2.2 CIMENTACION TUBERIAS PRINCIPALES, DESCOLE Y M3 2036.41632 $ 18,000.00 $ 36,655,493.76 $ 18,000.00 $ 36,655,493.76
DOMICILIARIAS ( COMPACTADO)
2.3 LLENADO CON MATERIAL DE EXCAVACION M3 4454.19196 $ 18,000.00 $ 80,175,455.28 $ 8,656.00 $ 38,555,485.61
3 CONSTRUCCION POZOS DE INSPECCION $ -
1 CONSTRUCCION DE MURO EN PIEDRA A TODO COSTO ML 120 $ 183,333.33 $ 21,999,999.60 $ 183,333.33 $ 21,999,999.60
PARA LA URBANIZACION CAMINOS DE MEDITERRANEO
PRESUPUESTO GENERAL PARA EL DESARROLLO DEL URBANISMO DEL PROYECTO CAMINOS DEL
MEDITERRANEO, UBICADO EN VILLAVICENCIO-META
5.20 VIGA CAJON CON PERFIL EN C 160X60 CLIBRE 2.5 MM ML 57.00 $ 42,500.00 $ 2,422,500.00 $ 74,227.00 $ 4,230,939.00
6 CUBIERTA $ -
6.10 CUBIERTA TRAPEZOIDAL T. AJOVER A360 M2 220.00 $ 37,400.00 $ 8,228,000.00 $ 34,108.00 $ 7,503,760.00
7 MAMPOSTERÍA $ -
7.10 MURO BLOQUE FLEX No4 10x20x30cms morte tipo S(1:3) M2 76.00 $ 36,339.00 $ 2,761,764.00 $ 39,631.00 $ 3,011,956.00
8 INSTALACIONES ELÉCTRICAS $ -
8.10 ACOMETIDA GENERAL BIFASICA UN 1.00 $ 472,044.00 $ 472,044.00 $ 1,223,833.00 $ 1,223,833.00
8.20 TABLERO PARCIAL12 CIRCUITOS.Inc totalizador,interr UN 1.00 $ 440,390.00 $ 440,390.00 $ 629,088.00 $ 629,088.00
8.30 SALIDA DE LAMPARA SLIM 2x48 estruct exterior/lamin PTO 10.00 $ 140,029.00 $ 1,400,290.00 $ 181,952.00 $ 1,819,520.00
PRESUPUESTO GENERAL PARA EL DESARROLLO DEL URBANISMO DEL PROYECTO CAMINOS DEL
MEDITERRANEO, UBICADO EN VILLAVICENCIO-META
10.20 VENTANA LAMINA COLL. R. C.20 , INC. PINTURA Y ANTI M2 4.25 $ 136,795.00 $ 581,378.75 $ 203,257.00 $ 863,842.25
11 INSTALACIONES HIDROSANITARIA $ -
10.10 TUBERIA PVC-S 4" AGUAS NEGRAS ML 10.00 $ 17,100.00 $ 171,000.00 $ 23,856.00 $ 238,560.00
10.20 Tuberia PVC 2" aguas negras ML 6.00 $ 15,300.00 $ 91,800.00 $ 12,500.00 $ 75,000.00
10.30 Desague en PVC 2" (pared) UND 2.00 $ 37,600.00 $ 75,200.00 $ 31,338.00 $ 62,676.00
10.40 Desague en PVC 4" (piso) UND 2.00 $ 26,400.00 $ 52,800.00 $ 43,311.00 $ 86,622.00
10.50 Red suministro agua potable de 1" ML 15.00 $ 9,200.00 $ 138,000.00 $ 5,740.00 $ 86,100.00
10.60 Red suministro agua potable de 1/2" ML 1.00 $ 6,570.00 $ 6,570.00 $ 3,992.00 $ 3,992.00
10.70 Registro en PVC de 1 " con universal UND 1.00 $ 19,950.00 $ 19,950.00 $ 86,792.00 $ 86,792.00
12 PAÑETES $ -
12.10 PAÑETE LISO MUROS 1:3 (IMPERM) e=0,025 mts M2 152.00 $ 20,806.00 $ 3,162,512.00 $ 28,396.00 $ 4,316,192.00
13 ACABADO DE PISOS $ -
13.10 TABLON GRAFIL-GRESS 25*25, Inc.afi. mt 1:4,e=3,5cm M2 192.00 $ 41,361.00 $ 7,941,312.00 $ 52,919.00 $ 10,160,448.00
14 PINTURA Y ENCHAPES $ -
14.10 ENCHAPE PARA MUROS EN CERAMICA 20*30CM M2 56.20 $ 45,400.00 $ 2,551,480.00 $ 36,049.00 $ 2,025,953.80
14.20 PINTURA VINILO T. 1 S/MURO (3 CAPAS) (ALTA CALID) M2 152.00 $ 6,750.00 $ 1,026,000.00 $ 8,971.00 $ 1,363,592.00
