Está en la página 1de 4

PRESUPUESTO DE OBRA

OBRA
VIVIENDA MULTIFAMILIAR
UBICACIÓN : PRIMAVERA - TRUJILLO - CALLE ISAAC ALBANIZ MZ B6 LOTE 20
CLIENTE : MARIELA VIDAL FERNANDEZ FECHA AL : 1-Jun-21
PLAZO EJECUCIÓN : 85 DIAS CALENDARIO FECHA DE INICIO : 6/8/2021
MONTO DEL CONTRATO : S/. 137,432.49 FECHA FINAL DE OBRA : 8/31/2021

Item Descripcion Und. Metrado P.U. PRESUPUESTO S/.

01.00.00 TRABAJOS PRELIMINARES 517.59


01.01.00 LIMPIEZA MANUAL DE SUPERFICIE m2 123.00 1.03 126.94
TRAZO Y REPLANTEO
01.02.00 m2 123.00 3.18 390.65
02.00.00 ESTRUCTURAS 0.00 66,927.67
02.01.00 OBRAS DE CONCRETO ARMADO 0.00 66,927.67
02.01.01. COLUMNAS 0.00 9,681.65
02.01.01.01 CONCRETO ARMADO FC=210 KG/CM2 m3 4.02 548.16 2,203.60
02.01.01.02 ACERO PARA COLUMNAS kg 852.20 5.80 4,942.76
02.01.01.03 ENCOFRADO Y DESENCOFRADO PARA COLUMNAS m2 56.39 44.96 2,535.29
02.01.02. VIGAS 0.00 7,449.83
02.01.02.01 CONCRETO ARMADO FC=210 KG/CM2 m3 3.68 548.16 2,017.23
02.01.02.02 ACERO PARA VIGAS kg 576.20 5.80 3,341.96
02.01.02.03 ENCOFRADO Y DESENCOFRADO PARA VIGAS m2 46.50 44.96 2,090.64
02.01.03. LOSA ALIGERADA 0.00 33,168.88
02.01.03.01 CONCRETO ARMADO FC=210 KG/CM2 m3 16.20 548.16 8,880.19
02.01.03.02 ACERO PARA VIGETAS Y LOSA ALIGERADA kg 3,012.50 5.80 17,472.50
02.01.03.03 ENCOFRADO Y DESENCOFRADO PARA LOSA m2 115.20 44.96 5,179.39
02.01.03.04 LADRILLO DE ARCILLA H=15CM Und. 1,100.00 1.49 1,636.80
02.01.04. ESCALERA 0.00 2,423.39
02.01.04.01 CONCRETO ARMADO FC=210 KG/CM2 m3 2.98 548.16 1,633.52
02.01.04.02 ACERO PARA ESCALERA kg 112.00 4.69 525.06
02.01.04.03 ENCOFRADO Y DESENCOFRADO PARA ESCALERA m2 5.89 44.96 264.81
02.02.05. OBRAS DE ARTE PARA MESADA 0.00 14,203.92
02.01.05.01 CONCRETO ARMADO FC=210 KG/CM2 m3 23.76 548.16 13,024.28
02.01.05.02 ACERO PARA ESCALERA kg 23.76 4.69 111.39
02.01.05.03 ENCOFRADO Y DESENCOFRADO PARA ESCALERA m2 23.76 44.96 1,068.25
03.00.00 ARQUITECTURA 0.00 27,950.41
03.01.00 TABIQUERIA 0.00 13,564.01
02.01.01 ASENTADO DE LADRILLO KING KONG DE 18 ALVEOLOS M2 210.36 64.48 13,564.01
03.02.00 PISO 0.00 2,326.69
03.02.01 SOBREPISO DE MORTERO DE H= 0.04m m2 123.76 18.80 2,326.69
03.03.00 REVOQUES Y ENLUCIDOS 0.00 9,288.80
03.03.01 TARRAJEO DE CIELO RAZO m2 118.00 20.24 2,388.32
03.03.02 TARRAJEO DE VIGAS ML 65.80 12.96 852.77
03.03.03 TARRAJEO E MUROS INTERIORES m2 298.80 20.24 6,047.71
03.04.00 REVESTIMIENTO CON MORTERO 0.00 2,770.91
03.04.01 REVESTIMIENTO CON MORTERO DE H= 0.04m PARA ESCALERA Y MESADA m2 132.20 20.96 2,770.91
04.00.00 INSTALACIONES SANITARIAS 0.00 3,981.60
04.01.00 SUMINISTRO E INSTALACION DE SERVICIOS HIGIENICOS Und. 3.00 388.00 1,164.00
04.02.00 SUMINISTRO E INSTALACION DE COCINA Und. 1.00 281.60 281.60
04.03.00. SUMINISTRO E INSTALACION DE LAVANDERIA Und. 1.00 148.00 148.00
04.04.00. SUMINISTRO E INSTALACION DE SANITARIOS Und. 8.00 172.00 1,376.00
04.05.00 SUMINISTRO E INSTALACION DE GRIFERIA Und. 11.00 92.00 1,012.00
05.00.00 INSTALACIONES ELECTRICAS 0.00 3,422.40
05.01.00 SUMINISTRO E INSTALACION DE PUNTOS DE ALUMBRADO Und. 20.00 28.80 576.00
05.02.00 SUMINISTRO E INSTALACION DE TOMACORRIENTES Und. 27.00 28.80 777.60
05.03.00 SUMINISTRO E INSTALACION DE INTERRUPTORES Und. 17.00 28.80 489.60
05.04.00 SUMINISTRO E INSTALACION DE LINEA DE TUBERIA DE 3/4" ml 352.00 2.00 704.00
05.05.00 SUMINISTRO E INSTALACION ACOMETIDA Und. 23.76 20.00 475.20
05.06.00 SUMINISTRO E INSTALACION DE TABLERO SUB-GENERAL Und. 1.00 400.00 400.00
05.00.00 ACABADOS SECOS 0.00 11,237.60
05.01.00 CARPINTERIA DE MADERA 0.00 5,600.00
05.01.01 SUMINISTRO E INSTALACION DE PUERTAS DE MADERA Und. 10.00 560.00 5,600.00
05.02.00 PINTADO 0.00 5,637.60
05.02.01 PINTADO DE CIELO RASO m2 136.20 12.96 1,765.15
05.02.02 PINTADO DE MUROS INTERIORES m2 298.80 12.96 3,872.45
06.00.00 TRABAJOS COMPEMENTARIOS 0.00 2,430.94
06.01.00. LIMPIEZA FINAL DE OBRA glb 123.00 1.03 126.94
06.02.00 SEGURIDAD Y SALUD EN OBRA glb 1.00 960.00 960.00
06.03.00 BIOSEGURIDAD EN OBRA glb 1.00 800.00 800.00
06.04.00 FLETE TERRESTRE glb 1.00 544.00 544.00

