CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECTO: MEJORAMIENTO DE CANALES DE RIEGO A TRAVES DE ALCANTARILLAS, PUENTES Y COMPUERTAS EN LOS SECTORES DE MARIATEGUI, CAMACHO Y
CAUCATO DEL DISTRITO DE SAN CLEMENTE - PROVINCIA DE PISCO - DEPARTAMENTO DE ICA

Cliente MUNICIPALIDAD DISTRITAL DE SAN CLEMENTE


Lugar ICA - PISCO - SAN CLEMENTE AGOSTO DEL 2021

PRESUPUESTO MES 01 MES 02 MES 03 MES 04


DESCRIPCION UND. PRECIO (S/.)
CANT. PRESUP. (S/.) CANT. PARCIAL CANT. PARCIAL CANT. PARCIAL CANT. PARCIAL
OPERARIO hh S/ 23.41 1,223.65 S/ 28,645.69 96.82 S/ 2,266.47 246.08 S/ 5,760.62 286.82 S/ 6,714.42 593.94 S/ 13,904.18
OFICIAL hh S/ 18.50 2,447.35 S/ 45,276.00 218.60 S/ 4,044.07 529.86 S/ 9,802.47 609.94 S/ 11,283.83 1,088.95 S/ 20,145.62
PEON hh S/ 16.73 3,059.71 S/ 51,188.95 367.43 S/ 6,147.09 674.46 S/ 11,283.63 808.98 S/ 13,534.18 1,208.85 S/ 20,224.05
OPERARIO TOPOGRAFO hh S/ 23.41 42.39 S/ 992.40 10.60 S/ 248.10 10.60 S/ 248.10 17.66 S/ 413.50 3.53 S/ 82.70
GUARDIAN DE NOCHE glb S/ 393.36 16.00 S/ 6,293.76 2.91 S/ 1,144.32 5.09 S/ 2,002.56 6.55 S/ 2,574.72 1.45 S/ 572.16
CONTENEDOR PARA DESECHOS 200 LT und S/ 165.25 2.00 S/ 330.50 0.48 S/ 79.32 0.52 S/ 85.93 0.52 S/ 85.93 0.48 S/ 79.32
ALAMBRE NEGRO RECOCIDO N° 8 kg S/ 4.70 98.25 S/ 461.80 6.84 S/ 32.12 14.52 S/ 68.27 21.36 S/ 100.39 55.54 S/ 261.02
ALAMBRE NEGRO N° 16 kg S/ 4.70 379.42 S/ 1,783.26 34.49 S/ 162.11 60.36 S/ 283.70 68.99 S/ 324.23 215.58 S/ 1,013.22
ACERO CORRUGADO fy = 4200 kg/cm2 GRADO 60 kg S/ 4.65 7,891.89 S/ 36,697.31 717.44 S/ 3,336.12 1,255.53 S/ 5,838.21 1,434.89 S/ 6,672.24 4,484.03 S/ 20,850.74
CLAVOS PARA MADERA CON CABEZA DE 2" kg S/ 5.10 149.61 S/ 763.00 10.88 S/ 55.49 23.12 S/ 117.92 27.20 S/ 138.73 88.40 S/ 450.86
CLAVOS PARA MADERA CON CABEZA DE 3" kg S/ 5.10 163.71 S/ 834.91 11.39 S/ 58.08 24.20 S/ 123.42 35.59 S/ 181.50 92.53 S/ 471.91
CLAVOS PARA MADERA CON CABEZA DE 4" kg S/ 5.10 9.40 S/ 47.94 0.00 S/ - 0.00 S/ - 9.40 S/ 47.94 0.00 S/ -
PIEDRA CHANCADA 1/2" m3 S/ 45.00 100.86 S/ 4,538.70 4.58 S/ 206.30 18.34 S/ 825.22 18.34 S/ 825.22 59.60 S/ 2,681.96
PIEDRA CHANCADA 3/4" m3 S/ 45.00 49.30 S/ 2,218.39 4.11 S/ 184.87 16.43 S/ 739.46 17.79 S/ 800.47 10.97 S/ 493.59
PIEDRA GRANDE DE 8" m3 S/ 40.00 65.28 S/ 2,611.15 7.07 S/ 282.87 20.13 S/ 805.11 22.66 S/ 906.29 15.42 S/ 616.88
ARENA GRUESA m3 S/ 30.00 124.51 S/ 3,735.22 7.32 S/ 219.72 29.30 S/ 878.88 30.50 S/ 915.13 57.38 S/ 1,721.50
