HOJA DE METRADOS

PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJAS m3 59.48
ZAPATAS (Z)
EJE 2-2 B (Z-1) 1.00 1.10 1.10 1.20 1.45
EJE 4-3 B (Z-1) 1.00 1.10 1.10 1.20 1.45
EJE 5-5 B (Z-1) 1.00 1.10 1.10 1.20 1.45
EJE 8-7 B (Z-1) 1.00 1.10 1.10 1.20 1.45
EJE 9-10 B (Z-1) 1.00 1.10 1.10 1.20 1.45
EJE 13-13 B (Z-2) 1.00 1.10 0.90 1.20 1.19

CIMIENTO CORRIDO (CC)


EJE 13 (A-B) CC-2 1.00 2.70 0.50 1.20 1.62
EJE 13 (B-C) CC-2 1.00 1.63 0.50 1.20 0.98
EJE 13 (C-D) CC-2 1.00 1.08 0.50 1.20 0.65

EJE 12 (B-C) CC-4 1.00 1.93 0.50 1.20 1.16


EJE 12 (C-D) CC-4 1.00 1.08 0.50 1.20 0.65

EJE 9 (A-B) CC-4 2.00 2.70 0.50 1.20 3.24


EJE 9 (B-C) CC-4 1.00 1.63 0.50 1.20 0.98
EJE 9 (C-D) CC-7 1.00 1.06 0.50 1.20 0.64

EJE 8 (B-C-D) CC-5 1.00 3.20 0.50 1.20 1.92

EJE 6 (A-B) CC-5 1.00 2.80 0.50 1.20 1.68


EJE 6 (C-D) CC-3 1.00 1.63 0.50 1.20 0.98

EJE 5 (A-B) CC-7 1.00 1.88 0.50 1.20 1.13


EJE 5 (B-C-D) CC-7 1.00 2.38 0.50 1.20 1.43
0.00
EJE 4 (B-C) CC 1.00 1.10 0.50 1.20 0.66

EJE 2 (A-B) CC-3 1.00 2.69 0.50 1.20 1.61


EJE 2 (B-C-D) CC-3 1.00 3.20 0.50 1.20 1.92

EJE A (6-13) CC-2 1.00 8.20 0.50 1.20 4.92


EJE A (6-1) CC-1 1.00 11.80 0.50 1.20 7.08

EJE B (13-12-9) CC-7 1.00 2.95 0.50 1.20 1.77


HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL

EJE B (9-8) CC-7 1.00 1.30 0.50 1.20 0.78

EJE B (5-4) CC-7 1.00 1.65 0.50 1.20 0.99

EJE B (4-2) CC-7 1.00 1.55 0.50 1.20 0.93

EJE C (13-12) CC-7 1.00 2.02 0.50 1.20 1.21

EJE C (12-9) CC-4 1.00 1.54 0.50 1.20 0.92

EJE D (13-11-10-7) CC-2 1.00 6.88 0.50 1.20 4.13

EJE D (7-5-3) CC-1 1.00 7.43 0.50 1.20 4.46

EJE D (1-2) CC-1 1.00 4.35 0.50 1.20 2.61

OBRAS DE CONCRETO SIMPLE

SOLADO ZAPATAS (Z) m2 7.04


EJE 2-2 B (Z-1) 1.00 1.10 1.10 1.21
EJE 4-3 B (Z-1) 1.00 1.10 1.10 1.21
EJE 5-5 B (Z-1) 1.00 1.10 1.10 1.21
EJE 8-7 B (Z-1) 1.00 1.10 1.10 1.21
EJE 9-10 B (Z-1) 1.00 1.10 1.10 1.21
EJE 13-13 B (Z-2) 1.00 1.10 0.90 0.99

CIMIENTO CORRIDO F'c=140 kg/cm2 m3 34.02


CIMIENTO CORRIDO (CC)
EJE 13 (A-B) CC-2 1.00 2.70 0.50 0.80 1.08
EJE 13 (B-C) CC-2 1.00 1.63 0.50 0.80 0.65
EJE 13 (C-D) CC-2 1.00 1.08 0.50 0.80 0.43

EJE 12 (B-C) CC-4 1.00 1.93 0.50 0.80 0.77


EJE 12 (C-D) CC-4 1.00 1.08 0.50 0.80 0.43

EJE 9 (A-B) CC-4 2.00 2.70 0.50 0.80 2.16


EJE 9 (B-C) CC-4 1.00 1.63 0.50 0.80 0.65
HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL
EJE 9 (C-D) CC-7 1.00 1.06 0.50 0.80 0.42

