Está en la página 1de 5

CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECTO : "MEJORAMIENTO DEL CAMINO VECINAL LLOCLLA-ARHUAY GRANDE, DISTRITO DE MASIN, PROVINCIA DE HUARI, DEPARTAMENTO DE ANCASH"-SALDO DE
OBRA.

FECHA : ENERO 2020

PRECIO PRESUPUESTO MES 01 MES 02


DESCRIPCION UND.
S/. CANT. PRESUP. (S/.) CANT. PARCIAL CANT. PARCIAL

CAPATAZ hh 21.73 59.0897 1,284.02 54.07 1,174.88 5.02 109.14


OPERARIO hh 18.95 295.4575 5,598.92 270.34 5,123.01 25.11 475.91
OFICIAL hh 17.39 170.8212 2,970.58 156.30 2,718.08 14.52 252.50
PEON hh 15.67 1,334.1040
20,905.41 1,220.71 19,128.45 113.40 1,776.96
OPERADOR DE EQUIPO LIVIANO hh 17.39 33.7150
586.30 30.85 536.47 2.87 49.84
TOPOGRAFO hh 22.48 82.3964 1,852.27 75.39 1,694.83 7.00 157.44
CONTROLADOR OFICIAL hh 17.39 52.2801 909.15 47.84 831.87 4.44 77.28
FLETE TERRESTRE glb 7,598.45 1.0000 7,598.45 0.92 6,952.58 0.09 645.87
MOVILIZACION Y DESMOVILIZACION DE EQUIPO glb 6,364.46 1.0000 6,364.46 0.92 5,823.48 0.09 540.98
TRANSPORTE DE MADERA PARA PUENTE m3 500.00 1.0000 500.00 0.92 457.50 0.09 42.50
ALAMBRE NEGRO RECOCIDO N° 8 kg 4.63 134.3850 622.20 122.96 569.32 11.42 52.89
ALAMBRE NEGRO RECOCIDO N° 16 kg 4.06 59.3241 240.86 54.28 220.38 5.04 20.47
ACERO CORRUGADO fy = 4200 kg/cm2 GRADO 60 kg 3.20 2,036.7941 6,517.74 1,863.67 5,963.73 173.13 554.01
CLAVOS PARA MADERA CON CABEZA kg 4.33 59.1294
256.03 54.10 234.27 5.03 21.76
ALCANTARILLA METALICA CIRCULAR TMC Ø=36" m 305.08 39.0000
11,898.12 35.69 10,886.78 3.32 1,011.34
PIEDRA MEDIANA m3 76.27 10.0660 767.73 9.21 702.48 0.86 65.26
PIEDRA GRANDE DE 8"-10" m3 30.00 115.6320 3,468.96 105.80 3,174.10 9.83 294.86
ARENA FINA (PUESTA EN OBRA) m3 80.00 0.0500 4.00 0.05 3.66 0.00 0.34
ARENA GRUESA (PUESTA EN OBRA) m3 127.12 35.4008 4,500.15 32.39 4,117.64 3.01 382.51
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECTO : "MEJORAMIENTO DEL CAMINO VECINAL LLOCLLA-ARHUAY GRANDE, DISTRITO DE MASIN, PROVINCIA DE HUARI, DEPARTAMENTO DE ANCASH"-SALDO DE
OBRA.