HORMIGON m3 S/ 25.00 18.65 S/ 466.13 2.49 S/ 62.15 5.28 S/ 132.07 6.22 S/ 155.38 4.66 S/ 116.53
AGUA PUESTA EN OBRA m3 S/ 9.60 103.92 S/ 997.65 10.03 S/ 96.32 27.59 S/ 264.89 29.87 S/ 286.74 36.43 S/ 349.69
CEMENTO PORTLAND TIPO I (42.5 kg) bol S/ 17.80 2,034.68 S/ 36,217.34 159.24 S/ 2,834.40 504.25 S/ 8,975.60 545.38 S/ 9,707.82 825.82 S/ 14,699.51
TIZA BOLSA DE 40 kg und S/ 59.32 10.60 S/ 628.67 2.65 S/ 157.17 2.65 S/ 157.17 4.42 S/ 261.95 0.88 S/ 52.39
OCRE ROJO kg S/ 7.70 5.30 S/ 40.80 1.32 S/ 10.20 1.32 S/ 10.20 2.21 S/ 17.00 0.44 S/ 3.40
BANDEJA DESINFECTANTE PARA CALZADO und S/ 250.00 5.00 S/ 1,250.00 1.23 S/ 306.25 1.30 S/ 325.00 1.30 S/ 325.00 1.18 S/ 293.75
ROLLIZO DE EUCALIPTO 3"X2.80 M. pza S/ 10.00 982.05 S/ 9,820.50 68.32 S/ 683.17 145.17 S/ 1,451.73 213.49 S/ 2,134.89 555.07 S/ 5,550.72
MADERA TORNILLO p2 S/ 5.08 2,765.34 S/ 14,047.95 192.37 S/ 977.25 408.79 S/ 2,076.65 601.16 S/ 3,053.90 1,563.02 S/ 7,940.14
DISPENSADOR DE JABON LIQUIDO und S/ 80.00 48.00 S/ 3,840.00 11.52 S/ 921.60 12.48 S/ 998.40 12.48 S/ 998.40 11.52 S/ 921.60
DISPENSADOR DE PAPEL TOALLA INTERFOLIADO und S/ 40.00 4.00 S/ 160.00 0.96 S/ 38.40 1.04 S/ 41.60 1.04 S/ 41.60 0.96 S/ 38.40
TERMOMETRO LASER und S/ 109.00 5.00 S/ 545.00 1.23 S/ 133.53 1.30 S/ 141.70 1.30 S/ 141.70 1.18 S/ 128.08
MASCARILLA TIPO N95 und S/ 2.00 160.00 S/ 320.00 38.40 S/ 76.80 41.60 S/ 83.20 41.60 S/ 83.20 38.40 S/ 76.80
GUANTES QUIRURGICO und S/ 1.50 160.00 S/ 240.00 38.40 S/ 57.60 41.60 S/ 62.40 41.60 S/ 62.40 38.40 S/ 57.60
ELABORACION Y SEGUIMIENTO DE IMPLEMENTACION DEL PLAN S/ 2,000.00 4.00 S/ 8,000.00 0.96 S/ 1,920.00 1.04 S/ 2,080.00 1.04 S/ 2,080.00 0.96 S/ 1,920.00
mes
COVID 19 EN OBRA
GORRO QUIRURGICO und S/ 0.30 160.00 S/ 48.00 38.40 S/ 11.52 41.60 S/ 12.48 41.60 S/ 12.48 38.40 S/ 11.52
SEÑALIZACION PREVENTIVAS und S/ 15.17 12.00 S/ 182.04 2.88 S/ 43.69 3.12 S/ 47.33 3.12 S/ 47.33 2.88 S/ 43.69
SEÑALIZACION INFORMATIVA und S/ 15.17 12.00 S/ 182.04 2.88 S/ 43.69 3.12 S/ 47.33 3.12 S/ 47.33 2.88 S/ 43.69
SEÑALIZACION PROHIBICION und S/ 15.17 4.00 S/ 60.68 0.96 S/ 14.56 1.04 S/ 15.78 1.04 S/ 15.78 0.96 S/ 14.56
CRONOGRAMA DE ADQUISICION DE MATERIALES
PROYECTO: MEJORAMIENTO DE CANALES DE RIEGO A TRAVES DE ALCANTARILLAS, PUENTES Y COMPUERTAS EN LOS SECTORES DE MARIATEGUI, CAMACHO Y
CAUCATO DEL DISTRITO DE SAN CLEMENTE - PROVINCIA DE PISCO - DEPARTAMENTO DE ICA

