Está en la página 1de 57

CURVA "S"

REPROGRAMADO VS EJECUTADO
MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N°
22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA
100.00% –
100.00% DEPARTAMENTO DE ICA
Avance Reprogramado Avance Ejecutado

90.00%
85.41%

80.00%

70.00%

60.00% 57.18%
55.48%

50.00%

40.00%

30.96%
30.00%

21.42%
17.18%
20.00%

10.00%

0.00%
ANTES DEL 15/05/2019 del 15/05/19 al 31/05/19 del 01/06/19 al 30/06/19 del 01/07/19 al 31/07/19 del 01/08/19 al 31/07/19 del 01/09/19 al 11/09/19
CRONOGRAMA PROGRAMADO - CONTRACTUAL GORE
PROYECTO: "MEJORAMIENTO Y AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. Nº 22273 Y DE LA I.E. Nº 320 – CHAVIN,
DISTRITO CHAVIN – PROVINCIA CHINCHA – ICA"

MAYO 2019 JUNIO 2019 JULIO 2019 AGOSTO 2019 SETIEMBRE 2019
DESCRIPCIÓN AVANCE DE OBRA
15 31 01 30 01 31 01 31 01 11

TOTAL COSTO DIRECTO DE OBRA (CD) S/. 536,858.52 S/. 133,281.84 S/. 759,322.64 S/. 823,571.89 S/. 682,243.08 S/. 189,494.26
% AVANCE DE MES 17.18% 4.27% 24.30% 26.36% 21.83% 6.06%
% AVANCE ACUMULADO MENSUAL 17.18% 21.45% 45.75% 72.10% 93.94% 100.00%
GASTOS GENERALES 9.21% S/. 49,421.34 S/. 12,269.47 S/. 69,900.62 S/. 75,815.18 S/. 62,804.94 S/. 17,444.19
UTILIDAD 9.00% S/. 48,317.27 S/. 11,995.37 S/. 68,339.04 S/. 74,121.47 S/. 61,401.88 S/. 17,054.48
SUBTOTAL S/. 634,597.13 S/. 157,546.67 S/. 897,562.29 S/. 973,508.54 S/. 806,449.90 S/. 223,992.93
IGV (18%) S/. 114,227.48 S/. 28,358.40 S/. 161,561.21 S/. 175,231.54 S/. 145,160.98 S/. 40,318.73
TOTAL MENSUAL S/. 748,824.61 S/. 185,905.07 S/. 1,059,123.50 S/. 1,148,740.08 S/. 951,610.88 S/. 264,311.66

GRÁFICO DE AVANCE DE OBRA


100%

90%

80%

70%
% DE AVANCE

60%

50%

40%

30%

20%

10%

0%
1 2 3 4 5 6 7
CRONOGRAMA REPROGRAMADO - CONTRACTUAL GORE
PROYECTO: "MEJORAMIENTO Y AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. Nº 22273 Y DE LA I.E. Nº 320 – CHAVIN,
DISTRITO CHAVIN – PROVINCIA CHINCHA – ICA"

MAYO 2019 JUNIO 2019 JULIO 2019 AGOSTO 2019 SETIEMBRE 2019
DESCRIPCIÓN AVANCE DE OBRA
15 31 01 30 01 31 01 31 01 11

TOTAL COSTO DIRECTO DE OBRA (CD) S/. 536,858.52 S/. 132,441.20 S/. 298,064.11 S/. 819,361.98 S/. 882,175.12 S/. 455,871.29
% AVANCE DE MES 17.18% 4.24% 9.54% 26.22% 28.23% 14.59%
% AVANCE ACUMULADO MENSUAL 17.18% 21.42% 30.96% 57.18% 85.41% 100.00%
GASTOS GENERALES 9.21% S/. 49,421.34 S/. 12,192.08 S/. 27,438.75 S/. 75,427.63 S/. 81,210.00 S/. 41,965.94
UTILIDAD 9.00% S/. 48,317.27 S/. 11,919.71 S/. 26,825.77 S/. 73,742.58 S/. 79,395.76 S/. 41,028.42
SUBTOTAL S/. 634,597.13 S/. 156,552.99 S/. 352,328.63 S/. 968,532.19 S/. 1,042,780.88 S/. 538,865.64
IGV (18%) S/. 114,227.48 S/. 28,179.54 S/. 63,419.15 S/. 174,335.79 S/. 187,700.56 S/. 96,995.82
TOTAL MENSUAL S/. 748,824.61 S/. 184,732.52 S/. 415,747.79 S/. 1,142,867.98 S/. 1,230,481.44 S/. 635,861.46

GRÁFICO DE AVANCE DE OBRA


100% 100.00%

90%
85.41%
80%

70%

60%
% DE AVANCE

57.18%
50%

40%

30% 30.96%

20% 21.42%
17.18%
10%

0% 0.00%
1 2 3 4 5 6 7
20% 21.42%
17.18%
10%

0% 0.00%
1 2 3 4 5 6 7
CRONOGRAMA EJECUTADO - CONTRACTUAL GORE
PROYECTO: "MEJORAMIENTO Y AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. Nº 22273 Y DE LA I.E. Nº 320 – CHAVIN,
DISTRITO CHAVIN – PROVINCIA CHINCHA – ICA"

MAYO 2019 JUNIO 2019 JULIO 2019 AGOSTO 2019 SETIEMBRE 2019
DESCRIPCIÓN EJECUCIÓN ANTERIOR
15 31 01 30 01 31 01 31 01 11

TOTAL COSTO DIRECTO DE OBRA (CD) S/. 536,858.52 S/. 132,441.20 S/. 298,064.11 S/. 766,184.62
% AVANCE DE MES 17.18% 4.24% 9.54% 24.52%
% AVANCE ACUMULADO MENSUAL 17.18% 21.42% 30.96% 55.48%
GASTOS GENERALES 9.21% S/. 49,421.34 S/. 12,192.08 S/. 27,438.75 S/. 70,532.31
UTILIDAD 9.00% S/. 48,317.27 S/. 11,919.71 S/. 26,825.77 S/. 68,956.62
SUBTOTAL S/. 634,597.13 S/. 156,552.99 S/. 352,328.63 S/. 905,673.54
IGV (18%) S/. 114,227.48 S/. 28,179.54 S/. 63,419.15 S/. 163,021.24
TOTAL MENSUAL S/. 748,824.61 S/. 184,732.52 S/. 415,747.78 S/. 1,068,694.78

GRÁFICO DE AVANCE DE OBRA


100%

90%

80%

70%

60%
% DE AVANCE

55.48%
50%

40%

30% 30.96%

20% 21.42%
17.18%
10%

0% 0.00%
1 2 3 4 5
RESUMEN DE AVANCE DE EJECUCIÓN

VALORIZACION PERIODO PROGRAMADO REPROGRAMA EJECUTADO


ACUMULADO ACUMULADO ACUMULADO
EJECUCION ANTES DEL 15/05/2019 17.18% 17.18% 17.18%
ANTERIOR
VAL 07 del 15/05/19 al 31/05/19 21.45% 21.42% 21.42%
VAL 08 del 01/06/19 al 30/06/19 45.75% 30.96% 30.96%
VAL 09 del 01/07/19 al 31/07/19 72.10% 57.18% 55.48%
VAL 10 del 01/08/19 al 31/07/19 93.94% 85.41%
VAL 11 del 01/09/19 al 11/09/19 100.00% 100.00%
OBRA : MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N° 22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA – DEPARTAMENTO DE ICA
ENTIDAD : GOBIERNO REGIONAL DE ICA
SUPERVISIÓN : CONSORCIO SUPERVISION CHINCHA
CONTRATISTA : PARADIZO S.R.L.
PLAZO : 180 DIAS CALENDARIOS
MODALIDAD : A SUMA ALZADA

PLANILLA DE VALORIZACION N° 06
01/10/2018 AL 31/10/2018

PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

01 TRABAJOS GENERALES 114,563.43


01.01 OBRAS PROVISIONALES 6,950.00
01.01.01 CARTEL PARA LA OBRA 2.40 X 3.60 und 1.00 950.00 950.00 1.00 950.00 100.00% 0.00 0.00 0.00% 1.00 950.00 100.00% 0.00 0.00 0.00%
01.01.02 ALMACEN DE OBRA glb 1.00 6,000.00 6,000.00 0.80 4,800.00 80.00% 0.00 0.00 0.00% 0.80 4,800.00 80.00% 0.20 1,200.00 20.00%
01.02 OBRAS PRELIMINARES 107,613.43
01.02.01 TRANSPORTE DE MATERIALES A OBRA glb 1.00 58,980.01 58,980.01 0.40 23,592.00 40.00% 0.00 0.00 0.00% 0.40 23,592.00 40.00% 0.60 35,388.01 60.00%
01.02.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y HERRAMIE glb 1.00 22,199.02 22,199.02 0.90 19,979.12 90.00% 0.00 0.00 0.00% 0.90 19,979.12 90.00% 0.10 2,219.90 10.00%
01.02.03 IMPLEMENTOS DE SEGURIDAD PARA LOS TRABAJADORES glb 1.00 10,000.00 10,000.00 1.00 10,000.00 100.00% 0.00 0.00 0.00% 1.00 10,000.00 100.00% 0.00 0.00 0.00%
01.02.04 DEMOLICION DE ESTRUCTURAS DE CONCRETO m3 80.00 189.58 15,166.40 80.00 15,166.40 100.00% 0.00 0.00 0.00% 80.00 15,166.40 100.00% 0.00 0.00 0.00%
01.02.05 ELIMINACION DE MATERIAL DEMOLIDO CARGUIO C/EQ 125HP m3 80.00 15.85 1,268.00 80.00 1,268.00 100.00% 0.00 0.00 0.00% 80.00 1,268.00 100.00% 0.00 0.00 0.00%
02 SECTOR INICIAL 225,861.54
02.01 ESTRUCTURAS 84,768.77
02.01.01 OBRAS PRELIMINARES 372.30
02.01.01.01 LIMPIEZA DE TERRENO m2 138.40 0.95 131.48 138.40 131.48 100.00% 0.00 0.00 0.00% 138.40 131.48 100.00% 0.00 0.00 0.00%
02.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 138.40 1.74 240.82 138.40 240.82 100.00% 0.00 0.00 0.00% 138.40 240.82 100.00% 0.00 0.00 0.00%
02.01.02 MOVIMIENTO DE TIERRAS 7,902.25
02.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 35.16 41.41 1,455.98 35.16 1,455.98 100.00% 0.00 0.00 0.00% 35.16 1,455.98 100.00% 0.00 0.00 0.00%
02.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 50.40 41.41 2,087.06 50.40 2,087.06 100.00% 0.00 0.00 0.00% 50.40 2,087.06 100.00% 0.00 0.00 0.00%
02.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 112.10 2.48 278.01 112.10 278.01 100.00% 0.00 0.00 0.00% 112.10 278.01 100.00% 0.00 0.00 0.00%
02.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 32.53 27.36 890.02 32.53 890.02 100.00% 0.00 0.00 0.00% 32.53 890.02 100.00% 0.00 0.00 0.00%
02.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 11.21 197.01 2,208.48 11.21 2,208.48 100.00% 0.00 0.00 0.00% 11.21 2,208.48 100.00% 0.00 0.00 0.00%
02.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 62.00 15.85 982.70 62.00 982.70 100.00% 0.00 0.00 0.00% 62.00 982.70 100.00% 0.00 0.00 0.00%
02.01.03 OBRAS DE CONCRETO SIMPLE 15,500.07
02.01.03.01 SOLADO PARA ZAPATAS m2 36.00 35.13 1,264.68 36.00 1,264.68 100.00% 0.00 0.00 0.00% 36.00 1,264.68 100.00% 0.00 0.00 0.00%
02.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 13.08 333.17 4,357.86 13.08 4,357.86 100.00% 0.00 0.00 0.00% 13.08 4,357.86 100.00% 0.00 0.00 0.00%
02.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 5.39 387.67 2,089.54 5.39 2,089.54 100.00% 0.00 0.00 0.00% 5.39 2,089.54 100.00% 0.00 0.00 0.00%
02.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 71.83 46.45 3,336.50 71.83 3,336.50 100.00% 0.00 0.00 0.00% 71.83 3,336.50 100.00% 0.00 0.00 0.00%
02.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 112.10 39.71 4,451.49 112.10 4,451.49 100.00% 0.00 0.00 0.00% 112.10 4,451.49 100.00% 0.00 0.00 0.00%
02.01.04 OBRAS DE CONCRETO ARMADO 60,994.15
02.01.04.01 ZAPATAS 10,006.67
02.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 18.00 449.81 8,096.58 18.00 8,096.58 100.00% 0.00 0.00 0.00% 18.00 8,096.58 100.00% 0.00 0.00 0.00%
02.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 456.96 4.18 1,910.09 456.96 1,910.09 100.00% 0.00 0.00 0.00% 456.96 1,910.09 100.00% 0.00 0.00 0.00%
02.01.04.02 VIGA DE CIMENTACION 13,214.46
02.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 9.50 449.81 4,273.20 9.50 4,273.20 100.00% 0.00 0.00 0.00% 9.50 4,273.20 100.00% 0.00 0.01 0.00%
02.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 76.00 51.41 3,907.16 76.00 3,907.16 100.00% 0.00 0.00 0.00% 76.00 3,907.16 100.00% 0.00 0.00 0.00%
02.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 1,204.33 4.18 5,034.10 1,204.33 5,034.10 100.00% 0.00 0.00 0.00% 1,204.33 5,034.10 100.00% 0.00 0.00 0.00%
02.01.04.03 COLUMNAS Y PLACAS 19,610.14
02.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 11.53 449.81 5,186.31 11.53 5,186.31 100.00% 0.00 0.00 0.00% 11.53 5,186.31 100.00% 0.00 0.00 0.00%
02.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 127.00 53.08 6,741.16 127.00 6,741.16 100.00% 0.00 0.00 0.00% 127.00 6,741.16 100.00% 0.00 0.00 0.00%
02.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 1,837.96 4.18 7,682.67 1,837.96 7,682.67 100.00% 0.00 0.00 0.00% 1,837.96 7,682.67 100.00% 0.00 0.00 0.00%
02.01.04.04 VIGAS 15,656.91
02.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 10.19 449.81 4,583.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.19 4,583.56 100.00%
02.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 98.14 62.13 6,097.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 98.14 6,097.44 100.00%
02.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 1,190.41 4.18 4,975.91 0.00 0.00 0.00% 1,190.41 4,975.91 100.00% 1,190.41 4,975.91 100.00% 0.00 0.00 0.00%

Página 7
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

02.01.04.05 COLUMNETAS 2,505.97


02.01.04.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 1.33 419.72 558.23 1.33 558.23 100.00% 0.00 0.00 0.00% 1.33 558.23 100.00% 0.00 0.00 0.00%
02.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 17.76 53.08 942.70 17.76 942.70 100.00% 0.00 0.00 0.00% 17.76 942.70 100.00% 0.00 0.00 0.00%
02.01.04.05.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 240.44 4.18 1,005.04 240.44 1,005.04 100.00% 0.00 0.00 0.00% 240.44 1,005.04 100.00% 0.00 0.00 0.00%
02.02 ARQUITECTURA 119,572.63
02.02.01 ALBAÑILERIA 6,173.76
02.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 111.48 55.38 6,173.76 111.48 6,173.76 100.00% 0.00 0.00 0.00% 111.48 6,173.76 100.00% 0.00 0.00 0.00%
02.02.02 REVOQUES 16,085.43
02.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 140.42 26.62 3,737.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.42 3,737.98 100.00%
02.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 93.80 26.62 2,496.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 93.80 2,496.96 100.00%
02.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 139.00 28.80 4,003.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 139.00 4,003.20 100.00%
02.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 245.20 3.45 845.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 245.20 845.94 100.00%
02.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 98.14 31.39 3,080.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 98.14 3,080.61 100.00%
02.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 99.44 3.45 343.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 99.44 343.07 100.00%
02.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 64.80 13.60 881.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 64.80 881.28 100.00%
02.02.02.08 BRUÑAS DE 1.0 cm m 74.72 9.32 696.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 74.72 696.39 100.00%
02.02.03 PISOS Y PAVIMENTOS 10,893.71
02.02.03.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 118.50 35.38 4,192.53 118.50 4,192.53 100.00% 0.00 0.00 0.00% 118.50 4,192.53 100.00% 0.00 0.00 0.00%
02.02.03.02 PISO DE CERAMICO 45 X 45 CM m2 118.50 56.55 6,701.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 118.50 6,701.18 100.00%
02.02.04 CONTRAZOCALOS 5,499.22
02.02.04.01 CONTRAZOCALO CERAMICO H=0.10 m. m 77.10 19.27 1,485.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.10 1,485.72 100.00%
02.02.04.02 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 96.80 15.40 1,490.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 96.80 1,490.72 100.00%
02.02.04.03 ZOCALO DE CERAMICA 20 X 30 CM m2 27.15 92.92 2,522.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.15 2,522.78 100.00%
02.02.05 CARPINTERIA MADERA 3,658.71
02.02.05.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 5.72 496.22 2,838.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.72 2,838.38 100.00%
02.02.05.02 PUERTA CONTRAPLACADA SEGUN DISEÑO m2 2.34 350.57 820.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.34 820.33 100.00%
02.02.06 CARPINTERIA METALICA 7,302.36
02.02.06.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 37.84 192.98 7,302.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.84 7,302.36 100.00%
02.02.07 CERRAJERIA 245.96
02.02.07.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
02.02.07.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 10.00 9.01 90.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 90.10 100.00%
02.02.08 VIDRIOS, CRISTALES Y SIMILARES 5,262.45
02.02.08.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 407.31 12.92 5,262.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 407.31 5,262.45 100.00%
02.02.09 PINTURAS 4,843.26
02.02.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 222.96 10.57 2,356.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 222.96 2,356.69 100.00%
02.02.09.02 PINTURA EN CONTRAZOCALO m2 9.68 7.96 77.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.68 77.05 100.00%
02.02.09.03 PINTURA EN VIGAS m2 98.14 13.73 1,347.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 98.14 1,347.46 100.00%
02.02.09.04 PINTURA EN COLUMNAS Y PLACAS m2 80.52 13.19 1,062.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 80.52 1,062.06 100.00%
02.02.10 CUBIERTA METALICA Y CIELO RASO 59,607.77
02.02.10.01 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 190.30 122.00 23,216.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 190.30 23,216.60 100.00%
02.02.10.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 183.00 75.18 13,757.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 183.00 13,757.94 100.00%
02.02.10.03 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 194.11 116.60 22,633.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 194.11 22,633.23 100.00%
02.03 INSTALACIONES ELECTRICAS 14,806.77
02.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 25.00 145.99 3,649.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 25.00 3,649.75 100.00%
02.03.02 SALIDA TOMACORRIENTE pto 8.00 215.17 1,721.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 1,721.36 100.00%
02.03.03 SALIDA TOMACORRIENTE A PRUEBA DE AGUA pto 2.00 219.38 438.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 438.76 100.00%
02.03.04 SALIDA PARA INTERRUPTOR SIMPLE pto 5.00 108.23 541.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 541.15 100.00%
02.03.05 SALIDA PARA INTERRUPTOR TRIPLE pto 2.00 114.38 228.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 228.76 100.00%
02.03.06 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 22.00 205.71 4,525.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.00 4,525.62 100.00%
02.03.07 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 3.00 68.59 205.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 205.77 100.00%
02.03.08 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 136.56 10.81 1,476.21 90.00 972.90 65.91% 0.00 0.00 0.00% 90.00 972.90 65.91% 46.56 503.31 34.09%
02.03.09 ALAMBRE THHN 2.5 mm2 m 264.68 1.67 442.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 264.68 442.02 100.00%
02.03.10 ALAMBRE THHN 4 mm2 m 106.00 2.19 232.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 106.00 232.14 100.00%
02.03.11 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
02.03.12 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
02.03.13 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
02.04 INSTALACIONES SANITARIAS 6,713.37
02.04.01 APARATOS Y ACCESORIOS SANITARIOS 1,193.88

Página 8
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

02.04.01.01 INODORO TANQUE BAJO pza 2.00 361.79 723.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 723.58 100.00%
02.04.01.02 LAVATORIO DE LOZA BLANCA und 2.00 195.88 391.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 391.76 100.00%
02.04.01.03 CAÑO DE BRONCE - LLAVE DE 1/2" und 2.00 39.27 78.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 78.54 100.00%
02.04.02 SISTEMA DE DESAGUE 2,066.22
02.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 2.00 93.15 186.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 186.30 100.00%
02.04.02.02 SALIDA DE DESAGUE PVC D=4" pto 2.00 145.54 291.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 291.08 100.00%
02.04.02.03 SALIDA VENTILACION DE 2" pto 2.00 58.08 116.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 116.16 100.00%
02.04.02.04 REGISTRO DE BRONCE 4" und 1.00 285.99 285.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 285.99 100.00%
02.04.02.05 SUMIDERO DE 2" pza 1.00 77.41 77.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 77.41 100.00%
02.04.02.06 TUBERIA PVC SAL P/DESAGUE D=4" m 10.00 33.95 339.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 339.50 100.00%
02.04.02.07 YEE PVC SAL 4"X2" und 3.00 61.97 185.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 185.91 100.00%
02.04.02.08 CODO PVC SAL P/DESAGUE D=2" und 2.00 25.81 51.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 51.62 100.00%
02.04.02.09 EXCAVACION MANUAL PARA TUBERIA m 10.00 14.89 148.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 148.90 100.00%
02.04.02.10 REFINE NIVELACION Y COMPACTACION DE ZANJA m 10.00 3.86 38.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 38.60 100.00%
02.04.02.11 CAMA DE APOYO m 10.00 9.44 94.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 94.40 100.00%
02.04.02.12 RELLENO COMPACTADO DE ZANJAS m 10.00 12.00 120.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 120.00 100.00%
02.04.02.13 CAJA DE REGISTRO CON REJILLA METALICA und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
02.04.03 SISTEMA DE AGUA FRIA 955.73
02.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 4.00 72.84 291.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 291.36 100.00%
02.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 8.05 17.01 136.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.05 136.93 100.00%
02.04.03.03 CODO PVC 1/2" und 1.00 9.94 9.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 9.94 100.00%
02.04.03.04 TEE PVC 1/2" und 3.00 11.04 33.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 33.12 100.00%
02.04.03.05 EXCAVACION MANUAL PARA TUBERIA m 7.05 14.89 104.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.05 104.97 100.00%
02.04.03.06 REFINE NIVELACION Y COMPACTACION DE ZANJA m 7.05 3.86 27.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.05 27.21 100.00%
02.04.03.07 CAMA DE APOYO m 7.05 9.44 66.55 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.05 66.55 100.00%
02.04.03.08 RELLENO COMPACTADO DE ZANJAS m 7.05 12.00 84.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.05 84.60 100.00%
02.04.03.09 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 1.00 70.70 70.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 70.70 100.00%
02.04.03.10 CAJA PARA VALVULAS und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
02.04.04 SISTEMA DE AGUA PLUVIAL 2,497.54
02.04.04.01 CANALETA PARA AGUA FLUVIAL DE 4" m 36.60 58.77 2,150.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.60 2,150.98 100.00%
02.04.04.02 TUBERIA PVC SAL D=4" m 6.00 45.40 272.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 272.40 100.00%
02.04.04.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 74.16 100.00%
03 SECTOR SECUNDARIA 373,415.79
03.01 ESTRUCTURAS 157,033.01
03.01.01 OBRAS PRELIMINARES 311.88
03.01.01.01 LIMPIEZA DE TERRENO m2 115.94 0.95 110.14 115.94 110.14 100.00% 0.00 0.00 0.00% 115.94 110.14 100.00% 0.00 0.00 0.00%
03.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 115.94 1.74 201.74 115.94 201.74 100.00% 0.00 0.00 0.00% 115.94 201.74 100.00% 0.00 0.00 0.00%
03.01.02 MOVIMIENTO DE TIERRAS 11,127.55
03.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 20.92 41.41 866.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.92 866.30 100.00%
03.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 85.68 41.41 3,548.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 85.68 3,548.01 100.00%
03.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 105.00 2.48 260.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 105.00 260.40 100.00%
03.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 55.88 27.36 1,528.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 55.88 1,528.88 100.00%
03.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 19.69 197.01 3,879.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19.69 3,879.13 100.00%
03.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 65.92 15.85 1,044.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 65.92 1,044.83 100.00%
03.01.03 OBRAS DE CONCRETO SIMPLE 12,111.33
03.01.03.01 SOLADO PARA ZAPATAS m2 65.83 35.13 2,312.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 65.83 2,312.61 100.00%
03.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.72 333.17 1,905.73 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.72 1,905.73 100.00%
03.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 3.70 387.67 1,434.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.70 1,434.38 100.00%
03.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 49.28 46.45 2,289.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.28 2,289.06 100.00%
03.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 105.00 39.71 4,169.55 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 105.00 4,169.55 100.00%
03.01.04 OBRAS DE CONCRETO ARMADO 133,482.25
03.01.04.01 ZAPATAS 20,484.56
03.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 35.51 449.81 15,972.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.51 15,972.75 100.00%
03.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 1,079.38 4.18 4,511.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,079.38 4,511.81 100.00%
03.01.04.02 VIGA DE CIMENTACION 12,509.61
03.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 8.59 449.81 3,863.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.59 3,863.87 100.00%
03.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 68.75 51.41 3,534.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 68.75 3,534.44 100.00%
03.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 1,222.80 4.18 5,111.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,222.80 5,111.30 100.00%

Página 9
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

03.01.04.03 COLUMNAS Y PLACAS 47,206.14


03.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 27.42 449.81 12,333.79 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.42 12,333.79 100.00%
03.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 281.66 53.08 14,950.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 281.66 14,950.51 100.00%
03.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 4,765.99 4.18 19,921.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4,765.99 19,921.84 100.00%
03.01.04.04 VIGAS 27,967.41
03.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 16.99 449.81 7,642.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.99 7,642.27 100.00%
03.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 163.64 62.13 10,166.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 163.64 10,166.95 100.00%
03.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 2,430.19 4.18 10,158.19 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,430.19 10,158.19 100.00%
03.01.04.05 LOSAS ALIGERADAS 16,968.05
03.01.04.05.01 CONCRETO LOSA ALIGERADA f'c= 210 kg/cm2 m3 11.60 449.81 5,217.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.60 5,217.80 100.00%
03.01.04.05.02 LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO m2 132.54 51.12 6,775.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.54 6,775.44 100.00%
03.01.04.05.03 LOSAS ALIGERADAS ACERO fy=4,200 kg/cm2 kg 466.17 4.18 1,948.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 466.17 1,948.59 100.00%
03.01.04.05.04 LOSA ALIGERADA LADRILLO HUECO 15X30X30 und 1,104.46 2.74 3,026.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,104.46 3,026.22 100.00%
03.01.04.06 COLUMNETAS 7,805.24
03.01.04.06.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 4.39 419.72 1,842.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.39 1,842.57 100.00%
03.01.04.06.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 58.56 53.08 3,108.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.56 3,108.36 100.00%
03.01.04.06.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 682.85 4.18 2,854.31 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 682.85 2,854.31 100.00%
03.01.04.07 VIGAS COLLARIN 541.24
03.01.04.07.01 CONCRETO VIGAS COLLARIN f'c=175 kg/cm2 m3 0.38 419.72 159.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.38 159.49 100.00%
03.01.04.07.02 ENCOFRADO Y DESENCOFRADO EN VIGAS COLLARIN m2 5.12 53.08 271.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.12 271.77 100.00%
03.01.04.07.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN VIGAS COLLARIN kg 26.31 4.18 109.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.31 109.98 100.00%
03.02 ARQUITECTURA 161,830.49
03.02.01 ALBAÑILERIA 8,900.12
03.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 160.71 55.38 8,900.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 160.71 8,900.12 100.00%
03.02.02 REVOQUES 27,991.70
03.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 210.39 26.62 5,600.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 210.39 5,600.58 100.00%
03.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 111.03 26.62 2,955.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 111.03 2,955.62 100.00%
03.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 281.66 28.80 8,111.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 281.66 8,111.81 100.00%
03.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 439.60 3.45 1,516.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 439.60 1,516.62 100.00%
03.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 163.64 31.39 5,136.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 163.64 5,136.66 100.00%
03.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 398.80 3.45 1,375.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 398.80 1,375.86 100.00%
03.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 115.20 13.60 1,566.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 115.20 1,566.72 100.00%
03.02.02.08 BRUÑAS DE 1.0 cm m 185.39 9.32 1,727.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 185.39 1,727.83 100.00%
03.02.03 CIELO RASO 5,746.93
03.02.03.01 TARRAJEO DE CIELO RASO - SUPERFICIE CON CEMENTO-A m2 132.54 43.36 5,746.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.54 5,746.93 100.00%
03.02.04 PISOS Y PAVIMENTOS 20,912.44
03.02.04.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 210.00 35.38 7,429.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 210.00 7,429.80 100.00%
03.02.04.02 PISO DE CERAMICO 45 X 45 CM m2 210.00 56.55 11,875.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 210.00 11,875.50 100.00%
03.02.04.03 PISO CEMENTO PULIDO E=2" m2 30.99 51.86 1,607.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 30.99 1,607.14 100.00%
03.02.05 CONTRAZOCALOS 3,920.57
03.02.05.01 CONTRAZOCALO CERAMICO H=0.10 m. m 140.40 19.27 2,705.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.40 2,705.51 100.00%
03.02.05.02 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 78.90 15.40 1,215.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 78.90 1,215.06 100.00%
03.02.06 CARPINTERIA MADERA 7,443.30
03.02.06.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 15.00 496.22 7,443.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 7,443.30 100.00%
03.02.07 CARPINTERIA METALICA 10,768.28
03.02.07.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 55.80 192.98 10,768.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 55.80 10,768.28 100.00%
03.02.08 CERRAJERIA 629.76
03.02.08.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 6.00 77.93 467.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 467.58 100.00%
03.02.08.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 18.00 9.01 162.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 162.18 100.00%
03.02.09 VIDRIOS, CRISTALES Y SIMILARES 7,760.14
03.02.09.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 600.63 12.92 7,760.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 600.63 7,760.14 100.00%
03.02.10 PINTURAS 9,374.13
03.02.10.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 331.68 10.57 3,505.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 331.68 3,505.86 100.00%
03.02.10.02 PINTURA EN CONTRAZOCALO m2 44.48 7.96 354.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 44.48 354.06 100.00%
03.02.10.03 PINTURA EN VIGAS m2 124.98 13.73 1,715.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 124.98 1,715.98 100.00%
03.02.10.04 PINTURA EN COLUMNAS m2 181.75 13.19 2,397.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 181.75 2,397.28 100.00%
03.02.10.05 PINTURA EN CIELO RASO m2 132.54 10.57 1,400.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.54 1,400.95 100.00%
03.02.11 CUBIERTA METALICA Y CIELO RASO 58,383.12

Página 10
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

03.02.11.01 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 185.92 116.60 21,678.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 185.92 21,678.27 100.00%
03.02.11.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 180.50 75.18 13,569.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 180.50 13,569.99 100.00%
03.02.11.03 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 189.63 122.00 23,134.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 189.63 23,134.86 100.00%
03.03 INSTALACIONES ELECTRICAS 26,845.81
03.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 48.00 145.99 7,007.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 48.00 7,007.52 100.00%
03.03.02 SALIDA TOMACORRIENTE pto 18.00 215.17 3,873.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 3,873.06 100.00%
03.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 108.23 100.00%
03.03.04 SALIDA PARA INTERRUPTOR DOBLE pto 6.00 112.89 677.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 677.34 100.00%
03.03.05 SALIDA PARA INTERRUPTOR TRIPLE pto 2.00 114.38 228.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 228.76 100.00%
03.03.06 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 48.00 205.71 9,874.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 48.00 9,874.08 100.00%
03.03.07 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 1.00 68.59 68.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 68.59 100.00%
03.03.08 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 218.62 10.81 2,363.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 218.62 2,363.28 100.00%
03.03.09 ALAMBRE THHN 2.5 mm2 m 324.68 1.67 542.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 324.68 542.22 100.00%
03.03.10 ALAMBRE THHN 4 mm2 m 131.32 2.19 287.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 131.32 287.59 100.00%
03.03.11 TABLERO DE DISTRIBUCION und 1.00 469.91 469.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 469.91 100.00%
03.03.12 SUBTABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
03.03.13 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
03.03.14 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
03.04 INSTALACIONES SANITARIAS 2,809.47
03.04.01 SISTEMA DE AGUA PLUVIAL 2,809.47
03.04.01.01 CANALETA PARA AGUA FLUVIAL DE 4" m 36.50 58.77 2,145.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.50 2,145.11 100.00%
03.04.01.02 TUBERIA PVC SAL D=4" m 13.00 45.40 590.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.00 590.20 100.00%
03.04.01.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 74.16 100.00%
03.05 CONSTRUCCION DE ESCALERAS 24,897.01
03.05.01 OBRAS PRELIMINARES 48.31
03.05.01.01 LIMPIEZA DE TERRENO m2 17.96 0.95 17.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.96 17.06 100.00%
03.05.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 17.96 1.74 31.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.96 31.25 100.00%
03.05.02 MOVIMIENTO DE TIERRAS 1,179.42
03.05.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 13.85 41.41 573.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.85 573.53 100.00%
03.05.02.02 NIVELACION Y APISONADO MANUAL PARA PISOS m2 14.13 2.48 35.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 35.04 100.00%
03.05.02.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 3.54 27.36 96.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.54 96.85 100.00%
03.05.02.04 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 1.41 197.01 277.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.41 277.78 100.00%
03.05.02.05 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 12.38 15.85 196.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.38 196.22 100.00%
03.05.03 OBRAS DE CONCRETO SIMPLE 3,851.27
03.05.03.01 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.33 333.17 1,775.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.33 1,775.80 100.00%
03.05.03.02 SOBRECIMIENTO 1:8 + 25% P.M m3 1.74 387.67 674.55 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.74 674.55 100.00%
03.05.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 18.08 46.45 839.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.08 839.82 100.00%
03.05.03.04 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 14.13 39.71 561.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 561.10 100.00%
03.05.04 OBRAS DE CONCRETO ARMADO 11,546.69
03.05.04.01 VIGA DE CIMENTACION 2,645.43
03.05.04.01.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 2.00 449.81 899.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 899.62 100.00%
03.05.04.01.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 20.02 51.41 1,029.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.02 1,029.23 100.00%
03.05.04.01.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 171.43 4.18 716.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 171.43 716.58 100.00%
03.05.04.02 COLUMNAS 2,896.60
03.05.04.02.01 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 1.67 449.81 751.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.67 751.18 100.00%
03.05.04.02.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 15.07 53.08 799.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 799.92 100.00%
03.05.04.02.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS kg 321.89 4.18 1,345.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 321.89 1,345.50 100.00%
03.05.04.03 VIGAS 2,222.94
03.05.04.03.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 1.66 449.81 746.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.66 746.68 100.00%
03.05.04.03.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 12.90 62.13 801.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 801.48 100.00%
03.05.04.03.03 VIGAS ACERO fy=4,200 kg/cm2 kg 161.43 4.18 674.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 161.43 674.78 100.00%
03.05.04.04 ESCALERAS 2,484.68
03.05.04.04.01 ESCALERAS CONCRETO FC=210 KG/CM2 m3 1.89 449.81 850.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.89 850.14 100.00%
03.05.04.04.02 ESCALERA ENCOFRADO Y DESENCOFRADO m2 11.19 60.97 682.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.19 682.25 100.00%
03.05.04.04.03 ESCALERA ACERO fy=4,200 kg/cm2 kg 227.82 4.18 952.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 227.82 952.29 100.00%
03.05.04.05 LOSA MACIZA 1,297.04
03.05.04.05.01 LOSA MACIZA CONCRETO FC=210 KG/CM2 m3 0.77 449.81 346.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.77 346.35 100.00%
03.05.04.05.02 ENCOFRADO Y DESENCOFRADO DE LOSA MACIZA m2 5.15 54.29 279.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.15 279.59 100.00%

Página 11
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

03.05.04.05.03 LOSA MACIZA ACERO fy=4,200 kg/cm2 kg 160.55 4.18 671.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 160.55 671.10 100.00%
03.05.05 ALBAÑILERIA 1,616.54
03.05.05.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 29.19 55.38 1,616.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 29.19 1,616.54 100.00%
03.05.06 REVOQUES 4,512.97
03.05.06.01 TARRAJEO EN EXTERIORES C:A-1:4 m2 58.38 26.62 1,554.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.38 1,554.08 100.00%
03.05.06.02 TARRAJEO DE COLUMNAS C:A-1:4 m2 15.07 28.80 434.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 434.02 100.00%
03.05.06.03 VESTIDURA DE ARISTAS EN COLUMNAS m 64.72 3.45 223.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 64.72 223.28 100.00%
03.05.06.04 TARRAJEO DE VIGAS C:A-1:4 m2 12.90 31.39 404.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 404.93 100.00%
03.05.06.05 VESTIDURA DE ARISTAS EN VIGAS m 51.73 3.45 178.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 51.73 178.47 100.00%
03.05.06.06 BRUÑAS DE 1.0 cm m 82.78 9.32 771.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 82.78 771.51 100.00%
03.05.06.07 REVESTIMIENTO DE GRADAS Y ESCALERA m2 15.39 36.85 567.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.39 567.12 100.00%
03.05.06.08 REVESTIMIENTO DE FONDO DE ESCALERAS CON CEMENTO m2 10.30 36.85 379.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.30 379.56 100.00%
03.05.07 PISOS 732.78
03.05.07.01 PISO CEMENTO PULIDO E=2" m2 14.13 51.86 732.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 732.78 100.00%
03.05.08 CONTRAZOCALOS 262.11
03.05.08.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 17.02 15.40 262.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.02 262.11 100.00%
03.05.09 PINTURAS 1,146.92
03.05.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 58.38 10.57 617.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.38 617.08 100.00%
03.05.09.02 PINTURA EN COLUMNAS m2 15.07 13.19 198.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 198.77 100.00%
03.05.09.03 PINTURA EN VIGAS m2 12.90 13.73 177.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 177.12 100.00%
03.05.09.04 PINTURA EN FONDO DE ESCALERA m2 8.39 11.37 95.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.39 95.39 100.00%
03.05.09.05 PINTURA EN LOSA MACIZA m2 5.15 11.37 58.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.15 58.56 100.00%
04 ADMINISTRACION, SALA DE COMPUTO Y SALON DE USOS MULTIPLES 379,732.21
04.01 ESTRUCTURAS 139,933.65
04.01.01 OBRAS PRELIMINARES 350.61
04.01.01.01 LIMPIEZA DE TERRENO m2 130.34 0.95 123.82 130.34 123.82 100.00% 0.00 0.00 0.00% 130.34 123.82 100.00% 0.00 0.00 0.00%
04.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 130.34 1.74 226.79 130.34 226.79 100.00% 0.00 0.00 0.00% 130.34 226.79 100.00% 0.00 0.00 0.00%
04.01.02 MOVIMIENTO DE TIERRAS 8,554.41
04.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 16.51 41.41 683.68 0.00 0.00 0.00% 16.51 683.68 100.00% 16.51 683.68 100.00% 0.00 0.00 0.00%
04.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 83.01 41.41 3,437.44 0.00 0.00 0.00% 83.01 3,437.44 100.00% 83.01 3,437.44 100.00% 0.00 0.00 0.00%
04.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 105.58 2.48 261.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 105.58 261.84 100.00%
04.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 26.24 27.36 717.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.24 717.93 100.00%
04.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 10.56 197.01 2,080.43 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.56 2,080.43 100.00%
04.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 86.63 15.85 1,373.09 0.00 0.00 0.00% 86.63 1,373.09 100.00% 86.63 1,373.09 100.00% 0.00 0.00 0.00%
04.01.03 OBRAS DE CONCRETO SIMPLE 12,520.73
04.01.03.01 SOLADO PARA ZAPATAS m2 63.86 35.13 2,243.40 0.00 0.00 0.00% 63.86 2,243.40 100.00% 63.86 2,243.40 100.00% 0.00 0.00 0.00%
04.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 6.35 333.17 2,115.63 0.00 0.00 0.00% 6.35 2,115.63 100.00% 6.35 2,115.63 100.00% 0.00 0.00 0.00%
04.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 5.23 387.67 2,027.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.23 2,027.51 100.00%
04.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 41.80 46.45 1,941.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 41.80 1,941.61 100.00%
04.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 105.58 39.71 4,192.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 105.58 4,192.58 100.00%
04.01.04 OBRAS DE CONCRETO ARMADO 118,507.90
04.01.04.01 ZAPATAS 20,173.23
04.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 34.85 449.81 15,675.88 0.00 0.00 0.00% 34.85 15,675.88 100.00% 34.85 15,675.88 100.00% 0.00 0.00 0.00%
04.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 1,075.92 4.18 4,497.35 0.00 0.00 0.00% 1,075.92 4,497.35 100.00% 1,075.92 4,497.35 100.00% 0.00 0.00 0.00%
04.01.04.02 VIGA DE CIMENTACION 11,190.06
04.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 7.98 449.81 3,589.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.98 3,589.48 100.00%
04.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 63.80 51.41 3,279.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.80 3,279.96 100.00%
04.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 1,033.64 4.18 4,320.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,033.64 4,320.62 100.00%
04.01.04.03 COLUMNAS Y PLACAS 35,879.80
04.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 21.44 449.81 9,643.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 21.44 9,643.93 100.00%
04.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 216.32 53.08 11,482.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 216.32 11,482.27 100.00%
04.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 3,529.57 4.18 14,753.60 0.00 0.00 0.00% 3,529.57 14,753.60 100.00% 3,529.57 14,753.60 100.00% 0.00 0.00 0.00%
04.01.04.04 VIGAS 23,771.80
04.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 16.27 449.81 7,318.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.27 7,318.41 100.00%
04.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 132.75 62.13 8,247.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.75 8,247.76 100.00%
04.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 1,963.07 4.18 8,205.63 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,963.07 8,205.63 100.00%
04.01.04.05 LOSAS ALIGERADAS 19,154.31
04.01.04.05.01 CONCRETO LOSA ALIGERADA f'c= 210 kg/cm2 m3 12.45 449.81 5,600.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.45 5,600.13 100.00%

Página 12
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

04.01.04.05.02 LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO m2 142.31 51.12 7,274.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 142.31 7,274.89 100.00%
04.01.04.05.03 LOSAS ALIGERADAS ACERO fy=4,200 kg/cm2 kg 724.91 4.18 3,030.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 724.91 3,030.12 100.00%
04.01.04.05.04 LOSA ALIGERADA LADRILLO HUECO 15X30X30 und 1,185.83 2.74 3,249.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,185.83 3,249.17 100.00%
04.01.04.06 COLUMNETAS 7,823.00
04.01.04.06.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 3.44 419.72 1,443.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.44 1,443.84 100.00%
04.01.04.06.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 77.48 53.08 4,112.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.48 4,112.64 100.00%
04.01.04.06.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 542.23 4.18 2,266.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 542.23 2,266.52 100.00%
04.01.04.07 VIGAS COLLARIN 515.70
04.01.04.07.01 CONCRETO VIGAS COLLARIN f'c=175 kg/cm2 m3 0.36 419.72 151.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.36 151.10 100.00%
04.01.04.07.02 ENCOFRADO Y DESENCOFRADO EN VIGAS COLLARIN m2 4.79 53.08 254.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.79 254.25 100.00%
04.01.04.07.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN VIGAS COLLARIN kg 26.40 4.18 110.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.40 110.35 100.00%
04.02 ARQUITECTURA 174,570.71
04.02.01 ALBAÑILERIA 8,721.24
04.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 157.48 55.38 8,721.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 157.48 8,721.24 100.00%
04.02.02 REVOQUES 24,798.60
04.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 208.54 26.62 5,551.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 208.54 5,551.33 100.00%
04.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 161.28 26.62 4,293.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 161.28 4,293.27 100.00%
04.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 216.32 28.80 6,230.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 216.32 6,230.02 100.00%
04.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 191.40 3.45 660.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 191.40 660.33 100.00%
04.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 132.75 31.39 4,167.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.75 4,167.02 100.00%
04.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 216.98 3.45 748.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 216.98 748.58 100.00%
04.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 138.00 13.60 1,876.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 138.00 1,876.80 100.00%
04.02.02.08 BRUÑAS DE 1.0 cm m 136.40 9.32 1,271.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 136.40 1,271.25 100.00%
04.02.03 CIELO RASO 6,170.56
04.02.03.01 TARRAJEO DE CIELO RASO - SUPERFICIE CON CEMENTO-A m2 142.31 43.36 6,170.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 142.31 6,170.56 100.00%
04.02.04 PISOS Y PAVIMENTOS 23,179.67
04.02.04.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 232.88 35.38 8,239.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 232.88 8,239.29 100.00%
04.02.04.02 PISO DE CERAMICO 45 X 45 CM m2 232.88 56.55 13,169.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 232.88 13,169.36 100.00%
04.02.04.03 PISO CEMENTO PULIDO E=2" m2 34.15 51.86 1,771.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 34.15 1,771.02 100.00%
04.02.05 CONTRAZOCALOS 5,606.04
04.02.05.01 CONTRAZOCALO CERAMICO H=0.10 m. m 138.18 19.27 2,662.73 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 138.18 2,662.73 100.00%
04.02.05.02 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 76.00 15.40 1,170.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.00 1,170.40 100.00%
04.02.05.03 ZOCALO DE CERAMICA 20 X 30 CM m2 19.08 92.92 1,772.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19.08 1,772.91 100.00%
04.02.06 CARPINTERIA MADERA 9,607.44
04.02.06.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 16.50 496.22 8,187.63 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.50 8,187.63 100.00%
04.02.06.02 PUERTA CONTRAPLACADA SEGUN DISEÑO m2 4.05 350.57 1,419.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.05 1,419.81 100.00%
04.02.07 CARPINTERIA METALICA 13,514.39
04.02.07.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 70.03 192.98 13,514.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 70.03 13,514.39 100.00%
04.02.08 CERRAJERIA 839.68
04.02.08.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 8.00 77.93 623.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 623.44 100.00%
04.02.08.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 24.00 9.01 216.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.00 216.24 100.00%
04.02.09 VIDRIOS, CRISTALES Y SIMILARES 9,738.32
04.02.09.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 753.74 12.92 9,738.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 753.74 9,738.32 100.00%
04.02.10 PINTURAS 10,210.13
04.02.10.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 369.82 10.57 3,909.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 369.82 3,909.00 100.00%
04.02.10.02 PINTURA EN CONTRAZOCALO m2 15.20 7.96 120.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.20 120.99 100.00%
04.02.10.03 PINTURA EN VIGAS m2 132.75 13.73 1,822.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.75 1,822.66 100.00%
04.02.10.04 PINTURA EN COLUMNAS Y PLACAS m2 216.32 13.19 2,853.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 216.32 2,853.26 100.00%
04.02.10.05 PINTURA EN CIELO RASO m2 142.31 10.57 1,504.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 142.31 1,504.22 100.00%
04.02.11 CUBIERTA METALICA Y CIELO RASO 62,184.64
04.02.11.01 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 201.47 122.00 24,579.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 201.47 24,579.34 100.00%
04.02.11.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 181.50 75.18 13,645.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 181.50 13,645.17 100.00%
04.02.11.03 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 205.49 116.60 23,960.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 205.49 23,960.13 100.00%
04.03 INSTALACIONES ELECTRICAS 33,036.01
04.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 41.00 145.99 5,985.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 41.00 5,985.59 100.00%
04.03.02 SALIDA TOMACORRIENTE pto 54.00 215.17 11,619.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 54.00 11,619.18 100.00%
04.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 8.00 108.23 865.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 865.84 100.00%
04.03.04 SALIDA PARA INTERRUPTOR TRIPLE pto 2.00 114.38 228.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 228.76 100.00%

