CRONOGRAMA DE UTILIZACION DE MANO DE OBRA

OBRA : “CONSTRUCCION DE PISTAS Y VEREDAS EN EL ANEXO DE YOJO, DISTRITO DE CUCHUMBAYA - MARISCAL NIETO - MOQUEGUA”
LUGAR : CUCHUMBAYA - MARISCAL NIETO - MOQUEGUA
PRECIO PARCIAL
ID MANO DE OBRA UND. CANT. MES 01 MES 02 MES 03
S/. S/.

1 OPERARIO hh 2,811.74 19.30 54,266.61 S/. 350.71 S/. 12,593.44 S/. 41,322.46
2 OFICIAL hh 1,622.43 16.01 25,975.17 S/. 1,047.11 S/. 5,796.10 S/. 19,131.97
3 PEON hh 6,428.78 14.40 92,574.49 S/. 14,031.36 S/. 33,325.69 S/. 45,217.44
4 CAPACITADOR EN SEGURIDAD und 1.00 250.00 250.00 S/. 250.00 S/. 0.00 S/. 0.00
5 CAPACITADOR EN SALUD und 1.00 250.00 250.00 S/. 250.00 S/. 0.00 S/. 0.00
6 TOPOGRAFO hh 40.15 25.09 1,007.46 S/. 883.92 S/. 62.83 S/. 60.72
COSTO DIRECTO S/. 174,323.75 S/. 16,813.10 S/. 51,778.06 S/. 105,732.58
CRONOGRAMA DE ADQUISICIÓN DE MATERIALES

OBRA : “CONSTRUCCION DE PISTAS Y VEREDAS EN EL ANEXO DE YOJO, DISTRITO DE CUCHUMBAYA -


MARISCAL NIETO - MOQUEGUA”

LUGAR : CUCHUMBAYA - MARISCAL NIETO - MOQUEGUA

PRECIO PARCIAL
ID MATERIALES UND. CANT. MES 01 MES 02 MES 03
S/. S/.
CRONOGRAMA DE UTILIZACION DE EQUIPOS

OBRA : “CONSTRUCCION DE PISTAS Y VEREDAS EN EL ANEXO DE YOJO, DISTRITO DE CUCHUMBAYA - MARISCAL NIETO - MOQUEGUA”

LUGAR : CUCHUMBAYA - MARISCAL NIETO - MOQUEGUA

PRECIO PARCIAL
ID EQUIPOS UND. CANT. MES 01 MES 02 MES 03
S/. S/.