COSTOS DIRECTOS S/116,468.21


IGV 18.00% S/20,964.28
PRESUPUESTO DE OBRA
OBRA
VIVIENDA MULTIFAMILIAR
UBICACIÓN : PRIMAVERA - TRUJILLO - CALLE ISAAC ALBANIZ MZ B6 LOTE 20
CLIENTE : MARIELA VIDAL FERNANDEZ FECHA AL : 1-Jun-21
PLAZO EJECUCIÓN : 85 DIAS CALENDARIO FECHA DE INICIO : 6/8/2021
MONTO DEL CONTRATO : S/. 137,432.49 FECHA FINAL DE OBRA : 8/31/2021

Item Descripcion Und. Metrado P.U. PRESUPUESTO S/.

TOTAL PRESUPUESTO S/137,432.49


CALENDARIO DE OBRA VALORIZADO
OBRA
VIVIENDA MULTIFAMILIAR
UBICACIÓN : PRIMAVERA - TRUJILLO - CALLE ISAAC ALBANIZ MZ B6 LOTE 20
CLIENTE : MARIELA VIDAL FERNANDEZ
PLAZO EJECUCIÓN : 80 DIAS CALENDARIO FECHA DE INICIO : 6/8/2021 PLAZO :
MONTO DEL CONTRATO : S/. 137,432.49 FECHA FINAL DE OBRA : 8/28/2021 FECHA AL : 1-Jun-21
AVANCES
08/06/21 al 30/06/21 01/07/21 al 31/07/21 01/08/21 al 26/08/21 MONTOS
Item Descripcion Und. Metrado P.U. PRESUPUESTO S/. 23 DIAS 31 DIAS 26 DIAS PARCIALES
% Monto S/. % Monto S/. % Monto S/.
01.00.00 TRABAJOS PRELIMINARES 517.59 0.00% 0.00 0.00% 0.00 0.00
01.01.00 LIMPIEZA MANUAL DE SUPERFICIE m2 123.00 1.03 126.94 100.00% 126.94 126.94
TRAZO Y REPLANTEO
01.02.00 m2 123.00 3.18 390.65 100.00% 390.65 390.65
02.00.00 ESTRUCTURAS 0.00 66,927.67 0.00
02.01.00 OBRAS DE CONCRETO ARMADO 0.00 66,927.67 0.00% 0.00 0.00% 0.00 0.00
02.01.01. COLUMNAS 0.00 9,681.65 0.00
02.01.01.01 CONCRETO ARMADO FC=210 KG/CM2 m3 4.02 548.16 2,203.60 90.76% 2,000.00 9.24% 203.60 2,203.60
02.01.01.02 ACERO PARA COLUMNAS kg 852.20 5.80 4,942.76 60.69% 3,000.00 39.31% 1,942.76 4,942.76
02.01.01.03 ENCOFRADO Y DESENCOFRADO PARA COLUMNAS m2 56.39 44.96 2,535.29 78.89% 2,000.00 21.11% 535.29 2,535.29
02.01.02. VIGAS 0.00 7,449.83 0.00
02.01.02.01 CONCRETO ARMADO FC=210 KG/CM2 m3 3.68 548.16 2,017.23 10.77% 217.23 89.23% 1,800.00 2,017.23
02.01.02.02 ACERO PARA VIGAS kg 576.20 5.80 3,341.96 26.37% 881.23 73.63% 2,460.73 3,341.96
02.01.02.03 ENCOFRADO Y DESENCOFRADO PARA VIGAS m2 46.50 44.96 2,090.64 8.16% 170.64 91.84% 1,920.00 2,090.64
02.01.03. LOSA ALIGERADA 0.00 33,168.88 0.00
02.01.03.01 CONCRETO ARMADO FC=210 KG/CM2 m3 16.20 548.16 8,880.19 21.17% 1,880.19 78.83% 7,000.00 8,880.19
02.01.03.02 ACERO PARA VIGETAS Y LOSA ALIGERADA kg 3,012.50 5.80 17,472.50 14.15% 2,472.50 85.85% 15,000.00 17,472.50
02.01.03.03 ENCOFRADO Y DESENCOFRADO PARA LOSA m2 115.20 44.96 5,179.39 13.12% 679.39 86.88% 4,500.00 5,179.39