Cliente MUNICIPALIDAD DISTRITAL DE SAN CLEMENTE


Lugar ICA - PISCO - SAN CLEMENTE AGOSTO DEL 2021

PRESUPUESTO MES 01 MES 02 MES 03 MES 04


DESCRIPCION UND. PRECIO (S/.)
CANT. PRESUP. (S/.) CANT. PARCIAL CANT. PARCIAL CANT. PARCIAL CANT. PARCIAL
CABINA DE DESINFECCION (1200X1500X2300) und S/ 1,200.00 4.00 S/ 4,800.00 0.96 S/ 1,152.00 1.04 S/ 1,248.00 1.04 S/ 1,248.00 0.96 S/ 1,152.00
SEÑALES DE OBLIGACION OBLIGATORIEDAD und S/ 15.17 12.00 S/ 182.04 2.88 S/ 43.69 3.12 S/ 47.33 3.12 S/ 47.33 2.88 S/ 43.69
ALCOHOL EN GEL 1 LT und S/ 17.00 4.00 S/ 68.00 0.96 S/ 16.32 1.04 S/ 17.68 1.04 S/ 17.68 0.96 S/ 16.32
ALCOHOL 96 GRADOS 1L und S/ 10.00 40.00 S/ 400.00 9.60 S/ 96.00 10.40 S/ 104.00 10.40 S/ 104.00 9.60 S/ 96.00
MOTOPULVERIZADOR 25 L und S/ 936.00 1.00 S/ 936.00 0.24 S/ 224.64 0.26 S/ 243.36 0.26 S/ 243.36 0.24 S/ 224.64
BOLSAS PARA DESECHO 200 LT und S/ 0.10 32.00 S/ 3.20 7.68 S/ 0.77 8.32 S/ 0.83 8.32 S/ 0.83 7.68 S/ 0.77
PAPEL HIGIENICO X48 UND und S/ 40.00 9.00 S/ 360.00 2.21 S/ 88.20 2.34 S/ 93.60 2.34 S/ 93.60 2.12 S/ 84.60
LAVAMANOS DE OBRA und S/ 1,200.00 8.00 S/ 9,600.00 1.92 S/ 2,304.00 2.08 S/ 2,496.00 2.08 S/ 2,496.00 1.92 S/ 2,304.00
PAPEL TOALLA INTERFOLIADO CAJA X 18 und S/ 175.82 20.00 S/ 3,516.40 4.80 S/ 843.94 5.20 S/ 914.26 5.20 S/ 914.26 4.80 S/ 843.94
DESINFECTANTES PARA SUPERFICIES und S/ 105.83 2.00 S/ 211.66 0.48 S/ 50.80 0.52 S/ 55.03 0.52 S/ 55.03 0.48 S/ 50.80
NIVEL he S/ 15.00 84.78 S/ 1,271.76 21.20 S/ 317.94 21.20 S/ 317.94 35.33 S/ 529.90 7.07 S/ 105.98
HERRAMIENTAS MANUALES %mo S/ 2,909.34 0.25 S/ 727.34 0.25 S/ 727.34 0.25 S/ 727.34 0.25 S/ 727.34
COMPACTADORA DE PLANCHA día S/ 80.00 75.07 S/ 6,005.34 12.51 S/ 1,000.89 25.02 S/ 2,001.78 27.09 S/ 2,166.93 10.45 S/ 835.74
RETROEXCAVADORA hm S/ 130.00 256.37 S/ 33,328.26 56.94 S/ 7,401.65 76.59 S/ 9,956.82 90.80 S/ 11,803.76 32.05 S/ 4,166.03
CAMION VOLQUETE hm S/ 120.00 40.00 S/ 4,800.00 8.00 S/ 960.00 10.00 S/ 1,200.00 18.00 S/ 2,160.00 4.00 S/ 480.00
