Está en la página 1de 2

Universidad Autónoma de Santo Domingo

UASD
Facultad de Ingeniería y Arquitectura
ARQ-361 Costo y Presupuesto I
Prof. Luis Miguel Caraballo Hernández

TAREA No.1
No. DESCRIPCION UNIDAD PRECIO SUMATORIA DE PRECIOS
1.00 MATERIALES DE FERRETERIAS
380+355+355+365+390+360+255+370+360+370
1.01 Cemento Gris Fdas 359.05
+365+424.80+317.80 /13
60+265+82.60+154.46+365+304.99+113.76+55+
1.02 Cal Fdas 133.74
80+60.75+62+88.50+46.61 /13
40+32+32.50+33.1+55+30+30.73+35+40+38.50+
1.03 Clavo Corriente de 2½" Lbs 39.08
55+53.10+33.10/13
54+51+55.04+73+55+54.24+45+60+50.84+60+7
1.04 Clavo de Acero de 2½" Lbs 57.27
0.80+58.34 /12
2,405+2,478+2,372+1,250.50+1,650+1,450+1,25
1.05 Varilla ؼ" Grado 40 qq 1,895.11
0.50+1,250+2950 /9
2245.76+3304+2158+2158.10+2665.32+2535+2
1.06 Varilla Ø⅜" Grado 40 qq 2,507.36
043.83+2372+2529+2757.3+2372+2950 /12
2,900+2,372+2,862.32+2,498+2,372+2,158.10+2
1.07 Varilla ؽ" Grado 40 qq 2495.99
,450+2,828.56+2,158+2,950+2,245 /12
2,140.00+2,498.99+2,950.00+3,163.00+2,158.10
1.08 Varilla ؾ" Grado 40 qq $2,530.22
+2,158.10+2,295.00+3,163.00+2,245.76/9
2,200.00+2,995.00+1,652.54+2,950.00+1,413.00
1.09 Varilla Ø1" Grado 40 qq $2,197.31 +2,200.00+2,200.00+1,625.00+2,852.00+1,885.5
6/10
2,158.10+2,250.00+2,650.00+2,496.86+2,950.00
1.10 Varilla Ø⅜" Grado 60 qq $2,434.22 +2,493.00+2,158.10+2,158.10+2,535.00+2,493.0
0/10
2,158.10+2,502.25+2,650.00+2,502.25+2,950.00
1.11 Varilla ؽ" Grado 60 qq $2,453.28 +2,502+2,158.10+2,158.10+2,450.00+2,502.00/1
0
2,158.10+2,250.00+2,650.00+2,496.63+2,950.00
1.12 Varilla ؾ" Grado 60 qq $2,361.39 +2,249.00+2,158.10+2,158.10+2,295.00+2,249.0
0/10
2,200.00+2,642.00+2,650.00+2,474.38+2,950.00
1.13 Varilla Ø1" Grado 60 qq $2,511.15
+2,642.00+2,200.00+2,200.00+2,642.00/9
50.00+175.00+51.95+49.22+70.80+65.00+33.00
1.14 Alambre No.18 Lbs $60.76
+50.00+45.00+59.99+48.00+51.92+40.00/13
75.00+141.39+101.17+155.00+236.00+900.00+1
1.15 Hilo de Naylon No.16 Rollo $194.69 41.39+131.50+180.00+140.00+141.00+118.64+1
70.00/13
1.16 Madera de Pino Americano (*) P2
580.00+556.00+548.7+525.01+777.00+548.70+5
1.17 Plywood de ¼" (4'x8') Unidad $572.40 80.00+575.00+505.94+479.00+508.47+685.00/1
2
750.00+768.00+932.20+985.01+1,168.20+932.2
1.18 Plywood de ⅜" (4'x8') Unidad $1,014.25 0+2,500.00+750.00+815.00+705.99+861.00+762
.71+1,255/13
1320.00+927.00+955.46+1,225.01+1,770.00+95
1.19 Plywood de ½" (4'x8') Unidad $1,133.46 5.80+1,320.00+1,110.00+876.21+910.00+932.20
+1,300.00/12
1,500.00+1,430.00+1,403.02+2,045.00+2,360.00
1.20 Plywood de ¾" (4'x8') Unidad $1,418.30 +1,403.02+1,560.00+1,330.00+1,322.61+1,478.0
0+1,610.67/11

