% 23.89% 18.18%
MENSUAL
PROGRAMADO ACUMULADO
167,886.21 679,793.94 1,002,708.49 1,522,446.48 2,451,451.62 3,462,513.87 4,231,729.92
AVANCE VALORIZADO ACUMULADO
3.97% 16.06% 23.69% 35.97% 57.93% 81.82% 100.00%