Está en la página 1de 58

MATERIALES DE CONSTRUCCION

CANT X PRECIO COSTO


M3/M2
M2/M3 UNITARIO TOTAL

PRIMER PISO
ZAPATAS 12.96 142.56 21 S/. 2,993.76
COLUMNAS Y PLACAS 10.05 110.55 21 S/. 2,321.55
S/. 7,735.61
LOSA ALIGERADA 5.99 65.912 21 S/. 1,384.15
VIGAS 4.49 49.3405 21 S/. 1,036.15
LADRILLO HUECO 69.00 621 2.2 S/. 1,366.20
LADRILLO KING KONG 74.78 2841.45 1 S/. 2,841.45
ARENA GRUESA 33.49 11.720625 40 S/. 468.83
PIEDRA CHANCADA 3/4" 33.49 11.720625 40 S/. 468.83

SEGUNDO PISO
COLUMNAS Y PLACAS 10.05 110.55 21 S/. 2,321.55
LOSA ALIGERADA 5.99 65.912 21 S/. 1,384.15 S/. 4,741.85
VIGAS 4.49 49.3405 21 S/. 1,036.15
LADRILLO HUECO 69.00 621 2.2 S/. 1,366.20
LADRILLO KING KONG 74.78 2841.45 1 S/. 2,841.45
ARENA GRUESA 20.53 7.184625 40 S/. 287.39
PIEDRA CHANCADA 3/4" 20.53 7.184625 40 S/. 287.39

ACERO CORRUGADO
3/8" 1/2" 5/8" COSTO
PRIMER PISO S/. 3,796.67
COLUMNAS Y PLACAS 50.00 25.666666667 20.533333333 S/. 2,796.67
VIGAS 20 S/. 1,000.00
SEGUNDO PISO
COLUMNAS Y PLACAS
VIGAS

CUADRO RESUMEN
FIERRO PIEDRA
CEMENTO LADRILLO LADRILLO CORRUGAD ARENA CHANCAD TOTAL
NIVEL
TIPO IP HUECO KING KONG O GRUESA A
PRIMER PISO S/. 7,735.61 S/. 1,366.20 S/. 2,841.45 S/. 3,796.67 S/. 468.83 S/. 468.83 S/. 16,677.58
SEGUNDO PISO S/. 4,741.85 S/. 1,366.20 S/. 2,841.45 S/. 3,796.67 S/. 287.39 S/. 287.39 S/. 13,320.94
S/. 29,998.52
HOJA DE METRADOS - ESTRUCTURA

Obra: VIVIENDA MULTIFAMILIAR - "LOS CEREZOS"

MEDIDAS
CODIGO PARTIDA UNID. N. VECES PARCIAL TOTAL
LARGO ANCHO ALTO
01.00.00 OBRAS PROVISIONALES
01.01.00 Construcciones provisionales
01.01.01 Almacen, Oficina y Caseta de Guardiania m2 35 35.00 35.00
01.01.02 Baño Temporal Mes 6 6.00 6.00

02.00.00 TRABAJOS PRELIMINARES


02.01.00 Trazos, niveles y replanteo 400.00
Global m2 1 Area 400.00 400.00
02.02.00 Replanteo durante el proceso 3100.00
Global m2 1 Area 3100.00 3100.00

03.00.00 MOVIMIENTO DE TIERRAS


03.01.00 EXCAVACIONES
03.01.01 Excavaciones Masivas 400.20
m3 1 Area 92.00 4.35 400.20

03.01.02 Excavaciones Manuales 24.94


Zapatas m3 19 1.25 1.50 0.70 24.94

03.01.03 Excavaciones de calzaduras 0.00

04.00.00 RELLENOS
04.01.00 Relleno con material propio #REF!
m3 #REF!

04.02.00 Relleno con material de prestamo 0.00


m3 1 Area 0.00

04.03.00 Nivelacion Interior y Apisonado


04.03.01 Nivelacion Compactado c/equipo 92.00
m2 1 Area 92 92.00

04.04.00 Eliminacion de Material Excedente


04.04.01 Eliminacion de Material Excedente m3 1 #REF! Fac 1.25 #REF! #REF!

05.00.00 OBRAS DE CONCRETO SIMPLE


05.01.00 Subcimiento
05.01.01 Concreto Ciclopeo 1:12+30%PG 23.12
Zapatas m3 1 4.60 1.00 0.20 0.92
m3 1 4.20 1.85 0.45 3.50
dados m3 1 1.50 1.50 2.20 4.95
m3 1 2.50 2.50 2.20 13.75

05.02.00 Cimientos Corrido


05.02.01 Concreto Ciclopeo 1:10+30%PG 0.88
Cimientos Corridos
m3 1 2.00 0.45 0.70 0.63
m3 1 0.80 0.45 0.70 0.25

05.03.00 Sobrecimientos
05.03.01 Sobrecimientos concreto 1:8+25%PM 0.50
m3 2 3.30 0.15 0.50 0.50
HOJA DE METRADOS - ESTRUCTURA

Obra: VIVIENDA MULTIFAMILIAR - "LOS CEREZOS"

MEDIDAS
CODIGO PARTIDA UNID. N. VECES PARCIAL TOTAL
LARGO ANCHO ALTO
05.03.02 Encofrado y Desencofrado de Sobrecimientos 6.60
m2 2 3.30 0.50 6.60

05.04.00 Falsopiso E=4'' 92.00


m2 1 Area 92 92.00

05.05.00 Calzaduras
05.05.01 Concreto Ciclopeo 1:10+30%PG 122.64
m3 1 42.40 2.40 1.00 101.76
m3 1 8.70 2.40 1.00 20.88

05.05.02 Encofrado 51.10


m2 1 42.40 1.00 42.40
m2 1 8.70 1.00 8.70

06.00.00 OBRAS DE CONCRETO ARMADO


06.01.00 Zapatas
06.01.01 Concreto (f'c = 210 kg/cm2) 12.96
Zapatas m3 1 area 0.90 0.60 0.54
m3 1 area 1.30 0.60 0.78
m3 1 area 1.40 0.60 0.84
m3 2 area 1.25 0.60 1.50
m3 2 area 1.90 0.60 2.28
m3 1 area 3.20 0.60 1.92
m3 1 area 5.50 0.60 3.30
m3 1 area 1.20 0.60 0.72
m3 2 area 0.90 0.60 1.08

06.01.02 Encofrado 73.15


Zapatas m2 19 1.25 0.70 2.00 33.25
m2 19 1.50 0.70 2.00 39.90

06.01.03 Acero ( Grado 60 ) Kg 3221.00 3221.00

06.02.00 Vigas de Cimentacion


06.02.01 Concreto (f'c = 210 kg/cm2) 1.86
VC1 m3 1 4.65 0.40 1.00 1.86

06.02.02 Encofrado y Desencofrado 9.30


m2 1 4.65 1.00 9.30

06.02.03 Acero ( Grado 60 ) Kg #NAME? #NAME?

06.04.00 Columnas y Placas


06.04.01 Concreto (f'c = 210 kg/cm2) 20.10

PRIMER
COL m3 7 0.25 0.50 2.70 2.36
COL m3 5 0.25 0.30 2.70 1.01
COL m3 1 AREA 0.25 2.70 0.68
COL m3 1 AREA 0.51 3.70 1.89
COL m3 1 AREA 0.39 4.70 1.83
COL m3 2 AREA 0.20 5.70 2.28
HOJA DE METRADOS - ESTRUCTURA

Obra: VIVIENDA MULTIFAMILIAR - "LOS CEREZOS"

MEDIDAS
CODIGO PARTIDA UNID. N. VECES PARCIAL TOTAL
LARGO ANCHO ALTO
SEGUNDO
COL m3 7 0.25 0.50 2.70 2.36
COL m3 5 0.25 0.30 2.70 1.01
COL m3 1 AREA 0.25 2.70 0.68
COL m3 1 AREA 0.51 3.70 1.89
COL m3 1 AREA 0.39 4.70 1.83
COL m3 2 AREA 0.20 5.70 2.28

06.04.02 Encofrado 166.86


PRIMER
COL m2 7 0.25 2.70 2.00 9.45 28.35
COL m2 7 0.50 2.70 2.00 18.90
COL m2 5 0.25 2.70 2.00 6.75
COL m2 5 0.30 2.70 2.00 8.10
COL m2 1 PERIM 2.50 2.70 6.75
COL m2 1 PERIM 4.60 2.70 12.42
COL m2 1 PERIM 3.60 2.70 9.72
COL m2 2 PERIM 2.10 2.70 11.34

SEGUNDO
COL m2 7 0.25 2.70 2.00 9.45
COL m2 7 0.50 2.70 2.00 18.90
COL m2 5 0.25 2.70 2.00 6.75
COL m2 5 0.30 2.70 2.00 8.10
COL m2 1 PERIM 2.50 2.70 6.75
COL m2 1 PERIM 4.60 2.70 12.42
COL m2 1 PERIM 3.60 2.70 9.72
COL m2 2 PERIM 2.10 2.70 11.34

06.04.03 Acero ( Grado 60 ) kg 20627.00


SOTANO kg 791.00
SEMISOTANO kg 6796.00
PRIMERO kg 6470.00
SEGUNDO kg 6570.00

06.05.00 Vigas
06.05.01 Concreto (f'c = 210 kg/cm2) 4.49
PRIMER PISO
m3 1 0.25 0.20 1.70 0.09
m3 1 0.25 0.20 3.00 0.15
m3 2 0.25 0.20 2.50 0.25
m3 2 0.25 0.20 1.85 0.19
m3 1 0.25 0.20 3.43 0.17
m3 2 0.25 0.20 1.66 0.17
m3 1 0.25 0.40 2.80 0.28
m3 1 0.25 0.40 2.50 0.25
m3 1 0.25 0.40 3.95 0.40
m3 1 0.25 0.40 3.64 0.36
m3 1 0.25 0.40 1.90 0.19
m3 1 0.25 0.40 2.91 0.29
m3 1 0.25 0.50 5.00 0.63
m3 2 0.25 0.40 3.70 0.74
m3 2 0.25 0.20 3.43 0.34
HOJA DE METRADOS - ESTRUCTURA

Obra: VIVIENDA MULTIFAMILIAR - "LOS CEREZOS"

MEDIDAS
CODIGO PARTIDA UNID. N. VECES PARCIAL TOTAL
LARGO ANCHO ALTO

06.05.02 Encofrado 0.00


SEMISOTANO
m2 0.00
m2 0.00
m2 0.00
m2 0.00
m2 0.00
m2 0.00
m2 0.00
m2 0.00
m2 0.00
m2 0.00
m2 0.00
m2 0.00
m2 0.00
m2 0.00
m2 0.00

06.05.03 Acero ( Grado 60 ) 0.00


SEMISOTANO kg
PRIMERO kg
SEGUNDO kg
TERCERO kg
CUARTO kg
QUINTO kg
SEXTO kg
SEPTIMO kg
AZOTEA kg

06.06.00 Losas Aligerada (e=0.20m)


06.06.01 Concreto ( f'c = 210 Kg/cm2) 11.98
PRIMER PISO Fac
m3 1 Area 5.75 0.09 0.50
m3 1 Area 19.90 0.09 1.74
m3 1 Area 8.53 0.09 0.75
m3 1 Area 14.10 0.09 1.23
m3 1 Area 7.80 0.09 0.68
m3 1 Area 12.40 0.09 1.09

SEGUNDO PISO Fac


m3 1 Area 5.75 0.09 0.50
m3 1 Area 19.90 0.09 1.74
m3 1 Area 8.53 0.09 0.75
m3 1 Area 14.10 0.09 1.23
m3 1 Area 7.80 0.09 0.68
m3 1 Area 12.40 0.09 1.09

06.06.02 Encofrados 103.48


SOTANO
m2 1 Area 26.60 26.60
m2 1 Area 25.30 25.30
m2 1 Area 26.60 26.60
SEMISOTANO
m2 1 Area 5.45 5.45
HOJA DE METRADOS - ESTRUCTURA

Obra: VIVIENDA MULTIFAMILIAR - "LOS CEREZOS"

MEDIDAS
CODIGO PARTIDA UNID. N. VECES PARCIAL TOTAL
LARGO ANCHO ALTO
m2 1 Area 10.65 10.65
m2 1 Area 8.88 8.88

06.06.03 Acero kg #NAME?


SEMISOTANO kg 610.00
PRIMERO kg 0.00
SEGUNDO kg 0.00
TERCERO kg #NAME?
CUARTO kg #NAME?
QUINTO kg #NAME?
SEXTO kg #NAME?
SEPTIMO kg #NAME?

06.06.04 Ladrillo hueco ( 0.15x0.30x0.30) 1242


PRIMER PISO
Und. 1 Area 69.00 9.00 621.00
SEGUNDO PISO
Und. 1 Area 69.00 9.00 621.00

06.07.00 Losa Maciza


06.07.01 Concreto (f'c = 210 Kg/cm2) 1.60
CISTERNA
m3 1 Area 8.00 0.20 1.60

06.07.02 Encofrado 8.00


CISTERNA
m2 1 Area 8.00 8.00

06.07.03 Acero Kg 725.00


CISTERNA Kg 123.00
PRIMERO Kg 47.00
SEGUNDO Kg 47.00
TERCERO Kg 47.00
CUARTO Kg 47.00
QUINTO Kg 47.00
SEXTO Kg 47.00
SEPTIMO Kg 47.00
AZOTEA Kg 273.00

06.08.00 Escaleras
06.08.01 Concreto ( f'c = 210 Kg/cm2) 3.42
PRIMER PISO
Cimiento m3 1 1.2 0.5 0.7 0.42
Losa m3 1 2.40 1.20 0.20 0.58
m3 1 1.20 1.20 0.20 0.29
Peldaños m3 15 0.25 0.19 1.20 0.43
SEGUNDO PISO
Cimiento m3 1 1.2 0.5 0.7 0.42
Losa m3 1 2.40 1.20 0.20 0.58
m3 1 1.20 1.20 0.20 0.29
Peldaños m3 15 0.25 0.19 1.20 0.43

06.08.02 Encofrados 107.56


Tramo 1
HOJA DE METRADOS - ESTRUCTURA

Obra: VIVIENDA MULTIFAMILIAR - "LOS CEREZOS"

MEDIDAS
CODIGO PARTIDA UNID. N. VECES PARCIAL TOTAL
LARGO ANCHO ALTO
Cimiento m2 1 1.2 0.5 0.7 2.38
Losa m2 1 2.00 1.20 2.40
m2 1 1.00 1.20 1.20
Peldaños m2 7 0.25 0.19 1.20 1.60
Tramo 2,4,6,8,10,12,14
Losa m2 7 1.20 1.20 0.20 10.08
m2 7 1.30 1.20 0.20 10.92
m2 7 2.50 1.20 0.15 21.00
Peldaños m2 56 0.25 0.19 1.20 12.77
Tramo 3,5,7,9,11,13
Losa m2 6 1.70 1.20 0.20 12.24
m2 6 2.25 1.20 0.15 16.20
m2 6 1.00 1.20 0.20 7.20
Peldaños m2 42 0.25 0.19 1.20 9.58

06.08.03 Acero Kg 1162.00 1162.00

07.00.00 MUROS Y TABIQUES DE ALBAÑILERÍA


07.01.00 Muros de Ladrillo Pandereta
07.01.01 Muros de Soga 74.78

PRIMER NIVEL
m2 1 3.43 2.50 8.58
m2 2 1.85 2.50 9.25
m2 2 2.50 2.50 12.50
m2 1 1.68 2.50 4.20
m2 1 3.00 2.50 7.50
m2 1 3.70 2.50 9.25
m2 1 3.62 2.50 9.05
m2 1 3.95 2.50 9.88
m2 1 1.83 2.50 4.58
2.50 0.00
2.50 0.00
2.50 0.00
PRIMER NIVEL

07.01.02 Muros de Cabeza 0.00

PRIMER NIVEL
HOJA DE METRADOS - ESTRUCTURA

Obra: VIVIENDA MULTIFAMILIAR - "LOS CEREZOS"