15 APARATOS SANITARIOS $ -
15.10 SANITARIO INFANTIL COMPLETO CRNA UND 2.00 $ 432,366.00 $ 864,732.00 $ 533,338.00 $ 1,066,676.00
15.20 SIFON PISO, DUCHA 2" PVC,incl. rejilla alum anticu UND 1.00 $ 24,229.00 $ 24,229.00 $ 21,396.00 $ 21,396.00
15.30 LAVAMANOS SOBREP. CORONA O SIMIL.Inc griferi,acces UND 2.00 $ 209,161.00 $ 418,322.00 $ 340,821.00 $ 681,642.00
3.40 ACERO REFUERZO FIGURADO 412MPa, (4200 KG 5,500.00 $ 6,506.00 $ 35,783,000.00 $ 4,686.00 $ 25,773,000.00
kg/cm2,G60)
3.50 CINTA PVC PARA UNION IMPERMEABLE DE CONCRETO ML 21.00 $ 40,700.00 $ 854,700.00 $ 41,788.00 $ 877,548.00
4 ESTRUCTURAS EN CONCRETO REFORZADO $ -
4.10 CONCRETO COLUMNA 24,13MPa, (3500psi) M3 0.70 $ 843,337.00 $ 590,336.00 $ 921,560.00 $ 645,092.00
4.20 VIGA AEREA CONCRETO 24,13 MPa, (3500 psi) M3 0.95 $ 853,993.00 $ 811,293.00 $ 860,618.00 $ 817,587.10
5 ESTRUCTURAS METÁLICAS $ -
5.10 CORREA MET TUB. ESTC.ACERO RECT 80*40 mm C.14 ML 39.00 $ 20,613.00 $ 803,907.00 $ 31,896.00 $ 1,243,944.00
5.20 VIGA CAJON CON PERFIL EN C 160X60 CLIBRE 2.5 MM ML 21.00 $ 43,500.00 $ 913,500.00 $ 74,227.00 $ 1,558,767.00
6 CUBIERTA $ -
6.10 CUBIERTA TRAPEZOIDAL T. AJOVER A360 M2 36.00 $ 38,400.00 $ 1,382,400.00 $ 34,108.00 $ 1,227,888.00
7 MAMPOSTERÍA $ -
7.10 MURO BLOQUE FLEX No4 10x20x30cms morte tipo S(1:3) M2 41.80 $ 37,339.00 $ 1,560,770.00 $ 39,631.00 $ 1,656,575.80
8 INSTALACIONES ELÉCTRICAS $ -
8.10 ACOMETIDA GENERAL TRIFASICA UN 1.00 $ 1,823,044.00 $ 1,823,044.00 $ 1,823,044.00 $ 1,823,044.00
8.20 TABLERO PARCIAL 18 CIRCUITOS.Inc totalizador,interr UN 1.00 $ 641,390.00 $ 641,390.00 $ 741,048.00 $ 741,048.00
8.30 SALIDA DE LAMPARA SLIM 2x48 estruct exterior/lamin PTO 2.00 $ 141,029.00 $ 282,058.00 $ 181,952.00 $ 363,904.00
1.1 TRANSPORTE DE EQUIPO, INSTALACION, ADECUACION, GLB 1 $ 1,500,000.00 $ 1,500,000.00 $ 1,500,000.00 $ 1,500,000.00
CONSTRUCCION DE PISCINA DE LODOS, CAMPAMENTO Y
TRABAJOS PREPARATORIOS
1.2 PERFORACION MECANICA EXPLORATORIA EN 8 1/2" ML 90 $ 160,000.00 $ 14,400,000.00 $ 160,000.00 $ 14,400,000.00
PARA ESTUDIO LITOLOGICO
1.3 ANALISIS LITOLOGICO Y GRANULOMETRICO PARA EL GLB 1 $ 450,000.00 $ 450,000.00 $ 450,000.00 $ 450,000.00
DISEÑO DEL POZO
1.4 EJECUCCION DE REGISTRO ELECTRICO (POTENCIAL GLB 1 $ 2,500,000.00 $ 2,500,000.00 $ 2,500,000.00 $ 2,500,000.00
ESPONTANEO, RESISTIVIDAD Y RAYOS GAMA)
1.5 ML 90 $ 140,000.00 $ 12,600,000.00 $ 140,000.00 $ 12,600,000.00
PERFORACION MECANICA PARA AMPLIACION A 12 1/4"
1.6 ML 27 $ 75,000.00 $ 2,025,000.00 $ 75,000.00 $ 2,025,000.00
S.I DE TUBERIA RANURADA EN PVC PARA FILTROS DE 6"
1.7 S.I DE TUBERIA PVC RDE 21 DE 6" ML 53 $ 70,000.00 $ 3,710,000.00 $ 70,000.00 $ 3,710,000.00
1.8 S.I GRAVILLA LAVADA Y SELECCIONADA PARA POZO BULTO 600 $ 4,650.00 $ 2,790,000.00 $ 4,650.00 $ 2,790,000.00
