Proyecto: RECONSTRUCCION DEL TRAO 2-1141-PUENTE LOS INGENIEROS DESDE EL JIRON BOLOGNESI HASTA EL JIRON SAN MARTIN
Propietario: MUNICIPALIDAD PROVINCIAL DE CAJABAMBA
Ubicación: CAJABAMBA - CAJABAMBA -CAJAMARCA
Fecha: Nov-19
MES 01 MES 02 MES 03
ITEM PARTIDA UND METRADO PRECIO PARCIAL PREINVERSION 1RA QUINCENA 2DA QUINCENA 3RA QUINCENA 4TA QUINCENA 5TA QUINCENA 6TA QUINCENA
RECONSTRUCCION PUENTE LOS INGENIEROS
01.00.00 OBRAS PRELIMINARES S/. 267,047.16 ###
01.01.00 MOVILIZACION Y DESMOVILIZACION DE GLB 2.00 10,907.53 21,815.06 S/. 15,102.73 S/. 6,712.33
01.02.00 CAMPAMENTO Y ALMACEN DE OBRA GLB 1.00 21,694.59 21,694.59 S/. 21,694.59 ###
01.03.00 DESBROCE Y LIMPIEZA EN OBRA HA 0.58 10,838.90 6,286.56 S/. 6,286.56 ###
01.04.00 CARTEL DE OBRA 2.40M X 3.60M UND 1.00 1,577.07 1,577.07 S/. 1,577.07 ###
01.05.00 MANTENIMIENTO DE TRANSITO Y SEGURI GLB 1.00 41,558.40 41,558.40 S/. 41,558.40 ###
01.06.00 DEMOLICION DE ESTRUCTURA DE CONC GLB 1.00 56,280.00 56,280.00 S/. 56,280.00 ###
01.07.00 PUENTE PEATONAL PROVISIONAL GLB 1.00 80,000.00 80,000.00 S/. 65,454.55 S/. 14,545.45 ###
01.08.00 REUBICACION DE POSTES DE LUZ GLB 1.00 750.00 750.00 S/. 613.64 S/. 136.36 ###
01.09.00 MANTENIMIENTO Y REPOSICION DE LOS GLB 1.00 34,235.48 34,235.48 S/. 17,117.74 S/. 5,705.91 S/. 11,411.83
01.09.01 ALQUILER DE BAÑO QUIMICO PORTATIL MES 3.00 950.00 2,850.00 S/. 475.00 S/. 475.00 S/. 475.00 S/. 475.00 S/. 475.00 S/. 475.00
###
02.00.00 ARQUITECTURA ###
###
02.02.00 PISO DE ADOQUIN DE CONCRETO S/. 5,612.96 ###
02.02.01 CAMA DE ARENA M3 1.94 9.48 18.39 S/. 18.39 ###
02.02.02 PISO DE ADOQUIN DE CONCRETO M2 38.80 144.19 5,594.57 S/. 4,577.38 S/. 1,017.19 ###
###
02.03.00 CARPINTERIA METALICA S/. 10,809.47 ###
02.03.01 BARANDAS METALICAS PARA PUENTES M 36.26 298.11 10,809.47 S/. 10,809.47 ###
###
03.00.00 ESTRUCTURAS ###
03.01.00 PUENTE ###
03.01.01 ESTRIBOS S/. 614,041.75 ###
03.01.01.01 EXCAVACION P/SUB ESTRUCTURAS EN M3 2,981.40 27.89 83,151.25 S/. 83,151.25 ###
03.01.01.02 EXCAVACION P/SUB ESTRUCTURAS EN M M3 170.30 33.54 5,711.86 S/. 5,711.86 ###
03.01.01.03 MEJORAMIENTO DEL TERRENO DE FUND M3 97.78 336.58 32,910.79 S/. 32,910.79 ###
03.01.01.04 ACERO DE REFUERZO FY=4,200 KG/CM2 KG 19,544.05 4.9 95,765.85 S/. 6,384.39 S/. 47,882.92 S/. 41,498.53 ###
03.01.01.05 ENCOFRADO CARA NO VISTA BAJO AGUA M2 37.10 73.16 2,714.24 S/. 904.75 S/. 904.75 S/. 904.75 ###
03.01.01.06 ENCOFRADO CARA NO VISTA EN SECO M2 195.80 55.87 10,939.35 S/. 4,861.93 S/. 6,077.42 ###
03.01.01.07 ENCOFRADO CARA VISTA EN SECO M2 323.10 94.49 30,529.72 S/. 30,529.72 ###
03.01.01.08 CONCRETO f'c=210 kg/cm2 BAJO AGUA M3 107.20 627.74 67,293.73 S/. 67,293.73 ###
