PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJAS m3 59.48
ZAPATAS (Z)
EJE 2-2 B (Z-1) 1.00 1.10 1.10 1.20 1.45
EJE 4-3 B (Z-1) 1.00 1.10 1.10 1.20 1.45
EJE 5-5 B (Z-1) 1.00 1.10 1.10 1.20 1.45
EJE 8-7 B (Z-1) 1.00 1.10 1.10 1.20 1.45
EJE 9-10 B (Z-1) 1.00 1.10 1.10 1.20 1.45
EJE 13-13 B (Z-2) 1.00 1.10 0.90 1.20 1.19
VIGAS DE CIMENTACION
VIGAS DE CIMENTACION, CONCRETO F'C= 210 KG/CM2 m3 3.15
EJE 13 (A-B) 1.00 3.30 0.15 0.30 0.15
EJE 13 (B-C) 1.00 2.20 0.15 0.30 0.10
EJE 13 (C-D) 1.00 1.45 0.15 0.30 0.07
SOBRECIMIENTOS m3 3.25
EJE 13 (A-B) CC-2 1.00 3.30 0.15 0.30 0.15
EJE 13 (B-C) CC-2 1.00 2.20 0.15 0.30 0.10
EJE 13 (C-D) CC-2 1.00 1.45 0.15 0.30 0.07
COLUMNAS
COLUMNAS, CONCRETO F'C=210 KG/CM2 m3
EJE 13-A (C-3) 1.00 AREA 0.07 3.60 0.24
EJE 13-B (C-2) 1.00 0.30 0.30 3.60 0.32
EJE 13-C (C-6) 1.00 0.30 0.15 3.60 0.16
EJE 13-D (C-2) 1.00 0.30 0.30 3.60 0.32
VIGAS
VIGAS, CONCRETO F'C=210 KG/CM2 m3 7.83
VA-1 (0.25*0.20) EJE 13-13 (A-B-C-D) 1.00 8.00 0.25 0.20 0.40
VA-1 (0.25*0.20) EJE 9-10 (A-B-C-D) 1.00 8.00 0.25 0.20 0.40
VA-1 (0.25*0.20) EJE 8-7 (A-B-C-D) 1.00 8.00 0.25 0.20 0.40
VA-1 (0.25*0.20) EJE 6 (A-B) 1.00 3.50 0.25 0.20 0.18
VA-1 (0.25*0.20) EJE 4-3 (A-B-C-D) 1.00 8.00 0.25 0.20 0.40
VA-1 (0.25*0.20) EJE 2-2 (A-B-C-D) 1.00 8.00 0.25 0.20 0.40
VA-2 (0.25*0.40) EJE 5-5 (A-B-C-D) 1.00 8.00 0.25 0.40 0.80