Página 13
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

04.03.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 38.00 205.71 7,816.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 38.00 7,816.98 100.00%
04.03.06 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 2.00 68.59 137.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 137.18 100.00%
04.03.07 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 285.11 10.81 3,082.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 285.11 3,082.04 100.00%
04.03.08 ALAMBRE THHN 2.5 mm2 m 344.56 1.67 575.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 344.56 575.42 100.00%
04.03.09 ALAMBRE THHN 4 mm2 m 415.47 2.19 909.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 415.47 909.88 100.00%
04.03.10 TABLERO DE DISTRIBUCION und 1.00 469.91 469.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 469.91 100.00%
04.03.11 SUBTABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
04.03.12 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
04.03.13 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
04.04 INSTALACIONES SANITARIAS 7,294.83
04.04.01 APARATOS Y ACCESORIOS SANITARIOS 1,193.88
04.04.01.01 INODORO TANQUE BAJO pza 2.00 361.79 723.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 723.58 100.00%
04.04.01.02 LAVATORIO DE LOZA BLANCA und 2.00 195.88 391.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 391.76 100.00%
04.04.01.03 CAÑO DE BRONCE - LLAVE DE 1/2" und 2.00 39.27 78.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 78.54 100.00%
04.04.02 SISTEMA DE DESAGUE 2,175.09
04.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 2.00 93.15 186.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 186.30 100.00%
04.04.02.02 SALIDA DE DESAGUE PVC D=4" pto 2.00 145.54 291.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 291.08 100.00%
04.04.02.03 SALIDA VENTILACION DE 2" pto 1.00 58.08 58.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 58.08 100.00%
04.04.02.04 REGISTRO DE BRONCE 4" und 1.00 285.99 285.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 285.99 100.00%
04.04.02.05 SUMIDERO DE 2" pza 2.00 77.41 154.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 154.82 100.00%
04.04.02.06 TUBERIA PVC SAL P/DESAGUE D=4" m 10.47 33.95 355.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.47 355.46 100.00%
04.04.02.07 YEE PVC SAL 4"X2" und 2.00 61.97 123.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 123.94 100.00%
04.04.02.08 YEE PVC SAL 2"X2" und 2.00 58.33 116.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 116.66 100.00%
04.04.02.09 CODO PVC SAL P/DESAGUE D=2" und 2.00 25.81 51.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 51.62 100.00%
04.04.02.10 EXCAVACION MANUAL PARA TUBERIA m 10.47 14.89 155.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.47 155.90 100.00%
04.04.02.11 REFINE NIVELACION Y COMPACTACION DE ZANJA m 10.47 3.86 40.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.47 40.41 100.00%
04.04.02.12 CAMA DE APOYO m 10.47 9.44 98.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.47 98.84 100.00%
04.04.02.13 RELLENO COMPACTADO DE ZANJAS m 10.47 12.00 125.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.47 125.64 100.00%
04.04.02.14 CAJA DE REGISTRO CON REJILLA METALICA und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
04.04.03 SISTEMA DE AGUA FRIA 1,193.38
04.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 4.00 72.84 291.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 291.36 100.00%
04.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 4.01 17.01 68.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.01 68.21 100.00%
04.04.03.03 TUBERIA PVC SAP CLASE 10-3/4" m 7.00 18.07 126.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.00 126.49 100.00%
04.04.03.04 CODO PVC 1/2" und 2.00 9.94 19.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 19.88 100.00%
04.04.03.05 TEE PVC 1/2" und 3.00 11.04 33.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 33.12 100.00%
04.04.03.06 CODO PVC 3/4" und 1.00 10.78 10.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 10.78 100.00%
04.04.03.07 EXCAVACION MANUAL PARA TUBERIA m 11.01 14.89 163.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.01 163.94 100.00%
04.04.03.08 REFINE NIVELACION Y COMPACTACION DE ZANJA m 11.01 3.86 42.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.01 42.50 100.00%
04.04.03.09 CAMA DE APOYO m 11.01 9.44 103.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.01 103.93 100.00%
04.04.03.10 RELLENO COMPACTADO DE ZANJAS m 11.01 12.00 132.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.01 132.12 100.00%
04.04.03.11 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 1.00 70.70 70.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 70.70 100.00%
04.04.03.12 CAJA PARA VALVULAS und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
04.04.04 SISTEMA DE AGUA PLUVIAL 2,732.48
04.04.04.01 CANALETA PARA AGUA FLUVIAL DE 4" m 32.10 58.77 1,886.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 32.10 1,886.52 100.00%
04.04.04.02 TUBERIA PVC SAL D=4" m 17.00 45.40 771.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.00 771.80 100.00%
04.04.04.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 74.16 100.00%
04.05 CONSTRUCCION DE ESCALERAS 24,897.01
04.05.01 OBRAS PRELIMINARES 48.31
04.05.01.01 LIMPIEZA DE TERRENO m2 17.96 0.95 17.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.96 17.06 100.00%
04.05.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 17.96 1.74 31.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.96 31.25 100.00%
04.05.02 MOVIMIENTO DE TIERRAS 1,179.42
04.05.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 13.85 41.41 573.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.85 573.53 100.00%
04.05.02.02 NIVELACION Y APISONADO MANUAL PARA PISOS m2 14.13 2.48 35.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 35.04 100.00%
04.05.02.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 3.54 27.36 96.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.54 96.85 100.00%
04.05.02.04 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 1.41 197.01 277.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.41 277.78 100.00%
04.05.02.05 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 12.38 15.85 196.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.38 196.22 100.00%
04.05.03 OBRAS DE CONCRETO SIMPLE 3,851.27
04.05.03.01 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.33 333.17 1,775.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.33 1,775.80 100.00%

Página 14
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

04.05.03.02 SOBRECIMIENTO 1:8 + 25% P.M m3 1.74 387.67 674.55 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.74 674.55 100.00%
04.05.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 18.08 46.45 839.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.08 839.82 100.00%
04.05.03.04 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 14.13 39.71 561.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 561.10 100.00%
04.05.04 OBRAS DE CONCRETO ARMADO 11,546.69 0.00
04.05.04.01 VIGA DE CIMENTACION 2,645.43
04.05.04.01.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 2.00 449.81 899.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 899.62 100.00%
04.05.04.01.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 20.02 51.41 1,029.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.02 1,029.23 100.00%
04.05.04.01.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 171.43 4.18 716.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 171.43 716.58 100.00%
04.05.04.02 COLUMNAS 2,896.60
04.05.04.02.01 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 1.67 449.81 751.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.67 751.18 100.00%
04.05.04.02.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 15.07 53.08 799.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 799.92 100.00%
04.05.04.02.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS kg 321.89 4.18 1,345.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 321.89 1,345.50 100.00%
04.05.04.03 VIGAS 2,222.94
04.05.04.03.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 1.66 449.81 746.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.66 746.68 100.00%
04.05.04.03.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 12.90 62.13 801.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 801.48 100.00%
04.05.04.03.03 VIGAS ACERO fy=4,200 kg/cm2 kg 161.43 4.18 674.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 161.43 674.78 100.00%
04.05.04.04 ESCALERAS 2,484.68
04.05.04.04.01 ESCALERAS CONCRETO FC=210 KG/CM2 m3 1.89 449.81 850.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.89 850.14 100.00%
04.05.04.04.02 ESCALERA ENCOFRADO Y DESENCOFRADO m2 11.19 60.97 682.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.19 682.25 100.00%
04.05.04.04.03 ESCALERA ACERO fy=4,200 kg/cm2 kg 227.82 4.18 952.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 227.82 952.29 100.00%
04.05.04.05 LOSA MACIZA 1,297.04
04.05.04.05.01 LOSA MACIZA CONCRETO FC=210 KG/CM2 m3 0.77 449.81 346.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.77 346.35 100.00%
04.05.04.05.02 ENCOFRADO Y DESENCOFRADO DE LOSA MACIZA m2 5.15 54.29 279.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.15 279.59 100.00%
04.05.04.05.03 LOSA MACIZA ACERO fy=4,200 kg/cm2 kg 160.55 4.18 671.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 160.55 671.10 100.00%
04.05.05 ALBAÑILERIA 1,616.54
04.05.05.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 29.19 55.38 1,616.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 29.19 1,616.54 100.00%
04.05.06 REVOQUES 4,512.97
04.05.06.01 TARRAJEO EN EXTERIORES C:A-1:4 m2 58.38 26.62 1,554.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.38 1,554.08 100.00%
04.05.06.02 TARRAJEO DE COLUMNAS C:A-1:4 m2 15.07 28.80 434.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 434.02 100.00%
04.05.06.03 VESTIDURA DE ARISTAS EN COLUMNAS m 64.72 3.45 223.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 64.72 223.28 100.00%
04.05.06.04 TARRAJEO DE VIGAS C:A-1:4 m2 12.90 31.39 404.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 404.93 100.00%
04.05.06.05 VESTIDURA DE ARISTAS EN VIGAS m 51.73 3.45 178.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 51.73 178.47 100.00%
04.05.06.06 BRUÑAS DE 1.0 cm m 82.78 9.32 771.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 82.78 771.51 100.00%
04.05.06.07 REVESTIMIENTO DE GRADAS Y ESCALERA m2 15.39 36.85 567.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.39 567.12 100.00%
04.05.06.08 REVESTIMIENTO DE FONDO DE ESCALERAS CON CEMENTO m2 10.30 36.85 379.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.30 379.56 100.00%
04.05.07 PISOS 732.78
04.05.07.01 PISO CEMENTO PULIDO E=2" m2 14.13 51.86 732.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 732.78 100.00%
04.05.08 CONTRAZOCALOS 262.11
04.05.08.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 17.02 15.40 262.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.02 262.11 100.00%
04.05.09 PINTURAS 1,146.92
04.05.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 58.38 10.57 617.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.38 617.08 100.00%
04.05.09.02 PINTURA EN COLUMNAS m2 15.07 13.19 198.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 198.77 100.00%
04.05.09.03 PINTURA EN VIGAS m2 12.90 13.73 177.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 177.12 100.00%
04.05.09.04 PINTURA EN FONDO DE ESCALERA m2 8.39 11.37 95.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.39 95.39 100.00%
04.05.09.05 PINTURA EN LOSA MACIZA m2 5.15 11.37 58.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.15 58.56 100.00%
05 CONSTRUCCION DE COMEDOR 144,917.87
05.01 ESTRUCTURAS 52,611.09
05.01.01 OBRAS PRELIMINARES 188.04
05.01.01.01 LIMPIEZA DE TERRENO m2 69.90 0.95 66.41 69.90 66.41 100.00% 0.00 0.00 0.00% 69.90 66.41 100.00% 0.00 0.00 0.01%
05.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 69.90 1.74 121.63 69.90 121.63 100.00% 0.00 0.00 0.00% 69.90 121.63 100.00% 0.00 0.00 0.00%
05.01.02 MOVIMIENTO DE TIERRAS 4,303.76
05.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 18.27 41.41 756.56 18.27 756.56 100.00% 0.00 0.00 0.00% 18.27 756.56 100.00% 0.00 0.00 0.00%
05.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 25.91 41.41 1,072.93 25.91 1,072.93 100.00% 0.00 0.00 0.00% 25.91 1,072.93 100.00% 0.00 0.00 0.00%
05.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 63.56 2.48 157.63 63.56 157.63 100.00% 0.00 0.00 0.00% 63.56 157.63 100.00% 0.00 0.00 0.00%
05.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 29.59 27.36 809.58 29.59 809.58 100.00% 0.00 0.00 0.00% 29.59 809.58 100.00% 0.00 0.00 0.00%
05.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 6.36 197.01 1,252.98 6.36 1,252.98 100.00% 0.00 0.00 0.00% 6.36 1,252.98 100.00% 0.00 0.00 0.00%
05.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 16.03 15.85 254.08 16.03 254.08 100.00% 0.00 0.00 0.00% 16.03 254.08 100.00% 0.00 0.00 0.00%
05.01.03 OBRAS DE CONCRETO SIMPLE 7,695.11

Página 15
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

05.01.03.01 SOLADO PARA ZAPATAS m2 19.93 35.13 700.14 19.93 700.14 100.00% 0.00 0.00 0.00% 19.93 700.14 100.00% 0.00 0.00 0.00%
05.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.29 333.17 1,762.47 5.29 1,762.47 100.00% 0.00 0.00 0.00% 5.29 1,762.47 100.00% 0.00 0.00 0.00%
05.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 2.69 387.67 1,042.83 2.69 1,042.83 100.00% 0.00 0.00 0.00% 2.69 1,042.83 100.00% 0.00 0.00 0.00%
05.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 35.86 46.45 1,665.70 35.86 1,665.70 100.00% 0.00 0.00 0.00% 35.86 1,665.70 100.00% 0.00 0.00 0.00%
05.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 63.56 39.71 2,523.97 63.56 2,523.97 100.00% 0.00 0.00 0.00% 63.56 2,523.97 100.00% 0.00 0.00 0.00%
05.01.04 OBRAS DE CONCRETO ARMADO 40,424.18
05.01.04.01 ZAPATAS 5,545.41
05.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 9.97 449.81 4,484.61 9.97 4,484.61 100.00% 0.00 0.00 0.00% 9.97 4,484.61 100.00% 0.00 0.00 0.00%
05.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 253.78 4.18 1,060.80 253.78 1,060.80 100.00% 0.00 0.00 0.00% 253.78 1,060.80 100.00% 0.00 0.00 0.00%
05.01.04.02 VIGA DE CIMENTACION 8,818.36
05.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 6.35 449.81 2,856.29 6.35 2,856.29 100.00% 0.00 0.00 0.00% 6.35 2,856.29 100.00% 0.00 0.00 0.00%
05.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 50.80 51.41 2,611.63 50.80 2,611.63 100.00% 0.00 0.00 0.00% 50.80 2,611.63 100.00% 0.00 0.00 0.00%
05.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 801.54 4.18 3,350.44 801.54 3,350.44 100.00% 0.00 0.00 0.00% 801.54 3,350.44 100.00% 0.00 0.00 0.00%
05.01.04.03 COLUMNAS Y PLACAS 13,991.50
05.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 8.21 449.81 3,692.94 8.21 3,692.94 100.00% 0.00 0.00 0.00% 8.21 3,692.94 100.00% 0.00 0.00 0.00%
05.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 91.20 53.08 4,840.90 91.20 4,840.90 100.00% 0.00 0.00 0.00% 91.20 4,840.90 100.00% 0.00 0.00 0.00%
05.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 1,305.66 4.18 5,457.66 1,305.66 5,457.66 100.00% 0.00 0.00 0.00% 1,305.66 5,457.66 100.00% 0.00 0.00 0.00%
05.01.04.04 VIGAS 10,012.03
05.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 6.62 449.81 2,977.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.62 2,977.74 100.00%
05.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 63.32 62.13 3,934.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.32 3,934.07 100.00%
05.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 741.68 4.18 3,100.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 741.68 3,100.22 100.00%
05.01.04.05 COLUMNETAS 2,056.88
05.01.04.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 1.13 419.72 474.28 1.13 474.28 100.00% 0.00 0.00 0.00% 1.13 474.28 100.00% 0.00 0.00 0.00%
05.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 15.12 53.08 802.57 15.12 802.57 100.00% 0.00 0.00 0.00% 15.12 802.57 100.00% 0.00 0.00 0.00%
05.01.04.05.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 186.61 4.18 780.03 186.61 780.03 100.00% 0.00 0.00 0.00% 186.61 780.03 100.00% 0.00 0.00 0.00%
05.02 ARQUITECTURA 78,614.27
05.02.01 ALBAÑILERIA 3,063.62
05.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 55.32 55.38 3,063.62 55.32 3,063.62 100.00% 0.00 0.00 0.00% 55.32 3,063.62 100.00% 0.00 0.00 0.00%
05.02.02 REVOQUES 11,385.22
05.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 84.51 26.62 2,249.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84.51 2,249.66 100.00%
05.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 53.01 26.62 1,411.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 53.01 1,411.13 100.00%
05.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 70.68 28.80 2,035.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 70.68 2,035.58 100.00%
05.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 92.00 3.45 317.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 92.00 317.40 100.00%
05.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 63.32 31.39 1,987.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.32 1,987.61 100.00%
05.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 61.60 3.45 212.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 61.60 212.52 100.00%
05.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A-1: m2 97.10 27.89 2,708.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 97.10 2,708.12 100.00%
05.02.02.08 BRUÑAS DE 1.0 cm m 49.70 9.32 463.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.70 463.20 100.00%
05.02.03 PISOS Y PAVIMENTOS 5,843.07
05.02.03.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 63.56 35.38 2,248.75 63.56 2,248.75 100.00% 0.00 0.00 0.00% 63.56 2,248.75 100.00% 0.00 0.00 0.00%
05.02.03.02 PISO DE CERAMICO 45 X 45 CM m2 63.56 56.55 3,594.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.56 3,594.32 100.00%
05.02.04 CONTRAZOCALOS 1,272.03
05.02.04.01 CONTRAZOCALO CERAMICO H=0.10 m. m 37.80 19.27 728.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.80 728.41 100.00%
05.02.04.02 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 35.30 15.40 543.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.30 543.62 100.00%
05.02.05 CARPINTERIA MADERA 6,321.84
05.02.05.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 12.74 496.22 6,321.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.74 6,321.84 100.00%
05.02.06 CARPINTERIA METALICA 5,773.96
05.02.06.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 29.92 192.98 5,773.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 29.92 5,773.96 100.00%
05.02.07 CERRAJERIA 524.80
05.02.07.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 5.00 77.93 389.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 389.65 100.00%
05.02.07.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 15.00 9.01 135.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 135.15 100.00%
05.02.08 VIDRIOS, CRISTALES Y SIMILARES 4,182.85
05.02.08.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 323.75 12.92 4,182.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 323.75 4,182.85 100.00%
05.02.09 PINTURAS 3,306.15
05.02.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 137.02 10.57 1,448.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 137.02 1,448.30 100.00%
05.02.09.02 PINTURA EN CONTRAZOCALO m2 7.06 7.96 56.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.06 56.20 100.00%
05.02.09.03 PINTURA EN VIGAS m2 63.32 13.73 869.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.32 869.38 100.00%
05.02.09.04 PINTURA EN COLUMNAS Y PLACAS m2 70.68 13.19 932.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 70.68 932.27 100.00%
05.02.10 CUBIERTA METALICA Y CIELO RASO 36,940.73

Página 16
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

05.02.10.01 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 113.85 122.00 13,889.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 113.85 13,889.70 100.00%
05.02.10.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 126.50 75.18 9,510.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 126.50 9,510.27 100.00%
05.02.10.03 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 116.13 116.60 13,540.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 116.13 13,540.76 100.00%
05.03 INSTALACIONES ELECTRICAS 8,742.62
05.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 10.00 145.99 1,459.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 1,459.90 100.00%
05.03.02 SALIDA TOMACORRIENTE pto 9.00 215.17 1,936.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.00 1,936.53 100.00%
05.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 4.00 108.23 432.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 432.92 100.00%
05.03.04 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 10.00 205.71 2,057.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 2,057.10 100.00%
05.03.05 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 100.00 10.81 1,081.00 40.00 432.40 40.00% 0.00 0.00 0.00% 40.00 432.40 40.00% 60.00 648.60 60.00%
05.03.06 ALAMBRE THHN 2.5 mm2 m 125.00 1.67 208.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 125.00 208.75 100.00%
05.03.07 ALAMBRE THHN 4 mm2 m 101.00 2.19 221.19 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 101.00 221.19 100.00%
05.03.08 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
05.03.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
05.03.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
05.04 INSTALACIONES SANITARIAS 4,949.89
05.04.01 APARATOS Y ACCESORIOS SANITARIOS 1,433.36
05.04.01.01 LAVADERO DE ACERO INOXIDABLE DOS POZAS CON ESCU und 2.00 447.76 895.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 895.52 100.00%
05.04.01.02 GRIFO TIPO CUELLO DE CISNE CROMADO 1/2" und 4.00 134.46 537.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 537.84 100.00%
05.04.02 SISTEMA DE DESAGUE 1,071.20
05.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 4.00 93.15 372.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 372.60 100.00%
05.04.02.02 SUMIDERO DE 2" pza 1.00 77.41 77.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 77.41 100.00%
05.04.02.03 TUBERIA PVC SAL P/DESAGUE D=2" m 6.25 29.80 186.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.25 186.25 100.00%
05.04.02.04 YEE PVC SAL P/DESAGUE D=2" und 1.00 27.59 27.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 27.59 100.00%
05.04.02.05 CODO PVC SAL P/DESAGUE D=2" und 1.00 25.81 25.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 25.81 100.00%
05.04.02.06 EXCAVACION MANUAL PARA TUBERIA m 6.25 14.89 93.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.25 93.06 100.00%
05.04.02.07 REFINE NIVELACION Y COMPACTACION DE ZANJA m 6.25 3.86 24.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.25 24.13 100.00%
05.04.02.08 CAMA DE APOYO m 6.25 9.44 59.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.25 59.00 100.00%
05.04.02.09 RELLENO COMPACTADO DE ZANJAS m 6.25 12.00 75.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.25 75.00 100.00%
05.04.02.10 CAJA DE REGISTRO CON REJILLA METALICA und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
05.04.03 SISTEMA DE AGUA FRIA 729.43
05.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 2.00 72.84 145.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 145.68 100.00%
05.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 6.15 17.01 104.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.15 104.61 100.00%
05.04.03.03 CODO PVC 1/2" und 2.00 9.94 19.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 19.88 100.00%
05.04.03.04 TEE PVC 1/2" und 1.00 11.04 11.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 11.04 100.00%
05.04.03.05 EXCAVACION MANUAL PARA TUBERIA m 6.15 14.89 91.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.15 91.57 100.00%
05.04.03.06 REFINE NIVELACION Y COMPACTACION DE ZANJA m 6.15 3.86 23.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.15 23.74 100.00%
05.04.03.07 CAMA DE APOYO m 6.15 9.44 58.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.15 58.06 100.00%
05.04.03.08 RELLENO COMPACTADO DE ZANJAS m 6.15 12.00 73.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.15 73.80 100.00%
05.04.03.09 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 1.00 70.70 70.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 70.70 100.00%
05.04.03.10 CAJA PARA VALVULAS und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
05.04.04 SISTEMA DE AGUA PLUVIAL 1,715.90
05.04.04.01 CANALETA PARA AGUA FLUVIAL DE 4" m 23.30 58.77 1,369.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.30 1,369.34 100.00%
05.04.04.02 TUBERIA PVC SAL D=4" m 6.00 45.40 272.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 272.40 100.00%
05.04.04.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 74.16 100.00%
06 CONSTRUCCIÓN DE SERVICIOS HIGIENICOS 232,892.65
06.01 ESTRUCTURAS 64,827.86
06.01.01 OBRAS PRELIMINARES 228.00
06.01.01.01 LIMPIEZA DE TERRENO m2 84.76 0.95 80.52 84.76 80.52 100.00% 0.00 0.00 0.00% 84.76 80.52 100.00% 0.00 0.00 0.00%
06.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 84.76 1.74 147.48 84.76 147.48 100.00% 0.00 0.00 0.00% 84.76 147.48 100.00% 0.00 0.00 0.00%
06.01.02 MOVIMIENTO DE TIERRAS 5,317.64
06.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 30.78 41.41 1,274.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 30.78 1,274.60 100.00%
06.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 26.68 41.41 1,104.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.68 1,104.82 100.00%
06.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 76.49 2.48 189.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.49 189.70 100.00%
06.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 19.68 27.36 538.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19.68 538.44 100.00%
06.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 7.65 197.01 1,507.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.65 1,507.13 100.00%
06.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 44.35 15.85 702.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 44.35 702.95 100.00%
06.01.03 CONCRETO SIMPLE 12,987.55
06.01.03.01 SOLADO PARA ZAPATAS m2 20.52 35.13 720.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.52 720.87 100.00%

Página 17
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

06.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 12.74 333.17 4,244.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.74 4,244.59 100.00%
06.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 4.95 387.67 1,918.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.95 1,918.97 100.00%
06.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 66.00 46.45 3,065.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 66.00 3,065.70 100.00%
06.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 76.49 39.71 3,037.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.49 3,037.42 100.00%
06.01.04 CONCRETO ARMADO 46,294.67
06.01.04.01 ZAPATAS 5,692.90
06.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 10.26 449.81 4,615.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.26 4,615.05 100.00%
06.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 257.86 4.18 1,077.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 257.86 1,077.85 100.00%
06.01.04.02 VIGA DE CIMENTACION 8,838.96
06.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 6.23 449.81 2,802.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.23 2,802.32 100.00%
06.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 49.80 51.41 2,560.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.80 2,560.22 100.00%
06.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 831.68 4.18 3,476.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 831.68 3,476.42 100.00%
06.01.04.03 COLUMNAS Y PLACAS 13,863.72
06.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 8.04 449.81 3,616.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.04 3,616.47 100.00%
06.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 89.52 53.08 4,751.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 89.52 4,751.72 100.00%
06.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 1,314.72 4.18 5,495.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,314.72 5,495.53 100.00%
06.01.04.04 VIGAS 13,462.21
06.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 8.81 449.81 3,962.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.81 3,962.83 100.00%
06.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 84.20 62.13 5,231.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84.20 5,231.35 100.00%
06.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 1,021.06 4.18 4,268.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,021.06 4,268.03 100.00%
06.01.04.05 COLUMNETAS 4,436.88
06.01.04.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 2.52 419.72 1,057.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.52 1,057.69 100.00%
06.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 33.64 53.08 1,785.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 33.64 1,785.61 100.00%
06.01.04.05.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 381.24 4.18 1,593.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 381.24 1,593.58 100.00%
06.02 ARQUITECTURA 122,519.44
06.02.01 MUROS Y TABIQUES 6,205.88
06.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 112.06 55.38 6,205.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.06 6,205.88 100.00%
06.02.02 REVOQUES 15,227.74
06.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 137.56 26.62 3,661.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 137.56 3,661.85 100.00%
06.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 86.56 26.62 2,304.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 86.56 2,304.23 100.00%
06.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 89.52 28.80 2,578.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 89.52 2,578.18 100.00%
06.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 169.60 3.45 585.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 169.60 585.12 100.00%
06.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 84.20 31.39 2,643.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84.20 2,643.04 100.00%
06.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 109.88 3.45 379.09 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 109.88 379.09 100.00%
06.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A-1: m2 92.20 27.89 2,571.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 92.20 2,571.46 100.00%
06.02.02.08 BRUÑAS DE 1.0 cm m 54.16 9.32 504.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 54.16 504.77 100.00%
06.02.03 PISOS 7,031.73
06.02.03.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 76.49 35.38 2,706.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.49 2,706.22 100.00%
06.02.03.02 PISO DE CERAMICO 45 X 45 CM m2 76.49 56.55 4,325.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.49 4,325.51 100.00%
06.02.04 ZOCALOS 16,988.89
06.02.04.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 32.00 15.40 492.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 32.00 492.80 100.00%
06.02.04.02 ZOCALO DE CERAMICA 20 X 30 CM m2 177.53 92.92 16,496.09 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 177.53 16,496.09 100.00%
06.02.05 CARPINTERIA DE MADERA 24,845.08
06.02.05.01 PUERTAS 14,785.70
06.02.05.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 17.08 496.22 8,475.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.08 8,475.44 100.00%
06.02.05.01.02 PUERTA CONTRAPLACADA SEGUN DISEÑO m2 18.00 350.57 6,310.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 6,310.26 100.00%
06.02.05.02 TABIQUES DIVISORIOS 10,059.38
06.02.05.02.01 DIVISIONES CONTRAPLACADAS DE MADERA (SSHH) m2 37.44 268.68 10,059.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.44 10,059.38 100.00%
06.02.06 CARPINTERIA METALICA 2,223.13
06.02.06.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 11.52 192.98 2,223.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.52 2,223.13 100.00%
06.02.07 CERRAJERIA 1,475.26
06.02.07.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 8.00 77.93 623.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 623.44 100.00%
06.02.07.02 PICAPORTE DE ALUMINIO 2 PULGADAS pza 18.00 17.29 311.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 311.22 100.00%
06.02.07.03 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 60.00 9.01 540.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 60.00 540.60 100.00%
06.02.08 VIDRIOS, CRISTALES Y SIMILARES 1,602.08
06.02.08.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 124.00 12.92 1,602.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 124.00 1,602.08 100.00%
06.02.09 PINTURAS 4,756.73
06.02.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 224.12 10.57 2,368.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 224.12 2,368.95 100.00%

Página 18
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

06.02.09.02 PINTURA EN CONTRAZOCALO m2 6.40 7.96 50.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.40 50.94 100.00%
06.02.09.03 PINTURA EN VIGAS m2 84.20 13.73 1,156.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84.20 1,156.07 100.00%
06.02.09.04 PINTURA EN COLUMNAS Y PLACAS m2 89.52 13.19 1,180.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 89.52 1,180.77 100.00%
06.02.10 CUBIERTA METALICA Y CIELO RASO 42,162.92
06.02.10.01 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 132.41 122.00 16,154.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.41 16,154.02 100.00%
06.02.10.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 136.50 75.18 10,262.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 136.50 10,262.07 100.00%
06.02.10.03 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 135.05 116.60 15,746.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 135.05 15,746.83 100.00%
06.03 INSTALACIONES ELECTRICAS 12,831.07
06.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 20.00 145.99 2,919.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 2,919.80 100.00%
06.03.02 SALIDA TOMACORRIENTE A PRUEBA DE AGUA pto 8.00 219.38 1,755.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 1,755.04 100.00%
06.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 10.00 108.23 1,082.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 1,082.30 100.00%
06.03.04 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 20.00 205.71 4,114.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 4,114.20 100.00%
06.03.05 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 99.90 10.81 1,079.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 99.90 1,079.92 100.00%
06.03.06 ALAMBRE THHN 2.5 mm2 m 206.80 1.67 345.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 206.80 345.36 100.00%
06.03.07 ALAMBRE THHN 4 mm2 m 86.40 2.19 189.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 86.40 189.22 100.00%
06.03.08 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
06.03.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
06.03.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
06.04 INSTALACIONES SANITARIAS 32,714.28
06.04.01 APARATOS Y ACCESORIOS SANITARIOS 11,468.50
06.04.01.01 INODORO TANQUE BAJO pza 20.00 361.79 7,235.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 7,235.80 100.00%
06.04.01.02 LAVATORIO DE LOZA BLANCA und 18.00 195.88 3,525.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 3,525.84 100.00%
06.04.01.03 CAÑO DE BRONCE - LLAVE DE 1/2" und 18.00 39.27 706.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 706.86 100.00%
06.04.02 SISTEMA DE DESAGUE 11,848.24
06.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 18.00 93.15 1,676.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 1,676.70 100.00%
06.04.02.02 SALIDA DE DESAGUE PVC D=4" pto 20.00 145.54 2,910.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 2,910.80 100.00%
06.04.02.03 SALIDA VENTILACION DE 2" pto 4.00 58.08 232.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 232.32 100.00%
06.04.02.04 REGISTRO DE BRONCE 4" und 8.00 285.99 2,287.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 2,287.92 100.00%
06.04.02.05 SUMIDERO DE 2" pza 10.00 77.41 774.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 774.10 100.00%
06.04.02.06 TUBERIA PVC SAL P/DESAGUE D=4" m 35.40 33.95 1,201.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.40 1,201.83 100.00%
06.04.02.07 YEE PVC SAL 4"X2" und 8.00 61.97 495.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 495.76 100.00%
06.04.02.08 CODO PVC SAL P/DESAGUE D=2" und 6.00 25.81 154.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 154.86 100.00%
06.04.02.09 YEE PVC SAL 4" und 4.00 64.85 259.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 259.40 100.00%
06.04.02.10 CODO PVC SAL P/DESAGUE D=4" und 6.00 28.52 171.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 171.12 100.00%
06.04.02.11 EXCAVACION MANUAL PARA TUBERIA m 35.40 14.89 527.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.40 527.11 100.00%
06.04.02.12 REFINE NIVELACION Y COMPACTACION DE ZANJA m 35.40 3.86 136.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.40 136.64 100.00%
06.04.02.13 CAMA DE APOYO m 35.40 9.44 334.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.40 334.18 100.00%
06.04.02.14 RELLENO COMPACTADO DE ZANJAS m 35.40 12.00 424.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.40 424.80 100.00%
06.04.02.15 CAJA DE REGISTRO CON REJILLA METALICA und 2.00 130.35 260.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 260.70 100.00%
06.04.03 SISTEMA DE AGUA FRIA 7,446.56
06.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 42.00 72.84 3,059.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 42.00 3,059.28 100.00%
06.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 41.40 17.01 704.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 41.40 704.21 100.00%
06.04.03.03 TUBERIA PVC SAP CLASE 10-3/4" m 7.74 18.07 139.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.74 139.86 100.00%
06.04.03.04 CODO PVC 1/2" und 10.00 9.94 99.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 99.40 100.00%
06.04.03.05 TEE PVC 1/2" und 12.00 11.04 132.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 132.48 100.00%
06.04.03.06 REDUCCION PVC 3/4" - 1/2" und 6.00 10.11 60.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 60.66 100.00%
06.04.03.07 CODO PVC 3/4" und 2.00 10.78 21.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 21.56 100.00%
06.04.03.08 TEE PVC 3/4" und 4.00 11.97 47.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 47.88 100.00%
06.04.03.09 EXCAVACION MANUAL PARA TUBERIA m 49.14 14.89 731.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.14 731.69 100.00%
06.04.03.10 REFINE NIVELACION Y COMPACTACION DE ZANJA m 49.14 3.86 189.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.14 189.68 100.00%
06.04.03.11 CAMA DE APOYO m 49.14 9.44 463.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.14 463.88 100.00%
06.04.03.12 RELLENO COMPACTADO DE ZANJAS m 49.14 12.00 589.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.14 589.68 100.00%
06.04.03.13 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 6.00 70.70 424.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 424.20 100.00%
06.04.03.14 CAJA PARA VALVULAS und 6.00 130.35 782.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 782.10 100.00%
06.04.04 SISTEMA DE AGUA PLUVIAL 1,950.98
06.04.04.01 CANALETA PARA AGUA FLUVIAL DE 4" m 27.30 58.77 1,604.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.30 1,604.42 100.00%
06.04.04.02 TUBERIA PVC SAL D=4" m 6.00 45.40 272.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 272.40 100.00%
06.04.04.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 74.16 100.00%

Página 19
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

07 TANQUE CISTERNA - TANQUE ELEVADO 49,283.11 0.00%


07.01 ESTRUCTURAS 26,769.78
07.01.01 OBRAS PRELIMINARES 23.54
07.01.01.01 LIMPIEZA DE TERRENO m2 8.75 0.95 8.31 8.75 8.31 100.00% 0.00 0.00 0.00% 8.75 8.31 100.00% 0.00 0.00 0.00%
07.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 8.75 1.74 15.23 8.75 15.23 100.00% 0.00 0.00 0.00% 8.75 15.23 100.00% 0.00 0.00 0.00%
07.01.02 MOVIMIENTO DE TIERRAS 1,079.23
07.01.02.01 EXCAVACION DE ZANJAS PARA CISTERNA m3 17.50 41.41 724.68 17.50 724.68 100.00% 0.00 0.00 0.00% 17.50 724.68 100.00% 0.00 0.01 0.00%
07.01.02.02 NIVELACION Y APISONADO MANUAL PARA PISOS m2 8.75 2.48 21.70 8.75 21.70 100.00% 0.00 0.00 0.00% 8.75 21.70 100.00% 0.00 0.00 0.00%
07.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 21.00 15.85 332.85 21.00 332.85 100.00% 0.00 0.00 0.00% 21.00 332.85 100.00% 0.00 0.00 0.00%
07.01.03 CONCRETO SIMPLE 586.88
07.01.03.01 SOLADO m2 8.75 35.13 307.39 8.75 307.39 100.00% 0.00 0.00 0.00% 8.75 307.39 100.00% 0.00 0.00 0.00%
07.01.03.02 SOBRECIMIENTO 1:8 + 25% P.M m3 0.28 387.67 108.55 0.28 108.55 100.00% 0.00 0.00 0.00% 0.28 108.55 100.00% 0.00 0.00 0.00%
07.01.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 3.68 46.45 170.94 3.68 170.94 100.00% 0.00 0.00 0.00% 3.68 170.94 100.00% 0.00 0.00 0.00%
07.01.04 CONCRETO ARMADO 25,080.13
07.01.04.01 COLUMNAS 7,138.87
07.01.04.01.01 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 3.98 449.81 1,790.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.98 1,790.24 100.00%
07.01.04.01.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 49.04 53.08 2,603.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.04 2,603.04 100.00%
07.01.04.01.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS kg 656.84 4.18 2,745.59 656.84 2,745.59 100.00% 0.00 0.00 0.00% 656.84 2,745.59 100.00% 0.00 0.00 0.00%
07.01.04.02 VIGAS 4,141.00
07.01.04.02.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 2.16 449.81 971.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.16 971.59 100.00%
07.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 24.48 62.13 1,520.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.48 1,520.94 100.00%
07.01.04.02.03 VIGAS ACERO fy=4,200 kg/cm2 kg 394.37 4.18 1,648.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 394.37 1,648.47 100.00%
07.01.04.03 LOSA MACIZA 3,002.53
07.01.04.03.01 LOSA MACIZA CONCRETO FC=210 KG/CM2 m3 2.40 449.81 1,079.54 2.40 1,079.54 100.00% 0.00 0.00 0.00% 2.40 1,079.54 100.00% 0.00 0.00 0.00%
07.01.04.03.02 ENCOFRADO Y DESENCOFRADO DE LOSA MACIZA m2 12.00 54.29 651.48 12.00 651.48 100.00% 0.00 0.00 0.00% 12.00 651.48 100.00% 0.00 0.00 0.00%
07.01.04.03.03 LOSA MACIZA ACERO fy=4,200 kg/cm2 kg 304.19 4.18 1,271.51 304.19 1,271.51 100.00% 0.00 0.00 0.00% 304.19 1,271.51 100.00% 0.00 0.00 0.00%
07.01.04.04 CISTERNA 10,317.18
07.01.04.04.01 CONCRETO EN CISTERNA f'c=210 kg/cm2 m3 11.25 485.41 5,460.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.25 5,460.86 100.00%
07.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN CISTERNA m2 18.22 51.41 936.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.22 936.69 100.00%
07.01.04.04.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN CISTERNA kg 937.71 4.18 3,919.63 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 937.71 3,919.63 100.00%
07.01.04.05 COLUMNETAS 480.55
07.01.04.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 0.28 419.72 117.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.28 117.52 100.00%
07.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 3.68 53.08 195.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.68 195.33 100.00%
07.01.04.05.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 40.12 4.18 167.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 40.12 167.70 100.00%
07.02 ARQUITECTURA 11,218.94
07.02.01 MUROS Y TABIQUES 835.13
07.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 15.08 55.38 835.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.08 835.13 100.00%
07.02.02 REVOQUES 4,950.63
07.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 15.84 26.62 421.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.84 421.66 100.00%
07.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 15.84 26.62 421.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.84 421.66 100.00%
07.02.02.03 TARRAJEO DE COLUMNAS C:A-1:4 m2 49.04 28.80 1,412.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.04 1,412.35 100.00%
07.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS m 152.00 3.45 524.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 152.00 524.40 100.00%
07.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 24.48 31.39 768.43 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.48 768.43 100.00%
07.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 57.60 3.45 198.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 57.60 198.72 100.00%
07.02.02.07 REVESTIMIENTO DE CIELO RASO EN LOSA MACIZA m2 12.00 36.85 442.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 442.20 100.00%
07.02.02.08 TARRAJEO CON IMPERMEABILIZANTE EN TANQUE CISTERN m2 18.22 38.42 700.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.22 700.01 100.00%
07.02.02.09 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 4.50 13.60 61.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.50 61.20 100.00%
07.02.03 PISOS 365.09
07.02.03.01 PISO CEMENTO PULIDO E=2" m2 7.04 51.86 365.09 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.04 365.09 100.00%
07.02.04 ZOCALOS 369.60 0.00
07.02.04.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 24.00 15.40 369.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.00 369.60 100.00%
07.02.05 CARPINTERIA DE MADERA 803.88
07.02.05.01 PUERTAS 803.88
07.02.05.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 1.62 496.22 803.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.62 803.88 100.00%
07.02.06 CARPINTERIA METALICA 2,119.02
07.02.06.01 VENTANAS 463.15
07.02.06.01.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 2.40 192.98 463.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.40 463.15 100.00%
07.02.06.02 ESCALERAS 1,655.87