03.01.01.09 CONCRETO f'c=210 kg/cm2 EN SECO M3 112.50 564.76 63,535.50 S/. 10,589.25 S/. 52,946.25 ###
03.01.01.10 CURADO DE CONCRETO M2 195.82 5.35 1,047.64 S/. 174.61 S/. 873.03 ###
03.01.01.11 RELLENO DE ESTRUCTURAS CON MATER M3 2,199.55 78.16 171,916.83 S/. 85,958.42 S/. 85,958.42 ###
03.01.01.12 ELIMINACION DE MATERIAL EXCEDENTE M3 2,405.80 20.17 48,524.99 S/. 24,262.49 S/. 24,262.49 ###
03.01.02 VIGAS METALICAS S/. 638,071.39 ###
03.01.02.01 FABRICACION DE ESTRUCTURAS METALI TON 26.57 10,506.76 279,164.61 S/. 111,665.84 S/. 111,665.84 S/. 55,832.92 ###
03.01.02.02 ARENADO DE ESTRUCTURA METALICA TON 26.57 796.13 21,153.17 S/. 10,576.59 S/. 10,576.59 ###
03.01.02.03 PINTURA DE ESTRUCTURA METALICA GLB 1.00 26,696.24 26,696.24 S/. 13,348.12 S/. 13,348.12 ###
03.01.02.04 MONTAJE DE ESTRUCTURAS METALICAS TON 26.57 914.51 24,298.53 S/. 13,253.74 S/. 11,044.79 ###
03.01.02.05 LANZAMIENTO GLB 1.00 259,398.84 259,398.84 S/. 259,398.84 ###
03.01.02.06 PLACAS RADIOGRAFICAS UND 72.00 130.00 9,360.00 S/. 4,680.00 S/. 4,680.00 ###
03.01.02.07 CONECTORES TIPO STUD UND 720.00 25.00 18,000.00 S/. 4,000.00 S/. 14,000.00 ###
SUB TOTAL S/. 914,006.22 S/. 641,898.41 S/. 356,240.29 S/. 419,228.22 S/. 119,021.36 S/. 52,689.04
COSTO DIRECTO S/. 2,503,083.54 TOTAL S/. 1,555,904.62 S/. 775,468.51 S/. 171,710.41
MES 01 MES 02 MES 03
ITEM DESCRIPCION UND METRADO PRECIO PARCIAL PREINVERSION 1RA QUINCENA 2DA QUINCENA 3RA QUINCENA 4TA QUINCENA 5TA QUINCENA 6TA QUINCENA
I GASTOS GENERALES GLB 1.00 S/. 270,358.94 S/. 270,358.94 S/. 98,722.14 S/. 69,331.67 S/. 38,477.64 S/. 45,280.99 S/. 12,855.54 S/. 5,690.96
II UTILIDAD GLB 1.00 S/. 200,246.68 S/. 200,246.68 S/. 73,120.50 S/. 51,351.87 S/. 28,499.22 S/. 33,538.26 S/. 9,521.71 S/. 4,215.12
III SUB TOTAL GLB 1.00 S/. 2,973,689.16 S/. 2,973,689.16 S/. 1,085,848.86 S/. 762,581.95 S/. 423,217.15 S/. 498,047.47 S/. 141,398.61 S/. 62,595.12
IV IGV GLB 1.00 S/. 535,264.05 S/. 535,264.05 S/. 195,452.79 S/. 137,264.75 S/. 76,179.09 S/. 89,648.55 S/. 25,451.75 S/. 11,267.12
V VALOR REFERENCIAL GLB 1.00 S/. 3,508,953.21 S/. 3,508,953.21 S/. 1,281,301.65 S/. 899,846.70 S/. 499,396.24 S/. 587,696.02 S/. 166,850.36 S/. 73,862.24
VI SUPERVISION DE OBRA GLB 1.00 S/. 144,448.03 S/. 144,448.03 S/. 52,745.50 S/. 37,042.69 S/. 20,557.93 S/. 24,192.84 S/. 6,868.49 S/. 3,040.58
VII TOTAL PRESUPUESTO GLB 1.00 S/. 3,653,401.24 S/. 3,653,401.24 S/. 1,334,047.15 S/. 936,889.39 S/. 519,954.17 S/. 611,888.86 S/. 173,718.85 S/. 76,902.82
01.02.00 ESTRIBOS
Proyecto: RECONSTRUCCION DEL TRAO 2-1141-PUENTE LOS INGENIEROS DESDE EL JIRON BOLOGNESI HASTA EL JIRON SAN MARTIN
#NAME?