02.01.03.04 LADRILLO DE ARCILLA H=15CM Und. 1,100.00 1.49 1,636.80 100.00% 1,636.80 1,636.80
02.01.04. ESCALERA 0.00 2,423.39 0.00
02.01.04.01 CONCRETO ARMADO FC=210 KG/CM2 m3 2.98 548.16 1,633.52 100.00% 1,633.52 1,633.52
02.01.04.02 ACERO PARA ESCALERA kg 112.00 4.69 525.06 100.00% 525.06 525.06
02.01.04.03 ENCOFRADO Y DESENCOFRADO PARA ESCALERA m2 5.89 44.96 264.81 100.00% 264.81 264.81
02.02.05. OBRAS DE ARTE PARA MESADA 0.00 14,203.92 0.00
02.01.05.01 CONCRETO ARMADO FC=210 KG/CM2 m3 23.76 548.16 13,024.28 100.00% 13,024.28 13,024.28
02.01.05.02 ACERO PARA ESCALERA kg 23.76 4.69 111.39 100.00% 111.39 111.39
02.01.05.03 ENCOFRADO Y DESENCOFRADO PARA ESCALERA m2 23.76 44.96 1,068.25 100.00% 1,068.25 1,068.25
03.00.00 ARQUITECTURA 0.00 27,950.41 0.00
03.01.00 TABIQUERIA 0.00 13,564.01 0.00
02.01.01 ASENTADO DE LADRILLO KING KONG DE 18 ALVEOLOS M2 210.36 64.48 13,564.01 100.00% 13,564.01 13,564.01
03.02.00 PISO 0.00 2,326.69 0.00
03.02.01 SOBREPISO DE MORTERO DE H= 0.04m m2 123.76 18.80 2,326.69 100.00% 2,326.69 2,326.69
03.03.00 REVOQUES Y ENLUCIDOS 0.00 9,288.80 0.00
03.03.01 TARRAJEO DE CIELO RAZO m2 118.00 20.24 2,388.32 41.87% 1,000.00 58.13% 1,388.32 2,388.32
03.03.02 TARRAJEO DE VIGAS ML 65.80 12.96 852.77 100.00% 852.77 852.77
03.03.03 TARRAJEO E MUROS INTERIORES m2 298.80 20.24 6,047.71 100.00% 6,047.71 6,047.71
03.04.00 REVESTIMIENTO CON MORTERO 0.00 2,770.91 0.00
03.04.01 REVESTIMIENTO CON MORTERO DE H= 0.04m PARA ESCALERA Y MESADA m2 132.20 20.96 2,770.91 100.00% 2,770.91 2,770.91
04.00.00 INSTALACIONES SANITARIAS 0.00 3,981.60 0.00
04.01.00 SUMINISTRO E INSTALACION DE SERVICIOS HIGIENICOS Und. 3.00 388.00 1,164.00 100.00% 1,164.00 1,164.00
04.02.00 SUMINISTRO E INSTALACION DE COCINA Und. 1.00 281.60 281.60 100.00% 281.60 281.60
04.03.00. SUMINISTRO E INSTALACION DE LAVANDERIA Und. 1.00 148.00 148.00 100.00% 148.00 148.00
04.04.00. SUMINISTRO E INSTALACION DE SANITARIOS Und. 8.00 172.00 1,376.00 100.00% 1,376.00 1,376.00
04.05.00 SUMINISTRO E INSTALCION DE GRIFERIA Und. 11.00 92.00 1,012.00 100.00% 1,012.00 1,012.00
05.00.00 INSTALACIONES ELECTRICAS 0.00 3,422.40 0.00
05.01.00 SUMINISTRO E INSTALACION DE PUNTOS DE ALUMBRADO Und. 20.00 28.80 576.00 34.72% 200.00 34.72% 200.00 30.56% 176.00 576.00
