Id ITEM Nombre de tarea Duracion Comienzo Fin

Calendario 03 ene '21 10 ene '21 17 ene '21 24 ene '21 31 ene '21 07 feb '21 14 feb '21 21 feb '21 28 feb '21 07 mar '21 14 mar '21 21 mar '21 28 mar '21 04 abr '21 11 abr '21 18 abr '21 25 abr '21 02 may '21 09 may '21 16 may '21 23 may '21 30 may '21 06 jun '21 13 jun '21 20 jun '21 27 jun '21 04 jul '21 11 jul '21 18 jul '21 25 jul '21 01 ago '21 08 ago '21 15 ago '21 22 ago '21 29 ago '21
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
1
2 MEJORAMIENTO DE LA ATENCIÓN  300 días jue  mar  300 día
3 Inicio de Obra 0 días jue 05/11/20 jue 05/11/20
4 COMPONENTE I: ADECUADA  240 días jue  vie  240 días
5 01 OBRAS PROVISIONALES 240 días jue 05/11/20 vie 02/07/21 240 días
6 01.01 OBRAS PROVISIONALES 38 días jue 05/11/20 sáb 12/12/20
7 01.01.01 CARTEL DE IDENTIFICACION DE  1 día jue 05/11/20 jue 05/11/20
LA OBRA DE 2 40X3 60 M
8 01.01.02 ALMACEN, CASETA DE  5 días jue 05/11/20 lun 09/11/20
GUARDIANIA Y OFICINA DE
9 01.01.03 CERCO PROVISIONAL CON  4 días vie 06/11/20 lun 09/11/20
MALLA ARPILLERA
10 01.01.04 MOVILIZACIÓN Y  27 días lun 16/11/20 sáb 12/12/20
DESMOVILIZACIÓN DE 240 días
11 01.02 INSTALACIONES PROVISIONALES 240 días jue 05/11/20 vie 02/07/21
12 01.02.01 ENERGÍA ELÉCTRICA  3 días jue 26/11/20 sáb 28/11/20
PROVISIONAL 240 días
13 01.02.02 CONSUMO DE ENERGIA  240 días jue 05/11/20 vie 02/07/21
ELECTRICA
14 01.03 SEGURIDAD, SALUD Y MEDIO  240 días jue 05/11/20 vie 02/07/21 240 días
AMBIENTE
15 01.03.01 ELABORACION DEL PLAN DE  12 días jue 05/11/20 lun 16/11/20
SEGURIDAD Y SALUD EN EL
16 01.03.02 EQUIPOS DE PROTECCION  146 días jue 05/11/20 mar 30/03/21 146 días
INDIVIDUAL
17 01.03.03 EQUIPOS DE PROTECCION  240 días jue 05/11/20 vie 02/07/21 240 días
COLECTIVA
18 01.03.04 SEÑALIZACION TEMPORAL DE  240 días jue 05/11/20 vie 02/07/21 240 días
SEGURIDAD
19 01.03.05 CAPACITACION SOBRE  240 días jue 05/11/20 vie 02/07/21 240 días
SEGURIDAD Y SALUD
20 01.03.06 RECURSOS PARA RESPUESTAS  240 días jue 05/11/20 vie 02/07/21 240 días
ANTE EMERGENCIAS EN
21 01.03.07 AGUA DE MESA PARA  240 días jue 05/11/20 vie 02/07/21 240 días
CONSUMO HUMANO
22 01.03.08 EXAMENES MEDICOS 240 días jue 05/11/20 vie 02/07/21 240 días
23 01.04 TRABAJOS PRELIMINARES 226 días jue 05/11/20 vie 18/06/21 226 días
24 01.04.01 LIMPIEZA DE TERRENO  2 días jue 05/11/20 vie 06/11/20
MANUAL
25 01.04.02 TRAZO, NIVELES Y REPLANTEO  2 días jue 05/11/20 vie 06/11/20
PRELIMINAR
26 01.04.03 CORTE C/EQUIPO EN MATERIAL 100 días lun 23/11/20 mar 02/03/21 100 días
SUELTO H 0 40M PROMEDIO
27 01.04.04 ELIMINACION DE MATERIAL  100 días jue 11/03/21 vie 18/06/21 100 días
EXCEDENTE C/MAQUINARIA
28 01.05 MITIGACION Y CONTROL  240 días jue 05/11/20 vie 02/07/21 240 días
AMBIENTAL
29 01.05.01 CAPACITACION PERMANENTE  240 días jue 05/11/20 vie 02/07/21 240 días
AL PERSONAL SOBRE SALUD
30 01.05.02 CONTROL DE PROPAGACION DE 240 días jue 05/11/20 vie 02/07/21 240 días
PARTICULAS
31 01.05.03 CONTROL DE DESECHOS  240 días jue 05/11/20 vie 02/07/21 240 días
SOLIDOS
32 01.06 MONITOREO ARQUEOLOGICO 21 días mié 02/12/20 mar 22/12/20
33 01.06.01 EJECUCIÓN DEL PLAN DE  21 días mié 02/12/20 mar 22/12/20
MONITOREO ARQUEOLOGICO
34
35 02 BLOQUE A ‐ UPS ADMINISTRACION Y  239 días vie 06/11/20 vie 02/07/21 239 días
RESIDENCIA
36 02.01 ESTRUCTURAS 221 días vie 06/11/20 lun 14/06/21 221 días
37 02.01.01 OBRAS PRELIMINARES 1 día vie 06/11/20 vie 06/11/20
38 02.01.01.01 TRAZO, NIVELES Y  1 día vie 06/11/20 vie 06/11/20
REPLANTEO
39 02.01.02 MOVIMIENTO DE TIERRAS 195 días sáb 07/11/20 jue 20/05/21 195 días
40 02.01.02.01 EXCAVACION MANUAL DE  15 días sáb 07/11/20 sáb 21/11/20
ZANJAS PARA ZAPATAS
41 02.01.02.02 EXCAVACION MANUAL DE  16 días lun 04/01/21 mar 19/01/21 16 días
ZANJA PARA CIMIENTOS 11 días
42 02.01.02.03 RELLENO Y COMPACTADO  11 días mié 27/01/21 sáb 06/02/21
C/EQUIPO MATERIAL
43 02.01.02.04 NIVELACION INTERIOR Y  6 días lun 19/04/21 sáb 24/04/21 6 días
COMPACTADO DEL 10 días
44 02.01.02.05 AFIRMADO DE 4" PARA  10 días mié 21/04/21 vie 30/04/21
PISOS
45 02.01.02.06 ACARREO DE MATERIAL  18 días vie 18/12/20 lun 04/01/21 18 días
EXCEDENTE D 30 2 días
46 02.01.02.07 ELIMINACION DE MATERIAL  2 días mié 19/05/21 jue 20/05/21
EXCEDENTE C/MAQUINARIA
47 02.01.03 IMPERMEABILIZACIÓN 18 días vie 11/12/20 lun 28/12/20 s
48 02.01.03.01 IMPERMEABILIZACION CON  18 días vie 11/12/20 lun 28/12/20 s
ASFALTO
49 02.01.04 OBRAS DE CONCRETO SIMPLE 173 días jue 24/12/20 lun 14/06/21 173 días
50 02.01.04.01 SOLADOS Y CIMIENTOS 33 días jue 24/12/20 lun 25/01/21 33 días
51 02.01.04.01.01 SOLADO CON MEZCLA  1 día mié 06/01/21 mié 06/01/21 1 día
1 12 C H E 4" 10 días
52 02.01.04.01.02 SUBZAPATA DE  10 días jue 24/12/20 sáb 02/01/21
CONCRETO 1 10 C H
53 02.01.04.01.03 CIMIENTO CORRIDO:  10 días sáb 16/01/21 lun 25/01/21 10 días
CONCRETO CICLOPEO 25 días
54 02.01.04.02 FALSO PISO 25 días vie 21/05/21 lun 14/06/21
55 02.01.04.02.01 FALSO PISO E=4" C:H 1:8  25 días vie 21/05/21 lun 14/06/21 25 días
C/ADITIVO
56 02.01.04.03 SOBRECIMIENTOS 3 días lun 25/01/21 mié 27/01/21 3 días
57 02.01.04.03.01 SOBRECIMIENTO:  1 día mié 27/01/21 mié 27/01/21 1 día
CONCRETO F'C 175
58 02.01.04.03.02 SOBRECIMIENTO:  2 días lun 25/01/21 mar 26/01/21 2 días
ENCOFRADO Y
59 02.01.05 OBRAS DE CONCRETO  148 días jue 24/12/20 jue 20/05/21 148 días
ARMADO
60 02.01.05.01 ZAPATAS 33 días jue 24/12/20 lun 25/01/21 33 días
61 02.01.05.01.01 ZAPATAS: CONCRETO  18 días vie 08/01/21 lun 25/01/21 18 días
F'C 210 KG/CM2
62 02.01.05.01.02 ACERO CORRUGADO  5 días jue 24/12/20 lun 28/12/20
F 4 200 k / 2
63 02.01.05.02 VIGAS DE CIMENTACION 5 días jue 07/01/21 lun 11/01/21 5 días
64 02.01.05.02.01 VIGAS DE CIMENTACIÓN:  1 día lun 11/01/21 lun 11/01/21 1 día
CONCRETO F'C 210
65 02.01.05.02.02 VIGAS DE CIMENTACIÓN:  3 días sáb 09/01/21 lun 11/01/21 3 días
ENCOFRADO Y
66 02.01.05.02.03 ACERO CORRUGADO  2 días jue 07/01/21 vie 08/01/21 2 días
F 4 200 k / 2
67 02.01.05.03 SOBRECIMIENTO ARMADO 17 días sáb 23/01/21 lun 08/02/21 17 días
68 02.01.05.03.01 SOBRECIMIENTO  11 días vie 29/01/21 lun 08/02/21 11 días
ARMADO CONCRETO
69 02.01.05.03.02 SOBRECIMIENTO  11 días vie 29/01/21 lun 08/02/21 11 días
ARMADO ENCOFRADO Y
70 02.01.05.03.03 ACERO CORRUGADO  6 días sáb 23/01/21 jue 28/01/21 6 días
F 4 200 k / 2
71 02.01.05.04 COLUMNAS Y PLACAS 115 días sáb 26/12/20 lun 19/04/21 115 días
72 02.01.05.04.01 COLUMNAS Y PLACAS:  17 días mar 02/03/21 jue 18/03/21 17 días
CONCRETO F'C 210
73 02.01.05.04.02 COLUMNAS Y PLACAS:  7 días vie 12/03/21 jue 18/03/21 7 días
CONCRETO F'C 210
74 02.01.05.04.03 COLUMNAS Y PLACAS:  49 días mar 02/03/21 lun 19/04/21 49 días
ENCOFRADO Y
75 02.01.05.04.04 ACERO CORRUGADO  53 días sáb 26/12/20 mar 16/02/21 53 días
F 4 200 k / 2
76 02.01.05.05 COLUMNETAS DE AMARRE 67 días lun 01/02/21 jue 08/04/21 67 días
77 02.01.05.05.01 COLUMNETAS DE  17 días mar 23/03/21 jue 08/04/21 17 días
AMARRE CONCRETO
78 02.01.05.05.02 COLUMNETAS DE  17 días mar 23/03/21 jue 08/04/21 17 días
AMARRE CONCRETO 29 días
79 02.01.05.05.03 COLUMNETAS DE  29 días jue 11/03/21 jue 08/04/21
AMARRE ENCOFRADO Y
80 02.01.05.05.04 ACERO CORRUGADO  44 días lun 01/02/21 mar 16/03/21 44 días
F 4 200 k / 2 52 días
81 02.01.05.06 VIGAS 52 días mar 30/03/21 jue 20/05/21
82 02.01.05.06.01 VIGAS: CONCRETO  42 días vie 09/04/21 jue 20/05/21 42 días
F'C 210 k / 2 52 días
83 02.01.05.06.02 VIGAS: ENCOFRADO Y  52 días mar 30/03/21 jue 20/05/21
DESENCOFRADO
84 02.01.05.06.03 ACERO CORRUGADO  46 días lun 05/04/21 jue 20/05/21 46 días
F 4 200 k / 2 12 días
85 02.01.05.07 VIGUETAS DE AMARRE 12 días lun 29/03/21 vie 09/04/21
86 02.01.05.07.01 VIGUETAS DE AMARRE:  8 días vie 02/04/21 vie 09/04/21 8 días
CONCRETO F'C 175 8 días
87 02.01.05.07.02 VIGUETAS DE AMARRE:  8 días vie 02/04/21 vie 09/04/21
ENCOFRADO Y
88 02.01.05.07.03 ACERO CORRUGADO  8 días lun 29/03/21 lun 05/04/21 8 días
F 4 200 k / 2 7 días
89 02.01.05.08 LOSA MACIZA 7 días vie 30/04/21 jue 06/05/21
90 02.01.05.08.01 LOSA MACIZA:  7 días vie 30/04/21 jue 06/05/21 7 días
CONCRETO F'C 210 7 días
91 02.01.05.08.02 LOSA MACIZA:  7 días vie 30/04/21 jue 06/05/21
ENCOFRADO Y
92 02.01.05.08.03 ACERO CORRUGADO  7 días vie 30/04/21 jue 06/05/21 7 días
F 4 200 k / 2 52 días
93 02.01.05.09 LOSAS ALIGERADAS 52 días mar 30/03/21 jue 20/05/21
94 02.01.05.09.01 LOSA ALIGERADA:  42 días vie 09/04/21 jue 20/05/21 42 días
CONCRETO F'C 210 52 días
95 02.01.05.09.02 LOSA ALIGERADA:  52 días mar 30/03/21 jue 20/05/21
ENCOFRADO Y
96 02.01.05.09.03 LOSA ALIGERADA:  49 días vie 02/04/21 jue 20/05/21 49 días
LADRILLO HUECO
97 02.01.05.09.04 ACERO CORRUGADO  52 días mar 30/03/21 jue 20/05/21 52 días
F 4 200 k / 2
98 02.01.05.10 ESCALERAS 3 días mar 18/05/21 jue 20/05/21 3 días
99 02.01.05.10.01 ESCALERAS: CONCRETO  1 día jue 20/05/21 jue 20/05/21 1 día
F'C 210 K / 2
100 02.01.05.10.02 ESCALERAS: ENCOFRADO  3 días mar 18/05/21 jue 20/05/21 3 días
Y DESENCOFRADO
101 02.01.05.10.03 ACERO CORRUGADO  2 días mié 19/05/21 jue 20/05/21 2 días
F 4 200 k / 2
102 02.01.05.11 MESONES CONCRETO  4 días lun 10/05/21 jue 13/05/21 4 días
ARMADO
103 02.01.05.11.01 MESON DE CONCRETO:  4 días lun 10/05/21 jue 13/05/21 4 días
CONCRETO F'C 175
104 02.01.05.11.02 MESON DE CONCRETO:  4 días lun 10/05/21 jue 13/05/21 4 días
ENCOFRADO Y
105 02.01.05.11.03 ACERO CORRUGADO  2 días mié 12/05/21 jue 13/05/21 2 días
F 4 200 k / 2
106 02.01.06 VARIOS 113 días lun 15/02/21 lun 07/06/21 113 días
107 02.01.06.01 CURADO DE ELEMENTOS DE  81 días lun 15/02/21 jue 06/05/21 81 días
CONCRETO
108 02.01.06.02 JUNTA DE CONSTRUCCION  12 días jue 27/05/21 lun 07/06/21 12 días
DE JEBE MICROPOROSO
109 02.01.06.03 ESTRUCTURA DE SOPORTE  1 día lun 24/05/21 lun 24/05/21 1 día
TANQUE ELEVADO
110 02.02 ARQUITECTURA 144 días mar 09/02/21 vie 02/07/21 144 días
111 02.02.01 MUROS Y TABIQUES DE  86 días mar 09/02/21 mié 05/05/21 86 días
ALBAÑILERIA
112 02.02.01.01 MURO DE LADRILLO KK TIPO 58 días mar 09/02/21 mié 07/04/21 58 días
IV SOGA M 1 1 5 E 1 5 CM
113 02.02.01.02 MURO DE LADRILLO KK TIPO 42 días jue 11/02/21 mié 24/03/21 42 días
IV CABEZA M 1 1 5 E 1 5 CM
114 02.02.01.03 TABIQUERÍA DE SISTEMA  2 días mar 04/05/21 mié 05/05/21 2 días
DRYWALL
115 02.02.02 REVOQUES ENLUCIDOS Y  76 días mié 14/04/21 lun 28/06/21 76 días
MOLDURAS
116 02.02.02.01 TARRAJEO PRIMARIO O  12 días sáb 05/06/21 mié 16/06/21 12 días
RAYADO C/MEZCLA 1 5
117 02.02.02.02 TARRAJEO MUROS  30 días jue 13/05/21 vie 11/06/21 30 días
INTERIORES MEZCLA C A 1 5
118 02.02.02.03 TARRAJEO MUROS  30 días jue 13/05/21 vie 11/06/21 30 días
EXTERIORES MEZCLA C A 1 5
119 02.02.02.04 TARRAJEO EN COLUMNAS  30 días mié 05/05/21 jue 03/06/21 30 días
MEZCLA C A 1 5 E 1 5 38 días
120 02.02.02.05 TARRAJEO EN VIGAS  38 días mié 05/05/21 vie 11/06/21
MEZCLA C A 1 5 E 1 5
121 02.02.02.06 VESTIDURA DE DERRAMES  24 días sáb 15/05/21 lun 07/06/21 24 días
MEZCLA C A 1 5 E 1 5 4 días
122 02.02.02.07 BRUÑAS SEGÚN DETALLE 1"  4 días vie 04/06/21 lun 07/06/21
1
123 02.02.02.08 BRUÑA PARA RODOJUNTA  4 días vie 04/06/21 lun 07/06/21 4 días
DE COLOR SEGÚN DETALLE 3 días
124 02.02.02.09 RODOJUNTA DE COLOR GRIS 3 días sáb 26/06/21 lun 28/06/21
SEGÚN DETALLE
125 02.02.02.10 ACABADO MICROCEMENTO  3 días mié 14/04/21 vie 16/04/21 3 días
GRIS OSCURO 38 días
126 02.02.03 CIELORRASOS 38 días lun 17/05/21 mié 23/06/21
127 02.02.03.01 TARRAJEO DE CIELO RASO  38 días lun 17/05/21 mié 23/06/21 38 días
MEZCLA 1 5 C A E 1 5CM 16 días
128 02.02.04 PISOS Y PAVIMENTOS 16 días mar 08/06/21 mié 23/06/21
129 02.02.04.01 CONTRAPISO C:H 1:8 E=2" 2 días mar 15/06/21 mié 16/06/21 2 días
130 02.02.04.02 PISO CERAMICA 0.45x0.45m  6 días mié 16/06/21 lun 21/06/21 6 días
(GRIS CLARO
131 02.02.04.03 PISO PORCELANATO  7 días mar 08/06/21 lun 14/06/21 7 días
0 60 0 60 1 día
132 02.02.04.04 PISO PORCELANATO  1 día mar 15/06/21 mar 15/06/21
0 60 0 60M
133 02.02.04.05 REVESTIMIENTO CON  2 días mar 22/06/21 mié 23/06/21 2 días
PORCELANATO 0 60 0 60M 2 días
134 02.02.04.06 REVESTIMIENTO CON  2 días mié 16/06/21 jue 17/06/21
PORCELANATO 0 60 0 60M
135 02.02.04.07 REVESTIMIENTO CON  1 día vie 18/06/21 vie 18/06/21 1 día
PORCELANATO 1 20 0 60M
136 02.02.05 ZOCALOS Y CONTRAZOCALOS 14 días sáb 19/06/21 vie 02/07/21 14 días
137 02.02.05.01 ZOCALO PORCELANATO  7 días vie 25/06/21 jue 01/07/21 7 días
0 60 0 60
138 02.02.05.02 ZOCALO CERAMICO  2 días mié 30/06/21 jue 01/07/21 2 días
0 45 0 45
139 02.02.05.03 LISTELO DE PORCELANATO  2 días mié 30/06/21 jue 01/07/21 2 días
CORTADO 0 60 0 10
140 02.02.05.04 LISTELO DE CERAMICO  1 día vie 02/07/21 vie 02/07/21 1 día
CORTADO 0 45 0 10
141 02.02.05.05 CONTRAZOCALO  5 días sáb 19/06/21 mié 23/06/21 5 días
PORCELANATO
142 02.02.05.06 CONTRAZOCALO CERAMICO  2 días mar 22/06/21 mié 23/06/21 2 días
ANTIDESLIZANTE GRIS
143 02.02.05.07 CONTRAZOCALO SANITARIO  8 días lun 21/06/21 lun 28/06/21 8 días
DE CONCRETO 0 10 0 10
144 02.02.05.08 CONTRAZOCALO CEMENTO  3 días sáb 26/06/21 lun 28/06/21 3 días
FROTACHADO GRIS OSCURO
145 02.02.06 CARPINTERIA DE MADERA 22 días lun 12/04/21 lun 03/05/21 22 días
146 02.02.06.01 PUERTA CONTRAPLACADA  16 días lun 12/04/21 mar 27/04/21 16 días
C/T i l 6 00 MARCO
147 02.02.06.02 PUERTA MADERA TABLERO  3 días mar 27/04/21 jue 29/04/21 3 días
C/MARCO DE MADERA
148 02.02.06.03 PUERTA MADERA TABLERO  1 día jue 29/04/21 jue 29/04/21 1 día
C/MARCO DE MADERA

Tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica
Proyecto: LOS OLIVOS_LA YARA
División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso

Página 1
Id ITEM Nombre de tarea Duracion Comienzo Fin
Calendario 03 ene '21 10 ene '21 17 ene '21 24 ene '21 31 ene '21 07 feb '21 14 feb '21 21 feb '21 28 feb '21 07 mar '21 14 mar '21 21 mar '21 28 mar '21 04 abr '21 11 abr '21 18 abr '21 25 abr '21 02 may '21 09 may '21 16 may '21 23 may '21 30 may '21 06 jun '21 13 jun '21 20 jun '21 27 jun '21 04 jul '21 11 jul '21 18 jul '21 25 jul '21 01 ago '21 08 ago '21 15 ago '21 22 ago '21 29 ago '21
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
149 02.02.06.04 PUERTA CONTRAPLACADA  2 días jue 29/04/21 vie 30/04/21 2 días
C/PERSIANA EN EL SOBRE
150 02.02.06.05 PUERTA MADERA TABLERO  3 días sáb 01/05/21 lun 03/05/21 3 días
C/PLANCHA DE ACERO INOX 5 días
151 02.02.06.06 DIVISION DE MELAMINA 18  5 días jue 29/04/21 lun 03/05/21
MM PARA SS HHH SEGÚN
152 02.02.06.07 PUERTA DE MELAMINA 18  3 días sáb 01/05/21 lun 03/05/21 3 días
MM PARA SS HHH SEGÚN 1 día
153 02.02.06.08 DIVISION DE MELAMINA 18  1 día lun 03/05/21 lun 03/05/21
MM PARA URINARIOS
154 02.02.07 CARPINTERIA METALICA 6 días jue 20/05/21 mar 25/05/21 6 días
155 02.02.07.01 BARANDAS METALICAS 3 días jue 20/05/21 sáb 22/05/21 3 días
156 02.02.07.01.01 BARANDA DE F°G° TUBO  2 días jue 20/05/21 vie 21/05/21 2 días
CIRCULAR DE Ø 2" 1 día
157 02.02.07.01.02 PASAMANO DE F°G°  1 día sáb 22/05/21 sáb 22/05/21
TUBO CIRCULAR DE Ø 2"
158 02.02.07.02 ESTRUCTURAS METALICAS 2 días lun 24/05/21 mar 25/05/21 2 días
159 02.02.07.02.01 PUERTA METÁLICA  2 días lun 24/05/21 mar 25/05/21 2 días
C/MARCO DE F°N° 4" 4"
160 02.02.07.02.02 CANTONERA  2 días lun 24/05/21 mar 25/05/21 2 días
ANTIDESLIZANTE DE 2 días
161 02.02.07.02.03 CLARABOYA DE TECHO  2 días lun 24/05/21 mar 25/05/21
TIPO 1
162 02.02.07.02.04 CLARABOYA DE TECHO  2 días lun 24/05/21 mar 25/05/21 2 días
TIPO 2
163 02.02.07.02.05 CLARABOYA DE TECHO  2 días lun 24/05/21 mar 25/05/21 2 días
TIPO 3
164 02.02.07.02.06 BARRA DE ALUMINIO  2 días lun 24/05/21 mar 25/05/21 2 días
CROMADO DE 1 1/2"
165 02.02.07.02.07 LETRAS METALICAS  1 día mar 25/05/21 mar 25/05/21 1 día
SEGUN DETALLE
166 02.02.08 CERRAJERIA 4 días vie 30/04/21 lun 03/05/21 4 días
167 02.02.08.01 PICAPORTE TIPO CERROJO  1 día vie 30/04/21 vie 30/04/21 1 día
PORTA CANDADO P/PUERTA
168 02.02.08.02 CERRADURA DE 3 GOLPES 3 días sáb 01/05/21 lun 03/05/21 3 días
169 02.02.08.03 CERRADURA DE EMBUTIR 3  3 días sáb 01/05/21 lun 03/05/21 3 días
GOLPES
170 02.02.08.04 CERRADURA TIPO PERILLA 3 días sáb 01/05/21 lun 03/05/21 3 días
171 02.02.08.05 BISAGRA CAPUCHINA DE  3 días sáb 01/05/21 lun 03/05/21 3 días
ALUMINIO DE 4" X 4"
172 02.02.08.06 BISAGRA ESTRUCTURAL DE  1 día lun 03/05/21 lun 03/05/21 1 día
FIERRO DE 3/8 4"
173 02.02.08.07 BISAGRA PIVOT DE GIRO  1 día lun 03/05/21 lun 03/05/21 1 día
VAIVEN
174 02.02.08.08 JALADOR O TIRADOR  1 día lun 03/05/21 lun 03/05/21 1 día
CROMADO DE 128MM PARA
175 02.02.09 VIDRIOS, CRISTALES Y  13 días lun 03/05/21 sáb 15/05/21 13 días
SIMILARES
176 02.02.09.01 VENTANA CON PERFILES DE  3 días lun 03/05/21 mié 05/05/21 3 días
ALUMNIO TIPO SISTEMA DE
177 02.02.09.02 INSTALACION DE ESPEJO  2 días jue 06/05/21 vie 07/05/21 2 días
E 6MM
178 02.02.09.03 MURO CORTINA CON  8 días sáb 08/05/21 sáb 15/05/21 8 días
VIDRIO REFLECTANTE DE
179 02.02.09.04 MAMPARA C/MARCO  3 días jue 13/05/21 sáb 15/05/21 3 días
METALICO ALUMINIZADO
180 02.02.10 PINTURA 35 días mié 21/04/21 mar 25/05/21 35 días
181 02.02.10.01 PINTURA OLEO MATE 02  9 días mié 21/04/21 jue 29/04/21 9 días
MANOS EN INTERIORES
182 02.02.10.02 PINTURA LATEX SATINADO  9 días mié 21/04/21 jue 29/04/21 9 días
02 MANOS EN EXTERIORES
183 02.02.10.03 PINTURA OLEO MATE 2  8 días jue 22/04/21 jue 29/04/21 8 días
MANOS EN CIELO RASO
184 02.02.10.04 PINTURA LATEX SATINADO  3 días mar 27/04/21 jue 29/04/21 3 días
02 MANOS EN COLUMNAS Y
185 02.02.10.05 PINTURA LATEX SATINADO  2 días mié 28/04/21 jue 29/04/21 2 días
02 MANOS EN VESTIDURA
186 02.02.10.06 PINTURA BARNIZ 02 MANOS 2 días mar 27/04/21 mié 28/04/21 2 días
EN PUERTAS DE MADERA
187 02.02.10.07 PINTURA DE ESMALTE  2 días jue 29/04/21 vie 30/04/21 2 días
COLOR GRIS CLARO 02 2 días
188 02.02.10.08 PINTURA ANTICORROSIVA  2 días lun 24/05/21 mar 25/05/21
EN PUERTAS DE METAL
189 02.02.11 CUBIERTAS 7 días mié 23/06/21 mar 29/06/21 7 días
190 02.02.11.01 CUBIERTA LADRILLO  3 días mié 23/06/21 vie 25/06/21 3 días
PASTELERO ASENTADO
191 02.02.11.02 IMPERMEABILIZACION DE  4 días sáb 26/06/21 mar 29/06/21 4 días
LADRILLO PASTELERO CON 4 días
192 02.02.11.03 PISO DE CEMENTO PULIDO,  4 días vie 25/06/21 lun 28/06/21
BRUÑADO 1"X1 EN
193 02.02.12 VARIOS 16 días jue 27/05/21 vie 11/06/21 16 días
194 02.02.12.01 JUNTA DE DILATACIÓN  3 días jue 27/05/21 sáb 29/05/21 3 días
C/TEKNOPORT Y SELLANTE
195 02.02.12.02 TAPA JUNTA METÁLICO  1 día mar 01/06/21 mar 01/06/21 1 día
SEGÚN DISEÑO 2 días
196 02.02.12.03 PROTECTOR METÁLICO DE  2 días mié 02/06/21 jue 03/06/21
ESQUINEROS
197 02.02.12.04 GUARDACAMILLAS SEGÚN  1 día vie 04/06/21 vie 04/06/21 1 día
DETALLE 7 días
198 02.02.12.05 LIMPIEZA FINAL DE OBRA 7 días sáb 05/06/21 vie 11/06/21
199 02.03 INSTALACIONES SANITARIAS 24 días lun 12/04/21 mié 05/05/21 24 días
200 02.03.01 APARATOS SANITARIOS Y  12 días jue 22/04/21 lun 03/05/21 12 días
ACCESORIOS
201 02.03.01.01 APARATOS SANITARIOS 12 días jue 22/04/21 lun 03/05/21 12 días
202 02.03.01.01.01 INODORO ONE PIECE SAVO5 días jue 29/04/21 lun 03/05/21 5 días
203 02.03.01.01.02 LAVAMANOS TIPO FONTA 5 días jue 29/04/21 lun 03/05/21 5 días
204 02.03.01.01.03 LAVAMANOS TIPO FONTA 1 día lun 03/05/21 lun 03/05/21 1 día
205 02.03.01.01.04 LAVAMANOS TIPO OVALIN5 días jue 29/04/21 lun 03/05/21 5 días
206 02.03.01.01.05 URINARIO TIPO BAMBI DE 4 días vie 30/04/21 lun 03/05/21 4 días
207 02.03.01.01.06 LAVADERO DE ACERO INO 5 días jue 29/04/21 lun 03/05/21 5 días
208 02.03.01.01.07 LAVADERO DE ACERO INO 1 día lun 03/05/21 lun 03/05/21 1 día
209 02.03.01.01.08 DUCHA ECO ROCIADOR DE3 días sáb 01/05/21 lun 03/05/21 3 días
210 02.03.01.01.09 GRIFERIA CLASICA INCLUID3 días sáb 01/05/21 lun 03/05/21 3 días
211 02.03.01.01.10 COLOCACION DE APARATO12 días jue 22/04/21 lun 03/05/21 12 días
212 02.03.01.02 ACCESORIOS SANITARIOS 4 días vie 30/04/21 lun 03/05/21 4 días
213 02.03.01.02.01 DISPENSADOR DE PAPEL T3 días sáb 01/05/21 lun 03/05/21 3 días
214 02.03.01.02.02 DISPENSADOR DE JABON L1 día lun 03/05/21 lun 03/05/21 1 día
215 02.03.01.02.03 PAPELERA DE LOSA Y BAR 3 días sáb 01/05/21 lun 03/05/21 3 días
216 02.03.01.02.04 JABONERA DE LOZA VITRIF3 días sáb 01/05/21 lun 03/05/21 3 días
217 02.03.01.02.05 PERCHERO DE LOSA VITRIF1 día lun 03/05/21 lun 03/05/21 1 día
218 02.03.01.02.06 COLOCACION DE ACCESOR4 días vie 30/04/21 lun 03/05/21 4 días
219 02.03.02 SISTEMA DE AGUA FRIA 9 días lun 12/04/21 mar 20/04/21 9 días
220 02.03.02.01 SALIDAS DE AGUA FRIA 3 días jue 15/04/21 sáb 17/04/21 3 días
221 02.03.02.01.01 SALIDA DE AGUA P/APARA3 días jue 15/04/21 sáb 17/04/21 3 días
222 02.03.02.02 REDES DE DISTRIBUCION 3 días lun 12/04/21 mié 14/04/21 3 días
223 02.03.02.02.01 TUBERÍA PVC Ø 1 1/2 " C/ 1 día lun 12/04/21 lun 12/04/21 1 día
224 02.03.02.02.02 TUBERÍA PVC Ø 1 1/4" C/R1 día mar 13/04/21 mar 13/04/21 1 día
225 02.03.02.02.03 TUBERÍA PVC Ø 1 " C/R. CL1 día mié 14/04/21 mié 14/04/21 1 día
226 02.03.02.02.04 TUBERÍA PVC Ø 3/4 " C/R. 2 días mar 13/04/21 mié 14/04/21 2 días
227 02.03.02.02.05 TUBERÍA PVC Ø 1/2" C/R.  2 días mar 13/04/21 mié 14/04/21 2 días
228 02.03.02.02.06 PRUEBA HIDRAÚLICA INTE2 días mar 13/04/21 mié 14/04/21 2 días
229 02.03.02.03 SUM. E INSTALACIÓN DE  5 días jue 15/04/21 lun 19/04/21 5 días
ACCESORIOS PVC
230 02.03.02.03.01 TEE PVC Ø 1 1/2"x1 1/2" C1 día jue 15/04/21 jue 15/04/21 1 día
231 02.03.02.03.02 TEE PVC Ø 1 1/4"x1 1/4" C1 día jue 15/04/21 jue 15/04/21 1 día
232 02.03.02.03.03 TEE PVC Ø 1"x1" C/R. C‐101 día jue 15/04/21 jue 15/04/21 1 día
233 02.03.02.03.04 TEE PVC Ø 3/4"x3/4" C/R. 1 día vie 16/04/21 vie 16/04/21 1 día
234 02.03.02.03.05 TEE PVC Ø 1/2"x1/2" C/R. 1 día vie 16/04/21 vie 16/04/21 1 día
235 02.03.02.03.06 REDUCCIÓN PVC Ø 1 1/2" 1 día vie 16/04/21 vie 16/04/21 1 día
236 02.03.02.03.07 REDUCCIÓN PVC Ø 1 1/4" 1 día sáb 17/04/21 sáb 17/04/21 1 día
237 02.03.02.03.08 REDUCCIÓN PVC Ø 1 " a 3/1 día sáb 17/04/21 sáb 17/04/21 1 día
238 02.03.02.03.09 REDUCCIÓN PVC Ø 3/4" a  1 día sáb 17/04/21 sáb 17/04/21 1 día
239 02.03.02.03.10 CODO PVC Ø 1 " x 90º C/R 1 día sáb 17/04/21 sáb 17/04/21 1 día
240 02.03.02.03.11 CODO PVC Ø 3/4" x 90º C/1 día lun 19/04/21 lun 19/04/21 1 día
241 02.03.02.03.12 CODO PVC Ø 1/2" x 90º C/2 días vie 16/04/21 sáb 17/04/21 2 días
242 02.03.02.04 VALVULAS DE CONTROL 3 días sáb 17/04/21 lun 19/04/21 3 días
243 02.03.02.04.01 VÁLVULA COMPUERTA PE 1 día lun 19/04/21 lun 19/04/21 1 día
244 02.03.02.04.02 VÁLVULA COMPUERTA PE 3 días sáb 17/04/21 lun 19/04/21 3 días
245 02.03.02.04.03 VÁLVULA COMPUERTA PE 1 día lun 19/04/21 lun 19/04/21 1 día
246 02.03.02.04.04 VÁLVULA TIPO GLOBO PES3 días sáb 17/04/21 lun 19/04/21 3 días
247 02.03.02.05 CAJAS PARA VALVULAS 3 días sáb 17/04/21 lun 19/04/21 3 días
248 02.03.02.05.01 CAJA DE MADERA SEGÚN  3 días sáb 17/04/21 lun 19/04/21 3 días
249 02.03.02.06 VARIOS 1 día mar 20/04/21 mar 20/04/21 1 día
250 02.03.02.06.01 FILTROS PARA AGUA 1 día mar 20/04/21 mar 20/04/21 1 día
251 02.03.03 SISTEMA DE DRENAJE PLUVIAL 7 días jue 15/04/21 mié 21/04/21 7 días
252 02.03.03.01 REDES DE RECOLECCIÓN 3 días lun 19/04/21 mié 21/04/21 3 días
253 02.03.03.01.01 TUBERÍA PVC SAP Ø 2" S/P3 días lun 19/04/21 mié 21/04/21 3 días
254 02.03.03.02 ACCESORIOS 3 días jue 15/04/21 sáb 17/04/21 3 días
255 02.03.03.02.01 YEE PVC SAP Ø 2"x2" S/P 1 día jue 15/04/21 jue 15/04/21 1 día
256 02.03.03.02.02 CODO 90º PVC SAP Ø 2" S/2 días vie 16/04/21 sáb 17/04/21 2 días
257 02.03.03.02.03 CODO 45º PVC SAP Ø 2" S/1 día sáb 17/04/21 sáb 17/04/21 1 día
258 02.03.03.02.04 SUMIDERO PVC SAP Ø3" S1 día sáb 17/04/21 sáb 17/04/21 1 día
259 02.03.03.02.05 SUMIDERO PVC SAP Ø2" S1 día sáb 17/04/21 sáb 17/04/21 1 día
260 02.03.03.03 POZO PERCOLADOR DE  5 días vie 16/04/21 mar 20/04/21 5 días
AGUAS PLUVIALES DE
261 02.03.03.03.01 EXCAVACION MANUAL EN1 día vie 16/04/21 vie 16/04/21 1 día
262 02.03.03.03.02 ACARREO DE MATERIAL EX1 día sáb 17/04/21 sáb 17/04/21 1 día
263 02.03.03.03.03 ELIMINACION DE MATERIA1 día mar 20/04/21 mar 20/04/21 1 día
264 02.03.03.03.04 RELLENO MANUAL CON A 1 día lun 19/04/21 lun 19/04/21 1 día
265 02.03.04 SISTEMA DE DESAGUE Y  20 días vie 16/04/21 mié 05/05/21 20 días
VENTILACION
266 02.03.04.01 SALIDAS DE DESAGUE 2 días vie 16/04/21 sáb 17/04/21 2 días
267 02.03.04.01.01 SALIDA DE DESAGUE PVC S2 días vie 16/04/21 sáb 17/04/21 2 días
268 02.03.04.01.02 SALIDA DE DESAGUE PVC S2 días vie 16/04/21 sáb 17/04/21 2 días
269 02.03.04.02 REDES DE DERIVACION 16 días mar 20/04/21 mié 05/05/21 16 días
270 02.03.04.02.01 TUBERÍA PVC SAP Ø 4" S/P2 días mar 20/04/21 mié 21/04/21 2 días
271 02.03.04.02.02 TUBERÍA PVC SAP Ø 3" S/P1 día mié 21/04/21 mié 21/04/21 1 día
272 02.03.04.02.03 TUBERÍA PVC SAP Ø 2" S/P2 días mar 20/04/21 mié 21/04/21 2 días
273 02.03.04.02.04 PRUEBA INTEGRAL DE EST 2 días mar 04/05/21 mié 05/05/21 2 días
274 02.03.04.03 ACCESORIOS DE REDES 9 días mié 21/04/21 jue 29/04/21 9 días
275 02.03.04.03.01 YEE PVC SAP Ø 4"x4" S/P 1 día mié 21/04/21 mié 21/04/21 1 día
276 02.03.04.03.02 YEE PVC SAP Ø 4"x3" S/P 1 día mié 21/04/21 mié 21/04/21 1 día
277 02.03.04.03.03 YEE PVC SAP Ø 4"x2" S/P 1 día jue 22/04/21 jue 22/04/21 1 día
278 02.03.04.03.04 YEE PVC SAP Ø 3"x3" S/P 1 día jue 22/04/21 jue 22/04/21 1 día
279 02.03.04.03.05 YEE PVC SAP Ø 3"x2" S/P 1 día jue 22/04/21 jue 22/04/21 1 día
280 02.03.04.03.06 YEE PVC SAP Ø 2"x2" S/P 2 días jue 22/04/21 vie 23/04/21 2 días
281 02.03.04.03.07 CODO 90º PVC SAP Ø 4" S/1 día sáb 24/04/21 sáb 24/04/21 1 día
282 02.03.04.03.08 CODO 90º PVC SAP Ø 3" S/1 día sáb 24/04/21 sáb 24/04/21 1 día
283 02.03.04.03.09 CODO 90º PVC SAP Ø 2" S/1 día sáb 24/04/21 sáb 24/04/21 1 día
284 02.03.04.03.10 CODO 45º PVC SAP Ø 4" S/1 día sáb 24/04/21 sáb 24/04/21 1 día
285 02.03.04.03.11 CODO 45º PVC SAP Ø 2" S/1 día lun 26/04/21 lun 26/04/21 1 día
286 02.03.04.03.12 TEE SANITARIA PVC SAP Ø 1 día lun 26/04/21 lun 26/04/21 1 día
287 02.03.04.03.13 TEE SANITARIA PVC SAP Ø 1 día lun 26/04/21 lun 26/04/21 1 día
288 02.03.04.03.14 SUMIDERO PVC SAP Ø3" S1 día lun 26/04/21 lun 26/04/21 1 día
289 02.03.04.03.15 SUMIDERO PVC SAP Ø2" S4 días vie 23/04/21 lun 26/04/21 4 días
290 02.03.04.03.16 REGISTRO ROSCADO DE B 2 días mar 27/04/21 mié 28/04/21 2 días
291 02.03.04.03.17 REGISTRO ROSCADO DE B 1 día mar 27/04/21 mar 27/04/21 1 día
292 02.03.04.03.18 REGISTRO ROSCADO DE B 2 días mié 28/04/21 jue 29/04/21 2 días
293 02.03.04.04 SISTEMA DE VENTILACION 7 días mar 27/04/21 lun 03/05/21 7 días
294 02.03.04.04.01 SALIDA DE VENTILACIÓN D2 días mar 27/04/21 mié 28/04/21 2 días
295 02.03.04.04.02 TUBERÍA PVC SAP Ø 2" S/P5 días jue 29/04/21 lun 03/05/21 5 días
296 02.03.04.04.03 SOMBRERO DE VENTILACI 1 día lun 03/05/21 lun 03/05/21 1 día

Tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica
Proyecto: LOS OLIVOS_LA YARA
División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso

Página 2
Id ITEM Nombre de tarea Duracion Comienzo Fin
Calendario 03 ene '21 10 ene '21 17 ene '21 24 ene '21 31 ene '21 07 feb '21 14 feb '21 21 feb '21 28 feb '21 07 mar '21 14 mar '21 21 mar '21 28 mar '21 04 abr '21 11 abr '21 18 abr '21 25 abr '21 02 may '21 09 may '21 16 may '21 23 may '21 30 may '21 06 jun '21 13 jun '21 20 jun '21 27 jun '21 04 jul '21 11 jul '21 18 jul '21 25 jul '21 01 ago '21 08 ago '21 15 ago '21 22 ago '21 29 ago '21
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
297 02.03.04.04.04 SOMBRERO DE VENTILACI 1 día lun 03/05/21 lun 03/05/21 1 día
298 02.03.04.04.05 SOMBRERO DE VENTILACI 3 días sáb 01/05/21 lun 03/05/21 3 días
299 02.04 INSTALACIONES ELECTRICAS Y  91 días mar 30/03/21 lun 28/06/21 91 días
MECANICAS
300 02.04.01 INSTALACIONES  30 días vie 07/05/21 sáb 05/06/21 30 días
ELECTROMECANICAS 30 días
301 02.04.01.01 SUMINISTRO DE  30 días vie 07/05/21 sáb 05/06/21
MATERIALES RP
302 02.04.01.01.01 POSTES Y ESTRUCTURAS 2 días vie 07/05/21 sáb 08/05/21 2 días
303 02.04.01.01.01.01 POSTE DE CONCRETO  2 días vie 07/05/21 sáb 08/05/21 2 días
ARMADO
304 02.04.01.01.01.02 POSTE DE CONCRETO  2 días vie 07/05/21 sáb 08/05/21 2 días
ARMADO 2 días
305 02.04.01.01.01.03 Bloque de concreto de 2 días vie 07/05/21 sáb 08/05/21
0 25 0 50 d
306 02.04.01.01.01.04 PERFIL ÁNGULAR DE  2 días vie 07/05/21 sáb 08/05/21 2 días
75 75 6 2 20 2 días
307 02.04.01.01.01.05 PERFIL ÁNGULAR DE  2 días vie 07/05/21 sáb 08/05/21
75 75 6 1 90
308 02.04.01.01.01.06 PERFIL ÁNGULAR  2 días vie 07/05/21 sáb 08/05/21 2 días
(RIOSTRA) DE 75 75 6 2 días
309 02.04.01.01.01.07 PERFIL ÁNGULAR DE  2 días vie 07/05/21 sáb 08/05/21
75 75 6 3 00
310 02.04.01.01.01.08 PERFIL ÁNGULAR DE  2 días vie 07/05/21 sáb 08/05/21 2 días
64 64 6 1 40
311 02.04.01.01.01.09 PERFIL ÁNGULAR DE  2 días vie 07/05/21 sáb 08/05/21 2 días
75 75 6 1 80
312 02.04.01.01.01.10 PERFIL ÁNGULAR DE  2 días vie 07/05/21 sáb 08/05/21 2 días
75 75 6 1 10
313 02.04.01.01.01.11 PERFIL ÁNGULAR  2 días vie 07/05/21 sáb 08/05/21 2 días
(RIOSTRA) DE 64 64 6
314 02.04.01.01.01.12 ABRAZADERA  2 días vie 07/05/21 sáb 08/05/21 2 días
PARTIDA DE F°G°
315 02.04.01.01.01.13 MEDIA PLATAFORMA  2 días vie 07/05/21 sáb 08/05/21 2 días
DE C A V DE 1 10/750
316 02.04.01.01.02 CONDUCTORES  18 días lun 17/05/21 jue 03/06/21 18 días
ELÉCTRICOS
317 02.04.01.01.02.01 CONDUCTOR DE MT  3 días lun 17/05/21 mié 19/05/21 3 días
N2XSY UNIPOLAR 25
318 02.04.01.01.02.02 CONDUCTOR DE  3 días lun 17/05/21 mié 19/05/21 3 días
ALEACION DE
319 02.04.01.01.02.03 CONDUCTOR DE  2 días jue 20/05/21 vie 21/05/21 2 días
COBRE DESNUDO DE
320 02.04.01.01.02.04 ALAMBRE DE AMARRE 3 días lun 17/05/21 mié 19/05/21 3 días
DE ALUMINIO
321 02.04.01.01.02.05 CABLE CONTROL TIPO  3 días mar 01/06/21 jue 03/06/21 3 días
NYY 7X4MM2 PARA
322 02.04.01.01.02.06 CONDUCTORES LIBRE  3 días mar 01/06/21 jue 03/06/21 3 días
DE HALÓGENOS
323 02.04.01.01.02.07 VARILLA DE ARMAR  2 días lun 17/05/21 mar 18/05/21 2 días
PREFORMADA SIMPLE
324 02.04.01.01.03 SUMINISTRO DE  5 días lun 10/05/21 vie 14/05/21 5 días
SUBESTACION
325 02.04.01.01.03.01 TRANSFORMADOR  5 días lun 10/05/21 vie 14/05/21 5 días
TRIFASICO TIPO SECO
326 02.04.01.01.03.02 CELDA DE LLEGADA Y  5 días lun 10/05/21 vie 14/05/21 5 días
PROTECCIÓN PARA 10
327 02.04.01.01.03.03 GRUPO  5 días lun 10/05/21 vie 14/05/21 5 días
ELECTROGENO
328 02.04.01.01.04 EQUIPOS DE  5 días lun 10/05/21 vie 14/05/21 5 días
TRANSFORMACION
329 02.04.01.01.04.01 TRANSFORMADOR  5 días lun 10/05/21 vie 14/05/21 5 días
COMBINADO DE
330 02.04.01.01.04.02 SECCIONADOR  5 días lun 10/05/21 vie 14/05/21 5 días
FUSIBLE UNIPOLAR
331 02.04.01.01.04.03 FUSIBLE DE  5 días lun 10/05/21 vie 14/05/21 5 días
EXPULSION TIPO K
332 02.04.01.01.05 AISLADORES 3 días lun 17/05/21 mié 19/05/21 3 días
333 02.04.01.01.05.01 AISLADOR  3 días lun 17/05/21 mié 19/05/21 3 días
POLIMERICO TIPO PIN
334 02.04.01.01.05.02 AISLADOR  3 días lun 17/05/21 mié 19/05/21 3 días
POLIMERICO TIPO
335 02.04.01.01.06 FERRETERIA Y  3 días lun 17/05/21 mié 19/05/21 3 días
ACCESORIOS 3 días
336 02.04.01.01.06.01 ARANDELA  3 días lun 17/05/21 mié 19/05/21
CUADRADA PLANA DE
337 02.04.01.01.06.02 CINTA PLANA DE  3 días lun 17/05/21 mié 19/05/21 3 días
ARMAR DE ALUMINIO 3 días
338 02.04.01.01.06.03 CONECTOR DE COBRE  3 días lun 17/05/21 mié 19/05/21
TIPO PERNO PARTIDO
339 02.04.01.01.06.04 CONECTORES DE  3 días lun 17/05/21 mié 19/05/21 3 días
AL/CU (35 240 2) 3 días
340 02.04.01.01.06.05 CONECTORES DE  3 días lun 17/05/21 mié 19/05/21
AL/AL (35 240 2)
341 02.04.01.01.06.06 FLEJE DE ACERO  3 días lun 17/05/21 mié 19/05/21 3 días
INOXIDABLE 3 días
342 02.04.01.01.06.07 HEBILLA DE A°G° PARA 3 días lun 17/05/21 mié 19/05/21
FLEJE DE 19 MM
343 02.04.01.01.06.08 GRAPA DE ANCLAJE  3 días lun 17/05/21 mié 19/05/21 3 días
DE AL AL TIPO 3 días
344 02.04.01.01.06.09 PERNO DOBLE  3 días lun 17/05/21 mié 19/05/21
ARMADO DE A°G°
345 02.04.01.01.06.10 PERNO MAQUINADO  3 días lun 17/05/21 mié 19/05/21 3 días
DE A°G° 16 Ø 80 3 días
346 02.04.01.01.06.11 PERNO MAQUINADO  3 días lun 17/05/21 mié 19/05/21
DE A°G° ti U d 16
347 02.04.01.01.06.12 PLANCHA DE COBRE  3 días lun 17/05/21 mié 19/05/21 3 días
PARA LINEA A TIERRA 3 días
348 02.04.01.01.06.13 TUERCA OJO DE A°G°  3 días lun 17/05/21 mié 19/05/21
DE 16 Ø X80X38
349 02.04.01.01.06.14 PLATINA DE COBRE  3 días lun 17/05/21 mié 19/05/21 3 días
5" 2" 1/8" (127 3 días
350 02.04.01.01.06.15 TERMINALES  3 días lun 17/05/21 mié 19/05/21
TERMOCONTRAIBLES
351 02.04.01.01.06.16 TUBO DE BAJADA Y  3 días lun 17/05/21 mié 19/05/21 3 días
ACCESORIOS FªGª 1
352 02.04.01.01.07 RETENIDAS 2 días vie 14/05/21 sáb 15/05/21 2 días
353 02.04.01.01.07.01 AISLADOR DE  2 días vie 14/05/21 sáb 15/05/21 2 días
TRACCION CLASE ANSI
354 02.04.01.01.07.02 ALAMBRE DE AMARRE 2 días vie 14/05/21 sáb 15/05/21 2 días
DE F°G° N° 12 AWG
355 02.04.01.01.07.03 ARANDELA  2 días vie 14/05/21 sáb 15/05/21 2 días
CUADRADA CURVA DE
356 02.04.01.01.07.04 ARANDELA  2 días vie 14/05/21 sáb 15/05/21 2 días
CUADRADA PLANA DE
357 02.04.01.01.07.05 BLOQUE DE ANCLAJE  2 días vie 14/05/21 sáb 15/05/21 2 días
DE CONCRETO
358 02.04.01.01.07.06 CABLE DE ACERO  2 días vie 14/05/21 sáb 15/05/21 2 días
SEIEMENS MARTIN
359 02.04.01.01.07.07 CANALETA  2 días vie 14/05/21 sáb 15/05/21 2 días
GUARDACABLE DE Aº
360 02.04.01.01.07.08 MORDAZA  2 días vie 14/05/21 sáb 15/05/21 2 días
PREFORMADA PARA
361 02.04.01.01.07.09 PERNO ANGULAR CON 2 días vie 14/05/21 sáb 15/05/21 2 días
OJAL GUARDACABO
362 02.04.01.01.07.10 GUARDACABO DE Fº  2 días vie 14/05/21 sáb 15/05/21 2 días
Gº PARA CABLE DE 10
363 02.04.01.01.07.11 VARILLA DE ANCLAJE  2 días vie 14/05/21 sáb 15/05/21 2 días
DE ACERO DE 16MM
364 02.04.01.01.07.12 TUERCA OJO DE A°G°  2 días vie 14/05/21 sáb 15/05/21 2 días
DE 16 Ø X80X38
365 02.04.01.01.07.13 CONTRAPUNTA DE  2 días vie 14/05/21 sáb 15/05/21 2 días
51MM? 1500
366 02.04.01.01.08 PUESTA A TIERRA 5 días jue 20/05/21 lun 24/05/21 5 días
367 02.04.01.01.08.01 CEMENTO  5 días jue 20/05/21 lun 24/05/21 5 días
CONDUCTIVO 25 KG
368 02.04.01.01.08.02 CAJA DE REGISTRO  5 días jue 20/05/21 lun 24/05/21 5 días
PARA PUESTA A
369 02.04.01.01.08.03 CONDUCTOR DE  5 días jue 20/05/21 lun 24/05/21 5 días
COBRE DESNUDO
370 02.04.01.01.08.04 CONECTOR DE  5 días jue 20/05/21 lun 24/05/21 5 días
ALEACION DE COBRE
371 02.04.01.01.08.05 TIERRA NEGRA  5 días jue 20/05/21 lun 24/05/21 5 días
VEGETAL CERNIDA Y
372 02.04.01.01.08.06 TUBO PVC‐SAP DE  5 días jue 20/05/21 lun 24/05/21 5 días
12 5 MM DE
373 02.04.01.01.08.07 VARILLA DE COBRE DE 5 días jue 20/05/21 lun 24/05/21 5 días
16MM Ø 2400MM
374 02.04.01.01.08.08 ARANDELA Y TUERCA  5 días jue 20/05/21 lun 24/05/21 5 días
DE ANCLAJE DE COBRE 2 días
375 02.04.01.01.09 SISTEMA DE MEDICION Y 2 días vie 04/06/21 sáb 05/06/21
ACCESORIOS
376 02.04.01.01.09.01 MEDIDOR KW/H  2 días vie 04/06/21 sáb 05/06/21 2 días
TRIFASICO 2 días
377 02.04.01.01.09.02 MURETE DE  2 días vie 04/06/21 sáb 05/06/21
CONCRETO
378 02.04.01.01.09.03 CAJA METALICA  2 días vie 04/06/21 sáb 05/06/21 2 días
PORTAMEDIDOR 32 días
379 02.04.01.02 MONTAJE ELECTROMECANICO  32 días mié 05/05/21 sáb 05/06/21
RP
380 02.04.01.02.01 OBRAS PRELIMINARES 2 días mié 05/05/21 jue 06/05/21 2 días
381 02.04.01.02.01.01 REPLANTEO Y UBICACIÓN 2 días mié 05/05/21 jue 06/05/21 2 días
DE ESTRUCTURAS
382 02.04.01.02.02 INSTALACION DE POSTES 2 días vie 07/05/21 sáb 08/05/21 2 días
383 02.04.01.02.02.01 DISTRIBUCION DE  1 día sáb 08/05/21 sáb 08/05/21 1 día
POSTES DE C A C 13
384 02.04.01.02.02.02 EXCAVACION DE HOYO  1 día vie 07/05/21 vie 07/05/21 1 día
PARA POSTE DE C A C 13 1 día
385 02.04.01.02.02.03 IZAJE DE POSTE DE  1 día sáb 08/05/21 sáb 08/05/21
CONCRETO ARMADO
386 02.04.01.02.03 MONTAJE DE ARMADOS 4 días lun 10/05/21 jue 13/05/21 4 días
387 02.04.01.02.03.01 MONTAJE DE ARMADO  1 día lun 10/05/21 lun 10/05/21 1 día
TIPO DS 3
388 02.04.01.02.03.02 MONTAJE DE ARMADO  1 día lun 10/05/21 lun 10/05/21 1 día
TIPO PMI S 1 día
389 02.04.01.02.03.03 MONTAJE DE ARMADO  1 día mar 11/05/21 mar 11/05/21
TIPO A13F
390 02.04.01.02.03.04 MONTAJE DE ARMADO  1 día mar 11/05/21 mar 11/05/21 1 día
TIPO A7713F 1 día
391 02.04.01.02.03.05 MONTAJE DE ARMADO  1 día mié 12/05/21 mié 12/05/21
TIPO A713F S
392 02.04.01.02.03.06 MONTAJE DE  1 día jue 13/05/21 jue 13/05/21 1 día
TRANSFORMADOR SECO
393 02.04.01.02.04 MONTAJE DE  3 días lun 17/05/21 mié 19/05/21 3 días
CONDUCTORES Y
394 02.04.01.02.04.01 TENDIDO DE  3 días lun 17/05/21 mié 19/05/21 3 días
CONDUCTOR DE MT
395 02.04.01.02.04.02 TENDIDO DE  1 día mié 19/05/21 mié 19/05/21 1 día
CONDUCTOR DE
396 02.04.01.02.05 INSTALACION DE  2 días vie 14/05/21 sáb 15/05/21 2 días
RETENIDAS
397 02.04.01.02.05.01 EXCAVACION DE HOYO  1 día vie 14/05/21 vie 14/05/21 1 día
PARA RETENIDA TIPO
398 02.04.01.02.05.02 INSTALACION DE  1 día sáb 15/05/21 sáb 15/05/21 1 día
RETENIDA RYV
399 02.04.01.02.06 INSTALACION DE PUESTAS  5 días jue 20/05/21 lun 24/05/21 5 días
A TIERRA
400 02.04.01.02.06.01 EXCAVACION DE HOYO  2 días jue 20/05/21 vie 21/05/21 2 días
PARA SISTEMA DE
401 02.04.01.02.06.02 INSTALACION DE PUESTA  1 día sáb 22/05/21 sáb 22/05/21 1 día
A TIERRA TIPO PAT 1
402 02.04.01.02.06.03 INSTALACION DE PUESTA  1 día lun 24/05/21 lun 24/05/21 1 día
A TIERRA TIPO PAT 0
403 02.04.01.02.07 RED PRIMARIA  9 días mar 25/05/21 mié 02/06/21 9 días
SUBTERRANEA
404 02.04.01.02.07.01 EXCAVACIÓN DE ZANJA  3 días mar 25/05/21 jue 27/05/21 3 días
DE (H 1 2 Y ANCHO 1)
405 02.04.01.02.07.02 ELIMINACCIÓN DE  1 día jue 27/05/21 jue 27/05/21 1 día
MATERIAL EXCEDENTE
406 02.04.01.02.07.03 COMPACTACIÓN DE  3 días sáb 29/05/21 lun 31/05/21 3 días
ZANJA CON MATERIAL
407 02.04.01.02.07.04 COLOCACIÓN DE  1 día vie 28/05/21 vie 28/05/21 1 día
BANCODUCTO
408 02.04.01.02.07.05 INSTALACIÓN DE  2 días mar 01/06/21 mié 02/06/21 2 días
TERMINACIONES
409 02.04.01.02.07.06 BUZONES DE INSPECCIÓN 3 días sáb 29/05/21 lun 31/05/21 3 días
DE MT DE (1 2M DE
410 02.04.01.02.08 OTROS 5 días mar 01/06/21 sáb 05/06/21 5 días
411 02.04.01.02.08.01 PRUEBA Y PUESTA EN  2 días vie 04/06/21 sáb 05/06/21 2 días
SERVICIO DE LA LINEA Y
412 02.04.01.02.08.02 SEÑALIZACION DE  1 día mar 01/06/21 mar 01/06/21 1 día
ESTRUCTURAS
413 02.04.01.02.08.03 CORTE Y REPOSICION DE  1 día jue 03/06/21 jue 03/06/21 1 día
SERVICIO
414 02.04.01.02.08.04 ELABORACION DE  1 día mié 02/06/21 mié 02/06/21 1 día
EXPEDIENTE DE RED
415 02.04.01.02.08.05 COSTO POR  1 día jue 03/06/21 jue 03/06/21 1 día
COMPENSACION DE 91 días
416 02.04.02 INSTALACIONES ELECTRICAS  91 días mar 30/03/21 lun 28/06/21
INTERIORES
417 02.04.02.01 SUMINISTRO DE  91 días mar 30/03/21 lun 28/06/21 91 días
MATERIALES 1 día
418 02.04.02.01.01 TRABAJOS  1 día mar 30/03/21 mar 30/03/21
PRELIMINARES
419 02.04.02.01.01.01 TRAZO, NIVELACION Y  1 día mar 30/03/21 mar 30/03/21 1 día
REPLANTEO 13 días
420 02.04.02.01.02 MOVIMIENTO DE  13 días mié 31/03/21 lun 12/04/21
TIERRAS
421 02.04.02.01.02.01 EXCAVACION  6 días mié 31/03/21 lun 05/04/21 6 días
MANUAL DE ZANJAS 5 días
422 02.04.02.01.02.02 EXCAVACION  5 días mar 06/04/21 sáb 10/04/21
MANUAL DE HOYO
423 02.04.02.01.02.03 CAMA DE APOYO  1 día mar 06/04/21 mar 06/04/21 1 día
E 0 10 2 días
424 02.04.02.01.02.04 RELLENO  2 días jue 08/04/21 vie 09/04/21
COMPACTADO CON
425 02.04.02.01.02.05 ACARREO DE  1 día sáb 10/04/21 sáb 10/04/21 1 día
MATERIAL EXCEDENTE 1 día
426 02.04.02.01.02.06 ELIMINACION DE  1 día lun 12/04/21 lun 12/04/21
MATERIAL EXCEDENTE
427 02.04.02.01.03 SALIDA PARA CENTROS  31 días jue 08/04/21 sáb 08/05/21 31 días
DE LUZ 27 días
428 02.04.02.01.03.01 CENTRO DE LUZ EN  27 días jue 08/04/21 mar 04/05/21
TECHO
429 02.04.02.01.03.02 CENTRO DE LUZ EN  3 días mié 05/05/21 vie 07/05/21 3 días
PARED 1 día
430 02.04.02.01.03.03 CENTRO DE LUZ  1 día sáb 08/05/21 sáb 08/05/21
P/DOWNLIGHT Y SPOT
431 02.04.02.01.04 SALIDA PARA LUZ DE  6 días mié 05/05/21 lun 10/05/21 6 días
EMERGENCIA
432 02.04.02.01.04.01 CENTRO DE LUZ DE  6 días mié 05/05/21 lun 10/05/21 6 días
EMERGENCIA
433 02.04.02.01.05 SALIDA PARA  2 días mar 11/05/21 mié 12/05/21 2 días
INTERRUPTORES
434 02.04.02.01.05.01 SALIDA PARA  2 días mar 11/05/21 mié 12/05/21 2 días
INTERRUPTORES
435 02.04.02.01.06 SALIDA PARA  8 días jue 13/05/21 jue 20/05/21 8 días
TOMACORRIENTES
436 02.04.02.01.06.01 TOMACORRIENTE  2 días jue 13/05/21 vie 14/05/21 2 días
DOBLE MIXTO (01
437 02.04.02.01.06.02 TOMACORRIENTE  3 días sáb 15/05/21 lun 17/05/21 3 días
DOBLE SCHUKO (02
438 02.04.02.01.06.03 TOMACORRIENTE  1 día mar 18/05/21 mar 18/05/21 1 día
DOBLE MIXTO (01
439 02.04.02.01.06.04 TOMACORRIENTE  1 día mié 19/05/21 mié 19/05/21 1 día
TIPO DOBLE SCHUKO
440 02.04.02.01.06.05 TOMACORRIENTE  1 día jue 20/05/21 jue 20/05/21 1 día
DOBLE MIXTO (01
441 02.04.02.01.07 SALIDA DE FUERZA  1 día vie 21/05/21 vie 21/05/21 1 día
ELECTRICA
442 02.04.02.01.07.01 SALIDA DE FUERZA  1 día vie 21/05/21 vie 21/05/21 1 día
ELECTRICA
443 02.04.02.01.08 CAJAS DE PASE 6 días sáb 22/05/21 jue 27/05/21 6 días
444 02.04.02.01.08.01 CAJA DE PASE DE F°G°  1 día sáb 22/05/21 sáb 22/05/21 1 día
ESPESOR 1 2

Tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica
Proyecto: LOS OLIVOS_LA YARA
División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso

