Está en la página 1de 8

$250,000

EVM ACCESO SUR

$200,000

$150,000
Actual Cost AC
COSTO

Plan Value PV
Earn Value EV
$100,000

$50,000

$0

44412

44413

44414

44415

44419

44420

44421

44422
44410

44411

44416

44417

44418
ES= 7.97 DIAS PROGRAMADOS 11
AT= 3.00 ETC(t)= 1.14 DIAS Finalizacion con variaciones atipicas 16.00 19/08
SV(t)= ES-AT 4.97 Días de adelanto EAC(t)= 4.14 DIAS Finalizacion con SPI ACTUAL 4.00 05/08
SPI(t)= 2.66 0.00

Variación del
Tiempo Plan Value Earn Value EV cronograma SPI(t) DIA SPI(t) Acum
PV
SV= EV-PV SPI(t) SPI(t) DIA
SPI(t) Acum
02/08 3000.063297 7000 3999.9 2.33 2.33
03/08 6000.126595 16901.034475 10900.9 3.30 2.82
04/08 9000.189892 23901.034475 14900.8 2.33 2.66
05/08 12000.25319 -12000.3
06/08 15000.31649 -15000.3
07/08 18000.37978 -18000.4
09/08 21000.44308 -21000.4
10/08 24000.50638 -24000.5
11/08 27000.56968 -27000.6
12/08 30000.63297 -30000.6
13/08 33000.69627 -33000.7
0 0 0 0 0 0 22 : 20AGO -8 AGO
SEMANA 0 1 1 1 1 1 1
Tramos 2 3 4 5 6 7 8
FRENTE ejecutados % Cum.
programa D N D N D N D N D N
Acceso Sur 6 0 0%

Programado por dia 1 1 1 1 1 1 0


Ejecutado por dia 0 0 0 0 0 0
% cumplimiento por dia 0% 0% 0% 0% 0% 0%
CRONOGRAMA INICIAL
Name Tp Comienzo Fin
ACCESO SUR 50 days Thu 17/06/21 Tue 17/08/21
Excavacion y Fase 1 y 2 20 days Sat 19/06/21 Tue 13/07/21 1.25 12
Demolicion Micropilotes + Muro forro 8 days Wed 14/07/21 Thu 22/07/21 7.5 13
Impermeabilizacion y Fase 3 10 days Fri 23/07/21 Thu 05/08/21
Hormigonado de solera 10 days Fri 06/08/21 Tue 17/08/21

FRENTE TRAMOS FALTANTES % Com. 8/2/2021 8/3/2021


D N D
Acceso Sur 11 11 100% 1 1
Produccion x dia 1 1
Produccion Semanal

CRONOGRAMA ACTUAL
Name Tp Comienzo Fin
ACCESO SUR
Excavacion y Fase 1 y 2 24 days Sat 13/07/21 Tue 12/08/21
8/3/2021 8/4/2021 8/5/2021 8/6/2021 8/7/2021 8/9/2021 8/10/2021
N D N D N D N D N D N D
1 1 1 1 1 1
1 1 1 1 1 1 1
6
8/10/2021 8/11/2021 8/12/2021 8/13/2021 8/14/2021
N D N D N D N D N
1 1 1
1 1 1 1
5
FRENTE TRAMOS FALTANTES % Com. 8/2/2021 8/3/2021
D N D
Acceso Sur 11 11 100% 1 1
Produccion x dia 1 1
Produccion Semanal

ITEM Descripción REAL


8/2/2021 8/3/2021
D N D
Excavacion y Shotcrete Fase 1 y 2 - metrado
Excavacion 175.66 15.96915 15.96915
Lanz. Concreto Fase 1 2.28 0.20745 0.20745
Lanz. Concreto Fase 2 22.14 2.012813 2.012813
Inst. Marco Metálico 158.88 14.444 14.444

Excavacion y Shotcrete Fase 1 y 2 PU


Excavacion 43.24 690.506046 0 690.506046
Lanz. Concreto Fase 1 679.39 140.9394555 0 140.9394555
Lanz. Concreto Fase 2 516.60 1039.819196 0 1039.819196
Inst. Marco Metálico 78.15 1128.7986 0 1128.7986
3000.0632973 3000.0632973

8/2/2021 8/3/2021 8/4/2021


3000.063297 3000.063297 3000.063297

Excavacion y Shotcrete Fase 1 y 2 REAL 8/2/2021 8/3/2021 8/4/2021


Excavacion
Lanz. Concreto Fase 1
Lanz. Concreto Fase 2
Inst. Marco Metálico
TOTAL 0 0 0

3000.063297 3000.063297 3000.063297


8/3/2021 8/4/2021 8/5/2021 8/6/2021 8/7/2021
N D N D N D N D
1 1 1 1
1 1 1 1 1
6

PROGRAMA
8/3/2021 8/4/2021 8/5/2021 8/6/2021 8/7/2021
N D N D N D N D

15.96915 15.96915 15.96915 15.96915


0.20745 0.20745 0.20745 0.20745
2.012813 2.012813 2.012813 2.012813
14.444 14.444 14.444 14.444

0 690.506046 0 690.506046 0 690.506046 0 690.506046


0 140.9394555 0 140.9394555 0 140.9394555 0 140.9394555
0 1039.819196 0 1039.819196 0 1039.819196 0 1039.819196
0 1128.7986 0 1128.7986 0 1128.7986 0 1128.7986
3000.0632973 3000.0632973 3000.0632973 3000.0632973 3000.0632973

8/5/2021 8/6/2021 8/7/2021 8/9/2021 8/10/2021 8/11/2021 8/12/2021 8/13/2021


3000.063297 3000.063297 3000.063297 3000.063297 3000.063297 3000.063297 3000.063297 3000.063297

8/5/2021 8/6/2021 8/7/2021 8/9/2021 8/10/2021 8/11/2021 8/12/2021 8/13/2021

0 0 0 0 0 0 0 0

3000.063297 3000.063297 3000.063297 3000.063297 3000.063297 3000.063297 3000.063297 3000.063297


8/7/2021 8/9/2021 8/10/2021 8/11/2021 8/12/2021
N D N D N D N D
1 1 1 1
1 1 1 1 1
5

PROGRAMACION
8/7/2021 8/9/2021 8/10/2021 8/11/2021 8/12/2021
N D N D N D N D

15.96915 15.96915 15.96915 15.96915


0.20745 0.20745 0.20745 0.20745
2.012813 2.012813 2.012813 2.012813
14.444 14.444 14.444 14.444

0 690.506046 0 690.506046 0 690.506046 0 690.506046


0 140.9394555 0 140.9394555 0 140.9394555 0 140.9394555
0 1039.819196 0 1039.819196 0 1039.819196 0 1039.819196
0 1128.7986 0 1128.7986 0 1128.7986 0 1128.7986
3000.0632973 3000.0632973 3000.0632973 3000.0632973 3000.0632973

8/14/2021 8/15/2021 8/16/2021 8/17/2021

8/14/2021 8/15/2021 8/16/2021 8/17/2021


8/12/2021 8/13/2021 8/14/2021
N D N D N
1
1 1

8/12/2021 8/13/2021 8/14/2021


N D N D N

15.96915
0.20745
2.012813
14.444

0 690.506046 0
0 140.9394555 0
0 1039.819196 0
0 1128.7986 0
3000.0632973 3000.0632973

También podría gustarte