05.02.00 SUMINISTRO E INSTALACION DE TOMACORRIENTES Und. 27.00 28.80 777.60 25.08% 195.00 20.09% 156.20 54.84% 426.40 777.60
05.03.00 SUMINISTRO E INSTALACION DE INTERRUPTORES Und. 17.00 28.80 489.60 31.86% 156.00 40.85% 200.00 27.29% 133.60 489.60
05.04.00 SUMINISTRO E INSTALACION DE LINEA DE TUBERIA DE 3/4" ml 352.00 2.00 704.00 100.00% 704.00 704.00
CALENDARIO DE OBRA VALORIZADO
OBRA
VIVIENDA MULTIFAMILIAR
UBICACIÓN : PRIMAVERA - TRUJILLO - CALLE ISAAC ALBANIZ MZ B6 LOTE 20
CLIENTE : MARIELA VIDAL FERNANDEZ
PLAZO EJECUCIÓN : 80 DIAS CALENDARIO FECHA DE INICIO : 6/8/2021 PLAZO :
MONTO DEL CONTRATO : S/. 137,432.49 FECHA FINAL DE OBRA : 8/28/2021 FECHA AL : 1-Jun-21
AVANCES
08/06/21 al 30/06/21 01/07/21 al 31/07/21 01/08/21 al 26/08/21 MONTOS
Item Descripcion Und. Metrado P.U. PRESUPUESTO S/. 23 DIAS 31 DIAS 26 DIAS PARCIALES
% Monto S/. % Monto S/. % Monto S/.
05.05.00 SUMINISTRO E INSTALACION ACOMETIDA Und. 23.76 20.00 475.20 100.00% 475.20 475.20
05.06.00 SUMINISTRO E INSTALACION DE TABLERO SUB-GENERAL Und. 1.00 400.00 400.00 100.00% 400.00 400.00
05.00.00 ACABADOS SECOS 0.00 11,237.60 0.00
05.01.00 CARPINTERIA DE MADERA 0.00 5,600.00 0.00
05.01.01 SUMINISTRO E INSTALACION DE PUERTAS DE MADERA Und. 10.00 560.00 5,600.00 100.00% 5,600.00 5,600.00
05.02.00 PINTADO 0.00 5,637.60 0.00
05.02.01 PINTADO DE CIELO RASO m2 136.20 12.96 1,765.15 100.00% 1,765.15 1,765.15
05.02.02 PINTADO DE MUROS INTERIORES m2 298.80 12.96 3,872.45 100.00% 3,872.45 3,872.45
06.00.00 TRABAJOS COMPEMENTARIOS 0.00 2,430.94 0.00
06.01.00. LIMPIEZA FINAL DE OBRA glb 123.00 1.03 126.94 100.00% 126.94 126.94
06.02.00 SEGURIDAD Y SALUD EN OBRA glb 1.00 960.00 960.00 37.50% 360.00 31.25% 300.00 31.25% 300.00 960.00
06.03.00 BIOSEGURIDAD EN OBRA glb 1.00 800.00 800.00 31.25% 250.00 31.25% 250.00 37.50% 300.00 800.00
06.04.00 FLETE TERRESTRE glb 1.00 544.00 544.00 100.00% 544.00 544.00

COSTOS DIRECTOS S/116,468.21 S/31,430.98 S/41,528.77 S/43,508.46 S/116,468.21


IGV 18.00% S/20,964.28 S/5,657.58 S/7,475.18 S/7,831.52 S/20,964.280
TOTAL PRESUPUESTO S/137,432.49 S/37,088.56 S/49,003.95 S/51,339.98 S/137,432.49

TOTAL CONTRATADO 100.00000% 26.98674818450860% 35.65674317623150% 37.35650863925990%


AVANCE PARCIAL 100.0% 26.99% 35.66% 37.36%
AVANCE ACUMULADO 100.0% 26.99% 62.64% 100.00%
VALORIZACION - 01 VALORIZACION - 02 VALORIZACION - 03

También podría gustarte