1.9 S.I DE MATERIAL ESTABILIZADOR Y RELLENO (BENTONITA KG 30 $ 53,000.00 $ 1,590,000.00 $ 53,000.00 $ 1,590,000.00
X50 KG C/U)
1.10 LAVADO Y DESARROLLO DEL POZO POR METODOS GLB 1 $ 1,200,000.00 $ 1,200,000.00 $ 1,200,000.00 $ 1,200,000.00
COMBINADOS (JETTING Y AIRE COMPRIMIDO)
1.11 PRUEBA DE BOMBEO CONSTANTE (INCLUYE ANALISIS DE GLB 1 $ 1,000,000.00 $ 1,000,000.00 $ 1,000,000.00 $ 1,000,000.00
BOMBEO E INFORME ESCRITO)
1.12 CONSTRUCCION DE CABEZA DE POZO Y SELLO SANITARIO GLB 1 $ 500,000.00 $ 500,000.00 $ 500,000.00 $ 500,000.00
EN CONCRETO
1.13 DESINFECCION DEL POZO GLB 1 $ 250,000.00 $ 250,000.00 $ 250,000.00 $ 250,000.00
1.14 ANALISIS FISICO, QUIMICO Y BACTERIOLOGICO DEL GLB 1 $ 500,000.00 $ 500,000.00 $ 500,000.00 $ 500,000.00
AGUA, PRUEBA DE DUREZA, HIERRO Y POLIMERO
SUBTOTAL CONSTRUCCION POZO PROFUNDO AGUA POTABLE 90 ML $ 45,015,000.00 $ 45,015,000.00
PAVIMENTO ASFALTICO $ -
SUMINISTRO, EXTENDIDA Y COMPACTACION DE BASE M2 14688 $ 3,885.90 $ 57,076,099.20 $ 3,885.90 $ 57,076,099.20
GRANULAR EN UN ESPESOR 7,5 CM
IMPRIMACION SOBRE BASE GRANULAR M2 14688 $ 1,157.50 $ 17,001,360.00 $ 2,985.00 $ 43,843,680.00
PRESUPUESTO GENERAL PARA EL DESARROLLO DEL URBANISMO DEL PROYECTO CAMINOS DEL
MEDITERRANEO, UBICADO EN VILLAVICENCIO-META
2 Excavacion, suministro e instalacion de ducteria PVC DP ML 682.5 $ 95,400 $ 65,110,500.00 $ 95,400.00 $ 65,110,500.00
2*4", incluye cableado en aluminio XLPE #1/0 a 15kv
3 Cajas para media tension tipo CODENSA CS275 UN 18 $ 445,000 $ 8,010,000.00 $ 445,000.00 $ 8,010,000.00
4 Cajas de empalme en media tension CS281 UN 3 $ 1,920,000 $ 5,760,000.00 $ 1,920,000.00 $ 5,760,000.00
5 Juego de Barrajes en media tension UN 3 $ 3,850,000 $ 11,550,000.00 $ 3,850,000.00 $ 11,550,000.00
6 Excavacion, suministro e instalacion de ducteria PVC DP ML 2177 $ 46,100 $ 100,359,700.00 $ 46,100.00 $ 100,359,700.00
2*3", incluye cableado en aluminio 3*4/0F+4/0N
7 Cajas para baja tension tipo CODENSA CS275 UN 78 $ 445,000 $ 34,710,000.00 $ 445,000.00 $ 34,710,000.00
8 UN 60 $ 779,000 $ 46,740,000.00 $ 779,000.00 $ 46,740,000.00
Empalmes submarinos - Barraje premoldeado sumergible
9 Suministro e instalacion de ducto vacio para acometidas UN 403 $ 202,000 $ 81,406,000.00 $ 202,000.00 $ 81,406,000.00
1-1/4" PVC hasta 30 metros
10 Suministro e instalacion de subestacion de 150KVA, según UN 3 $ 19,200,000 $ 57,600,000.00 $ 19,200,000.00 $ 57,600,000.00
norma codensa CTS-523-535
10 Suministro e instalacion de subestacion de 225KVA, según UN 1 $ 21,300,000 $ 21,300,000.00 $ 21,300,000.00 $ 21,300,000.00
norma codensa CTS-523-535
11 Puestas a tierra y accesorios varios GL 1 $ 9,400,000 $ 9,400,000.00 $ 9,400,000.00 $ 9,400,000.00
ILUMINACION $ - $ - $ -
1 Suministro e instalacion de poste metalico de 6 mts UN 98 $ 345,000 $ 33,810,000.00 $ 345,000.00 $ 33,810,000.00