Página 20
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

07.02.06.02.01 ESCALERA GATO, TUBO F.G. 1 1/2" Y 1" TQE. ELEVADO m 8.50 135.43 1,151.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.50 1,151.16 100.00%
07.02.06.02.02 ESCALERA GATO ALUMINIO - CISTERNA und 1.00 309.90 309.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 309.90 100.00%
07.02.06.02.03 MARCO Y TAPA DE FIERRO 60x60 und 1.00 194.81 194.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 194.81 100.00%
07.02.07 CERRAJERIA 104.96 0.00
07.02.07.01 CERRADURA DE DOS GOLPES TIPO PESADO pza 1.00 77.93 77.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 77.93 100.00%
07.02.07.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 3.00 9.01 27.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 27.03 100.00%
07.02.08 VIDRIOS, CRISTALES Y SIMILARES 333.72
07.02.08.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 25.83 12.92 333.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 25.83 333.72 100.00%
07.02.09 PINTURAS 1,336.91
07.02.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 31.68 10.57 334.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 31.68 334.86 100.00%
07.02.09.02 PINTURA EN CONTRAZOCALO m2 2.40 7.96 19.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.40 19.10 100.00%
07.02.09.03 PINTURA EN VIGAS m2 24.48 13.73 336.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.48 336.11 100.00%
07.02.09.04 PINTURA EN COLUMNAS m2 49.04 13.19 646.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.04 646.84 100.00%
07.03 INSTALACIONES ELECTRICAS 3,766.59
07.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 1.00 145.99 145.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 145.99 100.00%
07.03.02 SALIDA TOMACORRIENTE A PRUEBA DE AGUA pto 1.00 219.38 219.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 219.38 100.00%
07.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 108.23 100.00%
07.03.04 SALIDA PARA ELECTROBOMBA pto 2.00 104.38 208.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 208.76 100.00%
07.03.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 1.00 68.59 68.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 68.59 100.00%
07.03.06 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 9.96 10.81 107.67 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.96 107.67 100.00%
07.03.07 ALAMBRE THHN 2.5 mm2 m 5.08 1.67 8.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.08 8.48 100.00%
07.03.08 ALAMBRE THHN 4 mm2 m 22.26 2.19 48.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.26 48.75 100.00%
07.03.09 EQUIPO DE BOMBEO, INC. 2 ELECTROBOMBAS 1 HP Y TABL und 1.00 1,505.51 1,505.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,505.51 100.00%
07.03.10 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
07.03.11 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
07.03.12 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
07.04 INSTALACIONES SANITARIAS 7,527.80
07.04.01 VALVULAS Y LLAVES 1,332.90
07.04.01.01 VALVULA COMPUERTA DE 3/4" und 1.00 100.51 100.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 100.51 100.00%
07.04.01.02 VALVULA COMPUERTA DE 1 1/2" und 3.00 189.35 568.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 568.05 100.00%
07.04.01.03 VALVULA CHECK DE BRONCE 1 1/2" und 2.00 98.74 197.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 197.48 100.00%
07.04.01.04 VALVULA FLOTADORA 3/4" und 1.00 101.28 101.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 101.28 100.00%
07.04.01.05 VALVULA PIE CON CANASTILLA DE BRONCE 2" und 2.00 182.79 365.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 365.58 100.00%
07.04.02 ALMACENAMIENTO DE AGUA 6,033.58
07.04.02.01 TUBERIA F°G° 3" m 1.00 51.83 51.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 51.83 100.00%
07.04.02.02 TUBERIA F°G° 2" m 15.70 33.60 527.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.70 527.52 100.00%
07.04.02.03 TUBERIA F°G° 1 1/2" m 22.35 27.70 619.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.35 619.10 100.00%
07.04.02.04 CODO F°G° 3" x 90 und 1.00 56.76 56.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 56.76 100.00%
07.04.02.05 CODO F°G° 2" x 90 und 7.00 31.93 223.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.00 223.51 100.00%
07.04.02.06 CODO F°G° 1 1/2" x 90 und 8.00 26.51 212.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 212.08 100.00%
07.04.02.07 TEE F°G° 2" und 1.00 35.32 35.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 35.32 100.00%
07.04.02.08 TEE F°G° 1 1/2" und 2.00 31.08 62.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 62.16 100.00%
07.04.02.09 UNION UNIVERSAL F°G° 2" und 6.00 79.25 475.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 475.50 100.00%
07.04.02.10 UNION UNIVERSAL F°G° 1 1/2" und 8.00 56.84 454.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 454.72 100.00%
07.04.02.11 BRIDA ROMPE AGUA und 3.00 38.94 116.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 116.82 100.00%
07.04.02.12 JUNTA WATER STOP 8" m 11.20 76.42 855.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.20 855.90 100.00%
07.04.02.13 CAJA DE REBOSE C/REJILLA DE FIERRO und 1.00 280.52 280.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 280.52 100.00%
07.04.02.14 TAPA METALICA SANITARIA und 1.00 326.48 326.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 326.48 100.00%
07.04.02.15 ABRAZADERAS DE F°G° und 23.00 10.67 245.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.00 245.41 100.00%
07.04.02.16 TANQUE DE POLIETILENO 2500 LT und 1.00 1,489.95 1,489.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,489.95 100.00%
07.04.03 DESAGUE Y VENTILACION 161.32
07.04.03.01 SALIDA DE DESAGUE PVC D=4" pto 1.00 145.54 145.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 145.54 100.00%
07.04.03.02 SOMBRERO DE VENTILACION 2" und 1.00 15.78 15.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 15.78 100.00%
08 PORTADA Y CASETA DE VIGILANCIA 22,918.40
08.01 ESTRUCTURAS 9,518.16
08.01.01 OBRAS PRELIMINARES 16.90
08.01.01.01 LIMPIEZA DE TERRENO m2 6.28 0.95 5.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.28 5.97 100.00%
08.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 6.28 1.74 10.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.28 10.93 100.00%

Página 21
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

08.01.02 MOVIMIENTO DE TIERRAS 743.23


08.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 2.56 41.41 106.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.56 106.01 100.00%
08.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 7.96 41.41 329.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.96 329.62 100.00%
08.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 3.81 2.48 9.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.81 9.45 100.00%
08.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 0.96 27.36 26.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.96 26.27 100.00%
08.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 0.38 197.01 74.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.38 74.86 100.00%
08.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 12.43 15.85 197.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.43 197.02 100.00%
08.01.03 OBRAS DE CONCRETO SIMPLE 717.03
08.01.03.01 SOLADO PARA ZAPATAS m2 6.62 35.13 232.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.62 232.56 100.00%
08.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 1.00 333.17 333.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 333.17 100.00%
08.01.03.03 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 3.81 39.71 151.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.81 151.30 100.00%
08.01.04 OBRAS DE CONCRETO ARMADO 8,041.00
08.01.04.01 SOBRECIMIENTO ARMADO 1,094.65
08.01.04.01.01 SOBRECIMIENTO 1:8 + 25% P.M m3 0.88 387.67 341.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.88 341.15 100.00%
08.01.04.01.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 11.78 46.45 547.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.78 547.18 100.00%
08.01.04.01.03 SOBRECIMIENTO ACERO fy=4,200 kg/cm2 kg 49.36 4.18 206.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.36 206.32 100.00%
08.01.04.02 ZAPATAS 1,709.32
08.01.04.02.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 3.06 449.81 1,376.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.06 1,376.42 100.00%
08.01.04.02.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 79.64 4.18 332.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 79.64 332.90 100.00%
08.01.04.03 VIGA DE CIMENTACION 611.69
08.01.04.03.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 0.46 449.81 206.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.46 206.91 100.00%
08.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 3.70 51.41 190.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.70 190.22 100.00%
08.01.04.03.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 51.33 4.18 214.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 51.33 214.56 100.00%
08.01.04.04 COLUMNAS 2,534.69
08.01.04.04.01 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 1.21 449.81 544.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.21 544.27 100.00%
08.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 20.01 53.08 1,062.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.01 1,062.13 100.00%
08.01.04.04.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS kg 222.08 4.18 928.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 222.08 928.29 100.00%
08.01.04.05 VIGAS 1,500.04 0.00
08.01.04.05.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 0.84 449.81 377.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.84 377.84 100.00%
08.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 9.61 62.13 597.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.61 597.07 100.00%
08.01.04.05.03 VIGAS ACERO fy=4,200 kg/cm2 kg 125.63 4.18 525.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 125.63 525.13 100.00%
08.01.04.06 PARAPETO 276.08
08.01.04.06.01 CONCRETO PARAPETO f'c=210 kg/cm2 m3 0.18 449.81 80.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.18 80.97 100.00%
08.01.04.06.02 ENCOFRADO Y DESENCOFRADO EN PARAPETO m2 2.45 62.13 152.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.45 152.22 100.00%
08.01.04.06.03 PARAPETO ACERO fy=4,200 kg/cm2 kg 10.26 4.18 42.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.26 42.89 100.00%
08.01.04.07 LOSAS ALIGERADAS 314.53
08.01.04.07.01 CONCRETO LOSA ALIGERADA f'c= 210 kg/cm2 m3 0.21 449.81 94.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.21 94.46 100.00%
08.01.04.07.02 LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO m2 2.41 51.12 123.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.41 123.20 100.00%
08.01.04.07.03 LOSAS ALIGERADAS ACERO fy=4,200 kg/cm2 kg 9.41 4.18 39.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.41 39.33 100.00%
08.01.04.07.04 LOSA ALIGERADA LADRILLO HUECO 15X30X30 und 21.00 2.74 57.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 21.00 57.54 100.00%
08.02 ARQUITECTURA 9,207.85
08.02.01 ALBAÑILERIA 798.58
08.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 14.42 55.38 798.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.42 798.58 100.00%
08.02.02 REVOQUES 1,810.03
08.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 14.42 26.62 383.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.42 383.86 100.00%
08.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 14.42 26.62 383.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.42 383.86 100.00%
08.02.02.03 TARRAJEO DE COLUMNAS C:A-1:4 m2 12.72 28.80 366.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.72 366.34 100.00%
08.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS m 37.10 3.45 128.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.10 128.00 100.00%
08.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 9.61 31.39 301.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.61 301.66 100.00%
08.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 23.30 3.45 80.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.30 80.39 100.00%
08.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 12.20 13.60 165.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.20 165.92 100.00%
08.02.03 CIELO RASO 104.50
08.02.03.01 TARRAJEO DE CIELO RASO - SUPERFICIE CON CEMENTO-A m2 2.41 43.36 104.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.41 104.50 100.00%
08.02.04 PISOS Y PAVIMENTOS 197.59
08.02.04.01 PISO CEMENTO PULIDO E=2" m2 3.81 51.86 197.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.81 197.59 100.00%
08.02.05 CONTRAZOCALOS 267.96
08.02.05.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 17.40 15.40 267.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.40 267.96 100.00%
08.02.06 CARPINTERIA MADERA 1,276.07

Página 22
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

08.02.06.01 PUERTA CONTRAPLACADA SEGUN DISEÑO m2 3.64 350.57 1,276.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.64 1,276.07 100.00%
08.02.07 CARPINTERIA METALICA 3,627.00
08.02.07.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 2.44 192.98 470.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.44 470.87 100.00%
08.02.07.02 PUERTA INGRESO PRINCIPAL C/PERFILES 3/16" m2 9.62 328.08 3,156.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.62 3,156.13 100.00%
08.02.08 CERRAJERIA 209.92
08.02.08.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
08.02.08.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 6.00 9.01 54.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 54.06 100.00%
08.02.09 VIDRIOS, CRISTALES Y SIMILARES 339.28
08.02.09.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 26.26 12.92 339.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.26 339.28 100.00%
08.02.10 PINTURAS 576.92
08.02.10.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 23.84 10.57 251.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.84 251.99 100.00%
08.02.10.02 PINTURA EN CONTRAZOCALO m2 3.48 7.96 27.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.48 27.70 100.00%
08.02.10.03 PINTURA EN VIGAS m2 9.61 13.73 131.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.61 131.95 100.00%
08.02.10.04 PINTURA EN COLUMNAS m2 10.60 13.19 139.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.60 139.81 100.00%
08.02.10.05 PINTURA EN CIELO RASO m2 2.41 10.57 25.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.41 25.47 100.00%
08.03 INSTALACIONES ELECTRICAS 1,807.85
08.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 2.00 145.99 291.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 291.98 100.00%
08.03.02 SALIDA TOMACORRIENTE pto 2.00 215.17 430.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 430.34 100.00%
08.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 2.00 108.23 216.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 216.46 100.00%
08.03.04 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 2.00 68.59 137.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 137.18 100.00%
08.03.05 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 12.00 10.81 129.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 129.72 100.00%
08.03.06 ALAMBRE THHN 2.5 mm2 m 36.00 1.67 60.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.00 60.12 100.00%
08.03.07 ALAMBRE THHN 4 mm2 m 24.00 2.19 52.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.00 52.56 100.00%
08.03.08 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
08.03.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
08.04 INSTALACIONES SANITARIAS 2,384.54
08.04.01 APARATOS Y ACCESORIOS SANITARIOS 596.94
08.04.01.01 INODORO TANQUE BAJO pza 1.00 361.79 361.79 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 361.79 100.00%
08.04.01.02 LAVATORIO DE LOZA BLANCA und 1.00 195.88 195.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 195.88 100.00%
08.04.01.03 CAÑO DE BRONCE - LLAVE DE 1/2" und 1.00 39.27 39.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 39.27 100.00%
08.04.02 SISTEMA DE DESAGUE 1,219.68
08.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 2.00 93.15 186.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 186.30 100.00%
08.04.02.02 SALIDA DE DESAGUE PVC D=4" pto 1.00 145.54 145.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 145.54 100.00%
08.04.02.03 SALIDA VENTILACION DE 2" pto 1.00 58.08 58.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 58.08 100.00%
08.04.02.04 REGISTRO DE BRONCE 4" und 1.00 285.99 285.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 285.99 100.00%
08.04.02.05 SUMIDERO DE 2" pza 1.00 77.41 77.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 77.41 100.00%
08.04.02.06 TUBERIA PVC SAL P/DESAGUE D=4" m 3.00 33.95 101.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 101.85 100.00%
08.04.02.07 YEE PVC SAL 4"X2" und 1.00 61.97 61.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 61.97 100.00%
08.04.02.08 CODO PVC SAL P/DESAGUE D=2" und 2.00 25.81 51.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 51.62 100.00%
08.04.02.09 EXCAVACION MANUAL PARA TUBERIA m 3.00 14.89 44.67 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 44.67 100.00%
08.04.02.10 REFINE NIVELACION Y COMPACTACION DE ZANJA m 3.00 3.86 11.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 11.58 100.00%
08.04.02.11 CAMA DE APOYO m 3.00 9.44 28.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 28.32 100.00%
08.04.02.12 RELLENO COMPACTADO DE ZANJAS m 3.00 12.00 36.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 36.00 100.00%
08.04.02.13 CAJA DE REGISTRO CON REJILLA METALICA und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
08.04.03 SISTEMA DE AGUA FRIA 567.92
08.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 2.00 72.84 145.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 145.68 100.00%
08.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 3.50 17.01 59.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 59.54 100.00%
08.04.03.03 CODO PVC 1/2" und 1.00 9.94 9.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 9.94 100.00%
08.04.03.04 TEE PVC 1/2" und 1.00 11.04 11.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 11.04 100.00%
08.04.03.05 EXCAVACION MANUAL PARA TUBERIA m 3.50 14.89 52.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 52.12 100.00%
08.04.03.06 REFINE NIVELACION Y COMPACTACION DE ZANJA m 3.50 3.86 13.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 13.51 100.00%
08.04.03.07 CAMA DE APOYO m 3.50 9.44 33.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 33.04 100.00%
08.04.03.08 RELLENO COMPACTADO DE ZANJAS m 3.50 12.00 42.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 42.00 100.00%
08.04.03.09 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 1.00 70.70 70.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 70.70 100.00%
08.04.03.10 CAJA PARA VALVULAS und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
09 MITIGACIÓN AMBIENTAL 25,000.00
09.01 MITIGACION DEL IMPACTO AMBIENTAL glb 1.00 25,000.00 25,000.00 0.80 20,000.00 80.00% 0.00 0.00 0.00% 0.80 20,000.00 80.00% 0.20 5,000.00 20.00%
10 CAPACITACION Y SENSIBILIZACION 19,880.00

Página 23
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

10.01 CAPACITACION PARA MANTENIMIENTO glb 1.00 8,380.00 8,380.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 8,380.00 100.00%
10.02 SENSIBILIZACION DE BENEFICIARIOS glb 1.00 11,500.00 11,500.00 0.30 3,450.00 30.00% 0.00 0.00 0.00% 0.30 3,450.00 30.00% 0.70 8,050.00 70.00%
11 REMODELACION Y CAMBIO DE CUBIERTA SECTOR PRIMARIA AULAS 1 Y 2 65,432.56
11.01 CARPINTERIA MADERA 2,580.34
11.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 5.20 496.22 2,580.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.20 2,580.34 100.00%
11.02 CARPINTERIA METALICA 3,189.96
11.02.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 16.53 192.98 3,189.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.53 3,189.96 100.00%
11.03 CERRAJERIA 209.92
11.03.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
11.03.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 6.00 9.01 54.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 54.06 100.00%
11.04 VIDRIOS, CRISTALES Y SIMILARES 2,298.86
11.04.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 177.93 12.92 2,298.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 177.93 2,298.86 100.00%
11.05 PINTURAS 3,174.34
11.05.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 164.80 10.57 1,741.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 164.80 1,741.94 100.00%
11.05.02 PINTURA EN VIGAS m2 77.60 13.73 1,065.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.60 1,065.45 100.00%
11.05.03 PINTURA EN COLUMNAS m2 27.82 13.19 366.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.82 366.95 100.00%
11.06 CUBIERTA METALICA Y CIELO RASO 44,352.34
11.06.01 DESMONTAJE DE COBERTURA EXISTENTE glb 1.00 607.27 607.27 1.00 607.27 100.00% 0.00 0.00 0.00% 1.00 607.27 100.00% 0.00 0.00 0.00%
11.06.02 RESANE PRODUCTO DE DESMONTAJE glb 1.00 1,582.15 1,582.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,582.15 100.00%
11.06.03 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOSAS m2 132.41 122.00 16,154.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.41 16,154.02 100.00%
11.06.04 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPORT m 136.50 75.18 10,262.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 136.50 10,262.07 100.00%
11.06.05 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 135.05 116.60 15,746.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 135.05 15,746.83 100.00%
11.07 INSTALACIONES ELECTRICAS 8,783.50
11.07.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 15.00 145.99 2,189.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 2,189.85 100.00%
11.07.02 SALIDA TOMACORRIENTE pto 5.00 215.17 1,075.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 1,075.85 100.00%
11.07.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 108.23 100.00%
11.07.04 SALIDA PARA INTERRUPTOR DOBLE pto 2.00 112.89 225.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 225.78 100.00%
11.07.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 15.00 205.71 3,085.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 3,085.65 100.00%
11.07.06 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 73.02 10.81 789.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 73.02 789.35 100.00%
11.07.07 ALAMBRE THHN 2.5 mm2 m 147.44 1.67 246.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 147.44 246.22 100.00%
11.07.08 ALAMBRE THHN 4 mm2 m 71.61 2.19 156.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 71.61 156.83 100.00%
11.07.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
11.07.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
11.08 VARIOS 843.30 0.00
11.08.01 CANALETA PARA AGUA FLUVIAL DE 4" m 27.30 30.89 843.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.30 843.30 100.00%
12 REMODELACION Y CAMBIO DE CUBIERTA SECTOR PRIMARIA AULAS 1 Y 2 65,432.56
12.01 CARPINTERIA MADERA 2,580.34
12.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 5.20 496.22 2,580.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.20 2,580.34 100.00%
12.02 CARPINTERIA METALICA 3,189.96
12.02.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 16.53 192.98 3,189.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.53 3,189.96 100.00%
12.03 CERRAJERIA 209.92
12.03.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
12.03.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 6.00 9.01 54.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 54.06 100.00%
12.04 VIDRIOS, CRISTALES Y SIMILARES 2,298.86
12.04.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 177.93 12.92 2,298.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 177.93 2,298.86 100.00%
12.05 PINTURAS 3,174.34
12.05.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 164.80 10.57 1,741.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 164.80 1,741.94 100.00%
12.05.02 PINTURA EN VIGAS m2 77.60 13.73 1,065.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.60 1,065.45 100.00%
12.05.03 PINTURA EN COLUMNAS m2 27.82 13.19 366.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.82 366.95 100.00%
12.06 CUBIERTA METALICA Y CIELO RASO 44,352.34
12.06.01 DESMONTAJE DE COBERTURA EXISTENTE glb 1.00 607.27 607.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 607.27 100.00%
12.06.02 RESANE PRODUCTO DE DESMONTAJE glb 1.00 1,582.15 1,582.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,582.15 100.00%
12.06.03 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOSAS m2 132.41 122.00 16,154.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.41 16,154.02 100.00%
12.06.04 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPORT m 136.50 75.18 10,262.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 136.50 10,262.07 100.00%
12.06.05 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 135.05 116.60 15,746.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 135.05 15,746.83 100.00%
12.07 INSTALACIONES ELECTRICAS 8,783.50
12.07.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 15.00 145.99 2,189.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 2,189.85 100.00%
12.07.02 SALIDA TOMACORRIENTE pto 5.00 215.17 1,075.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 1,075.85 100.00%

Página 24
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

12.07.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 108.23 100.00%
12.07.04 SALIDA PARA INTERRUPTOR DOBLE pto 2.00 112.89 225.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 225.78 100.00%
12.07.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 15.00 205.71 3,085.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 3,085.65 100.00%
12.07.06 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 73.02 10.81 789.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 73.02 789.35 100.00%
12.07.07 ALAMBRE THHN 2.5 mm2 m 147.44 1.67 246.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 147.44 246.22 100.00%
12.07.08 ALAMBRE THHN 4 mm2 m 71.61 2.19 156.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 71.61 156.83 100.00%
12.07.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
12.07.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
12.08 VARIOS 843.30
12.08.01 CANALETA PARA AGUA FLUVIAL DE 4" m 27.30 30.89 843.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.30 843.30 100.00%
13 REMODELACION Y CAMBIO DE CUBIERTA SECTOR PRIMARIA AULAS 1 Y 2 65,432.56
13.01 CARPINTERIA MADERA 2,580.34
13.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 5.20 496.22 2,580.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.20 2,580.34 100.00%
13.02 CARPINTERIA METALICA 3,189.96
13.02.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 16.53 192.98 3,189.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.53 3,189.96 100.00%
13.03 CERRAJERIA 209.92
13.03.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
13.03.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 6.00 9.01 54.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 54.06 100.00%
13.04 VIDRIOS, CRISTALES Y SIMILARES 2,298.86
13.04.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 177.93 12.92 2,298.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 177.93 2,298.86 100.00%
13.05 PINTURAS 3,174.34
13.05.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 164.80 10.57 1,741.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 164.80 1,741.94 100.00%
13.05.02 PINTURA EN VIGAS m2 77.60 13.73 1,065.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.60 1,065.45 100.00%
13.05.03 PINTURA EN COLUMNAS m2 27.82 13.19 366.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.82 366.95 100.00%
13.06 CUBIERTA METALICA Y CIELO RASO 44,352.34 0.00
13.06.01 DESMONTAJE DE COBERTURA EXISTENTE glb 1.00 607.27 607.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 607.27 100.00%
13.06.02 RESANE PRODUCTO DE DESMONTAJE glb 1.00 1,582.15 1,582.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,582.15 100.00%
13.06.03 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOSAS m2 132.41 122.00 16,154.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.41 16,154.02 100.00%
13.06.04 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPORT m 136.50 75.18 10,262.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 136.50 10,262.07 100.00%
13.06.05 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 135.05 116.60 15,746.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 135.05 15,746.83 100.00%
13.07 INSTALACIONES ELECTRICAS 8,783.50
13.07.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 15.00 145.99 2,189.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 2,189.85 100.00%
13.07.02 SALIDA TOMACORRIENTE pto 5.00 215.17 1,075.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 1,075.85 100.00%
13.07.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 108.23 100.00%
13.07.04 SALIDA PARA INTERRUPTOR DOBLE pto 2.00 112.89 225.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 225.78 100.00%
13.07.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 15.00 205.71 3,085.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 3,085.65 100.00%
13.07.06 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 73.02 10.81 789.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 73.02 789.35 100.00%
13.07.07 ALAMBRE THHN 2.5 mm2 m 147.44 1.67 246.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 147.44 246.22 100.00%
13.07.08 ALAMBRE THHN 4 mm2 m 71.61 2.19 156.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 71.61 156.83 100.00%
13.07.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
13.07.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
13.08 VARIOS 843.30
13.08.01 CANALETA PARA AGUA FLUVIAL DE 4" m 27.30 30.89 843.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.30 843.30 100.00%
14 CONSTRUCCION DE VEREDAS 124,773.80
14.01 OBRAS PRELIMINARES 2,711.41
14.01.01 LIMPIEZA DE TERRENO m2 1,034.89 0.97 1,003.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,034.89 1,003.84 100.00%
14.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 1,034.89 1.65 1,707.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,034.89 1,707.57 100.00%
14.02 MOVIMIENTO DE TIERRAS 43,860.65
14.02.01 CORTE DE TERRENO CON MAQUINARIA m3 206.98 5.34 1,105.27 200.00 1,068.00 96.63% 0.00 0.00 0.00% 200.00 1,068.00 96.63% 6.98 37.27 3.37%
14.02.02 BASE PARA VEREDAS DE 0.15 M m2 1,034.89 37.51 38,818.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,034.89 38,818.72 100.00%
14.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 248.37 15.85 3,936.66 240.00 3,804.00 96.63% 0.00 0.00 0.00% 240.00 3,804.00 96.63% 8.37 132.66 3.37%
14.03 CONCRETO SIMPLE 78,201.74
14.03.01 VEREDA CONC. FC=175 KG/CM2 E=4" m2 1,034.89 43.57 45,090.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,034.89 45,090.16 100.00%
14.03.02 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 275.97 41.82 11,541.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 275.97 11,541.07 100.00%
14.03.03 JUNTA DE DILATACION m 1,379.85 13.78 19,014.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,379.85 19,014.33 100.00%
14.03.04 CURADO CON AGUA EN VEREDA m2 1,034.89 2.47 2,556.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,034.89 2,556.18 100.00%
15 RAMPAS 8,542.76
15.01 OBRAS PRELIMINARES 104.64

Página 25
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

15.01.01 LIMPIEZA DE TERRENO m2 39.94 0.97 38.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 39.94 38.74 100.00%
15.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 39.94 1.65 65.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 39.94 65.90 100.00%
15.02 MOVIMIENTO DE TIERRAS 255.14
15.02.01 CORTE DE TERRENO CON MAQUINARIA m3 1.25 5.34 6.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.25 6.68 100.00%
15.02.02 BASE PARA RAMPAS DE 0.15 M m2 5.99 37.51 224.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.99 224.68 100.00%
15.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 1.50 15.85 23.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.50 23.78 100.00%
15.03 CONCRETO SIMPLE 3,159.80
15.03.01 CONCRETO FROTACHADO EN LOSA FC=175 KG/CM2 E=4" m3 4.63 439.64 2,035.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.63 2,035.53 100.00%
15.03.02 ENCOFRADO Y DESENCOFRADO EN RAMPAS m2 19.17 41.82 801.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19.17 801.69 100.00%
15.03.03 JUNTA DE DILATACION m 16.25 13.78 223.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.25 223.93 100.00%
15.03.04 CURADO CON AGUA EN RAMPAS m2 39.94 2.47 98.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 39.94 98.65 100.00%
15.04 CARPINTERIA METALICA 5,023.18
15.04.01 BARANDAS METALICAS DE TUBO 2" m 63.90 78.61 5,023.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.90 5,023.18 100.00%
16 GRADAS Y ESCALERAS 15,269.04
16.01 OBRAS PRELIMINARES 60.34
16.01.01 LIMPIEZA DE TERRENO m2 22.43 0.95 21.31 2.90 2.76 12.93% 0.00 0.00 0.00% 2.90 2.76 12.93% 19.53 18.56 87.07%
16.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 22.43 1.74 39.03 2.90 5.05 12.93% 0.00 0.00 0.00% 2.90 5.05 12.93% 19.53 33.98 87.07%
16.02 MOVIMIENTO DE TIERRAS 1,247.62
16.02.01 EXCAVACION DE ZANJAS MANUAL m3 5.25 41.41 217.40 1.00 41.41 19.05% 0.00 0.00 0.00% 1.00 41.41 19.05% 4.25 175.99 80.95%
16.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 13.46 27.36 368.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.46 368.27 100.00%
16.02.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 3.36 197.01 661.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.36 661.95 100.00%
16.03 OBRAS DE CONCRETO 6,737.15
16.03.01 CIMIENTOS 1,749.14
16.03.01.01 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.25 333.17 1,749.14 1.00 333.17 19.05% 0.00 0.00 0.00% 1.00 333.17 19.05% 4.25 1,415.97 80.95%
16.03.02 ESCALERAS 4,988.01
16.03.02.01 ESCALERAS CONCRETO FC=210 KG/CM2 m3 7.98 449.81 3,589.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.98 3,589.48 100.00%
16.03.02.02 ESCALERA ENCOFRADO Y DESENCOFRADO m2 14.70 60.97 896.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.70 896.26 100.00%
16.03.02.03 ESCALERA ACERO fy=4,200 kg/cm2 kg 120.16 4.18 502.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 120.16 502.27 100.00%
16.04 REVOQUES 1,470.32
16.04.01 REVESTIMIENTO DE GRADAS Y ESCALERA m2 39.90 36.85 1,470.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 39.90 1,470.32 100.00%
16.05 CARPINTERIA METALICA 4,997.34
16.05.01 BARANDAS METALICAS DE TUBO 2" m 44.85 78.61 3,525.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 44.85 3,525.66 100.00%
16.05.02 CANTONERA DE ALUMINIO EN PASOS DE ESCALERA m 84.00 17.52 1,471.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84.00 1,471.68 100.00%
16.06 PINTURAS 466.89
16.06.01 PINTURA ANTICORROSIVA EN BARANDAS m 44.85 10.41 466.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 44.85 466.89 100.00%
16.07 VARIOS 289.38
16.07.01 JUNTA DE DILATACION m 21.00 13.78 289.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 21.00 289.38 100.00%
17 PATIO DE HONOR 28,317.10
17.01 OBRAS PRELIMINARES 709.26
17.01.01 LIMPIEZA DE TERRENO m2 270.71 0.97 262.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 270.71 262.59 100.00%
17.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 270.71 1.65 446.67 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 270.71 446.67 100.00%
17.02 MOVIMIENTO DE TIERRAS 11,012.28
17.02.01 CORTE DE TERRENO CON MAQUINARIA m3 27.07 5.34 144.55 27.07 144.55 100.00% 0.00 0.00 0.00% 27.07 144.55 100.00% 0.00 0.00 0.00%
17.02.02 BASE GRANULAR DE 0.15 M m2 276.00 37.51 10,352.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 276.00 10,352.76 100.00%
17.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 32.49 15.85 514.97 32.49 514.97 100.00% 0.00 0.00 0.00% 32.49 514.97 100.00% 0.00 0.00 0.00%
17.03 CONCRETO SIMPLE 16,595.56
17.03.01 CONCRETO SEMIPULIDO EN LOSA FC=175 KG/CM2 m3 27.07 439.64 11,901.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.07 11,901.05 100.00%
17.03.02 ENCOFRADO Y DESENCOFRADO EN PATIO m2 36.80 41.82 1,538.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.80 1,538.98 100.00%
17.03.03 JUNTA DE DILATACION m 180.47 13.78 2,486.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 180.47 2,486.88 100.00%
17.03.04 CURADO CON AGUA m2 270.71 2.47 668.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 270.71 668.65 100.00%
18 LOSAS DEPORTIVA 60,745.47
18.01 OBRAS PRELIMINARES 1,092.02
18.01.01 LIMPIEZA DE TERRENO m2 416.80 0.97 404.30 416.80 404.30 100.00% 0.00 0.00 0.00% 416.80 404.30 100.00% 0.00 0.00 0.00%
18.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 416.80 1.65 687.72 416.80 687.72 100.00% 0.00 0.00 0.00% 416.80 687.72 100.00% 0.00 0.00 0.00%
18.02 MOVIMIENTO DE TIERRAS 17,157.10
18.02.01 CORTE DE TERRENO CON MAQUINARIA m3 62.52 5.34 333.86 62.52 333.86 100.00% 0.00 0.00 0.00% 62.52 333.86 100.00% 0.00 0.00 0.00%
18.02.02 BASE GRANULAR DE 0.15 M m2 416.80 37.51 15,634.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 416.80 15,634.17 100.00%
18.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 75.02 15.85 1,189.07 75.02 1,189.07 100.00% 0.00 0.00 0.00% 75.02 1,189.07 100.00% 0.00 0.00 0.00%

Página 26
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

18.03 CONCRETO SIMPLE 31,783.50


18.03.01 CONCRETO SEMIPULIDO EN LOSA FC=175 KG/CM2 m3 62.52 439.64 27,486.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 62.52 27,486.29 100.00%
18.03.02 ENCOFRADO Y DESENCOFRADO EN LOSA DEPORTIVA m2 83.36 51.55 4,297.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 83.36 4,297.21 100.00%
18.04 PINTURAS 1,837.47
18.04.01 PINTURA DE MARCA EN LOSA DEPORTIVA m 266.30 6.90 1,837.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 266.30 1,837.47 100.00%
18.05 VARIOS 8,875.38
18.05.01 JUNTA DE DILATACION m 277.87 13.78 3,829.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 277.87 3,829.05 100.00%
18.05.02 CURADO CON ADITIVO ANTISOL m2 416.80 3.71 1,546.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 416.80 1,546.33 100.00%
18.05.03 ARCOS DE FUTBOL CON TABLERO DE BASQUET pza 2.00 1,500.00 3,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 3,000.00 100.00%
18.05.04 POSTE DE TUBO PARA VOLEY pza 2.00 250.00 500.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 500.00 100.00%
19 CONSTRUCCION DE MURO DE CONTENCION 647,548.41
19.01 OBRAS PRELIMINARES 2,466.94
19.01.01 LIMPIEZA DE TERRENO m2 941.58 0.97 913.33 800.00 776.00 84.96% 0.00 0.00 0.00% 800.00 776.00 84.96% 141.58 137.33 15.04%
19.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 941.58 1.65 1,553.61 800.00 1,320.00 84.96% 0.00 0.00 0.00% 800.00 1,320.00 84.96% 141.58 233.61 15.04%
19.02 MOVIMIENTO DE TIERRAS 123,308.74
19.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 685.44 41.41 28,384.07 120.40 4,985.76 17.57% 0.00 0.00 0.00% 120.40 4,985.76 17.57% 565.04 23,398.31 82.43%
19.02.02 NIVELACION Y APISONADO MANUAL m2 763.37 2.48 1,893.16 50.00 124.00 6.55% 0.00 0.00 0.00% 50.00 124.00 6.55% 713.37 1,769.16 93.45%
19.02.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO (AFI m3 381.63 197.01 75,184.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 381.63 75,184.93 100.00%
19.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 637.26 27.36 17,435.43 10.00 273.60 1.57% 0.00 0.00 0.00% 10.00 273.60 1.57% 627.26 17,161.83 98.43%
19.02.05 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 25.94 15.85 411.15 8.00 126.80 30.84% 0.00 0.00 0.00% 8.00 126.80 30.84% 17.94 284.35 69.16%
19.03 OBRAS DE CONCRETO 520,704.96
19.03.01 CONCRETO CICLOPEO MURO DE CONTENCION FC=140 KG/CM m3 1,108.26 372.14 412,427.88 215.00 80,010.10 19.40% 0.00 0.00 0.00% 215.00 80,010.10 19.40% 893.26 332,417.78 80.60%
19.03.02 ENCOFRADO Y DESENCOFRADO EN MURO DE CONTENCION m2 2,120.17 51.07 108,277.08 296.00 15,116.72 13.96% 0.00 0.00 0.00% 296.00 15,116.72 13.96% 1,824.17 93,160.36 86.04%
19.04 VARIOS 1,067.77
19.04.01 TUBERIA PVC SAL D=3" DRENAJE MUROS m 83.16 12.84 1,067.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 83.16 1,067.77 100.00%
20 CONSTRUCCION DE CERCO 53,726.28
20.01 OBRAS PRELIMINARES 127.62
20.01.01 LIMPIEZA DE TERRENO m2 48.71 0.97 47.25 48.71 47.25 100.00% 0.00 0.00 0.00% 48.71 47.25 100.00% 0.00 0.00 0.00%
20.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 48.71 1.65 80.37 48.71 80.37 100.00% 0.00 0.00 0.00% 48.71 80.37 100.00% 0.00 0.00 0.00%
20.02 MOVIMIENTO DE TIERRAS 49.07 0.00
20.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 0.81 41.41 33.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.81 33.54 100.00%
20.02.02 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 0.98 15.85 15.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.98 15.53 100.00%
20.03 OBRAS DE CONCRETO SIMPLE 269.87
20.03.01 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 30 m3 0.81 333.17 269.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.81 269.87 100.00%
20.04 CARPINTERIA METALICA 53,279.72
20.04.01 CERCO MALLA METALICA COCADA DE 2" m 173.51 307.07 53,279.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 173.51 53,279.72 100.00%
21 ADQUISICION E INSTALACION DE POSTES ORNAMENTALES 30,322.97
21.01 ADQUISICION DE POSTES ORNAMENTALES und 26.00 350.00 9,100.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.00 9,100.00 100.00%
21.02 TRAZO NIVELADO Y REPLANTEO m2 13.00 1.67 21.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.00 21.71 100.00%
21.03 CIMENTACION PARA POSTES m3 6.50 333.17 2,165.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.50 2,165.61 100.00%
21.04 EXCAVACION DE ZANJAS PARA CABLE SUBTERRANEO m3 76.53 41.41 3,169.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.53 3,169.11 100.00%
21.05 INSTALACION DE POSTES ORNAMENTALES und 26.00 6.34 164.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.00 164.84 100.00%
21.06 INSTALACION DE FAROLAS ORNAMENTALES und 26.00 209.37 5,443.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.00 5,443.62 100.00%
21.07 INSTALACION DE CABLE SUBTERRANEO NYY 3X10MM2 m 306.12 33.51 10,258.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 306.12 10,258.08 100.00%
22 CORTES GENERALES 145,915.73
22.01 EXCAVACION CON MAQUINARIA m3 5,516.20 6.96 38,392.75 5,516.20 38,392.75 100.00% 0.00 0.00 0.00% 5,516.20 38,392.75 100.00% 0.00 0.00 0.00%
22.02 RELLENO CON MATERIAL PROPIO, COMPACTADO m3 345.58 27.36 9,455.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 345.58 9,455.07 100.00%
22.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125HP m3 6,187.25 15.85 98,067.91 6,187.25 98,067.91 100.00% 0.00 0.00 0.00% 6,187.25 98,067.91 100.00% 0.00 0.00 0.00%
23 INSTALACION DE SISTEMA DE AGUA Y DESAGUE 28,190.61
23.01 SISTEMA DE DESAGUE 8,307.53
23.01.01 TRAZO NIVELADO Y REPLANTEO m 91.31 1.65 150.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.31 150.66 100.00%
23.01.02 EXCAVACION MANUAL PARA TUBERIA m 91.31 14.89 1,359.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.31 1,359.61 100.00%
23.01.03 REFINE NIVELACION Y COMPACTACION DE ZANJA m 91.31 3.86 352.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.31 352.46 100.00%
23.01.04 CAMA DE APOYO m 91.31 9.44 861.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.31 861.97 100.00%
23.01.05 RELLENO COMPACTADO DE ZANJAS m 91.31 12.00 1,095.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.31 1,095.72 100.00%
23.01.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 3.65 15.85 57.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.65 57.85 100.00%
23.01.07 SUMINISTRO E INSTALACION DE TUBERIA 4" DE DESAGUE m 14.03 21.56 302.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.03 302.49 100.00%
23.01.08 SUMINISTRO E INSTALACION DE TUBERIA 6" DE DESAGUE m 77.28 41.51 3,207.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.28 3,207.89 100.00%

Página 27
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

23.01.09 CAJAS DE REGISTRO DE DESAGUE 60 x 60 cm und 3.00 192.46 577.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 577.38 100.00%
23.01.10 PRUEBA HIDRAULICA m 91.31 3.74 341.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.31 341.50 100.00%
23.02 SISTEMA DE AGUA 6,827.77
23.02.01 TRAZO NIVELADO Y REPLANTEO m 112.03 1.65 184.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.03 184.85 100.00%
23.02.02 EXCAVACION MANUAL PARA TUBERIA m 112.03 14.89 1,668.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.03 1,668.13 100.00%
23.02.03 REFINE NIVELACION Y COMPACTACION DE ZANJA m 112.03 3.86 432.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.03 432.44 100.00%
23.02.04 CAMA DE APOYO m 112.03 9.44 1,057.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.03 1,057.56 100.00%
23.02.05 RELLENO COMPACTADO DE ZANJAS m 112.03 12.00 1,344.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.03 1,344.36 100.00%
23.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 5.38 15.85 85.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.38 85.27 100.00%
23.02.07 SUMINISTRO E INSTALACION DE TUBERIA 1 1/2" AGUA m 75.48 15.65 1,181.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 75.48 1,181.26 100.00%
23.02.08 SUMINISTRO E INSTALACION DE TUBERIA 3/4" AGUA m 36.55 10.07 368.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.55 368.06 100.00%
23.02.09 SUMINISTRO E INSTALACION DE ACCESORIOS glb 1.00 86.85 86.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 86.85 100.00%
23.02.10 PRUEBA HIDRAULICA m 112.03 3.74 418.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.03 418.99 100.00%
23.03 SISTEMA DE DRENAJE 13,055.31
23.03.01 TRAZO NIVELADO Y REPLANTEO m 133.95 1.65 221.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 133.95 221.02 100.00%
23.03.02 EXCAVACION MANUAL PARA TUBERIA m 133.95 14.89 1,994.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 133.95 1,994.52 100.00%
23.03.03 REFINE NIVELACION Y COMPACTACION DE ZANJA m 133.95 3.86 517.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 133.95 517.05 100.00%
23.03.04 CAMA DE APOYO m 133.95 9.44 1,264.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 133.95 1,264.49 100.00%
23.03.05 RELLENO COMPACTADO DE ZANJAS m 133.95 12.00 1,607.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 133.95 1,607.40 100.00%
23.03.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 5.36 15.85 84.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.36 84.96 100.00%
23.03.07 SUMINISTRO E INSTALACION DE TUBERIA 4" DE DESAGUE m 55.02 21.56 1,186.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 55.02 1,186.23 100.00%
23.03.08 SUMINISTRO E INSTALACION DE TUBERIA 6" DE DESAGUE m 41.00 41.51 1,701.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 41.00 1,701.91 100.00%
23.03.09 SUMINISTRO E INSTALACION DE TUBERIA 8" DE DESAGUE m 37.93 51.82 1,965.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.93 1,965.53 100.00%
23.03.10 CAJA DE REGISTRO 30X60 CM CON REJILLA METALICA und 11.00 130.35 1,433.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.00 1,433.85 100.00%
23.03.11 CAJAS DE REGISTRO DE DESAGUE 60 x 60 cm und 3.00 192.46 577.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 577.38 100.00%
23.03.12 PRUEBA HIDRAULICA m 133.95 3.74 500.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 133.95 500.97 100.00%
24 INSTALACIONES ELECTRICAS GENERALES 22,569.52
24.01 TRAZO NIVELADO Y REPLANTEO m 140.00 1.65 231.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.00 231.00 100.00%
24.02 EXCAVACION MANUAL PARA TUBERIA m 140.00 14.89 2,084.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.00 2,084.60 100.00%
24.03 REFINE NIVELACION Y COMPACTACION DE ZANJA m 140.00 3.86 540.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.00 540.40 100.00%
24.04 CAMA DE APOYO m 140.00 9.44 1,321.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.00 1,321.60 100.00%
24.05 RELLENO COMPACTADO DE ZANJAS m 140.00 12.00 1,680.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.00 1,680.00 100.00%
24.06 CABLE NYY 6MM2 m 657.93 7.04 4,631.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 657.93 4,631.83 100.00%
24.07 CABLE NYY 10MM2 m 347.04 10.57 3,668.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 347.04 3,668.21 100.00%
24.08 CABLE NYY 16MM2 m 255.00 15.18 3,870.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 255.00 3,870.90 100.00%
24.09 SUMINISTRO E INSTALACION DE TUBERIA ELECTRICA 1" m 419.99 8.79 3,691.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 419.99 3,691.71 100.00%
24.10 TABLERO DE DISTRIBUCION und 1.00 543.57 543.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 543.57 100.00%
24.11 CAJA DE REGISTRO 40X40 CM und 3.00 101.90 305.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 305.70 100.00%
25 AREAS VERDES 42,366.85
25.01 OBRAS PRELIMINARES 1,990.31
25.01.01 LIMPIEZA DE TERRENO m2 759.66 0.97 736.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 736.87 100.00%
25.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 759.66 1.65 1,253.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 1,253.44 100.00%
25.02 MOVIMIENTO DE TIERRAS 15,402.98
25.02.01 CORTE MANUAL DE TERRENO m3 75.97 24.14 1,833.92 50.00 1,207.00 65.82% 0.00 0.00 0.00% 50.00 1,207.00 65.82% 25.97 626.92 34.18%
25.02.02 PREPARACION DE TIERRA DE CHACRA m2 759.66 6.53 4,960.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 4,960.58 100.00%
25.02.03 EXT. Y NIV. DE TIERRA DE CHACRA PARA SEMBRADO DE GRA m2 759.66 9.43 7,163.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 7,163.59 100.00%
25.02.04 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 91.16 15.85 1,444.89 70.00 1,109.50 76.79% 0.00 0.00 0.00% 70.00 1,109.50 76.79% 21.16 335.39 23.21%
25.03 SEMBRADO DE GRASS 17,973.56
25.03.01 SEMBRADO DE GRASS m2 759.66 23.66 17,973.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 17,973.56 100.00%
25.04 VARIOS 7,000.00
25.04.01 ADQUISICION E INSTALACION DE JUEGO RECREATIVOS und 2.00 3,500.00 7,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 7,000.00 100.00%
26 ADQUISICION DE EQUIPAMIENTO 63,256.00
26.01 ADQUISICION DE EQUIPAMIENTO COCINA glb 1.00 4,980.00 4,980.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,980.00 100.00%
26.02 ADQUISICION DE EQUIPAMIENTO SALA DE COMPUTO glb 1.00 58,276.00 58,276.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 58,276.00 100.00%
27 ADQUISICION DE MOBILIARIO ESCOLAR 64,465.00
27.01 ADQUISICION DE MOBILIARIO ESCOLAR INICIAL glb 4.00 240.00 960.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 960.00 100.00%
27.02 ADQUISICION DE MOBILIARIO ESCOLAR PRIMARIO glb 74.00 270.00 19,980.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 74.00 19,980.00 100.00%
27.03 ADQUISICION DE MOBILIARIO ESCOLAR SECUNDARIO glb 53.00 270.00 14,310.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 53.00 14,310.00 100.00%

