Proyecto: CENTRO DE SALUD INTEGRAL TIRAQUE_

Cliente: G.A.M. TIRAQUE


Lugar: TIRAQUE

Nº Descripción Und. Cantidad Unitario Parcial (Bs)


> M01 - OBRAS PRELIMINARES 102,370.64
1 LIMPIEZA DE TERRENO Y DESHIERBE M2 10,170.00 3.84 39,052.80
2 INSTALACIÓN DE FAENAS (OBRAS MAYORES) glb 1.00 21,279.92 21,279.92
3 LETRERO DE OBRAS pza 1.00 4,002.12 4,002.12
4 REPLANTEO Y CONTROL TOPOGRÁFICO M2 10,170.00 3.74 38,035.80
> M02 - OBRA GRUESA 7,872,231.52
5 EXCAVACION SUELO SEMI DURO C/RETROEXCAVADORA M3 306.72 29.56 9,066.64
6 EXCAVACION MANUAL SUELO SEMIDURO M3 552.76 153.55 84,876.30
7 RELLENO Y COMPACTADO C/EQUIPO MANUAL M3 217.45 106.92 23,249.75
8 CARPETA NIVELACION Hº POBRE - E=5 CM. M2 11.95 46.32 553.52
9 HORMIGON ARMADO P/ZAPATAS H21 m³ 73.04 4,443.29 324,537.90
10 HORMIGON ARMADO P/COLUMNA m³ 91.49 5,280.84 483,144.05
11 HORMIGON ARMADO P/VIGA H21 m³ 169.45 5,032.36 852,733.40
12 HORMIGON ARMADO P/LOSA LLENA H-21 M3 8.86 3,665.76 32,478.63
13 HORMIGON ARMADO P/LOSA ENCASETONADA E=30 CM. M2 1,335.49 1,735.80 2,318,143.54
14 HORMIGON ARMADO H21 P/MURO M3 16.95 4,924.35 83,467.73
15 HORMIGON ARMADO P/ESCALERA H21 m³ 6.17 5,713.14 35,250.07
16 CIMIENTOS DE HºCº 60% P.D. H18 M3 193.96 1,040.08 201,733.92
17 SOBRECIMIENTOS DE H°C° 60% P.D. H18 M3 39.12 1,508.91 59,028.56
18 IMPERMEABILIZACION DE SOBRECIMIENTOS m² 122.87 93.07 11,435.51
19 MURO DE LADRILLO 6H E=12 CM. M2 4,905.54 222.43 1,091,139.26
20 CUBIERTA DE CALAMINA PLASTICA INC/EST m² 440.07 680.30 299,379.62
21 CUBIERTA DE CALAMINA Nº28 INC/EST m² 1,080.36 704.50 761,113.62
22 CUBIERTA DE CALAMINA TIPO TEJA Nº28 INC/EST m² 1,637.62 733.32 1,200,899.50
> M03 - OBRA FINA 9,898,121.61
23 REVOQUE INTERIOR DE YESO m² 8,312.79 214.89 1,786,335.44
24 REVOQUE EXTERIOR m² 2,978.41 399.16 1,188,862.14
25 CIELO RASO BAJO LOSA m² 1,004.15 446.92 448,774.72
26 CIELO FALSO C/PLACAS + EST. DE ALUMINIO m² 233.18 266.39 62,116.82
27 SOLADURA DE PIEDRA m² 6,672.64 97.06 647,646.44
28 CONTRAPISO DE CEMENTO SIN PIEDRA m² 5,390.90 94.57 509,817.41
29 CONTRAPISO DE CONTRAPISO DE CEMENTO S/LOSA m² 1,394.19 133.86 186,626.27
30 ACERA DE CEMENTO T-B + EMPEDRADO E=7.5CM M2 910.00 276.82 251,906.20
31 PISO DE MOSAICO GRANITICO M2 2,618.00 384.48 1,006,568.64
32 PISO DE CERAMICA ESMALTADA M2 3,204.09 321.63 1,030,531.47
33 REVESTIMIENTO DE CERAMICA ESMALTADA m² 1,161.36 301.09 349,673.88