2 Cajas para iluminacion subterranea de 40*40cm. UN 30 $ 140,000 $ 4,200,000.00 $ 140,000.00 $ 4,200,000.00
3 Luminarias Sodio 70W incluye brazo UN 121 $ 150,000 $ 18,150,000.00 $ 150,000.00 $ 18,150,000.00
4 Excavacion, suministro e instalacion de ducteria PVC DP ML 3056 $ 12,600 $ 38,505,600.00 $ 12,600.00 $ 38,505,600.00
1*1-1/4"", incluye cableado en aluminio 3#4AWG
SUBTOTAL CONSTRUCCION REDES ELECTRICAS E ILUMINACION $ 539,041,800.00 $ 539,041,800.00
CONSTRUCCION DE GAVIONES PARA DEFENSA RIO OCOA $ - $ -
1 SUMINISTRO DE MALLA TRIPLE TORCION, PIEDRA Y UND 513 $ 117,000.00 $ 60,021,000.00 $ 270,862.00 $ 138,952,206.00
LLENADO DE GAVIONES DE 1*1*2
PRESUPUESTO GENERAL PARA EL DESARROLLO DEL URBANISMO DEL PROYECTO CAMINOS DEL
MEDITERRANEO, UBICADO EN VILLAVICENCIO-META
2 SUMINISTRO DE MALLA TRIPLE TORCION PARA UND 314 $ 82,000.00 $ 25,748,000.00 $ 294,024.00 $ 92,323,536.00
COLCHONETA , INCLUYE PIEDRA Y LLENADO DE 0,5*1*2
SUBTOTAL CONSTRUCCION DE GAVIONES PARA DEFENSA RIO OCOA $ 85,769,000.00 $ 231,275,742.00
JARDINERIA Y PAISAJISMO $ -
1 UND 1434 $ 1,800.00 $ 2,581,200.00 $ 1,800.00 $ 2,581,200.00
SUMINISTRO E INSTALACION DE PLANTAS DURANTAS
2 SUMINISTRO E INSTALACION DE PLANTAS ISORAS UND 1127 $ 2,000.00 $ 2,254,000.00 $ 2,000.00 $ 2,254,000.00
3 SUMINISTRO E INSTALACION DE CROTOS VICTORIA UND 8 $ 7,000.00 $ 56,000.00 $ 7,000.00 $ 56,000.00
4 SUMINISTRO E INSTALACION DE PLANTAS CINTAS UN 56 $ 7,000.00 $ 392,000.00 $ 7,000.00 $ 392,000.00
5 SUMINISTRO E INSTALACION DE PLANTAS ORQUIDEA UND 6 $ 12,000.00 $ 72,000.00 $ 12,000.00 $ 72,000.00
BAMBU
6 SUMINISTRO E INSTALACION DE PALMA ROJA UND 8 $ 90,000.00 $ 720,000.00 $ 90,000.00 $ 720,000.00
7 SUMINISTRO E INSTALACION DE PALMAS MANILA UND 9 $ 90,000.00 $ 810,000.00 $ 90,000.00 $ 810,000.00
8 SUMINISTRO E INSTALACION DE PLANTAS GARDENIAS UND 8 $ 9,000.00 $ 72,000.00 $ 9,000.00 $ 72,000.00
2.2 SUMINISTRO E INSTALACION TUBERIA PVC DE 6" AGUA ML 20,000.00 5,700.00 $ 114,000,000 6,030.00 $ 120,600,000 4,824.00 $ 96,480,000 16,554.00 $ 331,080,000
POTABLE (15000 MAT + 5000 M/O)
ARENADO PARA ATRAQUE CON MATERIAL DE RIO
2.3 M3 20,000.00 1,140.00 $ 22,800,000 1,206.00 $ 24,120,000 964.80 $ 19,296,000 3,310.80 $ 66,216,000
TUBERIA DE 3" (2280/2)
TAPADO COMPACTADO CON MATERIAL DE
2.4 M3 7,000.00 1,140.00 $ 7,980,000 1,206.00 $ 8,442,000 964.80 $ 6,753,600 3,310.80 $ 23,175,600
EXCAVACION
2.5 ACCESORIOS EN HF 3" (136000 MAT + 20000 M/O) UN 156,000.00 37.00 $ 5,772,000 34.00 $ 5,304,000 28.00 $ 4,368,000 99.00 $ 15,444,000
2.6 CAJAS REGISTRO CONTADOR (50000MAT + 15000M/O) UN 65,000.00 582.00 $ 37,830,000 672.00 $ 43,680,000 537.00 $ 34,905,000 1,791.00 $ 116,415,000