MEDIDAS
CODIGO PARTIDA UNID. N. VECES PARCIAL TOTAL
LARGO ANCHO ALTO
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! ZAPATAS
3/4" 1 18 1.20 0.00 0.00 0.00 0.00 21.60
3/4" 1 8 3.50 0.00 0.00 0.00 0.00 28.00
5/8" 1 14 1.00 0.00 0.00 0.00 14.00 0.00
5/8" 1 5 2.70 0.00 0.00 0.00 13.50 0.00
5/8" 1 23 1.00 0.00 0.00 0.00 23.00 0.00
5/8" 1 8 4.60 0.00 0.00 0.00 36.80 0.00
5/8" 1 13 1.00 0.00 0.00 0.00 13.00 0.00
5/8" 1 5 2.50 0.00 0.00 0.00 12.50 0.00
5/8" 1 10 1.45 0.00 0.00 0.00 14.50 0.00
5/8" 1 8 2.00 0.00 0.00 0.00 16.00 0.00
1" 1 70 3.10 0.00 0.00 0.00 0.00 0.00
1" 1 16 8.30 0.00 0.00 0.00 0.00 0.00
1" 1 16 8.70 0.00 0.00 0.00 0.00 0.00
1" 1 21 2.85 0.00 0.00 0.00 0.00 0.00
3/4" 1 27 7.15 0.00 0.00 0.00 0.00 193.05
3/4" 1 27 5.60 0.00 0.00 0.00 0.00 151.20
3/4" 1 42 4.45 0.00 0.00 0.00 0.00 186.90
3/4" 1 14 2.90 0.00 0.00 0.00 0.00 40.60
3/4" 1 18 2.50 0.00 0.00 0.00 0.00 45.00
3/4" 1 4 3.25 0.00 0.00 0.00 0.00 13.00
3/4" 1 17 3.30 0.00 0.00 0.00 0.00 56.10
5/8" 1 42 1.85 0.00 0.00 0.00 77.70 0.00
5/8" 1 10 4.20 0.00 0.00 0.00 42.00 0.00
5/8" 1 10 1.45 0.00 0.00 0.00 14.50 0.00
5/8" 1 8 2.00 0.00 0.00 0.00 16.00 0.00
5/8" 1 23 1.00 0.00 0.00 0.00 23.00 0.00
5/8" 1 8 4.60 0.00 0.00 0.00 36.80 0.00
5/8" 1 10 1.95 0.00 0.00 0.00 19.50 0.00
5/8" 1 10 2.00 0.00 0.00 0.00 20.00 0.00
3/4" 1 7 6.75 0.00 0.00 0.00 0.00 47.25
3/4" 1 37 1.70 0.00 0.00 0.00 0.00 62.90
3/4" 1 8 1.70 0.00 0.00 0.00 0.00 13.60
3/4" 1 8 1.90 0.00 0.00 0.00 0.00 15.20
3/4" 1 14 1.70 0.00 0.00 0.00 0.00 23.80
3/4" 1 7 2.90 0.00 0.00 0.00 0.00 20.30
3/4" 1 7 4.55 0.00 0.00 0.00 0.00 31.85
3/4" 1 8 12.80 0.00 0.00 0.00 0.00 102.40
1" 1 59 1.90 0.00 0.00 0.00 0.00 0.00
A-A 3/8" 1 4 3.50 0.00 14.00 0.00 0.00 0.00
3/8" 1 4 5.40 0.00 21.60 0.00 0.00 0.00
3/8" 1 4 1.30 0.00 5.20 0.00 0.00 0.00
3/8" 1 4 1.50 0.00 6.00 0.00 0.00 0.00
B-B 3/8" 1 4 2.90 0.00 11.60 0.00 0.00 0.00
C-C 3/8" 1 4 2.90 0.00 11.60 0.00 0.00 0.00
D-D 3/8" 1 6 2.30 0.00 13.80 0.00 0.00 0.00
D'-D' 3/8" 1 4 1.50 0.00 6.00 0.00 0.00 0.00
E-E F-F 3/8" 1 4 3.15 0.00 12.60 0.00 0.00 0.00
G-G 3/8" 1 4 2.75 0.00 11.00 0.00 0.00 0.00
3/8" 1 4 2.60 0.00 10.40 0.00 0.00 0.00
H-H 3/8" 1 4 2.25 0.00 9.00 0.00 0.00 0.00
I-I 3/8" 1 4 0.80 0.00 3.20 0.00 0.00 0.00
O-O 3/8" 1 4 4.47 0.00 17.88 0.00 0.00 0.00
DADOS 3/8" 4 9 2.50 0.00 90.00 0.00 0.00 0.00
3/8" 4 9 2.20 0.00 79.20 0.00 0.00 0.00
3/8" 4 6 1.50 0.00 36.00 0.00 0.00 0.00
3/8" 4 6 2.20 0.00 52.80 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 411.88 0.00 392.80 1052.75
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 239 0 629 2353
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
TOTAL(kg) 3221

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Columnas
PRIMER PISO
COL 25X30 1/2" 5 4 3.30 0.00 0.00 66.00 0.00 0.00
COL 25X50 1/2" 7 2 3.30 0.00 0.00 46.20 0.00 0.00
COL 25X50 5/8" 7 4 3.30 0.00 0.00 0.00 92.40 0.00
COL ESQ 1/2" 3 4 3.30 0.00 0.00 39.60 0.00 0.00
COL ESQ 5/8" 3 4 3.30 0.00 0.00 0.00 39.60 0.00
PLACAS 1/2" 2 12 3.30 0.00 0.00 79.20 0.00 0.00
PLACAS 5/8" 2 8 3.30 0.00 0.00 0.00 52.80 0.00
Estribos
COL 25X30 3/8" 5 16.7 1.10 0.00 91.67 0.00 0.00 0.00
COL 25X50 3/8" 7 16.7 1.50 0.00 175.00 0.00 0.00 0.00
COL ESQ 3/8" 3 16.7 1.10 0.00 55.00 0.00 0.00 0.00
COL ESQ 3/8" 3 16.7 1.10 0.00 55.00 0.00 0.00 0.00
PLACAS 3/8" 2 16.7 1.10 0.00 36.67 0.00 0.00 0.00
PLACAS 3/8" 2 16.7 1.10 0.00 36.67 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 450.00 231.00 184.80 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 261 234 296 0
TOTAL(kg) 791
50 25.66667 20.53333
SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Columnas
SEMISOTANO
P1 1" 1 22 2.90 0.00 0.00 0.00 0.00 0.00
P2 1" 1 20 2.90 0.00 0.00 0.00 0.00 0.00
P3 1" 1 4 2.90 0.00 0.00 0.00 0.00 0.00
3/4" 1 12 2.90 0.00 0.00 0.00 0.00 34.80
P4 1" 4 4 2.90 0.00 0.00 0.00 0.00 0.00
3/4" 4 14 2.90 0.00 0.00 0.00 0.00 162.40
P5 3/4" 1 18 2.90 0.00 0.00 0.00 0.00 52.20
P6 1" 1 4 2.90 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.90 0.00 0.00 0.00 0.00 52.20
P7 3/4" 2 4 2.90 0.00 0.00 0.00 0.00 23.20
5/8" 2 12 2.90 0.00 0.00 0.00 69.60 0.00
P8 3/4" 1 4 2.90 0.00 0.00 0.00 0.00 11.60
5/8" 1 12 2.90 0.00 0.00 0.00 34.80 0.00
P9 5/8" 3 6 2.90 0.00 0.00 0.00 52.20 0.00
PLACA 1 3/4" 1 12 2.90 0.00 0.00 0.00 0.00 34.80
3/4" 1 10 2.90 0.00 0.00 0.00 0.00 29.00
3/4" 1 22 2.90 0.00 0.00 0.00 0.00 63.80
3/4" 1 14 2.90 0.00 0.00 0.00 0.00 40.60
1/2" 1 64 2.90 0.00 0.00 185.60 0.00 0.00
1/2" 1 26 2.90 0.00 0.00 75.40 0.00 0.00
1/2" 1 30 2.90 0.00 0.00 87.00 0.00 0.00
PLACA 2 3/4" 1 12 2.90 0.00 0.00 0.00 0.00 34.80
3/8" 1 18 2.90 0.00 52.20 0.00 0.00 0.00
PLACA 3 3/4" 1 18 2.90 0.00 0.00 0.00 0.00 52.20
5/8" 1 14 2.90 0.00 0.00 0.00 40.60 0.00
PLACA 4 3/4" 1 20 2.90 0.00 0.00 0.00 0.00 58.00
3/4" 1 4 2.90 0.00 0.00 0.00 0.00 11.60
PLACA 5 1" 1 12 2.90 0.00 0.00 0.00 0.00 0.00
1" 1 12 2.90 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.90 0.00 0.00 0.00 0.00 52.20
3/4" 1 18 2.90 0.00 0.00 0.00 0.00 52.20
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
5/8" 1 18 2.90 0.00 0.00 0.00 52.20 0.00
PLACA 6 1" 1 7 2.90 0.00 0.00 0.00 0.00 0.00
3/4" 1 37 2.90 0.00 0.00 0.00 0.00 107.30
Pa 3/8" 8 4 4.05 0.00 129.60 0.00 0.00 0.00
Estribos
P1 3/8" 1 42 1.30 0.00 54.60 0.00 0.00 0.00
3/8" 1 42 1.60 0.00 67.20 0.00 0.00 0.00
3/8" 1 21 2.20 0.00 46.20 0.00 0.00 0.00
P2 3/8" 1 84 1.40 0.00 117.60 0.00 0.00 0.00
P3 3/8" 1 42 1.40 0.00 58.80 0.00 0.00 0.00
3/8" 1 42 1.80 0.00 75.60 0.00 0.00 0.00
P4 3/8" 4 84 1.30 0.00 436.80 0.00 0.00 0.00
P5 3/8" 1 42 1.30 0.00 54.60 0.00 0.00 0.00
3/8" 1 21 1.60 0.00 33.60 0.00 0.00 0.00
P6 3/8" 1 42 1.50 0.00 63.00 0.00 0.00 0.00
3/8" 1 42 2.00 0.00 84.00 0.00 0.00 0.00
3/8" 1 42 1.10 0.00 46.20 0.00 0.00 0.00
P7 3/8" 2 42 1.40 0.00 117.60 0.00 0.00 0.00
3/8" 2 21 1.80 0.00 75.60 0.00 0.00 0.00
P8 3/8" 1 42 1.50 0.00 63.00 0.00 0.00 0.00
3/8" 1 21 1.95 0.00 40.95 0.00 0.00 0.00
P9 3/8" 3 42 0.90 0.00 113.40 0.00 0.00 0.00
PLACA 1 3/8" 1 21 1.10 0.00 23.10 0.00 0.00 0.00
3/8" 1 21 1.60 0.00 33.60 0.00 0.00 0.00
3/8" 1 21 1.75 0.00 36.75 0.00 0.00 0.00
3/8" 1 21 2.20 0.00 46.20 0.00 0.00 0.00
3/8" 1 21 1.70 0.00 35.70 0.00 0.00 0.00
3/8" 1 21 1.25 0.00 26.25 0.00 0.00 0.00
3/8" 1 42 1.45 0.00 60.90 0.00 0.00 0.00
3/8" 1 42 1.50 0.00 63.00 0.00 0.00 0.00
3/8" 1 21 1.10 0.00 23.10 0.00 0.00 0.00
5/8" 1 28 7.80 0.00 0.00 0.00 218.40 0.00
5/8" 1 28 3.80 0.00 0.00 0.00 106.40 0.00
5/8" 1 28 4.90 0.00 0.00 0.00 137.20 0.00
PLACA 2 3/8" 2 84 0.95 0.00 159.60 0.00 0.00 0.00
3/8" 2 28 3.10 0.00 173.60 0.00 0.00 0.00
PLACA 3 3/8" 1 126 0.95 0.00 119.70 0.00 0.00 0.00
3/8" 1 28 3.10 0.00 86.80 0.00 0.00 0.00
PLACA 4 3/8" 1 84 0.95 0.00 79.80 0.00 0.00 0.00
3/8" 1 42 1.20 0.00 50.40 0.00 0.00 0.00
3/8" 1 28 1.90 0.00 53.20 0.00 0.00 0.00
PLACA 5 3/8" 1 42 1.30 0.00 54.60 0.00 0.00 0.00
3/8" 1 42 1.30 0.00 54.60 0.00 0.00 0.00
5/8" 1 28 2.70 0.00 0.00 0.00 75.60 0.00
5/8" 1 28 2.70 0.00 0.00 0.00 75.60 0.00
1/2" 1 28 3.00 0.00 0.00 84.00 0.00 0.00
PLACA 6 3/8" 1 84 1.75 0.00 147.00 0.00 0.00 0.00
3/8" 1 42 1.30 0.00 54.60 0.00 0.00 0.00
3/8" 1 42 1.50 0.00 63.00 0.00 0.00 0.00
3/8" 1 42 1.40 0.00 58.80 0.00 0.00 0.00
3/8" 1 21 1.10 0.00 23.10 0.00 0.00 0.00
Pa 1/4" 8 12 0.80 76.80 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 76.80 3257.95 432.00 862.60 872.90
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 20 1890 437 1381 1951
TOTAL(kg) 6796

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Columnas
PRIMERO
P1 1" 1 22 2.75 0.00 0.00 0.00 0.00 0.00
P2 1" 1 20 2.75 0.00 0.00 0.00 0.00 0.00
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
P3 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
P4 1" 4 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 4 14 2.75 0.00 0.00 0.00 0.00 154.00
P5 3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
P6 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
PLACA 1 3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
3/4" 1 10 2.75 0.00 0.00 0.00 0.00 27.50
3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
3/4" 1 14 2.75 0.00 0.00 0.00 0.00 38.50
1/2" 1 64 2.75 0.00 0.00 176.00 0.00 0.00
1/2" 1 26 2.75 0.00 0.00 71.50 0.00 0.00
1/2" 1 30 2.75 0.00 0.00 82.50 0.00 0.00
PLACA 2 3/4" 2 12 2.75 0.00 0.00 0.00 0.00 66.00
3/8" 2 18 2.75 0.00 99.00 0.00 0.00 0.00
PLACA 3 3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
5/8" 1 14 2.75 0.00 0.00 0.00 38.50 0.00
PLACA 4 3/4" 1 20 2.75 0.00 0.00 0.00 0.00 55.00
3/4" 1 4 2.75 0.00 0.00 0.00 0.00 11.00
PLACA 5 1" 1 12 2.75 0.00 0.00 0.00 0.00 0.00
1" 1 12 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
PLACA 6 1" 1 7 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 17 2.75 0.00 0.00 0.00 0.00 46.75
Pa 3/8" 67 4 3.90 0.00 1045.20 0.00 0.00 0.00
Estribos
P1 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
P2 3/8" 1 80 1.40 0.00 112.00 0.00 0.00 0.00
P3 3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 40 1.80 0.00 72.00 0.00 0.00 0.00
P4 3/8" 4 80 1.30 0.00 416.00 0.00 0.00 0.00
P5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
P6 3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 2.00 0.00 80.00 0.00 0.00 0.00
3/8" 1 40 1.10 0.00 44.00 0.00 0.00 0.00
PLACA 1 3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
3/8" 1 20 1.75 0.00 35.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
3/8" 1 20 1.70 0.00 34.00 0.00 0.00 0.00
3/8" 1 20 1.25 0.00 25.00 0.00 0.00 0.00
3/8" 1 40 1.45 0.00 58.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
5/8" 1 28 7.80 0.00 0.00 0.00 218.40 0.00
5/8" 1 28 3.80 0.00 0.00 0.00 106.40 0.00
5/8" 1 28 4.90 0.00 0.00 0.00 137.20 0.00
PLACA 2 3/8" 2 80 0.95 0.00 152.00 0.00 0.00 0.00
3/8" 2 28 3.10 0.00 173.60 0.00 0.00 0.00
PLACA 3 3/8" 1 120 0.95 0.00 114.00 0.00 0.00 0.00
3/8" 1 28 3.10 0.00 86.80 0.00 0.00 0.00
PLACA 4 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 40 1.20 0.00 48.00 0.00 0.00 0.00
3/8" 1 28 1.90 0.00 53.20 0.00 0.00 0.00
PLACA 5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
5/8" 1 28 2.70 0.00 0.00 0.00 75.60 0.00
5/8" 1 28 2.70 0.00 0.00 0.00 75.60 0.00
PLACA 6 3/8" 1 80 1.75 0.00 140.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
Pa 1/4" 67 12 0.80 643.20 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 643.20 3697.80 330.00 651.70 772.75
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 161 2145 334 1043 1728
TOTAL(kg) 6470

