ITEM Descripción N° de veces Parcial
Largo Ancho Alto
01 TRABAJOS PRELIMINARES
01.01 LIMPIEZA DE TERRENO MANUAL
AREA DE CONSTRUCCION 1.00 20.00 10.00 200.00
01.02 TRAZO Y REPLANTEO
AREA DE CONSTRUCCION 1.00 20.00 10.00 200.00
02 MOVIMIENTO DE TIERRAS
02.01 EXCAVACION DE ZANJAS PARA ZAPATAS
ZAPATA 1 3.00 1.85 1.85 1.60 16.43
ZAPATA 2 3.00 2.70 2.00 1.60 25.92
ZAPATA 3 1.00 3.00 3.00 1.60 14.40
ZAPATA 4 2.00 1.60 1.20 1.60 6.14
ZAPATA 5 7.00 1.20 1.20 1.60 16.13
ZAPATA 6 5.00 1.00 1.00 1.60 8.00
ZAPATA 7 1.00 1.20 1.00 1.60 1.92
ZAPATA 8 1.00 1.50 1.30 1.60 3.12
ZAPATA 9 3.00 1.30 1.30 1.60 8.11
ZAPATA 10 3.00 1.25 0.95 1.60 5.70
02.02 EXCAVACION DE ZANJAS PARA CIMENTACION
SCA-2 (EJE A) 1.00 7.10 0.50 1.10 3.91
CC-2 (EJE A) 1.00 1.05 0.50 1.20 0.63
SCA-1(ENTRE EJE A Y B) 1.00 1.60 0.50 1.10 0.88
CC-1 (ENTRE EJE A Y B) 1.00 1.55 0.50 1.10 0.85
CC-1 (EJE B) 1.00 1.40 0.50 1.10 0.77
CC-1 (EJE C) 1.00 1.30 0.50 1.10 0.72
SCA-1 (EJE C) 1.00 1.40 0.50 1.10 0.77
SARDINEL S-1 (EJE C) 1.00 6.35 0.31 0.30 0.60
CC-2 (EJE C) 1.00 1.40 0.50 1.20 0.84
CC-1 (EJE D) 1.00 1.20 0.50 1.10 0.66
SARDINEL S-1 (EJE D) 1.00 1.20 0.31 0.30 0.11
CC-2 (EJE D) 1.00 0.85 0.50 1.20 0.51
SCA-2 (EJE E) 1.00 5.70 0.50 1.10 3.14
CC-2 (EJE E) 1.00 1.05 0.50 1.20 0.63
SCA-2 (EJE 1) 1.00 4.70 0.50 1.10 2.59
SCA-1 (EJE 2) 1.00 4.50 0.50 1.10 2.48
SCA-1 (EJE 3) 1.00 1.50 0.50 1.10 0.83
SCA-1 (EJE 4) 1.00 3.15 0.50 1.10 1.73
SCA-1 (ENTRE EJE 4 Y 5) 1.00 1.45 0.50 1.10 0.80
SCA-1 (EJE 5) 1.00 5.00 0.50 1.10 2.75
SCA-1 (EJE 6) 1.00 2.25 0.50 1.10 1.24
VC-1 (EJE 6) 1.00 2.90 0.30 1.50 1.31
VC-1 (EJE 7) 1.00 3.00 0.30 1.50 1.35
VC-1 (EJE 9) 1.00 3.60 0.30 1.50 1.62
02.03 RELLENO COMPACTADO CON MATERIAL PROPIO
ZAPATA 1 1.00 VOLUM= 16.43 16.43
QUITAR COLUMNA C-1 -3.00 0.45 0.45 0.90 -0.66
ZAPATA 2 1.00 VOLUM= 25.92 25.92
QUITAR COLUMNA C-1 -3.00 0.45 0.45 0.90 -0.66
RESUMEN DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
ZAPATA 3 1.00 VOLUM= 14.40 14.40
QUITAR COLUMNA C-1 -1.00 0.45 0.45 1.00 -0.32
ZAPATA 4 1.00 VOLUM= 6.14 6.14
QUITAR COLUMNA C-1 -2.00 0.45 0.45 1.10 -0.56
ZAPATA 5 1.00 VOLUM= 16.13 16.13
QUITAR COLUMNA C-3 -7.00 AREA= 0.12 1.10 -1.04
ZAPATA 6 1.00 VOLUM= 8.00 8.00
QUITAR COLUMNA C-3 -2.00 AREA= 0.12 1.10 -0.38
QUITAR COLUMNA C-5 -3.00 0.30 0.15 1.10 -0.26
ZAPATA 7 1.00 VOLUM= 1.92 1.92
QUITAR COLUMNA C-6 -1.00 0.40 0.25 1.10 -0.22
ZAPATA 8 1.00 VOLUM= 3.12 3.12
QUITAR COLUMNA C-7 -1.00 0.475 0.25 1.10 -0.24
ZAPATA 9 1.00 VOLUM= 8.11 8.11
QUITAR COLUMNA C-3 -2.00 AREA= 0.12 1.10 -0.38
QUITAR COLUMNA C-10 -1.00 AREA= 0.08 1.10 -0.20
ZAPATA 10 1.00 VOLUM= 5.70 5.70
QUITAR COLUMNA C-4 -1.00 0.625 0.15 1.10 -0.22
QUITAR COLUMNA C-8 -1.00 0.70 0.25 1.10 -0.31
QUITAR COLUMNA C-9 -1.00 0.45 0.15 1.10 -0.19
SCA-2 (EJE A) 1.00 7.10 0.25 0.25 0.44
CC-2 (EJE A) 1.00 1.05 0.35 0.30 0.11
SCA-1(ENTRE EJE A Y B) 1.00 1.60 0.25 0.25 0.10
CC-1 (ENTRE EJE A Y B) 1.00 1.55 0.35 0.20 0.11
CC-1 (EJE B) 1.00 1.40 0.35 0.20 0.10
CC-1 (EJE C) 1.00 1.30 0.35 0.20 0.09
SCA-1 (EJE C) 1.00 1.40 0.25 0.25 0.09
CC-2 (EJE C) 1.00 1.40 0.35 0.30 0.15
CC-1 (EJE D) 1.00 1.20 0.35 0.20 0.08
CC-2 (EJE D) 1.00 0.85 0.35 0.30 0.09
SCA-2 (EJE E) 1.00 5.70 0.25 0.25 0.36
CC-2 (EJE E) 1.00 1.05 0.35 0.30 0.11
SCA-2 (EJE 1) 1.00 4.70 0.25 0.25 0.29
SCA-1 (EJE 2) 1.00 4.50 0.25 0.25 0.28
SCA-1 (EJE 3) 1.00 1.50 0.25 0.25 0.09
SCA-1 (EJE 4) 1.00 3.15 0.25 0.25 0.20
SCA-1 (ENTRE EJE 4 Y 5) 1.00 1.45 0.25 0.25 0.09
SCA-1 (EJE 5) 1.00 5.00 0.25 0.25 0.31
SCA-1 (EJE 6) 1.00 2.25 0.25 0.25 0.14
SCA-1 (EJE 5) 1.00 2.25 0.25 0.25 0.14
VC-1 (EJE 6) 1.00 2.90 0.30 0.80 0.70
VC-1 (EJE 7) 1.00 3.00 0.30 0.80 0.72
VC-1 (EJE 9) 1.00 3.60 0.30 0.80 0.86
02.04 NIVELACION INTERIOR APISONADO MANUAL
PRIMER PISO 1.00 AREA= 178.80 178.80
02.05 ELIMINACION DE MATERIAL EXCEDENTE
EXCAVACION - RELLENO FACTOR= 1.25 VOLUMEN= 31.65 39.56
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
03.01 SOLADO DE CONCRETO MEZCLA 1:10
ZAPATA 1 3.00 1.85 1.85 10.27
ZAPATA 2 3.00 2.70 2.00 16.20
ZAPATA 3 1.00 3.00 3.00 9.00
ZAPATA 4 2.00 1.60 1.20 3.84
ZAPATA 5 7.00 1.20 1.20 10.08
ZAPATA 6 5.00 1.00 1.00 5.00
ZAPATA 7 1.00 1.20 1.00 1.20
ZAPATA 8 1.00 1.50 1.30 1.95
ZAPATA 9 3.00 1.30 1.30 5.07
ZAPATA 10 3.00 1.25 0.95 3.56
03.02 CIMIENTOS CORRIDOS 1:10 CEMENTO-HORMIGON+30% P.G.
SCA-2 (EJE A) 1.00 7.10 0.50 0.90 3.20
CC-2 (EJE A) 1.00 1.05 0.50 0.90 0.47
SCA-1(ENTRE EJE A Y B) 1.00 1.60 0.50 0.90 0.72
CC-1 (ENTRE EJE A Y B) 1.00 1.55 0.50 0.90 0.70
CC-1 (EJE B) 1.00 1.40 0.50 0.90 0.63
CC-1 (EJE C) 1.00 1.30 0.50 0.90 0.59
SCA-1 (EJE C) 1.00 1.40 0.50 0.90 0.63
CC-2 (EJE C) 1.00 1.40 0.50 0.90 0.63
CC-1 (EJE D) 1.00 1.20 0.50 0.90 0.54
CC-2 (EJE D) 1.00 0.85 0.50 0.90 0.38
SCA-2 (EJE E) 1.00 5.70 0.50 0.90 2.57
CC-2 (EJE E) 1.00 1.05 0.50 0.90 0.47
SCA-2 (EJE 1) 1.00 4.70 0.50 0.90 2.12
SCA-1 (EJE 2) 1.00 4.50 0.50 0.90 2.03
SCA-1 (EJE 3) 1.00 1.50 0.50 0.90 0.68
SCA-1 (EJE 4) 1.00 3.15 0.50 0.90 1.42
SCA-1 (ENTRE EJE 4 Y 5) 1.00 1.45 0.50 0.90 0.65
SCA-1 (EJE 5) 1.00 5.00 0.50 0.90 2.25
SCA-1 (EJE 6) 1.00 2.25 0.50 0.90 1.01
CIMIENTO ESCALERA 1.00 1.00 0.50 0.90 0.45
03.03 SOBRECIMIENTO CONCRETO 1:8 + 25% P.M.
CC-2 (EJE A) 1.00 1.45 0.15 0.20 0.04
CC-1 (ENTRE EJE A Y B) 1.00 1.00 0.15 0.20 0.03
CC-1 (EJE B) 1.00 2.60 0.15 0.20 0.08
CC-1 (EJE C) 1.00 2.60 0.15 0.20 0.08
CC-2 (EJE C) 1.00 0.90 0.15 0.20 0.03
CC-1 (EJE D) 1.00 1.35 0.15 0.20 0.04
CC-2 (EJE E) 1.00 1.75 0.15 0.20 0.05
03.04 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO
CC-2 (EJE A) 2.00 1.45 0.20 0.58
CC-1 (ENTRE EJE A Y B) 2.00 1.00 0.20 0.40
CC-1 (EJE B) 2.00 2.60 0.20 1.04
CC-1 (EJE C) 2.00 2.60 0.20 1.04
CC-2 (EJE C) 2.00 0.90 0.20 0.36
CC-1 (EJE D) 2.00 1.35 0.20 0.54
CC-2 (EJE E) 2.00 1.75 0.20 0.70
RESUMEN DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
04 OBRAS CONCRETO ARMADO
04.01 ZAPATAS
04.01.01 CONCRETO PARA ZAPATAS F'C= 210 KG/CM2
ZAPATA 1 3.00 1.85 1.85 0.70 7.19
ZAPATA 2 3.00 2.70 2.00 0.70 11.34
ZAPATA 3 1.00 3.00 3.00 0.60 5.40
ZAPATA 4 2.00 1.60 1.20 0.50 1.92
ZAPATA 5 7.00 1.20 1.20 0.50 5.04
ZAPATA 6 5.00 1.00 1.00 0.50 2.50
ZAPATA 7 1.00 1.20 1.00 0.50 0.60
ZAPATA 8 1.00 1.50 1.30 0.50 0.98
ZAPATA 9 3.00 1.30 1.30 0.50 2.54
ZAPATA 10 3.00 1.25 0.95 0.50 1.78
04.01.02 ZAPATAS - ACERO Fy=4200 KG/CM2
1.00 1,033.12 1,033.12
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
SCA-1 (ENTRE EJE 4 Y 5) 1.00 1.95 0.25 0.49
SCA-1 (EJE 5) 1.00 4.80 0.25 1.20
SCA-1 (EJE 6) 1.00 2.30 0.25 0.58
04.03.03 SOBRECIMIENTO ARMADO - ACERO Fy= 4200 KG/CM2
1.00 275.50 275.50
04.04 COLUMNAS
04.04.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2
T1 2do, 3er y 4to NIVEL 54.00 0.25 0.15 2.75 5.57
T2 AZOTEA 31.00 0.25 0.15 0.975 1.13
C1 EJE 6C, 7A, 7E 3.00 0.45 0.45 13.05 7.93
C1 EJE 9 3.00 0.45 0.45 13.05 7.93
C-1EJE 7C 1.00 0.45 0.45 13.15 2.66
C1 EJE C7 2.00 0.45 0.45 13.25 5.37
C2 EJE 6C 1.00 0.25 0.25 13.05 0.82
C2 EJE 6E 1.00 0.25 0.25 13.25 0.83
C3 11.00 AREA= 0.12 13.25 17.49
C4 1.00 0.625 0.15 13.25 1.24
C5 EN ZAPATA 3.00 0.30 0.15 13.25 1.79
C5 EN CIMIENTO 6.00 0.30 0.15 12.45 3.36
C6 1.00 0.40 0.25 13.25 1.33
C7 1.00 0.48 0.25 13.25 1.57
C8 1.00 0.70 0.25 13.25 2.32
C9 1.00 0.45 0.15 13.25 0.89
C10 1.00 AREA= 0.08 13.25 1.09
C11 EN ZAPATA 2.00 0.25 0.15 13.25 0.99
C11 EN CIMIENTO 2.00 0.25 0.15 12.45 0.93
C12 1.00 0.30 0.30 13.05 1.17
04.04.02 ENCOFRADO Y DESENCOFRADO PARA COLUMNAS
T1 2do, 3er y 4to NIVEL 54.00 0.25 2.00 2.75 74.25
T2 AZOTEA 31.00 0.25 2.00 0.975 15.11
C1 EJE 6C, 7A, 7E 3.00 1.80 13.05 70.47
C1 EJE 9 3.00 1.80 13.05 70.47
C1EJE 7C 1.00 1.80 13.15 23.67
C1 EJE C7 2.00 1.80 13.25 47.70
C2 EJE 6C 1.00 1.00 13.05 13.05
C2 EJE 6E 1.00 1.00 13.25 13.25
C3 11.00 PERIM= 1.60 13.25 233.20
C4 1.00 1.55 13.25 20.54
C5 EN ZAPATA 3.00 0.90 13.25 35.78