1.3 SUMINISTRO E INSTALACION TUBERIA PVC NOVAFORM ML 61,000.00 596.00 $ 36,356,000 596.00 $ 36,356,000 232.00 $ 14,152,000 1,424.00 $ 86,864,000
12" (46000 MAT + 15000 M/O)
ARENADO CON MATERIAL DE RIO PARA ATRAQUE DE
1.4 M3 20,000.00 342.00 $ 6,840,000 178.00 $ 3,560,000 111.00 $ 2,220,000 631.00 $ 12,620,000
TUBERIA (1028/3)
TAPADO COMPACTADO CON MATERIAL DE
1.5 M3 7,000.00 684.00 $ 4,788,000 356.00 $ 2,492,000 222.00 $ 1,554,000 1,262.00 $ 8,834,000
EXCAVACION (342*2)
CONSTRUCCION POZOS DE INSPECCION EN CONCRETO
1.6 DE 3000PSI CON E=0,20M H=1/1,50 UN 900,000.00 22.00 $ 19,800,000 14.00 $ 12,600,000 7.00 $ 6,300,000 43.00 $ 38,700,000
2.3 ARENADO PARA ATRAQUE CON MATERIAL DE RIO M3 20,000.00 1,096.00 $ 21,920,000 1,435.00 $ 28,700,000 1,167.00 $ 23,340,000 3,698.00 $ 73,960,000
TUBERIA DE 8" (3080/3)
SUMINISTRO E INSTALACION SILLAS "Y" DE 8" * 6" (50000
2.4 UN 60,000.00 582.00 $ 34,920,000 672.00 $ 40,320,000 507.00 $ 30,420,000 1,761.00 $ 105,660,000
MAT+10000 M/O)
TAPADO COMPACTADO CON MATERIAL DE
2.5 EXCAVACION M3 7,000.00 2,192.00 $ 15,344,000 2,870.00 $ 20,090,000 2,334.00 $ 16,338,000 7,396.00 $ 51,772,000
2.6 EXCAVACION A CIELO ABIERTO PARA TUBERIA DE REDES M3 7,000.00 7,200.00 $ 50,400,000 8,064.00 $ 56,448,000 6,084.00 $ 42,588,000 21,348.00 $ 149,436,000
DOMICILIARIAS DE 6" PRIMERA ETAPA
2.7 SUMINISTRO E INSTALACION TUBERIA PVC DE 6" PARA ML 27,500.00 7,200.00 $ 198,000,000 8,064.00 $ 221,760,000 6,084.00 $ 167,310,000 21,348.00 $ 587,070,000
REDES DOMICILIARIAS (17500 MAT + 10,000 M/O)
2.9 TAPADO COMPACTADO CON MATERIAL DE M3 7,000.00 4,800.00 $ 33,600,000 5,366.00 $ 37,562,000 4,056.00 $ 28,392,000 14,222.00 $ 99,554,000
EXCAVACION
2.10 CONSTRUCCION EN SITIO DE CAJAS DE INSPECCION UN 130,000.00 582.00 $ 75,660,000 672.00 $ 87,360,000 507.00 $ 65,910,000 1,761.00 $ 228,930,000
DOMICILIARIAS 1*1*1 EN CONCRETO DE 3000PSI E=0,10
3.00 CONSTRUCCION SUMINISTRO E INSTALACION DE ML 52,450.00 9,722.00 $ 509,918,900 11,306.85 $ 593,044,283 8,134.61 $ 426,660,295 29,163.46 $ 1,529,623,477
SARDINELES EN CONCRETO
CONSTRUCCION DE PORTERIA Y CERRAMIENTO PRINCIPAL
1.00 CONSTRUCCION DE MURO EN PIEDRA A TODO COSTO ML 245,000.00 160.00 $ 39,200,000 160.00 $ 39,200,000
PARA LA URBANIZACION CAMINOS DE MEDITERRANEO
5.20 VIGA CAJON CON PERFIL EN C 160X60 CLIBRE 2.5 MM ML 42,500.00 57.00 $ 2,422,500 57.00 $ 2,422,500
6.00 CUBIERTA - $ - $ -
6.10 CUBIERTA TRAPEZOIDAL T. AJOVER A360 M2 37,400.00 220.00 $ 8,228,000 220.00 $ 8,228,000
7.00 MAMPOSTERÍA - $ - $ -
7.10 MURO BLOQUE FLEX No4 10x20x30cms morte tipo S(1:3) M2 36,339.00 76.00 $ 2,761,764 76.00 $ 2,761,764
8.00 INSTALACIONES ELÉCTRICAS - $ - $ -
8.10 ACOMETIDA GENERAL BIFASICA UN 472,044.00 1.00 $ 472,044 1.00 $ 472,044
8.20 TABLERO PARCIAL12 CIRCUITOS.Inc totalizador,interr UN 440,390.00 1.00 $ 440,390 1.00 $ 440,390