Página 28
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

27.04 ADQUISICION DE MOBILIARIO PARA AULAS glb 1.00 10,380.00 10,380.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 10,380.00 100.00%
27.05 ADQUISICION DE MOBILIARIO PARA SALA DE USOS MULTIPLES glb 1.00 3,615.00 3,615.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,615.00 100.00%
27.06 ADQUISICION DE MOBILIARIO PARA SALA DE COMPUTO glb 1.00 6,865.00 6,865.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 6,865.00 100.00%
27.07 ADQUISICION DE MOBILIARIO PARA DIRECCION glb 1.00 715.00 715.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 715.00 100.00%
27.08 ADQUISICION DE MOBILIARIO PARA SECRETARIA Y ESPERA glb 1.00 970.00 970.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 970.00 100.00%
27.09 ADQUISICION DE MOBILIARIO PARA SALA DE PROFESORES glb 1.00 2,295.00 2,295.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,295.00 100.00%
27.10 ADQUISICION DE MOBILIARIO PARA CENTRO DE RECURSOS E glb 1.00 2,855.00 2,855.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,855.00 100.00%
27.11 ADQUISICION DE MOBILIARIO PARA COCINA glb 1.00 1,520.00 1,520.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,520.00 100.00%
28 FLETE TERRESTRE 4,000.00
28.01 TRANSPORTE DE EQUIPAMIENTO Y MOBILIARIO A OBRA glb 1.00 4,000.00 4,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,000.00 100.00%

COSTO DIRECTO 3,124,772.22 487,102.54 49,755.98 536,858.52 2,587,913.70


GASTOS GENERALES 9.21% 287,655.74 44,840.98 4,580.36 49,421.34 238,234.40
UTILIDAD 9.00% 281,229.50 43,839.23 4,478.04 48,317.27 232,912.23
SUB - TOTAL 3,693,657.46 575,782.75 58,814.38 634,597.13 3,059,060.33
FACTOR DE RELACION 1.00000 3,693,657.46 575,782.75 58,814.38 634,597.13 3,059,060.33

MONTO BRUTO VALORIZADO 3,693,657.46 575,782.75 58,814.38 634,597.13 3,059,060.33


SUB-TOTAL 3,693,657.46 575,782.75 58,814.38 634,597.13 3,059,060.33

IGV (18%) 18% 103,640.90 10,586.59 114,227.48 550,630.86

VALOR REFERENCIAL 4,358,515.80 679,423.65 15.59% 69,400.97 1.59% 748,824.61 17.18% 3,609,691.19 82.82%
EXPEDIENTE TECNICO 110,263.07

EJECUCION DE OBRA+EXPEDIENTE TECNICO 4,468,778.87


SUPERVISION 110,263.07

TOTAL DE INVERSION 4,579,041.94

Página 29
OBRA : MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N° 22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA – DEPARTAMENTO DE ICA
ENTIDAD : GOBIERNO REGIONAL DE ICA
SUPERVISIÓN : CONSORCIO SUPERVISION CHINCHA
CONTRATISTA : ICONSER SAC
PLAZO : 120 DIAS CALENDARIOS
MODALIDAD : A SUMA ALZADA

PLANILLA DE VALORIZACION N° 09
01/07/2019 AL 31/07/2019

PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

01 TRABAJOS GENERALES 114,563.43


01.01 OBRAS PROVISIONALES 6,950.00
01.01.01 CARTEL PARA LA OBRA 2.40 X 3.60 und 1.00 950.00 950.00 1.00 950.00 100.00% 0.00 0.00 0.00% 1.00 950.00 100.00% 0.00 0.00 0.00%
01.01.02 ALMACEN DE OBRA glb 1.00 6,000.00 6,000.00 1.00 6,000.00 100.00% 0.00 0.00 0.00% 1.00 6,000.00 100.00% 0.00 0.00 0.00%
01.02 OBRAS PRELIMINARES 107,613.43
01.02.01 TRANSPORTE DE MATERIALES A OBRA glb 1.00 58,980.01 58,980.01 0.75 44,235.01 75.00% 0.15 8,847.00 15.00% 0.90 53,082.01 90.00% 0.10 5,898.00 10.00%
01.02.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y HERRAMIE glb 1.00 22,199.02 22,199.02 0.93 20,645.09 93.00% 0.03 665.97 3.00% 0.96 21,311.06 96.00% 0.04 887.96 4.00%
01.02.03 IMPLEMENTOS DE SEGURIDAD PARA LOS TRABAJADORES glb 1.00 10,000.00 10,000.00 1.00 10,000.00 100.00% 0.00 0.00 0.00% 1.00 10,000.00 100.00% 0.00 0.00 0.00%
01.02.04 DEMOLICION DE ESTRUCTURAS DE CONCRETO m3 80.00 189.58 15,166.40 80.00 15,166.40 100.00% 0.00 0.00 0.00% 80.00 15,166.40 100.00% 0.00 0.00 0.00%
01.02.05 ELIMINACION DE MATERIAL DEMOLIDO CARGUIO C/EQ 125HP m3 80.00 15.85 1,268.00 80.00 1,268.00 100.00% 0.00 0.00 0.00% 80.00 1,268.00 100.00% 0.00 0.00 0.00%
02 SECTOR INICIAL 225,861.54
02.01 ESTRUCTURAS 84,768.77
02.01.01 OBRAS PRELIMINARES 372.30
02.01.01.01 LIMPIEZA DE TERRENO m2 138.40 0.95 131.48 138.40 131.48 100.00% 0.00 0.00 0.00% 138.40 131.48 100.00% 0.00 0.00 0.00%
02.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 138.40 1.74 240.82 138.40 240.82 100.00% 0.00 0.00 0.00% 138.40 240.82 100.00% 0.00 0.00 0.00%
02.01.02 MOVIMIENTO DE TIERRAS 7,902.25
02.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 35.16 41.41 1,455.98 35.16 1,455.98 100.00% 0.00 0.00 0.00% 35.16 1,455.98 100.00% 0.00 0.00 0.00%
02.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 50.40 41.41 2,087.06 50.40 2,087.06 100.00% 0.00 0.00 0.00% 50.40 2,087.06 100.00% 0.00 0.00 0.00%
02.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 112.10 2.48 278.01 112.10 278.01 100.00% 0.00 0.00 0.00% 112.10 278.01 100.00% 0.00 0.00 0.00%
02.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 32.53 27.36 890.02 32.53 890.02 100.00% 0.00 0.00 0.00% 32.53 890.02 100.00% 0.00 0.00 0.00%
02.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 11.21 197.01 2,208.48 11.21 2,208.48 100.00% 0.00 0.00 0.00% 11.21 2,208.48 100.00% 0.00 0.00 0.00%
02.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 62.00 15.85 982.70 62.00 982.70 100.00% 0.00 0.00 0.00% 62.00 982.70 100.00% 0.00 0.00 0.00%
02.01.03 OBRAS DE CONCRETO SIMPLE 15,500.07
02.01.03.01 SOLADO PARA ZAPATAS m2 36.00 35.13 1,264.68 36.00 1,264.68 100.00% 0.00 0.00 0.00% 36.00 1,264.68 100.00% 0.00 0.00 0.00%
02.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 13.08 333.17 4,357.86 13.08 4,357.86 100.00% 0.00 0.00 0.00% 13.08 4,357.86 100.00% 0.00 0.00 0.00%
02.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 5.39 387.67 2,089.54 5.39 2,089.54 100.00% 0.00 0.00 0.00% 5.39 2,089.54 100.00% 0.00 0.00 0.00%
02.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 71.83 46.45 3,336.50 71.83 3,336.50 100.00% 0.00 0.00 0.00% 71.83 3,336.50 100.00% 0.00 0.00 0.00%
02.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 112.10 39.71 4,451.49 112.10 4,451.49 100.00% 0.00 0.00 0.00% 112.10 4,451.49 100.00% 0.00 0.00 0.00%
02.01.04 OBRAS DE CONCRETO ARMADO 60,994.15
02.01.04.01 ZAPATAS 10,006.67
02.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 18.00 449.81 8,096.58 18.00 8,096.58 100.00% 0.00 0.00 0.00% 18.00 8,096.58 100.00% 0.00 0.00 0.00%
02.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 456.96 4.18 1,910.09 456.96 1,910.09 100.00% 0.00 0.00 0.00% 456.96 1,910.09 100.00% 0.00 0.00 0.00%
02.01.04.02 VIGA DE CIMENTACION 13,214.46
02.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 9.50 449.81 4,273.20 9.50 4,273.20 100.00% 0.00 0.00 0.00% 9.50 4,273.20 100.00% 0.00 0.01 0.00%
02.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 76.00 51.41 3,907.16 76.00 3,907.16 100.00% 0.00 0.00 0.00% 76.00 3,907.16 100.00% 0.00 0.00 0.00%
02.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 1,204.33 4.18 5,034.10 1,204.33 5,034.10 100.00% 0.00 0.00 0.00% 1,204.33 5,034.10 100.00% 0.00 0.00 0.00%
02.01.04.03 COLUMNAS Y PLACAS 19,610.14
02.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 11.53 449.81 5,186.31 11.53 5,186.31 100.00% 0.00 0.00 0.00% 11.53 5,186.31 100.00% 0.00 0.00 0.00%
02.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 127.00 53.08 6,741.16 127.00 6,741.16 100.00% 0.00 0.00 0.00% 127.00 6,741.16 100.00% 0.00 0.00 0.00%
02.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 1,837.96 4.18 7,682.67 1,837.96 7,682.67 100.00% 0.00 0.00 0.00% 1,837.96 7,682.67 100.00% 0.00 0.00 0.00%
02.01.04.04 VIGAS 15,656.91
02.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 10.19 449.81 4,583.56 10.19 4,583.56 100.00% 0.00 0.00 0.00% 10.19 4,583.56 100.00% 0.00 0.00 0.00%
02.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 98.14 62.13 6,097.44 98.14 6,097.44 100.00% 0.00 0.00 0.00% 98.14 6,097.44 100.00% 0.00 0.00 0.00%
02.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 1,190.41 4.18 4,975.91 1,190.41 4,975.91 100.00% 0.00 0.00 0.00% 1,190.41 4,975.91 100.00% 0.00 0.00 0.00%

Página 30
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

02.01.04.05 COLUMNETAS 2,505.97


02.01.04.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 1.33 419.72 558.23 1.33 558.23 100.00% 0.00 0.00 0.00% 1.33 558.23 100.00% 0.00 0.00 0.00%
02.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 17.76 53.08 942.70 17.76 942.70 100.00% 0.00 0.00 0.00% 17.76 942.70 100.00% 0.00 0.00 0.00%
02.01.04.05.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 240.44 4.18 1,005.04 240.44 1,005.04 100.00% 0.00 0.00 0.00% 240.44 1,005.04 100.00% 0.00 0.00 0.00%
02.02 ARQUITECTURA 119,572.63
02.02.01 ALBAÑILERIA 6,173.76
02.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 111.48 55.38 6,173.76 111.48 6,173.76 100.00% 0.00 0.00 0.00% 111.48 6,173.76 100.00% 0.00 0.00 0.00%
02.02.02 REVOQUES 16,085.43
02.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 140.42 26.62 3,737.98 28.08 747.60 20.00% 105.32 2,803.49 75.00% 133.40 3,551.08 95.00% 7.02 186.90 5.00%
02.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 93.80 26.62 2,496.96 0.00 0.00 0.00% 93.80 2,496.96 100.00% 93.80 2,496.96 100.00% 0.00 0.00 0.00%
02.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 139.00 28.80 4,003.20 27.80 800.64 20.00% 111.20 3,202.56 80.00% 139.00 4,003.20 100.00% 0.00 0.00 0.00%
02.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 245.20 3.45 845.94 0.00 0.00 0.00% 245.20 845.94 100.00% 245.20 845.94 100.00% 0.00 0.00 0.00%
02.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 98.14 31.39 3,080.61 19.63 616.12 20.00% 78.51 2,464.49 80.00% 98.14 3,080.61 100.00% 0.00 0.00 0.00%
02.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 99.44 3.45 343.07 0.00 0.00 0.00% 99.44 343.07 100.00% 99.44 343.07 100.00% 0.00 0.00 0.00%
02.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 64.80 13.60 881.28 0.00 0.00 0.00% 64.80 881.28 100.00% 64.80 881.28 100.00% 0.00 0.00 0.00%
02.02.02.08 BRUÑAS DE 1.0 cm m 74.72 9.32 696.39 0.00 0.00 0.00% 74.72 696.39 100.00% 74.72 696.39 100.00% 0.00 0.00 0.00%
02.02.03 PISOS Y PAVIMENTOS 10,893.71
02.02.03.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 118.50 35.38 4,192.53 118.50 4,192.53 100.00% 0.00 0.00 0.00% 118.50 4,192.53 100.00% 0.00 0.00 0.00%
02.02.03.02 PISO DE CERAMICO 45 X 45 CM m2 118.50 56.55 6,701.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 118.50 6,701.18 100.00%
02.02.04 CONTRAZOCALOS 5,499.22
02.02.04.01 CONTRAZOCALO CERAMICO H=0.10 m. m 77.10 19.27 1,485.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.10 1,485.72 100.00%
02.02.04.02 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 96.80 15.40 1,490.72 0.00 0.00 0.00% 91.96 1,416.18 95.00% 91.96 1,416.18 95.00% 4.84 74.54 5.00%
02.02.04.03 ZOCALO DE CERAMICA 20 X 30 CM m2 27.15 92.92 2,522.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.15 2,522.78 100.00%
02.02.05 CARPINTERIA MADERA 3,658.71
02.02.05.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 5.72 496.22 2,838.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.72 2,838.38 100.00%
02.02.05.02 PUERTA CONTRAPLACADA SEGUN DISEÑO m2 2.34 350.57 820.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.34 820.33 100.00%
02.02.06 CARPINTERIA METALICA 7,302.36
02.02.06.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 37.84 192.98 7,302.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.84 7,302.36 100.00%
02.02.07 CERRAJERIA 245.96
02.02.07.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
02.02.07.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 10.00 9.01 90.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 90.10 100.00%
02.02.08 VIDRIOS, CRISTALES Y SIMILARES 5,262.45
02.02.08.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 407.31 12.92 5,262.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 407.31 5,262.45 100.00%
02.02.09 PINTURAS 4,843.26
02.02.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 222.96 10.57 2,356.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 222.96 2,356.69 100.00%
02.02.09.02 PINTURA EN CONTRAZOCALO m2 9.68 7.96 77.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.68 77.05 100.00%
02.02.09.03 PINTURA EN VIGAS m2 98.14 13.73 1,347.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 98.14 1,347.46 100.00%
02.02.09.04 PINTURA EN COLUMNAS Y PLACAS m2 80.52 13.19 1,062.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 80.52 1,062.06 100.00%
02.02.10 CUBIERTA METALICA Y CIELO RASO 59,607.77
02.02.10.01 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 190.30 122.00 23,216.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 190.30 23,216.60 100.00%
02.02.10.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 183.00 75.18 13,757.94 164.70 12,382.15 90.00% 18.30 1,375.79 10.00% 183.00 13,757.94 100.00% 0.00 0.00 0.00%
02.02.10.03 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 194.11 116.60 22,633.23 0.00 0.00 0.00% 174.70 20,369.90 90.00% 174.70 20,369.90 90.00% 19.41 2,263.33 10.00%
02.03 INSTALACIONES ELECTRICAS 14,806.77
02.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 25.00 145.99 3,649.75 0.00 0.00 0.00% 12.50 1,824.88 50.00% 12.50 1,824.88 50.00% 12.50 1,824.88 50.00%
02.03.02 SALIDA TOMACORRIENTE pto 8.00 215.17 1,721.36 0.00 0.00 0.00% 4.00 860.68 50.00% 4.00 860.68 50.00% 4.00 860.68 50.00%
02.03.03 SALIDA TOMACORRIENTE A PRUEBA DE AGUA pto 2.00 219.38 438.76 0.00 0.00 0.00% 1.00 219.38 50.00% 1.00 219.38 50.00% 1.00 219.38 50.00%
02.03.04 SALIDA PARA INTERRUPTOR SIMPLE pto 5.00 108.23 541.15 0.00 0.00 0.00% 2.50 270.58 50.00% 2.50 270.58 50.00% 2.50 270.58 50.00%
02.03.05 SALIDA PARA INTERRUPTOR TRIPLE pto 2.00 114.38 228.76 0.00 0.00 0.00% 1.00 114.38 50.00% 1.00 114.38 50.00% 1.00 114.38 50.00%
02.03.06 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 22.00 205.71 4,525.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.00 4,525.62 100.00%
02.03.07 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 3.00 68.59 205.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 205.77 100.00%
02.03.08 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 136.56 10.81 1,476.21 90.00 972.90 65.91% 46.56 503.31 34.09% 136.56 1,476.21 100.00% 0.00 0.00 0.00%
02.03.09 ALAMBRE THHN 2.5 mm2 m 264.68 1.67 442.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 264.68 442.02 100.00%
02.03.10 ALAMBRE THHN 4 mm2 m 106.00 2.19 232.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 106.00 232.14 100.00%
02.03.11 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
02.03.12 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
02.03.13 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
02.04 INSTALACIONES SANITARIAS 6,713.37
02.04.01 APARATOS Y ACCESORIOS SANITARIOS 1,193.88

Página 31
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

02.04.01.01 INODORO TANQUE BAJO pza 2.00 361.79 723.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 723.58 100.00%
02.04.01.02 LAVATORIO DE LOZA BLANCA und 2.00 195.88 391.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 391.76 100.00%
02.04.01.03 CAÑO DE BRONCE - LLAVE DE 1/2" und 2.00 39.27 78.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 78.54 100.00%
02.04.02 SISTEMA DE DESAGUE 2,066.22
02.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 2.00 93.15 186.30 2.00 186.30 100.00% 0.00 0.00 0.00% 2.00 186.30 100.00% 0.00 0.00 0.00%
02.04.02.02 SALIDA DE DESAGUE PVC D=4" pto 2.00 145.54 291.08 2.00 291.08 100.00% 0.00 0.00 0.00% 2.00 291.08 100.00% 0.00 0.00 0.00%
02.04.02.03 SALIDA VENTILACION DE 2" pto 2.00 58.08 116.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 116.16 100.00%
02.04.02.04 REGISTRO DE BRONCE 4" und 1.00 285.99 285.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 285.99 100.00%
02.04.02.05 SUMIDERO DE 2" pza 1.00 77.41 77.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 77.41 100.00%
02.04.02.06 TUBERIA PVC SAL P/DESAGUE D=4" m 10.00 33.95 339.50 10.00 339.50 100.00% 0.00 0.00 0.00% 10.00 339.50 100.00% 0.00 0.00 0.00%
02.04.02.07 YEE PVC SAL 4"X2" und 3.00 61.97 185.91 3.00 185.91 100.00% 0.00 0.00 0.00% 3.00 185.91 100.00% 0.00 0.00 0.00%
02.04.02.08 CODO PVC SAL P/DESAGUE D=2" und 2.00 25.81 51.62 2.00 51.62 100.00% 0.00 0.00 0.00% 2.00 51.62 100.00% 0.00 0.00 0.00%
02.04.02.09 EXCAVACION MANUAL PARA TUBERIA m 10.00 14.89 148.90 10.00 148.90 100.00% 0.00 0.00 0.00% 10.00 148.90 100.00% 0.00 0.00 0.00%
02.04.02.10 REFINE NIVELACION Y COMPACTACION DE ZANJA m 10.00 3.86 38.60 10.00 38.60 100.00% 0.00 0.00 0.00% 10.00 38.60 100.00% 0.00 0.00 0.00%
02.04.02.11 CAMA DE APOYO m 10.00 9.44 94.40 10.00 94.40 100.00% 0.00 0.00 0.00% 10.00 94.40 100.00% 0.00 0.00 0.00%
02.04.02.12 RELLENO COMPACTADO DE ZANJAS m 10.00 12.00 120.00 10.00 120.00 100.00% 0.00 0.00 0.00% 10.00 120.00 100.00% 0.00 0.00 0.00%
02.04.02.13 CAJA DE REGISTRO CON REJILLA METALICA und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
02.04.03 SISTEMA DE AGUA FRIA 955.73
02.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 4.00 72.84 291.36 3.00 218.52 75.00% 0.00 0.00 0.00% 3.00 218.52 75.00% 1.00 72.84 25.00%
02.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 8.05 17.01 136.93 8.05 136.93 100.00% 0.00 0.00 0.00% 8.05 136.93 100.00% 0.00 0.00 0.00%
02.04.03.03 CODO PVC 1/2" und 1.00 9.94 9.94 1.00 9.94 100.00% 0.00 0.00 0.00% 1.00 9.94 100.00% 0.00 0.00 0.00%
02.04.03.04 TEE PVC 1/2" und 3.00 11.04 33.12 3.00 33.12 100.00% 0.00 0.00 0.00% 3.00 33.12 100.00% 0.00 0.00 0.00%
02.04.03.05 EXCAVACION MANUAL PARA TUBERIA m 7.05 14.89 104.97 7.05 104.97 100.00% 0.00 0.00 0.00% 7.05 104.97 100.00% 0.00 0.00 0.00%
02.04.03.06 REFINE NIVELACION Y COMPACTACION DE ZANJA m 7.05 3.86 27.21 7.05 27.21 100.01% 0.00 0.00 0.00% 7.05 27.21 100.01% 0.00 0.00 0.00%
02.04.03.07 CAMA DE APOYO m 7.05 9.44 66.55 7.05 66.55 100.00% 0.00 0.00 0.00% 7.05 66.55 100.00% 0.00 0.00 0.00%
02.04.03.08 RELLENO COMPACTADO DE ZANJAS m 7.05 12.00 84.60 7.05 84.60 100.00% 0.00 0.00 0.00% 7.05 84.60 100.00% 0.00 0.00 0.00%
02.04.03.09 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 1.00 70.70 70.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 70.70 100.00%
02.04.03.10 CAJA PARA VALVULAS und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
02.04.04 SISTEMA DE AGUA PLUVIAL 2,497.54
02.04.04.01 CANALETA PARA AGUA FLUVIAL DE 4" m 36.60 58.77 2,150.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.60 2,150.98 100.00%
02.04.04.02 TUBERIA PVC SAL D=4" m 6.00 45.40 272.40 0.00 0.00 0.00% 4.20 190.68 70.00% 4.20 190.68 70.00% 1.80 81.72 30.00%
02.04.04.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 0.00 0.00 0.00% 1.40 51.91 70.00% 1.40 51.91 70.00% 0.60 22.25 30.00%
03 SECTOR SECUNDARIA 373,415.79
03.01 ESTRUCTURAS 157,033.01
03.01.01 OBRAS PRELIMINARES 311.88
03.01.01.01 LIMPIEZA DE TERRENO m2 115.94 0.95 110.14 115.94 110.14 100.00% 0.00 0.00 0.00% 115.94 110.14 100.00% 0.00 0.00 0.00%
03.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 115.94 1.74 201.74 115.94 201.74 100.00% 0.00 0.00 0.00% 115.94 201.74 100.00% 0.00 0.00 0.00%
03.01.02 MOVIMIENTO DE TIERRAS 11,127.55
03.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 20.92 41.41 866.30 17.00 703.97 81.26% 3.92 162.33 18.74% 20.92 866.30 100.00% 0.00 0.00 0.00%
03.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 85.68 41.41 3,548.01 70.00 2,898.70 81.70% 15.68 649.31 18.30% 85.68 3,548.01 100.00% 0.00 0.00 0.00%
03.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 105.00 2.48 260.40 0.00 0.00 0.00% 105.00 260.40 100.00% 105.00 260.40 100.00% 0.00 0.00 0.00%
03.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 55.88 27.36 1,528.88 0.00 0.00 0.00% 55.88 1,528.88 100.00% 55.88 1,528.88 100.00% 0.00 0.00 0.00%
03.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 19.69 197.01 3,879.13 0.00 0.00 0.00% 19.69 3,879.13 100.00% 19.69 3,879.13 100.00% 0.00 0.00 0.00%
03.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 65.92 15.85 1,044.83 55.00 871.75 83.43% 10.92 173.08 16.57% 65.92 1,044.83 100.00% 0.00 0.00 0.00%
03.01.03 OBRAS DE CONCRETO SIMPLE 12,111.33
03.01.03.01 SOLADO PARA ZAPATAS m2 65.83 35.13 2,312.61 53.20 1,868.92 80.81% 12.63 443.69 19.19% 65.83 2,312.61 100.00% 0.00 0.00 0.00%
03.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.72 333.17 1,905.73 4.58 1,525.92 80.07% 1.14 379.81 19.93% 5.72 1,905.73 100.00% 0.00 0.00 0.00%
03.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 3.70 387.67 1,434.38 0.00 0.00 0.00% 3.70 1,434.38 100.00% 3.70 1,434.38 100.00% 0.00 0.00 0.00%
03.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 49.28 46.45 2,289.06 0.00 0.00 0.00% 49.28 2,289.06 100.00% 49.28 2,289.06 100.00% 0.00 0.00 0.00%
03.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 105.00 39.71 4,169.55 0.00 0.00 0.00% 105.00 4,169.55 100.00% 105.00 4,169.55 100.00% 0.00 0.00 0.00%
03.01.04 OBRAS DE CONCRETO ARMADO 133,482.25
03.01.04.01 ZAPATAS 20,484.56
03.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 35.51 449.81 15,972.75 28.50 12,819.59 80.26% 7.01 3,153.17 19.74% 35.51 15,972.75 100.00% 0.00 0.00 0.00%
03.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 1,079.38 4.18 4,511.81 1,079.38 4,511.81 100.00% 0.00 0.00 0.00% 1,079.38 4,511.81 100.00% 0.00 0.00 0.00%
03.01.04.02 VIGA DE CIMENTACION 12,509.61
03.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 8.59 449.81 3,863.87 0.00 0.00 0.00% 8.59 3,863.87 100.00% 8.59 3,863.87 100.00% 0.00 0.00 0.00%
03.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 68.75 51.41 3,534.44 0.00 0.00 0.00% 68.75 3,534.44 100.00% 68.75 3,534.44 100.00% 0.00 0.00 0.00%
03.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 1,222.80 4.18 5,111.30 856.00 3,578.08 70.00% 366.84 1,533.39 30.00% 1,222.84 5,111.47 100.00% -0.04 -0.17 0.00%

Página 32
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

03.01.04.03 COLUMNAS Y PLACAS 47,206.14


03.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 27.42 449.81 12,333.79 0.00 0.00 0.00% 27.42 12,333.79 100.00% 27.42 12,333.79 100.00% 0.00 0.00 0.00%
03.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 281.66 53.08 14,950.51 0.00 0.00 0.00% 281.66 14,950.51 100.00% 281.66 14,950.51 100.00% 0.00 0.00 0.00%
03.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 4,765.99 4.18 19,921.84 4,527.69 18,925.74 95.00% 238.30 996.09 5.00% 4,765.99 19,921.84 100.00% 0.00 0.00 0.00%
03.01.04.04 VIGAS 27,967.41
03.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 16.99 449.81 7,642.27 0.00 0.00 0.00% 8.50 3,821.14 50.00% 8.50 3,821.14 50.00% 8.49 3,821.13 50.00%
03.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 163.64 62.13 10,166.95 0.00 0.00 0.00% 81.82 5,083.48 50.00% 81.82 5,083.48 50.00% 81.82 5,083.47 50.00%
03.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 2,430.19 4.18 10,158.19 0.00 0.00 0.00% 1,215.10 5,079.10 50.00% 1,215.10 5,079.10 50.00% 1,215.09 5,079.09 50.00%
03.01.04.05 LOSAS ALIGERADAS 16,968.05
03.01.04.05.01 CONCRETO LOSA ALIGERADA f'c= 210 kg/cm2 m3 11.60 449.81 5,217.80 0.00 0.00 0.00% 11.60 5,217.80 100.00% 11.60 5,217.80 100.00% 0.00 0.00 0.00%
03.01.04.05.02 LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO m2 132.54 51.12 6,775.44 0.00 0.00 0.00% 132.54 6,775.44 100.00% 132.54 6,775.44 100.00% 0.00 0.00 0.00%
03.01.04.05.03 LOSAS ALIGERADAS ACERO fy=4,200 kg/cm2 kg 466.17 4.18 1,948.59 0.00 0.00 0.00% 466.17 1,948.59 100.00% 466.17 1,948.59 100.00% 0.00 0.00 0.00%
03.01.04.05.04 LOSA ALIGERADA LADRILLO HUECO 15X30X30 und 1,104.46 2.74 3,026.22 0.00 0.00 0.00% 1,104.46 3,026.22 100.00% 1,104.46 3,026.22 100.00% 0.00 0.00 0.00%
03.01.04.06 COLUMNETAS 7,805.24
03.01.04.06.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 4.39 419.72 1,842.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.39 1,842.57 100.00%
03.01.04.06.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 58.56 53.08 3,108.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.56 3,108.36 100.00%
03.01.04.06.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 682.85 4.18 2,854.31 0.00 0.00 0.00% 478.00 1,998.02 70.00% 478.00 1,998.02 70.00% 204.85 856.29 30.00%
03.01.04.07 VIGAS COLLARIN 541.24
03.01.04.07.01 CONCRETO VIGAS COLLARIN f'c=175 kg/cm2 m3 0.38 419.72 159.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.38 159.49 100.00%
03.01.04.07.02 ENCOFRADO Y DESENCOFRADO EN VIGAS COLLARIN m2 5.12 53.08 271.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.12 271.77 100.00%
03.01.04.07.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN VIGAS COLLARIN kg 26.31 4.18 109.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.31 109.98 100.00%
03.02 ARQUITECTURA 161,830.49
03.02.01 ALBAÑILERIA 8,900.12
03.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 160.71 55.38 8,900.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 160.71 8,900.12 100.00%
03.02.02 REVOQUES 27,991.70
03.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 210.39 26.62 5,600.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 210.39 5,600.58 100.00%
03.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 111.03 26.62 2,955.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 111.03 2,955.62 100.00%
03.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 281.66 28.80 8,111.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 281.66 8,111.81 100.00%
03.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 439.60 3.45 1,516.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 439.60 1,516.62 100.00%
03.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 163.64 31.39 5,136.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 163.64 5,136.66 100.00%
03.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 398.80 3.45 1,375.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 398.80 1,375.86 100.00%
03.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 115.20 13.60 1,566.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 115.20 1,566.72 100.00%
03.02.02.08 BRUÑAS DE 1.0 cm m 185.39 9.32 1,727.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 185.39 1,727.83 100.00%
03.02.03 CIELO RASO 5,746.93
03.02.03.01 TARRAJEO DE CIELO RASO - SUPERFICIE CON CEMENTO-A m2 132.54 43.36 5,746.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.54 5,746.93 100.00%
03.02.04 PISOS Y PAVIMENTOS 20,912.44
03.02.04.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 210.00 35.38 7,429.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 210.00 7,429.80 100.00%
03.02.04.02 PISO DE CERAMICO 45 X 45 CM m2 210.00 56.55 11,875.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 210.00 11,875.50 100.00%
03.02.04.03 PISO CEMENTO PULIDO E=2" m2 30.99 51.86 1,607.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 30.99 1,607.14 100.00%
03.02.05 CONTRAZOCALOS 3,920.57
03.02.05.01 CONTRAZOCALO CERAMICO H=0.10 m. m 140.40 19.27 2,705.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.40 2,705.51 100.00%
03.02.05.02 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 78.90 15.40 1,215.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 78.90 1,215.06 100.00%
03.02.06 CARPINTERIA MADERA 7,443.30
03.02.06.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 15.00 496.22 7,443.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 7,443.30 100.00%
03.02.07 CARPINTERIA METALICA 10,768.28
03.02.07.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 55.80 192.98 10,768.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 55.80 10,768.28 100.00%
03.02.08 CERRAJERIA 629.76
03.02.08.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 6.00 77.93 467.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 467.58 100.00%
03.02.08.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 18.00 9.01 162.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 162.18 100.00%
03.02.09 VIDRIOS, CRISTALES Y SIMILARES 7,760.14
03.02.09.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 600.63 12.92 7,760.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 600.63 7,760.14 100.00%
03.02.10 PINTURAS 9,374.13
03.02.10.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 331.68 10.57 3,505.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 331.68 3,505.86 100.00%
03.02.10.02 PINTURA EN CONTRAZOCALO m2 44.48 7.96 354.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 44.48 354.06 100.00%
03.02.10.03 PINTURA EN VIGAS m2 124.98 13.73 1,715.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 124.98 1,715.98 100.00%
03.02.10.04 PINTURA EN COLUMNAS m2 181.75 13.19 2,397.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 181.75 2,397.28 100.00%
03.02.10.05 PINTURA EN CIELO RASO m2 132.54 10.57 1,400.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.54 1,400.95 100.00%
03.02.11 CUBIERTA METALICA Y CIELO RASO 58,383.12

Página 33
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

03.02.11.01 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 185.92 116.60 21,678.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 185.92 21,678.27 100.00%
03.02.11.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 180.50 75.18 13,569.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 180.50 13,569.99 100.00%
03.02.11.03 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 189.63 122.00 23,134.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 189.63 23,134.86 100.00%
03.03 INSTALACIONES ELECTRICAS 26,845.81
03.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 48.00 145.99 7,007.52 0.00 0.00 0.00% 14.40 2,102.26 30.00% 14.40 2,102.26 30.00% 33.60 4,905.26 70.00%
03.03.02 SALIDA TOMACORRIENTE pto 18.00 215.17 3,873.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 3,873.06 100.00%
03.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 108.23 100.00%
03.03.04 SALIDA PARA INTERRUPTOR DOBLE pto 6.00 112.89 677.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 677.34 100.00%
03.03.05 SALIDA PARA INTERRUPTOR TRIPLE pto 2.00 114.38 228.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 228.76 100.00%
03.03.06 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 48.00 205.71 9,874.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 48.00 9,874.08 100.00%
03.03.07 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 1.00 68.59 68.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 68.59 100.00%
03.03.08 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 218.62 10.81 2,363.28 0.00 0.00 0.00% 98.38 1,063.48 45.00% 98.38 1,063.48 45.00% 120.24 1,299.80 55.00%
03.03.09 ALAMBRE THHN 2.5 mm2 m 324.68 1.67 542.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 324.68 542.22 100.00%
03.03.10 ALAMBRE THHN 4 mm2 m 131.32 2.19 287.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 131.32 287.59 100.00%
03.03.11 TABLERO DE DISTRIBUCION und 1.00 469.91 469.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 469.91 100.00%
03.03.12 SUBTABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
03.03.13 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
03.03.14 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
03.04 INSTALACIONES SANITARIAS 2,809.47
03.04.01 SISTEMA DE AGUA PLUVIAL 2,809.47
03.04.01.01 CANALETA PARA AGUA FLUVIAL DE 4" m 36.50 58.77 2,145.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.50 2,145.11 100.00%
03.04.01.02 TUBERIA PVC SAL D=4" m 13.00 45.40 590.20 0.00 0.00 0.00% 2.60 118.04 20.00% 2.60 118.04 20.00% 10.40 472.16 80.00%
03.04.01.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 0.00 0.00 0.00% 0.40 14.83 20.00% 0.40 14.83 20.00% 1.60 59.33 80.00%
03.05 CONSTRUCCION DE ESCALERAS 24,897.01
03.05.01 OBRAS PRELIMINARES 48.31
03.05.01.01 LIMPIEZA DE TERRENO m2 17.96 0.95 17.06 0.00 0.00 0.00% 17.96 17.06 100.00% 17.96 17.06 100.00% 0.00 0.00 0.00%
03.05.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 17.96 1.74 31.25 0.00 0.00 0.00% 17.96 31.25 100.00% 17.96 31.25 100.00% 0.00 0.00 0.00%
03.05.02 MOVIMIENTO DE TIERRAS 1,179.42
03.05.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 13.85 41.41 573.53 0.00 0.00 0.00% 13.85 573.53 100.00% 13.85 573.53 100.00% 0.00 0.00 0.00%
03.05.02.02 NIVELACION Y APISONADO MANUAL PARA PISOS m2 14.13 2.48 35.04 0.00 0.00 0.00% 14.13 35.04 100.00% 14.13 35.04 100.00% 0.00 0.00 0.00%
03.05.02.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 3.54 27.36 96.85 0.00 0.00 0.00% 3.54 96.85 100.00% 3.54 96.85 100.00% 0.00 0.00 0.00%
03.05.02.04 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 1.41 197.01 277.78 0.00 0.00 0.00% 1.41 277.78 100.00% 1.41 277.78 100.00% 0.00 0.00 0.00%
03.05.02.05 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 12.38 15.85 196.22 0.00 0.00 0.00% 12.38 196.22 100.00% 12.38 196.22 100.00% 0.00 0.00 0.00%
03.05.03 OBRAS DE CONCRETO SIMPLE 3,851.27
03.05.03.01 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.33 333.17 1,775.80 0.00 0.00 0.00% 5.33 1,775.80 100.00% 5.33 1,775.80 100.00% 0.00 0.00 0.00%
03.05.03.02 SOBRECIMIENTO 1:8 + 25% P.M m3 1.74 387.67 674.55 0.00 0.00 0.00% 1.74 674.55 100.00% 1.74 674.55 100.00% 0.00 0.00 0.00%
03.05.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 18.08 46.45 839.82 0.00 0.00 0.00% 18.08 839.82 100.00% 18.08 839.82 100.00% 0.00 0.00 0.00%
03.05.03.04 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 14.13 39.71 561.10 0.00 0.00 0.00% 14.13 561.10 100.00% 14.13 561.10 100.00% 0.00 0.00 0.00%
03.05.04 OBRAS DE CONCRETO ARMADO 11,546.69
03.05.04.01 VIGA DE CIMENTACION 2,645.43
03.05.04.01.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 2.00 449.81 899.62 0.00 0.00 0.00% 2.00 899.62 100.00% 2.00 899.62 100.00% 0.00 0.00 0.00%
03.05.04.01.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 20.02 51.41 1,029.23 0.00 0.00 0.00% 20.02 1,029.23 100.00% 20.02 1,029.23 100.00% 0.00 0.00 0.00%
03.05.04.01.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 171.43 4.18 716.58 0.00 0.00 0.00% 171.43 716.58 100.00% 171.43 716.58 100.00% 0.00 0.00 0.00%
03.05.04.02 COLUMNAS 2,896.60
03.05.04.02.01 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 1.67 449.81 751.18 0.00 0.00 0.00% 1.17 525.83 70.00% 1.17 525.83 70.00% 0.50 225.35 30.00%
03.05.04.02.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 15.07 53.08 799.92 0.00 0.00 0.00% 10.55 559.94 70.00% 10.55 559.94 70.00% 4.52 239.98 30.00%
03.05.04.02.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS kg 321.89 4.18 1,345.50 0.00 0.00 0.00% 321.89 1,345.50 100.00% 321.89 1,345.50 100.00% 0.00 0.00 0.00%
03.05.04.03 VIGAS 2,222.94
03.05.04.03.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 1.66 449.81 746.68 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.66 746.68 100.00%
03.05.04.03.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 12.90 62.13 801.48 0.00 0.00 0.00% 9.03 561.03 70.00% 9.03 561.03 70.00% 3.87 240.45 30.00%
03.05.04.03.03 VIGAS ACERO fy=4,200 kg/cm2 kg 161.43 4.18 674.78 0.00 0.00 0.00% 113.00 472.34 70.00% 113.00 472.34 70.00% 48.43 202.44 30.00%
03.05.04.04 ESCALERAS 2,484.68
03.05.04.04.01 ESCALERAS CONCRETO FC=210 KG/CM2 m3 1.89 449.81 850.14 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.89 850.14 100.00%
03.05.04.04.02 ESCALERA ENCOFRADO Y DESENCOFRADO m2 11.19 60.97 682.25 0.00 0.00 0.00% 11.19 682.25 100.00% 11.19 682.25 100.00% 0.00 0.00 0.00%
03.05.04.04.03 ESCALERA ACERO fy=4,200 kg/cm2 kg 227.82 4.18 952.29 0.00 0.00 0.00% 227.82 952.29 100.00% 227.82 952.29 100.00% 0.00 0.00 0.00%
03.05.04.05 LOSA MACIZA 1,297.04
03.05.04.05.01 LOSA MACIZA CONCRETO FC=210 KG/CM2 m3 0.77 449.81 346.35 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.77 346.35 100.00%
03.05.04.05.02 ENCOFRADO Y DESENCOFRADO DE LOSA MACIZA m2 5.15 54.29 279.59 0.00 0.00 0.00% 5.15 279.59 100.00% 5.15 279.59 100.00% 0.00 0.00 0.00%

Página 34
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

03.05.04.05.03 LOSA MACIZA ACERO fy=4,200 kg/cm2 kg 160.55 4.18 671.10 0.00 0.00 0.00% 160.55 671.10 100.00% 160.55 671.10 100.00% 0.00 0.00 0.00%
03.05.05 ALBAÑILERIA 1,616.54
03.05.05.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 29.19 55.38 1,616.54 0.00 0.00 0.00% 14.60 808.27 50.00% 14.60 808.27 50.00% 14.59 808.27 50.00%
03.05.06 REVOQUES 4,512.97
03.05.06.01 TARRAJEO EN EXTERIORES C:A-1:4 m2 58.38 26.62 1,554.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.38 1,554.08 100.00%
03.05.06.02 TARRAJEO DE COLUMNAS C:A-1:4 m2 15.07 28.80 434.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 434.02 100.00%
03.05.06.03 VESTIDURA DE ARISTAS EN COLUMNAS m 64.72 3.45 223.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 64.72 223.28 100.00%
03.05.06.04 TARRAJEO DE VIGAS C:A-1:4 m2 12.90 31.39 404.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 404.93 100.00%
03.05.06.05 VESTIDURA DE ARISTAS EN VIGAS m 51.73 3.45 178.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 51.73 178.47 100.00%
03.05.06.06 BRUÑAS DE 1.0 cm m 82.78 9.32 771.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 82.78 771.51 100.00%
03.05.06.07 REVESTIMIENTO DE GRADAS Y ESCALERA m2 15.39 36.85 567.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.39 567.12 100.00%
03.05.06.08 REVESTIMIENTO DE FONDO DE ESCALERAS CON CEMENTO m2 10.30 36.85 379.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.30 379.56 100.00%
03.05.07 PISOS 732.78
03.05.07.01 PISO CEMENTO PULIDO E=2" m2 14.13 51.86 732.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 732.78 100.00%
03.05.08 CONTRAZOCALOS 262.11
03.05.08.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 17.02 15.40 262.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.02 262.11 100.00%
03.05.09 PINTURAS 1,146.92
03.05.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 58.38 10.57 617.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.38 617.08 100.00%
03.05.09.02 PINTURA EN COLUMNAS m2 15.07 13.19 198.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 198.77 100.00%
03.05.09.03 PINTURA EN VIGAS m2 12.90 13.73 177.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 177.12 100.00%
03.05.09.04 PINTURA EN FONDO DE ESCALERA m2 8.39 11.37 95.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.39 95.39 100.00%
03.05.09.05 PINTURA EN LOSA MACIZA m2 5.15 11.37 58.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.15 58.56 100.00%
04 ADMINISTRACION, SALA DE COMPUTO Y SALON DE USOS MULTIPLES 379,732.21
04.01 ESTRUCTURAS 139,933.65
04.01.01 OBRAS PRELIMINARES 350.61
04.01.01.01 LIMPIEZA DE TERRENO m2 130.34 0.95 123.82 130.34 123.82 100.00% 0.00 0.00 0.00% 130.34 123.82 100.00% 0.00 0.00 0.00%
04.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 130.34 1.74 226.79 130.34 226.79 100.00% 0.00 0.00 0.00% 130.34 226.79 100.00% 0.00 0.00 0.00%
04.01.02 MOVIMIENTO DE TIERRAS 8,554.41
04.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 16.51 41.41 683.68 16.51 683.68 100.00% 0.00 0.00 0.00% 16.51 683.68 100.00% 0.00 0.00 0.00%
04.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 83.01 41.41 3,437.44 83.01 3,437.44 100.00% 0.00 0.00 0.00% 83.01 3,437.44 100.00% 0.00 0.00 0.00%
04.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 105.58 2.48 261.84 105.58 261.84 100.00% 0.00 0.00 0.00% 105.58 261.84 100.00% 0.00 0.00 0.00%
04.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 26.24 27.36 717.93 26.24 717.93 100.00% 0.00 0.00 0.00% 26.24 717.93 100.00% 0.00 0.00 0.00%
04.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 10.56 197.01 2,080.43 10.56 2,080.43 100.00% 0.00 0.00 0.00% 10.56 2,080.43 100.00% 0.00 0.00 0.00%
04.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 86.63 15.85 1,373.09 86.63 1,373.09 100.00% 0.00 0.00 0.00% 86.63 1,373.09 100.00% 0.00 0.00 0.00%
04.01.03 OBRAS DE CONCRETO SIMPLE 12,520.73
04.01.03.01 SOLADO PARA ZAPATAS m2 63.86 35.13 2,243.40 63.86 2,243.40 100.00% 0.00 0.00 0.00% 63.86 2,243.40 100.00% 0.00 0.00 0.00%
04.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 6.35 333.17 2,115.63 6.35 2,115.63 100.00% 0.00 0.00 0.00% 6.35 2,115.63 100.00% 0.00 0.00 0.00%
04.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 5.23 387.67 2,027.51 5.23 2,027.51 100.00% 0.00 0.00 0.00% 5.23 2,027.51 100.00% 0.00 0.00 0.00%
04.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 41.80 46.45 1,941.61 41.80 1,941.61 100.00% 0.00 0.00 0.00% 41.80 1,941.61 100.00% 0.00 0.00 0.00%
04.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 105.58 39.71 4,192.58 105.58 4,192.58 100.00% 0.00 0.00 0.00% 105.58 4,192.58 100.00% 0.00 0.00 0.00%
04.01.04 OBRAS DE CONCRETO ARMADO 118,507.90
04.01.04.01 ZAPATAS 20,173.23
04.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 34.85 449.81 15,675.88 34.85 15,675.88 100.00% 0.00 0.00 0.00% 34.85 15,675.88 100.00% 0.00 0.00 0.00%
04.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 1,075.92 4.18 4,497.35 1,075.92 4,497.35 100.00% 0.00 0.00 0.00% 1,075.92 4,497.35 100.00% 0.00 0.00 0.00%
04.01.04.02 VIGA DE CIMENTACION 11,190.06
04.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 7.98 449.81 3,589.48 7.98 3,589.48 100.00% 0.00 0.00 0.00% 7.98 3,589.48 100.00% 0.00 0.00 0.00%
04.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 63.80 51.41 3,279.96 63.80 3,279.96 100.00% 0.00 0.00 0.00% 63.80 3,279.96 100.00% 0.00 0.00 0.00%
04.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 1,033.64 4.18 4,320.62 1,033.64 4,320.62 100.00% 0.00 0.00 0.00% 1,033.64 4,320.62 100.00% 0.00 0.00 0.00%
04.01.04.03 COLUMNAS Y PLACAS 35,879.80
04.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 21.44 449.81 9,643.93 21.44 9,643.93 100.00% 0.00 0.00 0.00% 21.44 9,643.93 100.00% 0.00 0.00 0.00%
04.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 216.32 53.08 11,482.27 216.32 11,482.27 100.00% 0.00 0.00 0.00% 216.32 11,482.27 100.00% 0.00 0.00 0.00%
04.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 3,529.57 4.18 14,753.60 3,529.57 14,753.60 100.00% 0.00 0.00 0.00% 3,529.57 14,753.60 100.00% 0.00 0.00 0.00%
04.01.04.04 VIGAS 23,771.80
04.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 16.27 449.81 7,318.41 9.00 4,048.29 55.32% 7.27 3,270.12 44.68% 16.27 7,318.41 100.00% 0.00 0.00 0.00%
04.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 132.75 62.13 8,247.76 70.00 4,349.10 52.73% 62.75 3,898.66 47.27% 132.75 8,247.76 100.00% 0.00 0.00 0.00%
04.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 1,963.07 4.18 8,205.63 1,000.00 4,180.00 50.94% 963.07 4,025.63 49.06% 1,963.07 8,205.63 100.00% 0.00 0.00 0.00%
04.01.04.05 LOSAS ALIGERADAS 19,154.31
04.01.04.05.01 CONCRETO LOSA ALIGERADA f'c= 210 kg/cm2 m3 12.45 449.81 5,600.13 12.45 5,600.13 100.00% 0.00 0.00 0.00% 12.45 5,600.13 100.00% 0.00 0.00 0.00%