C5 EN CIMIENTO 6.00 0.90 13.35 72.09
C6 1.00 1.30 13.25 17.23
C7 1.00 1.45 13.25 19.21
C8 1.00 1.90 13.25 25.18
C9 1.00 1.20 13.25 15.90
C10 1.00 PERIM= 1.40 13.25 18.55
C11 EN ZAPATA 2.00 0.80 13.25 21.20
C11 EN CIMIENTO 2.00 0.80 13.35 21.36
C12 1.00 1.20 13.05 15.66
RESUMEN DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
04.04.03 COLUMNAS - ACERO Fy= 4200 KG/CM2
ACERO COLUMNAS 1.00 6,921.70 6,921.70
04.05 VIGAS
04.05.01 CONCRETO EN VIGAS F'C=210 KG/CM2
1ER NIVEL
VIGA VA EJE 6 1.00 1.50 0.15 0.20 0.05
VIGA VA EJE 7 1.00 4.15 0.15 0.20 0.12
VIGA VA ENTRE EJE 7 Y 8 1.00 3.05 0.15 0.20 0.09
VIGA VA EJE 8 1.00 6.15 0.15 0.20 0.18
VIGA VA ENTRE EJE A Y B 1.00 4.60 0.15 0.20 0.14
VIGA VA EJE B 1.00 5.05 0.15 0.20 0.15
VIGA VA EJE C 1.00 3.50 0.15 0.20 0.11
VIGA VA EJE D 1.00 3.20 0.15 0.20 0.10
VIGA 1V-1 EJE 1 Y 2 2.00 10.00 0.25 0.20 1.00
VIGA 1V-1 EJE 3 1.00 3.45 0.25 0.20 0.17
VIGA 1V-1 EJE 4 1.00 5.95 0.25 0.20 0.30
VIGA 1V-1 ENTRE EJE 6 Y 7 1.00 4.525 0.25 0.20 0.23
VIGA 1V-1 EJE A 1.00 9.00 0.25 0.20 0.45
VIGA 1V-1 ENTRE EJE A Y B 1.00 5.05 0.25 0.20 0.25
VIGA 1V-1 EJE B 1.00 2.75 0.25 0.20 0.14
VIGA 1V-1 EJE C 1.00 5.35 0.25 0.20 0.27
VIGA 1V-1 EJE D 1.00 3.40 0.25 0.20 0.17
VIGA 1V-1 EJE E 1.00 6.30 0.25 0.20 0.32
VIGA 1V-2 EJE 5 1.00 4.05 0.25 0.40 0.41
VIGA 1V-2 EJE 6, 7 Y 9 3.00 10.00 0.25 0.40 3.00
VIGA 1V-2 EJE C; 5-6 1.00 2.00 0.25 0.40 0.20
VIGA 1V-4 ENTRE EJE 4 Y 5 1.00 4.05 0.25 0.20 0.20
VIGA 1V-4 EJE 5 1.00 5.95 0.25 0.20 0.30
VIGA 1V-4 EJE E 1.00 1.75 0.25 0.20 0.09
VIGA 1V-6 EJE 7 Y 8 2.00 4.725 0.20 0.20 0.38
VIGA 1V-6 EJE 9 1.00 10.00 0.20 0.20 0.40
VIGA 1V-7 EJE C 1.00 2.70 0.25 0.20 0.14
VIGA V-101 1.00 8.25 0.25 0.40 0.83
VIGA V-102 EJE A Y B 2.00 8.70 0.25 0.40 1.74
2DO NIVEL
3ER NIVEL
4TO NIVEL
PARAPETO AZOTEA
VIGA VA-2 1.00 92.40 0.15 0.125 1.73
04.05.02 ENCOFRADO Y DESENCOFRADO EN VIGAS
1ER NIVEL
VIGA VA EJE 6 2.00 1.50 0.20 0.60
VIGA VA EJE 7 2.00 4.15 0.20 1.66
VIGA VA ENTRE EJE 7 Y 8 2.00 3.05 0.20 1.22
VIGA VA EJE 8 2.00 6.15 0.20 2.46
VIGA VA ENTRE EJE A Y B 2.00 4.60 0.20 1.84
VIGA VA EJE B 2.00 5.05 0.20 2.02
VIGA VA EJE C 2.00 3.50 0.20 1.40
RESUMEN DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
VIGA VA EJE D 2.00 3.20 0.20 1.28
VIGA 1V-1 EJE 1 Y 2 2.00 10.00 0.65 13.00
VIGA 1V-1 EJE 3 1.00 3.45 0.65 2.24
VIGA 1V-1 EJE 4 1.00 5.95 0.65 3.87
VIGA 1V-1 ENTRE EJE 6 Y 7 1.00 4.525 0.65 2.94
VIGA 1V-1 EJE A 1.00 9.00 0.65 5.85
VIGA 1V-1 ENTRE EJE A Y B 1.00 5.05 0.65 3.28
VIGA 1V-1 EJE B 1.00 2.75 0.65 1.79
VIGA 1V-1 EJE C 1.00 5.35 0.65 3.48
VIGA 1V-1 EJE D 1.00 3.40 0.65 2.21
VIGA 1V-1 EJE E 1.00 6.30 0.65 4.10
VIGA 1V-2 EJE 5 1.00 4.05 1.05 4.25
VIGA 1V-2 EJE 6, 7 Y 9 3.00 10.00 1.05 31.50
VIGA 1V-2 EJE C; 5-6 1.00 2.00 1.05 2.10
VIGA 1V-4 ENTRE EJE 4 Y 5 1.00 4.05 0.65 2.63
VIGA 1V-4 EJE 5 1.00 5.95 0.65 3.87
VIGA 1V-4 EJE E 1.00 1.75 0.65 1.14
VIGA 1V-6 EJE 7 Y 8 2.00 4.73 0.65 6.14
VIGA 1V-6 EJE 9 1.00 10.00 0.65 6.50
VIGA 1V-7 EJE C 1.00 2.70 0.65 1.76
VIGA V-101 1.00 8.25 1.05 8.66
VIGA V-102 EJE A Y B 2.00 8.70 1.05 18.27
2DO NIVEL
3ER NIVEL
4TO NIVEL
PARAPETO AZOTEA
VIGA VA-2 2.00 92.40 0.125 23.10
04.05.03 VIGAS - ACERO Fy= 4200 KG/CM2
1ER A 4TO NIVEL 4.00 1,853.00 7,412.00
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
ENTRE EJE 8-9 Y A-B 1.00 4.725 2.975 0.09 1.24
ENTRE EJE 7-9 Y C-E 1.00 5.725 4.525 0.09 2.28
ENTRE EJE 9 Y A-B 1.00 4.725 0.20 0.09 0.08
ENTRE EJE 9 Y C-E 1.00 4.525 0.20 0.09 0.08
2DO NIVEL
3ER NIVEL
4TO NIVEL
04.06.02 ENCOFRADO Y DESENCOFRADO EN LOSAS ALIGERADAS
1ER NIVEL
ENTRE EJE 1-2 Y A-B 1.00 2.90 2.50 7.25
1.00 2.75 1.10 3.03
ENTRE EJE 1-2 Y C-E 1.00 3.575 2.75 9.83
ENTRE EJE 2-3 Y A-B 1.00 1.90 1.20 2.28
ENTRE EJE 3-4 Y A-B 1.00 2.95 1.10 3.25
ENTRE EJE 2-4 Y B-C 1.00 1.35 0.45 0.61
1.00 2.70 2.25 6.08
ENTRE EJE 2-4 Y C-E 1.00 3.80 3.55 13.49
ENTRE EJE 4-5 Y A-B 1.00 2.95 2.56 7.55
ENTRE EJE 4-5 Y B-C 1.00 2.56 2.25 5.76
ENTRE EJE 4-5 Y C-D 1.00 1.75 1.00 1.75
ENTRE EJE 6-7 Y A-B 1.00 4.725 3.00 14.18
ENTRE EJE 6-7 Y C-D 1.00 1.70 1.625 2.76
ENTRE EJE 6-7 Y C-E 1.00 4.525 1.025 4.64
ENTRE EJE 7 Y A-B 1.00 4.725 0.70 3.31
ENTRE EJE 8 Y A-B 1.00 4.15 1.20 4.98
ENTRE EJE 8-9 Y A-B 1.00 4.725 2.975 14.06
ENTRE EJE 7-9 Y C-E 1.00 5.725 4.525 25.91
ENTRE EJE 9 Y A-B 1.00 4.725 0.20 0.95
ENTRE EJE 9 Y C-E 1.00 4.525 0.20 0.91
2DO NIVEL
3ER NIVEL
4TO NIVEL
04.06.03 LOSAS ALIGERADAS - ACERO Fy=4200 KG/CM2
1ER A 4TO NIVEL 4.00 712.00 2,848.00
04.06.04 LOSAS ALIGERADAS - LADRILLO HUECO 15X30X30 cm.
1ER NIVEL FACTOR
ENTRE EJE 1-2 Y A-B 1.00 2.90 2.50 8.25 59.81
1.00 2.75 1.10 8.25 24.96
ENTRE EJE 1-2 Y C-E 1.00 3.575 2.75 8.25 81.11
ENTRE EJE 2-3 Y A-B 1.00 1.90 1.20 8.25 18.81
ENTRE EJE 3-4 Y A-B 1.00 2.95 1.10 8.25 26.77
ENTRE EJE 2-4 Y B-C 1.00 1.35 0.45 8.25 5.01
1.00 2.70 2.25 8.25 50.12
ENTRE EJE 2-4 Y C-E 1.00 3.80 3.55 8.25 111.29
ENTRE EJE 4-5 Y A-B 1.00 2.95 2.56 8.25 62.30
ENTRE EJE 4-5 Y B-C 1.00 2.56 2.25 8.25 47.52
ENTRE EJE 4-5 Y C-D 1.00 1.75 1.00 8.25 14.44
ENTRE EJE 6-7 Y A-B 1.00 4.725 3.00 8.25 116.94
ENTRE EJE 6-7 Y C-D 1.00 1.70 1.625 8.25 22.79
RESUMEN DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
ENTRE EJE 6-7 Y C-E 1.00 4.525 1.025 8.25 38.26
ENTRE EJE 7 Y A-B 1.00 4.725 0.70 8.25 27.29
ENTRE EJE 8 Y A-B 1.00 4.15 1.20 8.25 41.09
ENTRE EJE 8-9 Y A-B 1.00 4.725 2.975 8.25 115.97
ENTRE EJE 7-9 Y C-E 1.00 5.725 4.525 8.25 213.72
ENTRE EJE 9 Y A-B 1.00 4.725 0.20 8.25 7.80
ENTRE EJE 9 Y C-E 1.00 4.525 0.20 8.25 7.47
2DO NIVEL
3ER NIVEL
4TO NIVEL
04.07 ESCALERAS
04.07.01 CONCRETO EN ESCALERAS F'C=210 KG/CM2
1ER NIVEL
GARGANTA ESCALERA TRAMO 1 1.00 2.00 1.00 0.15 0.30
GARGANTA ESCALERA TRAMO 2 1.00 2.45 1.00 0.15 0.37
ESCALERA PELDAÑOS TRAMO 1 8.00 1.00 0.25 0.175 0.18
ESCALERA PELDAÑOS TRAMO 2 8.00 1.00 0.25 0.175 0.18
ESCALERA DESCANSO TRAMO 1 1.00 1.20 1.00 0.15 0.09
ESCALERA DESCANSO TRAMO 2 2.00 1.20 1.00 0.15 0.18
2DO A 4TO NIVEL
GARGANTA ESCALERA TRAMO 1 3.00 2.45 1.00 0.15 1.10
GARGANTA ESCALERA TRAMO 2 3.00 2.45 1.00 0.15 1.10
ESCALERA PELDAÑOS TRAMO 1 24.00 1.00 0.25 0.175 0.53
ESCALERA PELDAÑOS TRAMO 2 24.00 1.00 0.25 0.175 0.53
ESCALERA DESCANSO TRAMO 1 6.00 1.20 1.00 0.15 0.54
ESCALERA DESCANSO TRAMO 2 6.00 1.20 1.00 0.15 0.54
04.07.02 ENCOFRADO Y DESENCOFRADO EN ESCALERAS
1ER NIVEL
GARGANTA ESCALERA TRAMO 1 1.00 2.00 1.00 2.00
GARGANTA ESCALERA TRAMO 2 1.00 2.45 1.00 2.45
CARA LATERAL ESCALERA TRAMO 1 1.00 2.00 0.30 0.60
CARA LATERAL ESCALERA TRAMO 2 1.00 2.45 0.30 0.74
ESCALERA PELDAÑOS TRAMO 1 8.00 1.00 0.175 0.70
ESCALERA PELDAÑOS TRAMO 2 8.00 1.00 0.175 0.70
ESCALERA DESCANSO TRAMO 1 1.00 1.20 1.00 0.60
ESCALERA DESCANSO TRAMO 2 2.00 1.20 1.00 1.20
2DO A 4TO NIVEL
GARGANTA ESCALERA TRAMO 1 3.00 2.45 1.00 7.35
GARGANTA ESCALERA TRAMO 2 3.00 2.45 1.00 7.35
CARA LATERAL ESCALERA TRAMO 1 3.00 2.45 0.30 2.21
CARA LATERAL ESCALERA TRAMO 2 3.00 2.45 0.30 2.21
ESCALERA PELDAÑOS TRAMO 1 24.00 1.00 0.175 2.10
ESCALERA PELDAÑOS TRAMO 2 24.00 1.00 0.175 2.10
ESCALERA DESCANSO TRAMO 1 6.00 1.20 1.00 3.60
ESCALERA DESCANSO TRAMO 2 6.00 1.20 1.00 3.60
04.07.03 ESCALERAS - ACERO Fy= 4200 KG/CM2
PRIMER NIVEL 1.00 424.00 424.00
RESUMEN DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
05 MUROS Y TABIQUES DE ALBAÑILERIA
05.01 MURO DE LADRILLO KK SOGA C:A 1:4
PRIMER NIVEL
EJE 1 1.00 8.25 2.80 23.10
EJE 2 1.00 6.175 2.80 17.29
EJE 3 1.00 2.45 2.80 6.86
EJE 4 1.00 2.80 2.80 7.84
EJE 4-5 1.00 1.95 2.80 5.46
EJE A 1.00 18.05 2.80 50.54
EJE B 1.00 9.65 2.80 27.02
EJE C 1.00 2.90 2.80 8.12
EJE D 1.00 1.35 2.80 3.78
EJE E 1.00 17.00 2.80 47.60
QUITAR AREA DE VENTANAS EJE 4-5 -1.00 1.95 1.80 -3.51
QUITAR AREA DE VENTANAS EJE 5 -1.00 2.70 1.30 -3.51
QUITAR AREA DE VENTANAS EJE 5 -1.00 1.61 1.30 -2.09
QUITAR AREA DE VENTANAS EJE A -1.00 1.20 0.50 -0.60