34 PISO CEMENTO FROTACHADO m² 1,289.00 172.80 222,739.20
35 BARANDA DE FG 2" (PROV. Y COLOCADO) ML 115.76 486.69 56,339.23
36 ESTRUCTURA METALICA EN FACHADA E=20 CM. ML 323.49 362.32 117,206.90
37 PUERTA TIPO REJA C/PLANCHA METALICA M2 56.50 808.59 45,685.33
38 CANALETA DE CALAMINA GALV. Nº26 ML 561.78 205.59 115,496.35
39 PINTURA LATEX EXTERIOR M2 2,978.41 64.22 191,273.49
40 PINTURA LATEX INTERIOR m² 8,312.79 53.91 448,142.51
41 PINTURA AL OLEO S/CARPINTERIA METALICA M2 865.23 86.95 75,231.75
42 VENTANA DE ALUMINIO + VIDRIO 4 MM. M2 505.33 1,007.83 509,286.73
43 PUERTA DE MELAMINICO P/BAÑOS m² 176.00 668.26 117,613.76
44 PUERTA DE MADERA ROBLE T/TABLERO + QUINC m² 207.90 1,331.54 276,827.17
45 PUERTA DOBLE DE MADERA ROBLE T/TABLERO + QUINC m² 178.53 1,419.48 253,419.76
> M04 - INST. SANITARIA 435,076.33
46 LAVAMANOS C/PEDESTAL+GRIF - PROV. Y COL. PZA 90.00 969.84 87,285.60
47 INODORO TANQUE BAJO - PROV. Y COLOC. PZA 70.00 1,049.73 73,481.10
48 TINA HIDROMASAJE - PROV. Y COLOC. PZA 12.00 2,269.56 27,234.72
49 DUCHA + BASE DE DUCHA - PROV. Y COLOC. PZA 11.00 1,309.05 14,399.55
50 LAVAPLATOS 2 DEPOSITOS - 1 FREGADERO PZA 21.00 898.66 18,871.86
51 URINARIO DE PARED C/TEMPORIZADOR PZA 6.00 1,032.33 6,193.98
52 TENDIDO TUBERIA PVC D=4" DESAGÜE ML 343.39 86.58 29,730.71
53 TENDIDO TUBERIA PVC D=2" DESAGÜE ML 311.70 61.76 19,250.59
54 TENDIDO TUBERIA PVC D=6" DESAGÜE ML 217.79 140.92 30,690.97
55 CAJA SIFONADA PVC 100X100X50 + REJILLA PZA 50.00 125.77 6,288.50
56 CAMARA DE INSPECCION HºCº 60% P.D H21 H=2.0 M+TAPA PZA 41.00 2,900.24 118,909.84
57 CAMARA CORTA ESPUMA PZA 1.00 690.01 690.01
58 CAMARA DESGRASADORA - 60X60 CM. PZA 2.00 1,024.45 2,048.90
> M05 - INST. AGUA POTABLE 125,814.79
59 TENDIDO TUBERIA PVC D=1 1/2" A.P. ML 13.45 106.86 1,437.27
60 TENDIDO TUBERIA PVC D=1" A.P. ML 235.32 70.91 16,686.54
61 TENDIDO TUBERIA PVC D=3/4" A.P. ML 74.13 56.11 4,159.43
62 TENDIDO TUBERIA PVC D=1/2" A.P. ML 524.79 54.02 28,349.16
63 LLAVE DE PASO 1 1/2" - PROV. Y COLOC. PZA 4.00 299.27 1,197.08
64 LLAVE DE PASO 1" - PROV. Y COLOC. PZA 6.00 213.20 1,279.20
65 LLAVE DE PASO 3/4" - PROV. Y COLOC. PZA 12.00 141.48 1,697.76
66 LLAVE DE PASO 1/2" - PROV. Y COLOC. PZA 50.00 102.81 5,140.50
67 PROV. INSTALACION EQUIPO DE FILTRO DE AGUA 1" pza 2.00 1,517.49 3,034.98
68 EQUIPO AUTOMATICO DE CLORACION glb 1.00 20,704.91 20,704.91