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Columnas
SEGUNDO
P1 1" 1 22 2.75 0.00 0.00 0.00 0.00 0.00
P2 1" 1 20 2.75 0.00 0.00 0.00 0.00 0.00
P3 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
P4 1" 4 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 4 14 2.75 0.00 0.00 0.00 0.00 154.00
P5 3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
P6 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
PLACA 1 3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
3/4" 1 10 2.75 0.00 0.00 0.00 0.00 27.50
3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
3/4" 1 14 2.75 0.00 0.00 0.00 0.00 38.50
1/2" 1 64 2.75 0.00 0.00 176.00 0.00 0.00
1/2" 1 26 2.75 0.00 0.00 71.50 0.00 0.00
1/2" 1 30 2.75 0.00 0.00 82.50 0.00 0.00
PLACA 2 3/4" 2 12 2.75 0.00 0.00 0.00 0.00 66.00
3/8" 2 18 2.75 0.00 99.00 0.00 0.00 0.00
PLACA 3 3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
5/8" 1 6 2.75 0.00 0.00 0.00 16.50 0.00
PLACA 4 3/4" 1 20 2.75 0.00 0.00 0.00 0.00 55.00
3/4" 1 4 2.75 0.00 0.00 0.00 0.00 11.00
PLACA 5 1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
PLACA 6 1" 1 7 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 17 2.75 0.00 0.00 0.00 0.00 46.75
Pa 3/8" 62 4 3.90 0.00 967.20 0.00 0.00 0.00
Estribos
P1 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
P2 3/8" 1 80 1.40 0.00 112.00 0.00 0.00 0.00
P3 3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 40 1.80 0.00 72.00 0.00 0.00 0.00
P4 3/8" 4 80 1.30 0.00 416.00 0.00 0.00 0.00
P5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
P6 3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 2.00 0.00 80.00 0.00 0.00 0.00
3/8" 1 40 1.10 0.00 44.00 0.00 0.00 0.00
PLACA 1 3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
3/8" 1 20 1.75 0.00 35.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
3/8" 1 20 1.70 0.00 34.00 0.00 0.00 0.00
3/8" 1 20 1.25 0.00 25.00 0.00 0.00 0.00
3/8" 1 40 1.45 0.00 58.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
5/8" 1 28 7.80 0.00 0.00 0.00 218.40 0.00
5/8" 1 28 3.80 0.00 0.00 0.00 106.40 0.00
5/8" 1 28 4.90 0.00 0.00 0.00 137.20 0.00
PLACA 2 3/8" 2 80 0.95 0.00 152.00 0.00 0.00 0.00
3/8" 2 28 3.10 0.00 173.60 0.00 0.00 0.00
PLACA 3 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 28 1.95 0.00 54.60 0.00 0.00 0.00
PLACA 4 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 40 1.20 0.00 48.00 0.00 0.00 0.00
3/8" 1 28 1.90 0.00 53.20 0.00 0.00 0.00
PLACA 5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
PLACA 6 3/8" 1 80 1.75 0.00 140.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
Pa 1/4" 62 12 0.80 595.20 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 595.20 3677.60 330.00 668.90 756.25
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 149 2134 334 1071 1691
TOTAL(kg) 6570

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Columnas
TERCERO
P1 1" 1 22 2.75 0.00 0.00 0.00 0.00 0.00
P2 1" 1 20 2.75 0.00 0.00 0.00 0.00 0.00
P3 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
P4 1" 4 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 4 14 2.75 0.00 0.00 0.00 0.00 154.00
P5 3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
P6 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
PLACA 1 3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
3/4" 1 10 2.75 0.00 0.00 0.00 0.00 27.50
3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
3/4" 1 14 2.75 0.00 0.00 0.00 0.00 38.50
1/2" 1 64 2.75 0.00 0.00 176.00 0.00 0.00
1/2" 1 26 2.75 0.00 0.00 71.50 0.00 0.00
1/2" 1 30 2.75 0.00 0.00 82.50 0.00 0.00
PLACA 2 3/4" 2 12 2.75 0.00 0.00 0.00 0.00 66.00
3/8" 2 18 2.75 0.00 99.00 0.00 0.00 0.00
PLACA 3 3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
5/8" 1 6 2.75 0.00 0.00 0.00 16.50 0.00
PLACA 4 3/4" 1 20 2.75 0.00 0.00 0.00 0.00 55.00
PLACA 5 1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
PLACA 6 1" 1 7 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 17 2.75 0.00 0.00 0.00 0.00 46.75
Pa 3/8" 62 4 3.90 0.00 967.20 0.00 0.00 0.00
Estribos
P1 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
P2 3/8" 1 80 1.40 0.00 112.00 0.00 0.00 0.00
P3 3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 40 1.80 0.00 72.00 0.00 0.00 0.00
P4 3/8" 4 80 1.30 0.00 416.00 0.00 0.00 0.00
P5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
P6 3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 2.00 0.00 80.00 0.00 0.00 0.00
3/8" 1 40 1.10 0.00 44.00 0.00 0.00 0.00
PLACA 1 3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
3/8" 1 20 1.75 0.00 35.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
3/8" 1 20 1.70 0.00 34.00 0.00 0.00 0.00
3/8" 1 20 1.25 0.00 25.00 0.00 0.00 0.00
3/8" 1 40 1.45 0.00 58.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
5/8" 1 28 7.80 0.00 0.00 0.00 218.40 0.00
5/8" 1 28 3.80 0.00 0.00 0.00 106.40 0.00
5/8" 1 28 4.90 0.00 0.00 0.00 137.20 0.00
PLACA 2 3/8" 2 80 0.95 0.00 152.00 0.00 0.00 0.00
3/8" 2 28 3.10 0.00 173.60 0.00 0.00 0.00
PLACA 3 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 28 1.95 0.00 54.60 0.00 0.00 0.00
PLACA 4 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 40 1.20 0.00 48.00 0.00 0.00 0.00
PLACA 5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
PLACA 6 3/8" 1 80 1.75 0.00 140.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
Pa 1/4" 62 12 0.80 595.20 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 595.20 3624.40 330.00 668.90 745.25
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 149 2103 334 1071 1666
TOTAL(kg) 6514

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Columnas
CUARTO
P1 1" 1 20 2.75 0.00 0.00 0.00 0.00 0.00
P2 1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
P3 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
P4 1" 4 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 4 14 2.75 0.00 0.00 0.00 0.00 154.00
P5 3/4" 1 16 2.75 0.00 0.00 0.00 0.00 44.00
P6 3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
PLACA 1 5/8" 1 12 2.75 0.00 0.00 0.00 33.00 0.00
5/8" 1 10 2.75 0.00 0.00 0.00 27.50 0.00
3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
5/8" 1 14 2.75 0.00 0.00 0.00 38.50 0.00
1/2" 1 64 2.75 0.00 0.00 176.00 0.00 0.00
1/2" 1 26 2.75 0.00 0.00 71.50 0.00 0.00
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
1/2" 1 30 2.75 0.00 0.00 82.50 0.00 0.00
PLACA 2 3/4" 2 12 2.75 0.00 0.00 0.00 0.00 66.00
3/8" 2 18 2.75 0.00 99.00 0.00 0.00 0.00
PLACA 3 3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
5/8" 1 6 2.75 0.00 0.00 0.00 16.50 0.00
PLACA 4 3/4" 1 20 2.75 0.00 0.00 0.00 0.00 55.00
PLACA 5 1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
PLACA 6 1" 1 7 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 17 2.75 0.00 0.00 0.00 0.00 46.75
Pa 3/8" 60 4 3.90 0.00 936.00 0.00 0.00 0.00
Estribos
P1 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
P2 3/8" 1 80 1.40 0.00 112.00 0.00 0.00 0.00
P3 3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 40 1.80 0.00 72.00 0.00 0.00 0.00
P4 3/8" 4 80 1.30 0.00 416.00 0.00 0.00 0.00
P5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
P6 3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 2.00 0.00 80.00 0.00 0.00 0.00
3/8" 1 40 1.10 0.00 44.00 0.00 0.00 0.00
PLACA 1 3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
3/8" 1 20 1.75 0.00 35.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
3/8" 1 20 1.70 0.00 34.00 0.00 0.00 0.00
3/8" 1 20 1.25 0.00 25.00 0.00 0.00 0.00
3/8" 1 40 1.45 0.00 58.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
1/2" 1 28 7.80 0.00 0.00 218.40 0.00 0.00
1/2" 1 28 3.80 0.00 0.00 106.40 0.00 0.00
1/2" 1 28 4.90 0.00 0.00 137.20 0.00 0.00
PLACA 2 3/8" 2 80 0.95 0.00 152.00 0.00 0.00 0.00
3/8" 2 28 3.10 0.00 173.60 0.00 0.00 0.00
PLACA 3 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 28 1.95 0.00 54.60 0.00 0.00 0.00
PLACA 4 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 40 1.20 0.00 48.00 0.00 0.00 0.00
PLACA 5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
PLACA 6 3/8" 1 80 1.75 0.00 140.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
Pa 1/4" 60 12 0.80 576.00 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 576.00 3593.20 792.00 305.90 651.75
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 144 2085 800 490 1457
TOTAL(kg) 6079

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
#REF! Columnas
QUINTO
P1 1" 1 20 2.75 0.00 0.00 0.00 0.00 0.00
P2 1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
P3 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
P4 1" 4 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 4 14 2.75 0.00 0.00 0.00 0.00 154.00
P5 3/4" 1 16 2.75 0.00 0.00 0.00 0.00 44.00
P6 3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
PLACA 1 5/8" 1 12 2.75 0.00 0.00 0.00 33.00 0.00
5/8" 1 10 2.75 0.00 0.00 0.00 27.50 0.00
3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
5/8" 1 14 2.75 0.00 0.00 0.00 38.50 0.00
1/2" 1 64 2.75 0.00 0.00 176.00 0.00 0.00
1/2" 1 26 2.75 0.00 0.00 71.50 0.00 0.00
1/2" 1 30 2.75 0.00 0.00 82.50 0.00 0.00
PLACA 2 3/4" 2 12 2.75 0.00 0.00 0.00 0.00 66.00
3/8" 2 18 2.75 0.00 99.00 0.00 0.00 0.00
PLACA 3 3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
5/8" 1 6 2.75 0.00 0.00 0.00 16.50 0.00
PLACA 4 3/4" 1 20 2.75 0.00 0.00 0.00 0.00 55.00
PLACA 5 1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
PLACA 6 1" 1 7 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 17 2.75 0.00 0.00 0.00 0.00 46.75
Pa 3/8" 60 4 3.90 0.00 936.00 0.00 0.00 0.00
Estribos
P1 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
P2 3/8" 1 80 1.40 0.00 112.00 0.00 0.00 0.00
P3 3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 40 1.80 0.00 72.00 0.00 0.00 0.00
P4 3/8" 4 80 1.30 0.00 416.00 0.00 0.00 0.00
P5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
P6 3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 2.00 0.00 80.00 0.00 0.00 0.00
3/8" 1 40 1.10 0.00 44.00 0.00 0.00 0.00
PLACA 1 3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
3/8" 1 20 1.75 0.00 35.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
3/8" 1 20 1.70 0.00 34.00 0.00 0.00 0.00
3/8" 1 20 1.25 0.00 25.00 0.00 0.00 0.00
3/8" 1 40 1.45 0.00 58.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
1/2" 1 28 7.80 0.00 0.00 218.40 0.00 0.00
1/2" 1 28 3.80 0.00 0.00 106.40 0.00 0.00
1/2" 1 28 4.90 0.00 0.00 137.20 0.00 0.00
PLACA 2 3/8" 2 80 0.95 0.00 152.00 0.00 0.00 0.00
3/8" 2 28 3.10 0.00 173.60 0.00 0.00 0.00
PLACA 3 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 28 1.95 0.00 54.60 0.00 0.00 0.00
PLACA 4 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 40 1.20 0.00 48.00 0.00 0.00 0.00
PLACA 5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
PLACA 6 3/8" 1 80 1.75 0.00 140.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
Pa 1/4" 60 12 0.80 576.00 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 576.00 3593.20 792.00 305.90 651.75
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 144 2085 800 490 1457
TOTAL(kg) 6079

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Columnas
SEXTO
P1 1" 1 20 2.75 0.00 0.00 0.00 0.00 0.00
P2 1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
P3 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
P4 1" 4 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 4 14 2.75 0.00 0.00 0.00 0.00 154.00
P5 3/4" 1 16 2.75 0.00 0.00 0.00 0.00 44.00
P6 3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
PLACA 1 5/8" 1 12 2.75 0.00 0.00 0.00 33.00 0.00
5/8" 1 10 2.75 0.00 0.00 0.00 27.50 0.00
3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
5/8" 1 14 2.75 0.00 0.00 0.00 38.50 0.00
1/2" 1 64 2.75 0.00 0.00 176.00 0.00 0.00
1/2" 1 26 2.75 0.00 0.00 71.50 0.00 0.00
1/2" 1 30 2.75 0.00 0.00 82.50 0.00 0.00
PLACA 2 3/4" 2 12 2.75 0.00 0.00 0.00 0.00 66.00
3/8" 2 18 2.75 0.00 99.00 0.00 0.00 0.00
PLACA 3 3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
5/8" 1 6 2.75 0.00 0.00 0.00 16.50 0.00
PLACA 4 3/4" 1 20 2.75 0.00 0.00 0.00 0.00 55.00
PLACA 5 1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
PLACA 6 1" 1 7 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 17 2.75 0.00 0.00 0.00 0.00 46.75
Pa 3/8" 60 4 3.90 0.00 936.00 0.00 0.00 0.00
Estribos
P1 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
P2 3/8" 1 80 1.40 0.00 112.00 0.00 0.00 0.00
P3 3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 40 1.80 0.00 72.00 0.00 0.00 0.00
P4 3/8" 4 80 1.30 0.00 416.00 0.00 0.00 0.00
P5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
P6 3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 2.00 0.00 80.00 0.00 0.00 0.00
3/8" 1 40 1.10 0.00 44.00 0.00 0.00 0.00
PLACA 1 3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
3/8" 1 20 1.75 0.00 35.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
3/8" 1 20 1.70 0.00 34.00 0.00 0.00 0.00
3/8" 1 20 1.25 0.00 25.00 0.00 0.00 0.00
3/8" 1 40 1.45 0.00 58.00 0.00 0.00 0.00
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
1/2" 1 28 7.80 0.00 0.00 218.40 0.00 0.00
1/2" 1 28 3.80 0.00 0.00 106.40 0.00 0.00
1/2" 1 28 4.90 0.00 0.00 137.20 0.00 0.00
PLACA 2 3/8" 2 80 0.95 0.00 152.00 0.00 0.00 0.00
3/8" 2 28 3.10 0.00 173.60 0.00 0.00 0.00
PLACA 3 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 28 1.95 0.00 54.60 0.00 0.00 0.00
PLACA 4 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 40 1.20 0.00 48.00 0.00 0.00 0.00
PLACA 5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
PLACA 6 3/8" 1 80 1.75 0.00 140.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
Pa 1/4" 60 12 0.80 576.00 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 576.00 3593.20 792.00 305.90 651.75
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 144 2085 800 490 1457
TOTAL(kg) 6079

