PROYECTO MEJORAMIENTO, MANTENIMIENTO Y CONSERVACIÓN DE LA VÍA PUERTO RICO-EL MOJON-SANTA ANA-LIMITES NAMAY Y LA ESPERANZA-LOMA LARGA-BUENOS AIRES MESETAS EN EL
MUNICIPIO DE SASAIMA DEPARTAMENTO DE CUNDINAMARCA
CONTRATANTE MUNICIPIO DE SASAIMA CUNDINAMARCA
OFERENTE CONSORCIO SANTA INES
CONTRATO CONTRATO DE OBRA PUBLICA No. CO-94 DE 2014DE 2014
FECHA DE INICIO AGOSTO 20 DE 2014
FECHA ESTIMADA DE TERMINACION DICIEMBRE 19 DE 2014
VALOR DEL CONTRATO $ 760,496,476.00
AGOSTO SEPTIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE
SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8 SEMANA 9 SEMANA 10 SEMANA 11 SEMANA 12 SEMANA 13 SEMANA 14 SEMANA 15 SEMANA 16 SEMANA 17 SEMANA 18
M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V
PRELIMINARES
LEGALIZACION POLIZAS (ACTA DE INICIO)
4.10% 7.18% 9% 17.14% 7.00% 7.00% 9.50% 9.00% 7.00% 8.00% 7.00% 8.08%
EXCAVACIONES VARIAS: Excavaciones varias en material c 975.4 24,968.00 24,353,787.20
998,505.28 $ 1,748,601.92 $ 2,191,840.85 4,174,239.13 1,704,765.10 1,704,765.10 2,313,609.78 2,191,840.85 1,704,765.10 1,948,302.98 1,704,765.10 1,967,786.01
50.00% 50.00%
DEMOLICIÓN Y REMOCIÓN 3.6 57,990.00 208,764.00 104,382.00 104,382.00
9.03% 3.01% 17.20% 35.38% 35.38%
CONFORMACIÓN DE LA CALZADA EXISTENTE 10000 787.00 7,870,000.00 710,661.00 236,887.00 1,353,640.00 2,784,406.00 2,784,406.00
100%
TRANSPORTE DE MATERIAL PROVENIENTE DE
EXCAVACIONES Y DERRUMBRES: Transporte de
877.72 1,192.00 1,046,242.24 1,046,242.24
materiales provenientes de la excavación de la explanación,
canales y prestamos a distancias mayores a 1000m
53.33% 46.67%
GAVIÓN: Gaviones 112.5 224,063.00 25,207,087.50 13,442,939.76 11,764,147.74
27.09% 22.05% 19.68% 16% 15.18%
AFIRMADO: afirmado 200 137,491.00 27,498,200.00
7,449,262.38 6,063,353.10 5,411,645.76 4,399,712.00 4,174,226.76
52.50% 23.75% 23.75%
SUBDRENES CON GEOTEXTIL Y MATERIAL GRANULAR: Materia
48 190,750.00 9,156,000.00 4,806,900.00 2,174,550.00 2,174,550.00
56.88% 43.12% 52.50%
SUBDRENES CON GEOTEXTIL Y MATERIAL GRANULAR: Geo240 9,253.00 2,220,720.00 1,263,145.54 957,574.46
50.00% 50.00%
TUBERÍA DE CONCRETO REFORZADO: Tubería de concreto re 24 464,018.00 11,136,432.00 5,568,216.00 5,568,216.00
2.83% 5.09% 9.00% 9.00% 9.00% 10.00% 10.00% 10.0% 10.0% 10% 10.0% 5.08%
CONCRETO ESTRUCTURAL: Concreto clase D 509 704,243.00 358,459,687.00 10,144,409.14 18,245,598.07 32,261,371.83 32,261,371.83 32,261,371.83 35,845,968.70 35,845,968.70 35,845,968.70 35,845,968.70 35,845,968.70 35,845,968.70 18,209,752.10
10.00% 10.00% 10.00% 10.00% 10.00% 10.00% 10.00% 10.00% 10.00% 10.00%
CONCRETO ESTRUCTURAL: Concreto clase F 85.28 556,247.00 47,436,744.16 4,743,674.42 4,743,674.42 4,743,674.42 4,743,674.42 4,743,674.42 4,743,674.42 4,743,674.42 4,743,674.42 4,743,674.42 4,743,674.42
7.16% 7.16% 2.84% 12.55% 2.76% 7.00% 7.00% 8.00% 8.00% 8.0% 8.0% 8% 8.0% 2.78% 2.75%
CONCRETO ESTRUCTURAL: Concreto clase G 296.88 458,201.00 136,030,712.88 9,739,799.04 9,739,799.04 3,863,272.25 17,071,854.47 3,754,447.68 9,522,149.90 9,522,149.90 10,882,457.03 10,882,457.03 10,882,457.03 10,882,457.03 10,882,457.03 10,882,457.03 3,781,653.82 3,740,844.60
4.25% 7.27% 12.00% 12.00% 12.00% 8.50% 8.50% 8.5% 8.5% 8.5% 8.5% 1.48%