MEZCLADORA DE CONCRETO 11 P3 (23 HP) día S/ 100.00 73.45 S/ 7,344.82 5.75 S/ 574.81 18.20 S/ 1,820.24 19.69 S/ 1,968.73 29.81 S/ 2,981.04
MOCHILA FUMIGADORA PISTON DE BRONCE 20 LT und S/ 13.47 35.20 S/ 474.14 8.45 S/ 113.79 9.15 S/ 123.28 9.15 S/ 123.28 8.45 S/ 113.79
WINCHA 5O MTS und S/ 40.68 1.06 S/ 43.11 0.26 S/ 10.78 0.26 S/ 10.78 0.44 S/ 17.96 0.09 S/ 3.59
WINCHA METALICA 5 MTS und S/ 8.48 1.06 S/ 8.99 0.26 S/ 2.25 0.26 S/ 2.25 0.44 S/ 3.74 0.09 S/ 0.75
CORDEL rll S/ 11.02 0.79 S/ 8.76 0.20 S/ 2.19 0.20 S/ 2.19 0.33 S/ 3.65 0.07 S/ 0.73
FLETE TERRESTRE glb S/ 500.00 9.00 S/ 4,500.00 9.00 S/ 4,500.00 0.00 S/ - 0.00 S/ - 0.00 S/ -
FLETE TERRESTRE OBRA glb S/ 3,000.00 1.00 S/ 3,000.00 0.00 S/ - 1.00 S/ 3,000.00 0.00 S/ - 0.00 S/ -
CARTEL DE OBRA INCLUIDO SUMINISTRO E INSTALACION glb S/ 850.00 1.00 S/ 850.00 0.00 S/ - 1.00 S/ 850.00 0.00 S/ - 0.00 S/ -
SC SUMINSITRO E INSTALACION COMPUERTA A= 1.20 M glb S/ 3,728.81 1.00 S/ 3,728.81 0.00 S/ - 0.00 S/ - 0.00 S/ - 1.00 S/ 3,728.81
SC SUMINSITRO E INSTALACION COMPUERTA A= 1.00 M glb S/ 3,291.53 1.00 S/ 3,291.53 0.00 S/ - 0.00 S/ - 0.00 S/ - 1.00 S/ 3,291.53
SC SUMINSITRO E INSTALACION COMPUERTA A= 0.98 M glb S/ 3,490.68 1.00 S/ 3,490.68 0.00 S/ - 0.00 S/ - 0.00 S/ - 1.00 S/ 3,490.68
SC SUMINSITRO E INSTALACION COMPUERTA A= 0.90 M glb S/ 3,371.19 1.00 S/ 3,371.19 0.00 S/ - 0.00 S/ - 0.00 S/ - 1.00 S/ 3,371.19
SC SUMINSITRO E INSTALACION COMPUERTA A= 0.82 M glb S/ 3,112.71 1.00 S/ 3,112.71 0.00 S/ - 0.00 S/ - 0.00 S/ - 1.00 S/ 3,112.71
SC SUMINSITRO E INSTALACION COMPUERTA A= 0.50 M glb S/ 2,894.07 1.00 S/ 2,894.07 0.00 S/ - 0.00 S/ - 0.00 S/ - 1.00 S/ 2,894.07
CRONOGRAMA DE ADQUISICION DE MATERIALES
PROYECTO: MEJORAMIENTO DE CANALES DE RIEGO A TRAVES DE ALCANTARILLAS, PUENTES Y COMPUERTAS EN LOS SECTORES DE MARIATEGUI, CAMACHO Y
CAUCATO DEL DISTRITO DE SAN CLEMENTE - PROVINCIA DE PISCO - DEPARTAMENTO DE ICA