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Columnas
SEPTIMO
P1 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 16 2.75 0.00 0.00 0.00 0.00 44.00
P2 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 14 2.75 0.00 0.00 0.00 0.00 38.50
P3 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
P4 1" 4 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 4 14 2.75 0.00 0.00 0.00 0.00 154.00
P5 3/4" 1 16 2.75 0.00 0.00 0.00 0.00 44.00
P6 3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
PLACA 1 5/8" 1 12 2.75 0.00 0.00 0.00 33.00 0.00
5/8" 1 10 2.75 0.00 0.00 0.00 27.50 0.00
3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
5/8" 1 14 2.75 0.00 0.00 0.00 38.50 0.00
1/2" 1 64 2.75 0.00 0.00 176.00 0.00 0.00
1/2" 1 26 2.75 0.00 0.00 71.50 0.00 0.00
1/2" 1 30 2.75 0.00 0.00 82.50 0.00 0.00
PLACA 2 3/4" 2 12 2.75 0.00 0.00 0.00 0.00 66.00
3/8" 2 18 2.75 0.00 99.00 0.00 0.00 0.00
PLACA 3 3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
5/8" 1 6 2.75 0.00 0.00 0.00 16.50 0.00
PLACA 4 3/4" 1 20 2.75 0.00 0.00 0.00 0.00 55.00
PLACA 5 1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
PLACA 6 1" 1 7 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 17 2.75 0.00 0.00 0.00 0.00 46.75
Pa 3/8" 60 4 3.90 0.00 936.00 0.00 0.00 0.00
Estribos
P1 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
P2 3/8" 1 80 1.40 0.00 112.00 0.00 0.00 0.00
P3 3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 40 1.80 0.00 72.00 0.00 0.00 0.00
P4 3/8" 4 80 1.30 0.00 416.00 0.00 0.00 0.00
P5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
P6 3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 2.00 0.00 80.00 0.00 0.00 0.00
3/8" 1 40 1.10 0.00 44.00 0.00 0.00 0.00
PLACA 1 3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
3/8" 1 20 1.75 0.00 35.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
3/8" 1 20 1.70 0.00 34.00 0.00 0.00 0.00
3/8" 1 20 1.25 0.00 25.00 0.00 0.00 0.00
3/8" 1 40 1.45 0.00 58.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
1/2" 1 28 7.80 0.00 0.00 218.40 0.00 0.00
1/2" 1 28 3.80 0.00 0.00 106.40 0.00 0.00
1/2" 1 28 4.90 0.00 0.00 137.20 0.00 0.00
PLACA 2 3/8" 2 80 0.95 0.00 152.00 0.00 0.00 0.00
3/8" 2 28 3.10 0.00 173.60 0.00 0.00 0.00
PLACA 3 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 28 1.95 0.00 54.60 0.00 0.00 0.00
PLACA 4 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 40 1.20 0.00 48.00 0.00 0.00 0.00
PLACA 5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
PLACA 6 3/8" 1 80 1.75 0.00 140.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
Pa 1/4" 60 12 0.80 576.00 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 576.00 3593.20 792.00 305.90 734.25
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 144 2085 800 490 1642
TOTAL(kg) 5937

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Columnas
OCTAVO
P1 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 16 2.75 0.00 0.00 0.00 0.00 44.00
P2 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 14 2.75 0.00 0.00 0.00 0.00 38.50
P3 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
P4 1" 4 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 4 14 2.75 0.00 0.00 0.00 0.00 154.00
P5 3/4" 1 16 2.75 0.00 0.00 0.00 0.00 44.00
P6 3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
PLACA 1 5/8" 1 12 2.75 0.00 0.00 0.00 33.00 0.00
5/8" 1 10 2.75 0.00 0.00 0.00 27.50 0.00
3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
5/8" 1 14 2.75 0.00 0.00 0.00 38.50 0.00
1/2" 1 64 2.75 0.00 0.00 176.00 0.00 0.00
1/2" 1 26 2.75 0.00 0.00 71.50 0.00 0.00
1/2" 1 30 2.75 0.00 0.00 82.50 0.00 0.00
PLACA 2 3/4" 2 12 2.75 0.00 0.00 0.00 0.00 66.00
3/8" 2 18 2.75 0.00 99.00 0.00 0.00 0.00
PLACA 3 3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
5/8" 1 6 2.75 0.00 0.00 0.00 16.50 0.00
PLACA 4 3/4" 1 20 2.75 0.00 0.00 0.00 0.00 55.00
PLACA 5 1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
PLACA 6 1" 1 7 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 17 2.75 0.00 0.00 0.00 0.00 46.75
Pa 3/8" 60 4 3.90 0.00 936.00 0.00 0.00 0.00
Estribos
P1 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
P2 3/8" 1 80 1.40 0.00 112.00 0.00 0.00 0.00
P3 3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 40 1.80 0.00 72.00 0.00 0.00 0.00
P4 3/8" 4 80 1.30 0.00 416.00 0.00 0.00 0.00
P5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
P6 3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 2.00 0.00 80.00 0.00 0.00 0.00
3/8" 1 40 1.10 0.00 44.00 0.00 0.00 0.00
PLACA 1 3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
3/8" 1 20 1.75 0.00 35.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
3/8" 1 20 1.70 0.00 34.00 0.00 0.00 0.00
3/8" 1 20 1.25 0.00 25.00 0.00 0.00 0.00
3/8" 1 40 1.45 0.00 58.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
1/2" 1 28 7.80 0.00 0.00 218.40 0.00 0.00
1/2" 1 28 3.80 0.00 0.00 106.40 0.00 0.00
1/2" 1 28 4.90 0.00 0.00 137.20 0.00 0.00
PLACA 2 3/8" 2 80 0.95 0.00 152.00 0.00 0.00 0.00
3/8" 2 28 3.10 0.00 173.60 0.00 0.00 0.00
PLACA 3 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 28 1.95 0.00 54.60 0.00 0.00 0.00
PLACA 4 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 40 1.20 0.00 48.00 0.00 0.00 0.00
PLACA 5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
PLACA 6 3/8" 1 80 1.75 0.00 140.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
Pa 1/4" 60 12 0.80 576.00 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 576.00 3593.20 792.00 305.90 734.25
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 144 2085 800 490 1642
TOTAL(kg) 5937

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG.
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Columnas
NOVENO
P1 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 16 2.75 0.00 0.00 0.00 0.00 44.00
P2 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 14 2.75 0.00 0.00 0.00 0.00 38.50
P3 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
P4 1" 4 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 4 14 2.75 0.00 0.00 0.00 0.00 154.00
P5 3/4" 1 16 2.75 0.00 0.00 0.00 0.00 44.00
P6 3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
PLACA 1 5/8" 1 12 2.75 0.00 0.00 0.00 33.00 0.00
5/8" 1 10 2.75 0.00 0.00 0.00 27.50 0.00
3/4" 1 22 2.75 0.00 0.00 0.00 0.00 60.50
5/8" 1 14 2.75 0.00 0.00 0.00 38.50 0.00
1/2" 1 64 2.75 0.00 0.00 176.00 0.00 0.00
1/2" 1 26 2.75 0.00 0.00 71.50 0.00 0.00
1/2" 1 30 2.75 0.00 0.00 82.50 0.00 0.00
PLACA 2 3/4" 2 12 2.75 0.00 0.00 0.00 0.00 66.00
3/8" 2 18 2.75 0.00 99.00 0.00 0.00 0.00
PLACA 3 3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
5/8" 1 6 2.75 0.00 0.00 0.00 16.50 0.00
PLACA 4 3/4" 1 20 2.75 0.00 0.00 0.00 0.00 55.00
PLACA 5 1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
1" 1 18 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
PLACA 6 1" 1 7 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 17 2.75 0.00 0.00 0.00 0.00 46.75
Pa 3/8" 60 4 3.90 0.00 936.00 0.00 0.00 0.00
Estribos
P1 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
P2 3/8" 1 80 1.40 0.00 112.00 0.00 0.00 0.00
P3 3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 40 1.80 0.00 72.00 0.00 0.00 0.00
P4 3/8" 4 80 1.30 0.00 416.00 0.00 0.00 0.00
P5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
P6 3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 2.00 0.00 80.00 0.00 0.00 0.00
3/8" 1 40 1.10 0.00 44.00 0.00 0.00 0.00
PLACA 1 3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
3/8" 1 20 1.60 0.00 32.00 0.00 0.00 0.00
3/8" 1 20 1.75 0.00 35.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
3/8" 1 20 1.70 0.00 34.00 0.00 0.00 0.00
3/8" 1 20 1.25 0.00 25.00 0.00 0.00 0.00
3/8" 1 40 1.45 0.00 58.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
1/2" 1 28 7.80 0.00 0.00 218.40 0.00 0.00
1/2" 1 28 3.80 0.00 0.00 106.40 0.00 0.00
1/2" 1 28 4.90 0.00 0.00 137.20 0.00 0.00
PLACA 2 3/8" 2 80 0.95 0.00 152.00 0.00 0.00 0.00
3/8" 2 28 3.10 0.00 173.60 0.00 0.00 0.00
PLACA 3 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 28 1.95 0.00 54.60 0.00 0.00 0.00
PLACA 4 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 40 1.20 0.00 48.00 0.00 0.00 0.00
PLACA 5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
PLACA 6 3/8" 1 80 1.75 0.00 140.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.50 0.00 60.00 0.00 0.00 0.00
3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
Pa 1/4" 60 12 0.80 576.00 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 576.00 3593.20 792.00 305.90 734.25
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 144 2085 800 490 1642
TOTAL(kg) 5937

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Columnas
AZOTEA
P1 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 16 2.75 0.00 0.00 0.00 0.00 44.00
P2 1" 1 4 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 14 2.75 0.00 0.00 0.00 0.00 38.50
P12 5/8" 1 6 3.15 0.00 0.00 0.00 18.90 0.00
P13 5/8" 1 8 3.15 0.00 0.00 0.00 25.20 0.00
P14 5/8" 1 10 3.15 0.00 0.00 0.00 31.50 0.00
PLACA 3 3/4" 1 12 2.75 0.00 0.00 0.00 0.00 33.00
5/8" 1 6 2.75 0.00 0.00 0.00 16.50 0.00
PLACA 5 1" 1 12 2.75 0.00 0.00 0.00 0.00 0.00
1" 1 12 2.75 0.00 0.00 0.00 0.00 0.00
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
3/4" 1 18 2.75 0.00 0.00 0.00 0.00 49.50
PLACA 6 3/4" 1 14 2.75 0.00 0.00 0.00 0.00 38.50
Pa 3/8" 15 4 3.90 0.00 234.00 0.00 0.00 0.00
Estribos
P1 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.60 0.00 64.00 0.00 0.00 0.00
3/8" 1 20 2.20 0.00 44.00 0.00 0.00 0.00
P2 3/8" 1 80 1.40 0.00 112.00 0.00 0.00 0.00
P12 3/8" 1 40 0.90 0.00 36.00 0.00 0.00 0.00
P13 3/8" 2 40 1.35 0.00 108.00 0.00 0.00 0.00
P14 3/8" 2 40 1.30 0.00 104.00 0.00 0.00 0.00
PLACA 3 3/8" 1 80 0.95 0.00 76.00 0.00 0.00 0.00
3/8" 1 28 1.95 0.00 54.60 0.00 0.00 0.00
PLACA 5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
5/8" 1 28 3.40 0.00 0.00 0.00 95.20 0.00
PLACA 6 3/8" 1 80 1.75 0.00 140.00 0.00 0.00 0.00
3/8" 1 40 1.40 0.00 56.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
Pa 1/4" 15 12 0.80 144.00 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 144.00 1206.60 0.00 282.50 253.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 36 700 0 452 566
TOTAL(kg) 2104

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Columnas
TANQUE ELEVADO
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
PLACA 5 1" 1 12 2.75 0.00 0.00 0.00 0.00 0.00
PLACA 6 3/4" 1 14 2.75 0.00 0.00 0.00 0.00 38.50
E'-E' 3/8" 1 10 3.70 0.00 37.00 0.00 0.00 0.00
G'-G' 3/8" 1 18 3.70 0.00 66.60 0.00 0.00 0.00
F'-F' 3/8" 2 28 2.70 0.00 151.20 0.00 0.00 0.00
Estribos
PLACA 5 3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
PLACA 6 3/8" 1 80 1.75 0.00 140.00 0.00 0.00 0.00
3/8" 1 40 1.30 0.00 52.00 0.00 0.00 0.00
3/8" 1 20 1.10 0.00 22.00 0.00 0.00 0.00
E'-E' 3/8" 1 32 1.40 0.00 44.80 0.00 0.00 0.00
G'-G' 3/8" 1 32 2.60 0.00 83.20 0.00 0.00 0.00
F'-F' 3/8" 2 22 3.65 0.00 160.60 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 809.40 0.00 0.00 38.50
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 470 0 0 87
TOTAL(kg) 689

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Vigas
SEMISOTANO
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 0.00 0.00 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 0 0 0 0
TOTAL(kg) 0

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Losa Aligerada
SOTANO
1--3 3/8" 1 18 2.65 0.00 47.70 0.00 0.00 0.00
1/2" 1 18 7.50 0.00 0.00 135.00 0.00 0.00
3/8" 1 18 3.05 0.00 54.90 0.00 0.00 0.00
3/8" 1 18 4.25 0.00 76.50 0.00 0.00 0.00
3--5 3/8" 1 18 1.20 0.00 21.60 0.00 0.00 0.00
1/2" 1 18 3.95 0.00 0.00 71.10 0.00 0.00
1/2" 1 18 7.00 0.00 0.00 126.00 0.00 0.00
3/8" 1 18 4.25 0.00 76.50 0.00 0.00 0.00
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
3/8" 1 18 3.05 0.00 54.90 0.00 0.00 0.00
Acero Temperatura FACTOR
1/4" 4.1 79.00 1 323.90 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 323.90 332.10 332.10 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 81 193 336 0 0
TOTAL(kg) 610

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Losa Aligerada
SEMISOTANO
1--3 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
3--5 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
Acero Temperatura FACTOR
1/4" 4.1 1 0.00 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 0.00 0.00 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 0 0 0 0
TOTAL(kg) 0

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
06.06.03 Losa Aligerada
PRIMERO
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
Acero Temperatura FACTOR
1/4" 4.1 1 0.00 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 0.00 0.00 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 0 0 0 0
TOTAL(kg) 0

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
06.06.03 Losa Aligerada
SEGUNDO
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
Acero Temperatura FACTOR
1/4" 4.1 1 0.00 0.00 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 0.00 0.00 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 0 0 0 0
TOTAL(kg) 0
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Losa Maciza
CISTERNA
3/8" 1 21 2.25 0.00 47.25 0.00 0.00 0.00
3/8" 1 21 2.65 0.00 55.65 0.00 0.00 0.00
3/8" 1 12 4.30 0.00 51.60 0.00 0.00 0.00
3/8" 1 12 4.70 0.00 56.40 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 210.90 0.00 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 123 0 0 0
TOTAL(kg) 123

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
06.07.03 Losa Maciza
PRIMERO
3/8" 1 45 1.45 0.00 65.25 0.00 0.00 0.00
3/8" 1 8 1.9 0.00 15.20 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 80.45 0.00 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 47 0 0 0
TOTAL(kg) 47

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
06.07.03 Losa Maciza
SEGUNDO
3/8" 1 45 1.45 0.00 65.25 0.00 0.00 0.00
3/8" 1 8 1.9 0.00 15.20 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 80.45 0.00 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 47 0 0 0
TOTAL(kg) 47

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
06.07.03 Losa Maciza
TERCERO
3/8" 1 45 1.45 0.00 65.25 0.00 0.00 0.00
3/8" 1 8 1.9 0.00 15.20 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 80.45 0.00 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 47 0 0 0
TOTAL(kg) 47

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
06.07.03 Losa Maciza
CUARTO
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
3/8" 1 45 1.45 0.00 65.25 0.00 0.00 0.00
3/8" 1 8 1.9 0.00 15.20 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 80.45 0.00 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 47 0 0 0
TOTAL(kg) 47

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
06.07.03 Losa Maciza
QUINTO
3/8" 1 45 1.45 0.00 65.25 0.00 0.00 0.00
3/8" 1 8 1.9 0.00 15.20 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 80.45 0.00 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 47 0 0 0
TOTAL(kg) 47

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
06.07.03 Losa Maciza
SEXTO
3/8" 1 45 1.45 0.00 65.25 0.00 0.00 0.00
3/8" 1 8 1.9 0.00 15.20 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 80.45 0.00 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 47 0 0 0
TOTAL(kg) 47

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
06.07.03 Losa Maciza
SEPTIMO
3/8" 1 45 1.45 0.00 65.25 0.00 0.00 0.00
3/8" 1 8 1.9 0.00 15.20 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 80.45 0.00 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 47 0 0 0
TOTAL(kg) 47

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
06.07.03 Losa Maciza
AZOTEA
3/8" 1 23 5 0.00 115.00 0.00 0.00 0.00
3/8" 1 23 5.4 0.00 124.20 0.00 0.00 0.00
3/8" 1 13 4.8 0.00 62.40 0.00 0.00 0.00
3/8" 1 13 5.2 0.00 67.60 0.00 0.00 0.00
3/8" 1 22 2.1 0.00 46.20 0.00 0.00 0.00
3/8" 1 22 2.5 0.00 55.00 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 470.40 0.00 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 273 0 0 0
TOTAL(kg) 273

SUB-TOTAL
CODIGO PARTIDA Φ N.E.E. N. BARRAS LONG. LONGITUD EN METROS
1/4" 3/8" 1/2" 5/8" 3/4"
#REF! Escaleras
TRAMO 1 3/8" 1 7 4.1 0.00 28.70 0.00 0.00 0.00
ACERO - ESTRUCTURA

Obra: #REF!