Página 35
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

04.01.04.05.02 LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO m2 142.31 51.12 7,274.89 142.31 7,274.89 100.00% 0.00 0.00 0.00% 142.31 7,274.89 100.00% 0.00 0.00 0.00%
04.01.04.05.03 LOSAS ALIGERADAS ACERO fy=4,200 kg/cm2 kg 724.91 4.18 3,030.12 724.91 3,030.12 100.00% 0.00 0.00 0.00% 724.91 3,030.12 100.00% 0.00 0.00 0.00%
04.01.04.05.04 LOSA ALIGERADA LADRILLO HUECO 15X30X30 und 1,185.83 2.74 3,249.17 1,185.83 3,249.17 100.00% 0.00 0.00 0.00% 1,185.83 3,249.17 100.00% 0.00 0.00 0.00%
04.01.04.06 COLUMNETAS 7,823.00
04.01.04.06.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 3.44 419.72 1,443.84 0.00 0.00 0.00% 3.44 1,443.84 100.00% 3.44 1,443.84 100.00% 0.00 0.00 0.00%
04.01.04.06.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 77.48 53.08 4,112.64 0.00 0.00 0.00% 77.48 4,112.64 100.00% 77.48 4,112.64 100.00% 0.00 0.00 0.00%
04.01.04.06.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 542.23 4.18 2,266.52 271.12 1,133.26 50.00% 271.12 1,133.26 50.00% 542.23 2,266.52 100.00% 0.00 0.00 0.00%
04.01.04.07 VIGAS COLLARIN 515.70
04.01.04.07.01 CONCRETO VIGAS COLLARIN f'c=175 kg/cm2 m3 0.36 419.72 151.10 0.00 0.00 0.00% 0.36 151.10 100.00% 0.36 151.10 100.00% 0.00 0.00 0.00%
04.01.04.07.02 ENCOFRADO Y DESENCOFRADO EN VIGAS COLLARIN m2 4.79 53.08 254.25 0.00 0.00 0.00% 4.79 254.25 100.00% 4.79 254.25 100.00% 0.00 0.00 0.00%
04.01.04.07.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN VIGAS COLLARIN kg 26.40 4.18 110.35 0.00 0.00 0.00% 26.40 110.35 100.00% 26.40 110.35 100.00% 0.00 0.00 0.00%
04.02 ARQUITECTURA 174,570.71
04.02.01 ALBAÑILERIA 8,721.24
04.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 157.48 55.38 8,721.24 0.00 0.00 0.00% 157.48 8,721.24 100.00% 157.48 8,721.24 100.00% 0.00 0.00 0.00%
04.02.02 REVOQUES 24,798.60
04.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 208.54 26.62 5,551.33 0.00 0.00 0.00% 166.83 4,441.07 80.00% 166.83 4,441.07 80.00% 41.71 1,110.26 20.00%
04.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 161.28 26.62 4,293.27 0.00 0.00 0.00% 129.02 3,434.62 80.00% 129.02 3,434.62 80.00% 32.26 858.65 20.00%
04.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 216.32 28.80 6,230.02 0.00 0.00 0.00% 173.06 4,984.01 80.00% 173.06 4,984.01 80.00% 43.26 1,246.01 20.00%
04.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 191.40 3.45 660.33 0.00 0.00 0.00% 153.12 528.26 80.00% 153.12 528.26 80.00% 38.28 132.07 20.00%
04.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 132.75 31.39 4,167.02 0.00 0.00 0.00% 106.20 3,333.62 80.00% 106.20 3,333.62 80.00% 26.55 833.40 20.00%
04.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 216.98 3.45 748.58 0.00 0.00 0.00% 173.58 598.86 80.00% 173.58 598.86 80.00% 43.40 149.72 20.00%
04.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 138.00 13.60 1,876.80 0.00 0.00 0.00% 110.40 1,501.44 80.00% 110.40 1,501.44 80.00% 27.60 375.36 20.00%
04.02.02.08 BRUÑAS DE 1.0 cm m 136.40 9.32 1,271.25 0.00 0.00 0.00% 109.12 1,017.00 80.00% 109.12 1,017.00 80.00% 27.28 254.25 20.00%
04.02.03 CIELO RASO 6,170.56
04.02.03.01 TARRAJEO DE CIELO RASO - SUPERFICIE CON CEMENTO-A m2 142.31 43.36 6,170.56 0.00 0.00 0.00% 142.31 6,170.56 100.00% 142.31 6,170.56 100.00% 0.00 0.00 0.00%
04.02.04 PISOS Y PAVIMENTOS 23,179.67
04.02.04.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 232.88 35.38 8,239.29 0.00 0.00 0.00% 232.88 8,239.29 100.00% 232.88 8,239.29 100.00% 0.00 0.00 0.00%
04.02.04.02 PISO DE CERAMICO 45 X 45 CM m2 232.88 56.55 13,169.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 232.88 13,169.36 100.00%
04.02.04.03 PISO CEMENTO PULIDO E=2" m2 34.15 51.86 1,771.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 34.15 1,771.02 100.00%
04.02.05 CONTRAZOCALOS 5,606.04
04.02.05.01 CONTRAZOCALO CERAMICO H=0.10 m. m 138.18 19.27 2,662.73 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 138.18 2,662.73 100.00%
04.02.05.02 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 76.00 15.40 1,170.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.00 1,170.40 100.00%
04.02.05.03 ZOCALO DE CERAMICA 20 X 30 CM m2 19.08 92.92 1,772.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19.08 1,772.91 100.00%
04.02.06 CARPINTERIA MADERA 9,607.44
04.02.06.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 16.50 496.22 8,187.63 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.50 8,187.63 100.00%
04.02.06.02 PUERTA CONTRAPLACADA SEGUN DISEÑO m2 4.05 350.57 1,419.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.05 1,419.81 100.00%
04.02.07 CARPINTERIA METALICA 13,514.39
04.02.07.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 70.03 192.98 13,514.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 70.03 13,514.39 100.00%
04.02.08 CERRAJERIA 839.68
04.02.08.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 8.00 77.93 623.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 623.44 100.00%
04.02.08.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 24.00 9.01 216.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.00 216.24 100.00%
04.02.09 VIDRIOS, CRISTALES Y SIMILARES 9,738.32
04.02.09.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 753.74 12.92 9,738.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 753.74 9,738.32 100.00%
04.02.10 PINTURAS 10,210.13
04.02.10.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 369.82 10.57 3,909.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 369.82 3,909.00 100.00%
04.02.10.02 PINTURA EN CONTRAZOCALO m2 15.20 7.96 120.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.20 120.99 100.00%
04.02.10.03 PINTURA EN VIGAS m2 132.75 13.73 1,822.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.75 1,822.66 100.00%
04.02.10.04 PINTURA EN COLUMNAS Y PLACAS m2 216.32 13.19 2,853.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 216.32 2,853.26 100.00%
04.02.10.05 PINTURA EN CIELO RASO m2 142.31 10.57 1,504.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 142.31 1,504.22 100.00%
04.02.11 CUBIERTA METALICA Y CIELO RASO 62,184.64
04.02.11.01 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 201.47 122.00 24,579.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 201.47 24,579.34 100.00%
04.02.11.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 181.50 75.18 13,645.17 0.00 0.00 0.00% 181.50 13,645.17 100.00% 181.50 13,645.17 100.00% 0.00 0.00 0.00%
04.02.11.03 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 205.49 116.60 23,960.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 205.49 23,960.13 100.00%
04.03 INSTALACIONES ELECTRICAS 33,036.01
04.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 41.00 145.99 5,985.59 0.00 0.00 0.00% 20.50 2,992.80 50.00% 20.50 2,992.80 50.00% 20.50 2,992.80 50.00%
04.03.02 SALIDA TOMACORRIENTE pto 54.00 215.17 11,619.18 0.00 0.00 0.00% 27.00 5,809.59 50.00% 27.00 5,809.59 50.00% 27.00 5,809.59 50.00%
04.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 8.00 108.23 865.84 0.00 0.00 0.00% 4.00 432.92 50.00% 4.00 432.92 50.00% 4.00 432.92 50.00%
04.03.04 SALIDA PARA INTERRUPTOR TRIPLE pto 2.00 114.38 228.76 0.00 0.00 0.00% 1.00 114.38 50.00% 1.00 114.38 50.00% 1.00 114.38 50.00%

Página 36
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

04.03.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 38.00 205.71 7,816.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 38.00 7,816.98 100.00%
04.03.06 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 2.00 68.59 137.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 137.18 100.00%
04.03.07 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 285.11 10.81 3,082.04 0.00 0.00 0.00% 171.07 1,849.22 60.00% 171.07 1,849.22 60.00% 114.04 1,232.82 40.00%
04.03.08 ALAMBRE THHN 2.5 mm2 m 344.56 1.67 575.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 344.56 575.42 100.00%
04.03.09 ALAMBRE THHN 4 mm2 m 415.47 2.19 909.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 415.47 909.88 100.00%
04.03.10 TABLERO DE DISTRIBUCION und 1.00 469.91 469.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 469.91 100.00%
04.03.11 SUBTABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
04.03.12 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
04.03.13 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
04.04 INSTALACIONES SANITARIAS 7,294.83
04.04.01 APARATOS Y ACCESORIOS SANITARIOS 1,193.88
04.04.01.01 INODORO TANQUE BAJO pza 2.00 361.79 723.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 723.58 100.00%
04.04.01.02 LAVATORIO DE LOZA BLANCA und 2.00 195.88 391.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 391.76 100.00%
04.04.01.03 CAÑO DE BRONCE - LLAVE DE 1/2" und 2.00 39.27 78.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 78.54 100.00%
04.04.02 SISTEMA DE DESAGUE 2,175.09
04.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 2.00 93.15 186.30 1.00 93.15 50.00% 0.00 0.00 0.00% 1.00 93.15 50.00% 1.00 93.15 50.00%
04.04.02.02 SALIDA DE DESAGUE PVC D=4" pto 2.00 145.54 291.08 2.00 291.08 100.00% 0.00 0.00 0.00% 2.00 291.08 100.00% 0.00 0.00 0.00%
04.04.02.03 SALIDA VENTILACION DE 2" pto 1.00 58.08 58.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 58.08 100.00%
04.04.02.04 REGISTRO DE BRONCE 4" und 1.00 285.99 285.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 285.99 100.00%
04.04.02.05 SUMIDERO DE 2" pza 2.00 77.41 154.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 154.82 100.00%
04.04.02.06 TUBERIA PVC SAL P/DESAGUE D=4" m 10.47 33.95 355.46 9.00 305.55 85.96% 0.00 0.00 0.00% 9.00 305.55 85.96% 1.47 49.91 14.04%
04.04.02.07 YEE PVC SAL 4"X2" und 2.00 61.97 123.94 2.00 123.94 100.00% 0.00 0.00 0.00% 2.00 123.94 100.00% 0.00 0.00 0.00%
04.04.02.08 YEE PVC SAL 2"X2" und 2.00 58.33 116.66 2.00 116.66 100.00% 0.00 0.00 0.00% 2.00 116.66 100.00% 0.00 0.00 0.00%
04.04.02.09 CODO PVC SAL P/DESAGUE D=2" und 2.00 25.81 51.62 2.00 51.62 100.00% 0.00 0.00 0.00% 2.00 51.62 100.00% 0.00 0.00 0.00%
04.04.02.10 EXCAVACION MANUAL PARA TUBERIA m 10.47 14.89 155.90 10.47 155.90 100.00% 0.00 0.00 0.00% 10.47 155.90 100.00% 0.00 0.00 0.00%
04.04.02.11 REFINE NIVELACION Y COMPACTACION DE ZANJA m 10.47 3.86 40.41 10.47 40.41 100.01% 0.00 0.00 0.00% 10.47 40.41 100.01% 0.00 0.00 0.00%
04.04.02.12 CAMA DE APOYO m 10.47 9.44 98.84 10.47 98.84 100.00% 0.00 0.00 0.00% 10.47 98.84 100.00% 0.00 0.00 0.00%
04.04.02.13 RELLENO COMPACTADO DE ZANJAS m 10.47 12.00 125.64 10.47 125.64 100.00% 0.00 0.00 0.00% 10.47 125.64 100.00% 0.00 0.00 0.00%
04.04.02.14 CAJA DE REGISTRO CON REJILLA METALICA und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
04.04.03 SISTEMA DE AGUA FRIA 1,193.38
04.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 4.00 72.84 291.36 3.00 218.52 75.00% 0.00 0.00 0.00% 3.00 218.52 75.00% 1.00 72.84 25.00%
04.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 4.01 17.01 68.21 3.00 51.03 74.81% 0.00 0.00 0.00% 3.00 51.03 74.81% 1.01 17.18 25.19%
04.04.03.03 TUBERIA PVC SAP CLASE 10-3/4" m 7.00 18.07 126.49 4.00 72.28 57.14% 0.00 0.00 0.00% 4.00 72.28 57.14% 3.00 54.21 42.86%
04.04.03.04 CODO PVC 1/2" und 2.00 9.94 19.88 1.00 9.94 50.00% 0.00 0.00 0.00% 1.00 9.94 50.00% 1.00 9.94 50.00%
04.04.03.05 TEE PVC 1/2" und 3.00 11.04 33.12 2.00 22.08 66.67% 0.00 0.00 0.00% 2.00 22.08 66.67% 1.00 11.04 33.33%
04.04.03.06 CODO PVC 3/4" und 1.00 10.78 10.78 1.00 10.78 100.00% 0.00 0.00 0.00% 1.00 10.78 100.00% 0.00 0.00 0.00%
04.04.03.07 EXCAVACION MANUAL PARA TUBERIA m 11.01 14.89 163.94 6.00 89.34 54.50% 0.00 0.00 0.00% 6.00 89.34 54.50% 5.01 74.60 45.50%
04.04.03.08 REFINE NIVELACION Y COMPACTACION DE ZANJA m 11.01 3.86 42.50 6.00 23.16 54.49% 0.00 0.00 0.00% 6.00 23.16 54.49% 5.01 19.34 45.51%
04.04.03.09 CAMA DE APOYO m 11.01 9.44 103.93 6.00 56.64 54.50% 0.00 0.00 0.00% 6.00 56.64 54.50% 5.01 47.29 45.50%
04.04.03.10 RELLENO COMPACTADO DE ZANJAS m 11.01 12.00 132.12 6.00 72.00 54.50% 0.00 0.00 0.00% 6.00 72.00 54.50% 5.01 60.12 45.50%
04.04.03.11 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 1.00 70.70 70.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 70.70 100.00%
04.04.03.12 CAJA PARA VALVULAS und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
04.04.04 SISTEMA DE AGUA PLUVIAL 2,732.48
04.04.04.01 CANALETA PARA AGUA FLUVIAL DE 4" m 32.10 58.77 1,886.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 32.10 1,886.52 100.00%
04.04.04.02 TUBERIA PVC SAL D=4" m 17.00 45.40 771.80 0.00 0.00 0.00% 8.50 385.90 50.00% 8.50 385.90 50.00% 8.50 385.90 50.00%
04.04.04.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 0.00 0.00 0.00% 1.00 37.08 50.00% 1.00 37.08 50.00% 1.00 37.08 50.00%
04.05 CONSTRUCCION DE ESCALERAS 24,897.01
04.05.01 OBRAS PRELIMINARES 48.31
04.05.01.01 LIMPIEZA DE TERRENO m2 17.96 0.95 17.06 17.96 17.06 100.01% 0.00 0.00 0.00% 17.96 17.06 100.00% 0.00 0.00 0.00%
04.05.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 17.96 1.74 31.25 17.96 31.25 100.00% 0.00 0.00 0.00% 17.96 31.25 100.00% 0.00 0.00 0.00%
04.05.02 MOVIMIENTO DE TIERRAS 1,179.42
04.05.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 13.85 41.41 573.53 13.85 573.53 100.00% 0.00 0.00 0.00% 13.85 573.53 100.00% 0.00 0.00 0.00%
04.05.02.02 NIVELACION Y APISONADO MANUAL PARA PISOS m2 14.13 2.48 35.04 7.00 17.36 49.54% 7.13 17.68 50.46% 14.13 35.04 100.00% 0.00 0.00 0.00%
04.05.02.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 3.54 27.36 96.85 1.60 43.78 45.20% 1.94 53.08 54.80% 3.54 96.85 100.00% 0.00 0.00 0.00%
04.05.02.04 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 1.41 197.01 277.78 1.00 197.01 70.92% 0.41 80.77 29.08% 1.41 277.78 100.00% 0.00 0.00 0.00%
04.05.02.05 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 12.38 15.85 196.22 12.38 196.22 100.00% 0.00 0.00 0.00% 12.38 196.22 100.00% 0.00 0.00 0.00%
04.05.03 OBRAS DE CONCRETO SIMPLE 3,851.27
04.05.03.01 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.33 333.17 1,775.80 5.33 1,775.80 100.00% 0.00 0.00 0.00% 5.33 1,775.80 100.00% 0.00 0.00 0.00%

Página 37
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

04.05.03.02 SOBRECIMIENTO 1:8 + 25% P.M m3 1.74 387.67 674.55 1.74 674.55 100.00% 0.00 0.00 0.00% 1.74 674.55 100.00% 0.00 0.00 0.00%
04.05.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 18.08 46.45 839.82 18.08 839.82 100.00% 0.00 0.00 0.00% 18.08 839.82 100.00% 0.00 0.00 0.00%
04.05.03.04 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 14.13 39.71 561.10 0.00 0.00 0.00% 14.13 561.10 100.00% 14.13 561.10 100.00% 0.00 0.00 0.00%
04.05.04 OBRAS DE CONCRETO ARMADO 11,546.69
04.05.04.01 VIGA DE CIMENTACION 2,645.43
04.05.04.01.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 2.00 449.81 899.62 2.00 899.62 100.00% 0.00 0.00 0.00% 2.00 899.62 100.00% 0.00 0.00 0.00%
04.05.04.01.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 20.02 51.41 1,029.23 20.02 1,029.23 100.00% 0.00 0.00 0.00% 20.02 1,029.23 100.00% 0.00 0.00 0.00%
04.05.04.01.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 171.43 4.18 716.58 171.43 716.58 100.00% 0.00 0.00 0.00% 171.43 716.58 100.00% 0.00 0.00 0.00%
04.05.04.02 COLUMNAS 2,896.60
04.05.04.02.01 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 1.67 449.81 751.18 0.00 0.00 0.00% 1.67 751.18 100.00% 1.67 751.18 100.00% 0.00 0.00 0.00%
04.05.04.02.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 15.07 53.08 799.92 0.00 0.00 0.00% 15.07 799.92 100.00% 15.07 799.92 100.00% 0.00 0.00 0.00%
04.05.04.02.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS kg 321.89 4.18 1,345.50 305.80 1,278.24 95.00% 16.09 67.28 5.00% 321.89 1,345.52 100.00% 0.00 -0.02 0.00%
04.05.04.03 VIGAS 2,222.94
04.05.04.03.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 1.66 449.81 746.68 0.00 0.00 0.00% 1.66 746.68 100.00% 1.66 746.68 100.00% 0.00 0.00 0.00%
04.05.04.03.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 12.90 62.13 801.48 0.00 0.00 0.00% 12.90 801.48 100.00% 12.90 801.48 100.00% 0.00 0.00 0.00%
04.05.04.03.03 VIGAS ACERO fy=4,200 kg/cm2 kg 161.43 4.18 674.78 0.00 0.00 0.00% 161.43 674.78 100.00% 161.43 674.78 100.00% 0.00 0.00 0.00%
04.05.04.04 ESCALERAS 2,484.68
04.05.04.04.01 ESCALERAS CONCRETO FC=210 KG/CM2 m3 1.89 449.81 850.14 0.00 0.00 0.00% 1.89 850.14 100.00% 1.89 850.14 100.00% 0.00 0.00 0.00%
04.05.04.04.02 ESCALERA ENCOFRADO Y DESENCOFRADO m2 11.19 60.97 682.25 0.00 0.00 0.00% 11.19 682.25 100.00% 11.19 682.25 100.00% 0.00 0.00 0.00%
04.05.04.04.03 ESCALERA ACERO fy=4,200 kg/cm2 kg 227.82 4.18 952.29 0.00 0.00 0.00% 227.82 952.29 100.00% 227.82 952.29 100.00% 0.00 0.00 0.00%
04.05.04.05 LOSA MACIZA 1,297.04
04.05.04.05.01 LOSA MACIZA CONCRETO FC=210 KG/CM2 m3 0.77 449.81 346.35 0.00 0.00 0.00% 0.77 346.35 100.00% 0.77 346.35 100.00% 0.00 0.00 0.00%
04.05.04.05.02 ENCOFRADO Y DESENCOFRADO DE LOSA MACIZA m2 5.15 54.29 279.59 0.00 0.00 0.00% 5.15 279.59 100.00% 5.15 279.59 100.00% 0.00 0.00 0.00%
04.05.04.05.03 LOSA MACIZA ACERO fy=4,200 kg/cm2 kg 160.55 4.18 671.10 0.00 0.00 0.00% 160.55 671.10 100.00% 160.55 671.10 100.00% 0.00 0.00 0.00%
04.05.05 ALBAÑILERIA 1,616.54
04.05.05.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 29.19 55.38 1,616.54 0.00 0.00 0.00% 20.43 1,131.58 70.00% 20.43 1,131.58 70.00% 8.76 484.96 30.00%
04.05.06 REVOQUES 4,512.97
04.05.06.01 TARRAJEO EN EXTERIORES C:A-1:4 m2 58.38 26.62 1,554.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.38 1,554.08 100.00%
04.05.06.02 TARRAJEO DE COLUMNAS C:A-1:4 m2 15.07 28.80 434.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 434.02 100.00%
04.05.06.03 VESTIDURA DE ARISTAS EN COLUMNAS m 64.72 3.45 223.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 64.72 223.28 100.00%
04.05.06.04 TARRAJEO DE VIGAS C:A-1:4 m2 12.90 31.39 404.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 404.93 100.00%
04.05.06.05 VESTIDURA DE ARISTAS EN VIGAS m 51.73 3.45 178.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 51.73 178.47 100.00%
04.05.06.06 BRUÑAS DE 1.0 cm m 82.78 9.32 771.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 82.78 771.51 100.00%
04.05.06.07 REVESTIMIENTO DE GRADAS Y ESCALERA m2 15.39 36.85 567.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.39 567.12 100.00%
04.05.06.08 REVESTIMIENTO DE FONDO DE ESCALERAS CON CEMENTO m2 10.30 36.85 379.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.30 379.56 100.00%
04.05.07 PISOS 732.78
04.05.07.01 PISO CEMENTO PULIDO E=2" m2 14.13 51.86 732.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 732.78 100.00%
04.05.08 CONTRAZOCALOS 262.11
04.05.08.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 17.02 15.40 262.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.02 262.11 100.00%
04.05.09 PINTURAS 1,146.92
04.05.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 58.38 10.57 617.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.38 617.08 100.00%
04.05.09.02 PINTURA EN COLUMNAS m2 15.07 13.19 198.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 198.77 100.00%
04.05.09.03 PINTURA EN VIGAS m2 12.90 13.73 177.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 177.12 100.00%
04.05.09.04 PINTURA EN FONDO DE ESCALERA m2 8.39 11.37 95.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.39 95.39 100.00%
04.05.09.05 PINTURA EN LOSA MACIZA m2 5.15 11.37 58.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.15 58.56 100.00%
05 CONSTRUCCION DE COMEDOR 144,917.87
05.01 ESTRUCTURAS 52,611.09
05.01.01 OBRAS PRELIMINARES 188.04
05.01.01.01 LIMPIEZA DE TERRENO m2 69.90 0.95 66.41 69.90 66.41 100.00% 0.00 0.00 0.00% 69.90 66.41 100.00% 0.00 0.00 0.00%
05.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 69.90 1.74 121.63 69.90 121.63 100.00% 0.00 0.00 0.00% 69.90 121.63 100.00% 0.00 0.00 0.00%
05.01.02 MOVIMIENTO DE TIERRAS 4,303.76
05.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 18.27 41.41 756.56 18.27 756.56 100.00% 0.00 0.00 0.00% 18.27 756.56 100.00% 0.00 0.00 0.00%
05.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 25.91 41.41 1,072.93 25.91 1,072.93 100.00% 0.00 0.00 0.00% 25.91 1,072.93 100.00% 0.00 0.00 0.00%
05.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 63.56 2.48 157.63 63.56 157.63 100.00% 0.00 0.00 0.00% 63.56 157.63 100.00% 0.00 0.00 0.00%
05.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 29.59 27.36 809.58 29.59 809.58 100.00% 0.00 0.00 0.00% 29.59 809.58 100.00% 0.00 0.00 0.00%
05.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 6.36 197.01 1,252.98 6.36 1,252.98 100.00% 0.00 0.00 0.00% 6.36 1,252.98 100.00% 0.00 0.00 0.00%
05.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 16.03 15.85 254.08 16.03 254.08 100.00% 0.00 0.00 0.00% 16.03 254.08 100.00% 0.00 0.00 0.00%
05.01.03 OBRAS DE CONCRETO SIMPLE 7,695.11

Página 38
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

05.01.03.01 SOLADO PARA ZAPATAS m2 19.93 35.13 700.14 19.93 700.14 100.00% 0.00 0.00 0.00% 19.93 700.14 100.00% 0.00 0.00 0.00%
05.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.29 333.17 1,762.47 5.29 1,762.47 100.00% 0.00 0.00 0.00% 5.29 1,762.47 100.00% 0.00 0.00 0.00%
05.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 2.69 387.67 1,042.83 2.69 1,042.83 100.00% 0.00 0.00 0.00% 2.69 1,042.83 100.00% 0.00 0.00 0.00%
05.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 35.86 46.45 1,665.70 35.86 1,665.70 100.00% 0.00 0.00 0.00% 35.86 1,665.70 100.00% 0.00 0.00 0.00%
05.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 63.56 39.71 2,523.97 63.56 2,523.97 100.00% 0.00 0.00 0.00% 63.56 2,523.97 100.00% 0.00 0.00 0.00%
05.01.04 OBRAS DE CONCRETO ARMADO 40,424.18
05.01.04.01 ZAPATAS 5,545.41
05.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 9.97 449.81 4,484.61 9.97 4,484.61 100.00% 0.00 0.00 0.00% 9.97 4,484.61 100.00% 0.00 0.00 0.00%
05.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 253.78 4.18 1,060.80 253.78 1,060.80 100.00% 0.00 0.00 0.00% 253.78 1,060.80 100.00% 0.00 0.00 0.00%
05.01.04.02 VIGA DE CIMENTACION 8,818.36
05.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 6.35 449.81 2,856.29 6.35 2,856.29 100.00% 0.00 0.00 0.00% 6.35 2,856.29 100.00% 0.00 0.00 0.00%
05.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 50.80 51.41 2,611.63 50.80 2,611.63 100.00% 0.00 0.00 0.00% 50.80 2,611.63 100.00% 0.00 0.00 0.00%
05.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 801.54 4.18 3,350.44 801.54 3,350.44 100.00% 0.00 0.00 0.00% 801.54 3,350.44 100.00% 0.00 0.00 0.00%
05.01.04.03 COLUMNAS Y PLACAS 13,991.50
05.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 8.21 449.81 3,692.94 8.21 3,692.94 100.00% 0.00 0.00 0.00% 8.21 3,692.94 100.00% 0.00 0.00 0.00%
05.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 91.20 53.08 4,840.90 91.20 4,840.90 100.00% 0.00 0.00 0.00% 91.20 4,840.90 100.00% 0.00 0.00 0.00%
05.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 1,305.66 4.18 5,457.66 1,305.66 5,457.66 100.00% 0.00 0.00 0.00% 1,305.66 5,457.66 100.00% 0.00 0.00 0.00%
05.01.04.04 VIGAS 10,012.03
05.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 6.62 449.81 2,977.74 6.62 2,977.74 100.00% 0.00 0.00 0.00% 6.62 2,977.74 100.00% 0.00 0.00 0.00%
05.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 63.32 62.13 3,934.07 63.32 3,934.07 100.00% 0.00 0.00 0.00% 63.32 3,934.07 100.00% 0.00 0.00 0.00%
05.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 741.68 4.18 3,100.22 741.68 3,100.22 100.00% 0.00 0.00 0.00% 741.68 3,100.22 100.00% 0.00 0.00 0.00%
05.01.04.05 COLUMNETAS 2,056.88
05.01.04.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 1.13 419.72 474.28 1.13 474.28 100.00% 0.00 0.00 0.00% 1.13 474.28 100.00% 0.00 0.00 0.00%
05.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 15.12 53.08 802.57 15.12 802.57 100.00% 0.00 0.00 0.00% 15.12 802.57 100.00% 0.00 0.00 0.00%
05.01.04.05.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 186.61 4.18 780.03 186.61 780.03 100.00% 0.00 0.00 0.00% 186.61 780.03 100.00% 0.00 0.00 0.00%
05.02 ARQUITECTURA 78,614.27
05.02.01 ALBAÑILERIA 3,063.62
05.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 55.32 55.38 3,063.62 55.32 3,063.62 100.00% 0.00 0.00 0.00% 55.32 3,063.62 100.00% 0.00 0.00 0.00%
05.02.02 REVOQUES 11,385.22
05.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 84.51 26.62 2,249.66 0.00 0.00 0.00% 84.51 2,249.66 100.00% 84.51 2,249.66 100.00% 0.00 0.00 0.00%
05.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 53.01 26.62 1,411.13 0.00 0.00 0.00% 53.01 1,411.13 100.00% 53.01 1,411.13 100.00% 0.00 0.00 0.00%
05.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 70.68 28.80 2,035.58 0.00 0.00 0.00% 70.68 2,035.58 100.00% 70.68 2,035.58 100.00% 0.00 0.00 0.00%
05.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 92.00 3.45 317.40 0.00 0.00 0.00% 92.00 317.40 100.00% 92.00 317.40 100.00% 0.00 0.00 0.00%
05.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 63.32 31.39 1,987.61 0.00 0.00 0.00% 63.32 1,987.61 100.00% 63.32 1,987.61 100.00% 0.00 0.00 0.00%
05.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 61.60 3.45 212.52 0.00 0.00 0.00% 61.60 212.52 100.00% 61.60 212.52 100.00% 0.00 0.00 0.00%
05.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A-1: m2 97.10 27.89 2,708.12 0.00 0.00 0.00% 97.10 2,708.12 100.00% 97.10 2,708.12 100.00% 0.00 0.00 0.00%
05.02.02.08 BRUÑAS DE 1.0 cm m 49.70 9.32 463.20 0.00 0.00 0.00% 49.70 463.20 100.00% 49.70 463.20 100.00% 0.00 0.00 0.00%
05.02.03 PISOS Y PAVIMENTOS 5,843.07
05.02.03.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 63.56 35.38 2,248.75 63.56 2,248.75 100.00% 0.00 0.00 0.00% 63.56 2,248.75 100.00% 0.00 0.00 0.00%
05.02.03.02 PISO DE CERAMICO 45 X 45 CM m2 63.56 56.55 3,594.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.56 3,594.32 100.00%
05.02.04 CONTRAZOCALOS 1,272.03
05.02.04.01 CONTRAZOCALO CERAMICO H=0.10 m. m 37.80 19.27 728.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.80 728.41 100.00%
05.02.04.02 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 35.30 15.40 543.62 0.00 0.00 0.00% 33.54 516.44 95.00% 33.54 516.44 95.00% 1.77 27.18 5.00%
05.02.05 CARPINTERIA MADERA 6,321.84
05.02.05.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 12.74 496.22 6,321.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.74 6,321.84 100.00%
05.02.06 CARPINTERIA METALICA 5,773.96
05.02.06.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 29.92 192.98 5,773.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 29.92 5,773.96 100.00%
05.02.07 CERRAJERIA 524.80
05.02.07.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 5.00 77.93 389.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 389.65 100.00%
05.02.07.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 15.00 9.01 135.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 135.15 100.00%
05.02.08 VIDRIOS, CRISTALES Y SIMILARES 4,182.85
05.02.08.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 323.75 12.92 4,182.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 323.75 4,182.85 100.00%
05.02.09 PINTURAS 3,306.15
05.02.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 137.02 10.57 1,448.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 137.02 1,448.30 100.00%
05.02.09.02 PINTURA EN CONTRAZOCALO m2 7.06 7.96 56.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.06 56.20 100.00%
05.02.09.03 PINTURA EN VIGAS m2 63.32 13.73 869.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.32 869.38 100.00%
05.02.09.04 PINTURA EN COLUMNAS Y PLACAS m2 70.68 13.19 932.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 70.68 932.27 100.00%
05.02.10 CUBIERTA METALICA Y CIELO RASO 36,940.73

Página 39
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

05.02.10.01 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 113.85 122.00 13,889.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 113.85 13,889.70 100.00%
05.02.10.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 126.50 75.18 9,510.27 0.00 0.00 0.00% 126.50 9,510.27 100.00% 126.50 9,510.27 100.00% 0.00 0.00 0.00%
05.02.10.03 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 116.13 116.60 13,540.76 0.00 0.00 0.00% 104.52 12,186.68 90.00% 104.52 12,186.68 90.00% 11.61 1,354.08 10.00%
05.03 INSTALACIONES ELECTRICAS 8,742.62
05.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 10.00 145.99 1,459.90 0.00 0.00 0.00% 5.00 729.95 50.00% 5.00 729.95 50.00% 5.00 729.95 50.00%
05.03.02 SALIDA TOMACORRIENTE pto 9.00 215.17 1,936.53 0.00 0.00 0.00% 4.50 968.27 50.00% 4.50 968.27 50.00% 4.50 968.27 50.00%
05.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 4.00 108.23 432.92 0.00 0.00 0.00% 2.00 216.46 50.00% 2.00 216.46 50.00% 2.00 216.46 50.00%
05.03.04 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 10.00 205.71 2,057.10 0.00 0.00 0.00% 5.00 1,028.55 50.00% 5.00 1,028.55 50.00% 5.00 1,028.55 50.00%
05.03.05 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 100.00 10.81 1,081.00 40.00 432.40 40.00% 55.00 594.55 55.00% 95.00 1,026.95 95.00% 5.00 54.05 5.00%
05.03.06 ALAMBRE THHN 2.5 mm2 m 125.00 1.67 208.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 125.00 208.75 100.00%
05.03.07 ALAMBRE THHN 4 mm2 m 101.00 2.19 221.19 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 101.00 221.19 100.00%
05.03.08 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
05.03.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
05.03.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
05.04 INSTALACIONES SANITARIAS 4,949.89
05.04.01 APARATOS Y ACCESORIOS SANITARIOS 1,433.36
05.04.01.01 LAVADERO DE ACERO INOXIDABLE DOS POZAS CON ESCU und 2.00 447.76 895.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 895.52 100.00%
05.04.01.02 GRIFO TIPO CUELLO DE CISNE CROMADO 1/2" und 4.00 134.46 537.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 537.84 100.00%
05.04.02 SISTEMA DE DESAGUE 1,071.20
05.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 4.00 93.15 372.60 4.00 372.60 100.00% 0.00 0.00 0.00% 4.00 372.60 100.00% 0.00 0.00 0.00%
05.04.02.02 SUMIDERO DE 2" pza 1.00 77.41 77.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 77.41 100.00%
05.04.02.03 TUBERIA PVC SAL P/DESAGUE D=2" m 6.25 29.80 186.25 6.25 186.25 100.00% 0.00 0.00 0.00% 6.25 186.25 100.00% 0.00 0.00 0.00%
05.04.02.04 YEE PVC SAL P/DESAGUE D=2" und 1.00 27.59 27.59 1.00 27.59 100.00% 0.00 0.00 0.00% 1.00 27.59 100.00% 0.00 0.00 0.00%
05.04.02.05 CODO PVC SAL P/DESAGUE D=2" und 1.00 25.81 25.81 1.00 25.81 100.00% 0.00 0.00 0.00% 1.00 25.81 100.00% 0.00 0.00 0.00%
05.04.02.06 EXCAVACION MANUAL PARA TUBERIA m 6.25 14.89 93.06 6.25 93.06 100.00% 0.00 0.00 0.00% 6.25 93.06 100.00% 0.00 0.00 0.00%
05.04.02.07 REFINE NIVELACION Y COMPACTACION DE ZANJA m 6.25 3.86 24.13 6.25 24.13 100.00% 0.00 0.00 0.00% 6.25 24.13 100.00% 0.00 0.01 0.00%
05.04.02.08 CAMA DE APOYO m 6.25 9.44 59.00 6.25 59.00 100.00% 0.00 0.00 0.00% 6.25 59.00 100.00% 0.00 0.00 0.00%
05.04.02.09 RELLENO COMPACTADO DE ZANJAS m 6.25 12.00 75.00 6.25 75.00 100.00% 0.00 0.00 0.00% 6.25 75.00 100.00% 0.00 0.00 0.00%
05.04.02.10 CAJA DE REGISTRO CON REJILLA METALICA und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
05.04.03 SISTEMA DE AGUA FRIA 729.43
05.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 2.00 72.84 145.68 2.00 145.68 100.00% 0.00 0.00 0.00% 2.00 145.68 100.00% 0.00 0.00 0.00%
05.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 6.15 17.01 104.61 6.15 104.61 100.00% 0.00 0.00 0.00% 6.15 104.61 100.00% 0.00 0.00 0.00%
05.04.03.03 CODO PVC 1/2" und 2.00 9.94 19.88 2.00 19.88 100.00% 0.00 0.00 0.00% 2.00 19.88 100.00% 0.00 0.00 0.00%
05.04.03.04 TEE PVC 1/2" und 1.00 11.04 11.04 1.00 11.04 100.00% 0.00 0.00 0.00% 1.00 11.04 100.00% 0.00 0.00 0.00%
05.04.03.05 EXCAVACION MANUAL PARA TUBERIA m 6.15 14.89 91.57 6.15 91.57 100.00% 0.00 0.00 0.00% 6.15 91.57 100.00% 0.00 0.00 0.00%
05.04.03.06 REFINE NIVELACION Y COMPACTACION DE ZANJA m 6.15 3.86 23.74 6.15 23.74 100.00% 0.00 0.00 0.00% 6.15 23.74 100.00% 0.00 0.00 0.00%
05.04.03.07 CAMA DE APOYO m 6.15 9.44 58.06 6.15 58.06 100.00% 0.00 0.00 0.00% 6.15 58.06 100.00% 0.00 0.00 0.00%
05.04.03.08 RELLENO COMPACTADO DE ZANJAS m 6.15 12.00 73.80 6.15 73.80 100.00% 0.00 0.00 0.00% 6.15 73.80 100.00% 0.00 0.00 0.00%
05.04.03.09 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 1.00 70.70 70.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 70.70 100.00%
05.04.03.10 CAJA PARA VALVULAS und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
05.04.04 SISTEMA DE AGUA PLUVIAL 1,715.90
05.04.04.01 CANALETA PARA AGUA FLUVIAL DE 4" m 23.30 58.77 1,369.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.30 1,369.34 100.00%
05.04.04.02 TUBERIA PVC SAL D=4" m 6.00 45.40 272.40 5.00 227.00 83.33% 0.00 0.00 0.00% 5.00 227.00 83.33% 1.00 45.40 16.67%
05.04.04.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 2.00 74.16 100.00% 0.00 0.00 0.00% 2.00 74.16 100.00% 0.00 0.00 0.00%
06 CONSTRUCCIÓN DE SERVICIOS HIGIENICOS 232,892.65
06.01 ESTRUCTURAS 64,827.86
06.01.01 OBRAS PRELIMINARES 228.00
06.01.01.01 LIMPIEZA DE TERRENO m2 84.76 0.95 80.52 84.76 80.52 100.00% 0.00 0.00 0.00% 84.76 80.52 100.00% 0.00 0.00 0.00%
06.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 84.76 1.74 147.48 84.76 147.48 100.00% 0.00 0.00 0.00% 84.76 147.48 100.00% 0.00 0.00 0.00%
06.01.02 MOVIMIENTO DE TIERRAS 5,317.64
06.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 30.78 41.41 1,274.60 0.00 0.00 0.00% 30.78 1,274.60 100.00% 30.78 1,274.60 100.00% 0.00 0.00 0.00%
06.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 26.68 41.41 1,104.82 0.00 0.00 0.00% 26.68 1,104.82 100.00% 26.68 1,104.82 100.00% 0.00 0.00 0.00%
06.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 76.49 2.48 189.70 0.00 0.00 0.00% 76.49 189.70 100.00% 76.49 189.70 100.00% 0.00 0.00 0.00%
06.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 19.68 27.36 538.44 0.00 0.00 0.00% 19.68 538.44 100.00% 19.68 538.44 100.00% 0.00 0.00 0.00%
06.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 7.65 197.01 1,507.13 0.00 0.00 0.00% 7.65 1,507.13 100.00% 7.65 1,507.13 100.00% 0.00 0.00 0.00%
06.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 44.35 15.85 702.95 0.00 0.00 0.00% 44.35 702.95 100.00% 44.35 702.95 100.00% 0.00 0.00 0.00%
06.01.03 CONCRETO SIMPLE 12,987.55
06.01.03.01 SOLADO PARA ZAPATAS m2 20.52 35.13 720.87 0.00 0.00 0.00% 20.52 720.87 100.00% 20.52 720.87 100.00% 0.00 0.00 0.00%