FECHA : ENERO 2020

PRECIO PRESUPUESTO MES 01 MES 02


DESCRIPCION UND.
S/. CANT. PRESUP. (S/.) CANT. PARCIAL CANT. PARCIAL

HORMIGON DE RIO SELECCIONADO (puesta en obra) m3 76.27 42.0749 3,209.05 38.50 2,936.28 3.58 272.77
AFIRMADO m3 38.14 254.7000 9,714.26 233.05 8,888.55 21.65 825.71
MATERIAL CLASIFICADO PARA BASE m3 3.50 11.8560 41.50 10.85 37.97 1.01 3.53
CEMENTO PORTLAND TIPO I (42.5 kg) bol 23.10 752.4262
17,381.05 688.47 15,903.66 63.96 1,477.39
YESO BOLSA 15 kg APROX. bol 6.78 0.4991
3.38 0.46 3.10 0.04 0.29
MADERA TORNILLO INC.CORTE PARA ENCOFRADO p2 4.23 1,316.9730 5,570.80 1,205.03 5,097.28 111.94 473.52
MADERA EUCALIPTO p2 4.50 1,947.0100 8,761.55 1,781.51 8,016.81 165.50 744.73
MADERA EUCALIPTO ROLLIZO und 50.00 20.0000 1,000.00 18.30 915.00 1.70 85.00
ESTACAS DE MADERA p2 3.50 5,083.0000 17,790.50 4,650.95 16,278.31 432.06 1,512.19
ESTACAS DE MADERA DE LA ZONA D=1"x40 CM pza 2.00 49.9100 99.82 45.67 91.34 4.24 8.48
PINTURA ESMALTE SINTETICO gal 25.42 5.1825 131.74 4.74 120.54 0.44 11.20
PINTURA ESMALTE PARA TRAFICO gal 59.98 0.6993 41.94 0.64 38.38 0.06 3.57
DISOLVENTE PARA PINTURA DE TRAFICO gal 46.60 0.2331 10.86 0.21 9.94 0.02 0.92
FULMINANTE und 1.80 346.0600
622.91 316.64 569.96 29.42 52.95
DINAMITA kg 15.95 69.2120
1,103.93 63.33 1,010.10 5.88 93.83
GUIA m 1.90 346.0600 657.51 316.64 601.63 29.42 55.89
AGUA m3 0.50 15.3871 7.69 14.08 7.04 1.31 0.65
BARRENO DE 5"x7/8 und 254.24 34.6060 8,798.23 31.66 8,050.38 2.94 747.85
NIVEL TOPOGRAFICO hm 8.47 1.0673 9.04 0.98 8.27 0.09 0.77
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECTO : "MEJORAMIENTO DEL CAMINO VECINAL LLOCLLA-ARHUAY GRANDE, DISTRITO DE MASIN, PROVINCIA DE HUARI, DEPARTAMENTO DE ANCASH"-SALDO DE
OBRA.

FECHA : ENERO 2020

PRECIO PRESUPUESTO MES 01 MES 02


DESCRIPCION UND.
S/. CANT. PRESUP. (S/.) CANT. PARCIAL CANT. PARCIAL

ESTACION TOTAL hm 12.71 81.3280 1,033.68 74.42 945.82 6.91 87.86


HERRAMIENTAS MANUALES %mo 1,089.20 0.00 544.60 0.00 544.60
COMPACTADORA VIBRATORIA TIPO PLANCHA 4 HP hm 18.90 51.9311 981.50 47.52 898.07 4.41 83.43
MARTILLO NEUMATICO DE 29 kg hm 13.90 27.9476
388.47 25.57 355.45 2.38 33.02
COMPRESORA NEUMATICA 125-175 PCM, 76 HP hm 8.98 4.6620
41.86 4.27 38.31 0.40 3.56
COMPRESORA NEUMATICA 196 HP 600-690 PCM hm 101.69 27.9477 2,842.00 25.57 2,600.43 2.38 241.57
CARGADOR SOBRE LLANTAS DE 160-195 HP 3.5 yd3 hm 186.44 14.4445 2,693.03 13.22 2,464.12 1.23 228.91
RETROEXCAVADORA hm 135.59 25.8280 3,502.02 23.63 3,204.35 2.20 297.67
RODILLO LISO VIBRATORIO AUTOPROPULSADO 101-135HP 10-12 Ton hm 186.44 6.5428 1,219.84 5.99 1,116.15 0.56 103.69
MOTONIVELADORA DE 125 HP hm 186.44 40.5668 7,563.27 37.12 6,920.40 3.45 642.88
CAMION VOLQUETE DE 15 m3 hm 127.12 15.1353 1,924.00 13.85 1,760.46 1.29 163.54
CAMION CISTERNA (2,500 GLNS.) hm 130.00 6.5428 850.56 5.99 778.27 0.56 72.30
MEZCLADORA DE CONCRETO DE 9-11 P3 hm 21.19 35.7150 756.80 32.68 692.47 3.04 64.33
VIBRADOR PARA CONCRETO 4 HP 1.50° hm 16.95 33.7150
571.47 30.85 522.89 2.87 48.57
TOTALES S/.177,258.83 S/.161,739.81 S/.15,519.02
AVANCE MENSUAL 100.00% 91.24% 8.76%
AVANCE MENSUAL ACUMULADO 100.00% 91.24% 100.00%
4.4% 5.7% 12.4% 19.1% 27.0% 25.4% 4.0% 2.0%

0.04361081 0.05690519 0.12416971 0.19101186 0.2698628 0.25436065 0.04041693 0.01993695


100.0%