FORMULA 01
3/8" 1 7 2.35 0.00 16.45 0.00 0.00 0.00
3/8" 1 7 1.70 0.00 11.90 0.00 0.00 0.00
3/8" 1 17 1.60 0.00 27.20 0.00 0.00 0.00
TRAMO 2,4,6,8,10,12,14 3/8" 7 7 1.95 0.00 95.55 0.00 0.00 0.00
3/8" 7 7 4.50 0.00 220.50 0.00 0.00 0.00
3/8" 7 7 4.60 0.00 225.40 0.00 0.00 0.00
3/8" 7 7 2.00 0.00 98.00 0.00 0.00 0.00
3/8" 7 36 1.60 0.00 403.20 0.00 0.00 0.00
TRAMO 3,5,7,9,11,13 3/8" 6 7 2.45 0.00 102.90 0.00 0.00 0.00
3/8" 6 7 4.70 0.00 197.40 0.00 0.00 0.00
3/8" 6 7 4.00 0.00 168.00 0.00 0.00 0.00
3/8" 6 7 1.70 0.00 71.40 0.00 0.00 0.00
3/8" 6 35 1.60 0.00 336.00 0.00 0.00 0.00
SUB-TOTAL(m) 0.00 2002.60 0.00 0.00 0.00
FATOR 0.25 0.58 1.01 1.60 2.24
SUB-TOTAL(kg) 0 1162 0 0 0
TOTAL(kg) 1162
HOJA DE METRADOS - ARQUITECTURA

Obra: #REF!

FORMULA 02

MEDIDAS
CODIGO PARTIDA UNIDAD No. VECES PARCIAL TOTAL
LARGO ANCHO ALTO
08.00.00 Revoques y Enlucidos

08.01.00 Tarrajeo Rayado 2375.49


Primer Nivel
SSHH m2 1 Per 9.20 1.60 14.72
P-1 m2 -1 Per 0.80 1.60 -1.28

Segundo al Onceavo Nivel


SSHH m2 10 Per 8.70 1.60 139.20
P-1 m2 -10 Per 0.80 1.60 -12.80
SSHH m2 10 Per 9.20 1.60 147.20
P-1 m2 -10 Per 0.80 1.60 -12.80
SSHH m2 10 Per 8.80 1.60 140.80
P-1 m2 -10 Per 0.80 1.60 -12.80
SSHH m2 10 Per 9.54 1.60 152.64
P-1 m2 -10 Per 0.80 1.60 -12.80
SSHH m2 10 Per 8.80 1.60 140.80
P-1 m2 -10 Per 0.80 1.60 -12.80
COCINA m2 10 Per 15.69 1.20 188.28
P-11 m2 -10 Per 1.00 1.20 -12.00
P-1 m2 -10 Per 0.80 1.20 -9.60
V-10 m2 -10 Per 0.65 0.30 -1.95
LAVANDERIA m2 10 Per 1.20 1.20 14.40
V-11 m2 -10 Per 0.82 0.30 -2.46
SSHH m2 10 Per 7.20 1.60 115.20
P-1 m2 -10 Per 0.80 1.60 -12.80
SSHH m2 10 Per 7.20 1.20 86.40
P-1 m2 -10 Per 0.80 1.60 -12.80
COCINA m2 10 Per 14.40 1.20 172.80
P-11 m2 -10 Per 1.00 1.20 -12.00
P-13 m2 -10 Per 0.85 1.20 -10.20
V-13 m2 -10 Per 1.50 0.30 -4.50
LAVANDERIA m2 10 Per 2.31 1.20 27.72
V-13 m2 -10 Per 1.50 0.30 -4.50
SSHH m2 10 Per 6.50 1.60 104.00
P-1 m2 -10 Per 0.80 1.60 -12.80
SSHH m2 10 Per 8.63 1.60 138.08
P-1 m2 -10 Per 0.80 1.60 -12.80
V-20 m2 -10 Per 0.99 0.30 -2.97
SSHH m2 10 Per 8.63 1.60 138.08
P-1 m2 -10 Per 0.80 1.60 -12.80
V-20 m2 -10 Per 0.99 0.30 -2.97
SSHH m2 10 Per 6.50 1.60 104.00
P-1 m2 -10 Per 0.80 1.60 -12.80
COCINA m2 10 Per 14.55 1.20 174.60
P-11 m2 -10 Per 1.00 1.20 -12.00
P-13 m2 -10 Per 0.85 1.20 -10.20
V-23 m2 -10 Per 1.55 0.30 -4.65
LAVANDERIA m2 10 Per 2.15 1.20 25.80
V-23 m2 -10 Per 1.55 0.30 -4.65
SSHH m2 10 Per 6.89 1.60 110.24
P-1 m2 -10 Per 0.80 1.60 -12.80
SSHH m2 10 Per 7.60 1.60 121.60
P-1 m2 -10 Per 0.80 1.60 -12.80
COCINA m2 10 Per 14.66 1.20 175.92
P-11 m2 -10 Per 1.00 1.20 -12.00
P-13 m2 -10 Per 0.85 1.20 -10.20
V-24 m2 -10 Per 1.65 0.30 -4.95
LAVANDERIA m2 10 Per 2.40 1.20 28.80
V-24 m2 -10 Per 1.65 0.30 -4.95
SSHH m2 10 Per 6.50 1.60 104.00
P-1 m2 -10 Per 0.80 1.60 -12.80
SSHH m2 10 Per 8.14 1.60 130.24
P-1 m2 -10 Per 0.80 1.60 -12.80

08.02.00 Tarrajeo en Interiores (Mortero 1:5 Cemento puzolanico-Arena fina) 13392.38

Semisotano
HOJA DE METRADOS - ARQUITECTURA

Obra: #REF!

FORMULA 02

MEDIDAS
CODIGO PARTIDA UNIDAD No. VECES PARCIAL TOTAL
LARGO ANCHO ALTO
m2 1 Per 315.18 2.35 740.67
PL m2 5 Per 4.10 2.35 48.18
PL m2 1 Per 3.21 2.35 7.54
PL m2 1 Per 4.90 2.35 11.52
PL m2 1 Per 2.40 2.35 5.64
PL m2 1 Per 0.80 2.35 1.88

Primer Nivel
m2 1 Per 212.83 2.70 574.64
PL m2 5 Per 4.10 2.70 55.35
PL m2 1 Per 3.21 2.70 8.67
PL m2 1 Per 4.90 2.70 13.23
PL m2 2 Per 2.40 2.70 12.96
PL m2 1 Per 5.60 2.70 15.12
P-6 m2 -1 Per 6.00 2.70 -16.20

Segundo al Onceavo Nivel


m2 10 Per 518.80 2.50 12970.00
P-1 m2 -10 Per 0.80 2.45 -19.60
M-1 m2 -10 Per 2.00 2.40 -48.00
V-7 m2 -10 Per 1.17 1.25 -14.63
P-1 m2 -10 Per 0.80 2.45 -19.60
V-6 m2 -10 Per 2.90 1.25 -36.25
P-11 m2 -10 Per 1.00 2.45 -24.50
P-1 m2 -10 Per 0.80 2.45 -19.60
V-3 m2 -10 Per 1.30 1.35 -17.55
V-4 m2 -10 Per 1.35 1.35 -18.23
M-2 m2 -10 Per 2.00 2.55 -51.00
V-1 m2 -10 Per 0.60 0.60 -3.60
V-2 m2 -10 Per 0.60 0.40 -2.40
M-3 m2 -10 Per 2.92 2.55 -74.46
P-1 m2 -10 Per 0.80 2.45 -19.60
V-14 m2 -10 Per 3.01 1.25 -37.63
P-1 m2 -10 Per 0.80 2.45 -19.60
V-19 m2 -10 Per 1.67 1.25 -20.88
V-18 m2 -10 Per 1.45 1.25 -18.13
V-16 m2 -20 Per 0.80 0.50 -8.00
P-1 m2 -10 Per 0.80 2.45 -19.60
P-11 m2 -10 Per 1.00 2.45 -24.50
V-9 m2 -20 Per 0.65 0.50 -6.50
P-1 m2 -80 Per 0.80 2.45 -156.80
V-11 m2 -10 Per 0.82 1.25 -10.25
V-12 m2 -10 Per 1.28 1.25 -16.00
V-18 m2 -10 Per 1.45 1.25 -18.13
V-22 m2 -10 Per 1.15 1.25 -14.38
V-19 m2 -10 Per 1.67 1.25 -20.88
P-1 m2 -10 Per 0.80 2.45 -19.60
V-21 m2 -10 Per 1.17 0.50 -5.85
V-16 m2 -40 Per 0.80 0.50 -16.00
P-1 m2 -20 Per 0.80 2.45 -39.20
P-11 m2 -20 Per 1.00 2.45 -49.00
V-21 m2 -10 Per 1.17 0.50 -5.85
V-19 m2 -10 Per 1.67 1.25 -20.88
P-1 m2 -10 Per 0.80 2.45 -19.60
V-17 m2 -10 Per 2.50 1.25 -31.25
P-1 m2 -10 Per 0.80 2.45 -19.60
M-5 m2 -10 Per 2.43 2.55 -61.97
V-2 m2 -20 Per 0.60 0.40 -4.80
V-1 m2 -10 Per 0.60 0.60 -3.60
M-4 m2 -10 Per 1.90 2.55 -48.45
P-1 m2 -10 Per 0.80 2.45 -19.60
V-15 m2 -10 Per 2.79 1.25 -34.88

Azotea
m2 1 Per 42.00 2.50 105.00
V-1 m2 -2 Per 0.60 0.60 -0.72
V-2 m2 -3 Per 0.60 0.40 -0.72
HOJA DE METRADOS - ARQUITECTURA

Obra: #REF!

FORMULA 02

MEDIDAS
CODIGO PARTIDA UNIDAD No. VECES PARCIAL TOTAL
LARGO ANCHO ALTO

08.03.00 Tarrajeo en Exteriores (Mortero 1:5 Cemento puzolanico-Arena fina) 2702.10


Semisotano
m2 1 Per 68.04 0.92 62.60
FRIZOS m2 -1 Per 68.04 0.25 -17.01

Primer Nivel
m2 1 Per 55.43 2.70 149.66
P-6 m2 -1 Per 6.00 2.45 -14.70
V-4 m2 -1 Per 1.35 1.35 -1.82
V-2 m2 -1 Per 1.6 1.15 -1.84
FRIZOS m2 1 Per 55.43 0.25 13.86

Segundo al Onceavo Nivel


m2 10 Per 118.28 2.50 2957.00
M-1 m2 -10 Per 2.00 2.40 -48.00
V-7 m2 -10 Per 1.17 1.25 -14.63
V-6 m2 -10 Per 2.90 1.25 -36.25
V-5 m2 -10 Per 1.35 0.50 -6.75
V-3 m2 -10 Per 1.30 1.35 -17.55
V-4 m2 -10 Per 1.35 1.35 -18.23
M-2 m2 -10 Per 2.00 2.55 -51.00
V-2 m2 -10 Per 0.60 0.40 -2.40
M-3 m2 -10 Per 2.92 2.55 -74.46
V-14 m2 -10 Per 3.01 1.25 -37.63
V-15 m2 -10 Per 2.79 1.25 -34.88
M-4 m2 -10 Per 1.90 2.55 -48.45
V-2 m2 -10 Per 0.60 0.40 -2.40
V-2 m2 -10 Per 0.6 0.4 -2.40
M-5 m2 -10 Per 2.43 2.55 -61.97
V-17 m2 -10 Per 2.5 1.25 -31.25
V-1 m2 -10 Per 0.57 0.6 -3.42
V-9 m2 -10 Per 0.65 0.5 -3.25
P-1 m2 -10 Per 0.8 2.45 -19.60
V-10 m2 -10 Per 0.65 1.25 -8.13
V-11 m2 -10 Per 0.82 1.25 -10.25
P-1 m2 -10 Per 0.8 2.45 -19.60
V-12 m2 -10 Per 1.28 1.25 -16.00
P-1 m2 -10 Per 0.8 2.45 -19.60
V-13 m2 -10 Per 1.5 1.25 -18.75
P-13 m2 -30 Per 0.85 2.45 -62.48
V-18 m2 -20 Per 1.45 1.25 -36.25
V-19 m2 -30 Per 1.67 1.25 -62.63
V-21 m2 -20 Per 1.17 0.5 -11.70
V-23 m2 -10 Per 1.55 1.25 -19.38
P-1 m2 -20 Per 0.8 2.45 -39.20
V-22 m2 -10 Per 1.15 1.25 -14.38
V-24 m2 -10 Per 1.65 1.25 -20.63
FRIZOS m2 10 Per 118.28 0.25 295.70

Azotea
m2 1 Per 48.30 2.50 120.75
V-2 m2 -3 Per 0.60 0.40 -0.72
FRIZOS m2 1 Per 48.30 0.25 12.08

08.04.00 Vestidura de Derrames 2423.80

Primer Nivel
V-4 ml 1 Per 1.35 1.35 5.40
V-2 ml 1 Per 0.6 0.4 2.00
V-? ml 1 Per 0.90 1.80
V-1 ml 2 Per 0.60 0.60 4.80

Segundo al Onceavo Nivel


M-1 ml 10 Per 2.00 2.40 88.00
V-7 ml 10 Per 1.17 1.25 48.40
V-6 ml 10 Per 2.90 1.25 83.00
V-5 ml 10 Per 1.35 0.50 37.00
HOJA DE METRADOS - ARQUITECTURA

Obra: #REF!