8.30 SALIDA DE LAMPARA SLIM 2x48 estruct exterior/lamin PTO 140,029.00 10.00 $ 1,400,290 10.00 $ 1,400,290
10.20 VENTANA LAMINA COLL. R. C.20 , INC. PINTURA Y ANTI M2 136,795.00 4.25 $ 581,379 4.25 $ 581,379
11.00 INSTALACIONES HIDROSANITARIA - $ - $ -
10.10 TUBERIA PVC-S 4" AGUAS NEGRAS ML 17,100.00 10.00 $ 171,000 10.00 $ 171,000
10.20 Tuberia PVC 2" aguas negras ML 15,300.00 6.00 $ 91,800 6.00 $ 91,800
10.30 Desague en PVC 2" (pared) UND 37,600.00 2.00 $ 75,200 2.00 $ 75,200
10.40 Desague en PVC 4" (piso) UND 26,400.00 2.00 $ 52,800 2.00 $ 52,800
10.50 Red suministro agua potable de 1" ML 9,200.00 15.00 $ 138,000 15.00 $ 138,000
10.60 Red suministro agua potable de 1/2" ML 6,570.00 1.00 $ 6,570 1.00 $ 6,570
10.70 Registro en PVC de 1 " con universal UND 19,950.00 1.00 $ 19,950 1.00 $ 19,950
12.00 PAÑETES - $ - $ -
12.10 PAÑETE LISO MUROS 1:3 (IMPERM) e=0,025 mts M2 20,806.00 152.00 $ 3,162,512 152.00 $ 3,162,512
13.10 ACABADO DE PISOS - $ - $ -
13.10 TABLON GRAFIL-GRESS 25*25, Inc.afi. mt 1:4,e=3,5cm M2 41,361.00 192.00 $ 7,941,312 192.00 $ 7,941,312
14.00 PINTURA Y ENCHAPES - $ - $ -
14.10 ENCHAPE PARA MUROS EN CERAMICA 20*30CM M2 45,400.00 56.20 $ 2,551,480 56.20 $ 2,551,480
14.20 PINTURA VINILO T. 1 S/MURO (3 CAPAS) (ALTA CALID) M2 6,750.00 152.00 $ 1,026,000 152.00 $ 1,026,000
15.00 APARATOS SANITARIOS - $ - $ -
15.10 SANITARIO INFANTIL COMPLETO CRNA UND 432,366.00 2.00 $ 864,732 2.00 $ 864,732
15.20 SIFON PISO, DUCHA 2" PVC,incl. rejilla alum anticu UND 24,229.00 1.00 $ 24,229 1.00 $ 24,229
PRESUPUESTO GENERAL PARA EL DESARROLLO DEL URBANISMO DEL PROYECTO PASEO DE VERSALLES, UBICADO EN VILLAVICENCIO-META
ETAPA 1 ETAPA 2 ETAPA 3 GENERAL
ITEM DESCRPCION UND V.UNIT CANT SUBTOTAL CANT SUBTOTAL CANT SUBTOTAL CANT SUBTOTAL
15.30 LAVAMANOS SOBREP. CORONA O SIMIL.Inc griferi,acces UND 209,161.00 2.00 $ 418,322 2.00 $ 418,322
1.1 Excavacion, suministro e instalacion de ducteria PVC DP 2*3", $ 46,100 1,787.10 $ 82,385,310 1,609.80 $ 74,211,780 1,282.20 $ 59,109,420 4,679.10 $ 215,706,510
incluye cableado en aluminio 3*2/0F+2/0N
1.2 Excavacion, suministro e instalacion de ducteria PVC DP 2*3", $ 50,820 2,260.20 $ 114,863,364 2,117.10 $ 107,591,022 1,800.10 $ 91,481,082 6,177.40 $ 313,935,468
incluye cableado en aluminio 3*4/0F+4/0N
1.3 Excavacion, suministro e instalacion de ducteria PVC DP 2*3", $ 71,400 626.00 $ 44,696,400 1,329.30 $ 94,912,020 77.70 $ 5,547,780 2,033.00 $ 145,156,200
incluye cableado en aluminio 3*250F+250N
1.4 Excavacion, suministro e instalacion de ducteria PVC DP 2*3", $ 83,760 - $ - 653.40 $ 54,728,784 982.40 $ 82,285,824 1,635.80 $ 137,014,608
incluye cableado en aluminio 3*350F+350N
1.5 Cajas para baja tension tipo CODENSA CS275 $ 489,500 189.00 $ 92,515,500 194.00 $ 94,963,000 151.00 $ 73,914,500 534.00 $ 261,393,000