69 TANQUE PLASTICO DE AGUA 5000 LT. C/ACC. PZA 2.00 9,343.06 18,686.12
70 BOMBA CENTRIFUGA P=3.0 HP C/ACC (PROV E INST) pza 2.00 11,720.92 23,441.84
> M06 - INST. ELECTRICA 1,090,529.41
71 TENDIDO DE DUCTO PVC 1" ML 790.00 12.25 9,677.50
72 TENDIDO DE DUCTO PVC 3/4" ML 4,167.00 9.47 39,461.49
73 TENDIDO DE DUCTO PVC 5/8" ML 5,316.00 8.22 43,697.52
74 TENDIDO CONDUCTOR DE CU AISLADO 14 AWG ML 10,746.00 7.41 79,627.86
75 TENDIDO CONDUCTOR DE CU AISLADO 12 AWG ML 8,334.00 12.81 106,758.54
76 TENDIDO CONDUCTOR DE CU AISLADO 10 AWG ML 503.12 15.72 7,909.05
77 LUMINARIA LED 1X7W pto 114.00 325.81 37,142.34
78 LUMINARIA FLUORESCENTE 2X40 W DE ADOSAR pza 394.00 909.78 358,453.32
79 LUMINARIA FLUORESCENTE 3X40 W DE ADOSAR pza 185.00 1,046.99 193,693.15
80 PROV. E INST. DE TOMA CORRIENTE DOBLE pto 398.00 458.63 182,534.74
81 PROV. E INST. DE TOMA CORRIENTE TIPO SCHUKO pto 33.00 481.33 15,883.89
82 PROV. E INST. PUNTO DE FUERZA P/DUCHA PTO 23.00 468.87 10,784.01
83 TABLERO TERMICOS (12 LINEAS) TDE A-0200 PTO 3.00 925.54 2,776.62
84 TABLERO DE BARRAS PRINCIPAL NORMAL PTO 1.00 2,129.38 2,129.38
> M07 - SIST. COMUNICACION ENF 8,799.69
85 PROV. E INST. PULSADOR pza 26.00 63.81 1,659.06
86 PTO. LUZ LLAMADA ENFERMERA pza 10.00 428.50 4,285.00
87 PTO. DE ANULACION DE LLAMADA pza 10.00 63.81 638.10
88 PROV. E INST. CENTRAL DE LLAMADAS ENFERMERIA pza 1.00 2,217.53 2,217.53
> M08 - ACOMETIDA ELECTRICA 208,904.64
89 TENDIDO CABLE COBRE AISLADO AWG N° 8 7 HILOS RST ML 1,500.00 21.33 31,995.00
90 TENDIDO ALAMBRE DE COBRE AISLADO AWG N° 12 ATERRAM ML 400.00 13.84 5,536.00
91 ALAMBRE DE COBRE AISLADO AWG N° 10 RED SECUNDARIA ML 500.00 15.72 7,860.00
92 PROV/INST. TRANSFORMADOR TRIFASICO 24.9/14.4 KV+ pza 1.00 47,575.95 47,575.95
93 GRUPO ELECTROGENO DE 50KW glb 1.00 115,313.00 115,313.00
94 REFLECTOR HALOGENO METALICO 400W/220V pza 1.00 624.69 624.69
> M09 - SIST. GAS MEDICINAL 80,329.47
95 PROV. INST TUBERIA DE COBRE D=1/2" OXIGENO m 281.00 85.94 24,149.14
96 PROV. INST TUBERIA DE COBRE D=3/4" PARA VACIO m 281.00 113.99 32,031.19
97 PROV. INST TUBERIA DE COBRE D=1/2" AIRE m 281.00 85.94 24,149.14
> M10 - OBRAS FINALES 20,542.16
98 PLACA DE ENTREGA DE OBRAS pza 1.00 1,234.16 1,234.16
99 LIMPIEZA Y RETIRO DE ESCOMBROS M3 200.00 96.54 19,308.00
Total presupuesto: 19,842,720.26
Son: Diecinueve Millon(es) Ochocientos Cuarenta y Dos Mil Setecientos Veinte con 26/100 Bolivianos