FORMULA 02

MEDIDAS
CODIGO PARTIDA UNIDAD No. VECES PARCIAL TOTAL
LARGO ANCHO ALTO
V-3 ml 10 Per 1.30 1.35 53.00
V-4 ml 10 Per 1.35 1.35 54.00
M-2 ml 10 Per 2.00 2.55 91.00
V-2 ml 10 Per 0.60 0.40 20.00
M-3 ml 10 Per 2.92 2.55 109.40
V-14 ml 10 Per 3.01 1.25 85.20
V-15 ml 10 Per 2.79 1.25 80.80
M-4 ml 10 Per 1.90 2.55 89.00
V-2 ml 10 Per 0.60 0.40 20.00
V-2 ml 10 Per 0.6 0.4 20.00
M-5 ml 10 Per 2.43 2.55 99.60
V-17 ml 10 Per 2.5 1.25 75.00
V-1 ml 10 Per 0.57 0.6 23.40
V-9 ml 10 Per 0.65 0.5 23.00
V-5 ml 10 Per 1.35 0.5 37.00
V-8 ml 10 Per 1.2 0.5 34.00
V-10 ml 10 Per 0.65 1.25 38.00
V-11 ml 10 Per 0.82 1.25 41.40
V-12 ml 10 Per 1.28 1.25 50.60
V-13 ml 10 Per 1.5 1.25 55.00
V-18 ml 10 Per 1.45 1.25 54.00
V-19 ml 10 Per 1.67 1.25 58.40
V-9 ml 20 Per 0.65 0.5 46.00
V-16 ml 90 Per 0.8 0.5 234.00
V-20 ml 20 Per 0.99 1.25 89.60
V-1 ml 20 Per 0.6 0.6 48.00
V-25 ml 10 Per 0.68 5 113.60
V-19 ml 10 Per 1.67 1.25 58.40
V-21 ml 10 Per 1.17 0.5 33.40
V-23 ml 10 Per 1.55 1.25 56.00
V-18 ml 10 Per 1.45 1.25 54.00
V-22 ml 10 Per 1.15 1.25 48.00
V-24 ml 10 Per 1.65 1.25 58.00
V-21 ml 10 Per 1.17 0.50 33.40
V-19 ml 10 Per 1.67 1.25 58.40

Azotea
V-1 ml 2 Per 0.6 0.60 4.80
V-2 ml 3 Per 0.6 0.40 6.00

09.00.00 CIELORRASO

09.01.00 Cielorraso ( con mortero de cemento puzoláanico 1:4) 7240.59

Semisotano
m2 1 Area 719.61 719.61

Primero
m2 1 Area 598.03 598.03

Segundo
m2 1 Area 589.01 589.01

Tercero
m2 1 Area 589.01 589.01

Cuarto
m2 1 Area 589.01 589.01

Quinto
m2 1 Area 589.01 589.01

Sexto
m2 1 Area 589.01 589.01

Septimo
m2 1 Area 589.01 589.01
HOJA DE METRADOS - ARQUITECTURA

Obra: #REF!

FORMULA 02

MEDIDAS
CODIGO PARTIDA UNIDAD No. VECES PARCIAL TOTAL
LARGO ANCHO ALTO
Octavo
m2 1 Area 589.01 589.01

Noveno
m2 1 Area 589.01 589.01

Decimo
m2 1 Area 589.01 589.01

Onceavo
m2 1 Area 589.01 589.01

Azotea
m2 1 Area 32.86 32.86

09.02.00 Fondo de Escaleras ( con mortero de cemento puzoláanico 1:4) 64.15


Tramo 1,2,3,4,5,6,7,8
m2 22 Area 2.92 64.15

10.00.00 PISOS
10.01.00 Contrapiso 7807.40

Semisotano
m2 1 Area 719.61 719.61

Primero
m2 1 Area 598.03 598.03

Segundo
m2 1 Area 589.01 589.01

Tercero
m2 1 Area 589.01 589.01

Cuarto
m2 1 Area 589.01 589.01

Quinto
m2 1 Area 589.01 589.01

Sexto
m2 1 Area 589.01 589.01

Septimo
m2 1 Area 589.01 589.01

Octavo
m2 1 Area 589.01 589.01

Noveno
m2 1 Area 589.01 589.01

Decimo
m2 1 Area 589.01 589.01

Onceavo
m2 1 Area 589.01 589.01

Azotea
m2 1 Area 599.67 599.67

10.01.00 Cemento pulido 1264.60

Semisotano
m2 1 Area 697.80 697.80

Azotea
m2 1 Area 566.80 566.80
HOJA DE METRADOS - ARQUITECTURA

Obra: #REF!

FORMULA 02

MEDIDAS
CODIGO PARTIDA UNIDAD No. VECES PARCIAL TOTAL
LARGO ANCHO ALTO

10.02.00 Piso Ceramico 1037.30

Primero
m2 1 Area 15.90 15.90
Segundo
m2 1 Area 102.14 102.14
Tercero
m2 1 Area 102.14 102.14
Cuarto
m2 1 Area 102.14 102.14
Quinto
m2 1 Area 102.14 102.14
Sexto
m2 1 Area 102.14 102.14
Septimo
m2 1 Area 102.14 102.14
Octavo
m2 1 Area 102.14 102.14
Noveno
m2 1 Area 102.14 102.14
Decimo
m2 1 Area 102.14 102.14
Onceavo
m2 1 Area 102.14 102.14

10.03.00 Piso Laminado 1766.00

Segundo
m2 1 Area 176.60 176.60
Tercero
m2 1 Area 176.60 176.60
Cuarto
m2 1 Area 176.60 176.60
Quinto
m2 1 Area 176.60 176.60
Sexto
m2 1 Area 176.60 176.60
Septimo
m2 1 Area 176.60 176.60
Octavo
m2 1 Area 176.60 176.60
Noveno
m2 1 Area 176.60 176.60
Decimo
m2 1 Area 176.60 176.60
Onceavo
m2 1 Area 176.60 176.60

10.04.00 Piso Porcelanato 3355.37

Semisotano
m2 1 Area 44.26 44.26
Primero
m2 1 Area 69.60 69.60
Segundo
m2 1 Area 320.87 320.87
Tercero
m2 1 Area 320.87 320.87
Cuarto
m2 1 Area 320.87 320.87
Quinto
m2 1 Area 320.87 320.87
Sexto
m2 1 Area 320.87 320.87
Septimo
m2 1 Area 320.87 320.87
Octavo
HOJA DE METRADOS - ARQUITECTURA

Obra: #REF!

FORMULA 02

MEDIDAS
CODIGO PARTIDA UNIDAD No. VECES PARCIAL TOTAL
LARGO ANCHO ALTO
m2 1 Area 320.87 320.87
Noveno
m2 1 Area 320.87 320.87
Decimo
m2 1 Area 320.87 320.87
Onceavo
m2 1 Area 320.87 320.87
Azotea
m2 1 Area 32.86 32.86

11.00.00 ZOCALO
11.01.00 Zocalo de ceramico 2375.49
m2 2375.49

12.00.00 CONTRAZOCALO
12.01.00 Contrazocalo de Ceramico 1710.60

Primero
ml 1 Per 21.90 21.90
Segundo
ml 1 Per 168.87 168.87
Tercero
ml 1 Per 168.87 168.87
Cuarto
ml 1 Per 168.87 168.87
Quinto
ml 1 Per 168.87 168.87
Sexto
ml 1 Per 168.87 168.87
Septimo
ml 1 Per 168.87 168.87
Octavo
ml 1 Per 168.87 168.87
Noveno
ml 1 Per 168.87 168.87
Decimo
ml 1 Per 168.87 168.87
Onceavo
ml 1 Per 168.87 168.87

12.02.00 Contrazocalo de Madera 1875.00

Segundo
ml 1 Per 187.50 187.50
Tercero
ml 1 Per 187.50 187.50
Cuarto
ml 1 Per 187.50 187.50
Quinto
ml 1 Per 187.50 187.50
Sexto
ml 1 Per 187.50 187.50
Septimo
ml 1 Per 187.50 187.50
Octavo
ml 1 Per 187.50 187.50
Noveno
ml 1 Per 187.50 187.50
Decimo
ml 1 Per 187.50 187.50
Onceavo
ml 1 Per 187.50 187.50

12.03.00 Contrazocalo de Porcelanato 3320.36

Semisotano
ml 1 Per 47.10 47.10
Primero
HOJA DE METRADOS - ARQUITECTURA

Obra: #REF!

FORMULA 02

MEDIDAS
CODIGO PARTIDA UNIDAD No. VECES PARCIAL TOTAL
LARGO ANCHO ALTO
ml 1 Per 65.36 65.36
Segundo
ml 1 Per 316.93 316.93
Tercero
ml 1 Per 316.93 316.93
Cuarto
ml 1 Per 316.93 316.93
Quinto
ml 1 Per 316.93 316.93
Sexto
ml 1 Per 316.93 316.93
Septimo
ml 1 Per 316.93 316.93
Octavo
ml 1 Per 316.93 316.93
Noveno
ml 1 Per 316.93 316.93
Decimo
ml 1 Per 316.93 316.93
Onceavo
ml 1 Per 316.93 316.93
Azotea
ml 1 Per 38.60 38.60

13.00.00 CARPINTERIA DE MADERA

13.01.00 Puertas contraplacadas 981.31

Semisotano
P-1 m2 10 0.80 2.45 19.60
P-3 m2 1 1.00 2.45 2.45
P-5 m2 1 0.90 2.45 2.21

Primer Nivel
P-1 m2 5 0.80 2.45 9.80
P-3 m2 2 1.00 2.45 4.90

Segundo, Tercero, Cuarto, Quinto, Sexto, Septimo, Octavo, Noveno, Decimo y Onceavo Nivel
P-1 m2 210 0.80 2.45 411.60
P-3 m2 120 1.00 2.45 294.00
P-11 m2 40 1.00 2.45 98.00
P-12 m2 50 0.60 2.50 75.00
P-13 m2 30 0.85 2.50 63.75

13.02.00 Puertas Tablero Rebajado 98.00

Segundo, Tercero, Cuarto, Quinto, Sexto, Septimo, Octavo, Noveno, Decimo y Onceavo Nivel
P-10 m2 40 1.00 2.45 98.00

13.03.00 Closets 268.70

Segundo, Tercero, Cuarto, Quinto, Sexto, Septimo, Octavo, Noveno, Decimo y Onceavo Nivel
ml 10 2.60 26.00
ml 10 1.75 17.50
ml 10 1.75 17.50
ml 10 2.20 22.00
ml 10 2.20 22.00
ml 10 2.60 26.00
ml 10 2.60 26.00
ml 10 2.13 21.30
ml 10 2.13 21.30
ml 10 2.18 21.80
ml 10 2.18 21.80
ml 10 2.55 25.50

13.04.00 Reposteros 147.10

Segundo, Tercero, Cuarto, Quinto, Sexto, Septimo, Octavo, Noveno, Decimo y Onceavo Nivel
HOJA DE METRADOS - ARQUITECTURA

Obra: #REF!

FORMULA 02

MEDIDAS
CODIGO PARTIDA UNIDAD No. VECES PARCIAL TOTAL
LARGO ANCHO ALTO
ml 10 4.33 43.30
ml 10 3.45 34.50
ml 10 3.53 35.30
ml 10 3.4 34.00

14.00.00 CARPINTERIA METALICA

14.01.00 Barandas Metalicas 208.80


Lado izquierdo ml 20 5.22 104.40
Lado derecho ml 20 5.22 104.40

14.02.00 Puertas Metalicas 107.80

Puerta de metal contra incendio

Semisotano
P-2 m2 2 1.00 2.45 4.90

Primer nivel
P-2 m2 2 1.00 2.45 4.90

Segundo, Tercero, Cuarto, Quinto, Sexto, Septimo, Octavo, Noveno, Decimo y Onceavo Nivel
P-2 m2 40 1.00 2.45 98.00

14.03.00 Puerta Garage 16.21


m2 1 16.21 16.21

15.00.00 CERRAJERIA
15.01.00 Cerradura para Puerta Exterior 40.00

Segundo, Tercero, Cuarto, Quinto, Sexto, Septimo, Octavo, Noveno, Decimo y Onceavo Nivel
pza 40 40.00

15.02.00 Cerradura para Puerta Interior 469.00

Semisotano
pza 12 12.00
Primer Nivel
pza 7 7.00
Segundo, Tercero, Cuarto, Quinto, Sexto, Septimo, Octavo, Noveno, Decimo y Onceavo Nivel
pza 450 450.00

15.03.00 Cerradura Pesada para Puerta de Metal 44.00


pza 44 44.00

15.04.00 Bisagras 1567.00


Puertas Exterior par 40 4 160.00
Puertas Interior par 469 3 1407.00

16.00.00 VIDRIOS CRISTALES Y SIMILARES

16.01.00 Vidrio templado de 6 mm 6349.77

Primer Nivel
V-? pie2 1 1.35 1.35 10.73 19.56
V-2 pie2 1 0.60 0.40 10.73 2.58
V-1 pie2 2 0.60 0.60 10.73 7.73

Segundo, Tercero, Cuarto, Quinto, Sexto, Septimo, Octavo, Noveno, Decimo y Onceavo Nivel
V-1 pie2 20 0.60 6.00 10.73 772.56
V-2 pie2 30 0.60 0.40 10.73 77.26
V-3 pie2 10 1.30 1.35 10.73 188.31
V-4 pie2 10 1.35 1.35 10.73 195.55
V-5 pie2 20 1.35 0.50 10.73 144.86
V-6 pie2 10 2.90 1.25 10.73 388.96
V-7 pie2 10 1.17 1.25 10.73 156.93
V-8 pie2 10 1.20 0.50 10.73 64.38
V-9 pie2 30 0.65 0.50 10.73 104.62
V-10 pie2 10 0.65 1.25 10.73 87.18
HOJA DE METRADOS - ARQUITECTURA

Obra: #REF!

FORMULA 02

MEDIDAS
CODIGO PARTIDA UNIDAD No. VECES PARCIAL TOTAL
LARGO ANCHO ALTO
V-11 pie2 10 0.82 1.25 10.73 109.98
V-12 pie2 10 1.28 1.25 10.73 171.68
V-13 pie2 10 1.50 1.25 10.73 201.19
V-14 pie2 10 3.01 1.25 10.73 403.72
V-15 pie2 10 2.79 1.25 10.73 374.21
V-16 pie2 90 0.80 0.50 10.73 386.28
V-17 pie2 10 2.50 1.25 10.73 335.31
V-18 pie2 20 1.45 1.25 10.73 388.96
V-19 pie2 30 1.67 1.25 10.73 671.97
V-20 pie2 20 0.99 1.25 10.73 265.57
V-21 pie2 20 1.17 0.50 10.73 125.54
V-22 pie2 10 1.15 1.25 10.73 154.24
V-23 pie2 10 1.55 1.25 10.73 207.89
V-24 pie2 10 1.65 1.25 10.73 221.31
V-25 pie2 10 0.68 0.50 10.73 36.48

Azotea
V-1 pie2 2 0.60 6.00 10.73 77.26
V-2 pie2 3 0.60 0.40 10.73 7.73

16.01.00 Vidrio templado de 8 mm 3201.40

Primer Nivel
P-7 pie2 2 1.80 2.45 10.73 94.64
P-8 pie2 1 2.00 2.45 10.73 52.58

Segundo, Tercero, Cuarto, Quinto, Sexto, Septimo, Octavo, Noveno, Decimo y Onceavo Nivel
M-1 pie2 10 2.00 2.40 10.73 515.04
M-2 pie2 10 2.00 2.55 10.73 547.23
M-3 pie2 10 2.95 2.55 10.73 807.16
M-4 pie2 10 1.90 2.55 10.73 519.87
M-5 pie2 10 2.43 2.55 10.73 664.88

17.00.00 PINTURA
17.01.00 Pintura en muros m2 16458.05
17.02.00 Pintura en cielo rraso m2 7304.74
17.03.00 Pintuta coin barniz en puertas m2 2158.61
HOJA DE METRADOS - INSTALACIONES ELECTRICAS

Obra: #REF!