QUITAR AREA DE VENTANAS EJE B -1.00 1.50 1.80 -2.70
SEGUNDO NIVEL
EJE 1 1.00 8.25 2.70 22.28
EJE 2 1.00 6.175 2.70 16.67
EJE 3 1.00 2.45 2.70 6.62
EJE 4 1.00 2.80 2.70 7.56
EJE 5 1.00 4.30 2.70 11.61
EJE 6 1.00 8.15 2.70 22.01
EJE 7 1.00 4.40 2.70 11.88
EJE 7-8 1.00 2.75 2.70 7.43
EJE 8 1.00 5.50 2.70 14.85
EJE 9 1.00 9.50 2.70 25.65
EJE A 1.00 19.65 2.70 53.06
EJE B 1.00 17.20 2.70 46.44
EJE C 1.00 7.05 2.70 19.04
EJE D 1.00 6.30 2.70 17.01
EJE E 1.00 17.40 2.70 46.98
QUITAR AREA DE VENTANAS EJE 4-5 -1.00 1.95 1.80 -3.51
QUITAR AREA DE VENTANAS EJE 5 -1.00 2.41 1.30 -3.13
QUITAR AREA DE VENTANAS EJE 5 -1.00 2.10 1.30 -2.73
QUITAR AREA DE VENTANAS EJE 6 -1.00 2.36 1.30 -3.07
QUITAR AREA DE VENTANAS EJE 6 -1.00 1.29 1.30 -1.68
QUITAR AREA DE VENTANAS EJE 6 -1.00 2.30 1.35 -3.11
QUITAR AREA DE VENTANAS EJE 6-7 -1.00 2.75 1.30 -3.58
QUITAR AREA DE VENTANAS EJE 9 -1.00 2.25 1.50 -3.38
QUITAR AREA DE VENTANAS EJE 9 -1.00 1.10 1.50 -1.65
QUITAR AREA DE VENTANAS EJE 9 -1.00 1.50 2.20 -3.30
QUITAR AREA DE VENTANAS EJE A -1.00 1.20 0.50 -0.60
QUITAR AREA DE VENTANAS EJE B -1.00 1.50 1.80 -2.70
QUITAR AREA DE VENTANAS EJE D -1.00 3.60 1.35 -4.86
3ER NIVEL
4TO NIVEL
RESUMEN DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
AZOTEA
PARAPETO 1.00 84.65 0.975 82.53
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
QUITAR AREA DE VENTANAS EJE 9 -1.00 2.25 1.50 -3.38
QUITAR AREA DE VENTANAS EJE 9 -1.00 1.10 1.50 -1.65
QUITAR AREA DE VENTANAS EJE 9 -1.00 1.50 2.20 -3.30
06.04 TARRAJEO DE VIGAS
1ER NIVEL
VIGA 1V-1 EJE 1 Y 2 2.00 10.00 0.65 13.00
VIGA 1V-1 EJE 3 1.00 3.45 0.65 2.24
VIGA 1V-1 EJE 4 1.00 5.95 0.65 3.87
VIGA 1V-1 ENTRE EJE 6 Y 7 1.00 4.525 0.65 2.94
VIGA 1V-1 EJE A 1.00 9.00 0.65 5.85
VIGA 1V-1 ENTRE EJE A Y B 1.00 5.05 0.65 3.28
VIGA 1V-1 EJE B 1.00 2.75 0.65 1.79
VIGA 1V-1 EJE C 1.00 5.35 0.65 3.48
VIGA 1V-1 EJE D 1.00 3.40 0.65 2.21
VIGA 1V-1 EJE E 1.00 6.30 0.65 4.10
VIGA 1V-2 EJE 5 1.00 4.05 1.05 4.25
VIGA 1V-2 EJE 6, 7 Y 9 3.00 10.00 1.05 31.50
VIGA 1V-2 EJE C; 5-6 1.00 2.00 1.05 2.10
VIGA 1V-4 ENTRE EJE 4 Y 5 1.00 4.05 0.65 2.63
VIGA 1V-4 EJE 5 1.00 5.95 0.65 3.87
VIGA 1V-4 EJE E 1.00 1.75 0.65 1.14
VIGA 1V-6 EJE 7 Y 8 2.00 4.73 0.65 6.14
VIGA 1V-6 EJE 9 1.00 10.00 0.65 6.50
VIGA 1V-7 EJE C 1.00 2.70 0.65 1.76
VIGA V-101 1.00 8.25 1.05 8.66
VIGA V-102 EJE A Y B 2.00 8.70 1.05 18.27
2DO NIVEL
3ER NIVEL
4TO NIVEL
PARAPETO AZOTEA
VIGA VA-2 2.00 92.40 0.125 23.10
06.05 VESTIDURA DE DERRAMES EN VANOS MEZCLA 1:5
PRIMER NIVEL
VENTANAS EJE 4-5 1.00 1.95 1.80 5.55
VENTANAS EJE 5 1.00 2.70 1.30 5.30
VENTANAS EJE 5 1.00 1.61 1.30 4.21
VENTANAS EJE A 1.00 1.20 0.50 2.20
VENTANAS EJE B 1.00 1.50 1.80 5.10
PUERTAS 1.00 11.00 3.00 17.00
2DO A 4TO NIVEL
VENTANAS EJE 4-5 3.00 1.95 1.80 16.65
VENTANAS EJE 5 3.00 2.41 1.30 15.03
VENTANAS EJE 5 3.00 2.10 1.30 14.10
VENTANAS EJE 6 3.00 2.36 1.30 14.88
VENTANAS EJE 6 3.00 1.29 1.30 11.67
VENTANAS EJE 6 3.00 2.30 1.35 15.00
VENTANAS EJE 6-7 3.00 2.75 1.30 16.05
VENTANAS EJE 9 3.00 2.25 1.50 15.75
VENTANAS EJE 9 3.00 1.10 1.50 12.30
RESUMEN DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
VENTANAS EJE 9 3.00 1.50 2.20 17.70
VENTANAS EJE A 3.00 1.20 0.50 6.60
VENTANAS EJE B 3.00 1.50 1.80 15.30
VENTANAS EJE D 3.00 3.60 1.35 18.90
PUERTAS 3.00 22.00 2.70 82.20
06.06 TARRAJEO EN GRADERIAS
1ER NIVEL
GARGANTA ESCALERA TRAMO 1 1.00 2.00 1.00 2.00
GARGANTA ESCALERA TRAMO 2 1.00 2.45 1.00 2.45
CARA LATERAL ESCALERA TRAMO 1 1.00 2.00 0.30 0.60
CARA LATERAL ESCALERA TRAMO 2 1.00 2.45 0.30 0.74
ESCALERA PELDAÑOS TRAMO 1 8.00 1.00 0.175 0.70
ESCALERA PELDAÑOS TRAMO 2 8.00 1.00 0.175 0.70
ESCALERA DESCANSO TRAMO 1 1.00 1.20 1.00 0.60
ESCALERA DESCANSO TRAMO 2 2.00 1.20 1.00 1.20
2DO A 4TO NIVEL
GARGANTA ESCALERA TRAMO 1 3.00 2.45 1.00 7.35
GARGANTA ESCALERA TRAMO 2 3.00 2.45 1.00 7.35
CARA LATERAL ESCALERA TRAMO 1 3.00 2.45 0.30 2.21
CARA LATERAL ESCALERA TRAMO 2 3.00 2.45 0.30 2.21
ESCALERA PELDAÑOS TRAMO 1 24.00 1.00 0.175 2.10
ESCALERA PELDAÑOS TRAMO 2 24.00 1.00 0.175 2.10
ESCALERA DESCANSO TRAMO 1 6.00 1.20 1.00 3.60
ESCALERA DESCANSO TRAMO 2 6.00 1.20 1.00 3.60
07 CIELORRASOS
07.01 CIELORRASOS CON MEZCLA DE CEMENTO-ARENA 1:5
1ER NIVEL
ENTRE EJE 1-2 Y A-B 1.00 2.90 2.50 7.25
1.00 2.75 1.10 3.03
ENTRE EJE 1-2 Y C-E 1.00 3.575 2.75 9.83
ENTRE EJE 2-3 Y A-B 1.00 1.90 1.20 2.28
ENTRE EJE 3-4 Y A-B 1.00 2.95 1.10 3.25
ENTRE EJE 2-4 Y B-C 1.00 1.35 0.45 0.61
1.00 2.70 2.25 6.08
ENTRE EJE 2-4 Y C-E 1.00 3.80 3.55 13.49
ENTRE EJE 4-5 Y A-B 1.00 2.95 2.56 7.55
ENTRE EJE 4-5 Y B-C 1.00 2.56 2.25 5.76
ENTRE EJE 4-5 Y C-D 1.00 1.75 1.00 1.75
ENTRE EJE 6-7 Y A-B 1.00 4.725 3.00 14.18
ENTRE EJE 6-7 Y C-D 1.00 1.70 1.625 2.76
ENTRE EJE 6-7 Y C-E 1.00 4.525 1.025 4.64
ENTRE EJE 7 Y A-B 1.00 4.725 0.70 3.31
ENTRE EJE 8 Y A-B 1.00 4.15 1.20 4.98
ENTRE EJE 8-9 Y A-B 1.00 4.725 2.975 14.06
ENTRE EJE 7-9 Y C-E 1.00 5.725 4.525 25.91
ENTRE EJE 9 Y A-B 1.00 4.725 0.20 0.95
ENTRE EJE 9 Y C-E 1.00 4.525 0.20 0.91
2DO NIVEL
RESUMEN DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
3ER NIVEL
4TO NIVEL
08 PISOS Y PAVIMENTOS
08.01 FALSO PISO
08.01.01 FALSOPISO MEZCLA 1:8 C-H E=4"
PRIMER PISO 1.00 AREA= 178.80 178.80
08.02 CONTRAPISO
08.02.01 CONTRAPISO DE 40 MM
2DO, 3ER Y 4TO PISO 3.00 AREA= 150.75 452.25
09 INSTALACIONES SANITARIAS
09.01 SISTEMA DE DRENAJE PLUVIAL
09.01.01 TUBERIA PVC-SAL 2"
AZOTEA 1.00 12.65 12.65
BAJADA DE LLUVIA 4.00 12.25 49.00
09.02 DESAGÜE Y VENTILACION
09.02.01 EXCAVACION DE ZANJAS
PRIMER NIVEL 1.00 48.00 48.00
09.02.02 SALIDA DE DESAGUE PVC SAL 2"
PRIMER NIVEL 1.00 4.00 4.00
SEGUNDO A CUARTO NIVEL 3.00 8.00 24.00
09.02.03 SALIDA DE DESAGUE PVC SAL 4"
PRIMER NIVEL 1.00 2.00 2.00
SEGUNDO A CUARTO NIVEL 3.00 4.00 12.00
09.02.04 SALIDA DE VENTILACION PVC 2" 6.00 6.00
09.02.05 TUBERIA PVC-SAL 2" PARA DESAGÜE
PRIMER NIVEL 1.00 12.00 12.00
SEGUNDO A CUARTO NIVEL 3.00 16.15 48.45
09.02.06 TUBERIA PVC-SAL 4" PARA DESAGÜE
PRIMER NIVEL 1.00 27.80 27.80
SEGUNDO A CUARTO NIVEL 3.00 15.55 46.65
09.02.06 TUBERIA PVC-SAL 6" PARA DESAGÜE
PRIMER NIVEL 1.00 36.05 36.05
SEGUNDO A CUARTO NIVEL 3.00 5.90 17.70
09.02.07 SOMBRERO VENTILACIÓN DE PVC DE 2" 6.00 6.00
09.02.08 SUMIDERO DE 2"
PRIMER NIVEL 1.00 6.00 6.00
SEGUNDO A CUARTO NIVEL 3.00 12.00 36.00
09.02.09 REGISTRO ROSCADO DE BRONCE DE 4"
PRIMER NIVEL 1.00 2.00 2.00
SEGUNDO A CUARTO NIVEL 3.00 4.00 12.00
09.02.10 CAJA DE REGISTRO 3.00 3.00
09.03 SISTEMA DE AGUA FRIA
09.03.01 EXCAVACION DE ZANJAS RED DE AGUA
PRIMER NIVEL 1.00 119.00 119.00
09.03.02 SALIDA DE AGUA FRIA PVC-SAP 1/2"
PRIMER NIVEL 1.00 8.00 8.00
SEGUNDO A CUARTO NIVEL 3.00 16.00 48.00
RESUMEN DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
09.03.03 TUBERIA DE PVC CLASE 10 DE 1/2"
PRIMER NIVEL 1.00 20.05 20.05
SEGUNDO A CUARTO NIVEL 3.00 41.50 124.50
09.03.04 TUBERIA DE PVC CLASE 10 DE 3/4"
AZOTEA 1.00 60.20 60.20
MONTANTE 7.00 12.25 85.75
09.03.04 TUBERIA DE PVC CLASE 10 DE 1"
PRIMER NIVEL 1.00 99.00 99.00
MONTANTE 7.00 12.25 85.75
09.03.05 VALVULA COMPUERTA DE BRONCE DE 1/2"
PRIMER NIVEL 1.00 4.00 4.00
SEGUNDO A CUARTO NIVEL 3.00 8.00 24.00
09.03.06 CAJA PARA VALVULA (NICHO DE MAYOLICA)
PRIMER NIVEL 1.00 4.00 4.00
SEGUNDO A CUARTO NIVEL 3.00 8.00 24.00
09.03 SISTEMA DE AGUA CALIENTE
09.03.01 EXCAVACION DE ZANJAS RED DE AGUA
PRIMER NIVEL 1.00 20.40 20.40
09.03.02 SALIDA DE AGUA CALIENTE PVC-SAP 1/2"
PRIMER NIVEL 1.00 5.00 5.00
SEGUNDO A CUARTO NIVEL 3.00 10.00 30.00
09.03.03 TUBERIA DE PVC H3 DE 1/2"
PRIMER NIVEL 1.00 20.40 20.40
SEGUNDO A CUARTO NIVEL 3.00 38.40 115.20
AZOTEA 1.00 17.50 17.50
MONTANTE 7.00 12.25 85.75
09.03.05 VALVULA COMPUERTA DE BRONCE DE 1/2"
PRIMER NIVEL 1.00 3.00 3.00
SEGUNDO A CUARTO NIVEL 3.00 6.00 18.00
09.03.06 CAJA PARA VALVULA
PRIMER NIVEL 1.00 3.00 3.00
SEGUNDO A CUARTO NIVEL 3.00 6.00 18.00