Página 40
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

06.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 12.74 333.17 4,244.59 0.00 0.00 0.00% 12.74 4,244.59 100.00% 12.74 4,244.59 100.00% 0.00 0.00 0.00%
06.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 4.95 387.67 1,918.97 0.00 0.00 0.00% 4.95 1,918.97 100.00% 4.95 1,918.97 100.00% 0.00 0.00 0.00%
06.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 66.00 46.45 3,065.70 0.00 0.00 0.00% 66.00 3,065.70 100.00% 66.00 3,065.70 100.00% 0.00 0.00 0.00%
06.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 76.49 39.71 3,037.42 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 76.49 3,037.42 100.00%
06.01.04 CONCRETO ARMADO 46,294.67
06.01.04.01 ZAPATAS 5,692.90
06.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 10.26 449.81 4,615.05 0.00 0.00 0.00% 10.26 4,615.05 100.00% 10.26 4,615.05 100.00% 0.00 0.00 0.00%
06.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 257.86 4.18 1,077.85 120.00 501.60 46.54% 137.86 576.25 53.46% 257.86 1,077.85 100.00% 0.00 0.00 0.00%
06.01.04.02 VIGA DE CIMENTACION 8,838.96
06.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 6.23 449.81 2,802.32 0.00 0.00 0.00% 6.23 2,802.32 100.00% 6.23 2,802.32 100.00% 0.00 0.00 0.00%
06.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 49.80 51.41 2,560.22 0.00 0.00 0.00% 49.80 2,560.22 100.00% 49.80 2,560.22 100.00% 0.00 0.00 0.00%
06.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 831.68 4.18 3,476.42 0.00 0.00 0.00% 831.68 3,476.42 100.00% 831.68 3,476.42 100.00% 0.00 0.00 0.00%
06.01.04.03 COLUMNAS Y PLACAS 13,863.72
06.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 8.04 449.81 3,616.47 0.00 0.00 0.00% 8.04 3,616.47 100.00% 8.04 3,616.47 100.00% 0.00 0.00 0.00%
06.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 89.52 53.08 4,751.72 0.00 0.00 0.00% 89.52 4,751.72 100.00% 89.52 4,751.72 100.00% 0.00 0.00 0.00%
06.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 1,314.72 4.18 5,495.53 825.00 3,448.50 62.75% 489.72 2,047.03 37.25% 1,314.72 5,495.53 100.00% 0.00 0.00 0.00%
06.01.04.04 VIGAS 13,462.21
06.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 8.81 449.81 3,962.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.81 3,962.83 100.00%
06.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 84.20 62.13 5,231.35 0.00 0.00 0.00% 50.52 3,138.81 60.00% 50.52 3,138.81 60.00% 33.68 2,092.54 40.00%
06.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 1,021.06 4.18 4,268.03 0.00 0.00 0.00% 612.64 2,560.82 60.00% 612.64 2,560.82 60.00% 408.42 1,707.21 40.00%
06.01.04.05 COLUMNETAS 4,436.88
06.01.04.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 2.52 419.72 1,057.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.52 1,057.69 100.00%
06.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 33.64 53.08 1,785.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 33.64 1,785.61 100.00%
06.01.04.05.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 381.24 4.18 1,593.58 0.00 0.00 0.00% 381.24 1,593.58 100.00% 381.24 1,593.58 100.00% 0.00 0.00 0.00%
06.02 ARQUITECTURA 122,519.44
06.02.01 MUROS Y TABIQUES 6,205.88
06.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 112.06 55.38 6,205.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.06 6,205.88 100.00%
06.02.02 REVOQUES 15,227.74
06.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 137.56 26.62 3,661.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 137.56 3,661.85 100.00%
06.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 86.56 26.62 2,304.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 86.56 2,304.23 100.00%
06.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 89.52 28.80 2,578.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 89.52 2,578.18 100.00%
06.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 169.60 3.45 585.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 169.60 585.12 100.00%
06.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 84.20 31.39 2,643.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84.20 2,643.04 100.00%
06.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 109.88 3.45 379.09 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 109.88 379.09 100.00%
06.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A-1: m2 92.20 27.89 2,571.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 92.20 2,571.46 100.00%
06.02.02.08 BRUÑAS DE 1.0 cm m 54.16 9.32 504.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 54.16 504.77 100.00%
06.02.03 PISOS 7,031.73
06.02.03.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 76.49 35.38 2,706.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.49 2,706.22 100.00%
06.02.03.02 PISO DE CERAMICO 45 X 45 CM m2 76.49 56.55 4,325.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.49 4,325.51 100.00%
06.02.04 ZOCALOS 16,988.89
06.02.04.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 32.00 15.40 492.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 32.00 492.80 100.00%
06.02.04.02 ZOCALO DE CERAMICA 20 X 30 CM m2 177.53 92.92 16,496.09 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 177.53 16,496.09 100.00%
06.02.05 CARPINTERIA DE MADERA 24,845.08
06.02.05.01 PUERTAS 14,785.70
06.02.05.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 17.08 496.22 8,475.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.08 8,475.44 100.00%
06.02.05.01.02 PUERTA CONTRAPLACADA SEGUN DISEÑO m2 18.00 350.57 6,310.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 6,310.26 100.00%
06.02.05.02 TABIQUES DIVISORIOS 10,059.38
06.02.05.02.01 DIVISIONES CONTRAPLACADAS DE MADERA (SSHH) m2 37.44 268.68 10,059.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.44 10,059.38 100.00%
06.02.06 CARPINTERIA METALICA 2,223.13
06.02.06.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 11.52 192.98 2,223.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.52 2,223.13 100.00%
06.02.07 CERRAJERIA 1,475.26
06.02.07.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 8.00 77.93 623.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 623.44 100.00%
06.02.07.02 PICAPORTE DE ALUMINIO 2 PULGADAS pza 18.00 17.29 311.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 311.22 100.00%
06.02.07.03 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 60.00 9.01 540.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 60.00 540.60 100.00%
06.02.08 VIDRIOS, CRISTALES Y SIMILARES 1,602.08
06.02.08.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 124.00 12.92 1,602.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 124.00 1,602.08 100.00%
06.02.09 PINTURAS 4,756.73
06.02.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 224.12 10.57 2,368.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 224.12 2,368.95 100.00%

Página 41
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

06.02.09.02 PINTURA EN CONTRAZOCALO m2 6.40 7.96 50.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.40 50.94 100.00%
06.02.09.03 PINTURA EN VIGAS m2 84.20 13.73 1,156.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84.20 1,156.07 100.00%
06.02.09.04 PINTURA EN COLUMNAS Y PLACAS m2 89.52 13.19 1,180.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 89.52 1,180.77 100.00%
06.02.10 CUBIERTA METALICA Y CIELO RASO 42,162.92
06.02.10.01 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 132.41 122.00 16,154.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.41 16,154.02 100.00%
06.02.10.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 136.50 75.18 10,262.07 0.00 0.00 0.00% 27.30 2,052.41 20.00% 27.30 2,052.41 20.00% 109.20 8,209.66 80.00%
06.02.10.03 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 135.05 116.60 15,746.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 135.05 15,746.83 100.00%
06.03 INSTALACIONES ELECTRICAS 12,831.07
06.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 20.00 145.99 2,919.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 2,919.80 100.00%
06.03.02 SALIDA TOMACORRIENTE A PRUEBA DE AGUA pto 8.00 219.38 1,755.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 1,755.04 100.00%
06.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 10.00 108.23 1,082.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 1,082.30 100.00%
06.03.04 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 20.00 205.71 4,114.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 4,114.20 100.00%
06.03.05 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 99.90 10.81 1,079.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 99.90 1,079.92 100.00%
06.03.06 ALAMBRE THHN 2.5 mm2 m 206.80 1.67 345.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 206.80 345.36 100.00%
06.03.07 ALAMBRE THHN 4 mm2 m 86.40 2.19 189.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 86.40 189.22 100.00%
06.03.08 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
06.03.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
06.03.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
06.04 INSTALACIONES SANITARIAS 32,714.28
06.04.01 APARATOS Y ACCESORIOS SANITARIOS 11,468.50
06.04.01.01 INODORO TANQUE BAJO pza 20.00 361.79 7,235.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 7,235.80 100.00%
06.04.01.02 LAVATORIO DE LOZA BLANCA und 18.00 195.88 3,525.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 3,525.84 100.00%
06.04.01.03 CAÑO DE BRONCE - LLAVE DE 1/2" und 18.00 39.27 706.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 706.86 100.00%
06.04.02 SISTEMA DE DESAGUE 11,848.24
06.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 18.00 93.15 1,676.70 0.00 0.00 0.00% 7.20 670.68 40.00% 7.20 670.68 40.00% 10.80 1,006.02 60.00%
06.04.02.02 SALIDA DE DESAGUE PVC D=4" pto 20.00 145.54 2,910.80 0.00 0.00 0.00% 8.00 1,164.32 40.00% 8.00 1,164.32 40.00% 12.00 1,746.48 60.00%
06.04.02.03 SALIDA VENTILACION DE 2" pto 4.00 58.08 232.32 0.00 0.00 0.00% 1.60 92.93 40.00% 1.60 92.93 40.00% 2.40 139.39 60.00%
06.04.02.04 REGISTRO DE BRONCE 4" und 8.00 285.99 2,287.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 2,287.92 100.00%
06.04.02.05 SUMIDERO DE 2" pza 10.00 77.41 774.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 774.10 100.00%
06.04.02.06 TUBERIA PVC SAL P/DESAGUE D=4" m 35.40 33.95 1,201.83 0.00 0.00 0.00% 35.40 1,201.83 100.00% 35.40 1,201.83 100.00% 0.00 0.00 0.00%
06.04.02.07 YEE PVC SAL 4"X2" und 8.00 61.97 495.76 0.00 0.00 0.00% 8.00 495.76 100.00% 8.00 495.76 100.00% 0.00 0.00 0.00%
06.04.02.08 CODO PVC SAL P/DESAGUE D=2" und 6.00 25.81 154.86 0.00 0.00 0.00% 6.00 154.86 100.00% 6.00 154.86 100.00% 0.00 0.00 0.00%
06.04.02.09 YEE PVC SAL 4" und 4.00 64.85 259.40 0.00 0.00 0.00% 4.00 259.40 100.00% 4.00 259.40 100.00% 0.00 0.00 0.00%
06.04.02.10 CODO PVC SAL P/DESAGUE D=4" und 6.00 28.52 171.12 0.00 0.00 0.00% 6.00 171.12 100.00% 6.00 171.12 100.00% 0.00 0.00 0.00%
06.04.02.11 EXCAVACION MANUAL PARA TUBERIA m 35.40 14.89 527.11 0.00 0.00 0.00% 35.40 527.11 100.00% 35.40 527.11 100.00% 0.00 0.00 0.00%
06.04.02.12 REFINE NIVELACION Y COMPACTACION DE ZANJA m 35.40 3.86 136.64 0.00 0.00 0.00% 35.40 136.64 100.00% 35.40 136.64 100.00% 0.00 0.00 0.00%
06.04.02.13 CAMA DE APOYO m 35.40 9.44 334.18 0.00 0.00 0.00% 35.40 334.18 100.00% 35.40 334.18 100.00% 0.00 0.00 0.00%
06.04.02.14 RELLENO COMPACTADO DE ZANJAS m 35.40 12.00 424.80 0.00 0.00 0.00% 35.40 424.80 100.00% 35.40 424.80 100.00% 0.00 0.00 0.00%
06.04.02.15 CAJA DE REGISTRO CON REJILLA METALICA und 2.00 130.35 260.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 260.70 100.00%
06.04.03 SISTEMA DE AGUA FRIA 7,446.56
06.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 42.00 72.84 3,059.28 0.00 0.00 0.00% 12.60 917.78 30.00% 12.60 917.78 30.00% 29.40 2,141.50 70.00%
06.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 41.40 17.01 704.21 0.00 0.00 0.00% 16.56 281.69 40.00% 16.56 281.69 40.00% 24.84 422.52 60.00%
06.04.03.03 TUBERIA PVC SAP CLASE 10-3/4" m 7.74 18.07 139.86 0.00 0.00 0.00% 3.10 55.94 40.00% 3.10 55.94 40.00% 4.64 83.92 60.00%
06.04.03.04 CODO PVC 1/2" und 10.00 9.94 99.40 0.00 0.00 0.00% 4.00 39.76 40.00% 4.00 39.76 40.00% 6.00 59.64 60.00%
06.04.03.05 TEE PVC 1/2" und 12.00 11.04 132.48 0.00 0.00 0.00% 4.80 52.99 40.00% 4.80 52.99 40.00% 7.20 79.49 60.00%
06.04.03.06 REDUCCION PVC 3/4" - 1/2" und 6.00 10.11 60.66 0.00 0.00 0.00% 2.40 24.26 40.00% 2.40 24.26 40.00% 3.60 36.40 60.00%
06.04.03.07 CODO PVC 3/4" und 2.00 10.78 21.56 0.00 0.00 0.00% 0.80 8.62 40.00% 0.80 8.62 40.00% 1.20 12.94 60.00%
06.04.03.08 TEE PVC 3/4" und 4.00 11.97 47.88 0.00 0.00 0.00% 1.60 19.15 40.00% 1.60 19.15 40.00% 2.40 28.73 60.00%
06.04.03.09 EXCAVACION MANUAL PARA TUBERIA m 49.14 14.89 731.69 0.00 0.00 0.00% 49.14 731.69 100.00% 49.14 731.69 100.00% 0.00 0.00 0.00%
06.04.03.10 REFINE NIVELACION Y COMPACTACION DE ZANJA m 49.14 3.86 189.68 0.00 0.00 0.00% 49.14 189.68 100.00% 49.14 189.68 100.00% 0.00 0.00 0.00%
06.04.03.11 CAMA DE APOYO m 49.14 9.44 463.88 0.00 0.00 0.00% 49.14 463.88 100.00% 49.14 463.88 100.00% 0.00 0.00 0.00%
06.04.03.12 RELLENO COMPACTADO DE ZANJAS m 49.14 12.00 589.68 0.00 0.00 0.00% 49.14 589.68 100.00% 49.14 589.68 100.00% 0.00 0.00 0.00%
06.04.03.13 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 6.00 70.70 424.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 424.20 100.00%
06.04.03.14 CAJA PARA VALVULAS und 6.00 130.35 782.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 782.10 100.00%
06.04.04 SISTEMA DE AGUA PLUVIAL 1,950.98
06.04.04.01 CANALETA PARA AGUA FLUVIAL DE 4" m 27.30 58.77 1,604.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.30 1,604.42 100.00%
06.04.04.02 TUBERIA PVC SAL D=4" m 6.00 45.40 272.40 0.00 0.00 0.00% 3.00 136.20 50.00% 3.00 136.20 50.00% 3.00 136.20 50.00%
06.04.04.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 0.00 0.00 0.00% 1.00 37.08 50.00% 1.00 37.08 50.00% 1.00 37.08 50.00%

Página 42
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

07 TANQUE CISTERNA - TANQUE ELEVADO 49,283.11 0.00%


07.01 ESTRUCTURAS 26,769.78
07.01.01 OBRAS PRELIMINARES 23.54
07.01.01.01 LIMPIEZA DE TERRENO m2 8.75 0.95 8.31 8.75 8.31 100.00% 0.00 0.00 0.00% 8.75 8.31 100.00% 0.00 0.00 0.00%
07.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 8.75 1.74 15.23 8.75 15.23 100.00% 0.00 0.00 0.00% 8.75 15.23 100.00% 0.00 0.00 0.00%
07.01.02 MOVIMIENTO DE TIERRAS 1,079.23
07.01.02.01 EXCAVACION DE ZANJAS PARA CISTERNA m3 17.50 41.41 724.68 17.50 724.68 100.00% 0.00 0.00 0.00% 17.50 724.68 100.00% 0.00 0.01 0.00%
07.01.02.02 NIVELACION Y APISONADO MANUAL PARA PISOS m2 8.75 2.48 21.70 8.75 21.70 100.00% 0.00 0.00 0.00% 8.75 21.70 100.00% 0.00 0.00 0.00%
07.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 21.00 15.85 332.85 21.00 332.85 100.00% 0.00 0.00 0.00% 21.00 332.85 100.00% 0.00 0.00 0.00%
07.01.03 CONCRETO SIMPLE 586.88
07.01.03.01 SOLADO m2 8.75 35.13 307.39 8.75 307.39 100.00% 0.00 0.00 0.00% 8.75 307.39 100.00% 0.00 0.00 0.00%
07.01.03.02 SOBRECIMIENTO 1:8 + 25% P.M m3 0.28 387.67 108.55 0.28 108.55 100.00% 0.00 0.00 0.00% 0.28 108.55 100.00% 0.00 0.00 0.00%
07.01.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 3.68 46.45 170.94 3.68 170.94 100.00% 0.00 0.00 0.00% 3.68 170.94 100.00% 0.00 0.00 0.00%
07.01.04 CONCRETO ARMADO 25,080.13
07.01.04.01 COLUMNAS 7,138.87
07.01.04.01.01 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 3.98 449.81 1,790.24 3.00 1,349.43 75.38% 0.98 440.81 24.62% 3.98 1,790.24 100.00% 0.00 0.00 0.00%
07.01.04.01.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 49.04 53.08 2,603.04 35.00 1,857.80 71.37% 14.04 745.24 28.63% 49.04 2,603.04 100.00% 0.00 0.00 0.00%
07.01.04.01.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS kg 656.84 4.18 2,745.59 656.84 2,745.59 100.00% 0.00 0.00 0.00% 656.84 2,745.59 100.00% 0.00 0.00 0.00%
07.01.04.02 VIGAS 4,141.00
07.01.04.02.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 2.16 449.81 971.59 0.86 388.64 40.00% 0.65 291.48 30.00% 1.51 680.11 70.00% 0.65 291.48 30.00%
07.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 24.48 62.13 1,520.94 9.79 608.38 40.00% 14.69 912.57 60.00% 24.48 1,520.94 100.00% 0.00 0.00 0.00%
07.01.04.02.03 VIGAS ACERO fy=4,200 kg/cm2 kg 394.37 4.18 1,648.47 157.75 659.39 40.00% 236.62 989.08 60.00% 394.37 1,648.47 100.00% 0.00 0.00 0.00%
07.01.04.03 LOSA MACIZA 3,002.53
07.01.04.03.01 LOSA MACIZA CONCRETO FC=210 KG/CM2 m3 2.40 449.81 1,079.54 2.40 1,079.54 100.00% 0.00 0.00 0.00% 2.40 1,079.54 100.00% 0.00 0.00 0.00%
07.01.04.03.02 ENCOFRADO Y DESENCOFRADO DE LOSA MACIZA m2 12.00 54.29 651.48 12.00 651.48 100.00% 0.00 0.00 0.00% 12.00 651.48 100.00% 0.00 0.00 0.00%
07.01.04.03.03 LOSA MACIZA ACERO fy=4,200 kg/cm2 kg 304.19 4.18 1,271.51 304.19 1,271.51 100.00% 0.00 0.00 0.00% 304.19 1,271.51 100.00% 0.00 0.00 0.00%
07.01.04.04 CISTERNA 10,317.18
07.01.04.04.01 CONCRETO EN CISTERNA f'c=210 kg/cm2 m3 11.25 485.41 5,460.86 11.25 5,460.86 100.00% 0.00 0.00 0.00% 11.25 5,460.86 100.00% 0.00 0.00 0.00%
07.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN CISTERNA m2 18.22 51.41 936.69 18.22 936.69 100.00% 0.00 0.00 0.00% 18.22 936.69 100.00% 0.00 0.00 0.00%
07.01.04.04.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN CISTERNA kg 937.71 4.18 3,919.63 937.71 3,919.63 100.00% 0.00 0.00 0.00% 937.71 3,919.63 100.00% 0.00 0.00 0.00%
07.01.04.05 COLUMNETAS 480.55
07.01.04.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 0.28 419.72 117.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.28 117.52 100.00%
07.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 3.68 53.08 195.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.68 195.33 100.00%
07.01.04.05.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 40.12 4.18 167.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 40.12 167.70 100.00%
07.02 ARQUITECTURA 11,218.94
07.02.01 MUROS Y TABIQUES 835.13
07.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 15.08 55.38 835.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.08 835.13 100.00%
07.02.02 REVOQUES 4,950.63
07.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 15.84 26.62 421.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.84 421.66 100.00%
07.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 15.84 26.62 421.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.84 421.66 100.00%
07.02.02.03 TARRAJEO DE COLUMNAS C:A-1:4 m2 49.04 28.80 1,412.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.04 1,412.35 100.00%
07.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS m 152.00 3.45 524.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 152.00 524.40 100.00%
07.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 24.48 31.39 768.43 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.48 768.43 100.00%
07.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 57.60 3.45 198.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 57.60 198.72 100.00%
07.02.02.07 REVESTIMIENTO DE CIELO RASO EN LOSA MACIZA m2 12.00 36.85 442.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 442.20 100.00%
07.02.02.08 TARRAJEO CON IMPERMEABILIZANTE EN TANQUE CISTERN m2 18.22 38.42 700.01 18.22 700.01 100.00% 0.00 0.00 0.00% 18.22 700.01 100.00% 0.00 0.00 0.00%
07.02.02.09 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 4.50 13.60 61.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.50 61.20 100.00%
07.02.03 PISOS 365.09
07.02.03.01 PISO CEMENTO PULIDO E=2" m2 7.04 51.86 365.09 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.04 365.09 100.00%
07.02.04 ZOCALOS 369.60
07.02.04.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 24.00 15.40 369.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.00 369.60 100.00%
07.02.05 CARPINTERIA DE MADERA 803.88
07.02.05.01 PUERTAS 803.88
07.02.05.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 1.62 496.22 803.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.62 803.88 100.00%
07.02.06 CARPINTERIA METALICA 2,119.02
07.02.06.01 VENTANAS 463.15
07.02.06.01.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 2.40 192.98 463.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.40 463.15 100.00%
07.02.06.02 ESCALERAS 1,655.87

Página 43
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

07.02.06.02.01 ESCALERA GATO, TUBO F.G. 1 1/2" Y 1" TQE. ELEVADO m 8.50 135.43 1,151.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.50 1,151.16 100.00%
07.02.06.02.02 ESCALERA GATO ALUMINIO - CISTERNA und 1.00 309.90 309.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 309.90 100.00%
07.02.06.02.03 MARCO Y TAPA DE FIERRO 60x60 und 1.00 194.81 194.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 194.81 100.00%
07.02.07 CERRAJERIA 104.96
07.02.07.01 CERRADURA DE DOS GOLPES TIPO PESADO pza 1.00 77.93 77.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 77.93 100.00%
07.02.07.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 3.00 9.01 27.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 27.03 100.00%
07.02.08 VIDRIOS, CRISTALES Y SIMILARES 333.72
07.02.08.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 25.83 12.92 333.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 25.83 333.72 100.00%
07.02.09 PINTURAS 1,336.91
07.02.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 31.68 10.57 334.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 31.68 334.86 100.00%
07.02.09.02 PINTURA EN CONTRAZOCALO m2 2.40 7.96 19.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.40 19.10 100.00%
07.02.09.03 PINTURA EN VIGAS m2 24.48 13.73 336.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.48 336.11 100.00%
07.02.09.04 PINTURA EN COLUMNAS m2 49.04 13.19 646.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.04 646.84 100.00%
07.03 INSTALACIONES ELECTRICAS 3,766.59
07.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 1.00 145.99 145.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 145.99 100.00%
07.03.02 SALIDA TOMACORRIENTE A PRUEBA DE AGUA pto 1.00 219.38 219.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 219.38 100.00%
07.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 108.23 100.00%
07.03.04 SALIDA PARA ELECTROBOMBA pto 2.00 104.38 208.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 208.76 100.00%
07.03.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 1.00 68.59 68.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 68.59 100.00%
07.03.06 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 9.96 10.81 107.67 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.96 107.67 100.00%
07.03.07 ALAMBRE THHN 2.5 mm2 m 5.08 1.67 8.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.08 8.48 100.00%
07.03.08 ALAMBRE THHN 4 mm2 m 22.26 2.19 48.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.26 48.75 100.00%
07.03.09 EQUIPO DE BOMBEO, INC. 2 ELECTROBOMBAS 1 HP Y TABL und 1.00 1,505.51 1,505.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,505.51 100.00%
07.03.10 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
07.03.11 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
07.03.12 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
07.04 INSTALACIONES SANITARIAS 7,527.80
07.04.01 VALVULAS Y LLAVES 1,332.90
07.04.01.01 VALVULA COMPUERTA DE 3/4" und 1.00 100.51 100.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 100.51 100.00%
07.04.01.02 VALVULA COMPUERTA DE 1 1/2" und 3.00 189.35 568.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 568.05 100.00%
07.04.01.03 VALVULA CHECK DE BRONCE 1 1/2" und 2.00 98.74 197.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 197.48 100.00%
07.04.01.04 VALVULA FLOTADORA 3/4" und 1.00 101.28 101.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 101.28 100.00%
07.04.01.05 VALVULA PIE CON CANASTILLA DE BRONCE 2" und 2.00 182.79 365.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 365.58 100.00%
07.04.02 ALMACENAMIENTO DE AGUA 6,033.58
07.04.02.01 TUBERIA F°G° 3" m 1.00 51.83 51.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 51.83 100.00%
07.04.02.02 TUBERIA F°G° 2" m 15.70 33.60 527.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.70 527.52 100.00%
07.04.02.03 TUBERIA F°G° 1 1/2" m 22.35 27.70 619.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.35 619.10 100.00%
07.04.02.04 CODO F°G° 3" x 90 und 1.00 56.76 56.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 56.76 100.00%
07.04.02.05 CODO F°G° 2" x 90 und 7.00 31.93 223.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.00 223.51 100.00%
07.04.02.06 CODO F°G° 1 1/2" x 90 und 8.00 26.51 212.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 212.08 100.00%
07.04.02.07 TEE F°G° 2" und 1.00 35.32 35.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 35.32 100.00%
07.04.02.08 TEE F°G° 1 1/2" und 2.00 31.08 62.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 62.16 100.00%
07.04.02.09 UNION UNIVERSAL F°G° 2" und 6.00 79.25 475.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 475.50 100.00%
07.04.02.10 UNION UNIVERSAL F°G° 1 1/2" und 8.00 56.84 454.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 454.72 100.00%
07.04.02.11 BRIDA ROMPE AGUA und 3.00 38.94 116.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 116.82 100.00%
07.04.02.12 JUNTA WATER STOP 8" m 11.20 76.42 855.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.20 855.90 100.00%
07.04.02.13 CAJA DE REBOSE C/REJILLA DE FIERRO und 1.00 280.52 280.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 280.52 100.00%
07.04.02.14 TAPA METALICA SANITARIA und 1.00 326.48 326.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 326.48 100.00%
07.04.02.15 ABRAZADERAS DE F°G° und 23.00 10.67 245.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.00 245.41 100.00%
07.04.02.16 TANQUE DE POLIETILENO 2500 LT und 1.00 1,489.95 1,489.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,489.95 100.00%
07.04.03 DESAGUE Y VENTILACION 161.32
07.04.03.01 SALIDA DE DESAGUE PVC D=4" pto 1.00 145.54 145.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 145.54 100.00%
07.04.03.02 SOMBRERO DE VENTILACION 2" und 1.00 15.78 15.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 15.78 100.00%
08 PORTADA Y CASETA DE VIGILANCIA 22,918.40
08.01 ESTRUCTURAS 9,518.16
08.01.01 OBRAS PRELIMINARES 16.90
08.01.01.01 LIMPIEZA DE TERRENO m2 6.28 0.95 5.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.28 5.97 100.00%
08.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 6.28 1.74 10.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.28 10.93 100.00%

Página 44
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

08.01.02 MOVIMIENTO DE TIERRAS 743.23


08.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 2.56 41.41 106.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.56 106.01 100.00%
08.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 7.96 41.41 329.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.96 329.62 100.00%
08.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 3.81 2.48 9.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.81 9.45 100.00%
08.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 0.96 27.36 26.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.96 26.27 100.00%
08.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 0.38 197.01 74.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.38 74.86 100.00%
08.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 12.43 15.85 197.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.43 197.02 100.00%
08.01.03 OBRAS DE CONCRETO SIMPLE 717.03
08.01.03.01 SOLADO PARA ZAPATAS m2 6.62 35.13 232.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.62 232.56 100.00%
08.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 1.00 333.17 333.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 333.17 100.00%
08.01.03.03 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 3.81 39.71 151.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.81 151.30 100.00%
08.01.04 OBRAS DE CONCRETO ARMADO 8,041.00
08.01.04.01 SOBRECIMIENTO ARMADO 1,094.65
08.01.04.01.01 SOBRECIMIENTO 1:8 + 25% P.M m3 0.88 387.67 341.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.88 341.15 100.00%
08.01.04.01.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 11.78 46.45 547.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.78 547.18 100.00%
08.01.04.01.03 SOBRECIMIENTO ACERO fy=4,200 kg/cm2 kg 49.36 4.18 206.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.36 206.32 100.00%
08.01.04.02 ZAPATAS 1,709.32
08.01.04.02.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 3.06 449.81 1,376.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.06 1,376.42 100.00%
08.01.04.02.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 79.64 4.18 332.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 79.64 332.90 100.00%
08.01.04.03 VIGA DE CIMENTACION 611.69
08.01.04.03.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 0.46 449.81 206.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.46 206.91 100.00%
08.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 3.70 51.41 190.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.70 190.22 100.00%
08.01.04.03.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 51.33 4.18 214.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 51.33 214.56 100.00%
08.01.04.04 COLUMNAS 2,534.69
08.01.04.04.01 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 1.21 449.81 544.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.21 544.27 100.00%
08.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 20.01 53.08 1,062.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.01 1,062.13 100.00%
08.01.04.04.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS kg 222.08 4.18 928.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 222.08 928.29 100.00%
08.01.04.05 VIGAS 1,500.04
08.01.04.05.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 0.84 449.81 377.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.84 377.84 100.00%
08.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 9.61 62.13 597.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.61 597.07 100.00%
08.01.04.05.03 VIGAS ACERO fy=4,200 kg/cm2 kg 125.63 4.18 525.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 125.63 525.13 100.00%
08.01.04.06 PARAPETO 276.08
08.01.04.06.01 CONCRETO PARAPETO f'c=210 kg/cm2 m3 0.18 449.81 80.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.18 80.97 100.00%
08.01.04.06.02 ENCOFRADO Y DESENCOFRADO EN PARAPETO m2 2.45 62.13 152.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.45 152.22 100.00%
08.01.04.06.03 PARAPETO ACERO fy=4,200 kg/cm2 kg 10.26 4.18 42.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.26 42.89 100.00%
08.01.04.07 LOSAS ALIGERADAS 314.53
08.01.04.07.01 CONCRETO LOSA ALIGERADA f'c= 210 kg/cm2 m3 0.21 449.81 94.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.21 94.46 100.00%
08.01.04.07.02 LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO m2 2.41 51.12 123.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.41 123.20 100.00%
08.01.04.07.03 LOSAS ALIGERADAS ACERO fy=4,200 kg/cm2 kg 9.41 4.18 39.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.41 39.33 100.00%
08.01.04.07.04 LOSA ALIGERADA LADRILLO HUECO 15X30X30 und 21.00 2.74 57.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 21.00 57.54 100.00%
08.02 ARQUITECTURA 9,207.85
08.02.01 ALBAÑILERIA 798.58
08.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 14.42 55.38 798.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.42 798.58 100.00%
08.02.02 REVOQUES 1,810.03
08.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 14.42 26.62 383.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.42 383.86 100.00%
08.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 14.42 26.62 383.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.42 383.86 100.00%
08.02.02.03 TARRAJEO DE COLUMNAS C:A-1:4 m2 12.72 28.80 366.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.72 366.34 100.00%
08.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS m 37.10 3.45 128.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.10 128.00 100.00%
08.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 9.61 31.39 301.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.61 301.66 100.00%
08.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 23.30 3.45 80.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.30 80.39 100.00%
08.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 12.20 13.60 165.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.20 165.92 100.00%
08.02.03 CIELO RASO 104.50
08.02.03.01 TARRAJEO DE CIELO RASO - SUPERFICIE CON CEMENTO-A m2 2.41 43.36 104.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.41 104.50 100.00%
08.02.04 PISOS Y PAVIMENTOS 197.59
08.02.04.01 PISO CEMENTO PULIDO E=2" m2 3.81 51.86 197.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.81 197.59 100.00%
08.02.05 CONTRAZOCALOS 267.96
08.02.05.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 17.40 15.40 267.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.40 267.96 100.00%
08.02.06 CARPINTERIA MADERA 1,276.07

Página 45
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

08.02.06.01 PUERTA CONTRAPLACADA SEGUN DISEÑO m2 3.64 350.57 1,276.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.64 1,276.07 100.00%
08.02.07 CARPINTERIA METALICA 3,627.00
08.02.07.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 2.44 192.98 470.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.44 470.87 100.00%
08.02.07.02 PUERTA INGRESO PRINCIPAL C/PERFILES 3/16" m2 9.62 328.08 3,156.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.62 3,156.13 100.00%
08.02.08 CERRAJERIA 209.92
08.02.08.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
08.02.08.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 6.00 9.01 54.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 54.06 100.00%
08.02.09 VIDRIOS, CRISTALES Y SIMILARES 339.28
08.02.09.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 26.26 12.92 339.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.26 339.28 100.00%
08.02.10 PINTURAS 576.92
08.02.10.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 23.84 10.57 251.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.84 251.99 100.00%
08.02.10.02 PINTURA EN CONTRAZOCALO m2 3.48 7.96 27.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.48 27.70 100.00%
08.02.10.03 PINTURA EN VIGAS m2 9.61 13.73 131.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.61 131.95 100.00%
08.02.10.04 PINTURA EN COLUMNAS m2 10.60 13.19 139.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.60 139.81 100.00%
08.02.10.05 PINTURA EN CIELO RASO m2 2.41 10.57 25.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.41 25.47 100.00%
08.03 INSTALACIONES ELECTRICAS 1,807.85
08.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 2.00 145.99 291.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 291.98 100.00%
08.03.02 SALIDA TOMACORRIENTE pto 2.00 215.17 430.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 430.34 100.00%
08.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 2.00 108.23 216.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 216.46 100.00%
08.03.04 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 2.00 68.59 137.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 137.18 100.00%
08.03.05 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 12.00 10.81 129.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 129.72 100.00%
08.03.06 ALAMBRE THHN 2.5 mm2 m 36.00 1.67 60.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.00 60.12 100.00%
08.03.07 ALAMBRE THHN 4 mm2 m 24.00 2.19 52.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.00 52.56 100.00%
08.03.08 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
08.03.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
08.04 INSTALACIONES SANITARIAS 2,384.54
08.04.01 APARATOS Y ACCESORIOS SANITARIOS 596.94
08.04.01.01 INODORO TANQUE BAJO pza 1.00 361.79 361.79 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 361.79 100.00%
08.04.01.02 LAVATORIO DE LOZA BLANCA und 1.00 195.88 195.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 195.88 100.00%
08.04.01.03 CAÑO DE BRONCE - LLAVE DE 1/2" und 1.00 39.27 39.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 39.27 100.00%
08.04.02 SISTEMA DE DESAGUE 1,219.68
08.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 2.00 93.15 186.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 186.30 100.00%
08.04.02.02 SALIDA DE DESAGUE PVC D=4" pto 1.00 145.54 145.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 145.54 100.00%
08.04.02.03 SALIDA VENTILACION DE 2" pto 1.00 58.08 58.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 58.08 100.00%
08.04.02.04 REGISTRO DE BRONCE 4" und 1.00 285.99 285.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 285.99 100.00%
08.04.02.05 SUMIDERO DE 2" pza 1.00 77.41 77.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 77.41 100.00%
08.04.02.06 TUBERIA PVC SAL P/DESAGUE D=4" m 3.00 33.95 101.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 101.85 100.00%
08.04.02.07 YEE PVC SAL 4"X2" und 1.00 61.97 61.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 61.97 100.00%
08.04.02.08 CODO PVC SAL P/DESAGUE D=2" und 2.00 25.81 51.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 51.62 100.00%
08.04.02.09 EXCAVACION MANUAL PARA TUBERIA m 3.00 14.89 44.67 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 44.67 100.00%
08.04.02.10 REFINE NIVELACION Y COMPACTACION DE ZANJA m 3.00 3.86 11.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 11.58 100.00%
08.04.02.11 CAMA DE APOYO m 3.00 9.44 28.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 28.32 100.00%
08.04.02.12 RELLENO COMPACTADO DE ZANJAS m 3.00 12.00 36.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 36.00 100.00%
08.04.02.13 CAJA DE REGISTRO CON REJILLA METALICA und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
08.04.03 SISTEMA DE AGUA FRIA 567.92
08.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 2.00 72.84 145.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 145.68 100.00%
08.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 3.50 17.01 59.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 59.54 100.00%
08.04.03.03 CODO PVC 1/2" und 1.00 9.94 9.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 9.94 100.00%
08.04.03.04 TEE PVC 1/2" und 1.00 11.04 11.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 11.04 100.00%
08.04.03.05 EXCAVACION MANUAL PARA TUBERIA m 3.50 14.89 52.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 52.12 100.00%
08.04.03.06 REFINE NIVELACION Y COMPACTACION DE ZANJA m 3.50 3.86 13.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 13.51 100.00%
08.04.03.07 CAMA DE APOYO m 3.50 9.44 33.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 33.04 100.00%
08.04.03.08 RELLENO COMPACTADO DE ZANJAS m 3.50 12.00 42.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 42.00 100.00%
08.04.03.09 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 1.00 70.70 70.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 70.70 100.00%
08.04.03.10 CAJA PARA VALVULAS und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
09 MITIGACIÓN AMBIENTAL 25,000.00
09.01 MITIGACION DEL IMPACTO AMBIENTAL glb 1.00 25,000.00 25,000.00 0.90 22,500.00 90.00% 0.05 1,250.00 5.00% 0.95 23,750.00 95.00% 0.05 1,250.00 5.00%
10 CAPACITACION Y SENSIBILIZACION 19,880.00

Página 46
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

10.01 CAPACITACION PARA MANTENIMIENTO glb 1.00 8,380.00 8,380.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 8,380.00 100.00%
10.02 SENSIBILIZACION DE BENEFICIARIOS glb 1.00 11,500.00 11,500.00 0.30 3,450.00 30.00% 0.00 0.00 0.00% 0.30 3,450.00 30.00% 0.70 8,050.00 70.00%
11 REMODELACION Y CAMBIO DE CUBIERTA SECTOR PRIMARIA AULAS 1 Y 2 65,432.56
11.01 CARPINTERIA MADERA 2,580.34
11.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 5.20 496.22 2,580.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.20 2,580.34 100.00%
11.02 CARPINTERIA METALICA 3,189.96
11.02.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 16.53 192.98 3,189.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.53 3,189.96 100.00%
11.03 CERRAJERIA 209.92
11.03.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
11.03.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 6.00 9.01 54.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 54.06 100.00%
11.04 VIDRIOS, CRISTALES Y SIMILARES 2,298.86
11.04.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 177.93 12.92 2,298.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 177.93 2,298.86 100.00%
11.05 PINTURAS 3,174.34
11.05.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 164.80 10.57 1,741.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 164.80 1,741.94 100.00%
11.05.02 PINTURA EN VIGAS m2 77.60 13.73 1,065.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.60 1,065.45 100.00%
11.05.03 PINTURA EN COLUMNAS m2 27.82 13.19 366.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.82 366.95 100.00%
11.06 CUBIERTA METALICA Y CIELO RASO 44,352.34
11.06.01 DESMONTAJE DE COBERTURA EXISTENTE glb 1.00 607.27 607.27 1.00 607.27 100.00% 0.00 0.00 0.00% 1.00 607.27 100.00% 0.00 0.00 0.00%
11.06.02 RESANE PRODUCTO DE DESMONTAJE glb 1.00 1,582.15 1,582.15 0.50 791.08 50.00% 0.20 316.43 20.00% 0.70 1,107.51 70.00% 0.30 474.65 30.00%
11.06.03 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOSAS m2 132.41 122.00 16,154.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.41 16,154.02 100.00%
11.06.04 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPORT m 136.50 75.18 10,262.07 0.00 0.00 0.00% 136.50 10,262.07 100.00% 136.50 10,262.07 100.00% 0.00 0.00 0.00%
11.06.05 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 135.05 116.60 15,746.83 0.00 0.00 0.00% 121.55 14,172.15 90.00% 121.55 14,172.15 90.00% 13.51 1,574.68 10.00%
11.07 INSTALACIONES ELECTRICAS 8,783.50
11.07.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 15.00 145.99 2,189.85 0.00 0.00 0.00% 7.50 1,094.93 50.00% 7.50 1,094.93 50.00% 7.50 1,094.93 50.00%
11.07.02 SALIDA TOMACORRIENTE pto 5.00 215.17 1,075.85 0.00 0.00 0.00% 2.50 537.93 50.00% 2.50 537.93 50.00% 2.50 537.93 50.00%
11.07.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.50 54.12 50.00% 0.50 54.12 50.00% 0.50 54.12 50.00%
11.07.04 SALIDA PARA INTERRUPTOR DOBLE pto 2.00 112.89 225.78 0.00 0.00 0.00% 1.00 112.89 50.00% 1.00 112.89 50.00% 1.00 112.89 50.00%
11.07.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 15.00 205.71 3,085.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 3,085.65 100.00%
11.07.06 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 73.02 10.81 789.35 0.00 0.00 0.00% 36.51 394.67 50.00% 36.51 394.67 50.00% 36.51 394.68 50.00%
11.07.07 ALAMBRE THHN 2.5 mm2 m 147.44 1.67 246.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 147.44 246.22 100.00%
11.07.08 ALAMBRE THHN 4 mm2 m 71.61 2.19 156.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 71.61 156.83 100.00%
11.07.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
11.07.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
11.08 VARIOS 843.30
11.08.01 CANALETA PARA AGUA FLUVIAL DE 4" m 27.30 30.89 843.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.30 843.30 100.00%
12 REMODELACION Y CAMBIO DE CUBIERTA SECTOR PRIMARIA AULAS 1 Y 2 65,432.56
12.01 CARPINTERIA MADERA 2,580.34
12.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 5.20 496.22 2,580.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.20 2,580.34 100.00%
12.02 CARPINTERIA METALICA 3,189.96
12.02.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 16.53 192.98 3,189.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.53 3,189.96 100.00%
12.03 CERRAJERIA 209.92
12.03.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
12.03.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 6.00 9.01 54.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 54.06 100.00%
12.04 VIDRIOS, CRISTALES Y SIMILARES 2,298.86
12.04.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 177.93 12.92 2,298.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 177.93 2,298.86 100.00%
12.05 PINTURAS 3,174.34
12.05.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 164.80 10.57 1,741.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 164.80 1,741.94 100.00%
12.05.02 PINTURA EN VIGAS m2 77.60 13.73 1,065.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.60 1,065.45 100.00%
12.05.03 PINTURA EN COLUMNAS m2 27.82 13.19 366.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.82 366.95 100.00%
12.06 CUBIERTA METALICA Y CIELO RASO 44,352.34
12.06.01 DESMONTAJE DE COBERTURA EXISTENTE glb 1.00 607.27 607.27 1.00 607.27 100.00% 0.00 0.00 0.00% 1.00 607.27 100.00% 0.00 0.00 0.00%
12.06.02 RESANE PRODUCTO DE DESMONTAJE glb 1.00 1,582.15 1,582.15 0.50 791.08 50.00% 0.20 316.43 20.00% 0.70 1,107.51 70.00% 0.30 474.65 30.00%
12.06.03 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOSAS m2 132.41 122.00 16,154.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.41 16,154.02 100.00%
12.06.04 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPORT m 136.50 75.18 10,262.07 0.00 0.00 0.00% 136.50 10,262.07 100.00% 136.50 10,262.07 100.00% 0.00 0.00 0.00%
12.06.05 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 135.05 116.60 15,746.83 0.00 0.00 0.00% 121.55 14,172.15 90.00% 121.55 14,172.15 90.00% 13.51 1,574.68 10.00%
12.07 INSTALACIONES ELECTRICAS 8,783.50
12.07.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 15.00 145.99 2,189.85 0.00 0.00 0.00% 7.50 1,094.93 50.00% 7.50 1,094.93 50.00% 7.50 1,094.93 50.00%
12.07.02 SALIDA TOMACORRIENTE pto 5.00 215.17 1,075.85 0.00 0.00 0.00% 2.50 537.93 50.00% 2.50 537.93 50.00% 2.50 537.93 50.00%