FORMULA 03

Metrado
Item Descripcion Unid Cant. Parcial Total
Largo Ancho Alto

18.00.00 INSTALACION ELECTRICA

18.01 Salida de Techo 263.00


Semisotano Pto 16.00
Primer Piso Pto 32.00
Segundo Piso Pto 36.00
Tercer Piso Pto 35.00
Cuarto Piso Pto 36.00
Quinto Piso Pto 35.00
Sexto Piso Pto 35.00
Seprimo Piso Pto 35.00
Azotea Pto 3.00
18.02 Salida de Pared 18.00
Semisotano Pto 1.00
Primer Piso Pto 4.00
Segundo Piso Pto 2.00
Tercer Piso Pto 2.00
Cuarto Piso Pto 2.00
Quinto Piso Pto 2.00
Sexto Piso Pto 2.00
Seprimo Piso Pto 2.00
Azotea Pto 1.00
18.03 Lampara Simple 148.00
Semisotano Pto 3.00
Primer Piso Pto 18.00
Segundo Piso Pto 21.00
Tercer Piso Pto 21.00
Cuarto Piso Pto 21.00
Quinto Piso Pto 21.00
Sexto Piso Pto 21.00
Seprimo Piso Pto 21.00
Azotea Pto 1.00
18.04 Spot Light 102.00
Semisotano Pto 0.00
Primer Piso Pto 14.00
Segundo Piso Pto 15.00
Tercer Piso Pto 14.00
Cuarto Piso Pto 15.00
Quinto Piso Pto 14.00
Sexto Piso Pto 14.00
Seprimo Piso Pto 14.00
Azotea Pto 2.00
18.05 Artefacto Fluorescente 13.00
Semisotano Pto 13.00
Primer Piso Pto 0.00
Segundo Piso Pto 0.00
Tercer Piso Pto 0.00
Cuarto Piso Pto 0.00
Quinto Piso Pto 0.00
Sexto Piso Pto 0.00
Seprimo Piso Pto 0.00
Azotea Pto 0.00
18.06 Braquette de pared 18.00
Semisotano Pto 1.00
Primer Piso Pto 4.00
HOJA DE METRADOS - INSTALACIONES ELECTRICAS

Obra: #REF!

FORMULA 03

Metrado
Item Descripcion Unid Cant. Parcial Total
Largo Ancho Alto

Segundo Piso Pto 2.00


Tercer Piso Pto 2.00
Cuarto Piso Pto 2.00
Quinto Piso Pto 2.00
Sexto Piso Pto 2.00
Seprimo Piso Pto 2.00
Azotea Pto 1.00
18.07 Luminaria de Emergencia 25.00
Semisotano Pto 3.00
Primer Piso Pto 3.00
Segundo Piso Pto 3.00
Tercer Piso Pto 3.00
Cuarto Piso Pto 3.00
Quinto Piso Pto 3.00
Sexto Piso Pto 3.00
Seprimo Piso Pto 3.00
Azotea Pto 1.00
18.08 Salida Para tomacorriente bipolar doble 351.00
Semisotano Pto 18.00
Primer Piso Pto 45.00
Segundo Piso Pto 48.00
Tercer Piso Pto 48.00
Cuarto Piso Pto 48.00
Quinto Piso Pto 48.00
Sexto Piso Pto 48.00
Seprimo Piso Pto 48.00
Azotea Pto 0.00
18.09 Caja de Pase Rectangular 0.00
Semisotano Pto 0.00
Primer Piso Pto 0.00
Segundo Piso Pto 0.00
Tercer Piso Pto 0.00
Cuarto Piso Pto 0.00
Quinto Piso Pto 0.00
Sexto Piso Pto 0.00
Seprimo Piso Pto 0.00
Azotea Pto 0.00
18.10 Caja de Pase 150x150x100 82.00
Semisotano Pto 3.00
Primer Piso Pto 11.00
Segundo Piso Pto 11.00
Tercer Piso Pto 11.00
Cuarto Piso Pto 11.00
Quinto Piso Pto 11.00
Sexto Piso Pto 11.00
Seprimo Piso Pto 11.00
Azotea Pto 2.00
18.11 Puesta a Tierra 1.00
General Pto 1.00
18.12 Tablero de Distribucion Principal 7.00
Semisotano Pto 1.00
Primer Piso Pto 2.00
Segundo Piso Pto 2.00
Tercer Piso Pto 2.00
Cuarto Piso Pto 2.00
HOJA DE METRADOS - INSTALACIONES ELECTRICAS

Obra: #REF!

FORMULA 03

Metrado
Item Descripcion Unid Cant. Parcial Total
Largo Ancho Alto

Quinto Piso Pto 2.00


Sexto Piso Pto 2.00
Seprimo Piso Pto 2.00
Azotea Pto 0.00
18.13 Salida de Fuerza 0.00
Semisotano Pto
Primer Piso Pto
Segundo Piso Pto
Tercer Piso Pto
Cuarto Piso Pto
Quinto Piso Pto
Sexto Piso Pto
Seprimo Piso Pto
Azotea Pto
Azotea Pto

18.14.00 Telefono, TV y Comunicación


18.14.01 Salidas para TV y Telefono 12.00
Semisotano Pto 0.00
Primer Piso Pto 4.00
Segundo Piso Pto 4.00
Tercer Piso Pto 4.00
Cuarto Piso Pto 4.00
Quinto Piso Pto 4.00
Sexto Piso Pto 4.00
Seprimo Piso Pto 4.00
Azotea Pto 0.00
18.14.02 Intercomunicador central 1.00
General Pto 1.00
18.14.03 Intercomunicador 6.00
Semisotano Pto 0.00
Primer Piso Pto 2.00
Segundo Piso Pto 2.00
Tercer Piso Pto 2.00
Cuarto Piso Pto 2.00
Quinto Piso Pto 2.00
Sexto Piso Pto 2.00
Seprimo Piso Pto 2.00
Azotea Pto 0.00
HOJA DE METRADOS - INSTALACIONES SANITARIAS

Obra: VIVIENDA MULTIFAMILIAR - "LOS CEREZOS"

FORMULA 04

Metrado
Item Descripcion Unid Cant. Parcial Total
Largo Ancho Alto

19.00.00 INSTALACIONES DE DESAGUE Y VENTILACION


19.01.00 SALIDA DE DESAGUE
19.01.01 INODORO 161.00
Primer Piso Pto. 1.00
Segundo Piso Pto. 16.00
Tercer Piso Pto. 16.00
Cuarto Piso Pto. 16.00
Quinto Piso Pto. 16.00
Sexto Piso Pto. 16.00
Septimo Piso Pto. 16.00
Octavo Piso Pto. 16.00
Noveno Piso Pto. 16.00
Decimo Piso Pto. 16.00
Onceavo Piso Pto. 16.00
19.01.02 LAVATORIO PEDESTAL 161.00
Primer Piso Pto. 1.00
Segundo Piso Pto. 16.00
Tercer Piso Pto. 16.00
Cuarto Piso Pto. 16.00
Quinto Piso Pto. 16.00
Sexto Piso Pto. 16.00
Septimo Piso Pto. 16.00
Octavo Piso Pto. 16.00
Noveno Piso Pto. 16.00
Decimo Piso Pto. 16.00
Onceavo Piso Pto. 16.00
19.01.03 DUCHA 121.00
Primer Piso Pto. 1.00
Segundo Piso Pto. 12.00
Tercer Piso Pto. 12.00
Cuarto Piso Pto. 12.00
Quinto Piso Pto. 12.00
Sexto Piso Pto. 12.00
Septimo Piso Pto. 12.00
Octavo Piso Pto. 12.00
Noveno Piso Pto. 12.00
Decimo Piso Pto. 12.00
Onceavo Piso Pto. 12.00
19.01.04 LAVADERO DE COCINA 40.00
Segundo Piso Pto. 4.00
Tercer Piso Pto. 4.00
Cuarto Piso Pto. 4.00
Quinto Piso Pto. 4.00
Sexto Piso Pto. 4.00
Septimo Piso Pto. 4.00
Octavo Piso Pto. 4.00
Noveno Piso Pto. 4.00
Decimo Piso Pto. 4.00
Onceavo Piso Pto. 4.00
19.01.05 LAVADERO DE ROPA 40.00
Segundo Piso Pto. 4.00
Tercer Piso Pto. 4.00
Cuarto Piso Pto. 4.00
Quinto Piso Pto. 4.00
Sexto Piso Pto. 4.00
Septimo Piso Pto. 4.00
Octavo Piso Pto. 4.00
Noveno Piso Pto. 4.00
Decimo Piso Pto. 4.00
Onceavo Piso Pto. 4.00
19.01.06 COLOCACION DE APARATOS CORRIENTES 419.00
Primer Piso Pto. 3.00
Segundo Piso Pto. 52.00
Tercer Piso Pto. 52.00
Cuarto Piso Pto. 52.00
Quinto Piso Pto. 52.00
Sexto Piso Pto. 52.00
Septimo Piso Pto. 52.00
Octavo Piso Pto. 52.00
HOJA DE METRADOS - INSTALACIONES SANITARIAS

Obra: VIVIENDA MULTIFAMILIAR - "LOS CEREZOS"

FORMULA 04

Metrado
Item Descripcion Unid Cant. Parcial Total
Largo Ancho Alto

Noveno Piso Pto. 52.00


Decimo Piso Pto. 52.00
Onceavo Piso Pto. 52.00
19.01.07 SALIDA DE DESAGUE PVC 2" 290.00
Primer Piso Pto. 2.00
Segundo Piso Pto. 36.00
Tercer Piso Pto. 36.00
Cuarto Piso Pto. 36.00
Quinto Piso Pto. 36.00
Sexto Piso Pto. 36.00
Septimo Piso Pto. 36.00
Octavo Piso Pto. 36.00
Noveno Piso Pto. 36.00
Decimo Piso Pto. 36.00
Onceavo Piso Pto. 36.00
19.01.08 SALIDA DE DESAGUE PVC 4" 129.00
Primer Piso Pto. 1.00
Segundo Piso Pto. 16.00
Tercer Piso Pto. 16.00
Cuarto Piso Pto. 16.00
Quinto Piso Pto. 16.00
Sexto Piso Pto. 16.00
Septimo Piso Pto. 16.00
Octavo Piso Pto. 16.00
Noveno Piso Pto. 16.00
Decimo Piso Pto. 16.00
Onceavo Piso Pto. 16.00
19.01.09 SALIDA DE VENTILACION PVC DE 2"-. 129.00
Primer Piso Pto. 1.00
Segundo Piso Pto. 16.00
Tercer Piso Pto. 16.00
Cuarto Piso Pto. 16.00
Quinto Piso Pto. 16.00
Sexto Piso Pto. 16.00
Septimo Piso Pto. 16.00
Octavo Piso Pto. 16.00
Noveno Piso Pto. 16.00
Decimo Piso Pto. 16.00
Onceavo Piso Pto. 16.00
19.01.10 TUBERIA DE PVC DE 2" P/ DESAGUE 474.90
Segundo Piso ml 47.49
Tercer Piso ml 47.49
Cuarto Piso ml 47.49
Quinto Piso ml 47.49
Sexto Piso ml 47.49
Septimo Piso ml 47.49
Octavo Piso ml 47.49
Noveno Piso ml 47.49
Decimo Piso ml 47.49
Onceavo Piso ml 47.49
19.01.10 TUBERIA DE PVC DE 4" P/DESAGUE 751.02
Semisotano ml 163.92
Primer Piso ml 130.53
Segundo Piso ml 73.65
Tercer Piso ml 73.65
Cuarto Piso ml 73.65
Quinto Piso ml 73.65
Sexto Piso ml 73.65
Septimo Piso ml 73.65
Octavo Piso ml 73.65
Noveno Piso ml 73.65
Decimo Piso ml 73.65
Onceavo Piso ml 73.65
Azotea ml 14.52
19.02.00 ACCESORIOS DE REDES
19.02.01 YEE PVC SAL 2" 90.00
Segundo Piso Pto. 9.00
Tercer Piso Pto. 9.00
Cuarto Piso Pto. 9.00
HOJA DE METRADOS - INSTALACIONES SANITARIAS

Obra: VIVIENDA MULTIFAMILIAR - "LOS CEREZOS"

FORMULA 04

Metrado
Item Descripcion Unid Cant. Parcial Total
Largo Ancho Alto

Quinto Piso Pto. 9.00


Sexto Piso Pto. 9.00
Septimo Piso Pto. 9.00
Octavo Piso Pto. 9.00
Noveno Piso Pto. 9.00
Decimo Piso Pto. 9.00
Onceavo Piso Pto. 9.00
19.02.02 YEE PVC SAL 4" 387.00
Semisotano Pto. 42.00
Primer Piso Pto. 25.00
Segundo Piso Pto. 32.00
Tercer Piso Pto. 32.00
Cuarto Piso Pto. 32.00
Quinto Piso Pto. 32.00
Sexto Piso Pto. 32.00
Septimo Piso Pto. 32.00
Octavo Piso Pto. 32.00
Noveno Piso Pto. 32.00
Decimo Piso Pto. 32.00
Onceavo Piso Pto. 32.00
19.02.03 CODOS PVC SAL 2" 45 250.00
Segundo Piso Pto. 25.00
Tercer Piso Pto. 25.00
Cuarto Piso Pto. 25.00
Quinto Piso Pto. 25.00
Sexto Piso Pto. 25.00
Septimo Piso Pto. 25.00
Octavo Piso Pto. 25.00
Noveno Piso Pto. 25.00
Decimo Piso Pto. 25.00
Onceavo Piso Pto. 25.00
19.02.04 REGISTROS ROSCADO DE BRONCE DE 4" 160.00
Segundo Piso Pto. 16.00
Tercer Piso Pto. 16.00
Cuarto Piso Pto. 16.00
Quinto Piso Pto. 16.00
Sexto Piso Pto. 16.00
Septimo Piso Pto. 16.00
Octavo Piso Pto. 16.00
Noveno Piso Pto. 16.00
Decimo Piso Pto. 16.00
Onceavo Piso Pto. 16.00
19.02.05 TRAMPA DE 2" 280.00
Segundo Piso Pto. 28.00
Tercer Piso Pto. 28.00
Cuarto Piso Pto. 28.00
Quinto Piso Pto. 28.00
Sexto Piso Pto. 28.00
Septimo Piso Pto. 28.00
Octavo Piso Pto. 28.00
Noveno Piso Pto. 28.00
Decimo Piso Pto. 28.00
Onceavo Piso Pto. 28.00
19.02.06 SOMBREROS DE VENTILACIÓN PVC DE 2" 0.00
General pza 0.00
19.03.00 CAMARAS DE INSPECCIÓN
19.03.01 CAJA DE REGISTRO 0.60x0.30 h=0.80 0.00
General pza 0.00
20.00.00 SISTEMA DE AGUA FRIA
20.01.00 SALIDA DE AGUA FRIA
20.01.01 SALIDA DE AGUA FRIA DE 1/2" 523.00
Primer Piso Pto. 3.00
Segundo Piso Pto. 52.00
Tercer Piso Pto. 52.00
Cuarto Piso Pto. 52.00
Quinto Piso Pto. 52.00
Sexto Piso Pto. 52.00
Septimo Piso Pto. 52.00
Octavo Piso Pto. 52.00
HOJA DE METRADOS - INSTALACIONES SANITARIAS

Obra: VIVIENDA MULTIFAMILIAR - "LOS CEREZOS"