Cliente MUNICIPALIDAD DISTRITAL DE SAN CLEMENTE


Lugar ICA - PISCO - SAN CLEMENTE AGOSTO DEL 2021

PRESUPUESTO MES 01 MES 02 MES 03 MES 04


DESCRIPCION UND. PRECIO (S/.)
CANT. PRESUP. (S/.) CANT. PARCIAL CANT. PARCIAL CANT. PARCIAL CANT. PARCIAL
SC SUMINSITRO E INSTALACION COMPUERTA A= 1.90 M glb S/ 4,186.44 1.00 S/ 4,186.44 0.00 S/ - 0.00 S/ - 0.00 S/ - 1.00 S/ 4,186.44
SC SUMINSITRO E INSTALACION COMPUERTA A= 0.85 M glb S/ 3,311.02 1.00 S/ 3,311.02 0.00 S/ - 0.00 S/ - 0.00 S/ - 1.00 S/ 3,311.02

glb
SC SUMINISTRO E INSTALACION COMPUERTA SEGUN DISEÑO A= 1.00 S/ 3,291.53 8.00 S/ 26,332.24 0.00 S/ - 0.00 S/ - 0.00 S/ - 8.00 S/ 26,332.24

glb
SC SUMINISTRO E INSTALACION COMPUERTA SEGUN DISEÑO A= 0.80 S/ 3,092.37 6.00 S/ 18,554.22 0.00 S/ - 0.00 S/ - 0.00 S/ - 6.00 S/ 18,554.22
SC ENSAYO DE CONCRETO und S/ 25.00 50.00 S/ 1,250.00 5.00 S/ 125.00 15.00 S/ 375.00 15.00 S/ 375.00 15.00 S/ 375.00
TOTAL PRESUPUESTO (COSTO DIRECTO) S/ 421,610.51 MES 01 MES 02 MES 03 MES 04
0.00
COSTO DIRECTO 0.00 S/ 47,412.35 S/ 81,394.72 S/ 90,092.00 S/ 202,711.45
GASTOS GENERALES (8%) 0.00 S/ 3,792.99 S/ 6,511.58 S/ 7,207.36 S/ 16,216.92
UTILIDAD (7%) 0.00 S/ 3,318.86 S/ 5,697.63 S/ 6,306.44 S/ 14,189.80
SUB TOTAL 0.00 S/ 54,524.20 S/ 93,603.93 S/ 103,605.80 S/ 233,118.16
IGV (18%) 0.00 S/ 9,814.36 S/ 16,848.71 S/ 18,649.04 S/ 41,961.27
PRESUPUESTO PARCIAL S/ 64,338.56 S/ 110,452.63 S/ 122,254.84 S/ 275,079.44
TOTAL PRESUPUESTO (SOLES) S/572,125.47
QUINIENTOS SETENTA Y DOS MIL CIENTO VEINTICINCO CON 46/100 SOLES