3 OBRAS PRELIMINARES 93.5 días jue 01/10/20 sáb 02/01/21 98% -S/15,889.67 S/60,770.38 S/44,880.71
7 CAPA NIVELANTE E= 0.05 cm 35 días lun 26/10/20 jue 14/01/21 63% -S/48,982.94 S/133,970.76 S/84,987.82 63%
8 MATERIAL GRANULAR DE CANTERA PARA 60
AFIRMADO
días E=0.15
dom 25/10/20
cm mié 03/02/21 45% -S/262,987.57 S/477,255.24 S/214,267.67 45%
9 TRANSPORTE 91.56 días mar 27/10/20 mar 26/01/21 45% -S/559,954.98 S/886,117.39 S/326,162.41
15 RECONFORMACION DE CUNETAS 20 días dom 13/12/20 sáb 06/02/21 45% -S/145,739.50 S/264,480.00 S/118,740.50 45%
16 SEÑALIZACION 22 días sáb 06/02/21 dom 28/02/21 0% -S/40,364.60 S/40,364.60 S/0.00
17 INSTALACION DE POSTES KILOMETRICOS 15 días sáb 06/02/21 dom 21/02/21 0% -S/18,536.16 S/18,536.16 S/0.00 0%
18 SEÑALES INFORMATIVAS 7 días dom 21/02/21 dom 28/02/21 0% -S/21,828.44 S/21,828.44 S/0.00 0%
19 IMPACTO AMBIENTAL 36.66 días dom 24/01/21 lun 01/03/21 89% -S/1,872.78 S/16,854.99 S/14,982.21
22 EMERGENCIA SANITARIA COVID - 19 144 días jue 01/10/20 lun 22/02/21 74% -S/10,078.64 S/38,764.00 S/28,685.36 74%
23 FIN 0 días dom 21/02/21 dom 21/02/21 0% S/0.00 S/0.00 S/0.00 21/02
Tarea Agrupar por síntesis Tareas externas Tarea manual solo fin