Página 3
Id ITEM Nombre de tarea Duracion Comienzo Fin
Calendario 03 ene '21 10 ene '21 17 ene '21 24 ene '21 31 ene '21 07 feb '21 14 feb '21 21 feb '21 28 feb '21 07 mar '21 14 mar '21 21 mar '21 28 mar '21 04 abr '21 11 abr '21 18 abr '21 25 abr '21 02 may '21 09 may '21 16 may '21 23 may '21 30 may '21 06 jun '21 13 jun '21 20 jun '21 27 jun '21 04 jul '21 11 jul '21 18 jul '21 25 jul '21 01 ago '21 08 ago '21 15 ago '21 22 ago '21 29 ago '21
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
445 02.04.02.01.08.02 CAJA RECTANGULAR  1 día lun 24/05/21 lun 24/05/21 1 día
DE F°G° ESPESOR
446 02.04.02.01.08.03 BUZÓN DE  2 días mar 25/05/21 mié 26/05/21 2 días
CONEXIONES 1 día
447 02.04.02.01.08.04 CAJA DE PASE PARA  1 día jue 27/05/21 jue 27/05/21
JUNTA DE
448 02.04.02.01.09 CANALIZACION Y/O  52 días mié 07/04/21 vie 28/05/21 52 días
TUBERIAS 8 días
449 02.04.02.01.09.01 TUBERIA HFT  8 días jue 20/05/21 jue 27/05/21
(ELECTRICA) DN 20
450 02.04.02.01.09.02 TUBERIA HFT  1 día vie 28/05/21 vie 28/05/21 1 día
(ELECTRICA) DN 25 1 día
451 02.04.02.01.09.03 TUBERIA HFT  1 día mié 07/04/21 mié 07/04/21
(ELECTRICA) DN 35
452 02.04.02.01.09.04 TUBERIA HFT  1 día mié 07/04/21 mié 07/04/21 1 día
(ELECTRICA) DN 40 1 día
453 02.04.02.01.09.05 TUBERIA HFT  1 día mié 07/04/21 mié 07/04/21
(ELECTRICA) DN 63
454 02.04.02.01.09.06 DUCTO  1 día mié 07/04/21 mié 07/04/21 1 día
SUBTERRANEO PARA 1 día
455 02.04.02.01.09.07 CINTA SEÑALIZADORA 1 día mié 07/04/21 mié 07/04/21
DE RIESGO ELECTRICO
456 02.04.02.01.10 CONDUCTORES Y CABLES 12 días jue 17/06/21 lun 28/06/21 12 días
DE ENERGÍA EN 3 días
457 02.04.02.01.10.01 CONDUCTOR  3 días jue 17/06/21 sáb 19/06/21
ELECTRICO LSOH 2 5
458 02.04.02.01.10.02 CONDUCTOR  3 días lun 21/06/21 mié 23/06/21 3 días
ELECTRICO LSOH 4
459 02.04.02.01.10.03 CONDUCTOR N2XOH:  1 día jue 24/06/21 jue 24/06/21 1 día
1 1X6 2 1X6
460 02.04.02.01.10.04 CONDUCTOR N2XOH:  1 día jue 24/06/21 jue 24/06/21 1 día
3 1X6 2 1X6
461 02.04.02.01.10.05 CONDUCTOR N2XOH:  1 día jue 24/06/21 jue 24/06/21 1 día
3 1X10 2 1X10
462 02.04.02.01.10.06 CONDUCTOR N2XOH:  1 día jue 24/06/21 jue 24/06/21 1 día
3 1X25 2 1X25
463 02.04.02.01.10.07 CONDUCTOR LSOH: 6  1 día vie 25/06/21 vie 25/06/21 1 día
2 (AMARILLO
464 02.04.02.01.10.08 CONDUCTOR LSOH: 10 1 día sáb 26/06/21 sáb 26/06/21 1 día
2 (AMARILLO
465 02.04.02.01.10.09 CABLE DESNUDO DE  1 día lun 28/06/21 lun 28/06/21 1 día
COBRE 10MM2
466 02.04.02.01.11 LUMINARIAS  8 días mié 16/06/21 mié 23/06/21 8 días
EMPOTRADAS Y/O
467 02.04.02.01.11.01 SPOT LIGHT PARA  1 día mié 16/06/21 mié 16/06/21 1 día
EMPOTRAR CON
468 02.04.02.01.11.02 LUMINARIA LED TIPO  1 día jue 17/06/21 jue 17/06/21 1 día
PLAFON 18W PARA
469 02.04.02.01.11.03 LUMINARIA LED TIPO  1 día vie 18/06/21 vie 18/06/21 1 día
PLAFON 24W PARA
470 02.04.02.01.11.04 LUMINARIA LED TIPO  2 días jue 17/06/21 vie 18/06/21 2 días
PANEL 36W PARA
471 02.04.02.01.11.05 LUMINARIA LED TIPO  1 día vie 18/06/21 vie 18/06/21 1 día
PANEL 72 W PARA
472 02.04.02.01.11.06 LUMINARIA LED TIPO  1 día sáb 19/06/21 sáb 19/06/21 1 día
PANEL 40 W PARA
473 02.04.02.01.11.07 LUMINARIA LED TIPO  1 día sáb 19/06/21 sáb 19/06/21 1 día
PANEL 50W PARA
474 02.04.02.01.11.08 LUMINARIA LED TIPO  1 día sáb 19/06/21 sáb 19/06/21 1 día
PANEL 45W PARA
475 02.04.02.01.11.09 LUMINARIA LED TIPO  1 día sáb 19/06/21 sáb 19/06/21 1 día
PANEL LINEAL 40W
476 02.04.02.01.11.10 LUMINARIA LED TIPO  2 días vie 18/06/21 sáb 19/06/21 2 días
PANEL 36 W PARA
477 02.04.02.01.11.11 LUMINARIA PANEL  1 día sáb 19/06/21 sáb 19/06/21 1 día
TIPO LED 60 W PARA
478 02.04.02.01.11.12 LUMINARIA PANEL  1 día sáb 19/06/21 sáb 19/06/21 1 día
LED TIPO LINEAL 40W
479 02.04.02.01.11.13 LUMINARIA LED TIPO  1 día lun 21/06/21 lun 21/06/21 1 día
DOWNLIGHT 4"13W
480 02.04.02.01.11.14 ALUMBRADO DE  2 días mar 22/06/21 mié 23/06/21 2 días
EMERGENCIA 7 5 W
481 02.04.02.01.11.15 LUMINARIA LED TIPO  1 día mié 23/06/21 mié 23/06/21 1 día
DOWNLIGHT 8"18W
482 02.04.02.01.11.16 SENSOR INFRARROJO  1 día mié 23/06/21 mié 23/06/21 1 día
PASIVO MODALIDAD
483 02.04.02.01.12 INSTALACION DE  5 días jue 24/06/21 lun 28/06/21 5 días
TOMACORRIENTES 3 días
484 02.04.02.01.12.01 TOMACORRIENTE  3 días jue 24/06/21 sáb 26/06/21
DOBLE MIXTO (01
485 02.04.02.01.12.02 TOMACORRIENTE  1 día sáb 26/06/21 sáb 26/06/21 1 día
DOBLE SCHUKO (02 1 día
486 02.04.02.01.12.03 TOMACORRIENTE  1 día sáb 26/06/21 sáb 26/06/21
DOBLE MIXTO (01
487 02.04.02.01.12.04 TOMACORRIENTE  1 día sáb 26/06/21 sáb 26/06/21 1 día
TIPO DOBLE SCHUKO 1 día
488 02.04.02.01.12.05 TOMACORRIENTE  1 día lun 28/06/21 lun 28/06/21
DOBLE SCHUKO (02
489 02.04.02.01.12.06 TOMACORRIENTE  1 día lun 28/06/21 lun 28/06/21 1 día
DOBLE SCHUKO (02 1 día
490 02.04.02.01.13 INSTALACION DE  1 día lun 28/06/21 lun 28/06/21
INTERRUPTORES
491 02.04.02.01.13.01 INTERRUPTOR SIMPLE 1 día lun 28/06/21 lun 28/06/21 1 día
492 02.04.02.01.13.02 INTERRUPTOR DOBLE 1 día lun 28/06/21 lun 28/06/21 1 día
493 02.04.02.01.13.03 INTERRUPTOR DE  1 día lun 28/06/21 lun 28/06/21 1 día
CONMUTACIÓN 1 día
494 02.04.02.01.14 LUMINARIAS  1 día lun 28/06/21 lun 28/06/21
EXTERIORES
495 02.04.02.01.14.01 LUMINARIA TIPO  1 día lun 28/06/21 lun 28/06/21 1 día
BRAQUET 45W 4050 1 día
496 02.04.02.01.14.02 LUMINARIA TIPO  1 día lun 28/06/21 lun 28/06/21
BRAQUET
497 02.04.02.01.14.03 LUMINARIA LED TIPO  1 día lun 28/06/21 lun 28/06/21 1 día
DOWNLIGHT 4"13W 1 día
498 02.04.02.01.14.04 REFLECTOR DE 30 W,  1 día lun 28/06/21 lun 28/06/21
2400 L
499 02.04.02.01.15 TABLEROS E  13 días mié 26/05/21 lun 07/06/21 13 días
INTERRUPTORES
500 02.04.02.01.15.01 TABLERO DE GENERAL 1 día mié 26/05/21 mié 26/05/21 1 día
(TG) SISTEMA FUERZA
501 02.04.02.01.15.02 TABLERO DE  1 día jue 27/05/21 jue 27/05/21 1 día
DISTRIBUCION
502 02.04.02.01.15.03 TABLERO DE  1 día vie 28/05/21 vie 28/05/21 1 día
DISTRIBUCION
503 02.04.02.01.15.04 TABLERO DE  1 día sáb 29/05/21 sáb 29/05/21 1 día
DISTRIBUCION
504 02.04.02.01.15.05 TABLERO DE  1 día lun 31/05/21 lun 31/05/21 1 día
DISTRIBUCION (TD 04)
505 02.04.02.01.15.06 TABLERO DE  1 día mar 01/06/21 mar 01/06/21 1 día
DISTRIBUCION (TD 05)
506 02.04.02.01.15.07 TABLERO DE  1 día mié 02/06/21 mié 02/06/21 1 día
DISTRIBUCION (TD 06)
507 02.04.02.01.15.08 TABLERO DE  1 día jue 03/06/21 jue 03/06/21 1 día
DISTRIBUCION
508 02.04.02.01.15.09 TABLERO DE  1 día vie 04/06/21 vie 04/06/21 1 día
DISTRIBUCION
509 02.04.02.01.15.10 TABLERO DE TENSION  1 día sáb 05/06/21 sáb 05/06/21 1 día
ESTABILIZADA(TTE G1)
510 02.04.02.01.15.11 TABLERO DE  1 día lun 07/06/21 lun 07/06/21 1 día
DISTRIBUCION
511 02.04.02.01.16 SISTEMA ELECTRICO  2 días mar 08/06/21 mié 09/06/21 2 días
ESTABILIZADO
512 02.04.02.01.16.01 TRANSFORMADOR DE  1 día mar 08/06/21 mar 08/06/21 1 día
AISLAMIENTO 12 KVA
513 02.04.02.01.16.02 UPS TRUE ONLINE  1 día mié 09/06/21 mié 09/06/21 1 día
TRIFASICO 10KVA
514 02.04.02.01.17 INSTALACION DEL  5 días lun 12/04/21 vie 16/04/21 5 días
SISTEMA PUESTA A
515 02.04.02.01.17.01 POZO DE PUESTA A  3 días lun 12/04/21 mié 14/04/21 3 días
TIERRA TENSION
516 02.04.02.01.17.02 POZO DE PUESTA A  2 días jue 15/04/21 vie 16/04/21 2 días
TIERRA TENSION
517 02.04.02.01.18 PRUEBAS ELÉCTRICAS 2 días lun 14/06/21 mar 15/06/21 2 días
518 02.04.02.01.18.01 PRUEBAS Y  2 días lun 14/06/21 mar 15/06/21 2 días
PROTOCOLOS EN
519 02.04.02.01.19 INSTALACIONES  1 día lun 28/06/21 lun 28/06/21 1 día
MECANICAS
520 02.04.02.01.19.01 AIRE  1 día lun 28/06/21 lun 28/06/21 1 día
ACONDICIONADO
521 02.05 INSTALACIONES DE  45 días lun 10/05/21 mié 23/06/21 45 días
TELECOMUNICACIONES
522 02.05.01 SALIDAS Y CANALIZACIONES 27 días lun 10/05/21 sáb 05/06/21 27 días
523 02.05.01.01 SALIDA DE RED DE DATOS  4 días vie 21/05/21 lun 24/05/21 4 días
EN MURO
524 02.05.01.02 SALIDA DE RED DE DATOS  1 día mar 25/05/21 mar 25/05/21 1 día
EN PISO 11 días
525 02.05.01.03 SALIDA DE RED DE DATOS  11 días lun 10/05/21 jue 20/05/21
EN TECHO
526 02.05.01.04 SALIDA PARA CAMARA DE  1 día mié 26/05/21 mié 26/05/21 1 día
EXTERIOR 1 día
527 02.05.01.05 SALIDA DE AUDIO 1 día mié 26/05/21 mié 26/05/21
528 02.05.01.06 SALIDA DE PARLANTE 1 día mié 26/05/21 mié 26/05/21 1 día
529 02.05.01.07 SALIDA PARA ATENUADOR  1 día mié 26/05/21 mié 26/05/21 1 día
DE VOLUMEN
530 02.05.01.08 SALIDA PARA CONTROL DE  1 día mié 26/05/21 mié 26/05/21 1 día
ASISTENCIA O ACCESO 3 días
531 02.05.01.09 SALIDA PARA SENSOR DE  3 días jue 27/05/21 sáb 29/05/21
TECHO
532 02.05.01.10 SALIDA PARA ESTACION  1 día sáb 29/05/21 sáb 29/05/21 1 día
MANUAL DE ALARMA 2 días
533 02.05.01.11 SALIDA PARA SENSOR DE  2 días vie 28/05/21 sáb 29/05/21
INUNDACION
534 02.05.01.12 SALIDA PARA BOCINA CON  1 día sáb 29/05/21 sáb 29/05/21 1 día
LUZ ESTROBOSCOPICA 1 día
535 02.05.01.13 SALIDA PARA MODULO  1 día lun 31/05/21 lun 31/05/21
AISLADOR DE FALLAS
536 02.05.01.14 SALIDA PARA  1 día lun 31/05/21 lun 31/05/21 1 día
INTERCOMUNICADOR 2 días
537 02.05.01.15 CAJA DE PASE  2 días mar 01/06/21 mié 02/06/21
100X100X50MM
538 02.05.01.16 CAJA DE PASE  1 día mié 02/06/21 mié 02/06/21 1 día
150X150X100MM 2 días
539 02.05.01.17 CAJA DE PASE  2 días mar 01/06/21 mié 02/06/21
200X200X100MM
540 02.05.01.18 CAJA DE PASE  2 días mar 01/06/21 mié 02/06/21 2 días
300X300X100MM
541 02.05.01.19 TUBERIA PVC SAP ELECTRICA 1 día mié 02/06/21 mié 02/06/21 1 día
50MM
542 02.05.01.20 TUBERIA PVC SAP ELECTRICA 3 días jue 03/06/21 sáb 05/06/21 3 días
25MM
543 02.05.01.21 TUBERIA PVC SAP ELECTRICA 3 días jue 03/06/21 sáb 05/06/21 3 días
20MM
544 02.05.02 CIRCUITO DE RED DE DATOS 3 días lun 31/05/21 mié 02/06/21 3 días
545 02.05.02.01 PUNTO DE RED DE DATOS  2 días lun 31/05/21 mar 01/06/21 2 días
SIMPLE EN MURO
546 02.05.02.02 PUNTO DE RED DE DATOS  1 día mar 01/06/21 mar 01/06/21 1 día
DOBLE EN MURO
547 02.05.02.03 PUNTO DE RED DE DATOS  1 día mar 01/06/21 mar 01/06/21 1 día
SIMPLE EN PISO
548 02.05.02.04 PUNTO DE RED DE DATOS  1 día mar 01/06/21 mar 01/06/21 1 día
SIMPLE EN TECHO PARA AP
549 02.05.02.05 PUNTO DE RED DE DATOS  1 día mié 02/06/21 mié 02/06/21 1 día
SIMPLE EN TECHO PARA
550 02.05.02.06 PUNTO DE RED PARA  1 día mié 02/06/21 mié 02/06/21 1 día
CAMARA IP EN EXTERIOR
551 02.05.02.07 PUNTO DE AUDIO 1 día mié 02/06/21 mié 02/06/21 1 día
552 02.05.03 CONDUCTORES Y CABLES EN  32 días mié 19/05/21 sáb 19/06/21 32 días
TUBERIAS
553 02.05.03.01 CABLE UTP CAT 6A 8 días mié 19/05/21 mié 26/05/21 8 días
554 02.05.03.02 CABLE 2X18AWG LSZH FPLP 3 días jue 27/05/21 sáb 29/05/21 3 días
555 02.05.03.03 CABLE DE AUDIO 2X12 AWG 1 día sáb 29/05/21 sáb 29/05/21 1 día
556 02.05.03.04 CONDUCTOR DE COBRE  1 día vie 18/06/21 vie 18/06/21 1 día
FORRADO PARA POZO A
557 02.05.03.05 CONDUCTOR ELÉCTRICO  1 día sáb 19/06/21 sáb 19/06/21 1 día
4MM2 LSOH
558 02.05.03.06 CONDUCTOR ELÈCTRICO  1 día sáb 19/06/21 sáb 19/06/21 1 día
10MM2 LSOH
559 02.05.04 EQUIPOS DE RED DE DATOS  1 día lun 31/05/21 lun 31/05/21 1 día
(NETWORKING)
560 02.05.04.01 GABINETES Y SWITCH'ES 1 día lun 31/05/21 lun 31/05/21 1 día
561 02.05.04.01.01 GABINETE DE DATOS DE  1 día lun 31/05/21 lun 31/05/21 1 día
PISO
562 02.05.04.01.02 SWITCH 48 PUERTOS  1 día lun 31/05/21 lun 31/05/21 1 día
10/100/100 L2/3
563 02.05.04.01.03 SWITCH 24 PUERTOS  1 día lun 31/05/21 lun 31/05/21 1 día
10/100/100 L2/3 1 día
564 02.05.04.01.04 ACCESS POINT 1 día lun 31/05/21 lun 31/05/21
565 02.05.05 SISTEMA DE SEGURIDAD  4 días mar 01/06/21 vie 04/06/21 4 días
ELECTRONICA 2 días
566 02.05.05.01 SISTEMA DE  2 días mar 01/06/21 mié 02/06/21
VIDEOVIGILANCIA
567 02.05.05.01.01 CENTRAL DE CAMARAS  1 día mar 01/06/21 mar 01/06/21 1 día
DE SEGURIDAD 1 día
568 02.05.05.01.02 CAMARA EXTERIOR  1 día mié 02/06/21 mié 02/06/21
VIDEOVIGILANCIA
569 02.05.05.01.03 CAMARA INTERIOR  1 día mié 02/06/21 mié 02/06/21 1 día
VIDEOVIGILANCIA DE 1 día
570 02.05.05.01.04 CAMARA INTERIOR  1 día mié 02/06/21 mié 02/06/21
VIDEOVIGILANCIA DE
571 02.05.05.02 SISTEMA DE DETECCION Y  3 días mié 02/06/21 vie 04/06/21 3 días
ALARMA DE INCENDIO 1 día
572 02.05.05.02.01 CENTRAL DE ALARMA 1 día jue 03/06/21 jue 03/06/21
573 02.05.05.02.02 SENSOR DE  1 día jue 03/06/21 jue 03/06/21 1 día
TEMPERATURA 2 días
574 02.05.05.02.03 SENSOR DE HUMO 2 días mié 02/06/21 jue 03/06/21
575 02.05.05.02.04 SENSOR  1 día jue 03/06/21 jue 03/06/21 1 día
MULTIPROPOSITO 2 días
576 02.05.05.02.05 SENSOR DE INUNDACION 2 días mié 02/06/21 jue 03/06/21
577 02.05.05.02.06 ESTACION MANUAL 1 día jue 03/06/21 jue 03/06/21 1 día
578 02.05.05.02.07 BOCINA CON LUZ  1 día vie 04/06/21 vie 04/06/21 1 día
ESTROBOSCOPICA
579 02.05.05.02.08 SENSOR DE MONITOREO  1 día vie 04/06/21 vie 04/06/21 1 día
Y CONTROL DE FALLAS
580 02.05.05.02.09 ANUNCIADOR REMOTO 1 día vie 04/06/21 vie 04/06/21 1 día
581 02.05.05.03 SISTEMA DE CONTROL DE  1 día vie 04/06/21 vie 04/06/21 1 día
ASISTENCIA BIOMETRICO
582 02.05.05.03.01 CONTROL DE ASISTENCIA  1 día vie 04/06/21 vie 04/06/21 1 día
BIOMETRICO
583 02.05.05.03.02 CONTROL DE ACCESO 1 día vie 04/06/21 vie 04/06/21 1 día
584 02.05.06 SISTEMA DE TELEFONIA,  1 día sáb 05/06/21 sáb 05/06/21 1 día
INTERCOMUNICADOR
585 02.05.06.01 CENTRAL TELEFONICA IP 1 día sáb 05/06/21 sáb 05/06/21 1 día
586 02.05.06.02 TELEFONO IP 1 día sáb 05/06/21 sáb 05/06/21 1 día
587 02.05.06.03 PORTERO ‐  1 día sáb 05/06/21 sáb 05/06/21 1 día
INTERCOMUNICADOR
588 02.05.07 SISTEMA DE AUDIO Y/O  1 día lun 07/06/21 lun 07/06/21 1 día
PERIFONEO
589 02.05.07.01 AMPLIFICADOR DE AUDIO 1 día lun 07/06/21 lun 07/06/21 1 día
590 02.05.07.02 PARLANTE PARA PERIFONEO 1 día lun 07/06/21 lun 07/06/21 1 día
Y SONIDO AMBIENTAL
591 02.05.08 CIRCUITO ELECTRICO  17 días lun 07/06/21 mié 23/06/21 17 días
ESTABILIZADO
592 02.05.08.01 UPS MONOFASICO 3KVA  1 día mar 22/06/21 mar 22/06/21 1 día
RACKEABLE

Tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica
Proyecto: LOS OLIVOS_LA YARA
División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso

Página 4
Id ITEM Nombre de tarea Duracion Comienzo Fin
Calendario 03 ene '21 10 ene '21 17 ene '21 24 ene '21 31 ene '21 07 feb '21 14 feb '21 21 feb '21 28 feb '21 07 mar '21 14 mar '21 21 mar '21 28 mar '21 04 abr '21 11 abr '21 18 abr '21 25 abr '21 02 may '21 09 may '21 16 may '21 23 may '21 30 may '21 06 jun '21 13 jun '21 20 jun '21 27 jun '21 04 jul '21 11 jul '21 18 jul '21 25 jul '21 01 ago '21 08 ago '21 15 ago '21 22 ago '21 29 ago '21
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
593 02.05.08.02 TRANSFORMADOR DE  1 día mié 23/06/21 mié 23/06/21 1 día
AISLAMIENTO MONOFASICO
594 02.05.08.03 POZO A TIERRA 5 OHMIOS 2 días mié 16/06/21 jue 17/06/21 2 días
595 02.05.08.04 BARRA DE COBRE TMGB 1 día lun 07/06/21 lun 07/06/21 1 día
596 02.05.08.05 TABLERO ELECTRICO  1 día lun 21/06/21 lun 21/06/21 1 día
ESTABILIZADO 1 día
597 02.05.08.06 TOMACORRIENTE DOBLE  1 día lun 21/06/21 lun 21/06/21
CON TOMA A TIERRA PARA
598 02.05.08.07 TOMACORRIENTE DOBLE  1 día lun 21/06/21 lun 21/06/21 1 día
CON TOMA A TIERRA PARA 195 días
599 03 BLOQUE B ‐ ATENCIÓN  195 días mié 16/12/20 lun 28/06/21
DIFERENCIADA
600 03.01 ESTRUCTURAS 161 días mié 16/12/20 mar 25/05/21 161 días
601 03.01.01 OBRAS PRELIMINARES 1 día mié 16/12/20 mié 16/12/20
602 03.01.01.01 TRAZO, NIVELES Y  1 día mié 16/12/20 mié 16/12/20
REPLANTEO 152 días
603 03.01.02 MOVIMIENTO DE TIERRAS 152 días jue 17/12/20 lun 17/05/21
604 03.01.02.01 EXCAVACION MANUAL DE  2 días jue 17/12/20 vie 18/12/20
ZANJAS PARA ZAPATAS
605 03.01.02.02 EXCAVACION MANUAL DE  3 días mar 22/12/20 jue 24/12/20
ZANJA PARA CIMIENTOS
606 03.01.02.03 RELLENO Y COMPACTADO  1 día mié 14/04/21 mié 14/04/21 1 día
C/EQUIPO MATERIAL
607 03.01.02.04 NIVELACION INTERIOR Y  1 día sáb 15/05/21 sáb 15/05/21 1 día
COMPACTADO DEL
608 03.01.02.05 AFIRMADO DE 4" PARA  1 día lun 17/05/21 lun 17/05/21 1 día
PISOS
609 03.01.02.06 ACARREO DE MATERIAL  2 días mié 14/04/21 jue 15/04/21 2 días
EXCEDENTE D 30
610 03.01.02.07 ELIMINACION DE MATERIAL  1 día jue 22/04/21 jue 22/04/21 1 día
EXCEDENTE C/MAQUINARIA
611 03.01.03 IMPERMEABILIZACIÓN 1 día mar 13/04/21 mar 13/04/21 1 día
612 03.01.03.01 IMPERMEABILIZACION CON  1 día mar 13/04/21 mar 13/04/21 1 día
ASFALTO
613 03.01.04 OBRAS DE CONCRETO SIMPLE 151 días sáb 19/12/20 mar 18/05/21 151 días
614 03.01.04.01 SOLADOS Y CIMIENTOS 7 días sáb 19/12/20 vie 25/12/20
615 03.01.04.01.01 SOLADO CON MEZCLA  1 día sáb 19/12/20 sáb 19/12/20
1 12 C H E 4"
616 03.01.04.01.02 CIMIENTO CORRIDO:  1 día vie 25/12/20 vie 25/12/20
CONCRETO CICLOPEO
617 03.01.04.02 FALSO PISO 1 día mar 18/05/21 mar 18/05/21 1 día
618 03.01.04.02.01 FALSO PISO E=4" C:H 1:8  1 día mar 18/05/21 mar 18/05/21 1 día
C/ADITIVO
619 03.01.04.03 SOBRECIMIENTOS 3 días sáb 26/12/20 lun 28/12/20
620 03.01.04.03.01 SOBRECIMIENTO:  1 día lun 28/12/20 lun 28/12/20
CONCRETO F'C 175
621 03.01.04.03.02 SOBRECIMIENTO:  3 días sáb 26/12/20 lun 28/12/20
ENCOFRADO Y
622 03.01.05 OBRAS DE CONCRETO  158 días sáb 19/12/20 mar 25/05/21 158 días
ARMADO
623 03.01.05.01 ZAPATAS 1 día lun 21/12/20 lun 21/12/20
624 03.01.05.01.01 ZAPATAS: CONCRETO  1 día lun 21/12/20 lun 21/12/20
F'C 210 KG/CM2
625 03.01.05.01.02 ACERO CORRUGADO  1 día lun 21/12/20 lun 21/12/20
F 4 200 k / 2
626 03.01.05.02 COLUMNAS Y PLACAS 116 días sáb 19/12/20 mar 13/04/21 116 días
627 03.01.05.02.01 COLUMNAS Y PLACAS:  1 día mar 13/04/21 mar 13/04/21 1 día
CONCRETO F'C 210
628 03.01.05.02.02 COLUMNAS Y PLACAS:  4 días sáb 10/04/21 mar 13/04/21 4 días
ENCOFRADO Y
629 03.01.05.02.03 ACERO CORRUGADO  3 días sáb 19/12/20 lun 21/12/20
F 4 200 k / 2
630 03.01.05.03 COLUMNETAS DE AMARRE 2 días mar 13/04/21 mié 14/04/21 2 días
631 03.01.05.03.01 COLUMNETAS DE  1 día mié 14/04/21 mié 14/04/21 1 día
AMARRE CONCRETO 1 día
632 03.01.05.03.02 COLUMNETAS DE  1 día mié 14/04/21 mié 14/04/21
AMARRE CONCRETO
633 03.01.05.03.03 COLUMNETAS DE  2 días mar 13/04/21 mié 14/04/21 2 días
AMARRE ENCOFRADO Y 2 días
634 03.01.05.03.04 ACERO CORRUGADO  2 días mar 13/04/21 mié 14/04/21
F 4 200 k / 2
635 03.01.05.04 VIGAS 9 días mié 14/04/21 jue 22/04/21 9 días
636 03.01.05.04.01 VIGAS: CONCRETO  1 día jue 22/04/21 jue 22/04/21 1 día
F'C 210 k / 2
637 03.01.05.04.02 VIGAS: ENCOFRADO Y  8 días mié 14/04/21 mié 21/04/21 8 días
DESENCOFRADO 2 días
638 03.01.05.04.03 ACERO CORRUGADO  2 días mar 20/04/21 mié 21/04/21
F 4 200 k / 2
639 03.01.05.05 VIGUETAS DE AMARRE 2 días jue 15/04/21 vie 16/04/21 2 días
640 03.01.05.05.01 VIGUETAS DE AMARRE:  1 día vie 16/04/21 vie 16/04/21 1 día
CONCRETO F'C 175
641 03.01.05.05.02 VIGUETAS DE AMARRE:  2 días jue 15/04/21 vie 16/04/21 2 días
ENCOFRADO Y 1 día
642 03.01.05.05.03 ACERO CORRUGADO  1 día jue 15/04/21 jue 15/04/21
F 4 200 k / 2
643 03.01.05.06 LOSA MACIZA 2 días mié 21/04/21 jue 22/04/21 2 días
644 03.01.05.06.01 LOSA MACIZA:  1 día jue 22/04/21 jue 22/04/21 1 día
CONCRETO F'C 210
645 03.01.05.06.02 LOSA MACIZA:  1 día mié 21/04/21 mié 21/04/21 1 día
ENCOFRADO Y 1 día
646 03.01.05.06.03 ACERO CORRUGADO  1 día mié 21/04/21 mié 21/04/21
F 4 200 k / 2
647 03.01.05.07 LOSAS ALIGERADAS 4 días lun 19/04/21 jue 22/04/21 4 días
648 03.01.05.07.01 LOSA ALIGERADA:  1 día jue 22/04/21 jue 22/04/21 1 día
CONCRETO F'C 210
649 03.01.05.07.02 LOSA ALIGERADA:  3 días lun 19/04/21 mié 21/04/21 3 días
ENCOFRADO Y
650 03.01.05.07.03 LOSA ALIGERADA:  1 día mié 21/04/21 mié 21/04/21 1 día
LADRILLO HUECO
651 03.01.05.07.04 ACERO CORRUGADO  1 día mié 21/04/21 mié 21/04/21 1 día
F 4 200 k / 2
652 03.01.05.08 MESONES CONCRETO  1 día mar 25/05/21 mar 25/05/21 1 día
ARMADO
653 03.01.05.08.01 MESON DE CONCRETO:  1 día mar 25/05/21 mar 25/05/21 1 día
CONCRETO F'C 175
654 03.01.05.08.02 MESON DE CONCRETO:  1 día mar 25/05/21 mar 25/05/21 1 día
ENCOFRADO Y
655 03.01.05.08.03 ACERO CORRUGADO  1 día mar 25/05/21 mar 25/05/21 1 día
F 4 200 k / 2
656 03.01.06 VARIOS 21 días mié 14/04/21 mar 04/05/21 21 días
657 03.01.06.01 CURADO DE ELEMENTOS DE  21 días mié 14/04/21 mar 04/05/21 21 días
CONCRETO
658 03.02 ARQUITECTURA 83 días mié 07/04/21 lun 28/06/21 83 días
659 03.02.01 MUROS Y TABIQUES DE  6 días mié 07/04/21 lun 12/04/21 6 días
ALBAÑILERIA
660 03.02.01.01 MURO DE LADRILLO KK TIPO 6 días mié 07/04/21 lun 12/04/21 6 días
IV SOGA M 1 1 5 E 1 5 CM
661 03.02.01.02 MURO DE LADRILLO KK TIPO 3 días sáb 10/04/21 lun 12/04/21 3 días
IV CABEZA M 1 1 5 E 1 5 CM
662 03.02.02 REVOQUES ENLUCIDOS Y  20 días vie 07/05/21 mié 26/05/21 20 días
MOLDURAS
663 03.02.02.01 TARRAJEO PRIMARIO O  3 días jue 13/05/21 sáb 15/05/21 3 días
RAYADO C/MEZCLA 1 5
664 03.02.02.02 TARRAJEO MUROS  6 días vie 07/05/21 mié 12/05/21 6 días
INTERIORES MEZCLA C A 1 5
665 03.02.02.03 TARRAJEO MUROS  3 días jue 13/05/21 sáb 15/05/21 3 días
EXTERIORES MEZCLA C A 1 5
666 03.02.02.04 TARRAJEO EN COLUMNAS  1 día mié 12/05/21 mié 12/05/21 1 día
MEZCLA C A 1 5 E 1 5
667 03.02.02.05 TARRAJEO EN VIGAS  1 día mié 12/05/21 mié 12/05/21 1 día
MEZCLA C A 1 5 E 1 5
668 03.02.02.06 VESTIDURA DE DERRAMES  2 días jue 13/05/21 vie 14/05/21 2 días
MEZCLA C A 1 5 E 1 5
669 03.02.02.07 BRUÑA PARA RODOJUNTA  1 día mié 26/05/21 mié 26/05/21 1 día
DE COLOR SEGÚN DETALLE
670 03.02.02.08 RODOJUNTA DE COLOR GRIS 1 día mié 26/05/21 mié 26/05/21 1 día
SEGÚN DETALLE 2 días
671 03.02.03 CIELORRASOS 2 días mar 11/05/21 mié 12/05/21
672 03.02.03.01 TARRAJEO DE CIELO RASO  2 días mar 11/05/21 mié 12/05/21 2 días
MEZCLA 1 5 C A E 1 5CM 2 días
673 03.02.04 PISOS Y PAVIMENTOS 2 días mar 25/05/21 mié 26/05/21
674 03.02.04.01 PISO CERAMICA 0.45x0.45m  2 días mar 25/05/21 mié 26/05/21 2 días
(GRIS CLARO 1 día
675 03.02.04.02 REVESTIMIENTO DE  1 día mié 26/05/21 mié 26/05/21
PORCELANATO
676 03.02.05 ZOCALOS Y CONTRAZOCALOS 3 días mar 25/05/21 jue 27/05/21 3 días
677 03.02.05.01 ZOCALO CERAMICO  3 días mar 25/05/21 jue 27/05/21 3 días
0 45 0 45
678 03.02.05.02 ZOCALO CERAMICO 45 X 45  1 día jue 27/05/21 jue 27/05/21 1 día
ANTIDESLIZANTE DE COLOR 1 día
679 03.02.05.03 LISTELO DE CERAMICO  1 día jue 27/05/21 jue 27/05/21
CORTADO 0 45 0 10
680 03.02.05.04 CONTRAZOCALO SANITARIO  2 días mié 26/05/21 jue 27/05/21 2 días
DE CONCRETO 0 10 0 10 2 días
681 03.02.05.05 CONTRAZOCALO DE  2 días mié 26/05/21 jue 27/05/21
CEMENTO FROTACHADO
682 03.02.06 CARPINTERIA DE MADERA 3 días lun 03/05/21 mié 05/05/21 3 días
683 03.02.06.01 PUERTA CONTRAPLACADA  3 días lun 03/05/21 mié 05/05/21 3 días
C/T i l 6 00 MARCO
684 03.02.06.02 PUERTA MADERA TABLERO  3 días lun 03/05/21 mié 05/05/21 3 días
C/MARCO DE MADERA 5 días
685 03.02.07 CARPINTERIA METALICA 5 días sáb 01/05/21 mié 05/05/21
686 03.02.07.01 PUERTA METÁLICA  5 días sáb 01/05/21 mié 05/05/21 5 días
C/MARCO DE F°N° 4" 4" 2 días
687 03.02.08 CERRAJERIA 2 días mié 05/05/21 jue 06/05/21
688 03.02.08.01 PICAPORTE TIPO CERROJO  1 día mié 05/05/21 mié 05/05/21 1 día
PORTA CANDADO P/PUERTA
689 03.02.08.02 CERRADURA DE 3 GOLPES 1 día jue 06/05/21 jue 06/05/21 1 día
690 03.02.08.03 CERRADURA TIPO PERILLA 1 día jue 06/05/21 jue 06/05/21 1 día
691 03.02.08.04 BISAGRA CAPUCHINA DE  1 día jue 06/05/21 jue 06/05/21 1 día
ALUMINIO DE 4" X 4"
692 03.02.08.05 BISAGRA ESTRUCTURAL DE  1 día jue 06/05/21 jue 06/05/21 1 día
FIERRO DE 3/8 4"
693 03.02.08.06 JALADOR O TIRADOR  1 día jue 06/05/21 jue 06/05/21 1 día
CROMADO DE 128MM PARA
694 03.02.09 VIDRIOS, CRISTALES Y  1 día jue 06/05/21 jue 06/05/21 1 día
SIMILARES
695 03.02.09.01 VENTANA CON PERFILES DE  1 día jue 06/05/21 jue 06/05/21 1 día
ALUMNIO TIPO SISTEMA DE
696 03.02.09.02 INSTALACION DE ESPEJO  1 día jue 06/05/21 jue 06/05/21 1 día
E 6MM
697 03.02.10 PINTURA 8 días vie 30/04/21 vie 07/05/21 8 días
698 03.02.10.01 PINTURA OLEO MATE 02  3 días mar 04/05/21 jue 06/05/21 3 días
MANOS EN INTERIORES
699 03.02.10.02 PINTURA LATEX SATINADO  3 días sáb 01/05/21 lun 03/05/21 3 días
02 MANOS EN EXTERIORES
700 03.02.10.03 PINTURA OLEO MATE 2  1 día vie 30/04/21 vie 30/04/21 1 día
MANOS EN CIELO RASO
701 03.02.10.04 PINTURA LATEX SATINADO  1 día vie 30/04/21 vie 30/04/21 1 día
02 MANOS EN COLUMNAS Y
702 03.02.10.05 PINTURA LATEX SATINADO  1 día jue 06/05/21 jue 06/05/21 1 día
02 MANOS EN VESTIDURA
703 03.02.10.06 PINTURA BARNIZ 02 MANOS 1 día jue 06/05/21 jue 06/05/21 1 día
EN PUERTAS DE MADERA
704 03.02.10.07 PINTURA DE ESMALTE  1 día jue 06/05/21 jue 06/05/21 1 día
COLOR GRIS CLARO 02
705 03.02.10.08 PINTURA ANTICORROSIVA  2 días jue 06/05/21 vie 07/05/21 2 días
EN PUERTAS DE METAL
706 03.02.11 CUBIERTAS 2 días lun 14/06/21 mar 15/06/21 2 días
707 03.02.11.01 CUBIERTA LADRILLO  2 días lun 14/06/21 mar 15/06/21 2 días
PASTELERO ASENTADO
708 03.02.11.02 IMPERMEABILIZACION DE  1 día mar 15/06/21 mar 15/06/21 1 día
LADRILLO PASTELERO CON
709 03.02.12 VARIOS 4 días vie 25/06/21 lun 28/06/21 4 días
710 03.02.12.01 JUNTA DE DILATACIÓN  4 días vie 25/06/21 lun 28/06/21 4 días
C/TEKNOPORT Y SELLANTE
711 03.03 INSTALACIONES SANITARIAS 30 días lun 03/05/21 mar 01/06/21 30 días
712 03.03.01 APARATOS SANITARIOS Y  4 días lun 03/05/21 jue 06/05/21 4 días
ACCESORIOS
713 03.03.01.01 APARATOS SANITARIOS 4 días lun 03/05/21 jue 06/05/21 4 días
714 03.03.01.01.01 INODORO ONE PIECE  2 días mié 05/05/21 jue 06/05/21 2 días
SAVONA O SIMILAR DE
715 03.03.01.01.02 LAVAMANOS TIPO  2 días mié 05/05/21 jue 06/05/21 2 días
FONTANA CON PEDESTAL 1 día
716 03.03.01.01.03 URINARIO TIPO BAMBI  1 día jue 06/05/21 jue 06/05/21
DE LOZA VITRIFICADA
717 03.03.01.01.04 LAVADERO DE ACERO  2 días mié 05/05/21 jue 06/05/21 2 días
INOXIDABLE DE 1 POZA 4 días
718 03.03.01.01.05 COLOCACION DE  4 días lun 03/05/21 jue 06/05/21
APARATOS SANITARIOS
719 03.03.01.02 ACCESORIOS SANITARIOS 2 días mié 05/05/21 jue 06/05/21 2 días
720 03.03.01.02.01 DISPENSADOR DE PAPEL  2 días mié 05/05/21 jue 06/05/21 2 días
TOALLA PLASTICO
721 03.03.01.02.02 DISPENSADOR DE JABON  1 día jue 06/05/21 jue 06/05/21 1 día
LIQUIDO PLASTICO 1 día
722 03.03.01.02.03 PAPELERA DE LOSA Y  1 día jue 06/05/21 jue 06/05/21
BARRA PLASTICA
723 03.03.01.02.04 COLOCACION DE  2 días mié 05/05/21 jue 06/05/21 2 días
ACCESORIOS SANITARIOS 14 días
724 03.03.02 SISTEMA DE AGUA FRIA 14 días mié 19/05/21 mar 01/06/21
725 03.03.02.01 SALIDAS DE AGUA FRIA 1 día mié 19/05/21 mié 19/05/21 1 día
726 03.03.02.01.01 SALIDA DE AGUA  1 día mié 19/05/21 mié 19/05/21 1 día
P/APARATOS
727 03.03.02.02 REDES DE DISTRIBUCION 13 días jue 20/05/21 mar 01/06/21 13 días
728 03.03.02.02.01 TUBERÍA PVC Ø 3/4 " C/R. 1 día jue 20/05/21 jue 20/05/21 1 día
CLASE 10
729 03.03.02.02.02 TUBERÍA PVC Ø 1/2" C/R.  1 día jue 20/05/21 jue 20/05/21 1 día
CLASE 10
730 03.03.02.02.03 PRUEBA HIDRAÚLICA  1 día mar 01/06/21 mar 01/06/21 1 día
INTEGRAL
731 03.03.02.03 SUM. E INSTALACIÓN DE  2 días vie 21/05/21 sáb 22/05/21 2 días
ACCESORIOS PVC
732 03.03.02.03.01 TEE PVC Ø 3/4"x3/4" C/R. 1 día vie 21/05/21 vie 21/05/21 1 día
C 10
733 03.03.02.03.02 REDUCCIÓN PVC Ø 3/4" a 1 día vie 21/05/21 vie 21/05/21 1 día
1/2" C/R C 10
734 03.03.02.03.03 CODO PVC Ø 3/4" x 90º  1 día vie 21/05/21 vie 21/05/21 1 día
C/R C 10
735 03.03.02.03.04 CODO PVC Ø 1/2" x 90º  1 día sáb 22/05/21 sáb 22/05/21 1 día
C/R C 10
736 03.03.02.04 VALVULAS DE CONTROL 1 día lun 24/05/21 lun 24/05/21 1 día
737 03.03.02.04.01 VÁLVULA COMPUERTA  1 día lun 24/05/21 lun 24/05/21 1 día
PESADA BCE 150 PSI Ø
738 03.03.02.04.02 VÁLVULA TIPO GLOBO  1 día lun 24/05/21 lun 24/05/21 1 día
PESADA BCE 150 PSI Ø
739 03.03.02.05 CAJAS PARA VALVULAS 1 día mar 25/05/21 mar 25/05/21 1 día
740 03.03.02.05.01 CAJA DE MADERA SEGÚN 1 día mar 25/05/21 mar 25/05/21 1 día
DETALLE EN MURO

Tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica
Proyecto: LOS OLIVOS_LA YARA
División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso

Página 5
Id ITEM Nombre de tarea Duracion Comienzo Fin
Calendario 03 ene '21 10 ene '21 17 ene '21 24 ene '21 31 ene '21 07 feb '21 14 feb '21 21 feb '21 28 feb '21 07 mar '21 14 mar '21 21 mar '21 28 mar '21 04 abr '21 11 abr '21 18 abr '21 25 abr '21 02 may '21 09 may '21 16 may '21 23 may '21 30 may '21 06 jun '21 13 jun '21 20 jun '21 27 jun '21 04 jul '21 11 jul '21 18 jul '21 25 jul '21 01 ago '21 08 ago '21 15 ago '21 22 ago '21 29 ago '21
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
741 03.03.03 SISTEMA DE DRENAJE PLUVIAL 14 días jue 06/05/21 mié 19/05/21 14 días
742 03.03.03.01 REDES DE RECOLECCIÓN 1 día mar 18/05/21 mar 18/05/21 1 día
743 03.03.03.01.01 TUBERÍA PVC SAP Ø 2"  1 día mar 18/05/21 mar 18/05/21 1 día
S/P
744 03.03.03.02 ACCESORIOS 14 días jue 06/05/21 mié 19/05/21 14 días
745 03.03.03.02.01 CODO 90º PVC SAP Ø 2"  1 día mié 19/05/21 mié 19/05/21 1 día
S/P
746 03.03.03.02.02 CODO 45º PVC SAP Ø 2"  1 día mié 19/05/21 mié 19/05/21 1 día
S/P 1 día
747 03.03.03.02.03 SUMIDERO PVC SAP Ø3"  1 día jue 06/05/21 jue 06/05/21
S BRONCE CROMADO
748 03.03.03.02.04 SUMIDERO PVC SAP Ø2"  1 día jue 06/05/21 jue 06/05/21 1 día
S BRONCE CROMADO 12 días
749 03.03.04 SISTEMA DE DESAGUE Y  12 días jue 20/05/21 lun 31/05/21
VENTILACION
750 03.03.04.01 SALIDAS DE DESAGUE 1 día jue 20/05/21 jue 20/05/21 1 día
751 03.03.04.01.01 SALIDA DE DESAGUE PVC  1 día jue 20/05/21 jue 20/05/21 1 día
SAP Ø 4" S/P
752 03.03.04.01.02 SALIDA DE DESAGUE PVC  1 día jue 20/05/21 jue 20/05/21 1 día
SAP Ø 2" S/P 11 días
753 03.03.04.02 REDES DE DERIVACION 11 días vie 21/05/21 lun 31/05/21
754 03.03.04.02.01 TUBERÍA PVC SAP Ø 4"  1 día vie 21/05/21 vie 21/05/21 1 día
S/P
755 03.03.04.02.02 TUBERÍA PVC SAP Ø 2"  1 día vie 21/05/21 vie 21/05/21 1 día
S/P
756 03.03.04.02.03 PRUEBA INTEGRAL DE  1 día lun 31/05/21 lun 31/05/21 1 día
ESTANQUEIDAD EN RED
757 03.03.04.03 ACCESORIOS DE REDES 5 días sáb 22/05/21 mié 26/05/21 5 días
758 03.03.04.03.01 YEE PVC SAP Ø 4"x4" S/P 1 día sáb 22/05/21 sáb 22/05/21 1 día
759 03.03.04.03.02 YEE PVC SAP Ø 4"x2" S/P 1 día sáb 22/05/21 sáb 22/05/21 1 día
760 03.03.04.03.03 YEE PVC SAP Ø 2"x2" S/P 1 día sáb 22/05/21 sáb 22/05/21 1 día
761 03.03.04.03.04 CODO 45º PVC SAP Ø 4"  1 día lun 24/05/21 lun 24/05/21 1 día
S/P
762 03.03.04.03.05 CODO 45º PVC SAP Ø 2"  1 día lun 24/05/21 lun 24/05/21 1 día
S/P
763 03.03.04.03.06 SUMIDERO PVC SAP Ø2"  1 día mar 25/05/21 mar 25/05/21 1 día
S BRONCE CROMADO
764 03.03.04.03.07 REGISTRO ROSCADO DE  1 día mié 26/05/21 mié 26/05/21 1 día
BCE PESADO Ø4"
765 03.03.04.03.08 REGISTRO ROSCADO DE  1 día mié 26/05/21 mié 26/05/21 1 día
BCE PESADO Ø2"
766 03.03.04.04 SISTEMA DE VENTILACION 2 días mar 25/05/21 mié 26/05/21 2 días
767 03.03.04.04.01 SALIDA DE VENTILACIÓN  1 día mar 25/05/21 mar 25/05/21 1 día
DE PVC SAP Ø2" S/P
768 03.03.04.04.02 TUBERÍA PVC SAP Ø 2"  1 día mié 26/05/21 mié 26/05/21 1 día
S/P
769 03.03.04.04.03 SOMBRERO DE  1 día mié 26/05/21 mié 26/05/21 1 día
VENTILACION DE PVC 2"
770 04 BLOQUE C ‐ SERVICIOS GENERALES 212 días mié 25/11/20 jue 24/06/21 212 días
771 04.01 ESTRUCTURAS 168 días mié 25/11/20 mar 11/05/21 168 días
772 04.01.01 OBRAS PRELIMINARES 1 día mié 25/11/20 mié 25/11/20
773 04.01.01.01 TRAZO, NIVELES Y  1 día mié 25/11/20 mié 25/11/20
REPLANTEO
774 04.01.02 MOVIMIENTO DE TIERRAS 166 días jue 26/11/20 lun 10/05/21 166 días
775 04.01.02.01 EXCAVACION MANUAL DE  2 días jue 26/11/20 vie 27/11/20
ZANJAS PARA ZAPATAS
776 04.01.02.02 EXCAVACION MANUAL DE  3 días jue 03/12/20 sáb 05/12/20
ZANJA PARA CIMIENTOS
777 04.01.02.03 RELLENO Y COMPACTADO  1 día mié 31/03/21 mié 31/03/21 1 día
C/EQUIPO MATERIAL
778 04.01.02.04 AFIRMADO DE 4" PARA  1 día lun 10/05/21 lun 10/05/21 1 día
PISOS
779 04.01.02.05 NIVELACION INTERIOR Y  1 día sáb 08/05/21 sáb 08/05/21 1 día
COMPACTADO DEL 4 días
780 04.01.02.06 ACARREO DE MATERIAL  4 días mié 31/03/21 sáb 03/04/21
EXCEDENTE D 30
781 04.01.02.07 ELIMINACION DE MATERIAL  1 día vie 09/04/21 vie 09/04/21 1 día
EXCEDENTE C/MAQUINARIA 1 día
782 04.01.03 IMPERMEABILIZACIÓN 1 día mié 31/03/21 mié 31/03/21
783 04.01.03.01 IMPERMEABILIZACION CON  1 día mié 31/03/21 mié 31/03/21 1 día
ASFALTO 159 días
784 04.01.04 OBRAS DE CONCRETO SIMPLE 159 días vie 04/12/20 mar 11/05/21
785 04.01.04.01 SOLADOS Y CIMIENTOS 9 días vie 04/12/20 sáb 12/12/20
786 04.01.04.01.01 SOLADO CON MEZCLA  1 día vie 04/12/20 vie 04/12/20
1 12 C H E 4"
787 04.01.04.01.02 CIMIENTO CORRIDO:  1 día sáb 12/12/20 sáb 12/12/20
CONCRETO CICLOPEO 1 día
788 04.01.04.02 FALSO PISO 1 día mar 11/05/21 mar 11/05/21
789 04.01.04.02.01 FALSO PISO E=4" C:H 1:8  1 día mar 11/05/21 mar 11/05/21 1 día
C/ADITIVO
790 04.01.04.03 SOBRECIMIENTOS 3 días jue 24/12/20 sáb 26/12/20
791 04.01.04.03.01 SOBRECIMIENTO:  1 día sáb 26/12/20 sáb 26/12/20
CONCRETO F'C 175
792 04.01.04.03.02 SOBRECIMIENTO:  3 días jue 24/12/20 sáb 26/12/20
ENCOFRADO Y
793 04.01.05 OBRAS DE CONCRETO  123 días mié 02/12/20 sáb 03/04/21 123 días
ARMADO
794 04.01.05.01 ZAPATAS 2 días jue 03/12/20 vie 04/12/20
795 04.01.05.01.01 ZAPATAS: CONCRETO  1 día vie 04/12/20 vie 04/12/20
F'C 210 KG/CM2
796 04.01.05.01.02 ACERO CORRUGADO  2 días jue 03/12/20 vie 04/12/20
F 4 200 k / 2
797 04.01.05.02 COLUMNAS Y PLACAS 119 días mié 02/12/20 mar 30/03/21 119 días
798 04.01.05.02.01 COLUMNAS Y PLACAS:  1 día mar 30/03/21 mar 30/03/21 1 día
CONCRETO F'C 210
799 04.01.05.02.02 COLUMNAS Y PLACAS:  4 días sáb 27/03/21 mar 30/03/21 4 días
ENCOFRADO Y
800 04.01.05.02.03 ACERO CORRUGADO  3 días mié 02/12/20 vie 04/12/20
F 4 200 k / 2
801 04.01.05.03 COLUMNETAS DE AMARRE 98 días vie 25/12/20 jue 01/04/21 98 días
802 04.01.05.03.01 COLUMNETAS DE  1 día jue 01/04/21 jue 01/04/21 1 día
AMARRE CONCRETO
803 04.01.05.03.02 COLUMNETAS DE  1 día jue 01/04/21 jue 01/04/21 1 día
AMARRE CONCRETO
804 04.01.05.03.03 COLUMNETAS DE  2 días mié 31/03/21 jue 01/04/21 2 días
AMARRE ENCOFRADO Y
805 04.01.05.03.04 ACERO CORRUGADO  2 días vie 25/12/20 sáb 26/12/20
F 4 200 k / 2
806 04.01.05.04 VIGAS 9 días vie 26/03/21 sáb 03/04/21 9 días
807 04.01.05.04.01 VIGAS: CONCRETO  1 día sáb 03/04/21 sáb 03/04/21 1 día
F'C 210 k / 2
808 04.01.05.04.02 VIGAS: ENCOFRADO Y  8 días vie 26/03/21 vie 02/04/21 8 días
DESENCOFRADO
809 04.01.05.04.03 ACERO CORRUGADO  2 días jue 01/04/21 vie 02/04/21 2 días
F 4 200 k / 2
810 04.01.05.05 VIGUETAS DE AMARRE 2 días lun 29/03/21 mar 30/03/21 2 días
811 04.01.05.05.01 VIGUETAS DE AMARRE:  1 día mar 30/03/21 mar 30/03/21 1 día
CONCRETO F'C 175
812 04.01.05.05.02 VIGUETAS DE AMARRE:  1 día mar 30/03/21 mar 30/03/21 1 día
ENCOFRADO Y
813 04.01.05.05.03 ACERO CORRUGADO  1 día lun 29/03/21 lun 29/03/21 1 día
F 4 200 k / 2
814 04.01.05.06 LOSAS ALIGERADAS 9 días vie 26/03/21 sáb 03/04/21 9 días
815 04.01.05.06.01 LOSA ALIGERADA:  1 día sáb 03/04/21 sáb 03/04/21 1 día
CONCRETO F'C 210
816 04.01.05.06.02 LOSA ALIGERADA:  8 días vie 26/03/21 vie 02/04/21 8 días
ENCOFRADO Y
817 04.01.05.06.03 LOSA ALIGERADA:  1 día vie 02/04/21 vie 02/04/21 1 día
LADRILLO HUECO
818 04.01.05.06.04 ACERO CORRUGADO  1 día vie 02/04/21 vie 02/04/21 1 día
F 4 200 k / 2 24 días
819 04.01.06 VARIOS 24 días sáb 20/03/21 lun 12/04/21
820 04.01.06.01 CURADO DE ELEMENTOS DE  24 días sáb 20/03/21 lun 12/04/21 24 días
CONCRETO 92 días
821 04.02 ARQUITECTURA 92 días jue 25/03/21 jue 24/06/21
822 04.02.01 MUROS Y TABIQUES DE  6 días jue 25/03/21 mar 30/03/21 6 días
ALBAÑILERIA 6 días
823 04.02.01.01 MURO DE LADRILLO KK TIPO 6 días jue 25/03/21 mar 30/03/21
IV SOGA M 1 1 5 E 1 5 CM
824 04.02.01.02 MURO DE LADRILLO KK TIPO 1 día mar 30/03/21 mar 30/03/21 1 día
IV CABEZA M 1 1 5 E 1 5 CM 24 días
825 04.02.02 REVOQUES ENLUCIDOS Y  24 días lun 26/04/21 mié 19/05/21
MOLDURAS
826 04.02.02.01 TARRAJEO PRIMARIO O  4 días sáb 01/05/21 mar 04/05/21 4 días
RAYADO C/MEZCLA 1 5 8 días
827 04.02.02.02 TARRAJEO MUROS  8 días mar 27/04/21 mar 04/05/21
INTERIORES MEZCLA C A 1 5
828 04.02.02.03 TARRAJEO MUROS  4 días sáb 01/05/21 mar 04/05/21 4 días
EXTERIORES MEZCLA C A 1 5 1 día
829 04.02.02.04 TARRAJEO EN COLUMNAS  1 día lun 26/04/21 lun 26/04/21
MEZCLA C A 1 5 E 1 5
830 04.02.02.05 TARRAJEO EN VIGAS  1 día lun 26/04/21 lun 26/04/21 1 día
MEZCLA C A 1 5 E 1 5 3 días
831 04.02.02.06 VESTIDURA DE DERRAMES  3 días mié 05/05/21 vie 07/05/21
MEZCLA C A 1 5 E 1 5
832 04.02.02.07 BRUÑA PARA RODOJUNTA  1 día mar 18/05/21 mar 18/05/21 1 día
DE COLOR SEGÚN DETALLE 1 día
833 04.02.02.08 RODOJUNTA DE COLOR GRIS 1 día mié 19/05/21 mié 19/05/21
SEGÚN DETALLE
834 04.02.03 CIELORRASOS 5 días jue 22/04/21 lun 26/04/21 5 días
835 04.02.03.01 TARRAJEO DE CIELO RASO  5 días jue 22/04/21 lun 26/04/21 5 días
MEZCLA 1 5 C A E 1 5CM
836 04.02.04 PISOS Y PAVIMENTOS 2 días mar 18/05/21 mié 19/05/21 2 días
837 04.02.04.01 PISO DE CONCRETO F'C=175  1 día mié 19/05/21 mié 19/05/21 1 día
KG/CM2 E 2'' ACABADO
838 04.02.04.02 PISO CERAMICA 0.45x0.45m  1 día mar 18/05/21 mar 18/05/21 1 día
(GRIS CLARO
839 04.02.04.03 REVESTIMIENTO DE  1 día mar 18/05/21 mar 18/05/21 1 día
PORCELANATO
840 04.02.05 ZOCALOS Y CONTRAZOCALOS 6 días sáb 15/05/21 jue 20/05/21 6 días
841 04.02.05.01 ZOCALO CERAMICO  3 días sáb 15/05/21 lun 17/05/21 3 días
0 45 0 45
842 04.02.05.02 LISTELO DE CERAMICO  1 día lun 17/05/21 lun 17/05/21 1 día
CORTADO 0 45 0 10
843 04.02.05.03 CONTRAZOCALO CERAMICO  1 día mié 19/05/21 mié 19/05/21 1 día
ANTIDESLIZANTE GRIS
844 04.02.05.04 CONTRAZOCALO SANITARIO  1 día jue 20/05/21 jue 20/05/21 1 día
DE CONCRETO 0 10 0 10
845 04.02.05.05 CONTRAZOCALO DE  1 día jue 20/05/21 jue 20/05/21 1 día
CEMENTO PULIDO H 0 20M
846 04.02.06 CARPINTERIA DE MADERA 2 días vie 07/05/21 sáb 08/05/21 2 días
847 04.02.06.01 PUERTA CONTRAPLACADA  1 día vie 07/05/21 vie 07/05/21 1 día
C/T i l 6 00 MARCO
848 04.02.06.02 PUERTA MADERA TABLERO  2 días vie 07/05/21 sáb 08/05/21 2 días
C/MARCO DE MADERA
849 04.02.07 CARPINTERIA METALICA 6 días lun 10/05/21 sáb 15/05/21 6 días
850 04.02.07.01 ESTRUCTURAS METALICAS 6 días lun 10/05/21 sáb 15/05/21 6 días
851 04.02.07.01.01 PUERTA METALICA  6 días lun 10/05/21 sáb 15/05/21 6 días
C/MALLA GALVANIZADA
852 04.02.08 CERRAJERIA 2 días lun 10/05/21 mar 11/05/21 2 días
853 04.02.08.01 PICAPORTE TIPO CERROJO  1 día lun 10/05/21 lun 10/05/21 1 día
PORTA CANDADO P/PUERTA
854 04.02.08.02 CERRADURA DE 3 GOLPES 2 días lun 10/05/21 mar 11/05/21 2 días
855 04.02.08.03 CERRADURA TIPO PERILLA 1 día lun 10/05/21 lun 10/05/21 1 día
856 04.02.08.04 BISAGRA CAPUCHINA DE  1 día lun 10/05/21 lun 10/05/21 1 día
ALUMINIO DE 4" X 4"
857 04.02.08.05 BISAGRA ESTRUCTURAL DE  1 día lun 10/05/21 lun 10/05/21 1 día
FIERRO DE 3/8 4"
858 04.02.08.06 JALADOR O TIRADOR  1 día lun 10/05/21 lun 10/05/21 1 día
CROMADO DE 128MM PARA
859 04.02.09 VIDRIOS, CRISTALES Y  2 días vie 07/05/21 sáb 08/05/21 2 días
SIMILARES 1 día
860 04.02.09.01 VENTANA CON PERFILES DE  1 día vie 07/05/21 vie 07/05/21
ALUMNIO TIPO SISTEMA DE
861 04.02.09.02 INSTALACION DE ESPEJO  1 día sáb 08/05/21 sáb 08/05/21 1 día
E 6MM 13 días
862 04.02.10 PINTURA 13 días lun 10/05/21 sáb 22/05/21
863 04.02.10.01 PINTURA OLEO MATE 02  4 días mar 18/05/21 vie 21/05/21 4 días
MANOS EN INTERIORES 2 días
864 04.02.10.02 PINTURA LATEX SATINADO  2 días jue 20/05/21 vie 21/05/21
02 MANOS EN EXTERIORES
865 04.02.10.03 PINTURA OLEO MATE 2  2 días jue 20/05/21 vie 21/05/21 2 días
MANOS EN CIELO RASO 1 día
866 04.02.10.04 PINTURA LATEX SATINADO  1 día vie 21/05/21 vie 21/05/21
02 MANOS EN COLUMNAS Y
867 04.02.10.05 PINTURA LATEX SATINADO  1 día sáb 22/05/21 sáb 22/05/21 1 día
02 MANOS EN VESTIDURA 2 días
868 04.02.10.06 PINTURA BARNIZ 02 MANOS 2 días lun 10/05/21 mar 11/05/21
EN PUERTAS DE MADERA
869 04.02.10.07 PINTURA DE ESMALTE  1 día mié 12/05/21 mié 12/05/21 1 día
COLOR GRIS CLARO 02 2 días
870 04.02.10.08 PINTURA ANTICORROSIVA  2 días lun 17/05/21 mar 18/05/21
EN PUERTAS DE METAL
871 04.02.11 CUBIERTAS 6 días mié 26/05/21 lun 31/05/21 6 días
872 04.02.11.01 CUBIERTA LADRILLO  3 días mié 26/05/21 vie 28/05/21 3 días
PASTELERO ASENTADO
873 04.02.11.02 IMPERMEABILIZACION DE  3 días sáb 29/05/21 lun 31/05/21 3 días
LADRILLO PASTELERO CON 3 días
874 04.02.12 VARIOS 3 días mar 22/06/21 jue 24/06/21
875 04.02.12.01 JUNTA DE DILATACIÓN  3 días mar 22/06/21 jue 24/06/21 3 días
C/TEKNOPORT Y SELLANTE
876 04.03 INSTALACIONES SANITARIAS 21 días mar 11/05/21 lun 31/05/21 21 días
877 04.03.01 APARATOS SANITARIOS Y  3 días jue 20/05/21 sáb 22/05/21 3 días
ACCESORIOS
878 04.03.01.01 APARATOS SANITARIOS 3 días jue 20/05/21 sáb 22/05/21 3 días
879 04.03.01.01.01 INODORO ONE PIECE  1 día sáb 22/05/21 sáb 22/05/21 1 día
SAVONA O SIMILAR DE
880 04.03.01.01.02 LAVAMANOS TIPO  1 día sáb 22/05/21 sáb 22/05/21 1 día
FONTANA CON PEDESTAL
881 04.03.01.01.03 DUCHA ECO ROCIADOR  1 día sáb 22/05/21 sáb 22/05/21 1 día
DE BROCE CROMADO
882 04.03.01.01.04 COLOCACION DE  3 días jue 20/05/21 sáb 22/05/21 3 días
APARATOS SANITARIOS
883 04.03.01.02 ACCESORIOS SANITARIOS 3 días jue 20/05/21 sáb 22/05/21 3 días
884 04.03.01.02.01 DISPENSADOR DE PAPEL  1 día sáb 22/05/21 sáb 22/05/21 1 día
TOALLA PLASTICO
885 04.03.01.02.02 DISPENSADOR DE JABON  1 día sáb 22/05/21 sáb 22/05/21 1 día
LIQUIDO PLASTICO
886 04.03.01.02.03 PAPELERA DE LOSA Y  1 día sáb 22/05/21 sáb 22/05/21 1 día
BARRA PLASTICA
887 04.03.01.02.04 JABONERA DE LOZA  1 día sáb 22/05/21 sáb 22/05/21 1 día
VITRIFICADA COLOR
888 04.03.01.02.05 PERCHERO DE LOSA  1 día sáb 22/05/21 sáb 22/05/21 1 día
VITRIFICADA BLANCA

Tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica
Proyecto: LOS OLIVOS_LA YARA
División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso

Página 6
Id ITEM Nombre de tarea Duracion Comienzo Fin
Calendario 03 ene '21 10 ene '21 17 ene '21 24 ene '21 31 ene '21 07 feb '21 14 feb '21 21 feb '21 28 feb '21 07 mar '21 14 mar '21 21 mar '21 28 mar '21 04 abr '21 11 abr '21 18 abr '21 25 abr '21 02 may '21 09 may '21 16 may '21 23 may '21 30 may '21 06 jun '21 13 jun '21 20 jun '21 27 jun '21 04 jul '21 11 jul '21 18 jul '21 25 jul '21 01 ago '21 08 ago '21 15 ago '21 22 ago '21 29 ago '21
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
889 04.03.01.02.06 COLOCACION DE  3 días jue 20/05/21 sáb 22/05/21 3 días
ACCESORIOS SANITARIOS
890 04.03.02 SISTEMA DE AGUA FRIA 8 días mar 11/05/21 mar 18/05/21 8 días
891 04.03.02.01 SALIDAS DE AGUA FRIA 1 día mar 11/05/21 mar 11/05/21 1 día
892 04.03.02.01.01 SALIDA DE AGUA  1 día mar 11/05/21 mar 11/05/21 1 día
P/APARATOS 7 días
893 04.03.02.02 REDES DE DISTRIBUCION 7 días mié 12/05/21 mar 18/05/21
894 04.03.02.02.01 TUBERÍA PVC Ø 3/4 " C/R. 1 día mié 12/05/21 mié 12/05/21 1 día
CLASE 10 1 día
895 04.03.02.02.02 TUBERÍA PVC Ø 1/2" C/R.  1 día jue 13/05/21 jue 13/05/21
CLASE 10
896 04.03.02.02.03 PRUEBA HIDRAÚLICA  1 día mar 18/05/21 mar 18/05/21 1 día
INTEGRAL 2 días
897 04.03.02.03 SUM. E INSTALACIÓN DE  2 días jue 13/05/21 vie 14/05/21
ACCESORIOS PVC
898 04.03.02.03.01 TEE PVC Ø 3/4"x3/4" C/R. 1 día jue 13/05/21 jue 13/05/21 1 día
C 10 1 día
899 04.03.02.03.02 REDUCCIÓN PVC Ø 3/4" a 1 día jue 13/05/21 jue 13/05/21
1/2" C/R C 10
900 04.03.02.03.03 CODO PVC Ø 3/4" x 90º  1 día vie 14/05/21 vie 14/05/21 1 día
C/R C 10 1 día
901 04.03.02.03.04 CODO PVC Ø 1/2" x 90º  1 día vie 14/05/21 vie 14/05/21
C/R C 10
902 04.03.02.04 VALVULAS DE CONTROL 1 día sáb 15/05/21 sáb 15/05/21 1 día
903 04.03.02.04.01 VÁLVULA COMPUERTA  1 día sáb 15/05/21 sáb 15/05/21 1 día
PESADA BCE 150 PSI Ø
904 04.03.02.05 CAJAS PARA VALVULAS 1 día lun 17/05/21 lun 17/05/21 1 día
905 04.03.02.05.01 CAJA DE MADERA SEGÚN 1 día lun 17/05/21 lun 17/05/21 1 día
DETALLE EN MURO
906 04.03.03 SISTEMA DE DRENAJE PLUVIAL 21 días mar 11/05/21 lun 31/05/21 21 días
907 04.03.03.01 REDES DE RECOLECCIÓN 2 días mar 11/05/21 mié 12/05/21 2 días
908 04.03.03.01.01 TUBERÍA PVC SAP Ø 2"  2 días mar 11/05/21 mié 12/05/21 2 días
S/P
909 04.03.03.02 CANALETAS DE CONCRETO 11 días vie 21/05/21 lun 31/05/21 11 días
910 04.03.03.02.01 EXCAVACION MANUAL  1 día vie 21/05/21 vie 21/05/21 1 día
EN TERRENO NORMAL
911 04.03.03.02.02 ACARREO DE MATERIAL  1 día sáb 22/05/21 sáb 22/05/21 1 día
EXCEDENTE D 30
912 04.03.03.02.03 ELIMINACION DE  1 día lun 24/05/21 lun 24/05/21 1 día
MATERIAL EXCEDENTE
913 04.03.03.02.04 CANALETA CON REJILLA  4 días vie 28/05/21 lun 31/05/21 4 días
DE FIERRO DE 35 CM
914 04.03.03.03 ACCESORIOS 2 días jue 13/05/21 vie 14/05/21 2 días
915 04.03.03.03.01 CODO 90º PVC SAP Ø 2"  1 día jue 13/05/21 jue 13/05/21 1 día
S/P
916 04.03.03.03.02 CODO 45º PVC SAP Ø 2"  1 día jue 13/05/21 jue 13/05/21 1 día
S/P
917 04.03.03.03.03 SUMIDERO PVC SAP Ø3"  1 día vie 14/05/21 vie 14/05/21 1 día
S BRONCE CROMADO
918 04.03.03.03.04 SUMIDERO PVC SAP Ø2"  1 día vie 14/05/21 vie 14/05/21 1 día
S BRONCE CROMADO
919 04.03.04 SISTEMA DE DESAGUE Y  15 días jue 13/05/21 jue 27/05/21 15 días
VENTILACION
920 04.03.04.01 SALIDAS DE DESAGUE 2 días jue 13/05/21 vie 14/05/21 2 días
921 04.03.04.01.01 SALIDA DE DESAGUE PVC  1 día jue 13/05/21 jue 13/05/21 1 día
SAP Ø 4" S/P
922 04.03.04.01.02 SALIDA DE DESAGUE PVC  1 día vie 14/05/21 vie 14/05/21 1 día
SAP Ø 2" S/P
923 04.03.04.02 REDES DE DERIVACION 13 días sáb 15/05/21 jue 27/05/21 13 días
924 04.03.04.02.01 TUBERÍA PVC SAP Ø 4"  1 día sáb 15/05/21 sáb 15/05/21 1 día
S/P
925 04.03.04.02.02 TUBERÍA PVC SAP Ø 3"  1 día sáb 15/05/21 sáb 15/05/21 1 día
S/P
926 04.03.04.02.03 TUBERÍA PVC SAP Ø 2"  1 día sáb 15/05/21 sáb 15/05/21 1 día
S/P
927 04.03.04.02.04 PRUEBA INTEGRAL DE  1 día jue 27/05/21 jue 27/05/21 1 día
ESTANQUEIDAD EN RED 3 días
928 04.03.04.03 ACCESORIOS DE REDES 3 días sáb 15/05/21 lun 17/05/21
929 04.03.04.03.01 YEE PVC SAP Ø 4"x4" S/P 1 día lun 17/05/21 lun 17/05/21 1 día
930 04.03.04.03.02 YEE PVC SAP Ø 4"x2" S/P 1 día lun 17/05/21 lun 17/05/21 1 día
931 04.03.04.03.03 YEE PVC SAP Ø 3"x2" S/P 1 día lun 17/05/21 lun 17/05/21 1 día
932 04.03.04.03.04 YEE PVC SAP Ø 2"x2" S/P 1 día lun 17/05/21 lun 17/05/21 1 día
933 04.03.04.03.05 CODO 45º PVC SAP Ø 4"  1 día lun 17/05/21 lun 17/05/21 1 día
S/P 1 día
934 04.03.04.03.06 CODO 45º PVC SAP Ø 2"  1 día lun 17/05/21 lun 17/05/21
S/P
935 04.03.04.03.07 SUMIDERO PVC SAP Ø2"  1 día sáb 15/05/21 sáb 15/05/21 1 día
S BRONCE CROMADO 1 día
936 04.03.04.03.08 REGISTRO ROSCADO DE  1 día sáb 15/05/21 sáb 15/05/21
BCE PESADO Ø4"
937 04.03.04.03.09 REGISTRO ROSCADO DE  1 día sáb 15/05/21 sáb 15/05/21 1 día
BCE PESADO Ø 3" 3 días
938 04.03.04.04 SISTEMA DE VENTILACION 3 días mar 18/05/21 jue 20/05/21
939 04.03.04.04.01 SALIDA DE VENTILACIÓN  1 día mar 18/05/21 mar 18/05/21 1 día
DE PVC SAP Ø2" S/P 1 día
940 04.03.04.04.02 TUBERÍA PVC SAP Ø 2"  1 día mié 19/05/21 mié 19/05/21
S/P
941 04.03.04.04.03 SOMBRERO DE  1 día jue 20/05/21 jue 20/05/21 1 día
VENTILACION DE PVC 2" 40 días
942 05 CERCO PERIMETRICO 40 días mar 18/05/21 sáb 26/06/21
943 05.01 ESTRUCTURAS 40 días mar 18/05/21 sáb 26/06/21 40 días
944 05.01.01 OBRAS PRELIMINARES 2 días mar 18/05/21 mié 19/05/21 2 días
945 05.01.01.01 TRAZO, NIVELES Y  2 días mar 18/05/21 mié 19/05/21 2 días
REPLANTEO
946 05.01.02 MOVIMIENTO DE TIERRAS 18 días mié 19/05/21 sáb 05/06/21 18 días
947 05.01.02.01 EXCAVACION MANUAL DE  8 días mié 19/05/21 mié 26/05/21 8 días
ZANJA PARA CIMIENTOS
948 05.01.02.02 RELLENO Y COMPACTADO  3 días jue 27/05/21 sáb 29/05/21 3 días
C/EQUIPO MATERIAL
949 05.01.02.03 ACARREO DE MATERIAL  5 días lun 31/05/21 vie 04/06/21 5 días
EXCEDENTE D 30
950 05.01.02.04 ELIMINACION DE MATERIAL  1 día sáb 05/06/21 sáb 05/06/21 1 día
EXCEDENTE C/MAQUINARIA
951 05.01.03 OBRAS DE CONCRETO SIMPLE 1 día mié 26/05/21 mié 26/05/21 1 día
952 05.01.03.01 SOLADOS Y CIMIENTOS 1 día mié 26/05/21 mié 26/05/21 1 día
953 05.01.03.01.01 CIMIENTO CORRIDO:  1 día mié 26/05/21 mié 26/05/21 1 día
CONCRETO CICLOPEO
954 05.01.04 OBRAS DE CONCRETO  30 días mié 26/05/21 jue 24/06/21 30 días
ARMADO
955 05.01.04.01 SOBRECIMIENTO ARMADO 6 días mié 26/05/21 lun 31/05/21 6 días
956 05.01.04.01.01 SOBRECIMIENTO  1 día lun 31/05/21 lun 31/05/21 1 día
ARMADO CONCRETO
957 05.01.04.01.02 SOBRECIMIENTO  5 días jue 27/05/21 lun 31/05/21 5 días
ARMADO ENCOFRADO Y
958 05.01.04.01.03 ACERO CORRUGADO  2 días mié 26/05/21 jue 27/05/21 2 días
F 4 200 k / 2
959 05.01.04.02 COLUMNAS Y PLACAS 4 días lun 14/06/21 jue 17/06/21 4 días
960 05.01.04.02.01 COLUMNAS: CONCRETO  4 días lun 14/06/21 jue 17/06/21 4 días
F'C 210 KG/CM2 C/ADIT
961 05.01.04.02.02 COLUMNAS: ENCOFRADO 4 días lun 14/06/21 jue 17/06/21 4 días
Y DESENCOFRADO
962 05.01.04.02.03 ACERO CORRUGADO  4 días lun 14/06/21 jue 17/06/21 4 días
F 4 200 k / 2
963 05.01.04.03 VIGAS 7 días vie 18/06/21 jue 24/06/21 7 días
964 05.01.04.03.01 VIGAS: CONCRETO  1 día jue 24/06/21 jue 24/06/21 1 día
F'C 210 KG/CM2
965 05.01.04.03.02 VIGAS: ENCOFRADO Y  6 días vie 18/06/21 mié 23/06/21 6 días
DESENCOFRADO
966 05.01.04.03.03 ACERO CORRUGADO  2 días mar 22/06/21 mié 23/06/21 2 días
F 4 200 k / 2 2 días
967 05.01.04.04 LOSAS ALIGERADAS 2 días mié 23/06/21 jue 24/06/21
968 05.01.04.04.01 LOSA ALIGERADA:  1 día jue 24/06/21 jue 24/06/21 1 día
CONCRETO F'C 210 1 día
969 05.01.04.04.02 LOSA ALIGERADA:  1 día mié 23/06/21 mié 23/06/21
ENCOFRADO Y
970 05.01.04.04.03 LOSA ALIGERADA:  1 día mié 23/06/21 mié 23/06/21 1 día
LADRILLO HUECO 1 día
971 05.01.04.04.04 ACERO CORRUGADO  1 día mié 23/06/21 mié 23/06/21
F 4 200 k / 2
972 05.01.05 VARIOS 31 días jue 27/05/21 sáb 26/06/21 31 días
973 05.01.05.01 CURADO DE ELEMENTOS DE  23 días jue 27/05/21 vie 18/06/21 23 días
CONCRETO
974 05.01.05.02 JUNTA DE CONSTRUCCION  2 días vie 25/06/21 sáb 26/06/21 2 días
DE JEBE MICROPOROSO 23 días
975 05.02 ARQUITECTURA 23 días mié 26/05/21 jue 17/06/21
976 05.02.01 MUROS Y TABIQUES DE  8 días mar 01/06/21 mar 08/06/21 8 días
ALBAÑILERIA 8 días
977 05.02.01.01 MURO DE LADRILLO KK TIPO 8 días mar 01/06/21 mar 08/06/21
IV SOGA M 1 1 5 E 1 5 CM
978 05.02.01.02 MURO DE LADRILLO KK TIPO 2 días lun 07/06/21 mar 08/06/21 2 días
IV CABEZA M 1 1 5 E 1 5 CM 18 días
979 05.02.02 REVOQUES ENLUCIDOS Y  18 días mié 26/05/21 sáb 12/06/21
MOLDURAS
980 05.02.02.01 TARRAJEO EN MUROS  9 días mié 26/05/21 jue 03/06/21 9 días
INTERIORES Y EXTERIORES 1 día
981 05.02.02.02 TARRAJEO EN COLUMNAS  1 día mar 01/06/21 mar 01/06/21
MEZCLA C A 1 5 E 1 5
982 05.02.02.03 TARRAJEO EN VIGAS  1 día mar 01/06/21 mar 01/06/21 1 día
MEZCLA C A 1 5 E 1 5 3 días
983 05.02.02.04 VESTIDURA DE DERRAMES  3 días jue 10/06/21 sáb 12/06/21
MEZCLA C A 1 5 E 1 5
984 05.02.02.05 BRUÑAS SEGÚN DETALLE 1"  3 días lun 31/05/21 mié 02/06/21 3 días
1
985 05.02.03 CIELORRASOS 1 día jue 17/06/21 jue 17/06/21 1 día
986 05.02.03.01 TARRAJEO DE CIELO RASO  1 día jue 17/06/21 jue 17/06/21 1 día
MEZCLA 1 5 C A E 1 5CM
987 05.02.04 ZOCALOS Y CONTRAZOCALOS 1 día jue 03/06/21 jue 03/06/21 1 día
988 05.02.04.01 CONTRAZOCALO CEMENTO  1 día jue 03/06/21 jue 03/06/21 1 día
FROTACHADO GRIS OSCURO
989 05.02.05 PINTURA 12 días vie 04/06/21 mar 15/06/21 12 días
990 05.02.05.01 PINTURA LATEX SANITADO  9 días lun 07/06/21 mar 15/06/21 9 días
02 MANOS EN INTERIORES Y
991 05.02.05.02 PINTURA LATEX SATINADO 2 1 día vie 04/06/21 vie 04/06/21 1 día
MANOS EN CIELO RASO
992 05.02.05.03 PINTURA LATEX SATINADO  1 día sáb 05/06/21 sáb 05/06/21 1 día
02 MANOS EN COLUMNAS Y
993 05.02.06 CUBIERTAS 2 días mié 16/06/21 jue 17/06/21 2 días
994 05.02.06.01 CUBIERTA LADRILLO  1 día mié 16/06/21 mié 16/06/21 1 día
PASTELERO ASENTADO
995 05.02.06.02 IMPERMEABILIZACION DE  1 día jue 17/06/21 jue 17/06/21 1 día
LADRILLO PASTELERO CON
996 05.02.07 VARIOS 2 días lun 31/05/21 mar 01/06/21 2 días
997 05.02.07.01 LIMPIEZA FINAL DE OBRA 2 días lun 31/05/21 mar 01/06/21 2 días
998 06 ESTRUCTURAS HIDRAULICAS DE  35 días vie 28/05/21 jue 01/07/21 35 días
CONCRETO
999 06.01 OBRAS PRELIMINARES 4 días vie 28/05/21 lun 31/05/21 4 días
1000 06.01.01 TRAZO, NIVELES Y REPLANTEO  4 días vie 28/05/21 lun 31/05/21 4 días
P/ESTRUCTURAS
1001 06.02 MOVIMIENTO DE TIERRAS 35 días vie 28/05/21 jue 01/07/21 35 días
1002 06.02.01 EXCAVACION MANUAL PARA  12 días vie 28/05/21 mar 08/06/21 12 días
ESTRUCTURAS
1003 06.02.02 NIVELACION INTERIOR Y  8 días mié 02/06/21 mié 09/06/21 8 días
COMPACTADO DEL FONDO
1004 06.02.03 RELLENO Y COMPACTADO  4 días lun 28/06/21 jue 01/07/21 4 días
C/EQUIPO MATERIAL
1005 06.02.04 ACARREO DE MATERIAL  14 días mié 09/06/21 mar 22/06/21 14 días
EXCEDENTE D 30
1006 06.02.05 ELIMINACION DE MATERIAL  1 día mié 23/06/21 mié 23/06/21 1 día
EXCEDENTE C/MAQUINARIA
1007 06.03 OBRAS DE CONCRETO SIMPLE 24 días jue 03/06/21 sáb 26/06/21 24 días
1008 06.03.01 SOLADO CON MEZCLA 1:12 C:H  2 días jue 03/06/21 vie 04/06/21 2 días
E 4"
1009 06.03.02 CIMIENTO CORRIDO:  5 días mar 22/06/21 sáb 26/06/21 5 días
CONCRETO CICLOPEO MEZCLA 22 días
1010 06.04 OBRAS DE CONCRETO ARMADO 22 días jue 10/06/21 jue 01/07/21
1011 06.04.01 TANQUE CISTERNA 13 días jue 10/06/21 mar 22/06/21 13 días
1012 06.04.01.01 TANQUE CISTERNA: LOSA  2 días lun 14/06/21 mar 15/06/21 2 días
CONCRETO F'C 280 k / 2
1013 06.04.01.02 TANQUE CISTERNA: MURO  1 día sáb 19/06/21 sáb 19/06/21 1 día
CONCRETO F'C 280 k / 2 1 día
1014 06.04.01.03 TANQUE CISTERNA: LOSA  1 día mar 22/06/21 mar 22/06/21
MACIZA CONCRETO F'C 280
1015 06.04.01.04 TANQUE CISTERNA: MUROS  4 días mié 16/06/21 sáb 19/06/21 4 días
ENCOFRADO Y 1 día
1016 06.04.01.05 TANQUE CISTERNA: LOSA  1 día lun 21/06/21 lun 21/06/21
MACIZA ENCOFRADO Y
1017 06.04.01.06 TANQUE CISTERNA: ACERO  12 días jue 10/06/21 lun 21/06/21 12 días
FY 4200 KG/CM2 1 día
1018 06.04.02 PLATAFORMA PARA  1 día sáb 26/06/21 sáb 26/06/21
BIODIGESTOR
1019 06.04.02.01 PLATAFORMA: CONCRETO  1 día sáb 26/06/21 sáb 26/06/21 1 día
F'C 175 KG/CM2 1 día
1020 06.04.02.02 PLATAFORMA: ACERO  1 día sáb 26/06/21 sáb 26/06/21
f 4200 k / 2
1021 06.04.03 CAJA DE BIODIGESTOR 10 días mar 22/06/21 jue 01/07/21 10 días
1022 06.04.03.01 CAJA DE BIODIGESTOR:  1 día vie 25/06/21 vie 25/06/21 1 día
MURO CONCRETO F'C 175
1023 06.04.03.02 CAJA DE BIODIGESTOR:  3 días mar 22/06/21 jue 24/06/21 3 días
MURO ENCOFRADO Y
1024 06.04.03.03 CAJA DE BIODIGESTOR:  1 día jue 24/06/21 jue 24/06/21 1 día
MURO ACERO CORRUGADO
1025 06.04.03.04 CAJA DE REGISTRO P/  1 día jue 01/07/21 jue 01/07/21 1 día
BIOGESTOR
1026 06.04.04 CAJA DE LODOS 2 días vie 25/06/21 sáb 26/06/21 2 días
1027 06.04.04.01 CAJA DE LODOS: CONCRETO  1 día sáb 26/06/21 sáb 26/06/21 1 día
F'C 175 K / 2 C/ADIT
1028 06.04.04.02 CAJA DE LODOS:  1 día vie 25/06/21 vie 25/06/21 1 día
ENCOFRADO Y
1029 06.04.04.03 CAJA DE LODOS: ACERO  1 día vie 25/06/21 vie 25/06/21 1 día
CORRUGADO F 4 200
1030 06.04.05 POZO PERCOLADOR 6 días sáb 26/06/21 jue 01/07/21 6 días
1031 06.04.05.01 VIGAS DE CONFINAMIENTO 5 días sáb 26/06/21 mié 30/06/21 5 días
1032 06.04.05.01.01 VIGAS DE  5 días sáb 26/06/21 mié 30/06/21 5 días
CONFINAMIENTO
1033 06.04.05.01.02 VIGAS DE  5 días sáb 26/06/21 mié 30/06/21 5 días
CONFINAMIENTO
1034 06.04.05.01.03 VIGAS DE  5 días sáb 26/06/21 mié 30/06/21 5 días
CONFINAMIENTO ACERO
1035 06.04.05.02 LOSA MACIZA EN POZO DE  2 días mié 30/06/21 jue 01/07/21 2 días
PERCOLACIÓN
1036 06.04.05.02.01 LOSA MACIZA:  1 día mié 30/06/21 mié 30/06/21 1 día
CONCRETO F'C 175

Tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica
Proyecto: LOS OLIVOS_LA YARA
División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso

Página 7
Id ITEM Nombre de tarea Duracion Comienzo Fin
Calendario 03 ene '21 10 ene '21 17 ene '21 24 ene '21 31 ene '21 07 feb '21 14 feb '21 21 feb '21 28 feb '21 07 mar '21 14 mar '21 21 mar '21 28 mar '21 04 abr '21 11 abr '21 18 abr '21 25 abr '21 02 may '21 09 may '21 16 may '21 23 may '21 30 may '21 06 jun '21 13 jun '21 20 jun '21 27 jun '21 04 jul '21 11 jul '21 18 jul '21 25 jul '21 01 ago '21 08 ago '21 15 ago '21 22 ago '21 29 ago '21
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
1037 06.04.05.02.02 LOSA MACIZA:  1 día jue 01/07/21 jue 01/07/21 1 día
ENCOFRADO Y
1038 06.04.05.02.03 LOSA MACIZA: ACERO  1 día jue 01/07/21 jue 01/07/21 1 día
CORRUGADO F 4 200 4 días
1039 06.05 MUROS 4 días sáb 26/06/21 mar 29/06/21
1040 06.05.01 MUROS DE LADRILLO KK  4 días sáb 26/06/21 mar 29/06/21 4 días
10 14 24 CM 1 4 X 1 5 CM DE 1 día
1041 06.06 OTROS 1 día jue 01/07/21 jue 01/07/21
1042 06.06.01 IMPERMEABILIZACION CON  1 día jue 01/07/21 jue 01/07/21 1 día
ASFALTO 1 día
1043 06.06.02 REVESTIMIENTO INTERIOR CON 1 día jue 01/07/21 jue 01/07/21
ADITIVO
1044 06.06.03 RELLENO MANUAL CON GRAVA 1 día jue 01/07/21 jue 01/07/21 1 día
1'' A 1 1/2'' 1 día
1045 06.06.04 RELLENO MANUAL CON GRAVA 1 día jue 01/07/21 jue 01/07/21
3/4'' A 1''
1046 06.06.05 TAPA METALICA P/POZO  1 día jue 01/07/21 jue 01/07/21 1 día
PERCOLADOR 34 días
1047 07 CAMINERIAS Y AREAS VERDES 34 días sáb 29/05/21 jue 01/07/21
1048 07.01 AREAS DE CIRCULACION 34 días sáb 29/05/21 jue 01/07/21 34 días
1049 07.01.01 ESTRUCTURAS 20 días sáb 29/05/21 jue 17/06/21 20 días
1050 07.01.01.01 OBRAS PRELIMINARES 3 días sáb 29/05/21 lun 31/05/21 3 días
1051 07.01.01.01.01 TRAZO, NIVELES Y  3 días sáb 29/05/21 lun 31/05/21 3 días
REPLANTEO PRELIMINAR
1052 07.01.01.02 MOVIMIENTO DE TIERRAS 12 días lun 31/05/21 vie 11/06/21 12 días
1053 07.01.01.02.01 NIVELACION INTERIOR Y  8 días lun 31/05/21 lun 07/06/21 8 días
COMPACTADO DEL
1054 07.01.01.02.02 AFIRMADO DE 4" PARA  5 días lun 07/06/21 vie 11/06/21 5 días
PISOS
1055 07.01.01.03 ENCOFRADO Y SOLAQUEO 15 días jue 03/06/21 jue 17/06/21 15 días
1056 07.01.01.03.01 ENCOFRADO Y  7 días vie 11/06/21 jue 17/06/21 7 días
DESENCOFRADO DE
1057 07.01.01.03.02 SOLAQUEO EN VEREDAS 2 días jue 03/06/21 vie 04/06/21 2 días
1058 07.01.02 ARQUITECTURA 27 días sáb 05/06/21 jue 01/07/21 27 días
1059 07.01.02.01 CAMINERÍAS 14 días vie 18/06/21 jue 01/07/21 14 días
1060 07.01.02.01.01 VEREDA DE CONCRETO  4 días lun 28/06/21 jue 01/07/21 4 días
F'C 175 KG/CM2 E 4"
1061 07.01.02.01.02 RAMPA DE CONCRETO  1 día vie 18/06/21 vie 18/06/21 1 día
F'C 175 KG/CM2 E 4"
1062 07.01.02.02 PINTURA 3 días sáb 19/06/21 lun 21/06/21 3 días
1063 07.01.02.02.01 SEÑALIZACIÓN DEL  3 días sáb 19/06/21 lun 21/06/21 3 días
PAVIMENTO
1064 07.01.02.03 VARIOS 14 días sáb 05/06/21 vie 18/06/21 14 días
1065 07.01.02.03.01 SUMINISTRO E  2 días jue 17/06/21 vie 18/06/21 2 días
INSTALACIÓN DE
1066 07.01.02.03.02 LIMPIEZA FINAL DE OBRA 6 días sáb 05/06/21 jue 10/06/21 6 días
1067 07.02 AREAS VERDES 4 días mié 16/06/21 sáb 19/06/21 4 días
1068 07.02.01 ARQUITECTURA 4 días mié 16/06/21 sáb 19/06/21 4 días
1069 07.02.01.01 PINTURA 2 días mié 16/06/21 jue 17/06/21 2 días
1070 07.02.01.01.01 PINTURA ESMALTE EN  2 días mié 16/06/21 jue 17/06/21 2 días
SARDINEL PERALTADO
1071 07.02.01.02 SEMBRIO DE GRASS,  2 días vie 18/06/21 sáb 19/06/21 2 días
PLANTAS Y ARBOLES
1072 07.02.01.02.01 SUMINISTRO Y  1 día vie 18/06/21 vie 18/06/21 1 día
COLOCACION DE PIEDRA
1073 07.02.01.02.02 SUMINISTRO Y  1 día sáb 19/06/21 sáb 19/06/21 1 día
PLANTADO DE ARBOLES
1074 07.03 SEÑALIZACION 1 día sáb 05/06/21 sáb 05/06/21 1 día
1075 07.03.01 SEÑALIZACION 1 día sáb 05/06/21 sáb 05/06/21 1 día
1076 07.03.01.01 CARTEL DE SALIDA 1 día sáb 05/06/21 sáb 05/06/21 1 día
1077 07.03.01.02 SALIDA A LA DERECHA 1 día sáb 05/06/21 sáb 05/06/21 1 día
1078 07.03.01.03 SALIDA A LA IZQUIERDA 1 día sáb 05/06/21 sáb 05/06/21 1 día
1079 07.03.01.04 ALARMA CONTRA  1 día sáb 05/06/21 sáb 05/06/21 1 día
INCENDIOS 1 día
1080 07.03.01.05 ZONA SEGURA EN CASOS DE 1 día sáb 05/06/21 sáb 05/06/21
SISMO
1081 07.03.01.06 BOTIQUIN DE PRIMEROS  1 día sáb 05/06/21 sáb 05/06/21 1 día
AUXILIOS 1 día
1082 07.03.01.07 EXTINTOR PQS ‐ ABC N 1 día sáb 05/06/21 sáb 05/06/21
1083 07.03.01.08 ATENCIÓN: RIESGO  1 día sáb 05/06/21 sáb 05/06/21 1 día
ELÉCTRICO 1 día
1084 07.03.01.09 ALARMA SIRENA 1 día sáb 05/06/21 sáb 05/06/21
1085 08 INSTALACIONES SANITARIAS 42 días sáb 22/05/21 vie 02/07/21 42 días
1086 08.01 OBRAS PROVISIONALES 3 días sáb 22/05/21 lun 24/05/21 3 días
1087 08.01.01 TRAZO, NIVELACION Y  3 días sáb 22/05/21 lun 24/05/21 3 días
REPLANTEO INICIAL C /EQUIPO 18 días
1088 08.02 MOVIMIENTO DE TIERRAS 18 días lun 24/05/21 jue 10/06/21
1089 08.02.01 EXCAVACION MANUAL DE  3 días lun 24/05/21 mié 26/05/21 3 días
ZANJA P/TUBERIAS 1 día
1090 08.02.02 CAMA DE APOYO E=0.10 M 1 día jue 27/05/21 jue 27/05/21
1091 08.02.03 SOBRECAMA PROTECTORA  1 día sáb 29/05/21 sáb 29/05/21 1 día
C/MAT PRESTAMO
1092 08.02.04 RELLENO Y COMPACTADO  1 día mié 02/06/21 mié 02/06/21 1 día
C/MATERIAL PROPIO
1093 08.02.05 ACARREO DE MATERIAL  1 día mié 09/06/21 mié 09/06/21 1 día
EXCEDENTE D 30
1094 08.02.06 ELIMINACION DE MATERIAL  1 día jue 10/06/21 jue 10/06/21 1 día
EXCEDENTE C/MAQUINARIA
1095 08.03 APARATOS SANITARIOS Y  3 días mar 08/06/21 jue 10/06/21 3 días
ACCESORIOS
1096 08.03.01 APARATOS SANITARIOS 3 días mar 08/06/21 jue 10/06/21 3 días
1097 08.03.01.01 GRIFERÍA CLÁSICA INC.  3 días mar 08/06/21 jue 10/06/21 3 días
ACCESORIOS
1098 08.03.01.02 GRIFO DE RIEGO DE 1/2" 3 días mar 08/06/21 jue 10/06/21 3 días
1099 08.03.01.03 COLOCACION DE APARATOS  3 días mar 08/06/21 jue 10/06/21 3 días
SANITARIOS
1100 08.04 SISTEMA DE AGUA FRIA 37 días jue 27/05/21 vie 02/07/21 37 días
1101 08.04.01 SALIDAS DE AGUA FRIA 1 día sáb 29/05/21 sáb 29/05/21 1 día
1102 08.04.01.01 SALIDA DE AGUA  1 día sáb 29/05/21 sáb 29/05/21 1 día
P/APARATOS SANITARIOS Ø
1103 08.04.02 REDES DE ALIMENTACION 12 días jue 27/05/21 lun 07/06/21 12 días
1104 08.04.02.01 TUBERÍA PVC Ø 2" C/R  1 día vie 28/05/21 vie 28/05/21 1 día
CLASE 10
1105 08.04.02.02 TUBERÍA PVC Ø 1 1/2 " C/R.  1 día vie 28/05/21 vie 28/05/21 1 día
CLASE 10
1106 08.04.02.03 TUBERÍA PVC Ø 1 1/4" C/R.  2 días jue 27/05/21 vie 28/05/21 2 días
CLASE 10
1107 08.04.02.04 TUBERÍA PVC Ø 1 " C/R.  2 días jue 27/05/21 vie 28/05/21 2 días
CLASE 10
1108 08.04.02.05 TUBERÍA PVC Ø 3/4 " C/R.  1 día jue 27/05/21 jue 27/05/21 1 día
CLASE 10
1109 08.04.02.06 TUBERÍA PVC Ø 1/2" C/R.  2 días jue 27/05/21 vie 28/05/21 2 días
CLASE 10
1110 08.04.02.07 PRUEBA HIDRAÚLICA  3 días sáb 05/06/21 lun 07/06/21 3 días
INTEGRAL DESINFECCIÓN
1111 08.04.03 SUM. E INSTALACIÓN DE  5 días sáb 29/05/21 mié 02/06/21 5 días
ACCESORIOS PVC
1112 08.04.03.01 TEE PVC Ø 2"x2" C/R. C‐10 1 día sáb 29/05/21 sáb 29/05/21 1 día
1113 08.04.03.02 TEE PVC Ø 1 1/2"x1 1/2"  1 día sáb 29/05/21 sáb 29/05/21 1 día
C/R C 10
1114 08.04.03.03 TEE PVC Ø 1 1/4"x1 1/4"  1 día sáb 29/05/21 sáb 29/05/21 1 día
C/R C 10 1 día
1115 08.04.03.04 TEE PVC Ø 1"x1" C/R. C‐10 1 día lun 31/05/21 lun 31/05/21
1116 08.04.03.05 TEE PVC Ø 1/2"x1/2" C/R.  1 día lun 31/05/21 lun 31/05/21 1 día
C 10 1 día
1117 08.04.03.06 REDUCCIÓN PVC Ø 2" a 1  1 día lun 31/05/21 lun 31/05/21
1/2" C/R C 10
1118 08.04.03.07 REDUCCIÓN PVC Ø 1 1/2" a  1 día lun 31/05/21 lun 31/05/21 1 día
1 1/4" C/R C 10 1 día
1119 08.04.03.08 REDUCCIÓN PVC Ø 1 1/4" a  1 día mar 01/06/21 mar 01/06/21
1" C/R C 10
1120 08.04.03.09 REDUCCIÓN PVC Ø 1 " a 3/4" 1 día mar 01/06/21 mar 01/06/21 1 día
C/R C 10 1 día
1121 08.04.03.10 REDUCCIÓN PVC Ø 3/4" a  1 día mar 01/06/21 mar 01/06/21
1/2" C/R C 10
1122 08.04.03.11 CODO PVC Ø 2" x 90º C/R.  1 día mar 01/06/21 mar 01/06/21 1 día
C 10 1 día
1123 08.04.03.12 CODO PVC Ø 1 1/2 " x 90º  1 día mié 02/06/21 mié 02/06/21
C/R C 10
1124 08.04.03.13 CODO PVC Ø 1 1/4" x 90º  1 día mié 02/06/21 mié 02/06/21 1 día
C/R C 10 1 día
1125 08.04.03.14 CODO PVC Ø 1 " x 90º C/R.  1 día mié 02/06/21 mié 02/06/21
C 10
1126 08.04.03.15 CODO PVC Ø 1/2" x 90º C/R.  1 día mié 02/06/21 mié 02/06/21 1 día
C 10 1 día
1127 08.04.04 VALVULAS DE CONTROL 1 día jue 03/06/21 jue 03/06/21
1128 08.04.04.01 VÁLVULA TIPO GLOBO  1 día jue 03/06/21 jue 03/06/21 1 día
PESADA BCE 150 PSI Ø 1/2" 1 día
1129 08.04.05 CAJAS PARA VALVULAS 1 día vie 04/06/21 vie 04/06/21
1130 08.04.05.01 CAJA DE MADERA SEGÚN  1 día vie 04/06/21 vie 04/06/21 1 día
DETALLE EN MURO 19 días
1131 08.04.06 CISTERNA: TUBERIA Y  19 días lun 14/06/21 vie 02/07/21
ACCESORIOS
1132 08.04.06.01 TUBERÍA F°G° Ø 2" C/R 1 día lun 14/06/21 lun 14/06/21 1 día
1133 08.04.06.02 TUBERÍA F°G° Ø 1 1/2" C/R 2 días mar 15/06/21 mié 16/06/21 2 días
1134 08.04.06.03 CODO F°G° Ø 2" x 90° C/R. 1 día mié 16/06/21 mié 16/06/21 1 día
1135 08.04.06.04 CODO F°G° Ø 1 1/2" x 90º  1 día mié 16/06/21 mié 16/06/21 1 día
C/R
1136 08.04.06.05 UNION UNIVERSAL F° G° Ø1" 1 día mié 16/06/21 mié 16/06/21 1 día
1137 08.04.06.06 UNION UNIVERSAL F° G° Ø1  1 día jue 17/06/21 jue 17/06/21 1 día
1/2"
1138 08.04.06.07 UNION UNIVERSAL PVC Ø2"  1 día jue 17/06/21 jue 17/06/21 1 día
C/R
1139 08.04.06.08 TEE F°G° Ø 1 " x 1" C/R 1 día jue 17/06/21 jue 17/06/21 1 día
1140 08.04.06.09 VALVULA CHECK Ø1 1/2" 1 día jue 17/06/21 jue 17/06/21 1 día
1141 08.04.06.10 ELECTROBOMBA  2 días vie 25/06/21 sáb 26/06/21 2 días
CENTRIFUGA 3 HP
1142 08.04.06.11 BRIDA DE F°.G° ROMPE  1 día vie 02/07/21 vie 02/07/21 1 día
AGUA Ø 1"
1143 08.04.06.12 BRIDA DE F°.G° ROMPE  1 día vie 02/07/21 vie 02/07/21 1 día
AGUA Ø 2"
1144 08.04.06.13 VALVULA DE PIE DE 2" CON  1 día vie 18/06/21 vie 18/06/21 1 día
CANASTILLA
1145 08.04.06.14 VALVULA FLOTADORA DE 1" 1 día vie 18/06/21 vie 18/06/21 1 día
1146 08.04.06.15 VALVULA DE COMPUERTA  2 días vie 18/06/21 sáb 19/06/21 2 días
PESADA BCE 150 PSI Ø 1 "
1147 08.04.06.16 TAPA SANITARIA INGRESO  1 día lun 21/06/21 lun 21/06/21 1 día
0 50X0 50 M
1148 08.04.06.17 TAPA SANITARIA 0.80X0.80  1 día lun 21/06/21 lun 21/06/21 1 día
M
1149 08.04.06.18 TAPON PVC Ø1" 1 día lun 28/06/21 lun 28/06/21 1 día
1150 08.04.06.19 CONTROL DE NIVEL 1 día lun 28/06/21 lun 28/06/21 1 día
1151 08.04.06.20 REJILLA METALICA PARA  1 día lun 21/06/21 lun 21/06/21 1 día
CAJA DE BOMBA DE
1152 08.04.07 TANQUE ELEVADO 5 días lun 21/06/21 vie 25/06/21 5 días
1153 08.04.07.01 TUBERÍA PVC Ø 2" C/R  1 día lun 21/06/21 lun 21/06/21 1 día
CLASE 10
1154 08.04.07.02 TEE F°G° Ø 1 1/2" x 1 1/2"  1 día lun 21/06/21 lun 21/06/21 1 día
C/R
1155 08.04.07.03 CODO F°G° Ø 1 1/2" x 90º  1 día lun 21/06/21 lun 21/06/21 1 día
C/R 1 día
1156 08.04.07.04 UNION UNIVERSAL PVC Ø2"  1 día mar 22/06/21 mar 22/06/21
C/R
1157 08.04.07.05 UNION UNIVERSAL F° G° Ø1  1 día mar 22/06/21 mar 22/06/21 1 día
1/2" 1 día
1158 08.04.07.06 VALVULA GLOBO 2" 1 día mié 23/06/21 mié 23/06/21
1159 08.04.07.07 VALVULA GLOBO 1 1/2" 1 día jue 24/06/21 jue 24/06/21 1 día
1160 08.04.07.08 SUMNISTRO E INSTALACION  1 día vie 25/06/21 vie 25/06/21 1 día
DE TANQUE ELEVADO DE
1161 08.04.07.09 SOMBRERO DE  1 día vie 25/06/21 vie 25/06/21 1 día
VENTILACION DE PVC 2" 20 días
1162 08.04.08 VARIOS COMPLEMENTARIOS 20 días vie 11/06/21 mié 30/06/21
1163 08.04.08.01 PROTECCIÓN PARA TUBERIA  1 día mié 30/06/21 mié 30/06/21 1 día
EN TECHO 1 día
1164 08.04.08.02 EMPALME A RED EXISTENTE  1 día vie 11/06/21 vie 11/06/21
DE AGUA
1165 08.04.08.03 PRUEBA HIDRAÚLICA  1 día sáb 26/06/21 sáb 26/06/21 1 día
INTEGRAL DESINFECCIÓN 18 días
1166 08.05 SISTEMA DE DESAGUE EXTERIOR 18 días lun 24/05/21 jue 10/06/21
1167 08.05.01 TRABAJOS PRELIMINARES 2 días lun 24/05/21 mar 25/05/21 2 días
1168 08.05.01.01 TRAZO, NIVELACION Y  2 días lun 24/05/21 mar 25/05/21 2 días
REPLANTEO INICIAL
1169 08.05.02 MOVIMIENTO DE TIERRAS 17 días mar 25/05/21 jue 10/06/21 17 días
1170 08.05.02.01 EXCAVACION MANUAL DE  4 días mar 25/05/21 vie 28/05/21 4 días
ZANJA P/TUBERIAS
1171 08.05.02.02 CAMA DE APOYO E=0.10 M 2 días jue 27/05/21 vie 28/05/21 2 días
1172 08.05.02.03 SOBRECAMA PROTECTORA  3 días sáb 29/05/21 lun 31/05/21 3 días
C/MAT PRESTAMO
1173 08.05.02.04 RELLENO Y COMPACTADO  1 día mar 01/06/21 mar 01/06/21 1 día
C/MATERIAL PROPIO
1174 08.05.02.05 ACARREO DE MATERIAL  2 días mar 08/06/21 mié 09/06/21 2 días
EXCEDENTE D 30
1175 08.05.02.06 ELIMINACION DE MATERIAL  1 día jue 10/06/21 jue 10/06/21 1 día
EXCEDENTE C/MAQUINARIA
1176 08.05.03 REDES COLECTORAS DE  13 días jue 27/05/21 mar 08/06/21 13 días
DESAGUE
1177 08.05.03.01 SUMINISTRO E INSTALACION 2 días jue 27/05/21 vie 28/05/21 2 días
DE TUBERIA S 25 UF 160
1178 08.05.03.02 SUMINISTRO E INSTALACION 2 días jue 27/05/21 vie 28/05/21 2 días
DE TUBERIA S 25 UF 110
1179 08.05.03.03 TUBERÍA PVC SAP Ø 2" S/P 1 día vie 28/05/21 vie 28/05/21 1 día
1180 08.05.03.04 PRUEBA INTEGRAL DE  2 días lun 07/06/21 mar 08/06/21 2 días
ESTANQUEIDAD EN RED DE
1181 08.05.04 CAJAS 4 días mié 02/06/21 sáb 05/06/21 4 días
1182 08.05.04.01 CAJA DE REGISTRO CIEGA  2 días mié 02/06/21 jue 03/06/21 2 días
PREFABRICADA DE
1183 08.05.04.02 CAJA DE REGISTRO CIEGA  1 día jue 03/06/21 jue 03/06/21 1 día
PREFABRICADA DE
1184 08.05.04.03 CAJA DE REGISTRO  1 día vie 04/06/21 vie 04/06/21 1 día
PREFABRICADA DE

Tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica
Proyecto: LOS OLIVOS_LA YARA
División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso

Página 8
Id ITEM Nombre de tarea Duracion Comienzo Fin
Calendario 03 ene '21 10 ene '21 17 ene '21 24 ene '21 31 ene '21 07 feb '21 14 feb '21 21 feb '21 28 feb '21 07 mar '21 14 mar '21 21 mar '21 28 mar '21 04 abr '21 11 abr '21 18 abr '21 25 abr '21 02 may '21 09 may '21 16 may '21 23 may '21 30 may '21 06 jun '21 13 jun '21 20 jun '21 27 jun '21 04 jul '21 11 jul '21 18 jul '21 25 jul '21 01 ago '21 08 ago '21 15 ago '21 22 ago '21 29 ago '21
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
1185 08.05.04.04 CAJA DE REGISTRO  1 día vie 04/06/21 vie 04/06/21 1 día
PREFABRICADA DE
1186 08.05.04.05 CAJA DE REGISTRO  1 día sáb 05/06/21 sáb 05/06/21 1 día
PREFABRICADA DE 19 días
1187 08.06 VARIOS 19 días lun 14/06/21 vie 02/07/21
1188 08.06.01 INSTALACION DE  19 días lun 14/06/21 vie 02/07/21 19 días
TRATAMIENTOS DE AGUAS 1 día
1189 08.06.01.01 OBRAS PRELIMINARES 1 día lun 14/06/21 lun 14/06/21
1190 08.06.01.01.01 TRAZO, NIVELACION Y  1 día lun 14/06/21 lun 14/06/21 1 día
REPLANTEO INICIAL 8 días
1191 08.06.01.02 MOVIMIENTO DE TIERRAS 8 días mar 15/06/21 mar 22/06/21
1192 08.06.01.02.01 EXCAVACION MANUAL  1 día mar 15/06/21 mar 15/06/21 1 día
DE ZANJA P/TUBERIAS 1 día
1193 08.06.01.02.02 CAMA DE APOYO E=0.10  1 día mié 16/06/21 mié 16/06/21
M
1194 08.06.01.02.03 SOBRECAMA  1 día mié 16/06/21 mié 16/06/21 1 día
PROTECTORA C/MAT 1 día
1195 08.06.01.02.04 RELLENO Y  1 día jue 17/06/21 jue 17/06/21
COMPACTADO
1196 08.06.01.02.05 ACARREO DE MATERIAL  1 día vie 18/06/21 vie 18/06/21 1 día
EXCEDENTE D 30 1 día
1197 08.06.01.02.06 ELIMINACION DE  1 día mar 22/06/21 mar 22/06/21
MATERIAL EXCEDENTE
1198 08.06.01.03 CARPINTERIA METALICA 1 día vie 25/06/21 vie 25/06/21 1 día
1199 08.06.01.03.01 SUMINISTRO E  1 día vie 25/06/21 vie 25/06/21 1 día
INSTALACION DE TAPA
1200 08.06.01.03.02 SUMINISTRO E  1 día vie 25/06/21 vie 25/06/21 1 día
INSTALACION DE TAPA
1201 08.06.01.04 SISTEMA DE  1 día mié 16/06/21 mié 16/06/21 1 día
ALCANTARILLADO
1202 08.06.01.04.01 SUMINISTRO E  1 día mié 16/06/21 mié 16/06/21 1 día
INSTALACION DE
1203 08.06.01.04.02 SUMINISTRO E  1 día mié 16/06/21 mié 16/06/21 1 día
INSTALACION DE
1204 08.06.01.04.03 SUMINISTRO E  1 día mié 16/06/21 mié 16/06/21 1 día
INSTALACION DE
1205 08.06.01.04.04 SUMINISTRO E  1 día mié 16/06/21 mié 16/06/21 1 día
INSTALACION DE CODO
1206 08.06.01.05 SUMINISTRO E  1 día vie 02/07/21 vie 02/07/21 1 día
INSTALACION DE
1207 08.06.01.05.01 SUMINISTRO E INST. DE  1 día vie 02/07/21 vie 02/07/21 1 día
BIODIGESTOR DE 5000
1208 COMPONENTE II : ADECUADO  60 días sáb  mar  60 días
1209 EQUIPOS Y MOBILIARIOS 60 días sáb 03/07/21 mar 31/08/21 60 días
1210 CONSULTORIO DE MEDICINA  60 días sáb 03/07/21 mar 31/08/21 60 días
GENERAL
1211 CONSULTORIO DE ATENCION  60 días sáb 03/07/21 mar 31/08/21 60 días
INTEGRAL AL ADOLESCENTE Y
1212 CONSULTORIO DE PLANIFICACION  60 días sáb 03/07/21 mar 31/08/21 60 días
FAMILIAR
1213 CONSULTORIO DE CONTROL  60 días sáb 03/07/21 mar 31/08/21 60 días
PRENATAL
1214 CONSULTORIO DE  60 días sáb 03/07/21 mar 31/08/21 60 días
PSICOPROFILAXIS
1215 CONSULTORIO DE ESTIMULACION  60 días sáb 03/07/21 mar 31/08/21 60 días
TEMPRANA
1216 CONSULTORIO DE CRECIMIENTO Y  60 días sáb 03/07/21 mar 31/08/21 60 días
DESARROLLO
1217 SALA DE INMUNIZACIONES 60 días sáb 03/07/21 mar 31/08/21 60 días
1218 CONSULTORIO ODONTOLOGICO 60 días sáb 03/07/21 mar 31/08/21 60 días
1219 ADMISION 60 días sáb 03/07/2mar 31/08/2 60 días
1220 HALL SALA DE ESPERA (1ER PISO) 60 días sáb 03/07/21 mar 31/08/21 60 días
1221 INFORMES ADMISION Y CAJA 60 días sáb 03/07/21 mar 31/08/21 60 días
1222 ARCHIVO E HISTORIAS CLINICAS 60 días sáb 03/07/21 mar 31/08/21 60 días
1223 SEGUROS REFERENCIA Y  60 días sáb 03/07/21 mar 31/08/21 60 días
CONTRAREFERENCIA 60 días
1224 CUARTO TECNICO 60 días sáb 03/07/21 mar 31/08/21
1225 DEPOSITO DE LIMPIEZA 60 días sáb 03/07/21 mar 31/08/21 60 días
1226 TOPICO DE PROCEDIMIENTOS DE 60 días sáb  mar  60 días
CONSULTA EXTERNA
1227 TOPICO 60 días sáb 03/07/21 mar 31/08/21 60 días
1228 TOPICO DE EMERGENCIA 60 días sáb 03/07/2mar 31/08/2 60 días
1229 TOPICO DE EMERGENCIA 60 días sáb 03/07/21 mar 31/08/21 60 días
1230 TRIAJE, SS.HH. Y DEPOSITO 60 días sáb 03/07/2mar 31/08/2 60 días
1231 APOYO (TRIAJE, SS.HH. ) 60 días sáb 03/07/21 mar 31/08/21 60 días
1232 PREVENCION Y CONTROL DEL TBC 60 días sáb 03/07/2mar 31/08/2 60 días
1233 CONSULTORIO DE TBC 60 días sáb 03/07/21 mar 31/08/21 60 días
1234 TOMA DE MEDICAMENTOS 60 días sáb 03/07/21 mar 31/08/21 60 días
1235 TOMA DE MUESTRAS DE ESPUTO 60 días sáb 03/07/21 mar 31/08/21 60 días
1236 SERVICIOS HIGIENICOS 60 días sáb 03/07/21 mar 31/08/21 60 días
1237 DISPENSACION Y EXPENDIO DE 60 días sáb  mar  60 días
MEDICAMENTOS
1238 DISPENSACION DE  60 días sáb 03/07/21 mar 31/08/21 60 días
MEDICAMENTOS Y ALMACEN DE
1239 ATENCION DIRECTA Y DE SOPORTE-UPS 60 días sáb  mar  60 días
SERVICIOS GENERALES
1240 CADENA DE FRIO 60 días sáb 03/07/21 mar 31/08/21 60 días
1241 UPS DE TRANSPORTE 60 días sáb 03/07/21 mar 31/08/21 60 días
1242 UPS SALUD AMBIENTAL 60 días sáb 03/07/2mar 31/08/2 60 días
1243 SALUD AMBIENTAL 60 días sáb 03/07/21 mar 31/08/21 60 días
1244 UPS RESIDENCIA PARA PERSONAL 60 días sáb 03/07/2mar 31/08/2 60 días
1245 SALA DE STAR‐COCINA‐COMEDOR 60 días sáb 03/07/21 mar 31/08/21 60 días
1246 DORMITORIO Y SS.HH. (DAMAS Y  60 días sáb 03/07/21 mar 31/08/21 60 días
1247 UPSVARONES)
DE ADMINISTRACION 60 días sáb 03/07/2mar 31/08/2 60 días
1248 HALL 2DO NIVEL 60 días sáb 03/07/21 mar 31/08/21 60 días
1249 GERENCIA 60 días sáb 03/07/21 mar 31/08/21 60 días
1250 SALA DE REUNIONES 60 días sáb 03/07/21 mar 31/08/21 60 días
1251 SECRETARIA Y ESPERA 60 días sáb 03/07/21 mar 31/08/21 60 días
1252 DEPOSITO DE LIMPIEZA 60 días sáb 03/07/21 mar 31/08/21 60 días
1253 UPS GESTION DE LA INFORMACION 60 días sáb 03/07/2mar 31/08/2 60 días
1254 SALA DE ESTADISTICA 60 días sáb 03/07/21 mar 31/08/21 60 días
1255 COMPONENTE III : ADECUADA  44 días lun  mar  44 días
1256 CAPACITACION I 15 días lun 19/07/2 lun 02/08/2 15 días
1257 CLIMA LABORAL, TRABAJO EN 15 días lun  lun  15 días
EQUIPO Y MANEJO DE
1258 CAPACITACION II 16 días lun 02/08/2 mar 17/08/2 16 días
1259 SERVICIO AL CIUDADANO 16 días lun 02/08/21mar 17/08/2 16 días
1260 CAPACITACION III 15 días mar 17/08/2mar 31/08/2 15 días
1261 ATENCION DE CALIDAD Y 15 días mar  mar  15 días
CALIDEZ PARA EL CLIENTE

Tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica
Proyecto: LOS OLIVOS_LA YARA
División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso

Página 9