1.6 Juego de barrajes premoldeados para baja tension $ 779,000 142.00 $ 110,618,000 153.00 $ 119,187,000 121.00 $ 94,259,000 416.00 $ 324,064,000
1.7 Puesta a tierra terminal de baja tension $ 175,000 36.00 $ 6,300,000 34.00 $ 5,950,000 26.00 $ 4,550,000 96.00 $ 16,800,000
1.8 Suministro e instalacion de ducto vacio para acometidas 1-1/4" $ 202,000 590.00 $ 119,180,000 679.00 $ 137,158,000 507.00 $ 102,414,000 1,776.00 $ 358,752,000
PVC hasta 30 metros
2 RED DE MEDIA TENSION $ - $ - - $ -
2.1 Red de media tension area ecologica compacta en 34,5 kV KM $ 109,500,000 4.70 $ 514,650,000 $ - $ - 4.70 $ 514,650,000
2.2 Subestacion en media tension 10 MW, 34,5-13,2 Kv tipo patio GLB $ 660,000,000 $ - $ - 1.00 $ 660,000,000 1.00 $ 660,000,000
2.9 Suministro e instalacion de subestacion de 225KVA, según UND $ 23,430,000 1.00 $ 23,430,000 1.00 $ 23,430,000 3.00 $ 70,290,000 5.00 $ 117,150,000
norma codensa CTS-523-535
2.10 Puestas a tierra para subestaciones UND $ 820,000 4.00 $ 3,280,000 4.00 $ 3,280,000 3.00 $ 2,460,000 11.00 $ 9,020,000
3 RED DE ILUMINACION $ - $ - $ - - $ -
3.1 Suministro e instalacion de poste metalico de 10 mts $ 800,000 36.00 $ 28,800,000 36.00 $ 28,800,000 28.00 $ 22,400,000 100.00 $ 80,000,000
3.2 Suministro e instalacion de poste metalico de 6 mts $ 379,500 276.00 $ 104,742,000 276.00 $ 104,742,000 216.00 $ 81,972,000 768.00 $ 291,456,000
3.3 Cajas para iluminacion subterranea de 40*40cm. $ 154,000 312.00 $ 48,048,000 312.00 $ 48,048,000 244.00 $ 37,576,000 868.00 $ 133,672,000
3.4 Luminarias LED 50W incluye brazo $ 180,000 276.00 $ 49,680,000 276.00 $ 49,680,000 216.00 $ 38,880,000 768.00 $ 138,240,000
3.5 Luminarias Led 100W incluye brazo $ 280,000 72.00 $ 20,160,000 72.00 $ 20,160,000 56.00 $ 15,680,000 200.00 $ 56,000,000
3.6 Excavacion, suministro e instalacion de ducteria PVC DP 1*1- $ 13,860 7,946.23 $ 110,134,692 7,946.23 $ 110,134,692 6,180.40 $ 85,660,316 22,072.85 $ 305,929,701
1/4"", incluye cableado en aluminio 3#4AWG
PLANTAS DE TRATAMIENTO DE AGUA RESIDUAL Y POTABLE #REF!
1.00 PLANTA DE TRATAMIENTO DE AGUA RESIDUALES PTAR GLB 1,316,300,000 1.00 $ 1,316,300,000 1.00 $ 1,316,300,000
PARA 1668 VIVIENDAS #REF!
2.00 PLANTA DE TRATAMIENTO DE AGUA POTABLE PTAP GLB 65,800,000.00 1.00 $ 65,800,000 1.00 $ 65,800,000 #REF!
CONSTRUCCION DE GAVIONES PARA DEFENSA RIOS Y PUENTES VEHICULARES #REF!
PRESUPUESTO GENERAL PARA EL DESARROLLO DEL URBANISMO DEL PROYECTO PASEO DE VERSALLES, UBICADO EN VILLAVICENCIO-META
ETAPA 1 ETAPA 2 ETAPA 3 GENERAL
ITEM DESCRPCION UND V.UNIT CANT SUBTOTAL CANT SUBTOTAL CANT SUBTOTAL CANT SUBTOTAL
1.00 SUMINISTRO DE MALLA TRIPLE TORCION, PIEDRA Y UND 117,000.00 1,400.00 $ 163,800,000 1,400.00 $ 163,800,000
LLENADO DE GAVIONES DE 1*1*2 #REF!