Página 47
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

12.07.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.50 54.12 50.00% 0.50 54.12 50.00% 0.50 54.12 50.00%
12.07.04 SALIDA PARA INTERRUPTOR DOBLE pto 2.00 112.89 225.78 0.00 0.00 0.00% 1.00 112.89 50.00% 1.00 112.89 50.00% 1.00 112.89 50.00%
12.07.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 15.00 205.71 3,085.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 3,085.65 100.00%
12.07.06 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 73.02 10.81 789.35 0.00 0.00 0.00% 36.51 394.67 50.00% 36.51 394.67 50.00% 36.51 394.68 50.00%
12.07.07 ALAMBRE THHN 2.5 mm2 m 147.44 1.67 246.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 147.44 246.22 100.00%
12.07.08 ALAMBRE THHN 4 mm2 m 71.61 2.19 156.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 71.61 156.83 100.00%
12.07.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
12.07.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
12.08 VARIOS 843.30
12.08.01 CANALETA PARA AGUA FLUVIAL DE 4" m 27.30 30.89 843.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.30 843.30 100.00%
13 REMODELACION Y CAMBIO DE CUBIERTA SECTOR PRIMARIA AULAS 1 Y 2 65,432.56
13.01 CARPINTERIA MADERA 2,580.34
13.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 5.20 496.22 2,580.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.20 2,580.34 100.00%
13.02 CARPINTERIA METALICA 3,189.96
13.02.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 16.53 192.98 3,189.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.53 3,189.96 100.00%
13.03 CERRAJERIA 209.92
13.03.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
13.03.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 6.00 9.01 54.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 54.06 100.00%
13.04 VIDRIOS, CRISTALES Y SIMILARES 2,298.86
13.04.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 177.93 12.92 2,298.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 177.93 2,298.86 100.00%
13.05 PINTURAS 3,174.34
13.05.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 164.80 10.57 1,741.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 164.80 1,741.94 100.00%
13.05.02 PINTURA EN VIGAS m2 77.60 13.73 1,065.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.60 1,065.45 100.00%
13.05.03 PINTURA EN COLUMNAS m2 27.82 13.19 366.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.82 366.95 100.00%
13.06 CUBIERTA METALICA Y CIELO RASO 44,352.34
13.06.01 DESMONTAJE DE COBERTURA EXISTENTE glb 1.00 607.27 607.27 1.00 607.27 100.00% 0.00 0.00 0.00% 1.00 607.27 100.00% 0.00 0.00 0.00%
13.06.02 RESANE PRODUCTO DE DESMONTAJE glb 1.00 1,582.15 1,582.15 0.50 791.08 50.00% 0.20 316.43 20.00% 0.70 1,107.51 70.00% 0.30 474.65 30.00%
13.06.03 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOSAS m2 132.41 122.00 16,154.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.41 16,154.02 100.00%
13.06.04 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPORT m 136.50 75.18 10,262.07 0.00 0.00 0.00% 136.50 10,262.07 100.00% 136.50 10,262.07 100.00% 0.00 0.00 0.00%
13.06.05 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 135.05 116.60 15,746.83 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 135.05 15,746.83 100.00%
13.07 INSTALACIONES ELECTRICAS 8,783.50
13.07.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 15.00 145.99 2,189.85 0.00 0.00 0.00% 7.50 1,094.93 50.00% 7.50 1,094.93 50.00% 7.50 1,094.93 50.00%
13.07.02 SALIDA TOMACORRIENTE pto 5.00 215.17 1,075.85 0.00 0.00 0.00% 2.50 537.93 50.00% 2.50 537.93 50.00% 2.50 537.93 50.00%
13.07.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.50 54.12 50.00% 0.50 54.12 50.00% 0.50 54.12 50.00%
13.07.04 SALIDA PARA INTERRUPTOR DOBLE pto 2.00 112.89 225.78 0.00 0.00 0.00% 1.00 112.89 50.00% 1.00 112.89 50.00% 1.00 112.89 50.00%
13.07.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 15.00 205.71 3,085.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 3,085.65 100.00%
13.07.06 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 73.02 10.81 789.35 0.00 0.00 0.00% 36.51 394.67 50.00% 36.51 394.67 50.00% 36.51 394.68 50.00%
13.07.07 ALAMBRE THHN 2.5 mm2 m 147.44 1.67 246.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 147.44 246.22 100.00%
13.07.08 ALAMBRE THHN 4 mm2 m 71.61 2.19 156.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 71.61 156.83 100.00%
13.07.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
13.07.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
13.08 VARIOS 843.30
13.08.01 CANALETA PARA AGUA FLUVIAL DE 4" m 27.30 30.89 843.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.30 843.30 100.00%
14 CONSTRUCCION DE VEREDAS 124,773.80
14.01 OBRAS PRELIMINARES 2,711.41
14.01.01 LIMPIEZA DE TERRENO m2 1,034.89 0.97 1,003.84 0.00 0.00 0.00% 413.96 401.54 40.00% 413.96 401.54 40.00% 620.93 602.30 60.00%
14.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 1,034.89 1.65 1,707.57 0.00 0.00 0.00% 413.96 683.03 40.00% 413.96 683.03 40.00% 620.93 1,024.54 60.00%
14.02 MOVIMIENTO DE TIERRAS 43,860.65
14.02.01 CORTE DE TERRENO CON MAQUINARIA m3 206.98 5.34 1,105.27 200.00 1,068.00 96.63% 0.00 0.00 0.00% 200.00 1,068.00 96.63% 6.98 37.27 3.37%
14.02.02 BASE PARA VEREDAS DE 0.15 M m2 1,034.89 37.51 38,818.72 0.00 0.00 0.00% 413.96 15,527.49 40.00% 413.96 15,527.49 40.00% 620.93 23,291.23 60.00%
14.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 248.37 15.85 3,936.66 240.00 3,804.00 96.63% 0.00 0.00 0.00% 240.00 3,804.00 96.63% 8.37 132.66 3.37%
14.03 CONCRETO SIMPLE 78,201.74
14.03.01 VEREDA CONC. FC=175 KG/CM2 E=4" m2 1,034.89 43.57 45,090.16 0.00 0.00 0.00% 269.07 11,723.44 26.00% 269.07 11,723.44 26.00% 765.82 33,366.72 74.00%
14.03.02 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 275.97 41.82 11,541.07 0.00 0.00 0.00% 71.75 3,000.68 26.00% 71.75 3,000.68 26.00% 204.22 8,540.39 74.00%
14.03.03 JUNTA DE DILATACION m 1,379.85 13.78 19,014.33 0.00 0.00 0.00% 68.99 950.72 5.00% 68.99 950.72 5.00% 1,310.86 18,063.61 95.00%
14.03.04 CURADO CON AGUA EN VEREDA m2 1,034.89 2.47 2,556.18 0.00 0.00 0.00% 269.07 664.61 26.00% 269.07 664.61 26.00% 765.82 1,891.57 74.00%
15 RAMPAS 8,542.76
15.01 OBRAS PRELIMINARES 104.64

Página 48
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

15.01.01 LIMPIEZA DE TERRENO m2 39.94 0.97 38.74 0.00 0.00 0.00% 15.98 15.50 40.00% 15.98 15.50 40.00% 23.96 23.24 60.00%
15.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 39.94 1.65 65.90 0.00 0.00 0.00% 15.98 26.36 40.00% 15.98 26.36 40.00% 23.96 39.54 60.00%
15.02 MOVIMIENTO DE TIERRAS 255.14
15.02.01 CORTE DE TERRENO CON MAQUINARIA m3 1.25 5.34 6.68 0.00 0.00 0.00% 0.50 2.67 39.97% 0.50 2.67 39.97% 0.75 4.01 60.03%
15.02.02 BASE PARA RAMPAS DE 0.15 M m2 5.99 37.51 224.68 0.00 0.00 0.00% 2.40 89.87 40.00% 2.40 89.87 40.00% 3.59 134.81 60.00%
15.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 1.50 15.85 23.78 0.00 0.00 0.00% 0.60 9.51 39.99% 0.60 9.51 39.99% 0.90 14.27 60.01%
15.03 CONCRETO SIMPLE 3,159.80
15.03.01 CONCRETO FROTACHADO EN LOSA FC=175 KG/CM2 E=4" m3 4.63 439.64 2,035.53 0.00 0.00 0.00% 1.85 814.21 40.00% 1.85 814.21 40.00% 2.78 1,221.32 60.00%
15.03.02 ENCOFRADO Y DESENCOFRADO EN RAMPAS m2 19.17 41.82 801.69 0.00 0.00 0.00% 7.67 320.68 40.00% 7.67 320.68 40.00% 11.50 481.01 60.00%
15.03.03 JUNTA DE DILATACION m 16.25 13.78 223.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.25 223.93 100.00%
15.03.04 CURADO CON AGUA EN RAMPAS m2 39.94 2.47 98.65 0.00 0.00 0.00% 15.98 39.46 40.00% 15.98 39.46 40.00% 23.96 59.19 60.00%
15.04 CARPINTERIA METALICA 5,023.18
15.04.01 BARANDAS METALICAS DE TUBO 2" m 63.90 78.61 5,023.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.90 5,023.18 100.00%
16 GRADAS Y ESCALERAS 15,269.04
16.01 OBRAS PRELIMINARES 60.34
16.01.01 LIMPIEZA DE TERRENO m2 22.43 0.95 21.31 2.90 2.76 12.93% 0.00 0.00 0.00% 2.90 2.76 12.93% 19.53 18.56 87.07%
16.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 22.43 1.74 39.03 2.90 5.05 12.93% 0.00 0.00 0.00% 2.90 5.05 12.93% 19.53 33.98 87.07%
16.02 MOVIMIENTO DE TIERRAS 1,247.62
16.02.01 EXCAVACION DE ZANJAS MANUAL m3 5.25 41.41 217.40 1.00 41.41 19.05% 0.00 0.00 0.00% 1.00 41.41 19.05% 4.25 175.99 80.95%
16.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 13.46 27.36 368.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.46 368.27 100.00%
16.02.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 3.36 197.01 661.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.36 661.95 100.00%
16.03 OBRAS DE CONCRETO 6,737.15
16.03.01 CIMIENTOS 1,749.14
16.03.01.01 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.25 333.17 1,749.14 1.00 333.17 19.05% 0.00 0.00 0.00% 1.00 333.17 19.05% 4.25 1,415.97 80.95%
16.03.02 ESCALERAS 4,988.01
16.03.02.01 ESCALERAS CONCRETO FC=210 KG/CM2 m3 7.98 449.81 3,589.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.98 3,589.48 100.00%
16.03.02.02 ESCALERA ENCOFRADO Y DESENCOFRADO m2 14.70 60.97 896.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.70 896.26 100.00%
16.03.02.03 ESCALERA ACERO fy=4,200 kg/cm2 kg 120.16 4.18 502.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 120.16 502.27 100.00%
16.04 REVOQUES 1,470.32
16.04.01 REVESTIMIENTO DE GRADAS Y ESCALERA m2 39.90 36.85 1,470.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 39.90 1,470.32 100.00%
16.05 CARPINTERIA METALICA 4,997.34
16.05.01 BARANDAS METALICAS DE TUBO 2" m 44.85 78.61 3,525.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 44.85 3,525.66 100.00%
16.05.02 CANTONERA DE ALUMINIO EN PASOS DE ESCALERA m 84.00 17.52 1,471.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84.00 1,471.68 100.00%
16.06 PINTURAS 466.89
16.06.01 PINTURA ANTICORROSIVA EN BARANDAS m 44.85 10.41 466.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 44.85 466.89 100.00%
16.07 VARIOS 289.38
16.07.01 JUNTA DE DILATACION m 21.00 13.78 289.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 21.00 289.38 100.00%
17 PATIO DE HONOR 28,317.10
17.01 OBRAS PRELIMINARES 709.26
17.01.01 LIMPIEZA DE TERRENO m2 270.71 0.97 262.59 0.00 0.00 0.00% 270.71 262.59 100.00% 270.71 262.59 100.00% 0.00 0.00 0.00%
17.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 270.71 1.65 446.67 0.00 0.00 0.00% 270.71 446.67 100.00% 270.71 446.67 100.00% 0.00 0.00 0.00%
17.02 MOVIMIENTO DE TIERRAS 11,012.28
17.02.01 CORTE DE TERRENO CON MAQUINARIA m3 27.07 5.34 144.55 27.07 144.55 100.00% 0.00 0.00 0.00% 27.07 144.55 100.00% 0.00 0.00 0.00%
17.02.02 BASE GRANULAR DE 0.15 M m2 276.00 37.51 10,352.76 0.00 0.00 0.00% 276.00 10,352.76 100.00% 276.00 10,352.76 100.00% 0.00 0.00 0.00%
17.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 32.49 15.85 514.97 32.49 514.97 100.00% 0.00 0.00 0.00% 32.49 514.97 100.00% 0.00 0.00 0.00%
17.03 CONCRETO SIMPLE 16,595.56
17.03.01 CONCRETO SEMIPULIDO EN LOSA FC=175 KG/CM2 m3 27.07 439.64 11,901.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.07 11,901.05 100.00%
17.03.02 ENCOFRADO Y DESENCOFRADO EN PATIO m2 36.80 41.82 1,538.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.80 1,538.98 100.00%
17.03.03 JUNTA DE DILATACION m 180.47 13.78 2,486.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 180.47 2,486.88 100.00%
17.03.04 CURADO CON AGUA m2 270.71 2.47 668.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 270.71 668.65 100.00%
18 LOSAS DEPORTIVA 60,745.47
18.01 OBRAS PRELIMINARES 1,092.02
18.01.01 LIMPIEZA DE TERRENO m2 416.80 0.97 404.30 416.80 404.30 100.00% 0.00 0.00 0.00% 416.80 404.30 100.00% 0.00 0.00 0.00%
18.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 416.80 1.65 687.72 416.80 687.72 100.00% 0.00 0.00 0.00% 416.80 687.72 100.00% 0.00 0.00 0.00%
18.02 MOVIMIENTO DE TIERRAS 17,157.10
18.02.01 CORTE DE TERRENO CON MAQUINARIA m3 62.52 5.34 333.86 62.52 333.86 100.00% 0.00 0.00 0.00% 62.52 333.86 100.00% 0.00 0.00 0.00%
18.02.02 BASE GRANULAR DE 0.15 M m2 416.80 37.51 15,634.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 416.80 15,634.17 100.00%
18.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 75.02 15.85 1,189.07 75.02 1,189.07 100.00% 0.00 0.00 0.00% 75.02 1,189.07 100.00% 0.00 0.00 0.00%

Página 49
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

18.03 CONCRETO SIMPLE 31,783.50


18.03.01 CONCRETO SEMIPULIDO EN LOSA FC=175 KG/CM2 m3 62.52 439.64 27,486.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 62.52 27,486.29 100.00%
18.03.02 ENCOFRADO Y DESENCOFRADO EN LOSA DEPORTIVA m2 83.36 51.55 4,297.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 83.36 4,297.21 100.00%
18.04 PINTURAS 1,837.47
18.04.01 PINTURA DE MARCA EN LOSA DEPORTIVA m 266.30 6.90 1,837.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 266.30 1,837.47 100.00%
18.05 VARIOS 8,875.38
18.05.01 JUNTA DE DILATACION m 277.87 13.78 3,829.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 277.87 3,829.05 100.00%
18.05.02 CURADO CON ADITIVO ANTISOL m2 416.80 3.71 1,546.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 416.80 1,546.33 100.00%
18.05.03 ARCOS DE FUTBOL CON TABLERO DE BASQUET pza 2.00 1,500.00 3,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 3,000.00 100.00%
18.05.04 POSTE DE TUBO PARA VOLEY pza 2.00 250.00 500.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 500.00 100.00%
19 CONSTRUCCION DE MURO DE CONTENCION 647,548.41
19.01 OBRAS PRELIMINARES 2,466.94
19.01.01 LIMPIEZA DE TERRENO m2 941.58 0.97 913.33 800.00 776.00 84.96% 47.45 46.03 5.04% 847.45 822.03 90.00% 94.13 91.30 10.00%
19.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 941.58 1.65 1,553.61 800.00 1,320.00 84.96% 47.45 78.29 5.04% 847.45 1,398.29 90.00% 94.13 155.32 10.00%
19.02 MOVIMIENTO DE TIERRAS 123,308.74
19.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 685.44 41.41 28,384.07 497.39 20,597.00 72.57% 110.72 4,584.83 16.15% 608.11 25,181.84 88.72% 77.33 3,202.23 11.28%
19.02.02 NIVELACION Y APISONADO MANUAL m2 763.37 2.48 1,893.16 469.85 1,165.24 61.55% 216.20 536.17 28.32% 686.05 1,701.40 89.87% 77.32 191.76 10.13%
19.02.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO (AFI m3 381.63 197.01 75,184.93 60.00 11,820.60 15.72% 282.90 55,734.13 74.13% 342.90 67,554.73 89.85% 38.73 7,630.20 10.15%
19.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 637.26 27.36 17,435.43 110.00 3,009.60 17.26% 451.95 12,365.35 70.92% 561.95 15,374.95 88.18% 75.31 2,060.48 11.82%
19.02.05 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 25.94 15.85 411.15 8.00 126.80 30.84% 15.56 246.69 60.00% 23.56 373.49 90.84% 2.38 37.66 9.16%
19.03 OBRAS DE CONCRETO 520,704.96
19.03.01 CONCRETO CICLOPEO MURO DE CONTENCION FC=140 KG/CM m3 1,108.26 372.14 412,427.88 570.86 212,439.84 51.51% 424.44 157,951.10 38.30% 995.30 370,390.94 89.81% 112.96 42,036.94 10.19%
19.03.02 ENCOFRADO Y DESENCOFRADO EN MURO DE CONTENCION m2 2,120.17 51.07 108,277.08 1,091.61 55,748.52 51.49% 813.39 41,539.83 38.36% 1,905.00 97,288.35 89.85% 215.17 10,988.73 10.15%
19.04 VARIOS 1,067.77
19.04.01 TUBERIA PVC SAL D=3" DRENAJE MUROS m 83.16 12.84 1,067.77 30.00 385.20 36.08% 45.33 582.04 54.51% 75.33 967.24 91.00% 7.83 100.53 9.42%
20 CONSTRUCCION DE CERCO 53,726.28
20.01 OBRAS PRELIMINARES 127.62
20.01.01 LIMPIEZA DE TERRENO m2 48.71 0.97 47.25 48.71 47.25 100.00% 0.00 0.00 0.00% 48.71 47.25 100.00% 0.00 0.00 0.00%
20.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 48.71 1.65 80.37 48.71 80.37 100.00% 0.00 0.00 0.00% 48.71 80.37 100.00% 0.00 0.00 0.00%
20.02 MOVIMIENTO DE TIERRAS 49.07
20.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 0.81 41.41 33.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.81 33.54 100.00%
20.02.02 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 0.98 15.85 15.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.98 15.53 100.00%
20.03 OBRAS DE CONCRETO SIMPLE 269.87
20.03.01 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 30 m3 0.81 333.17 269.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.81 269.87 100.00%
20.04 CARPINTERIA METALICA 53,279.72
20.04.01 CERCO MALLA METALICA COCADA DE 2" m 173.51 307.07 53,279.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 173.51 53,279.72 100.00%
21 ADQUISICION E INSTALACION DE POSTES ORNAMENTALES 30,322.97
21.01 ADQUISICION DE POSTES ORNAMENTALES und 26.00 350.00 9,100.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.00 9,100.00 100.00%
21.02 TRAZO NIVELADO Y REPLANTEO m2 13.00 1.67 21.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.00 21.71 100.00%
21.03 CIMENTACION PARA POSTES m3 6.50 333.17 2,165.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.50 2,165.61 100.00%
21.04 EXCAVACION DE ZANJAS PARA CABLE SUBTERRANEO m3 76.53 41.41 3,169.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.53 3,169.11 100.00%
21.05 INSTALACION DE POSTES ORNAMENTALES und 26.00 6.34 164.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.00 164.84 100.00%
21.06 INSTALACION DE FAROLAS ORNAMENTALES und 26.00 209.37 5,443.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.00 5,443.62 100.00%
21.07 INSTALACION DE CABLE SUBTERRANEO NYY 3X10MM2 m 306.12 33.51 10,258.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 306.12 10,258.08 100.00%
22 CORTES GENERALES 145,915.73
22.01 EXCAVACION CON MAQUINARIA m3 5,516.20 6.96 38,392.75 5,516.20 38,392.75 100.00% 0.00 0.00 0.00% 5,516.20 38,392.75 100.00% 0.00 0.00 0.00%
22.02 RELLENO CON MATERIAL PROPIO, COMPACTADO m3 345.58 27.36 9,455.07 69.12 1,891.01 20.00% 259.19 7,091.30 75.00% 328.30 8,982.32 95.00% 17.28 472.75 5.00%
22.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125HP m3 6,187.25 15.85 98,067.91 6,187.25 98,067.91 100.00% 0.00 0.00 0.00% 6,187.25 98,067.91 100.00% 0.00 0.00 0.00%
23 INSTALACION DE SISTEMA DE AGUA Y DESAGUE 28,190.61
23.01 SISTEMA DE DESAGUE 8,307.53
23.01.01 TRAZO NIVELADO Y REPLANTEO m 91.31 1.65 150.66 0.00 0.00 0.00% 36.52 60.26 40.00% 36.52 60.26 40.00% 54.79 90.40 60.00%
23.01.02 EXCAVACION MANUAL PARA TUBERIA m 91.31 14.89 1,359.61 0.00 0.00 0.00% 36.52 543.84 40.00% 36.52 543.84 40.00% 54.79 815.77 60.00%
23.01.03 REFINE NIVELACION Y COMPACTACION DE ZANJA m 91.31 3.86 352.46 0.00 0.00 0.00% 36.52 140.98 40.00% 36.52 140.98 40.00% 54.79 211.48 60.00%
23.01.04 CAMA DE APOYO m 91.31 9.44 861.97 0.00 0.00 0.00% 36.52 344.79 40.00% 36.52 344.79 40.00% 54.79 517.18 60.00%
23.01.05 RELLENO COMPACTADO DE ZANJAS m 91.31 12.00 1,095.72 0.00 0.00 0.00% 36.52 438.29 40.00% 36.52 438.29 40.00% 54.79 657.43 60.00%
23.01.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 3.65 15.85 57.85 0.00 0.00 0.00% 1.46 23.14 40.00% 1.46 23.14 40.00% 2.19 34.71 60.00%
23.01.07 SUMINISTRO E INSTALACION DE TUBERIA 4" DE DESAGUE m 14.03 21.56 302.49 0.00 0.00 0.00% 5.61 120.99 40.00% 5.61 120.99 40.00% 8.42 181.50 60.00%
23.01.08 SUMINISTRO E INSTALACION DE TUBERIA 6" DE DESAGUE m 77.28 41.51 3,207.89 0.00 0.00 0.00% 30.91 1,283.16 40.00% 30.91 1,283.16 40.00% 46.37 1,924.73 60.00%

Página 50
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

23.01.09 CAJAS DE REGISTRO DE DESAGUE 60 x 60 cm und 3.00 192.46 577.38 0.00 0.00 0.00% 1.20 230.95 40.00% 1.20 230.95 40.00% 1.80 346.43 60.00%
23.01.10 PRUEBA HIDRAULICA m 91.31 3.74 341.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.31 341.50 100.00%
23.02 SISTEMA DE AGUA 6,827.77
23.02.01 TRAZO NIVELADO Y REPLANTEO m 112.03 1.65 184.85 0.00 0.00 0.00% 44.81 73.94 40.00% 44.81 73.94 40.00% 67.22 110.91 60.00%
23.02.02 EXCAVACION MANUAL PARA TUBERIA m 112.03 14.89 1,668.13 0.00 0.00 0.00% 44.81 667.25 40.00% 44.81 667.25 40.00% 67.22 1,000.88 60.00%
23.02.03 REFINE NIVELACION Y COMPACTACION DE ZANJA m 112.03 3.86 432.44 0.00 0.00 0.00% 44.81 172.97 40.00% 44.81 172.97 40.00% 67.22 259.47 60.00%
23.02.04 CAMA DE APOYO m 112.03 9.44 1,057.56 0.00 0.00 0.00% 44.81 423.03 40.00% 44.81 423.03 40.00% 67.22 634.53 60.00%
23.02.05 RELLENO COMPACTADO DE ZANJAS m 112.03 12.00 1,344.36 0.00 0.00 0.00% 44.81 537.74 40.00% 44.81 537.74 40.00% 67.22 806.62 60.00%
23.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 5.38 15.85 85.27 0.00 0.00 0.00% 2.15 34.11 40.00% 2.15 34.11 40.00% 3.23 51.16 60.00%
23.02.07 SUMINISTRO E INSTALACION DE TUBERIA 1 1/2" AGUA m 75.48 15.65 1,181.26 0.00 0.00 0.00% 30.19 472.50 40.00% 30.19 472.50 40.00% 45.29 708.76 60.00%
23.02.08 SUMINISTRO E INSTALACION DE TUBERIA 3/4" AGUA m 36.55 10.07 368.06 0.00 0.00 0.00% 14.62 147.22 40.00% 14.62 147.22 40.00% 21.93 220.84 60.00%
23.02.09 SUMINISTRO E INSTALACION DE ACCESORIOS glb 1.00 86.85 86.85 0.00 0.00 0.00% 0.40 34.74 40.00% 0.40 34.74 40.00% 0.60 52.11 60.00%
23.02.10 PRUEBA HIDRAULICA m 112.03 3.74 418.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.03 418.99 100.00%
23.03 SISTEMA DE DRENAJE 13,055.31
23.03.01 TRAZO NIVELADO Y REPLANTEO m 133.95 1.65 221.02 30.00 49.50 22.40% 53.58 88.41 40.00% 83.58 137.91 62.40% 50.37 83.11 37.60%
23.03.02 EXCAVACION MANUAL PARA TUBERIA m 133.95 14.89 1,994.52 30.00 446.70 22.40% 53.58 797.81 40.00% 83.58 1,244.51 62.40% 50.37 750.01 37.60%
23.03.03 REFINE NIVELACION Y COMPACTACION DE ZANJA m 133.95 3.86 517.05 30.00 115.80 22.40% 53.58 206.82 40.00% 83.58 322.62 62.40% 50.37 194.43 37.60%
23.03.04 CAMA DE APOYO m 133.95 9.44 1,264.49 30.00 283.20 22.40% 53.58 505.80 40.00% 83.58 789.00 62.40% 50.37 475.49 37.60%
23.03.05 RELLENO COMPACTADO DE ZANJAS m 133.95 12.00 1,607.40 30.00 360.00 22.40% 53.58 642.96 40.00% 83.58 1,002.96 62.40% 50.37 604.44 37.60%
23.03.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 5.36 15.85 84.96 1.00 15.85 18.66% 2.14 33.98 40.00% 3.14 49.83 58.66% 2.22 35.13 41.35%
23.03.07 SUMINISTRO E INSTALACION DE TUBERIA 4" DE DESAGUE m 55.02 21.56 1,186.23 15.00 323.40 27.26% 22.01 474.49 40.00% 37.01 797.89 67.26% 18.01 388.34 32.74%
23.03.08 SUMINISTRO E INSTALACION DE TUBERIA 6" DE DESAGUE m 41.00 41.51 1,701.91 0.00 0.00 0.00% 16.40 680.76 40.00% 16.40 680.76 40.00% 24.60 1,021.15 60.00%
23.03.09 SUMINISTRO E INSTALACION DE TUBERIA 8" DE DESAGUE m 37.93 51.82 1,965.53 0.00 0.00 0.00% 15.17 786.21 40.00% 15.17 786.21 40.00% 22.76 1,179.32 60.00%
23.03.10 CAJA DE REGISTRO 30X60 CM CON REJILLA METALICA und 11.00 130.35 1,433.85 0.00 0.00 0.00% 4.40 573.54 40.00% 4.40 573.54 40.00% 6.60 860.31 60.00%
23.03.11 CAJAS DE REGISTRO DE DESAGUE 60 x 60 cm und 3.00 192.46 577.38 0.00 0.00 0.00% 1.20 230.95 40.00% 1.20 230.95 40.00% 1.80 346.43 60.00%
23.03.12 PRUEBA HIDRAULICA m 133.95 3.74 500.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 133.95 500.97 100.00%
24 INSTALACIONES ELECTRICAS GENERALES 22,569.52
24.01 TRAZO NIVELADO Y REPLANTEO m 140.00 1.65 231.00 0.00 0.00 0.00% 56.00 92.40 40.00% 56.00 92.40 40.00% 84.00 138.60 60.00%
24.02 EXCAVACION MANUAL PARA TUBERIA m 140.00 14.89 2,084.60 0.00 0.00 0.00% 56.00 833.84 40.00% 56.00 833.84 40.00% 84.00 1,250.76 60.00%
24.03 REFINE NIVELACION Y COMPACTACION DE ZANJA m 140.00 3.86 540.40 0.00 0.00 0.00% 56.00 216.16 40.00% 56.00 216.16 40.00% 84.00 324.24 60.00%
24.04 CAMA DE APOYO m 140.00 9.44 1,321.60 0.00 0.00 0.00% 56.00 528.64 40.00% 56.00 528.64 40.00% 84.00 792.96 60.00%
24.05 RELLENO COMPACTADO DE ZANJAS m 140.00 12.00 1,680.00 0.00 0.00 0.00% 56.00 672.00 40.00% 56.00 672.00 40.00% 84.00 1,008.00 60.00%
24.06 CABLE NYY 6MM2 m 657.93 7.04 4,631.83 0.00 0.00 0.00% 263.17 1,852.73 40.00% 263.17 1,852.73 40.00% 394.76 2,779.10 60.00%
24.07 CABLE NYY 10MM2 m 347.04 10.57 3,668.21 0.00 0.00 0.00% 138.82 1,467.29 40.00% 138.82 1,467.29 40.00% 208.22 2,200.92 60.00%
24.08 CABLE NYY 16MM2 m 255.00 15.18 3,870.90 0.00 0.00 0.00% 102.00 1,548.36 40.00% 102.00 1,548.36 40.00% 153.00 2,322.54 60.00%
24.09 SUMINISTRO E INSTALACION DE TUBERIA ELECTRICA 1" m 419.99 8.79 3,691.71 50.00 439.50 11.91% 265.00 2,329.35 63.10% 315.00 2,768.85 75.01% 104.99 922.86 25.00%
24.10 TABLERO DE DISTRIBUCION und 1.00 543.57 543.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 543.57 100.00%
24.11 CAJA DE REGISTRO 40X40 CM und 3.00 101.90 305.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 305.70 100.00%
25 AREAS VERDES 42,366.85
25.01 OBRAS PRELIMINARES 1,990.31
25.01.01 LIMPIEZA DE TERRENO m2 759.66 0.97 736.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 736.87 100.00%
25.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 759.66 1.65 1,253.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 1,253.44 100.00%
25.02 MOVIMIENTO DE TIERRAS 15,402.98
25.02.01 CORTE MANUAL DE TERRENO m3 75.97 24.14 1,833.92 50.00 1,207.00 65.82% 0.00 0.00 0.00% 50.00 1,207.00 65.82% 25.97 626.92 34.18%
25.02.02 PREPARACION DE TIERRA DE CHACRA m2 759.66 6.53 4,960.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 4,960.58 100.00%
25.02.03 EXT. Y NIV. DE TIERRA DE CHACRA PARA SEMBRADO DE GRA m2 759.66 9.43 7,163.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 7,163.59 100.00%
25.02.04 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 91.16 15.85 1,444.89 70.00 1,109.50 76.79% 0.00 0.00 0.00% 70.00 1,109.50 76.79% 21.16 335.39 23.21%
25.03 SEMBRADO DE GRASS 17,973.56
25.03.01 SEMBRADO DE GRASS m2 759.66 23.66 17,973.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 17,973.56 100.00%
25.04 VARIOS 7,000.00
25.04.01 ADQUISICION E INSTALACION DE JUEGO RECREATIVOS und 2.00 3,500.00 7,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 7,000.00 100.00%
26 ADQUISICION DE EQUIPAMIENTO 63,256.00
26.01 ADQUISICION DE EQUIPAMIENTO COCINA glb 1.00 4,980.00 4,980.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,980.00 100.00%
26.02 ADQUISICION DE EQUIPAMIENTO SALA DE COMPUTO glb 1.00 58,276.00 58,276.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 58,276.00 100.00%
27 ADQUISICION DE MOBILIARIO ESCOLAR 64,465.00
27.01 ADQUISICION DE MOBILIARIO ESCOLAR INICIAL glb 4.00 240.00 960.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 960.00 100.00%
27.02 ADQUISICION DE MOBILIARIO ESCOLAR PRIMARIO glb 74.00 270.00 19,980.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 74.00 19,980.00 100.00%
27.03 ADQUISICION DE MOBILIARIO ESCOLAR SECUNDARIO glb 53.00 270.00 14,310.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 53.00 14,310.00 100.00%

Página 51
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

27.04 ADQUISICION DE MOBILIARIO PARA AULAS glb 1.00 10,380.00 10,380.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 10,380.00 100.00%
27.05 ADQUISICION DE MOBILIARIO PARA SALA DE USOS MULTIPLES glb 1.00 3,615.00 3,615.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,615.00 100.00%
27.06 ADQUISICION DE MOBILIARIO PARA SALA DE COMPUTO glb 1.00 6,865.00 6,865.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 6,865.00 100.00%
27.07 ADQUISICION DE MOBILIARIO PARA DIRECCION glb 1.00 715.00 715.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 715.00 100.00%
27.08 ADQUISICION DE MOBILIARIO PARA SECRETARIA Y ESPERA glb 1.00 970.00 970.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 970.00 100.00%
27.09 ADQUISICION DE MOBILIARIO PARA SALA DE PROFESORES glb 1.00 2,295.00 2,295.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,295.00 100.00%
27.10 ADQUISICION DE MOBILIARIO PARA CENTRO DE RECURSOS E glb 1.00 2,855.00 2,855.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,855.00 100.00%
27.11 ADQUISICION DE MOBILIARIO PARA COCINA glb 1.00 1,520.00 1,520.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,520.00 100.00%
28 FLETE TERRESTRE 4,000.00
28.01 TRANSPORTE DE EQUIPAMIENTO Y MOBILIARIO A OBRA glb 1.00 4,000.00 4,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,000.00 100.00%

COSTO DIRECTO 3,124,772.22 967,363.83 766,184.62 1,733,548.45 1,391,223.77


GASTOS GENERALES 9.21% 287,655.74 89,052.17 70,532.31 159,584.48 128,071.26
UTILIDAD 9.00% 281,229.50 87,062.75 68,956.62 156,019.36 125,210.14
SUB - TOTAL 3,693,657.46 1,143,478.75 905,673.54 2,049,152.29 1,644,505.17
FACTOR DE RELACION 1.00000 3,693,657.46 1,143,478.75 905,673.54 2,049,152.29 1,644,505.17

MONTO BRUTO VALORIZADO 3,693,657.46 1,143,478.75 905,673.54 2,049,152.29 1,644,505.17


SUB-TOTAL 3,693,657.46 1,143,478.75 905,673.54 2,049,152.29 1,644,505.17

IGV (18%) 18% 205,826.17 163,021.24 368,847.41 296,010.93

VALOR REFERENCIAL 4,358,515.80 1,349,304.92 30.96% 1,068,694.78 24.52% 2,417,999.70 55.48% 1,940,516.10 44.52%
EXPEDIENTE TECNICO 110,263.07

EJECUCION DE OBRA+EXPEDIENTE TECNICO 4,468,778.87


SUPERVISION 110,263.07

TOTAL DE INVERSION 4,579,041.94

Página 52
VALORIZACION DE OBRA N° 04
CORRESPONDIENTE AL MES DE NOVIEMBRE DEL 2012

Obra : MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA INSTITUCIÓN EDUCATIVA CARLOS FERMIN FITZCARRALD N° DE CONTRATO : 036-2012/GOREMAD/GGR.

Form. : 01 PRESUPUESTO GENERAL CONTRATISTA: CONSORCIO CARLOS F. FITZCARRALD FECHA : 03/07/2012


Cliente : GOBIERNO REGIONAL DE MADRE DE DIOS INSPECTOR: ING. EDUARDO DONAIRES CASTILLO MONTO DE CONTRATO : S/. 23,508,980.65 (INC. IGV.)
Ubicac. : TAMBOPATA - TAMBOPATA - MADRE DE DIOS. FACTOR DE RELACION: 1.0000000000 PLAZO EJECUCION : 548 DIAS CALENDARIOS

(XV) VOL 3b - PABELLON DE 11 AULAS + SSHH (B2b) - INST. SANITARIAS


Item Descripcion und Metrado P.unit Parcial ACUMULADO ANTERIOR MES ACTUAL ACUMULADO ACTUAL SALDO POR VALORIZAR
01 RED DE AGUA FRIA 12,413.98 METRADO S/. % METRADOS/. % METRADOS/. % METRADOS/. %
01.01 TRABAJOS PRELIMINARES 144.33
01.01.01 TRAZO Y REPLANTEO DE REDES DE AGUA m 51.00 2.83 144.33 51.00 144.33 100.00% - 0.00% 51.00 144.33 100.00% - - 0.00%
01.02 MOVIMIENTO DE TIERRAS 3,231.13
01.02.01 EXCAVACION DE ZANJAS MANUAL TN, HASTA 1.0 M m 51.00 28.58 1,457.58 51.00 1,457.58 100.00% - 0.00% 51.00 1,457.58 100.00% - - 0.00%
01.02.02 REFINE Y NIVELACION ZANJA T.N. m 51.00 1.61 82.11 51.00 82.11 100.00% - 0.00% 51.00 82.11 100.00% - - 0.00%
01.02.03 PREPARACION DE CAMA DE APOYO CON MATERIAL PROPIO ZARANDEADO E=10CM. m 51.00 1.98 100.98 51.00 100.98 100.00% - 0.00% 51.00 100.98 100.00% - - 0.00%
01.02.04 RELLENO Y COMPACTADO DE ZANJA, HASTA 1.00 m CON MATERIAL PROPIO m 51.00 29.51 1,505.01 51.00 1,505.01 100.00% - 0.00% 51.00 1,505.01 100.00% -
01.02.05 ACARREO MATERIAL EXCEDENTE HASTA UN DISTANCIA PROMEDIO DE 30 M m3 2.99 28.58 85.45 2.99 85.45 100.00% - 0.00% 2.99 85.45 100.00% -
01.03 TUBERIAS Y ACCESORIOS 278.49
01.03.01 TUBERIA PVC SAP DE 3/4" C- 10 C/R m 1.00 5.15 5.15 1.00 5.15 100.00% - 0.00% 1.00 5.15 100.00% - - 0.00%
01.03.02 TUBERIA PVC SAP DE 1/2" C- 10 C/R m 50.00 4.10 205.00 50.00 205.00 100.00% - 0.00% 50.00 205.00 100.00% - - 0.00%
01.03.03 PRUEBA HIDRAULICA Y DESINFECCIÓN m 51.00 1.34 68.34 51.00 68.34 100.00% - 0.00% 51.00 68.34 100.00% - - 0.00%
01.04 VALVULAS 769.18
01.04.01 VALVULA COMPUERTA DE 3/4". und 2.00 91.92 183.84 0.00 0.00 0.00% - 0.00% - - 0.00% 2.00 183.84 100.00%
01.04.02 VALVULA COMPUERTA DE 1/2" und 7.00 83.62 585.34 0.00 0.00 0.00% - 0.00% - - 0.00% 7.00 585.34 100.00%
01.05 SALIDAS DE AGUA FRIA 1,657.22
01.05.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" - INODORO pto 6.00 69.27 415.62 6.00 415.62 100.00% - 0.00% 6.00 415.62 100.00% - - 0.00%
01.05.02 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" - LAVATORIO pto 2.00 69.27 138.54 2.00 138.54 100.00% - 0.00% 2.00 138.54 100.00% - - 0.00%
01.05.03 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" - LAVADERO CORRIDO pto 1.00 68.28 68.28 1.00 68.28 100.00% - 0.00% 1.00 68.28 100.00% - - 0.00%
01.05.04 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" - URINARIO CORRIDO pto 7.00 107.78 754.46 7.00 754.46 100.00% - 0.00% 7.00 754.46 100.00% - - 0.00%
01.05.05 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" - DUCHA pto 4.00 70.08 280.32 4.00 280.32 100.00% - 0.00% 4.00 280.32 100.00% - - 0.00%
01.06 ACCESORIOS VARIOS 964.28
01.06.01 REDUCCION PVC SAP 3/4" - 1/2" und 2.00 21.77 43.54 2.00 43.54 100.00% - 0.00% 2.00 43.54 100.00% - - 0.00%
01.06.02 CODO PVC U.R. SAP 1/2"X90° und 19.00 14.65 278.35 19.00 278.35 100.00% - 0.00% 19.00 278.35 100.00% - - 0.00%
01.06.03 TEE PVC U.R. SAP 1/2" und 19.00 33.81 642.39 19.00 642.39 100.00% - 0.00% 19.00 642.39 100.00% - - 0.00%
01.07 SUMINISTRO E INSTALACION DE APARATOS Y ACCESORIOS SANITARIOS 5,369.35
01.07.01 INODORO TIPO SIFON JET COLOR BLANCO (SIN COLOCACION) pza 7.00 215.05 1,505.35 0.00 0.00 0.00% - 0.00% - - 0.00% 7.00 1,505.35 100.00%
01.07.02 LAVATORIO DE LOSA TIPO OVALIN BLANCO COMERCIAL (SIN COLOCACION pza 6.00 287.00 1,722.00 0.00 0.00 0.00% - 0.00% - - 0.00% 6.00 1,722.00 100.00%
01.07.03 DUCHA CROMADA 1 LLAVE INCLUYE ACCESORIOS und 4.00 175.12 700.48 0.00 0.00 0.00% - 0.00% - - 0.00% 4.00 700.48 100.00%
01.07.04 CAÑO DE BRONCE STANDARD - LLAVE DE 1/2" und 2.00 55.00 110.00 0.00 0.00 0.00% - 0.00% - - 0.00% 2.00 110.00 100.00%
01.01.07.07 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS pza 19.00 70.08 1,331.52 0.00 0.00 0.00% - 0.00% - - 0.00% 19.00 1,331.52 100.00%
.02 RED DE DESAGUES 12,938.85
02.01 TRABAJOS PRELIMINARES 183.95
02.01.01 TRAZO Y REPLANTEO RED DE DESAGUES m 65.00 2.83 183.95 65.00 183.95 100.00% - 0.00% 65.00 183.95 100.00% - - 0.00%
02.02 MOVIMIENTO DE TIERRAS 5,511.69
02.02.01 EXCAVACION DE ZANJAS MANUAL TN Ø 2"-6", HASTA 1.0 M m 65.00 50.02 3,251.30 65.00 3,251.30 100.00% - 0.00% 65.00 3,251.30 100.00% - - 0.00%
02.02.02 REFINE Y NIVELACION ZANJA TERR.NORMAL"C" PARA TUB. 2"-6" m 65.00 1.61 104.65 65.00 104.65 100.00% - 0.00% 65.00 104.65 100.00% - - 0.00%
02.02.03 PREPARACION DE CAMA DE APOYO CON MATERIAL PROPIO ZARANDEADO E=10CM. m 65.00 1.98 128.70 65.00 128.70 100.00% - 0.00% 65.00 128.70 100.00% - - 0.00%
02.02.04 RELLENO Y COMPACTADO DE ZANJA, HASTA 1.00 m CON MATERIAL PROPIO m 65.00 29.51 1,918.15 65.00 1,918.15 100.00% - 0.00% 65.00 1,918.15 100.00% - - 0.00%
02.02.05 ACARREO MATERIAL EXCEDENTE HASTA UN DISTANCIA PROMEDIO DE 30 M m3 3.81 28.58 108.89 3.81 108.89 100.00% - 0.00% 3.81 108.89 100.00% - 0.00 0.00%
02.03 TUBERIAS 876.11
02.03.01 TUBERIA PVC SAL Ø2" m 42.50 10.69 454.33 42.50 454.33 100.00% - 0.00% 42.50 454.33 100.00% - 0.00 0.00%
02.03.02 TUBERIA PVC SAL Ø 4" m 22.50 9.79 220.28 22.50 220.28 100.00% - 0.00% 22.50 220.28 100.00% - 0.01 0.00%
02.03.03 PRUEBA HIDRAULICA+ESCORRENTIA DE TUB. P/DESAGUE m 130.00 1.55 201.50 130.00 201.50 100.00% - 0.00% 130.00 201.50 100.00% - - 0.00%
02.04 SALIDAS DE DESAGUES 5,302.76
02.04.01 SALIDA DE DESAGUE TUB PVC 4" - INODORO pto 7.00 92.73 649.11 7.00 649.11 100.00% - 0.00% 7.00 649.11 100.00% - - 0.00%
02.04.02 SALIDA DE DESAGUE TUB PVC 2" - LAVATORIO pto 6.00 58.85 353.10 6.00 353.10 100.00% - 0.00% 6.00 353.10 100.00% - - 0.00%
02.04.03 SALIDA DE DESAGUE TUB PVC 2" - LAVADERO CORRIDO pto 2.00 58.85 117.70 2.00 117.70 100.00% - 0.00% 2.00 117.70 100.00% - - 0.00%
02.04.04 SALIDA DE DESAGUE TUB PVC 2" - URINARIO CORRIDO pto 1.00 66.85 66.85 1.00 66.85 100.00% - 0.00% 1.00 66.85 100.00% - - 0.00%
02.04.05 SALIDA DE DESAGUE TUB PVC 2" - DUCHA pto 4.00 81.85 327.40 4.00 327.40 100.00% - 0.00% 4.00 327.40 100.00% - - 0.00%
02.04.06 SALIDA DE TUBERIA DE VENTILACION PVC 2 pto 25.92 115.63 2,997.13 25.92 2,997.13 100.00% - 0.00% 25.92 2,997.13 100.00% - 0.00 0.00%
02.04.07 REGISTRO DE BRONCE ROSCADO DE 2" pto 2.00 53.43 106.86 2.00 106.86 100.00% - 0.00% 2.00 106.86 100.00% - - 0.00%
02.04.08 REGISTRO DE BRONCE ROSCADO DE 4" pto 5.00 65.93 329.65 5.00 329.65 100.00% - 0.00% 5.00 329.65 100.00% - - 0.00%
02.04.09 SUMIDERO DE BRONCE 2" pto 6.00 59.16 354.96 6.00 354.96 100.00% - 0.00% 6.00 354.96 100.00% - - 0.00%
02.05 ACCESORIOS VARIOS 1,064.34
02.05.01 YEE DE 4"X4" pza 7.00 26.55 185.85 7.00 185.85 100.00% - 0.00% 7.00 185.85 100.00% - - 0.00%
02.05.02 YEE DE 4"X2" pza 5.00 28.05 140.25 5.00 140.25 100.00% - 0.00% 5.00 140.25 100.00% - - 0.00%
02.05.03 YEE DE 2"X2" pza 17.00 14.22 241.74 17.00 241.74 100.00% - 0.00% 17.00 241.74 100.00% - - 0.00%
02.05.04 TEE PVC DE 4"* 4" und 2.00 38.72 77.44 2.00 77.44 100.00% - 0.00% 2.00 77.44 100.00% - - 0.00%
02.05.05 TEE PVC DE 4"* 2" und 9.00 35.72 321.48 9.00 321.48 100.00% - 0.00% 9.00 321.48 100.00% - - 0.00%
02.05.06 CODO DE 90° "X2" pza 5.00 12.94 64.70 5.00 64.70 100.00% - 0.00% 5.00 64.70 100.00% - - 0.00%
02.05.07 CODO DE 45°X2" pza 2.00 16.44 32.88 2.00 32.88 100.00% - 0.00% 2.00 32.88 100.00% - - 0.00%
03 SISTEMA DE AGUA DE LLUVIA 7,666.85
03.01 TUBERIA PVC-SAP 4" DE DESCARGA PLUVIAL DE TECHO m 90.14 72.70 6,553.18 45.00 3,271.50 49.92% - 0.00% 45.00 3,271.50 49.92% 45.14 3,281.68 50.08%
03.02 CODO PVC-SAP 4" * 90 und 16.00 24.22 387.52 16.00 387.52 100.00% - 0.00% 16.00 387.52 100.00% - - 0.00%
03.03 CAJA DE REGISTRO DE DESAGUE 12" X 24" C/TAPA DE CONCRETO pza 3.00 242.05 726.15 0.00 0.00 0.00% - - - - 0.00% 3.00 726.15 100.00%

33,019.68 22,873.31 69.27% 0.00 0.00% 22,873.31 69.27% 10,146.37 30.73%


VALORIZACION DE OBRA N° 04
CORRESPONDIENTE AL MES DE NOVIEMBRE DEL 2012

Obra : MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA INSTITUCIÓN EDUCATIVA CARLOS FERMIN FITZCARRALD N° DE CONTRATO : 036-2012/GOREMAD/GGR.