10 INSTALACIONES ELECTRICAS
10.01 SALIDAS
10.01.01 SALIDA DE TECHO PARA CENTROS DE LUZ
PRIMER NIVEL 1.00 15.00 15.00
SEGUNDO A CUARTO NIVEL 3.00 19.00 57.00
10.01.02 SALIDA DE TECHO PARA SPOTLIGHT
PRIMER NIVEL 1.00 18.00 18.00
SEGUNDO A CUARTO NIVEL 3.00 24.00 72.00
10.01.03 SALIDA PARA LUZ EN PARED
PRIMER NIVEL 1.00 4.00 4.00
SEGUNDO A CUARTO NIVEL 3.00 7.00 21.00
10.01.04 SALIDA PARA INTERRUPTORES
PRIMER NIVEL 1.00 17.00 17.00
SEGUNDO A CUARTO NIVEL 3.00 24.00 72.00
10.01.05 SALIDA PARA TOMACORRIENTES
PRIMER NIVEL 1.00 27.00 27.00
RESUMEN DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial
Largo Ancho Alto
SEGUNDO A CUARTO NIVEL 3.00 55.00 165.00
10.02 CANALIZACIONES Y/O TUBERIAS
10.02.01 TUBERIAS PVC SAP (ELECTRICAS) D=3/4"
PRIMER NIVEL 1.00 135.30 135.30
SEGUNDO A CUARTO NIVEL 3.00 194.30 582.90
10.02.02 TUBERIAS PVC SAP (ELECTRICAS) D=1"
PRIMER NIVEL 1.00 20.15 20.15
SEGUNDO A CUARTO NIVEL 3.00 13.15 39.45
10.03 CAJAS DE PASO
10.03.01 CAJA DE PASO CIRCULAR 4.00 2.00 8.00
10.05.07 TABLEROS DISTRIBUCIÓN CAJA METALICA 4.00 4.00
11 INSTALACIONES DE COMUNICACIONES
11.01 SALIDAS
11.01.01 SALIDA PARA TELEFONO Y TV-CABLE
PRIMER NIVEL 1.00 7.00 7.00
SEGUNDO A CUARTO NIVEL 3.00 14.00 42.00
11.01.01 SALIDA PARA INTERCOMUNICADOR
PRIMER NIVEL 1.00 2.00 2.00
SEGUNDO A CUARTO NIVEL 3.00 2.00 6.00
11.02 CANALIZACIONES Y/O TUBERIAS
11.02.01 TUBERIAS PVC SAP (TELEFONO Y TV-CABLE) D=3/4"
PRIMER NIVEL 1.00 28.80 28.80
SEGUNDO A CUARTO NIVEL 3.00 51.20 153.60
11.02.01 TUBERIAS PVC SAP (INTERCOMUNICADOR) D=3/4"
PRIMER NIVEL 1.00 25.95 25.95
SEGUNDO A CUARTO NIVEL 3.00 13.75 41.25
11.03 CAJAS DE PASO
11.03.01 CAJA DE PASO DE 200x200x150 FºGº 1.00 19.00 19.00
12 LIMPIEZA FINAL
12.01 LIMPIEZA FINAL DE OBRA 1.00 20.00 10.00 200.00
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
200.00 M2
200.00 M2
105.87 M3
31.68 M3
105.91 M3
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
178.80 M2
39.56 M3
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
66.17 M2
22.12 M3
0.35 M3
4.66 M2
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
39.28 M3
1,033.12 KG
1.97 M3
13.14 M2
321.10 KG
3.92 M3
15.68 M2
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
275.50 KG
66.42 M3
843.86 M2
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
6,921.70 KG
49.31 M3
11.90
11.90
11.90
11.90
1.73
591.32 M2
142.05
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
142.05
142.05
142.05
23.10
7,412.00 KG
46.65 M3
11.66
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
11.66
11.66
11.66
530.17 M2
132.54
132.54
132.54
132.54
2,848.00 KG
4,376.00 UND
1,094.00
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
1,094.00
1,094.00
1,094.00
5.62 M3
1.29
4.34
39.50 M2
8.99
30.51
424.00 KG
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
1,143.07 M2
185.20
291.78
291.78
291.78
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
82.53
300.24 M2
40.23
260.01
1,584.78 M2
90.68 M2
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
541.40 M2
129.57
129.57
129.57
129.57
23.10
311.49 M
39.36
272.13
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
39.50 M2
8.99
30.51
530.17 M2
132.54
132.54
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
132.54
132.54
178.80 M2
452.25 M2
61.65 M
48.00 M
28.00 PTO
14.00 PTO
6.00 PTO
60.45 M
74.45 M
53.75 M
6.00 UND
42.00 UND
14.00 UND
3.00 UND
119.00 M
56.00 PTO
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
144.55 M
145.95 M
184.75 M
28.00 UND
28.00 UND
20.40 M
35.00 PTO
238.85 M
21.00 UND
21.00 UND
72.00 PTO
90.00 PTO
25.00 PTO
89.00 PTO
192.00 PTO
RESUMEN DE METRADOS
ROYECTO: VIVIENDA MULTIFAMILIAR
Total Unidad
718.20 M
59.60 M
8.00 UND
4.00 PZA
49.00 PTO
8.00 PTO
182.40 M
67.20 M
19.00 UND
200.00 M2
PLANILLA DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial Total Unidad
Largo Ancho Alto
01 OBRAS DE CONCRETO SIMPLE
01.01 SOLADO DE CONCRETO MEZCLA 1:10 66.17 M2
ZAPATA 1 3.00 1.85 1.85 10.27
ZAPATA 2 3.00 2.70 2.00 16.20
ZAPATA 3 1.00 3.00 3.00 9.00
ZAPATA 4 2.00 1.60 1.20 3.84
ZAPATA 5 7.00 1.20 1.20 10.08
ZAPATA 6 5.00 1.00 1.00 5.00
ZAPATA 7 1.00 1.20 1.00 1.20
ZAPATA 8 1.00 1.50 1.30 1.95
ZAPATA 9 3.00 1.30 1.30 5.07
ZAPATA 10 3.00 1.25 0.95 3.56
01.02 CIMIENTOS CORRIDOS 1:10 CEMENTO-HORMIGON+30% P.G. 22.12 M3
SCA-2 (EJE A) 1.00 7.10 0.50 0.90 3.20
CC-2 (EJE A) 1.00 1.05 0.50 0.90 0.47
SCA-1(ENTRE EJE A Y B) 1.00 1.60 0.50 0.90 0.72
CC-1 (ENTRE EJE A Y B) 1.00 1.55 0.50 0.90 0.70
CC-1 (EJE B) 1.00 1.40 0.50 0.90 0.63
CC-1 (EJE C) 1.00 1.30 0.50 0.90 0.59
SCA-1 (EJE C) 1.00 1.40 0.50 0.90 0.63
CC-2 (EJE C) 1.00 1.40 0.50 0.90 0.63
CC-1 (EJE D) 1.00 1.20 0.50 0.90 0.54
CC-2 (EJE D) 1.00 0.85 0.50 0.90 0.38
SCA-2 (EJE E) 1.00 5.70 0.50 0.90 2.57
CC-2 (EJE E) 1.00 1.05 0.50 0.90 0.47
SCA-2 (EJE 1) 1.00 4.70 0.50 0.90 2.12
SCA-1 (EJE 2) 1.00 4.50 0.50 0.90 2.03
SCA-1 (EJE 3) 1.00 1.50 0.50 0.90 0.68
SCA-1 (EJE 4) 1.00 3.15 0.50 0.90 1.42
SCA-1 (ENTRE EJE 4 Y 5) 1.00 1.45 0.50 0.90 0.65
SCA-1 (EJE 5) 1.00 5.00 0.50 0.90 2.25
SCA-1 (EJE 6) 1.00 2.25 0.50 0.90 1.01
CIMIENTO ESCALERA 1.00 1.00 0.50 0.90 0.45
03.03 SOBRECIMIENTO CONCRETO 1:8 + 25% P.M. 0.35 M3
CC-2 (EJE A) 1.00 1.45 0.15 0.20 0.04
CC-1 (ENTRE EJE A Y B) 1.00 1.00 0.15 0.20 0.03
CC-1 (EJE B) 1.00 2.60 0.15 0.20 0.08
CC-1 (EJE C) 1.00 2.60 0.15 0.20 0.08
CC-2 (EJE C) 1.00 0.90 0.15 0.20 0.03
CC-1 (EJE D) 1.00 1.35 0.15 0.20 0.04
CC-2 (EJE E) 1.00 1.75 0.15 0.20 0.05
03.04 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO 4.66 M2
CC-2 (EJE A) 2.00 1.45 0.20 0.58
CC-1 (ENTRE EJE A Y B) 2.00 1.00 0.20 0.40
CC-1 (EJE B) 2.00 2.60 0.20 1.04
CC-1 (EJE C) 2.00 2.60 0.20 1.04
CC-2 (EJE C) 2.00 0.90 0.20 0.36
CC-1 (EJE D) 2.00 1.35 0.20 0.54
CC-2 (EJE E) 2.00 1.75 0.20 0.70
DIMENSIONES
ITEM Descripción N° de veces Parcial Total Unidad
Largo Ancho Alto
ZAPATA 10 3.00 1.25 0.95 0.50 1.78
04.01.02 ZAPATAS - ACERO Fy=4200 KG/CM2 1,033.12 KG
1.00 1,033.12 1,033.12
04.04 COLUMNAS
04.04.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 66.42 M3
T1 2do, 3er y 4to NIVEL 54.00 0.25 0.15 2.75 5.57
T2 AZOTEA 31.00 0.25 0.15 0.975 1.13
C1 EJE 6C, 7A, 7E 3.00 0.45 0.45 13.05 7.93
C1 EJE 9 3.00 0.45 0.45 13.05 7.93
C-1EJE 7C 1.00 0.45 0.45 13.15 2.66
C1 EJE C7 2.00 0.45 0.45 13.25 5.37
C2 EJE 6C 1.00 0.25 0.25 13.05 0.82
C2 EJE 6E 1.00 0.25 0.25 13.25 0.83
C3 11.00 AREA= 0.12 13.25 17.49
C4 1.00 0.625 0.15 13.25 1.24
C5 EN ZAPATA 3.00 0.30 0.15 13.25 1.79
C5 EN CIMIENTO 6.00 0.30 0.15 12.45 3.36
C6 1.00 0.40 0.25 13.25 1.33
C7 1.00 0.48 0.25 13.25 1.57
C8 1.00 0.70 0.25 13.25 2.32
C9 1.00 0.45 0.15 13.25 0.89
C10 1.00 AREA= 0.08 13.25 1.09
PLANILLA DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial Total Unidad
Largo Ancho Alto
C11 EN ZAPATA 2.00 0.25 0.15 13.25 0.99
C11 EN CIMIENTO 2.00 0.25 0.15 12.45 0.93
C12 1.00 0.30 0.30 13.05 1.17
04.04.02 ENCOFRADO Y DESENCOFRADO PARA COLUMNAS 843.86 M2
T1 2do, 3er y 4to NIVEL 54.00 0.25 2.00 2.75 74.25
T2 AZOTEA 31.00 0.25 2.00 0.975 15.11
C1 EJE 6C, 7A, 7E 3.00 1.80 13.05 70.47
C1 EJE 9 3.00 1.80 13.05 70.47
C1EJE 7C 1.00 1.80 13.15 23.67
C1 EJE C7 2.00 1.80 13.25 47.70
C2 EJE 6C 1.00 1.00 13.05 13.05
C2 EJE 6E 1.00 1.00 13.25 13.25
C3 11.00 PERIM= 1.60 13.25 233.20
C4 1.00 1.55 13.25 20.54
C5 EN ZAPATA 3.00 0.90 13.25 35.78
C5 EN CIMIENTO 6.00 0.90 13.35 72.09
C6 1.00 1.30 13.25 17.23
C7 1.00 1.45 13.25 19.21
C8 1.00 1.90 13.25 25.18
C9 1.00 1.20 13.25 15.90
C10 1.00 PERIM= 1.40 13.25 18.55
C11 EN ZAPATA 2.00 0.80 13.25 21.20
C11 EN CIMIENTO 2.00 0.80 13.35 21.36
C12 1.00 1.20 13.05 15.66
04.04.03 COLUMNAS - ACERO Fy= 4200 KG/CM2 6,921.70 KG
ACERO COLUMNAS 1.00 6,921.70 6,921.70
04.05 VIGAS
04.05.01 CONCRETO EN VIGAS F'C=210 KG/CM2 - 1ER NIVEL 49.31 M3
1ER NIVEL 11.90
VIGA VA EJE 6 1.00 1.50 0.15 0.20 0.05