Propietario: MUNICIPALIDAD PROVINCIAL DE CAJABAMBA
Ubicación: CAJABAMBA - CAJABAMBA -CAJAMARCA Hecho por: J.A.R.B.
Fecha: 43797
TOTAL = 315.00
TOTAL = 1,921.78
01.02.03 EXCAVACION P/SUB ESTRUCTURAS EN MATERIAL COMUN BAJO AGUA 799.10 GLB
TOTAL = 799.11
TOTAL = 110.00
TOTAL = 16.88
01.02.00 ESTRIBOS
Proyecto: RECONSTRUCCION DEL TRAO 2-1141-PUENTE LOS INGENIEROS DESDE EL JIRON BOLOGNESI HASTA EL JIRON SAN MARTIN
#NAME?
Propietario: MUNICIPALIDAD PROVINCIAL DE CAJABAMBA
Ubicación: CAJABAMBA - CAJABAMBA -CAJAMARCA Hecho por: J.A.R.B.
Fecha: 43797
01.02.06 CAMPAMENTO Y ALMACEN DE OBRA 202.20 GLB
Total/estribo 202.23
TOTAL = 202.23
Zapata
Zapata 2.00 10.50 7.00 1.50 115.76
TOTAL = 115.76
Total 110.22 kg
01.03.05 LANZAMIENTO 1 HA
TOTAL 625.20
TOTAL = 140.00
01.05.02 EXCAVACION MANUAL P/SUB ESTRUCTURA EN TERRENO COMUN SECO 19.40 GLB
TOTAL = 19.44
TOTAL = 3.24
Total/estribo 12.60
TOTAL = 12.60
TOTAL = 24.30
01.06.00 VARIOS
Proyecto:RECONSTRUCCION DEL TRAO 2-1141-PUENTE LOS INGENIEROS DESDE EL JIRON BOLOGNESI HASTA EL JIRON SAN MARTIN
MUNICIPALIDAD PROVINCIAL DE CAJABAMBA
Propietario: MUNICIPALIDAD PROVINCIAL DE CAJABAMBA Hecho por: J.A.R.B.
Ubicación: CAJABAMBA - CAJABAMBA -CAJAMARCA
Fecha: 43797
TOTAL = 14.40
TOTAL = 172.80
TOTAL = 22.00
TOTAL = 262.80
TOTAL = 87.20
01.06.06 SISTEMA DE ALIGERAMIENTO DE VEREDAS CON TUBO PVC SAP DE 6" 270.00 M
TOTAL = 270.00
En puente 1 1.00
01.06.00 VARIOS
Proyecto:RECONSTRUCCION DEL TRAO 2-1141-PUENTE LOS INGENIEROS DESDE EL JIRON BOLOGNESI HASTA EL JIRON SAN MARTIN
MUNICIPALIDAD PROVINCIAL DE CAJABAMBA
Propietario: MUNICIPALIDAD PROVINCIAL DE CAJABAMBA Hecho por: J.A.R.B.