Form. : 01 PRESUPUESTO GENERAL CONTRATISTA: CONSORCIO CARLOS F. FITZCARRALD FECHA : 03/07/2012


Cliente : GOBIERNO REGIONAL DE MADRE DE DIOS INSPECTOR: ING. EDUARDO DONAIRES CASTILLO MONTO DE CONTRATO : S/. 23,508,980.65 (INC. IGV.)
Ubicac. : TAMBOPATA - TAMBOPATA - MADRE DE DIOS. FACTOR DE RELACION: 1.0000000000 PLAZO EJECUCION : 548 DIAS CALENDARIOS

(XXI) VOL 5 - TALLER 1: ELECTRICIDAD Y ELECTRONICA (B4) - ESTRUCTURAS


Item Descripcion und Metrado P.unit Parcial ACUMULADO ANTERIOR MES ACTUAL ACUMULADO ACTUAL SALDO POR VALORIZAR
01 TRABAJOS PRELIMINARES 2,486.76 METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. %
01.01 LIMPIEZA DE TERRENO MANUAL m2 469.20 1.12 525.50 469.20 525.50 100.00% 0.00 0.00% 469.20 525.50 100.00% 0.00 0.00 0.00%
01.02 TRAZO, NIVELES Y REPLANTEO INICIAL m2 469.20 4.18 1,961.26 469.20 1,961.26 100.00% 0.00 0.00% 469.20 1,961.26 100.00% 0.00 0.00 0.00%
02 MOVIMIENTO DE TIERRAS 23,133.44
02.01 NIVELACION DE TERRENO M2 469.20 2.49 1,168.31 469.20 1,168.31 100.00% 0.00 0.00% 469.20 1,168.31 100.00% 0.00 0.00 0.00%
02.02 EXCAVACION DE ZANJAS m3 277.39 33.34 9,248.18 277.39 9,248.18 100.00% 0.00 0.00% 277.39 9,248.18 100.00% 0.00 0.00 0.00%
02.03 RELLENO Y COMPACTADO C/ MATERIAL PROPIO m3 190.67 23.67 4,513.16 190.67 4,513.16 100.00% 0.00 0.00% 190.67 4,513.16 100.00% 0.00 0.00 0.00%
02.04 ACARREO INTERNO MAT. PROCED. DE EXCAVACIONES Dprom= m3 169.94 17.00 2,888.98 335.09 5,696.45 197.18% 0.00 0.00% 335.09 5,696.45 197.18% -165.15 -2,807.47 -97.18%
02.05 ELIMINACION MATERIAL EXCEDENTE CON MAQUINARIA VOLQUm3 169.94 7.91 1,344.23 169.94 1,344.23 100.00% 0.00 0.00% 169.94 1,344.23 100.00% 0.00 0.00 0.00%
02.06 NIVELACION Y APISONADO PARA FALSO PISO O PISO m2 399.39 2.18 870.67 399.39 870.67 100.00% 0.00 0.00% 399.39 870.67 100.00% 0.00 0.00 0.00%
02.07 RELLENO CON AFIRMADO DE e=4" (100% COMPACTACION) m3 40.58 76.39 3,099.91 40.58 3,099.91 100.00% 0.00 0.00% 40.58 3,099.91 100.00% 0.00 0.00 0.00%
03 OBRAS DE CONCRETO SIMPLE 36,975.49
03.01 CONCRETO EN FALSA ZAPATAS F'C= 100 KG/CM2 m3 56.97 257.89 14,691.99 62.89 16,218.70 110.39% 0.00 0.00% 62.89 16,218.70 110.39% -5.92 -1,526.71 -10.39%
03.02 CIMIENTO CORRIDO F'c=140 kg/cm2 m3 9.38 303.68 2,848.52 9.38 2,848.52 100.00% 0.00 0.00% 9.38 2,848.52 100.00% 0.00 0.00 0.00%
03.03 CONCRETO EN SOBRECIMIENTO F'C= 175 KG/CM2 m3 3.75 411.54 1,543.28 3.75 1,543.28 100.00% 0.00 0.00% 3.75 1,543.28 100.00% 0.00 0.00 0.00%
03.04 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO m2 50.13 31.61 1,584.61 50.13 1,584.61 100.00% 0.00 0.00% 50.13 1,584.61 100.00% 0.00 0.00 0.00%
03.05 FALSO PISO e= 4" (10CM.) 1:6 C:H m2 399.39 40.83 16,307.09 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 399.39 16,307.09 100.00%
04 OBRAS DE CONCRETO ARMADO 192,998.43
04.01 ZAPATAS 31,979.03
04.01.01 ZAPATAS, CONCRETO F'C=210 KG/CM2 m3 65.80 349.47 22,995.13 65.80 22,995.13 100.00% 0.00 0.00% 65.80 22,995.13 100.00% 0.00 0.00 0.00%
04.01.02 ZAPATAS, ACERO FY=4200KG/CM2 kg 1,860.02 4.83 8,983.90 1,860.02 8,983.90 100.00% 0.00 0.00% 1,860.02 8,983.90 100.00% 0.00 0.00 0.00%
04.02 VIGAS DE CIMENTACION 9,867.55
04.02.01 VIGAS DE CIMENTACION, CONCRETO F'C= 210 KG/CM2 m3 6.27 371.88 2,331.69 6.27 2,331.69 100.00% 0.00 0.00% 6.27 2,331.69 100.00% 0.00 0.00 0.00%
04.02.02 VIGAS DE CIMENTACION, ENCOFRADO Y DESENCOFRADO m2 60.25 54.27 3,269.77 60.25 3,269.77 100.00% 0.00 0.00% 60.25 3,269.77 100.00% 0.00 0.00 0.00%
04.02.03 VIGAS DE CIMENTACION, ACERO FY=4200 KG/CM2. kg 828.88 4.96 4,111.24 828.88 4,111.24 100.00% 0.00 0.00% 828.88 4,111.24 100.00% 0.00 0.00 0.00%
04.02.04 VIGAS DE CIMENTACION, BASE CON POLIESTILENO EXPANDIDO m2 9.19 16.85 154.85 9.19 154.85 100.00% 0.00 0.00% 9.19 154.85 100.00% 0.00 0.00 0.00%
04.03 SOBRECIMIENTOS REFORZADOS 13,392.28
04.03.01 CONCRETO EN SOBRECIMIENTO REFORZADO F'C= 175 KG/CM2 m3 12.14 401.74 4,877.12 12.14 4,877.12 100.00% 0.00 0.00% 12.14 4,877.12 100.00% 0.00 0.00 0.00%
04.03.02 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO m2 140.24 31.61 4,432.99 140.24 4,432.99 100.00% 0.00 0.00% 140.24 4,432.99 100.00% 0.00 0.00 0.00%
04.03.03 SOBRECIMIENTO, ACERO FY=4200 KG/CM2 . kg 779.04 5.24 4,082.17 779.04 4,082.17 100.00% 0.00 0.00% 779.04 4,082.17 100.00% 0.00 0.00 0.00%
04.04 COLUMNETAS 8,449.56
04.04.01 COLUMNETAS, CONCRETO F'C= 175 KG/CM2 m3 4.33 381.44 1,651.64 4.33 1,651.64 100.00% 0.00 0.00% 4.33 1,651.64 100.00% 0.00 0.00 0.00%
04.04.02 COLUMNETAS, ENCOFRADO Y DESENCOFRADO m2 42.41 46.14 1,956.80 42.41 1,956.80 100.00% 0.00 0.00% 42.41 1,956.80 100.00% 0.00 0.00 0.00%
04.04.03 COLUMNETAS, ACERO FY=4200 KG/CM2 kg 1,014.91 4.77 4,841.12 1,014.91 4,841.12 100.00% 0.00 0.00% 1,014.91 4,841.12 100.00% 0.00 0.00 0.00%
04.05 COLUMNAS 73,972.99
04.05.01 COLUMNAS, CONCRETO F'C= 210 KG/CM2 m3 41.00 507.07 20,789.87 41.00 20,789.87 100.00% 0.00 0.00% 41.00 20,789.87 100.00% 0.00 0.00 0.00%
04.05.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 416.20 56.37 23,461.19 416.20 23,461.19 100.00% 0.00 0.00% 416.20 23,461.19 100.00% 0.00 0.00 0.00%
04.05.03 COLUMNAS, ACERO FY=4200 KG/CM2 kg 5,885.53 5.05 29,721.93 5,885.53 29,721.93 100.00% 0.00 0.00% 5,885.53 29,721.93 100.00% 0.00 0.00 0.00%
04.06 VIGUETAS DE ARRIOSTRE 2,797.25
04.06.01 VIGUETAS DE ARRIOSTRE, CONCRETO F'c= 175KG/CM2 m3 1.80 329.85 593.73 1.80 593.73 100.00% 0.00 0.00% 1.80 593.73 100.00% 0.00 0.00 0.00%
04.06.02 VIGUETAS DE ARRIOSTRE, ENCOFRADO Y DESENCOFRADO m2 23.47 53.91 1,265.27 23.47 1,265.27 100.00% 0.00 0.00% 23.47 1,265.27 100.00% 0.00 0.00 0.00%
04.06.03 VIGA DE ARRIOSTRE, ACERO FY=4200 KG/CM2. kg 191.48 4.90 938.25 191.48 938.25 100.00% 0.00 0.00% 191.48 938.25 100.00% 0.00 0.00 0.00%
04.07 VIGAS 23,310.95
04.07.01 VIGAS, CONCRETO F'C=210 KG/CM2 m3 15.91 391.02 6,221.13 15.91 6,221.13 100.00% 0.00 0.00% 15.91 6,221.13 100.00% 0.00 0.00 0.00%
04.07.02 VIGAS, ENCOFRADO Y DESENCOFRADO m2 155.95 59.62 9,297.74 155.95 9,297.74 100.00% 0.00 0.00% 155.95 9,297.74 100.00% 0.00 0.00 0.00%
04.07.03 VIGAS, ACERO FY=4200 KG/CM2. kg 1,590.22 4.90 7,792.08 1,590.22 7,792.08 100.00% 0.00 0.00% 1,590.22 7,792.08 100.00% 0.00 0.00 0.00%
04.08 CANALETA DE CONCRETO EN TECHO 29,228.82
04.08.01 CANALETA DE CONCRETO EN TECHO, CONCRETO F'C=210 KG/CMm3 12.60 412.67 5,199.64 12.60 5,199.64 100.00% 0.00 0.00% 12.60 5,199.64 100.00% 0.00 0.00 0.00%
04.08.02 CANALETA DE CONCRETO EN TECHO, ENCOFRADO Y DESENCOFRm2 267.12 72.87 19,465.03 267.12 19,465.03 100.00% 0.00 0.00% 267.12 19,465.03 100.00% 0.00 0.00 0.00%
04.08.03 CANALETA DE CONCRETO EN TECHO, ACERO FY=4200 KG/CM2. kg 931.46 4.90 4,564.15 931.46 4,564.15 100.00% 0.00 0.00% 931.46 4,564.15 100.00% 0.00 0.00 0.00%
05 ESTRUCTURA METALICA Y COBERTURA 110,699.04
05.01 TIJERAL METÁLICO DE SECCIÓN RECTANGULAR T-1 und 5.00 6,670.74 33,353.70 5.00 33,353.70 100.00% 0.00 0.00% 5.00 33,353.70 100.00% 0.00 0.00 0.00%
05.02 SOPORTES METALICOS PARA CERCHAS und 10.00 580.16 5,801.60 10.00 5,801.60 100.00% 0.00 0.00% 10.00 5,801.60 100.00% 0.00 0.00 0.00%
05.03 VIGUETA TIPO "Z" DE 100mm x 51mm x 4.5mmm x 6.00m m 453.60 80.82 36,659.95 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 453.60 36,659.95 100.00%
05.04 TENSORES METALICOS DE ACERO LISO DE 3/8" m 100.80 28.32 2,854.66 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 100.80 2,854.66 100.00%
05.05 TEMPLADORES METALICOS DE ACERO LISO DE 1/2" (ENTRE TIJERm 170.56 23.45 3,999.63 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 170.56 3,999.63 100.00%
05.06 COBERTURA CON PLANCHA METALICA TIPO TECNOTECHO MOD.m2 359.86 77.89 28,029.50 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 359.86 28,029.50 100.00%
06 MUROS Y TABIQUES DE ALBAÑILERIA 5,153.01
06.01 MURO DE SOGA CON LADRILLO DE ARCILLA 9x13x24 CM (CON ALm2 44.63 91.18 4,069.36 44.63 4,069.36 100.00% 0.00 0.00% 44.63 4,069.36 100.00% 0.00 0.00 0.00%
06.02 MURO DE CABEZA CON LADRILLO DE ARCILLA 9X13X24 (CON ALAm2 7.32 148.04 1,083.65 7.32 1,083.65 100.00% 0.00 0.00% 7.32 1,083.65 100.00% 0.00 0.00 0.00%

COSTO DIRECTO 371,446.17 287,929.50 66.70% 0.00 0.00% 287,929.50 77.52% 83,516.67 22.48%
VALORIZACION DE OBRA N° 04
CORRESPONDIENTE AL MES DE NOVIEMBRE DEL 2012

Obra : MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA INSTITUCIÓN EDUCATIVA CARLOS FERMIN FITZCARRALD N° DE CONTRATO : 036-2012/GOREMAD/GGR.

Form. : 01 PRESUPUESTO GENERAL CONTRATISTA: CONSORCIO CARLOS F. FITZCARRALD FECHA : 03/07/2012


Cliente : GOBIERNO REGIONAL DE MADRE DE DIOS INSPECTOR: ING. EDUARDO DONAIRES CASTILLO MONTO DE CONTRATO : S/. 23,508,980.65 (INC. IGV.)
Ubicac. : TAMBOPATA - TAMBOPATA - MADRE DE DIOS. FACTOR DE 1.0000000000 PLAZO EJECUCION : 548 DIAS CALENDARIOS

0801064 +MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA INSTITUCIÓN EDUCATIVA "CARLOS FERMÍN FITZCARRALD"


Subpresupuesto 027 (XXVI) V OL 6 - TALLER 2: MECÁNICA DE PRODUCCIÓN ( B5) - ARQUITECTURA
Item Descripciòn Und Metrado P.Unit P.Parcial ACUMULADO ANTERIOR MES ACTUAL ACUMULADO ACTUAL SALDO POR VALORIZAR
01 REVOQUES Y ENLUCIDOS 26,011.68 METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. %
01.01 TARRAJEO EXTERIOR EN MUROS C:A 1:5 e=1.50 cm. m2 108.44 21.18 2,296.76 108.44 2,296.76 100.00% - 0.00% 108.44 2,296.76 100.00% -
01.02 TARRAJEO INTERIOR EN MUROS C:A 1:5 e=1.50 cm. m2 261.78 18.14 4,748.69 261.78 4,748.69 100.00% - 0.00% 261.78 4,748.69 100.00% -
01.03 TARRAJEO EN COLUMNAS - PLACAS C:A 1:5 e=1.50 cm m2 321.03 26.37 8,465.56 321.03 8,465.56 100.00% - 0.00% 321.03 8,465.56 100.00% -
01.04 TARRAJEO EN VIGAS C:A 1/5, e=1.50 cm m2 116.31 32.75 3,809.15 116.31 3,809.15 100.00% - 0.00% 116.31 3,809.15 100.00% -
01.05 TARRAJEO EN TAPASOL Y CANALETA C:A 1:5 e=1.50 cm. m2 148.68 29.52 4,389.03 148.68 4,389.03 100.00% - 0.00% 148.68 4,389.03 100.00% -
01.06 VESTIDURA DE DERRAMES a=0.15 C:A 1:5 e=1.50cm. m 29.20 12.28 358.58 29.20 358.58 100.00% - 0.00% 29.20 358.58 100.00% -
01.07 BRUÑAS VERTICALES DE 1" m 153.60 6.71 1,030.66 153.60 1,030.66 100.00% - 0.00% 153.60 1,030.66 100.00% -
01.08 JUNTAS DE DILATACIÓN VERTICAL DE 25 CM CON TEKNOPm 35.20 9.47 333.34 35.20 333.34 100.00% - 0.00% 35.20 333.34 100.00% -
01.09 JUNTA DE DILATACION VERTICAL DE 15 C.M. CON TECNORm 19.80 7.34 145.33 19.80 145.33 100.00% - 0.00% 19.80 145.33 100.00% -
01.10 TARRAJEO PRIMARIO RAYADO CON CEMENTO-ARENA PARm2 4.06 17.52 71.13 4.06 71.13 100.00% - 0.00% 4.06 71.13 100.00% -
01.11 REVESTIMIENTO DE MUEBLE DE CONCRETO CON CERÁMIm2 4.38 82.98 363.45 4.38 363.45 100.00% - 0.00% 4.38 363.45 100.00% -
02 PISOS Y PAVIMENTOS 15,478.97 - 0.00%
02.01 PISOS INTERIORES DE CONCRETO - ACABADOS C:A 1:4 DE m2 322.94 27.36 8,835.64 - - 0.00% - 0.00% - - 0.00% 322.94 8,835.64 100.00%
02.02 VEREDA DE CONCRETO F'C=175 KG/CM2 h=0.10m, ACABAm2 91.25 57.62 5,257.83 - - 0.00% - 0.00% - - 0.00% 91.25 5,257.83 100.00%
02.03 JUNTAS DE DILATACIÓN HORIZONTAL + SELLO ASFALTICOm 101.80 13.61 1,385.50 - - 0.00% - 0.00% - - 0.00% 101.80 1,385.50 100.00%
03 ZOCALOS Y CONTRAZOCALOS 2,589.38
03.01 CONTRAZOCALO CEMENTO PULIDO S/COLOREAR H=40cmm 90.60 13.95 1,263.87 - - 0.00% - 0.00% - - 0.00% 90.60 1,263.87 100.00%
03.02 CONTRAZOCALO CEMENTO PULIDO S/COLOREAR H=10 cmm 122.55 7.76 950.99 - - 0.00% - 0.00% - - 0.00% 122.55 950.99 100.00%
03.03 ZOCALO DE CERÁMICO DE 20X30 COLOR CLARO m2 6.03 62.11 374.52 - - 0.00% - 0.00% - - 0.00% 6.03 374.52 100.00%
04 CARPINTERIA DE MADERA 1,403.50
04.01 PUERTA DE MADERA QUINILLA MACHIHEMBRADA + MARCO m2 4.01 350.00 1,403.50 - - 0.00% - 0.00% - - 0.00% 4.01 1,403.50 100.00%
05 CARPINTERIA METALICA Y ALUMINIO 47,081.30
05.01 VENTANA METALICA CON MALLA OLIMPICA 2" + MARCO DE m2 109.76 220.00 24,147.20 - - 0.00% - 0.00% - - 0.00% 109.76 24,147.20 100.00%
05.02 PUERTA METALICA ENROLLABLE CON PLANCHA GALVANIZm2 18.28 260.00 4,752.80 - - 0.00% - 0.00% - - 0.00% 18.28 4,752.80 100.00%
05.03 PUERTA METALICA CORREDIZA DE TUBO CUADRADO CONm2 14.90 400.00 5,960.00 - - 0.00% - 0.00% - - 0.00% 14.90 5,960.00 100.00%
05.04 PARASOL DE POLICARBONATO CON MARCO DE ALUMINIOm2 94.01 130.00 12,221.30 - - 0.00% - 0.00% - - 0.00% 94.01 12,221.30 100.00%
06 CERRAJERIA 350.68
06.01 BISAGRA DE BRONCE ALUMINIZADAS DE 4" und 8.00 13.52 108.16 - - 0.00% - 0.00% - - 0.00% 8.00 108.16 100.00%
06.02 CERRADURA NACIONAL DE 3 GOLPES PARA PUERTA und 2.00 90.97 181.94 - - 0.00% - 0.00% - - 0.00% 2.00 181.94 100.00%
06.03 MANIJA DE BRONCE PARA PUERTAS und 2.00 30.29 60.58 - - 0.00% - 0.00% - - 0.00% 2.00 60.58 100.00%
07 PINTURA 8,347.09
07.01 PINTURA EN MUROS EXTERIORES AL LATEX SATINADO 2 m2 108.44 8.65 938.01 - - 0.00% - 0.00% - - 0.00% 108.44 938.01 100.00%
07.02 PINTURA EN MUROS INTERIORES AL LATEX SATINADO 2 m2 261.78 7.96 2,083.77 - - 0.00% - 0.00% - - 0.00% 261.78 2,083.77 100.00%
07.03 PINTURA EN COLUMNAS Y PLACAS AL LATEX SATINADO m2 321.03 9.25 2,969.53 - - 0.00% - 0.00% - - 0.00% 321.03 2,969.53 100.00%
07.04 PINTURA EN VIGAS AL LATEX SATINADO 2 MANOS m2 116.31 9.24 1,074.70 - - 0.00% - 0.00% - - 0.00% 116.31 1,074.70 100.00%
07.05 PINTURA EN TAPASOL Y CANALETA AL LATEX SATINADO m2 148.68 8.50 1,263.78 - - 0.00% - 0.00% - - 0.00% 148.68 1,263.78 100.00%
07.06 PINTURA EN DERRAMES AL LATEX SATINADO 2 MANOS m 4.38 3.95 17.30 - - 0.00% - 0.00% - - 0.00% 4.38 17.30 100.00%

COSTO DIRECTO 101,262.60


26,011.69 17.16% - 0.00% 26,011.69 25.69% 75,250.92 74.31%
VALORIZACION DE OBRA N° 04
CORRESPONDIENTE AL MES DE NOVIEMBRE DEL 2012

Obra : MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA INSTITUCIÓN EDUCATIVA CARLOS FERMIN FITZCARRALD N° DE CONTRATO : 036-2012/GOREMAD/GGR.
Form. : 01 PRESUPUESTO GENERAL CONTRATISTA: CONSORCIO CARLOS F. FITZCARRALD FECHA : 03/07/2012
Cliente : GOBIERNO REGIONAL DE MADRE DE DIOS INSPECTOR: ING. EDUARDO DONAIRES CASTILLO MONTO DE CONTRATO : S/. 23,508,980.65 (INC. IGV.)
Ubicac. : TAMBOPATA - TAMBOPATA - MADRE DE DIOS. FACTOR DE RELACION: 1.0000000000 PLAZO EJECUCION : 548 DIAS CALENDARIOS

(XXXII) VOL 8 - TALLER 4: MECÁNICA Y MOTORES (B7) - INST. ELECTRICAS


Item Descripcion und Metrado P.unit Parcial ACUMULADO ANTERIOR MES ACTUAL ACUMULADO ACTUAL SALDO POR VALORIZAR
01 TRABAJOS PRELIMINARES 1,761.40 METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. %
01.01 TRAZO Y REPLANTEO glb 1.00 511.57 511.57 1 511.57 100.00% 0.00 0.00% 0.00 511.57 100.00%
01.02 INGENIERIA DE DETALLE Exp 1.00 475.04 475.04 1 475.04 100.00% 0.00 0.00% 0.00 475.04 100.00%
01.03 ACABADO Y SEÑALIZACION m2 1.00 247.06 247.06 1 247.06 1.00 0.00 0.00% 0.00 247.06 100.00%
01.04 PRUEBAS Y PUESTA EN SERVICIO glb 1.00 527.73 527.73 1 527.73 100.00% 0.00 0.00% 0.00 527.73 100.00%
02 TABLEROS 5,631.78
02.01 MURO DE CONCRETO ARMADO DE 0.8X1.6X0.3 MTS M2 1.00 275.21 275.21 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 275.21 100.00%
02.02 SUMINISTRO E INSTALAC. DE TD 07/SEG ESPECIF. EN EL PLANO JGO 1.00 3,446.38 3,446.38 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 3,446.38 100.00%
02.03 SUMINISTRO E INSTALAC. DE TD 071/SEG ESPECIF. EN EL PLANO JGO 1.00 1,910.19 1,910.19 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 1,910.19 100.00%
03 ALIMENTADORES 907.12
03.01 CONDUCTOR NYY TRIPOLAR 1-3X10+T10 mm2, 1 KV ml 23.00 39.44 907.12 0.00 0.00% 0.00 0.00% 0.00 0.00% 23.00 907.12 100.00%
04 SISTEMA DE PROTECCION A TIERRA 1,569.63
04.01 SISTEMA DE PUESTA TIERRA TIPO 01 JGO 1.00 971.13 971.13 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 971.13 100.00%
04.02 TENDIDO DE CONDUCTOR DE CU DESNUDO 35 MM2 ml 38.00 15.75 598.50 0.00 0.00% 0.00 0.00% 0.00 0.00% 38.00 598.50 100.00%
05 TUBERIAS Y CAJAS DE PASO 2,155.96
05.01 TUBERIA PVC-P DIAM 20 mm (3/4"x3m) EMPOTRADO m 132.00 4.38 578.16 132.00 578.16 100.00% 0.00 0.00% 0.00 578.16 100.00%
05.02 TUBERIA PVC-P DIAM 20 mm (3/4"x3m) ADOSADO m 148.00 6.87 1,016.76 148.00 1,016.76 100.00% 0.00 0.00% 0.00 1,016.76 100.00%
05.03 TUBERIA PVC-P DIAM 25 mm (1"x3m) EMPOTRADO m 49.30 4.91 242.06 49.30 242.06 100.00% 0.00 0.00% 0.00 242.06 100.00%
05.04 TUBERIA PVC-P DIAM 50 mm (2") EMPOTRADO m 23.00 5.56 127.88 23.00 127.88 100.00% 0.00 0.00% 0.00 127.88 100.00%
05.05 CAJA DE PASE -DERIVACION CIRCUITO DE FUERZA und 14.00 13.65 191.10 14.00 191.10 100.00% 0.00 0.00% 0.00 191.10 100.00%
06 CONDUCTORES Y CABLES 2,662.34
06.01 CONDUCTOR THW 3-1X10+T10mm2 m 20.00 23.14 462.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 20.00 462.80 100.00%
06.02 CONDUCTOR THW 4-1X4 mm2 m 29.30 9.40 275.42 0.00 0.00% 0.00 0.00% 0.00 0.00% 29.30 275.42 100.00%
06.03 CONDUCTOR THW 3-1X4 mm2 m 69.30 7.69 532.92 0.00 0.00% 0.00 0.00% 0.00 0.00% 69.30 532.92 100.00%
06.04 CONDUCTOR THW 3-1X2.5 mm2 m 100.36 5.22 523.88 0.00 0.00% 0.00 0.00% 0.00 0.00% 100.36 523.88 100.00%
06.05 CONDUCTOR THW 2-1X2.5 mm2 m 230.67 3.76 867.32 0.00 0.00% 0.00 0.00% 0.00 0.00% 230.67 867.32 100.00%
07 SALIDAS PARA ALUMBRADO 1,797.56
07.01 SALIDA PARA CENTRO DE LUZ EN TECHO und 20.00 63.04 1,260.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 20.00 1,260.80 100.00%
07.02 SALIDA PARA CENTRO DE LUZ EN PARED und 8.00 29.59 236.72 0.00 0.00% 0.00 0.00% 0.00 0.00% 8.00 236.72 100.00%
07.03 SALIDA PARA LUZ DE EMERGENCIA und 4.00 30.05 120.20 0.00 0.00% 0.00 0.00% 0.00 0.00% 4.00 120.20 100.00%
07.04 SALIDA PARA INTERRUPTORES EN PARED und 8.00 22.48 179.84 0.00 0.00% 0.00 0.00% 0.00 0.00% 8.00 179.84 100.00%
08 ILUMINACION 5,757.92
08.01 SALIDA PARA LUMINARIA TIPO A und 20.00 219.18 4,383.60 0.00 0.00% 0.00 0.00% 0.00 0.00% 20.00 4,383.60 100.00%
08.02 SALIDA PARA LUMINARIA TIPO B und 8.00 53.03 424.24 0.00 0.00% 0.00 0.00% 0.00 0.00% 8.00 424.24 100.00%
08.03 SALIDA PARA LUMINARIA TIPO K und 4.00 179.92 719.68 0.00 0.00% 0.00 0.00% 0.00 0.00% 4.00 719.68 100.00%
08.04 INSTALACION DE INTERRUPTOR SIMPLE und 7.00 28.14 196.98 0.00 0.00% 0.00 0.00% 0.00 0.00% 7.00 196.98 100.00%
08.05 INSTALACION DE INTERRUPTOR DOBLE und 1.00 33.42 33.42 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 33.42 100.00%
09 FUERZA Y TOMACORRIENTES 2,122.51
09.01 SALIDA PARA TOMACORRIENTE DOBLE CON P/TIERRA 1.8 Mts und 1.00 74.31 74.31 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 74.31 100.00%
09.02 SALIDA PARA TOMACORRIENTE DOBLE CON P/TIERRA 0.40 Mts und 22.00 49.12 1,080.64 0.00 0.00% 0.00 0.00% 0.00 0.00% 22.00 1,080.64 100.00%
09.03 SALIDA PARA TOMACORRIENTE P/CARGA ESPECIAL MONOFASICA und 1.00 99.07 99.07 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 99.07 100.00%
09.04 SALIDA PARA TOMACORRIENTE P/CARGA ESPECIAL TRIFASICA und 7.00 124.07 868.49 0.00 0.00% 0.00 0.00% 0.00 0.00% 7.00 868.49 100.00%

24,366.22 3,917.36 16.08% 0.00 0.00% 3,917.36 16.08% 20,448.86 83.92%


#REF!
#REF!

Obra : MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA INSTITUCIÓN EDUCATIVA CARLOS FERMIN FITZCARRALD N° DE CONTRATO : 036-2012/GOREMAD/GGR.

Form. : 01 PRESUPUESTO GENERAL CONTRATISTA: CONSORCIO CARLOS F. FITZCARRALD FECHA : 03/07/2012


Cliente : GOBIERNO REGIONAL DE MADRE DE DIOS INSPECTOR: ING. EDUARDO DONAIRES CASTILLO MONTO DE CONTRATO : S/. 23,508,980.65 (INC. IGV.)
Ubicac. : TAMBOPATA - TAMBOPATA - MADRE DE DIOS. FACTOR DE RELACION: 1.0000000000 PLAZO EJECUCION : 548 DIAS CALENDARIOS

(XXXIII) VOL 9 - TALLER 5-6: HOSTELERÍA - CONFECCIONES (B8) - ESTRUCTURAS


Item Descripcion und Metrado P.unit Parcial ACUMULADO ANTERIOR MES ACTUAL ACUMULADO ACTUAL SALDO POR VALORIZAR
01 TRABAJOS PRELIMINARES 2,486.76 METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. %
01.01 LIMPIEZA DE TERRENO MANUAL m2 469.20 1.12 525.50 469.2 525.50 100.00% 0.00 0.00% 469.20 525.50 100.00% 0.00 0.00 100.00%
01.02 TRAZO, NIVELES Y REPLANTEO INICIAL m2 469.20 4.18 1,961.26 469.2 1,961.26 100.00% 0.00 0.00% 469.20 1,961.26 100.00% 0.00 0.00 100.00%
02 MOVIMIENTO DE TIERRAS 25,520.77
02.01 NIVELACION DE TERRENO m2 469.20 2.49 1,168.31 469.2 1,168.31 100.00% 0.00 0.00% 469.20 1,168.31 100.00% 0.00 0.00 100.00%
02.02 EXCAVACION DE ZANJAS m3 305.65 33.34 10,190.37 305.65 10,190.37 100.00% 0.00 0.00% 305.65 10,190.37 100.00% 0.00 0.00 100.00%
02.03 RELLENO Y COMPACTADO C/ MATERIAL PROPIO m3 202.88 23.67 4,802.17 202.88 4,802.17 100.00% 0.00 0.00% 202.88 4,802.17 100.00% 0.00 0.00 100.00%
02.04 ACARREO INTERNO MAT. PROCED. DE EXCAVACIONES Dprom=30M m3 194.47 17.00 3,305.99 367.26 6,243.42 188.85% 0.00 0.00% 367.26 6,243.42 188.85% -172.79 -2,937.43 100.00%
02.05 ELIMINACION MATERIAL EXCEDENTE CON MAQUINARIA VOLQUETE 15M3m3 194.47 7.91 1,538.26 194.47 1,538.26 100.00% 0.00 0.00% 194.47 1,538.26 100.00% 0.00 0.00 100.00%
02.06 NIVELACION Y APISONADO PARA FALSO PISO O PISO m2 454.25 2.18 990.27 454.25 990.27 100.00% 0.00 0.00% 454.25 990.27 100.00% 0.00 0.00 100.00%
02.07 RELLENO CON AFIRMADO DE e=4" (100% COMPACTACION) m3 46.15 76.39 3,525.40 46.15 3,525.40 100.00% 0.00 0.00% 46.15 3,525.40 100.00% 0.00 0.00 100.00%
03 OBRAS DE CONCRETO SIMPLE 45,816.78
03.01 CONCRETO EN FALSA ZAPATAS F'C= 100 KG/CM2 m3 56.97 257.89 14,691.99 62.89 16,218.70 110.39% 0.00 0.00% 62.89 16,218.70 110.39% -5.92 -1,526.71 100.00%
03.02 CIMIENTO CORRIDO F'c=140 kg/cm2 m3 26.05 303.68 7,910.86 26.05 7,910.86 100.00% 0.00 0.00% 26.05 7,910.86 100.00% 0.00 0.00 100.00%
03.03 CONCRETO EN SOBRECIMIENTO F'C= 175 KG/CM2 m3 5.70 411.54 2,345.78 5.70 2,345.78 100.00% 0.00 0.00% 5.70 2,345.78 100.00% 0.00 0.00 100.00%
03.04 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO m2 73.43 31.61 2,321.12 73.43 2,321.12 100.00% 0.00 0.00% 73.43 2,321.12 100.00% 0.00 0.00 100.00%
03.05 FALSO PISO e= 4" (10CM.) 1:6 C:H m2 454.25 40.83 18,547.03 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 454.25 18,547.03 100.00%
04 OBRAS DE CONCRETO ARMADO 208,647.99
04.01 ZAPATAS 31,968.40
04.01.01 ZAPATAS, CONCRETO F'C=210 KG/CM2 m3 65.80 349.47 22,995.13 65.80 22,995.13 100.00% 0.00 0.00% 65.80 22,995.13 100.00% 0.00 0.00 100.00%
04.01.02 ZAPATAS, ACERO FY=4200KG/CM2 kg 1,857.82 4.83 8,973.27 1,857.82 8,973.27 100.00% 0.00 0.00% 1,857.82 8,973.27 100.00% 0.00 0.00 100.00%
04.02 VIGAS DE CIMENTACION 9,867.55
04.02.01 VIGAS DE CIMENTACION, CONCRETO F'C= 210 KG/CM2 m3 6.27 371.88 2,331.69 6.27 2,331.69 100.00% 0.00 0.00% 6.27 2,331.69 100.00% 0.00 0.00 100.00%
04.02.02 VIGAS DE CIMENTACION, ENCOFRADO Y DESENCOFRADO m2 60.25 54.27 3,269.77 60.25 3,269.77 100.00% 0.00 0.00% 60.25 3,269.77 100.00% 0.00 0.00 100.00%
04.02.03 VIGAS DE CIMENTACION, ACERO FY=4200 KG/CM2. kg 828.88 4.96 4,111.24 828.88 4,111.24 100.00% 0.00 0.00% 828.88 4,111.24 100.00% 0.00 0.00 100.00%
04.02.04 VIGAS DE CIMENTACION, BASE CON POLIESTILENO EXPANDIDO (TECNOPOR
m2 9.19 16.85 154.85 9.19 154.85 100.00% 0.00 0.00% 9.19 154.85 100.00% 0.00 0.00 100.00%
04.03 SOBRECIMIENTOS REFORZADOS 20,419.12
04.03.01 CONCRETO EN SOBRECIMIENTO REFORZADO F'C= 175 KG/CM2 m3 17.88 401.74 7,183.11 17.88 7,183.11 100.00% 0.00 0.00% 17.88 7,183.11 100.00% 0.00 0.00 100.00%
04.03.02 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO m2 223.64 31.61 7,069.26 223.64 7,069.26 100.00% 0.00 0.00% 223.64 7,069.26 100.00% 0.00 0.00 100.00%
04.03.03 SOBRECIMIENTO, ACERO FY=4200 KG/CM2 . kg 1,176.86 5.24 6,166.75 1,176.86 6,166.75 100.00% 0.00 0.00% 1,176.86 6,166.75 100.00% 0.00 0.00 100.00%
04.04 COLUMNETAS 12,773.96
04.04.01 COLUMNETAS, CONCRETO F'C= 175 KG/CM2 m3 6.70 381.44 2,555.65 6.70 2,555.65 100.00% 0.00 0.00% 6.70 2,555.65 100.00% 0.00 0.00 100.00%
04.04.02 COLUMNETAS, ENCOFRADO Y DESENCOFRADO m2 67.69 46.14 3,123.22 67.69 3,123.22 100.00% 0.00 0.00% 67.69 3,123.22 100.00% 0.00 0.00 100.00%
04.04.03 COLUMNETAS, ACERO FY=4200 KG/CM2 kg 1,487.44 4.77 7,095.09 1,487.44 7,095.09 100.00% 0.00 0.00% 1,487.44 7,095.09 100.00% 0.00 0.00 100.00%
04.05 COLUMNAS 73,972.99
04.05.01 COLUMNAS, CONCRETO F'C=210 KG/CM2 m3 41.00 507.07 20,789.87 41.00 20,789.87 100.00% 0.00 0.00% 41.00 20,789.87 100.00% 0.00 0.00 100.00%
04.05.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 416.20 56.37 23,461.19 416.20 23,461.19 100.00% 0.00 0.00% 416.20 23,461.19 100.00% 0.00 0.00 100.00%
04.05.03 COLUMNAS, ACERO FY=4200 KG/CM2. kg 5,885.53 5.05 29,721.93 5,885.53 29,721.93 100.00% 0.00 0.00% 5,885.53 29,721.93 100.00% 0.00 0.00 100.00%
04.06 VIGUETAS DE ARRIOSTRE 7,106.20
04.06.01 VIGUETAS DE ARRIOSTRE, CONCRETO F'c= 175KG/CM2 m3 3.99 329.85 1,316.10 3.99 1,316.10 100.00% 0.00 0.00% 3.99 1,316.10 100.00% 0.00 0.00 100.00%
04.06.02 VIGUETAS DE ARRIOSTRE, ENCOFRADO Y DESENCOFRADO m2 60.35 53.91 3,253.47 60.35 3,253.47 100.00% 0.00 0.00% 60.35 3,253.47 100.00% 0.00 0.00 100.00%
04.06.03 VIGA DE ARRIOSTRE, ACERO FY=4200 KG/CM2. kg 517.68 4.90 2,536.63 517.68 2,536.63 100.00% 0.00 0.00% 517.68 2,536.63 100.00% 0.00 0.00 100.00%
04.07 VIGAS 23,310.95
04.07.01 VIGAS, CONCRETO F'C=210 KG/CM2 m3 15.91 391.02 6,221.13 0.00 0.00 0.00% 15.91 6,221.13 100.00% 15.91 6,221.13 100.00% 0.00 0.00 100.00%
04.07.02 VIGAS, ENCOFRADO Y DESENCOFRADO m2 155.95 59.62 9,297.74 155.95 9,297.74 100.00% 0.00 0.00% 155.95 9,297.74 100.00% 0.00 0.00 100.00%
04.07.03 VIGAS, ACERO FY=4200 KG/CM2. kg 1,590.22 4.90 7,792.08 1,590.22 7,792.08 100.00% 0.00 0.00% 1,590.22 7,792.08 100.00% 0.00 0.00 100.00%
04.08 CANALETA DE CONCRETO EN TECHO 29,228.82
04.08.01 CANALETA DE CONCRETO EN TECHO, CONCRETO F'C=210 KG/CM2 CON ADm3 12.60 412.67 5,199.64 0.00 0.00 0.00% 12.60 5,199.64 100.00% 12.60 5,199.64 100.00% 0.00 0.00 100.00%
04.08.02 CANALETA DE CONCRETO EN TECHO, ENCOFRADO Y DESENCOFRADO m2 267.12 72.87 19,465.03 267.12 19,465.03 100.00% 0.00 0.00% 267.12 19,465.03 100.00% 0.00 0.00 100.00%
04.08.03 CANALETA DE CONCRETO EN TECHO, ACERO FY=4200 KG/CM2. kg 931.46 4.90 4,564.15 931.46 4,564.15 100.00% 0.00 0.00% 931.46 4,564.15 100.00% 0.00 0.00 100.00%
05 ESTRUCTURA METALICA Y COBERTURA 110,699.04
05.01 TIJERAL METÁLICO DE SECCIÓN RECTANGULAR T-1 und 5.00 6,670.74 33,353.70 5.00 33,353.70 100.00% 0.00 0.00% 5.00 33,353.70 100.00% 0.00 0.00 100.00%
05.02 SOPORTES METALICOS PARA CERCHAS und 10.00 580.16 5,801.60 10.00 5,801.60 100.00% 0.00 0.00% 10.00 5,801.60 100.00% 0.00 0.00 100.00%
05.03 VIGUETA TIPO "Z" DE 100mm x 51mm x 4.5mmm x 6.00m m 453.60 80.82 36,659.95 0.00 0.00 0.00% 453.60 36,659.95 100.00% 453.60 36,659.95 100.00% 0.00 0.00 100.00%
05.04 TENSORES METALICOS DE ACERO LISO DE 3/8" m 100.80 28.32 2,854.66 0.00 0.00 0.00% 100.80 2,854.66 100.00% 100.80 2,854.66 100.00% 0.00 0.00 100.00%
05.05 TEMPLADORES METALICOS DE ACERO LISO DE 1/2" (ENTRE TIJERALES) m 170.56 23.45 3,999.63 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 170.56 3,999.63 100.00%
05.06 COBERTURA CON PLANCHA METALICA TIPO TECNOTECHO MOD. TR4 950xm2 359.86 77.89 28,029.50 0 0 0.00% 0.00 0.00% 0.00 0.00 0.00% 359.86 28,029.50 100.00%
06 MUROS Y TABIQUES DE ALBAÑILERIA 24,826.96
06.01 MURO DE SOGA CON LADRILLO DE ARCILLA 9x13x24 CM. (CON ALAMBRE m
N2 72.16 91.18 6,579.55 72.16 6579.5488 100.00% 0.00 0.00% 72.16 6,579.55 100.00% 0.00 0.00 100.00%
06.02 MURO DE CABEZA CON LADRILLO DE ARCILLA 9X13X24 (CON ALAMBRE N°m2 123.26 148.04 18,247.41 123.26 18247.4104 100.00% 0.00 0.00% 123.26 18,247.41 100.00% 0.00 0.00 100.00%

COSTO DIRECTO 417,998.30 320,950.89 76.78% 50,935.38 12.19% 371,886.27 88.97% 46,112.03 11.03%