VIGA VA EJE 7 1.00 4.15 0.15 0.20 0.12
VIGA VA ENTRE EJE 7 Y 8 1.00 3.05 0.15 0.20 0.09
VIGA VA EJE 8 1.00 6.15 0.15 0.20 0.18
VIGA VA ENTRE EJE A Y B 1.00 4.60 0.15 0.20 0.14
VIGA VA EJE B 1.00 5.05 0.15 0.20 0.15
VIGA VA EJE C 1.00 3.50 0.15 0.20 0.11
VIGA VA EJE D 1.00 3.20 0.15 0.20 0.10
VIGA 1V-1 EJE 1 Y 2 2.00 10.00 0.25 0.20 1.00
VIGA 1V-1 EJE 3 1.00 3.45 0.25 0.20 0.17
VIGA 1V-1 EJE 4 1.00 5.95 0.25 0.20 0.30
VIGA 1V-1 ENTRE EJE 6 Y 7 1.00 4.525 0.25 0.20 0.23
VIGA 1V-1 EJE A 1.00 9.00 0.25 0.20 0.45
VIGA 1V-1 ENTRE EJE A Y B 1.00 5.05 0.25 0.20 0.25
VIGA 1V-1 EJE B 1.00 2.75 0.25 0.20 0.14
VIGA 1V-1 EJE C 1.00 5.35 0.25 0.20 0.27
VIGA 1V-1 EJE D 1.00 3.40 0.25 0.20 0.17
VIGA 1V-1 EJE E 1.00 6.30 0.25 0.20 0.32
VIGA 1V-2 EJE 5 1.00 4.05 0.25 0.40 0.41
VIGA 1V-2 EJE 6, 7 Y 9 3.00 10.00 0.25 0.40 3.00
VIGA 1V-2 EJE C; 5-6 1.00 2.00 0.25 0.40 0.20
VIGA 1V-4 ENTRE EJE 4 Y 5 1.00 4.05 0.25 0.20 0.20
VIGA 1V-4 EJE 5 1.00 5.95 0.25 0.20 0.30
VIGA 1V-4 EJE E 1.00 1.75 0.25 0.20 0.09
VIGA 1V-6 EJE 7 Y 8 2.00 4.725 0.20 0.20 0.38
VIGA 1V-6 EJE 9 1.00 10.00 0.20 0.20 0.40
VIGA 1V-7 EJE C 1.00 2.70 0.25 0.20 0.14
VIGA V-101 1.00 8.25 0.25 0.40 0.83
VIGA V-102 EJE A Y B 2.00 8.70 0.25 0.40 1.74
2DO NIVEL 11.90
3ER NIVEL 11.90
4TO NIVEL 11.90
PLANILLA DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial Total Unidad
Largo Ancho Alto
PARAPETO AZOTEA 1.73
VIGA VA-2 1.00 92.40 0.15 0.125 1.73
04.05.02 ENCOFRADO Y DESENCOFRADO EN VIGAS - 1ER NIVEL 591.32 M2
1ER NIVEL 142.05
VIGA VA EJE 6 2.00 1.50 0.20 0.60
VIGA VA EJE 7 2.00 4.15 0.20 1.66
VIGA VA ENTRE EJE 7 Y 8 2.00 3.05 0.20 1.22
VIGA VA EJE 8 2.00 6.15 0.20 2.46
VIGA VA ENTRE EJE A Y B 2.00 4.60 0.20 1.84
VIGA VA EJE B 2.00 5.05 0.20 2.02
VIGA VA EJE C 2.00 3.50 0.20 1.40
VIGA VA EJE D 2.00 3.20 0.20 1.28
VIGA 1V-1 EJE 1 Y 2 2.00 10.00 0.65 13.00
VIGA 1V-1 EJE 3 1.00 3.45 0.65 2.24
VIGA 1V-1 EJE 4 1.00 5.95 0.65 3.87
VIGA 1V-1 ENTRE EJE 6 Y 7 1.00 4.525 0.65 2.94
VIGA 1V-1 EJE A 1.00 9.00 0.65 5.85
VIGA 1V-1 ENTRE EJE A Y B 1.00 5.05 0.65 3.28
VIGA 1V-1 EJE B 1.00 2.75 0.65 1.79
VIGA 1V-1 EJE C 1.00 5.35 0.65 3.48
VIGA 1V-1 EJE D 1.00 3.40 0.65 2.21
VIGA 1V-1 EJE E 1.00 6.30 0.65 4.10
VIGA 1V-2 EJE 5 1.00 4.05 1.05 4.25
VIGA 1V-2 EJE 6, 7 Y 9 3.00 10.00 1.05 31.50
VIGA 1V-2 EJE C; 5-6 1.00 2.00 1.05 2.10
VIGA 1V-4 ENTRE EJE 4 Y 5 1.00 4.05 0.65 2.63
VIGA 1V-4 EJE 5 1.00 5.95 0.65 3.87
VIGA 1V-4 EJE E 1.00 1.75 0.65 1.14
VIGA 1V-6 EJE 7 Y 8 2.00 4.73 0.65 6.14
VIGA 1V-6 EJE 9 1.00 10.00 0.65 6.50
VIGA 1V-7 EJE C 1.00 2.70 0.65 1.76
VIGA V-101 1.00 8.25 1.05 8.66
VIGA V-102 EJE A Y B 2.00 8.70 1.05 18.27
2DO NIVEL 142.05
3ER NIVEL 142.05
4TO NIVEL 142.05
PARAPETO AZOTEA 23.10
VIGA VA-2 2.00 92.40 0.125 23.10
04.05.03 VIGAS - ACERO Fy= 4200 KG/CM2 7,412.00 KG
1ER A 4TO NIVEL 4.00 1,853.00 7,412.00
DIMENSIONES
ITEM Descripción N° de veces Parcial Total Unidad
Largo Ancho Alto
ENTRE EJE 9 Y A-B 1.00 4.725 0.20 0.09 0.08
ENTRE EJE 9 Y C-E 1.00 4.525 0.20 0.09 0.08
2DO NIVEL 11.66
3ER NIVEL 11.66
4TO NIVEL 11.66
04.06.02 ENCOFRADO Y DESENCOFRADO EN LOSAS ALIGERADAS - 1ER NIVEL 530.17 M2
1ER NIVEL 132.54
ENTRE EJE 1-2 Y A-B 1.00 2.90 2.50 7.25
1.00 2.75 1.10 3.03
ENTRE EJE 1-2 Y C-E 1.00 3.575 2.75 9.83
ENTRE EJE 2-3 Y A-B 1.00 1.90 1.20 2.28
ENTRE EJE 3-4 Y A-B 1.00 2.95 1.10 3.25
ENTRE EJE 2-4 Y B-C 1.00 1.35 0.45 0.61
1.00 2.70 2.25 6.08
ENTRE EJE 2-4 Y C-E 1.00 3.80 3.55 13.49
ENTRE EJE 4-5 Y A-B 1.00 2.95 2.56 7.55
ENTRE EJE 4-5 Y B-C 1.00 2.56 2.25 5.76
ENTRE EJE 4-5 Y C-D 1.00 1.75 1.00 1.75
ENTRE EJE 6-7 Y A-B 1.00 4.725 3.00 14.18
ENTRE EJE 6-7 Y C-D 1.00 1.70 1.625 2.76
ENTRE EJE 6-7 Y C-E 1.00 4.525 1.025 4.64
ENTRE EJE 7 Y A-B 1.00 4.725 0.70 3.31
ENTRE EJE 8 Y A-B 1.00 4.15 1.20 4.98
ENTRE EJE 8-9 Y A-B 1.00 4.725 2.975 14.06
ENTRE EJE 7-9 Y C-E 1.00 5.725 4.525 25.91
ENTRE EJE 9 Y A-B 1.00 4.725 0.20 0.95
ENTRE EJE 9 Y C-E 1.00 4.525 0.20 0.91
2DO NIVEL 132.54
3ER NIVEL 132.54
4TO NIVEL 132.54
04.06.03 LOSAS ALIGERADAS - ACERO Fy=4200 KG/CM2 2,848.00 KG
1ER A 4TO NIVEL 4.00 712.00 2,848.00
04.06.04 LOSAS ALIGERADAS - LADRILLO HUECO 15X30X30 cm. - 1ER NIVEL 4,376.00 UND
1ER NIVEL FACTOR 1,094.00
ENTRE EJE 1-2 Y A-B 1.00 2.90 2.50 8.25 59.81
1.00 2.75 1.10 8.25 24.96
ENTRE EJE 1-2 Y C-E 1.00 3.575 2.75 8.25 81.11
ENTRE EJE 2-3 Y A-B 1.00 1.90 1.20 8.25 18.81
ENTRE EJE 3-4 Y A-B 1.00 2.95 1.10 8.25 26.77
ENTRE EJE 2-4 Y B-C 1.00 1.35 0.45 8.25 5.01
1.00 2.70 2.25 8.25 50.12
ENTRE EJE 2-4 Y C-E 1.00 3.80 3.55 8.25 111.29
ENTRE EJE 4-5 Y A-B 1.00 2.95 2.56 8.25 62.30
ENTRE EJE 4-5 Y B-C 1.00 2.56 2.25 8.25 47.52
ENTRE EJE 4-5 Y C-D 1.00 1.75 1.00 8.25 14.44
ENTRE EJE 6-7 Y A-B 1.00 4.725 3.00 8.25 116.94
ENTRE EJE 6-7 Y C-D 1.00 1.70 1.625 8.25 22.79
ENTRE EJE 6-7 Y C-E 1.00 4.525 1.025 8.25 38.26
ENTRE EJE 7 Y A-B 1.00 4.725 0.70 8.25 27.29
ENTRE EJE 8 Y A-B 1.00 4.15 1.20 8.25 41.09
ENTRE EJE 8-9 Y A-B 1.00 4.725 2.975 8.25 115.97
ENTRE EJE 7-9 Y C-E 1.00 5.725 4.525 8.25 213.72
ENTRE EJE 9 Y A-B 1.00 4.725 0.20 8.25 7.80
ENTRE EJE 9 Y C-E 1.00 4.525 0.20 8.25 7.47
2DO NIVEL 1,094.00
3ER NIVEL 1,094.00
4TO NIVEL 1,094.00
04.07 ESCALERAS
04.07.01 CONCRETO EN ESCALERAS F'C=210 KG/CM2 5.62 M3
1ER NIVEL 1.29
GARGANTA ESCALERA TRAMO 1 1.00 2.00 1.00 0.15 0.30
PLANILLA DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial Total Unidad
Largo Ancho Alto
GARGANTA ESCALERA TRAMO 2 1.00 2.45 1.00 0.15 0.37
ESCALERA PELDAÑOS TRAMO 1 8.00 1.00 0.25 0.175 0.18
ESCALERA PELDAÑOS TRAMO 2 8.00 1.00 0.25 0.175 0.18
ESCALERA DESCANSO TRAMO 1 1.00 1.20 1.00 0.15 0.09
ESCALERA DESCANSO TRAMO 2 2.00 1.20 1.00 0.15 0.18
2DO A 4TO NIVEL 4.34
GARGANTA ESCALERA TRAMO 1 3.00 2.45 1.00 0.15 1.10
GARGANTA ESCALERA TRAMO 2 3.00 2.45 1.00 0.15 1.10
ESCALERA PELDAÑOS TRAMO 1 24.00 1.00 0.25 0.175 0.53
ESCALERA PELDAÑOS TRAMO 2 24.00 1.00 0.25 0.175 0.53
ESCALERA DESCANSO TRAMO 1 6.00 1.20 1.00 0.15 0.54
ESCALERA DESCANSO TRAMO 2 6.00 1.20 1.00 0.15 0.54
04.07.02 ENCOFRADO Y DESENCOFRADO EN ESCALERAS - 1ER NIVEL 39.50 M2
1ER NIVEL 8.99
GARGANTA ESCALERA TRAMO 1 1.00 2.00 1.00 2.00
GARGANTA ESCALERA TRAMO 2 1.00 2.45 1.00 2.45
CARA LATERAL ESCALERA TRAMO 1 1.00 2.00 0.30 0.60
CARA LATERAL ESCALERA TRAMO 2 1.00 2.45 0.30 0.74
ESCALERA PELDAÑOS TRAMO 1 8.00 1.00 0.175 0.70
ESCALERA PELDAÑOS TRAMO 2 8.00 1.00 0.175 0.70
ESCALERA DESCANSO TRAMO 1 1.00 1.20 1.00 0.60
ESCALERA DESCANSO TRAMO 2 2.00 1.20 1.00 1.20
2DO A 4TO NIVEL 30.51
GARGANTA ESCALERA TRAMO 1 3.00 2.45 1.00 7.35
GARGANTA ESCALERA TRAMO 2 3.00 2.45 1.00 7.35
CARA LATERAL ESCALERA TRAMO 1 3.00 2.45 0.30 2.21
CARA LATERAL ESCALERA TRAMO 2 3.00 2.45 0.30 2.21
ESCALERA PELDAÑOS TRAMO 1 24.00 1.00 0.175 2.10
ESCALERA PELDAÑOS TRAMO 2 24.00 1.00 0.175 2.10
ESCALERA DESCANSO TRAMO 1 6.00 1.20 1.00 3.60
ESCALERA DESCANSO TRAMO 2 6.00 1.20 1.00 3.60
04.07.03 ESCALERAS - ACERO Fy= 4200 KG/CM2 - 1ER NIVEL 424.00 KG
PRIMER NIVEL 1.00 424.00 424.00
DIMENSIONES
ITEM Descripción N° de veces Parcial Total Unidad
Largo Ancho Alto
EJE 9 1.00 9.50 2.70 25.65
EJE A 1.00 19.65 2.70 53.06
EJE B 1.00 17.20 2.70 46.44
EJE C 1.00 7.05 2.70 19.04
EJE D 1.00 6.30 2.70 17.01
EJE E 1.00 17.40 2.70 46.98
QUITAR AREA DE VENTANAS EJE 4-5 -1.00 1.95 1.80 -3.51
QUITAR AREA DE VENTANAS EJE 5 -1.00 2.41 1.30 -3.13
QUITAR AREA DE VENTANAS EJE 5 -1.00 2.10 1.30 -2.73
QUITAR AREA DE VENTANAS EJE 6 -1.00 2.36 1.30 -3.07
QUITAR AREA DE VENTANAS EJE 6 -1.00 1.29 1.30 -1.68
QUITAR AREA DE VENTANAS EJE 6 -1.00 2.30 1.35 -3.11
QUITAR AREA DE VENTANAS EJE 6-7 -1.00 2.75 1.30 -3.58
QUITAR AREA DE VENTANAS EJE 9 -1.00 2.25 1.50 -3.38
QUITAR AREA DE VENTANAS EJE 9 -1.00 1.10 1.50 -1.65
QUITAR AREA DE VENTANAS EJE 9 -1.00 1.50 2.20 -3.30
QUITAR AREA DE VENTANAS EJE A -1.00 1.20 0.50 -0.60