FORMULA 04

Metrado
Item Descripcion Unid Cant. Parcial Total
Largo Ancho Alto

Noveno Piso Pto. 52.00


Decimo Piso Pto. 52.00
Onceavo Piso Pto. 52.00
20.02.00 REDES DE DISTRIBUCION
20.02.01 TUBERIA DE 3" 4.64
Semisotano
Primer Piso ml
Segundo Piso ml
Tercer Piso ml
Cuarto Piso ml
Quinto Piso ml
Sexto Piso ml
Septimo Piso ml
Octavo Piso ml
Noveno Piso ml
Decimo Piso ml
Onceavo Piso ml
Azotea ml 4.64
20.02.01 TUBERIA DE 2 1/2" 10.60
Semisotano
Primer Piso ml
Segundo Piso ml
Tercer Piso ml
Cuarto Piso ml
Quinto Piso ml
Sexto Piso ml
Septimo Piso ml
Octavo Piso ml
Noveno Piso ml 5.30
Decimo Piso ml 5.30
Onceavo Piso ml 5.30
20.02.01 TUBERIA DE 2" 21.60
Semisotano
Primer Piso ml
Segundo Piso ml
Tercer Piso ml
Cuarto Piso ml
Quinto Piso ml
Sexto Piso ml
Septimo Piso ml 8.05
Octavo Piso ml 8.05
Noveno Piso ml 2.75
Decimo Piso ml 2.75
Onceavo Piso ml 2.75
20.02.02 TUBERIA DE 1 1/2" 133.96
Primer Piso ml
Segundo Piso ml
Tercer Piso ml 5.30
Cuarto Piso ml 5.30
Quinto Piso ml 25.92
Sexto Piso ml 25.92
Septimo Piso ml 17.88
Octavo Piso ml 17.88
Noveno Piso ml 17.88
Decimo Piso ml 17.88
Onceavo Piso ml 17.88
20.02.03 TUBERIA DE 1" 319.92
Semisotano ml 29.38
Primer Piso ml 8.31
Segundo Piso ml 30.67
Tercer Piso ml 25.93
Cuarto Piso ml 25.93
Quinto Piso ml 19.96
Sexto Piso ml 19.96
Septimo Piso ml 19.96
Octavo Piso ml 19.96
Noveno Piso ml 37.64
Decimo Piso ml 37.64
Onceavo Piso ml 37.64
HOJA DE METRADOS - INSTALACIONES SANITARIAS

Obra: VIVIENDA MULTIFAMILIAR - "LOS CEREZOS"

FORMULA 04

Metrado
Item Descripcion Unid Cant. Parcial Total
Largo Ancho Alto

Azotea ml 6.94
20.02.04 TUBERIA DE 3/4" 750.05
Semisotano ml 3.22
Primer Piso ml 21.52
Segundo Piso ml 67.94
Tercer Piso ml 67.95
Cuarto Piso ml 67.95
Quinto Piso ml 52.36
Sexto Piso ml 52.36
Septimo Piso ml 95.79
Octavo Piso ml 95.79
Noveno Piso ml 76.13
Decimo Piso ml 76.13
Onceavo Piso ml 76.13
20.02.05 TUBERIA DE 1/2" 794.71
Primer Piso ml 2.66
Segundo Piso ml 100.04
Tercer Piso ml 100.52
Cuarto Piso ml 100.52
Quinto Piso ml 100.51
Sexto Piso ml 100.51
Septimo Piso ml 58.02
Octavo Piso ml 58.02
Noveno Piso ml 57.97
Decimo Piso ml 57.97
Onceavo Piso ml 57.97
20.03.00 LLAVES Y VALVULAS
20.03.01 LLAVE DE COMPUERTA DE 1/2" 445.00
Semisotano Pto. 4.00
Primer Piso Pto. 1.00
Segundo Piso Pto. 44.00
Tercer Piso Pto. 44.00
Cuarto Piso Pto. 44.00
Quinto Piso Pto. 44.00
Sexto Piso Pto. 44.00
Septimo Piso Pto. 44.00
Octavo Piso Pto. 44.00
Noveno Piso Pto. 44.00
Decimo Piso Pto. 44.00
Onceavo Piso Pto. 44.00
21.00.00 SISTEMA DE AGUA CALIENTE
21.01.00 SALIDA DE AGUA CALIENTE
21.01.01 SALIDA DE AGUA CALIENTE DE 1/2" 320.00
Segundo Piso Pto. 32.00
Tercer Piso Pto. 32.00
Cuarto Piso Pto. 32.00
Quinto Piso Pto. 32.00
Sexto Piso Pto. 32.00
Septimo Piso Pto. 32.00
Octavo Piso Pto. 32.00
Noveno Piso Pto. 32.00
Decimo Piso Pto. 32.00
Onceavo Piso Pto. 32.00
21.02.00 REDES DE DISTRIBUCION
21.02.01 TUBERIA DE 1/2" 1451.10
Segundo Piso ml 145.11
Tercer Piso ml 145.11
Cuarto Piso ml 145.11
Quinto Piso ml 145.11
Sexto Piso ml 145.11
Septimo Piso ml 145.11
Octavo Piso ml 145.11
Noveno Piso ml 145.11
Decimo Piso ml 145.11
Onceavo Piso ml 145.11
21.00.00 SISTEMA DE AGUA CONTRA INCENDIOS
21.01.00 SALIDA DE AGUA CONTRA INCENDIOS
21.01.01 SALIDA DE AGUA CONTRA INCENDIOS DE 4" 24.00
Semisotano Pto. 2.00
HOJA DE METRADOS - INSTALACIONES SANITARIAS

Obra: VIVIENDA MULTIFAMILIAR - "LOS CEREZOS"

FORMULA 04

Metrado
Item Descripcion Unid Cant. Parcial Total
Largo Ancho Alto

Primer Piso Pto. 2.00


Segundo Piso Pto. 2.00
Tercer Piso Pto. 2.00
Cuarto Piso Pto. 2.00
Quinto Piso Pto. 2.00
Sexto Piso Pto. 2.00
Septimo Piso Pto. 2.00
Octavo Piso Pto. 2.00
Noveno Piso Pto. 2.00
Decimo Piso Pto. 2.00
Onceavo Piso Pto. 2.00
21.02.00 REDES DE DISTRIBUCION
21.02.01 TUBERIA SCH 40 148.04
Semisotano ml 37.50
Primer Piso ml 12.44
Segundo Piso ml 9.81
Tercer Piso ml 9.81
Cuarto Piso ml 9.81
Quinto Piso ml 9.81
Sexto Piso ml 9.81
Septimo Piso ml 9.81
Octavo Piso ml 9.81
Noveno Piso ml 9.81
Decimo Piso ml 9.81
Onceavo Piso ml 9.81
22.00.00 SISTEMA DE AGUA PLUVIAL
22.01.00 BAJADA DE LLUVIA 5.00
General pto 5.00
22.02.00 TUBERIA PVC SAL 4" 162.53
General m 162.53
22.03.00 Sumideros de 4" 5.00
General pto 5.00
RESUMEN DE METRADOS

PROYECTO: EDIFICIO MULTIFAMILIAR CAMPO VERDE


PROPIETARIO R.M & R. PROMOTORA CONSTRUCTORA S.A.C.

CODIGO PARTIDA UNID.

01.00.00 OBRAS PROVISIONALES


01.01.00 Construcciones provisionales
01.01.01 Almacen, Oficina y Caseta de Guardiania m2
01.01.02 Baño Mes

02.00.00 TRABAJOS PRELIMINARES


02.01.00 Trazos, niveles y replanteo m2
02.02.00 Replanteo durante el proceso m2

03.00.00 MOVIMIENTO DE TIERRAS


03.01.00 EXCAVACIONES
03.01.01 Excavaciones Masivas m3
03.01.02 Excavaciones Manuales m3
03.01.03 Excavaciones de Calzaduras m3

04.00.00 RELLENOS
04.01.00 Relleno con material propio m3
04.02.00 Relleno con material de prestamo m3
04.03.00 Nivelacion Interior y Apisonado
04.03.01 Nivelacion Compactado Manual m2
04.04.00 Eliminacion de Material Excedente
04.04.01 Eliminacion de Material Excedente m3

05.00.00 OBRAS DE CONCRETO SIMPLE


05.01.00 Subcimiento
05.01.01 Concreto Ciclopeo 1:12+30%PG m3
05.02.00 Cimientos Corrido
05.02.01 Concreto Ciclopeo 1:10+30%PG m3
05.03.00 Sobrecimientos
05.03.01 Sobrecimientos concreto 1:8+25%PM m3
05.03.02 Encofrado y Desencofrado de Sobrecimientos m2
05.04.00 Falsopiso E=4'' m2
05.05.00 Calzaduras
05.05.01 Concreto Ciclopeo 1:10+30%PG m3
05.05.02 Encofrado m2

06.00.00 OBRAS DE CONCRETO ARMADO


06.01.00 Zapatas
06.01.01 Concreto (f'c = 210 kg/cm2) m3
06.01.02 Encofrado m2
06.01.03 Acero ( Grado 60 ) Kg
06.02.00 Vigas de Cimentacion
06.02.01 Concreto (f'c = 210 kg/cm2) m3
06.02.02 Encofrado y Desencofrado m2
06.02.03 Acero ( Grado 60 ) Kg
06.03.00 Muros de concreto
06.03.01 Concreto (f'c = 210 kg/cm2) m3
06.03.02 Encofrado m2
06.03.03 Acero ( Grado 60 ) Kg
06.04.00 Columnas y Placas
06.04.01 Concreto (f'c = 210 kg/cm2) m3
06.04.02 Encofrado m2
06.04.03 Acero ( Grado 60 ) Kg
06.05.00 Vigas
06.05.01 Concreto (f'c = 210 kg/cm2) m3
06.05.02 Encofrado m2
06.05.03 Acero ( Grado 60 ) Kg
06.06.00 Losas Aligerada (e=0.20m)
06.06.01 Concreto ( f'c = 210 Kg/cm2) m3
06.06.02 Encofrados m2
06.06.03 Acero Kg
06.06.04 Ladrillo hueco ( 0.15x0.30x0.30) Und.
06.07.00 Losa Maciza
06.07.01 Concreto (f'c = 210 Kg/cm2) m3
06.07.02 Encofrado m2
06.07.03 Acero Kg
06.08.00 Escaleras
06.08.01 Concreto ( f'c = 210 Kg/cm2) m3
06.08.02 Encofrados m2
06.08.03 Acero Kg

07.00.00 MUROS Y TABIQUES DE ALBAÑILERÍA


07.01.00 Muros de Ladrillo Pandereta
07.01.01 Muros de Soga m2
07.01.02 Muros de Cabeza m2

08.00.00 REVOQUES Y ENLUCIDOS


08.01.00 Tarrajeo Rayado m2
08.02.00 Tarrajeo en Interiores (Mortero 1:5 Cemento puzolanico-Arena fina) m2
08.03.00 Tarrajeo en Exteriores (Mortero 1:5 Cemento puzolanico-Arena fina) m2
08.04.00 Vestidura de Derrames ml

09.00.00 CIELORRASO
09.01.00 Cielorraso ( con mortero de cemento puzoláanico 1:4) m2
09.02.00 Fondo de Escaleras ( con mortero de cemento puzoláanico 1:4) m2

10.00.00 PISOS
10.01.00 Contrapiso m2
10.02.00 Piso Ceramico m2
10.03.00 Piso Laminado m2
10.04.00 Piso Porcelanato m2

11.00.00 ZOCALO
11.01.00 Zocalo de ceramico m2

12.00.00 CONTRAZOCALO
12.01.00 Contrazocalo de Ceramico ml
12.02.00 Contrazocalo de Madera ml
12.03.00 Contrazocalo de Porcelanato ml

13.00.00 CARPINTERIA DE MADERA


13.01.00 Puertas contraplacadas m2
13.02.00 Puertas Tablero Rebajado m2
13.03.00 Closets ml
13.04.00 Reposteros ml

14.00.00 CARPINTERIA METALICA


14.01.00 Barandas Metalicas ml
14.02.00 Puertas Metalicas m2
14.03.00 Puerta Garage m2

15.00.00 CERRAJERIA
15.01.00 Cerradura para Puerta Exterior pza
15.02.00 Cerradura para Puerta Interior pza
15.03.00 Cerradura Pesada para Puerta de Metal pza
15.04.00 Bisagras par

16.00.00 VIDRIOS CRISTALES Y SIMILARES


16.01.00 Ventanas de Vidrio Templado pie2

17.00.00 PINTURA
17.01.00 Pintura en muros m2
17.02.00 Pintura en cielo rraso m2
17.03.00 Pintuta coin barniz en puertas m2

18.00.00 INSTALACION ELECTRICA


18.01 Salida de Techo Pto
18.02 Salida de Pared Pto
18.03 Lampara Simple Pto
18.04 Spot Light Pto
18.05 Artefacto Fluorescente Pto
18.06 Braquette de pared Pto
18.07 Luminaria de Emergencia Pto
18.08 Salida Para tomacorriente bipolar doble Pto
18.09 Caja de Pase Rectangular Pto
18.1 Caja de Pase 150x150x100 Pto
18.11 Puesta a Tierra Pto
18.12 Tablero de Distribucion Principal Pto
18.13 Salida de Fuerza Pto
18.14.00 Telefono, TV y Comunicación
18.14.01 Salidas para TV y Telefono Pto
18.14.02 Intercomunicador central Pto
18.14.03 Intercomunicador Pto

19.00.00 INSTALACIONES DE DESAGUE Y VENTILACION


19.01.00 SALIDA DE DESAGUE
19.01.01 INODORO Pto
19.01.02 LAVATORIO PEDESTAL Pto
19.01.03 DUCHA Pto
19.01.04 LAVADERO DE COCINA Pto
19.01.05 LAVADERO DE ROPA Pto
19.01.06 COLOCACION DE APARATOS CORRIENTES Pto
19.01.07 SALIDA DE DESAGUE PVC 2" Pto
19.01.08 SALIDA DE DESAGUE PVC 4" Pto
19.01.09 SALIDA DE VENTILACION PVC DE 2"-. Pto
19.01.10 TUBERIA DE PVC DE 2" P/ DESAGUE ml
19.01.10 TUBERIA DE PVC DE 4" P/DESAGUE ml
19.02.00 ACCESORIOS DE REDES
19.02.01 YEE PVC SAL 2" Pto
19.02.02 YEE PVC SAL 4" Pto
19.02.03 CODOS PVC SAL 2" 45 Pto
19.02.04 REGISTROS ROSCADO DE BRONCE DE 4" Pto
19.02.05 TRAMPA DE 2" Pto
19.02.06 SOMBREROS DE VENTILACIÓN PVC DE 2" Pto
19.03.00 CAMARAS DE INSPECCIÓN
19.03.01 CAJA DE REGISTRO 0.60x0.30 h=0.80 Pto

20.00.00 SISTEMA DE AGUA FRIA


20.01.00 SALIDA DE AGUA FRIA
20.01.01 SALIDA DE AGUA FRIA DE 1/2" Pto
20.02.00 REDES DE DISTRIBUCION
20.02.01 TUBERIA DE 2" ml
20.02.02 TUBERIA DE 1 1/2" ml
20.02.03 TUBERIA DE 1" ml
20.02.04 TUBERIA DE 3/4" ml
20.02.05 TUBERIA DE 1/2" ml
20.03.00 LLAVES Y VALVULAS
20.03.01 LLAVE DE COMPUERTA DE 1/2" Pto

21.00.00 SISTEMA DE AGUA CALIENTE


21.01.00 SALIDA DE AGUA CALIENTE
21.01.01 SALIDA DE AGUA CALIENTE DE 1/2" Pto
21.02.00 REDES DE DISTRIBUCION
21.02.01 TUBERIA DE 1/2" ml

22.00.00 SISTEMA DE AGUA PLUVIAL


22.01.00 BAJADA DE LLUVIA Pto
22.02.00 TUBERIA PVC SAL 3" ml
22.03.00 Sumideros de 3" Pto
TOTAL

#REF!
#REF!

#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!
#REF!

#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!

2375.49
13392.38
2702.10
2423.80

7240.59
64.15

7807.40
1037.30
1766.00
3355.37

2375.49

1710.60 762510
1875.00 340.40625 121.573661
3320.36 23.76
14.5
3.3
981.31 41.56
98.00
268.70
147.10

208.80
107.80
16.21

40.00
469.00
44.00
1567.00

6349.77

16458.05
7304.74
2158.61

263.00 repite en
18.00 acabados
148.00
102.00
13.00
18.00
25.00
351.00
0.00
82.00
1.00
14.00
0.00

12.00
1.00
14.00

161.00
161.00
121.00
40.00
40.00
419.00
290.00
129.00
129.00
474.90
751.02

90.00
387.00
250.00
160.00
280.00
35.00

0.00

523.00

21.60
133.96
319.92
750.05
794.71

445.00

320.00

1451.10

5.00
162.53
5.00