2.00 PUENTE VEHICULAR SOBRE CAÑO MAIZARO 12 ML GLB 310,000,000.00 1.00 $ 310,000,000 1.00 $ 310,000,000
3.00 BOX CULVERT SOBRE CAÑO RODAS GLB 166,867,967.00 1.00 $ 166,867,967 1.00 $ 166,867,967 #REF!
JARDINERIA Y PAISAJISMO
1.00 UND $ 1,800 2,868.00 $ 5,162,400 1,434.00 $ 2,581,200 1,434.00 $ 2,581,200 5,736.00 $ 10,324,800
SUMINISTRO E INSTALACION DE PLANTAS DURANTAS
2.00 SUMINISTRO E INSTALACION DE PLANTAS ISORAS UND $ 2,000 2,254.00 $ 4,508,000 1,127.00 $ 2,254,000 1,127.00 $ 2,254,000 4,508.00 $ 9,016,000
3.00 SUMINISTRO E INSTALACION DE CROTOS VICTORIA UND $ 7,000 16.00 $ 112,000 8.00 $ 56,000 8.00 $ 56,000 32.00 $ 224,000
4.00 SUMINISTRO E INSTALACION DE PLANTAS CINTAS UN $ 7,000 112.00 $ 784,000 56.00 $ 392,000 56.00 $ 392,000 224.00 $ 1,568,000
5.00 SUMINISTRO E INSTALACION DE PLANTAS ORQUIDEA UND $ 12,000 12.00 $ 144,000 6.00 $ 72,000 6.00 $ 72,000 24.00 $ 288,000
BAMBU
6.00 SUMINISTRO E INSTALACION DE PALMA ROJA UND $ 90,000 16.00 $ 1,440,000 8.00 $ 720,000 8.00 $ 720,000 32.00 $ 2,880,000
7.00 SUMINISTRO E INSTALACION DE PALMAS MANILA UND $ 90,000 18.00 $ 1,620,000 9.00 $ 810,000 9.00 $ 810,000 36.00 $ 3,240,000
8.00 SUMINISTRO E INSTALACION DE PLANTAS GARDENIAS UND $ 9,000 16.00 $ 144,000 8.00 $ 72,000 8.00 $ 72,000 32.00 $ 288,000
9.00 UND $ 8,000 20.00 $ 160,000 10.00 $ 80,000 10.00 $ 80,000 40.00 $ 320,000
SUMINISTRO E INSTALACION DE PLANTAS LLUVIA DE ORO
10.00 M2 $ 4,000 1,438.00 $ 5,752,000 719.00 $ 2,876,000 719.00 $ 2,876,000 2,876.00 $ 11,504,000
ADECUACION DE TERRENO PARA SIEMBRA DE GRAMA
11.00 SUMINISTRO EN INSTALACION DE GRAMA TRENZA M2 $ 8,000 748.00 $ 5,984,000 374.00 $ 2,992,000 374.00 $ 2,992,000 1,496.00 $ 11,968,000
12.00 SUMINISTRO E INSTALACION DE SWINGLEA UND $ 800 600.00 $ 480,000 300.00 $ 240,000 300.00 $ 240,000 1,200.00 $ 960,000
13.00 SUMINISTRO DE LODO DE RIO VIAJE $ 180,000 16.00 $ 2,880,000 8.00 $ 1,440,000 8.00 $ 1,440,000 32.00 $ 5,760,000
14.00 SUMINISTRO DE TIERRA NEGRA VIAJE $ 550,000 4.00 $ 2,200,000 2.00 $ 1,100,000 2.00 $ 1,100,000 8.00 $ 4,400,000
15.00 SUMINISTRO DE PIEDRA ARRECIFE M2 $ 75,000 26.00 $ 1,950,000 13.00 $ 975,000 13.00 $ 975,000 52.00 $ 3,900,000
16.00 INSTALACION DE PIEDRA LAJA M2 $ 35,000 16.00 $ 560,000 8.00 $ 280,000 8.00 $ 280,000 32.00 $ 1,120,000
17.00 SERVICIO DE ROSERIA Y RECOLECCION DE MATERIAL GLB $ 1,900,000 2.00 $ 3,800,000 1.00 $ 1,900,000 1.00 $ 1,900,000 4.00 $ 7,600,000
VEGETAL
18.00 SUMINISTRO Y DECORACION DEL POZO DE AGUA UND $ 600,000 2.00 $ 1,200,000 1.00 $ 600,000 1.00 $ 600,000 4.00 $ 2,400,000
19.00 INSTALACION DE PLANTAS SUMINISTRADAS POR FRANCY GLB $ 282,500 2.00 $ 565,000 1.00 $ 282,500 1.00 $ 282,500 4.00 $ 1,130,000
TORRES
20.00 GLB $ 109,749,000 2.00 $ 219,498,000 1.00 $ 109,749,000 1.00 $ 109,749,000 4.00 $ 438,996,000
SUMINISTRO E INSTALACION DE JARDIN SEGÚN DISEÑO
TOTAL COSTOS DIRECTOS 7,361,477,313 7,161,144,641 7,015,839,064 21,538,461,018
ADMINISTRACION (8%) 588,918,185 572,891,571 561,267,125 1,723,076,881
IMPREVISTOS (2%) 147,229,546 143,222,893 140,316,781 430,769,220
UTILIDAD (5%) 368,073,866 358,057,232 350,791,953 1,076,923,051
IVA SOBRE LA UTILIDAD (19%) 69,934,034 68,030,874 66,650,471 204,615,380
VALOR COSTOS INDIRECTOS 1,174,155,631 1,142,202,570 1,119,026,331 3,435,384,532
VALOR TOTAL DEL PROYECTO 8,535,632,945 8,303,347,211 8,134,865,395 24,973,845,551
$ 24,973,845,551