QUITAR AREA DE VENTANAS EJE B -1.00 1.50 1.80 -2.70
QUITAR AREA DE VENTANAS EJE D -1.00 3.60 1.35 -4.86
3ER NIVEL 291.78
4TO NIVEL 291.78
AZOTEA 82.53
PARAPETO 1.00 84.65 0.975 82.53
DIMENSIONES
ITEM Descripción N° de veces Parcial Total Unidad
Largo Ancho Alto
QUITAR TARRAJEO PRIMARIO BAÑO (DEP 1) -3.00 6.20 1.80 -33.48
QUITAR TARRAJEO PRIMARIO BAÑO PRINCIPAL (DEP 1) -3.00 6.30 1.80 -34.02
QUITAR TARRAJEO PRIMARIO COCINA Y LAVANDERIA (DEP 2) -3.00 12.65 1.80 -68.31
QUITAR TARRAJEO PRIMARIO BAÑO (DEP 2) -3.00 6.20 1.80 -33.48
QUITAR TARRAJEO PRIMARIO BAÑO PRINCIPAL (DEP 2) -3.00 6.65 1.80 -35.91
06.03 TARRAJEO EN EXTERIORES MEZCLA C:A 1:5 90.68 M2
FACHADA 2DO A 4TO NIVEL 3.00 9.95 2.95 88.06
PARAPETOS 1.00 9.95 1.10 10.95
QUITAR AREA DE VENTANAS EJE 9 -1.00 2.25 1.50 -3.38
QUITAR AREA DE VENTANAS EJE 9 -1.00 1.10 1.50 -1.65
QUITAR AREA DE VENTANAS EJE 9 -1.00 1.50 2.20 -3.30
06.04 TARRAJEO DE VIGAS 541.40 M2
1ER NIVEL 129.57
VIGA 1V-1 EJE 1 Y 2 2.00 10.00 0.65 13.00
VIGA 1V-1 EJE 3 1.00 3.45 0.65 2.24
VIGA 1V-1 EJE 4 1.00 5.95 0.65 3.87
VIGA 1V-1 ENTRE EJE 6 Y 7 1.00 4.525 0.65 2.94
VIGA 1V-1 EJE A 1.00 9.00 0.65 5.85
VIGA 1V-1 ENTRE EJE A Y B 1.00 5.05 0.65 3.28
VIGA 1V-1 EJE B 1.00 2.75 0.65 1.79
VIGA 1V-1 EJE C 1.00 5.35 0.65 3.48
VIGA 1V-1 EJE D 1.00 3.40 0.65 2.21
VIGA 1V-1 EJE E 1.00 6.30 0.65 4.10
VIGA 1V-2 EJE 5 1.00 4.05 1.05 4.25
VIGA 1V-2 EJE 6, 7 Y 9 3.00 10.00 1.05 31.50
VIGA 1V-2 EJE C; 5-6 1.00 2.00 1.05 2.10
VIGA 1V-4 ENTRE EJE 4 Y 5 1.00 4.05 0.65 2.63
VIGA 1V-4 EJE 5 1.00 5.95 0.65 3.87
VIGA 1V-4 EJE E 1.00 1.75 0.65 1.14
VIGA 1V-6 EJE 7 Y 8 2.00 4.73 0.65 6.14
VIGA 1V-6 EJE 9 1.00 10.00 0.65 6.50
VIGA 1V-7 EJE C 1.00 2.70 0.65 1.76
VIGA V-101 1.00 8.25 1.05 8.66
VIGA V-102 EJE A Y B 2.00 8.70 1.05 18.27
2DO NIVEL 129.57
3ER NIVEL 129.57
4TO NIVEL 129.57
PARAPETO AZOTEA 23.10
VIGA VA-2 2.00 92.40 0.125 23.10
06.05 VESTIDURA DE DERRAMES EN VANOS MEZCLA 1:5 311.49 M
PRIMER NIVEL 39.36
VENTANAS EJE 4-5 1.00 1.95 1.80 5.55
VENTANAS EJE 5 1.00 2.70 1.30 5.30
VENTANAS EJE 5 1.00 1.61 1.30 4.21
VENTANAS EJE A 1.00 1.20 0.50 2.20
VENTANAS EJE B 1.00 1.50 1.80 5.10
PUERTAS 1.00 11.00 3.00 17.00
2DO A 4TO NIVEL 272.13
VENTANAS EJE 4-5 3.00 1.95 1.80 16.65
VENTANAS EJE 5 3.00 2.41 1.30 15.03
VENTANAS EJE 5 3.00 2.10 1.30 14.10
VENTANAS EJE 6 3.00 2.36 1.30 14.88
VENTANAS EJE 6 3.00 1.29 1.30 11.67
VENTANAS EJE 6 3.00 2.30 1.35 15.00
VENTANAS EJE 6-7 3.00 2.75 1.30 16.05
VENTANAS EJE 9 3.00 2.25 1.50 15.75
VENTANAS EJE 9 3.00 1.10 1.50 12.30
VENTANAS EJE 9 3.00 1.50 2.20 17.70
VENTANAS EJE A 3.00 1.20 0.50 6.60
VENTANAS EJE B 3.00 1.50 1.80 15.30
VENTANAS EJE D 3.00 3.60 1.35 18.90
PUERTAS 3.00 22.00 2.70 82.20
PLANILLA DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial Total Unidad
Largo Ancho Alto
06.06 TARRAJEO EN GRADERIAS 39.50 M2
1ER NIVEL 8.99
GARGANTA ESCALERA TRAMO 1 1.00 2.00 1.00 2.00
GARGANTA ESCALERA TRAMO 2 1.00 2.45 1.00 2.45
CARA LATERAL ESCALERA TRAMO 1 1.00 2.00 0.30 0.60
CARA LATERAL ESCALERA TRAMO 2 1.00 2.45 0.30 0.74
ESCALERA PELDAÑOS TRAMO 1 8.00 1.00 0.175 0.70
ESCALERA PELDAÑOS TRAMO 2 8.00 1.00 0.175 0.70
ESCALERA DESCANSO TRAMO 1 1.00 1.20 1.00 0.60
ESCALERA DESCANSO TRAMO 2 2.00 1.20 1.00 1.20
2DO A 4TO NIVEL 30.51
GARGANTA ESCALERA TRAMO 1 3.00 2.45 1.00 7.35
GARGANTA ESCALERA TRAMO 2 3.00 2.45 1.00 7.35
CARA LATERAL ESCALERA TRAMO 1 3.00 2.45 0.30 2.21
CARA LATERAL ESCALERA TRAMO 2 3.00 2.45 0.30 2.21
ESCALERA PELDAÑOS TRAMO 1 24.00 1.00 0.175 2.10
ESCALERA PELDAÑOS TRAMO 2 24.00 1.00 0.175 2.10
ESCALERA DESCANSO TRAMO 1 6.00 1.20 1.00 3.60
ESCALERA DESCANSO TRAMO 2 6.00 1.20 1.00 3.60
07 CIELORRASOS
07.01 CIELORRASOS CON MEZCLA DE CEMENTO-ARENA 1:5 530.17 M2
1ER NIVEL 132.54
ENTRE EJE 1-2 Y A-B 1.00 2.90 2.50 7.25
1.00 2.75 1.10 3.03
ENTRE EJE 1-2 Y C-E 1.00 3.575 2.75 9.83
ENTRE EJE 2-3 Y A-B 1.00 1.90 1.20 2.28
ENTRE EJE 3-4 Y A-B 1.00 2.95 1.10 3.25
ENTRE EJE 2-4 Y B-C 1.00 1.35 0.45 0.61
1.00 2.70 2.25 6.08
ENTRE EJE 2-4 Y C-E 1.00 3.80 3.55 13.49
ENTRE EJE 4-5 Y A-B 1.00 2.95 2.56 7.55
ENTRE EJE 4-5 Y B-C 1.00 2.56 2.25 5.76
ENTRE EJE 4-5 Y C-D 1.00 1.75 1.00 1.75
ENTRE EJE 6-7 Y A-B 1.00 4.725 3.00 14.18
ENTRE EJE 6-7 Y C-D 1.00 1.70 1.625 2.76
ENTRE EJE 6-7 Y C-E 1.00 4.525 1.025 4.64
ENTRE EJE 7 Y A-B 1.00 4.725 0.70 3.31
ENTRE EJE 8 Y A-B 1.00 4.15 1.20 4.98
ENTRE EJE 8-9 Y A-B 1.00 4.725 2.975 14.06
ENTRE EJE 7-9 Y C-E 1.00 5.725 4.525 25.91
ENTRE EJE 9 Y A-B 1.00 4.725 0.20 0.95
ENTRE EJE 9 Y C-E 1.00 4.525 0.20 0.91
2DO NIVEL 132.54
3ER NIVEL 132.54
4TO NIVEL 132.54
08 PISOS Y PAVIMENTOS
08.01 FALSO PISO
08.01.01 FALSOPISO MEZCLA 1:8 C-H E=4" 178.80 M2
PRIMER PISO 1.00 AREA= 178.80 178.80
08.02 CONTRAPISO
08.02.01 CONTRAPISO DE 40 MM 452.25 M2
2DO, 3ER Y 4TO PISO 3.00 AREA= 150.75 452.25
09 INSTALACIONES SANITARIAS
09.01 SISTEMA DE DRENAJE PLUVIAL
09.01.01 TUBERIA PVC-SAL 2" 61.65 M
AZOTEA 1.00 12.65 12.65
BAJADA DE LLUVIA 4.00 12.25 49.00
09.02 DESAGÜE Y VENTILACION
09.02.01 EXCAVACION DE ZANJAS 48.00 M
PLANILLA DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial Total Unidad
Largo Ancho Alto
PRIMER NIVEL 1.00 48.00 48.00
09.02.02 SALIDA DE DESAGUE PVC SAL 2" 28.00 PTO
PRIMER NIVEL 1.00 4.00 4.00
SEGUNDO A CUARTO NIVEL 3.00 8.00 24.00
09.02.03 SALIDA DE DESAGUE PVC SAL 4" 14.00 PTO
PRIMER NIVEL 1.00 2.00 2.00
SEGUNDO A CUARTO NIVEL 3.00 4.00 12.00
09.02.04 SALIDA DE VENTILACION PVC 2" 6.00 6.00 6.00 PTO
09.02.05 TUBERIA PVC-SAL 2" PARA DESAGÜE 60.45 M
PRIMER NIVEL 1.00 12.00 12.00
SEGUNDO A CUARTO NIVEL 3.00 16.15 48.45
09.02.06 TUBERIA PVC-SAL 4" PARA DESAGÜE 74.45 M
PRIMER NIVEL 1.00 27.80 27.80
SEGUNDO A CUARTO NIVEL 3.00 15.55 46.65
09.02.06 TUBERIA PVC-SAL 6" PARA DESAGÜE 53.75 M
PRIMER NIVEL 1.00 36.05 36.05
SEGUNDO A CUARTO NIVEL 3.00 5.90 17.70
09.02.07 SOMBRERO VENTILACIÓN DE PVC DE 2" 6.00 6.00 6.00 UND
09.02.08 SUMIDERO DE 2" 42.00 UND
PRIMER NIVEL 1.00 6.00 6.00
SEGUNDO A CUARTO NIVEL 3.00 12.00 36.00
09.02.09 REGISTRO ROSCADO DE BRONCE DE 4" 14.00 UND
PRIMER NIVEL 1.00 2.00 2.00
SEGUNDO A CUARTO NIVEL 3.00 4.00 12.00
09.02.10 CAJA DE REGISTRO 3.00 3.00 3.00 UND
09.03 SISTEMA DE AGUA FRIA
09.03.01 EXCAVACION DE ZANJAS RED DE AGUA 119.00 M
PRIMER NIVEL 1.00 119.00 119.00
09.03.02 SALIDA DE AGUA FRIA PVC-SAP 1/2" 56.00 PTO
PRIMER NIVEL 1.00 8.00 8.00
SEGUNDO A CUARTO NIVEL 3.00 16.00 48.00
09.03.03 TUBERIA DE PVC CLASE 10 DE 1/2" 144.55 M
PRIMER NIVEL 1.00 20.05 20.05
SEGUNDO A CUARTO NIVEL 3.00 41.50 124.50
09.03.04 TUBERIA DE PVC CLASE 10 DE 3/4" 145.95 M
AZOTEA 1.00 60.20 60.20
MONTANTE 7.00 12.25 85.75
09.03.04 TUBERIA DE PVC CLASE 10 DE 1" 184.75 M
PRIMER NIVEL 1.00 99.00 99.00
MONTANTE 7.00 12.25 85.75
09.03.05 VALVULA COMPUERTA DE BRONCE DE 1/2" 28.00 UND
PRIMER NIVEL 1.00 4.00 4.00
SEGUNDO A CUARTO NIVEL 3.00 8.00 24.00
09.03.06 CAJA PARA VALVULA (NICHO DE MAYOLICA) 28.00 UND
PRIMER NIVEL 1.00 4.00 4.00
SEGUNDO A CUARTO NIVEL 3.00 8.00 24.00
09.03 SISTEMA DE AGUA CALIENTE
09.03.01 EXCAVACION DE ZANJAS RED DE AGUA 20.40 M
PRIMER NIVEL 1.00 20.40 20.40
09.03.02 SALIDA DE AGUA CALIENTE PVC-SAP 1/2" 35.00 PTO
PRIMER NIVEL 1.00 5.00 5.00
SEGUNDO A CUARTO NIVEL 3.00 10.00 30.00
09.03.03 TUBERIA DE PVC H3 DE 1/2" 238.85 M
PRIMER NIVEL 1.00 20.40 20.40
SEGUNDO A CUARTO NIVEL 3.00 38.40 115.20
AZOTEA 1.00 17.50 17.50
MONTANTE 7.00 12.25 85.75
09.03.05 VALVULA COMPUERTA DE BRONCE DE 1/2" 21.00 UND
PRIMER NIVEL 1.00 3.00 3.00
SEGUNDO A CUARTO NIVEL 3.00 6.00 18.00
09.03.06 CAJA PARA VALVULA 21.00 UND
PRIMER NIVEL 1.00 3.00 3.00
PLANILLA DE METRADOS
PROYECTO: VIVIENDA MULTIFAMILIAR
DIMENSIONES
ITEM Descripción N° de veces Parcial Total Unidad
Largo Ancho Alto
SEGUNDO A CUARTO NIVEL 3.00 6.00 18.00
10 INSTALACIONES ELECTRICAS
10.01 SALIDAS
10.01.01 SALIDA DE TECHO PARA CENTROS DE LUZ 72.00 PTO