2.00 HORMIGONES INDUSTRIALES


5,400.00+5,800.00+5,400.00+6,125.06+6,100.00
2 3
2.01 Hormigón Industrial f 'c= 180 Kg/cm M $5,575.01 +6,200.00+4,800.00+5,400.00+6,500.00+4,800.0
0+4,800.00/11
5,600.00+6,100.00+5,750.00+6,500.00+6,450.00
2 3
2.02 Hormigón Industrial f 'c= 210 Kg/cm M $5,750.00 +5,000.00+5,600.00+6,700.00+5,000.00+5,050.0
0/10
5,850.00+6,400.00+5,900.00+6,750.00+6,650.00
2.03 Hormigón Industrial f 'c= 240 Kg/cm 2 M3 $6,026.80 +5,300.00+5,850.00+7,018.00+5,300.00+5,250.0
0/10
5,950.00+6,500.00+6,450.00+7,000.00+6,750.00
2.04 Hormigón Industrial f 'c= 250 Kg/cm 2 M3 $6,329.40 +6,570.00+5,950.00+7,134.00+5,690.00+5,300.0
0/10
6,850.00+6,700.00+6,300.00+6,643.74+7,300.00
2.05 Hormigón Industrial f 'c= 280 Kg/cm 2 M3 $6,572.15 +6,850.00+6,050.00+6,850.00+7,250.00+6,050.0
0+5,450.00/11
6,915.10+6,950.00+6,550.00+7,550.00+6,915.00
2.06 Hormigón Industrial f 'c= 300 Kg/cm 2 M3 $6,810.56 +6,606.40+6,915.10+7,482.00+6,707.00+5,515.0
0/10
7,446.00+7,446.00+7,050.00+8,500.00+7,446.00
2.07 Hormigón Industrial f 'c= 350 Kg/cm 2 M3 $7,441.56 +7,920.60+7,446.00+7,900.00+7,215.00+6,046.0
0/10
1,400.00+8,000.00+8,000.00+1,400.00+1,400.00
2.08 Uso de Equipo para Bombeo de Hormigón M3 $3,600.00
+1,400.00/6

2.00 OTROS MATERIALES


843.75+2,385.00+1,016.94+864.41+1,021.00+90
3
2.01 Arena Gruesa M $1,065.89 0.00+1,400.00+843.75+800.00+850.00+800.00/1
1
1,600.00+5,721.00+1,849.99+2,006.00+1,700.00
2.02 Arena Gruesa Lavada M3 $1,974.95 +850.00+1,700.00+1,170.00+1,800.00+1,675.00
+1,652.54/11
950.00+2,700.00+1,062.00+1,498.31+1,180.00+
2.03 Grava M3 $1,367.30 1,100.00+1,400.00+1,200.00+1,150.00+2,000.00
+800.00/11
1,200.00+5,625.00+1,567.80+1,210.00+1,180.00
2.04 Grava Triturada M3 $1,590.54 +1,200.00+973.25+1,250.00+999.99+1,400.00+8
89.93/11
790.00+296.61+737.50+944.00+1,243.00+310.2
2.05 Caliche M3 $818.26
5+800.00+1,000.00+1,243.00/9
1,175.00+1,567.79+1,037.29+1,888.00+1,600.00
2.06 Arena para Pañete M3 $1,419.60 +1,400.00+1,175.00+1,650.00+2,100.00+603.00/
10

NOTA: (*) Algunas Ferreterías no venden la


madera por P2 en ese caso tendran que
comprar una tabla (Unidad), por ejemplo:
(1) 1"x4" de 10' U 287.32 236.00+227.26+459.02+227.00/4
459.02+414.99+460.33+491.52+454.00+461.96/
(1) 2"x4" de 10'
U 456.97 6
(1) 1"x4" de 12' U 284.86 295.00+272.71+296.61+272.00+288.00/5
(1) 1"x4" de 14' U 348.28+318.17+343.22+318.00/4

(1) 2"x4" de 12' U


563.83 572.30+500.00+644.45+572.30+544.00+549.96/6
(1) 4"x4" de 14' U 953.91 1,016.95+1,521.80+641.92+635.00/4