Ubicación: CAJABAMBA - CAJABAMBA -CAJAMARCA
Fecha: 43797
TOTAL = 1.00
01.07.00 ACCESOS
Proyecto:RECONSTRUCCION DEL TRAO 2-1141-PUENTE LOS INGENIEROS DESDE EL JIRON BOLOGNESI HASTA EL JIRON SAN MARTIN
MUNICIPALIDAD PROVINCIAL DE CAJABAMBA
Propietario: MUNICIPALIDAD PROVINCIAL DE CAJABAMBA Hecho por: J.A.R.B.
Ubicación: CAJABAMBA - CAJABAMBA -CAJAMARCA
Fecha: 43797
TOTAL = 1,000.00
TOTAL = 500.00
TOTAL = 400.00
TOTAL = 320.00
01.08.00 SEÑALIZACION
Proyecto:RECONSTRUCCION DEL TRAO 2-1141-PUENTE LOS INGENIEROS DESDE EL JIRON BOLOGNESI HASTA EL JIRON SAN MARTIN
MUNICIPALIDAD PROVINCIAL DE CAJABAMBA
Propietario: MUNICIPALIDAD PROVINCIAL DE CAJABAMBA Hecho por: J.A.R.B.
Ubicación: CAJABAMBA - CAJABAMBA -CAJAMARCA
Fecha: 43797
Descripción Cantidad
(und)
TOTAL = 3.00
TOTAL = 7.20
Descripción Longitud
(m)
TOTAL = 19.60
Descripción Cantidad
(und)
TOTAL = 2.00
01.09.00 IMPACTO AMBIENTAL
Proyecto:RECONSTRUCCION DEL TRAO 2-1141-PUENTE LOS INGENIEROS DESDE EL JIRON BOLOGNESI HASTA EL JIRON SAN MARTIN
MUNICIPALIDAD PROVINCIAL DE CAJABAMBA
Propietario: MUNICIPALIDAD PROVINCIAL DE CAJABAMBA Hecho por: J.A.R.B.
Ubicación: CAJABAMBA - CAJABAMBA -CAJAMARCA
Fecha: 43797
Descripción Unidad
(Glb)
TOTAL = 1.00
TOTAL = 1.00
TOTAL = 2,182.60
01.10.00 IMPACTO AMBIENTAL
Proyecto:RECONSTRUCCION DEL TRAO 2-1141-PUENTE LOS INGENIEROS DESDE EL JIRON BOLOGNESI HASTA EL JIRON SAN MARTIN
MUNICIPALIDAD PROVINCIAL DE CAJABAMBA
Propietario: MUNICIPALIDAD PROVINCIAL DE CAJABAMBA Hecho por: J.A.R.B.
Ubicación: CAJABAMBA - CAJABAMBA -CAJAMARCA
Fecha: 43797
Descripción Unidad
(tn)
TOTAL = 420.00
Nro Diám. Area Long. Peso Peso Long.
(1/8") (pul) (cm2) (mt) (Kg/mt) (Var.) Emp.
2 1/4" 0.32 9.00 0.25 2.25 0.30
3 3/8" 0.71 9.00 0.58 5.22 0.30
4 1/2" 1.29 9.00 1.00 9.00 0.45
5 5/8" 2.00 9.00 1.60 14.40 0.55
6 3/4" 2.84 9.00 2.26 20.34 0.70
8 1" 5.06 9.00 4.05 36.45 1.20
11 1 3/8" 9.57 12.00 7.97 95.64 2.00
Final de BDRefuerzo
MES 1 MES 2 MES 3
AVANCE DE OBRA 2,181,148.35 1,087,092.26 240,712.59 3,508,953.20
% DE AVANCE DE OBRA MENSUAL 62.16% 30.98% 6.86%
AVANCE DE OBRA ACUMULADO 2,181,148.35 3,268,240.61 3,508,953.20
% DE AVANCE DE OBRA ACUMULADO 62.16% 93.14% 100.00%
10.00000%