PRIMER NIVEL 1.00 15.00 15.00
SEGUNDO A CUARTO NIVEL 3.00 19.00 57.00
10.01.02 SALIDA DE TECHO PARA SPOTLIGHT 90.00 PTO
PRIMER NIVEL 1.00 18.00 18.00
SEGUNDO A CUARTO NIVEL 3.00 24.00 72.00
10.01.03 SALIDA PARA LUZ EN PARED 25.00 PTO
PRIMER NIVEL 1.00 4.00 4.00
SEGUNDO A CUARTO NIVEL 3.00 7.00 21.00
10.01.04 SALIDA PARA INTERRUPTORES 89.00 PTO
PRIMER NIVEL 1.00 17.00 17.00
SEGUNDO A CUARTO NIVEL 3.00 24.00 72.00
10.01.05 SALIDA PARA TOMACORRIENTES 192.00 PTO
PRIMER NIVEL 1.00 27.00 27.00
SEGUNDO A CUARTO NIVEL 3.00 55.00 165.00
10.02 CANALIZACIONES Y/O TUBERIAS
10.02.01 TUBERIAS PVC SAP (ELECTRICAS) D=3/4" 718.20 M
PRIMER NIVEL 1.00 135.30 135.30
SEGUNDO A CUARTO NIVEL 3.00 194.30 582.90
10.02.02 TUBERIAS PVC SAP (ELECTRICAS) D=1" 59.60 M
PRIMER NIVEL 1.00 20.15 20.15
SEGUNDO A CUARTO NIVEL 3.00 13.15 39.45
10.03 CAJAS DE PASO
10.03.01 CAJA DE PASO CIRCULAR 4.00 2.00 8.00 8.00 UND
10.05.07 TABLEROS DISTRIBUCIÓN CAJA METALICA 4.00 4.00 4.00 PZA
11 INSTALACIONES DE COMUNICACIONES
11.01 SALIDAS
11.01.01 SALIDA PARA TELEFONO Y TV-CABLE 49.00 PTO
PRIMER NIVEL 1.00 7.00 7.00
SEGUNDO A CUARTO NIVEL 3.00 14.00 42.00
11.01.01 SALIDA PARA INTERCOMUNICADOR 8.00 PTO
PRIMER NIVEL 1.00 2.00 2.00
SEGUNDO A CUARTO NIVEL 3.00 2.00 6.00
11.02 CANALIZACIONES Y/O TUBERIAS
11.02.01 TUBERIAS PVC SAP (TELEFONO Y TV-CABLE) D=3/4" 182.40 M
PRIMER NIVEL 1.00 28.80 28.80
SEGUNDO A CUARTO NIVEL 3.00 51.20 153.60
11.02.01 TUBERIAS PVC SAP (INTERCOMUNICADOR) D=3/4" 67.20 M
PRIMER NIVEL 1.00 25.95 25.95
SEGUNDO A CUARTO NIVEL 3.00 13.75 41.25
11.03 CAJAS DE PASO
11.03.01 CAJA DE PASO DE 200x200x150 FºGº 1.00 19.00 19.00 19.00 UND
12 LIMPIEZA FINAL
12.01 LIMPIEZA FINAL DE OBRA 1.00 20.00 10.00 200.00 200.00 M2
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø N° BARRAS 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
VECES BARRA
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
04.01 ZAPATAS
04.01.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
ZAPATA 1
ACERO LONG. 5/8 3.00 10.00 1.70 51.00
ACERO TRANSV. 5/8 3.00 10.00 1.70 51.00
ZAPATA 2
ACERO LONG. 5/8 3.00 11.00 2.55 84.15
ACERO TRANSV. 5/8 3.00 15.00 1.85 83.25
ZAPATA 3
ACERO LONG. 5/8 1.00 17.00 2.85 48.45
ACERO TRANSV. 5/8 1.00 17.00 2.85 48.45
ZAPATA 4
ACERO LONG. 5/8 2.00 6.00 1.45 17.40
ACERO TRANSV. 5/8 2.00 9.00 1.05 18.90
ZAPATA 5
ACERO LONG. 5/8 7.00 6.00 1.05 44.10
ACERO TRANSV. 5/8 7.00 6.00 1.05 44.10
ZAPATA 6
ACERO LONG. 5/8 5.00 5.00 0.85 21.25
ACERO TRANSV. 5/8 5.00 5.00 0.85 21.25
ZAPATA 7
ACERO LONG. 5/8 1.00 5.00 1.05 5.25
ACERO TRANSV. 5/8 1.00 6.00 0.85 5.10
ZAPATA 8
ACERO LONG. 5/8 1.00 7.00 1.35 9.45
ACERO TRANSV. 5/8 1.00 8.00 1.15 9.20
ZAPATA 9
ACERO LONG. 5/8 3.00 7.00 1.15 24.15
ACERO TRANSV. 5/8 3.00 7.00 1.15 24.15
ZAPATA 10
ACERO LONG. 5/8 3.00 5.00 0.80 12.00
ACERO TRANSV. 5/8 3.00 7.00 1.10 23.10
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø
VECES
N° BARRAS
BARRA 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø N° BARRAS 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
VECES BARRA
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
04.02 VIGAS DE CIMENTACION
04.02.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
VC1 EJE 6
ACERO LONG. SUPERIOR CORR 3/4 1.00 3.00 4.775 14.33
ACERO LONG. NEGATIVO 3/4 1.00 1.00 2.35 2.35
ACERO LONG. NEGATIVO 3/4 2.00 2.00 1.80 7.20
ACERO LONG. NEGATIVO 5/8 2.00 1.00 1.80 3.60
ACERO LONG. INTERMEDIO 5/8 1.00 2.00 4.175 8.35
ACERO LONG. INFERIOR CORR 3/4 1.00 2.00 4.775 9.55
ESTRIBOS 3/8 1.00 24.00 1.80 43.20
VC1 EJE 7
ACERO LONG. SUPERIOR CORR 3/4 2.00 3.00 4.775 28.65
ACERO LONG. NEGATIVO 3/4 2.00 1.00 2.35 4.70
ACERO LONG. NEGATIVO 3/4 4.00 2.00 1.80 14.40
ACERO LONG. NEGATIVO 5/8 4.00 1.00 1.80 7.20
ACERO LONG. INTERMEDIO 5/8 2.00 2.00 4.175 16.70
ACERO LONG. INFERIOR CORR 3/4 2.00 2.00 4.775 19.10
ESTRIBOS 3/8 2.00 48.00 1.80 172.80
VC1 EJE 9
ACERO LONG. SUPERIOR CORR 3/4 2.00 3.00 4.775 28.65
ACERO LONG. NEGATIVO 3/4 2.00 1.00 2.35 4.70
ACERO LONG. NEGATIVO 3/4 4.00 2.00 1.80 14.40
ACERO LONG. NEGATIVO 5/8 4.00 1.00 1.80 7.20
ACERO LONG. INTERMEDIO 5/8 2.00 2.00 4.175 16.70
ACERO LONG. INFERIOR CORR 3/4 2.00 2.00 4.775 19.10
ESTRIBOS 3/8 2.00 48.00 1.80 172.80
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø N° BARRAS 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
VECES BARRA
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
04.03 SOBRECIMIENTO ARMADO
04.03.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
SCA-1 EJE 2
ACERO LONG 5/8 1.00 4.00 5.90
ESTRIBOS 3/8 1.00 50.00 1.00 50.00
SCA-1 EJE 3
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø N° BARRAS 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
VECES BARRA
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
ACERO LONG 5/8 1.00 4.00 2.45
ESTRIBOS 3/8 1.00 17.00 1.00 17.00
SCA-1 EJE 4
ACERO LONG 5/8 1.00 4.00 2.80
ESTRIBOS 3/8 1.00 24.00 1.00 24.00
SCA-1 EJE 4-5
ACERO LONG 5/8 1.00 4.00 1.95
ESTRIBOS 3/8 1.00 22.00 1.00 22.00
SCA-1 EJE 5
ACERO LONG 5/8 1.00 4.00 4.80
ESTRIBOS 3/8 1.00 56.00 1.00 56.00
SCA-1 EJE 6
ACERO LONG 5/8 1.00 4.00 2.30
ESTRIBOS 3/8 1.00 16.00 1.00 16.00
SCA-1 EJE A-B
ACERO LONG 5/8 1.00 4.00 2.45
ESTRIBOS 3/8 1.00 17.00 1.00 17.00
SCA-1 EJE C
ACERO LONG 5/8 1.00 4.00 2.00
ESTRIBOS 3/8 1.00 17.00 1.00 17.00
SCA-2 EJE 1
ACERO LONG 5/8 1.00 4.00 8.25
ESTRIBOS 3/8 1.00 59.00 1.00 59.00
SCA-2 EJE A
ACERO LONG 5/8 1.00 4.00 14.95
ESTRIBOS 3/8 1.00 101.00 1.00 101.00
SCA-2 EJE E
ACERO LONG 5/8 1.00 4.00 14.85
ESTRIBOS 3/8 1.00 96.00 1.00 96.00
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø N° BARRAS 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
VECES BARRA
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
04.04 COLUMNAS
04.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
T1
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø N° BARRAS 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
VECES BARRA
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
ACERO VERTICAL 3/8 54.00 4.00 3.40 734.40
ESTRIBOS 1/4 54.00 18.00 0.80 777.60
T2
ACERO VERTICAL 3/8 31.00 4.00 1.52 188.48
ESTRIBOS 6mm 31.00 5.00 0.80 124.00
C1
ACERO VERTICAL 5/8 9.00 4.00 14.45 520.20
ACERO VERTICAL 3/4 9.00 4.00 14.45 520.20
ESTRIBOS 3/8 9.00 76.00 1.80 1,231.20
C2
ACERO VERTICAL 5/8 2.00 4.00 14.45 115.60
ESTRIBOS 3/8 2.00 80.00 1.00 160.00
C3
ACERO VERTICAL 1/2 11.00 4.00 14.45 635.80
ACERO VERTICAL 5/8 11.00 4.00 14.45 635.80
ESTRIBOS 1/4 11.00 88.00 1.60 1,548.80
C4
ACERO VERTICAL 3/8 1.00 6.00 14.45 86.70
ACERO VERTICAL 1/2 1.00 4.00 14.45 57.80
ESTRIBOS 1/4 1.00 80.00 1.55 124.00
C5
ACERO VERTICAL 1/2 9.00 6.00 14.45 780.30
ESTRIBOS 1/4 9.00 88.00 0.90 712.80
C6
ACERO VERTICAL 5/8 1.00 6.00 14.45 86.70
ESTRIBOS 3/8 1.00 80.00 1.30 104.00
C7
ACERO VERTICAL 1/2 1.00 4.00 14.45 57.80
ACERO VERTICAL 5/8 1.00 4.00 14.45 57.80
ESTRIBOS 1/4 1.00 80.00 1.45 116.00
C8
ACERO VERTICAL 1/2 1.00 6.00 14.45 86.70
ACERO VERTICAL 5/8 1.00 4.00 14.45 57.80
ESTRIBOS 1/4 1.00 80.00 1.90 152.00
C9
ACERO VERTICAL 1/2 1.00 6.00 14.45 86.70
ESTRIBOS 1/4 1.00 88.00 1.20 105.60
C10
ACERO VERTICAL 1/2 1.00 7.00 14.45 101.15
ESTRIBOS 1/4 1.00 88.00 1.40 123.20
C11
ACERO VERTICAL 3/8 4.00 4.00 14.45 231.20
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø N° BARRAS 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
VECES BARRA
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
ESTRIBOS 1/4 4.00 28.00 0.80 89.60
C12
ACERO VERTICAL 1/2 1.00 4.00 14.45 57.80
ACERO VERTICAL 5/8 1.00 4.00 14.45 57.80
ESTRIBOS 3/8 1.00 26.00 1.20 31.20
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø
VECES
N° BARRAS
BARRA
6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
04.05 VIGAS
04.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