1 CAMILLA DE LONA und 1.00 200.00 200.00 200.00


2 HERRAMIENTAS MANUALES %MO 5,492.11 5,492.11
3 MASCARA DE SOLDAR und 5.00 70.00 350.00 350.00
4 CASCO DE SEGURIDAD und 35.00 15.00 525.00 525.00
5 ALQUILER DE MULTIMEDIA und 1.00 25.00 25.00 25.00
6 EQUIPO DE PINTURA PARA PAVIMENTOS hm 8.31 20.00 166.24 166.24
7 WINCHA DE 30m und 5.04 25.00 125.94 110.25 7.75 7.94
8 ZAPATOS DE SEGURIDAD PAR 35.00 80.00 2,800.00 2,800.00
9 GUANTES DE CUERO PAR 35.00 25.00 875.00 875.00
10 REGLA DE MADERA PINO 2" X 6" X 10' und 1,115.62 3.00 3,346.85 1,093.32 2,253.53
11 RESPIRADORES und 35.00 12.00 420.00 420.00
12 CHALECOS und 35.00 20.81 728.35 728.35
13 ANTEOJOS und 35.00 20.00 700.00 700.00
14 BOTAS DE SEGURIDAD PAR 35.00 80.00 2,800.00 2,800.00
15 MEZCLADORA DE CONCRETO DE 11 P3-18 HP hm 322.40 18.00 5,803.14 1,664.64 4,138.50
16 CAMION CISTERNA 4x2 (AGUA) 122 HP 2,000 hm 18.24 150.00 2,736.27 103.50 2,437.50 195.27
17 CAMION VOLQUETE 15 M3. hm 394.81 150.00 59,221.74 21,993.00 35,080.50 2,148.24
18 SOLDADORA hm 92.20 70.00 6,454.00 6,454.00
19 MOCHILA PULVERIZADORA hm 44.92 0.10 4.49 4.49
20 CIZALLA hm 110.28 5.00 551.40 108.00 443.40
21 COMPRESORA NEUMATICA 93 HP 335-375 PCM hm 1.49 90.00 134.06 134.06
22 MARTILLO NEUMATICO DE 24 kg (INC. CINCEL Y ACC.) hm 2.98 130.00 387.86 387.86
23 COMPACTADOR VIBR. TIPO PLANCHA 7 HP hm 310.97 20.00 6,219.42 5,048.00 1,171.42
24 RODILLO LISO VIBRATORIO AUTOPROPULSADO 70-100 HP 7- 9 ton hm 18.24 140.00 2,553.85 96.60 2,275.00 182.25
25 TRACTOR DE ORUGAS DE 140-160 HP hm 3.10 200.00 619.54 231.40 388.14
26 CARGADOR SOBRE LLANTAS DE 125-135 HP 3 yd3 hm 202.97 180.00 36,534.44 13,320.00 21,560.40 1,654.04
27 COCINA DE ASFALTO hm 15.37 17.00 261.27 261.27
28 VIBRADOR DE CONCRETO 4 HP 1.50" hm 322.40 18.00 5,803.14 1,664.64 4,138.50
29 TRACTOR S/ORUGA C/BULDOZER D6D N°75W1505 hm 25.72 200.00 5,143.10 2,239.50 2,903.60
30 MOTONIVELADORA DE 125 HP hm 18.24 250.00 4,560.45 172.50 4,062.50 325.45
31 ESTACION TOTAL CON PRISMA hm 40.15 25.00 1,003.85 880.75 62.50 60.60
32 NIVEL TOPOGRAFICO CON TRIPODE HE 40.15 15.00 602.31 528.45 37.50 36.36
SIRENA DE ALARMA _x000D_ 1.00 50.16 50.16
33 und 50.16
COSTO DIRECTO S/. 157,198.99 S/. 49,671.37 S/. 78,393.99 S/. 29,133.63
CRONOGRAMA DE SUBCONTRATOS

OBRA : “CONSTRUCCION DE PISTAS Y VEREDAS EN EL ANEXO DE YOJO, DISTRITO DE CUCHUMBAYA - MARISCAL NIETO - MOQUEGUA”

LUGAR : CUCHUMBAYA - MARISCAL NIETO - MOQUEGUA

PRECIO PARCIAL
ID SUB-CONTRATOS UND. CANT. MES 01 MES 02 MES 03
S/. S/.

1 ALQUILER DE CASA PARA OFICINAS, ALMACEN Y CASETA DE GUARDIANIA mes 3.00 1,500.00 4,500.00 1,500.00 1,500.00 1,500.00
MITIGACION DE LA POLVAREDA DURANTE LA EJECUCION DE LA OBRA 1.00 10,000.00 3,500.00 4,000.00 2,500.00
2 GLB 10,000.00
SC SISTEMA DATA
3 NIVELACION DE BUZONES und 5.00 385.00 1,925.00 1,925.00
4 REUBICACION DE POSTE DE CONCRETO und 5.00 1,900.00 9,500.00 9,500.00
5 MOVILIZACIÓN Y DESMOVILIZACIÓN GLB 1.00 19,500.00 19,500.00 9,750.00 9,750.00
ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE ELABORACIÓN E 1.00 1,200.00 1,200.00
6 GLB 1,200.00
IMPLEMENTACIÓN DEL PLAN DE SEGURIDAD Y SALUD
COSTO DIRECTO S/. 46,625.00 S/. 15,950.00 S/. 15,000.00 S/. 15,675.00