NIVEL TIPICO
VIGA VA
ACERO LONG 1/2 1.00 4.00 32.80 131.20
ESTRIBOS 6mm 1.00 284.00 0.70 198.80
VIGA VA-2 PARAPETO AZOTEA
ACERO LONG 5/8 1.00 2.00 92.40 184.80
VIGA 1V-1 EJE 1 Y 2
ACERO LONG 1/2 2.00 4.00 10.30 82.40
ESTRIBOS 1/4 2.00 59.00 0.90 106.20
VIGA 1V-1 EJE 3
ACERO LONG 1/2 1.00 4.00 3.75 15.00
ESTRIBOS 1/4 1.00 18.00 0.90 16.20
VIGA 1V-1 EJE 4
ACERO LONG 1/2 1.00 4.00 6.25 25.00
ESTRIBOS 1/4 1.00 36.00 0.90 32.40
VIGA 1V-1 ENTRE EJE 6 Y 7
ACERO LONG 1/2 1.00 4.00 4.83 19.30
ESTRIBOS 1/4 1.00 28.00 0.90 25.20
VIGA 1V-1 EJE B
ACERO LONG 1/2 1.00 4.00 3.05 12.20
ESTRIBOS 1/4 1.00 36.00 0.90 32.40
VIGA 1V-1 EJE C
ACERO LONG 1/2 1.00 4.00 5.65 22.60
ESTRIBOS 1/4 1.00 35.00 0.90 31.50
VIGA 1V-1 EJE D
ACERO LONG 1/2 1.00 4.00 3.70 14.80
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø N° BARRAS 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
VECES BARRA
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
ESTRIBOS 1/4 1.00 28.00 0.90 25.20
VIGA 1V-1 EJE E
ACERO LONG 1/2 1.00 4.00 6.60 26.40
ESTRIBOS 1/4 1.00 41.00 0.90 36.90
VIGA 1V-2 EJE 5
ACERO LONG 1/2 1.00 2.00 4.35 8.70
ACERO LONG 5/8 1.00 4.00 4.35 17.40
ESTRIBOS 3/8 1.00 22.00 1.30 28.60
VIGA 1V-2 EJE 6, 7 Y 9
ACERO LONG 1/2 3.00 2.00 10.30 61.80
ACERO LONG 5/8 3.00 4.00 10.30 123.60
ESTRIBOS 3/8 3.00 48.00 1.30 187.20
VIGA 1V-2 EJE C; 5-6
ACERO LONG 1/2 1.00 2.00 4.30 8.60
ACERO LONG 5/8 1.00 4.00 4.30 17.20
ESTRIBOS 3/8 1.00 14.00 1.30 18.20
VIGA 1V-4 ENTRE EJE 4 Y 5
ACERO LONG 5/8 1.00 4.00 4.35 17.40
ESTRIBOS 1/4 1.00 24.00 0.90 21.60
VIGA 1V-4 EJE 5
ACERO LONG 5/8 1.00 4.00 6.25 25.00
ESTRIBOS 1/4 1.00 35.00 0.90 31.50
VIGA 1V-4 EJE E
ACERO LONG 5/8 1.00 4.00 2.05 8.20
ESTRIBOS 1/4 1.00 28.00 0.90 25.20
VIGA 1V-6 EJE 7 Y 8
ACERO LONG 3/8 2.00 4.00 5.03 40.20
ESTRIBOS 1/4 2.00 29.00 0.80 46.40
VIGA 1V-6 EJE 9
ACERO LONG 3/8 1.00 4.00 10.30 41.20
ESTRIBOS 1/4 1.00 57.00 0.80 45.60
VIGA 1V-7 EJE C
ACERO LONG 1/2 1.00 1.00 3.00 3.00
ACERO LONG 5/8 1.00 4.00 3.00 12.00
ESTRIBOS 1/4 1.00 19.00 0.90 17.10
VIGA V-101
ACERO LONG SUPERIOR 5/8 1.00 2.00 9.30 18.60
ACERO LONG INFERIOR 5/8 1.00 2.00 9.30 18.60
ACERO LONG NEGATIVO EJE 7 5/8 1.00 2.00 2.90 5.80
ACERO LONG NEGATIVO EJE 9 5/8 1.00 2.00 1.90 3.80
ACERO LONG INTERMEDIO 5/8 1.00 2.00 8.90 17.80
ESTRIBOS 3/8 1.00 46.00 1.30 59.80
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø N° BARRAS 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
VECES BARRA
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
VIGA V-102 EJE A Y B
ACERO LONG SUPERIOR 5/8 2.00 2.00 9.30 37.20
ACERO LONG INFERIOR 5/8 2.00 2.00 9.30 37.20
ACERO LONG NEGATIVO EJE 7 5/8 2.00 2.00 2.90 11.60
ACERO LONG NEGATIVO EJE 9 5/8 2.00 2.00 1.90 7.60
ACERO LONG INTERMEDIO 5/8 2.00 2.00 8.90 35.60
ESTRIBOS 3/8 2.00 46.00 1.30 119.60
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø N° BARRAS 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
VECES BARRA
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
04.06 LOSA ALIGERADA
04.06.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
NIVEL TIPICO
ENTRE EJE 1-2
ACERO POSITIVO 1/2 1.00 7.00 8.00 56.00
ACERO NEGATIVO 3/8 1.00 7.00 1.10 7.70
ACERO NEGATIVO 1/2 3.00 7.00 1.10 23.10
ACERO TEMPERATURA 6mm 1.00 32.00 2.75 88.00
ENTRE EJE 2-3,A-B
ACERO POSITIVO 1/2 1.00 3.00 2.10 6.30
ACERO NEGATIVO 1/2 1.00 3.00 3.10 9.30
ACERO TEMPERATURA 6mm 1.00 11.00 1.20 13.20
ENTRE EJE 3-4,A-B
ACERO POSITIVO 3/8 1.00 2.00 3.40 6.80
ACERO NEGATIVO 1/2 1.00 2.00 3.10 6.20
ACERO TEMPERATURA 6mm 1.00 13.00 1.10 14.30
ENTRE EJE 2-4,B-C
ACERO POSITIVO 3/8 1.00 6.00 2.95 17.70
ACERO NEGATIVO 1/2 1.00 6.00 1.80 10.80
ACERO TEMPERATURA 6mm 1.00 11.00 2.70 29.70
ENTRE EJE 2-4,C-E
ACERO POSITIVO 1/2 1.00 8.00 4.65 37.20
ACERO NEGATIVO 1/2 1.00 8.00 1.05 8.40
ACERO TEMPERATURA 6mm 1.00 18.00 3.55 63.90
ENTRE EJE 4-5,A-C
ACERO POSITIVO 3/8 1.00 6.00 5.90 35.40
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø N° BARRAS 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
VECES BARRA
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
ACERO NEGATIVO 3/8 1.00 6.00 2.00 12.00
ACERO NEGATIVO 1/2 1.00 6.00 1.05 6.30
ACERO TEMPERATURA 6mm 1.00 23.00 2.60 59.80
ENTRE EJE 4-5,C-D
ACERO POSITIVO 3/8 1.00 4.00 1.10 4.40
ACERO NEGATIVO 3/8 1.00 4.00 2.20 8.80
ACERO TEMPERATURA 6mm 1.00 4.00 1.75 7.00
ENTRE EJE 6-7,A-B
ACERO POSITIVO 3/8 1.00 8.00 3.15 25.20
ACERO POSITIVO 1/2 1.00 8.00 5.20 41.60
ACERO NEGATIVO 3/8 1.00 8.00 1.05 8.40
ACERO TEMPERATURA 6mm 1.00 12.00 3.00 36.00
ENTRE EJE 6-6',B-E
ACERO POSITIVO 1/2 1.00 4.00 1.80 7.20
ACERO NEGATIVO 3/8 1.00 4.00 2.25 9.00
ACERO NEGATIVO 1/2 1.00 4.00 3.85 15.40
ACERO TEMPERATURA 6mm 1.00 7.00 3.00 21.00
ENTRE EJE 6'-7,B-E
ACERO POSITIVO 1/2 1.00 2.00 4.75 9.50
ACERO NEGATIVO 3/8 1.00 2.00 1.30 2.60
ACERO NEGATIVO 1/2 1.00 2.00 1.85 3.70
ACERO TEMPERATURA 6mm 1.00 19.00 1.05 19.95
ENTRE EJE 7-8,A-B
ACERO POSITIVO 3/8 1.00 5.00 3.15 15.75
ACERO POSITIVO 1/2 1.00 5.00 5.20 26.00
ACERO NEGATIVO 3/8 1.00 5.00 1.30 6.50
ACERO NEGATIVO 1/2 1.00 5.00 2.25 11.25
ACERO NEGATIVO 1/2 1.00 5.00 3.50 17.50
ACERO TEMPERATURA 6mm 1.00 20.00 2.10 42.00
ENTRE EJE 8-9,A-B
ACERO POSITIVO 3/8 1.00 7.00 3.15 22.05
ACERO POSITIVO 1/2 1.00 7.00 5.20 36.40
ACERO NEGATIVO 3/8 1.00 7.00 1.30 9.10
ACERO NEGATIVO 1/2 1.00 7.00 2.25 15.75
ACERO NEGATIVO 1/2 1.00 7.00 3.50 24.50
ACERO TEMPERATURA 6mm 1.00 20.00 2.10 42.00
ENTRE EJE 7-9,B-E
ACERO POSITIVO 3/8 1.00 14.00 3.00 42.00
ACERO POSITIVO 1/2 1.00 14.00 4.75 66.50
ACERO NEGATIVO 3/8 1.00 14.00 1.30 18.20
ACERO TEMPERATURA 6mm 1.00 19.00 5.30 100.70
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø N° BARRAS 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
VECES BARRA
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
Longitud (m) 537.55 - - 251.60 438.90 - - -
Peso (Kg/m) 0.22 0.25 0.40 0.58 1.02 1.60 2.26 4.00
Peso (Kg) 118.26 - - 145.93 447.68 - -
TOTAL (kg) 712.00
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø N° BARRAS 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
VECES BARRA
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
04.07 ESCALERA
04.07.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
PRIMER NIVEL
TRAMO 1
ACERO INFERIOR 1/2 1.00 5.00 1.65 8.25
ACERO INFERIOR 1/2 1.00 5.00 1.45 7.25
ACERO GARGANTA 3/8 1.00 5.00 2.80 14.00
ACERO GARGANTA 3/8 1.00 5.00 1.25 6.25
ACERO GARGANTA 3/8 1.00 5.00 1.00 5.00
ACERO TEMP. INCLINADO 3/8 1.00 15.00 1.00 15.00
ACERO TEMP. DESCANSO 3/8 1.00 9.00 1.00 9.00
TRAMO 2
ACERO INFERIOR 3/8 1.00 5.00 2.10 10.50
ACERO INFERIOR 3/8 1.00 5.00 1.25 6.25
ACERO GARGANTA 3/8 1.00 5.00 4.50 22.50
ACERO SUPERIOR 3/8 1.00 5.00 1.95 9.75
ACERO SUPERIOR 3/8 1.00 5.00 2.30 11.50
ACERO TEMP. INCLINADO 3/8 1.00 12.00 1.00 12.00
ACERO TEMP. DESCANSO 3/8 1.00 9.00 1.00 9.00
ACERO TEMP. DESCANSO 3/8 1.00 12.00 1.00 12.00
2DO A 4TO NIVEL
TRAMO 1
ACERO INFERIOR 3/8 3.00 5.00 2.10 31.50
ACERO INFERIOR 3/8 3.00 5.00 1.25 18.75
ACERO GARGANTA 3/8 3.00 5.00 4.50 67.50
ACERO SUPERIOR 3/8 3.00 5.00 1.95 29.25
ACERO SUPERIOR 3/8 3.00 5.00 2.30 34.50
ACERO TEMP. INCLINADO 3/8 3.00 12.00 1.00 36.00
ACERO TEMP. DESCANSO 3/8 3.00 9.00 1.00 27.00
ACERO TEMP. DESCANSO 3/8 3.00 12.00 1.00 36.00
TRAMO 2
ACERO INFERIOR 3/8 3.00 5.00 2.10 31.50
ACERO INFERIOR 3/8 3.00 5.00 1.25 18.75
ACERO GARGANTA 3/8 3.00 5.00 4.50 67.50
LONGITUD X DIAMETRO
N° LONG.
PARTIDA ELEMENTO - DESCRIPCION Ø N° BARRAS 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1
VECES BARRA
Ø6mm Ø1/4" Ø8mm Ø3/8" Ø1/2" Ø5/8" Ø3/4" Ø1"
ACERO SUPERIOR 3/8 3.00 5.00 1.95 29.25
ACERO SUPERIOR 3/8 3.00 5.00 2.30 34.50
ACERO TEMP. INCLINADO 3/8 3.00 12.00 1.00 36.00
ACERO TEMP. DESCANSO 3/8 3.00 9.00 1.00 27.00
ACERO TEMP. DESCANSO 3/8 3.00 12.00 1.00 36.00