EJE 8 (B-C-D) CC-5 1.00 3.20 0.50 0.80 1.28

EJE 6 (A-B) CC-5 1.00 2.80 0.50 0.80 1.12


EJE 6 (C-D) CC-3 1.00 1.63 0.50 0.80 0.65

EJE 5 (A-B) CC-7 1.00 1.88 0.50 0.80 0.75


EJE 5 (B-C-D) CC-7 1.00 2.38 0.50 0.80 0.95
0.00
EJE 4 (B-C) CC 1.00 1.10 0.50 0.80 0.44

EJE 2 (A-B) CC-3 1.00 2.69 0.50 0.80 1.08


EJE 2 (B-C-D) CC-3 1.00 3.20 0.50 0.80 1.28

EJE A (6-13) CC-2 1.00 8.20 0.50 0.80 3.28


EJE A (6-1) CC-1 1.00 11.80 0.50 0.80 4.72

EJE B (13-12-9) CC-7 1.00 2.95 0.50 0.80 1.18

EJE B (9-8) CC-7 1.00 1.30 0.50 0.80 0.52

EJE B (5-4) CC-7 1.00 1.65 0.50 0.80 0.66

EJE B (4-2) CC-7 1.00 1.55 0.50 0.80 0.62

EJE C (13-12) CC-7 1.00 2.02 0.50 0.80 0.81

EJE C (12-9) CC-4 1.00 1.54 0.50 0.80 0.62

EJE D (13-11-10-7) CC-2 1.00 6.88 0.50 0.80 2.75

EJE D (7-5-3) CC-1 1.00 7.43 0.50 0.80 2.97

EJE D (1-2) CC-1 1.00 4.35 0.50 0.80 1.74

OBRAS DE CONCRETO ARMADO


ZAPATAS, CONCRETO F'C=210 KG/CM2 m3 4.22
HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL
EJE 2-2 B (Z-1) 1.00 1.10 1.10 0.60 0.73
EJE 4-3 B (Z-1) 1.00 1.10 1.10 0.60 0.73
EJE 5-5 B (Z-1) 1.00 1.10 1.10 0.60 0.73
EJE 8-7 B (Z-1) 1.00 1.10 1.10 0.60 0.73
EJE 9-10 B (Z-1) 1.00 1.10 1.10 0.60 0.73
EJE 13-13 B (Z-2) 1.00 1.10 0.90 0.60 0.59

ZAPATAS, ACERO FY=4200 KG/CM2 . kg 112.51


1.00 112.51 112.51

CURADO DE CONCRETO m2 7.04


EJE 2-2 B (Z-1) 1.00 1.10 1.10 1.21
EJE 4-3 B (Z-1) 1.00 1.10 1.10 1.21
EJE 5-5 B (Z-1) 1.00 1.10 1.10 1.21
EJE 8-7 B (Z-1) 1.00 1.10 1.10 1.21
EJE 9-10 B (Z-1) 1.00 1.10 1.10 1.21
EJE 13-13 B (Z-2) 1.00 1.10 0.90 0.99

VIGAS DE CIMENTACION
VIGAS DE CIMENTACION, CONCRETO F'C= 210 KG/CM2 m3 3.15
EJE 13 (A-B) 1.00 3.30 0.15 0.30 0.15
EJE 13 (B-C) 1.00 2.20 0.15 0.30 0.10
EJE 13 (C-D) 1.00 1.45 0.15 0.30 0.07

EJE B (13-12) 1.00 0.55 0.30 0.30 0.05


EJE C (13-12) 1.00 0.55 0.15 0.30 0.02

EJE 12 (B-C) 1.00 2.65 0.15 0.30 0.12


EJE 12 (C-D) 1.00 1.30 0.15 0.30 0.06

EJE 9 (A-B) 1.00 5.40 0.15 0.30 0.24


EJE 9 (B-C) 1.00 2.20 0.15 0.30 0.10
EJE 9 (C-D) 1.00 0.65 0.15 0.30 0.03

EJE 8 (B-C-D) 1.00 1.88 0.15 0.30 0.08

EJE 6 (A-B) 1.00 2.10 0.15 0.30 0.09


EJE 6 (C-D) 1.00 1.25 0.15 0.30 0.06
HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL

EJE 5 (B-C-D) 1.00 0.45 0.15 0.30 0.02

EJE 2 (A-B) 1.00 2.90 0.15 0.30 0.13


EJE 2 (B-C-D) 1.00 1.85 0.15 0.30 0.08

EJE A (1-13) 1.00 16.37 0.15 0.30 0.74

EJE B (9-8) 1.00 1.20 0.15 0.30 0.05

EJE B (5-4) 1.00 2.88 0.15 0.30 0.13

EJE B (4-2) 1.00 1.06 0.15 0.30 0.05

EJE C (12-9) 1.00 2.05 0.15 0.30 0.09

EJE D (1-13) 1.00 15.24 0.15 0.30 0.69

VIGAS DE CIMENTACION, ENCOFRADO Y DESENCOFRADO m2 41.69


EJE 13 (A-B) 2.00 3.30 0.30 1.98
EJE 13 (B-C) 2.00 2.20 0.30 1.32
EJE 13 (C-D) 2.00 1.45 0.30 0.87

EJE B (13-12) 2.00 0.55 0.30 0.33


EJE C (13-12) 2.00 0.55 0.30 0.33

EJE 12 (B-C) 2.00 2.65 0.30 1.59


EJE 12 (C-D) 2.00 1.30 0.30 0.78

EJE 9 (A-B) 2.00 5.40 0.30 3.24


EJE 9 (B-C) 2.00 2.20 0.30 1.32
EJE 9 (C-D) 2.00 0.65 0.30 0.39

EJE 8 (B-C-D) 2.00 1.88 0.30 1.13

EJE 6 (A-B) 2.00 2.10 0.30 1.26


EJE 6 (C-D) 2.00 1.25 0.30 0.75
HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL
EJE 5 (B-C-D) 2.00 0.45 0.30 0.27

EJE 2 (A-B) 2.00 2.90 0.30 1.74


EJE 2 (B-C-D) 2.00 1.85 0.30 1.11

EJE A (1-13) 2.00 16.37 0.30 9.82

EJE B (9-8) 2.00 1.20 0.30 0.72

EJE B (5-4) 2.00 2.88 0.30 1.73

EJE B (4-2) 2.00 1.06 0.30 0.64

EJE C (12-9) 2.00 2.05 0.30 1.23

EJE D (1-13) 2.00 15.24 0.30 9.14

VIGAS DE CIMENTACION, ACERO FY=4200 KG/CM2. kg 354.88


354.88 354.88

CURADO DE CONCRETO m2 2.07


EJE 13 (A-B) 1.00 0.15 0.60 0.09
EJE 13 (B-C) 1.00 0.15 0.60 0.09
EJE 13 (C-D) 1.00 0.15 0.60 0.09

EJE B (13-12) 1.00 0.30 0.60 0.18


EJE C (13-12) 1.00 0.15 0.60 0.09

EJE 12 (B-C) 1.00 0.15 0.60 0.09


EJE 12 (C-D) 1.00 0.15 0.60 0.09

EJE 9 (A-B) 1.00 0.15 0.60 0.09


EJE 9 (B-C) 1.00 0.15 0.60 0.09
EJE 9 (C-D) 1.00 0.15 0.60 0.09

EJE 8 (B-C-D) 1.00 0.15 0.60 0.09

EJE 6 (A-B) 1.00 0.15 0.60 0.09


HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL
EJE 6 (C-D) 1.00 0.15 0.60 0.09

EJE 5 (B-C-D) 1.00 0.15 0.60 0.09

EJE 2 (A-B) 1.00 0.15 0.60 0.09


EJE 2 (B-C-D) 1.00 0.15 0.60 0.09

EJE A (1-13) 1.00 0.15 0.60 0.09

EJE B (9-8) 1.00 0.15 0.60 0.09

EJE B (5-4) 1.00 0.15 0.60 0.09

EJE B (4-2) 1.00 0.15 0.60 0.09

EJE C (12-9) 1.00 0.15 0.60 0.09

EJE D (1-13) 1.00 0.15 0.60 0.09

SOBRECIMIENTOS m3 3.25
EJE 13 (A-B) CC-2 1.00 3.30 0.15 0.30 0.15
EJE 13 (B-C) CC-2 1.00 2.20 0.15 0.30 0.10
EJE 13 (C-D) CC-2 1.00 1.45 0.15 0.30 0.07

EJE B (13-12) CC-7 1.00 0.55 0.15 0.10 0.01


EJE C (13-12) CC-7 1.00 0.55 0.15 0.10 0.01

EJE 12 (B-C) CC-4 1.00 2.65 0.15 0.30 0.12


EJE 12 (C-D) CC-4 1.00 1.30 0.15 0.30 0.06

EJE 9 (A-B) CC-4 1.00 5.40 0.15 0.30 0.24


EJE 9 (B-C) CC-4 1.00 2.20 0.15 0.30 0.10
EJE 9 (C-D) CC-7 1.00 0.65 0.15 0.10 0.01

EJE 8 (B-C-D) CC-5 1.00 1.88 0.15 0.55 0.16

EJE 6 (A-B) CC-5 1.00 2.10 0.15 0.55 0.17


EJE 6 (C-D) CC-3 1.00 1.25 0.15 0.30 0.06
HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL

EJE 5 (B-C-D) CC-7 1.00 0.45 0.15 0.10 0.01

EJE 2 (A-B) CC-3 1.00 2.90 0.15 0.30 0.13


EJE 2 (B-C-D) CC-3 1.00 1.85 0.15 0..30 0.28

EJE A (1-13) CC-1, CC-2 1.00 16.37 0.15 0.30 0.74

EJE B (9-8) CC-7 1.00 1.20 0.15 0.10 0.02

EJE B (5-4) CC-7 1.00 2.88 0.15 0.10 0.04

EJE B (4-2) CC-7 1.00 1.06 0.15 0.10 0.02

EJE C (12-9) CC-4 1.00 2.05 0.15 0.30 0.09

EJE D (1-13) CC-1, CC-2 1.00 15.24 0.15 0.30 0.69

SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO m2


EJE 13 (A-B) CC-2 1.00 3.30 0.60 1.98
EJE 13 (B-C) CC-2 1.00 2.20 0.60 1.32
EJE 13 (C-D) CC-2 1.00 1.45 0.60 0.87

EJE B (13-12) CC-7 1.00 0.55 0.20 0.11


EJE C (13-12) CC-7 1.00 0.55 0.20 0.11

EJE 12 (B-C) CC-4 1.00 2.65 0.60 1.59


EJE 12 (C-D) CC-4 1.00 1.30 0.60 0.78

EJE 9 (A-B) CC-4 1.00 5.40 0.60 3.24


EJE 9 (B-C) CC-4 1.00 2.20 0.60 1.32
EJE 9 (C-D) CC-7 1.00 0.65 0.20 0.13

EJE 8 (B-C-D) CC-5 1.00 1.88 1.10 2.07

EJE 6 (A-B) CC-5 1.00 2.10 1.10 2.31


EJE 6 (C-D) CC-3 1.00 1.25 0.60 0.75
HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL
EJE 5 (B-C-D) CC-7 1.00 0.45 0.20 0.09

EJE 2 (A-B) CC-3 1.00 2.90 0.60 1.74


EJE 2 (B-C-D) CC-3 1.00 1.85 0.60 1.11

EJE A (1-13) CC-1, CC-2 1.00 16.37 0.60 9.82

EJE B (9-8) CC-7 1.00 1.20 0.20 0.24

EJE B (5-4) CC-7 1.00 2.88 0.20 0.58

EJE B (4-2) CC-7 1.00 1.06 0.20 0.21

EJE C (12-9) CC-4 1.00 2.05 0.60 1.23

EJE D (1-13) CC-1, CC-2 1.00 15.24 0.60 9.14

CURADO DE CONCRETO m2 1.71


EJE 13 (A-B) CC-2 1.00 0.15 0.60 0.09
EJE 13 (B-C) CC-2 1.00 0.15 0.60 0.09
EJE 13 (C-D) CC-2 1.00 0.15 0.60 0.09

EJE B (13-12) CC-7 1.00 0.15 0.20 0.03


EJE C (13-12) CC-7 1.00 0.15 0.20 0.03

EJE 12 (B-C) CC-4 1.00 0.15 0.60 0.09


EJE 12 (C-D) CC-4 1.00 0.15 0.60 0.09

EJE 9 (A-B) CC-4 1.00 0.15 0.60 0.09


EJE 9 (B-C) CC-4 1.00 0.15 0.60 0.09
EJE 9 (C-D) CC-7 1.00 0.15 0.20 0.03

EJE 8 (B-C-D) CC-5 1.00 0.15 1.10 0.17

EJE 6 (A-B) CC-5 1.00 0.15 1.10 0.17


EJE 6 (C-D) CC-3 1.00 0.15 0.60 0.09

EJE 5 (B-C-D) CC-7 1.00 0.15 0.20 0.03


HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL

EJE 2 (A-B) CC-3 1.00 0.15 0.60 0.09


EJE 2 (B-C-D) CC-3 1.00 0.15 0.60 0.09

EJE A (1-13) CC-1, CC-2 1.00 0.15 0.60 0.09

EJE B (9-8) CC-7 1.00 0.15 0.20 0.03

EJE B (5-4) CC-7 1.00 0.15 0.20 0.03

EJE B (4-2) CC-7 1.00 0.15 0.20 0.03

EJE C (12-9) CC-4 1.00 0.15 0.60 0.09

EJE D (1-13) CC-1, CC-2 1.00 0.15 0.60 0.09

COLUMNAS
COLUMNAS, CONCRETO F'C=210 KG/CM2 m3
EJE 13-A (C-3) 1.00 AREA 0.07 3.60 0.24
EJE 13-B (C-2) 1.00 0.30 0.30 3.60 0.32
EJE 13-C (C-6) 1.00 0.30 0.15 3.60 0.16
EJE 13-D (C-2) 1.00 0.30 0.30 3.60 0.32

EJE 12-B (C-6) 1.00 0.30 0.15 3.60 0.16


EJE 12-C (C-13) 1.00 0.30 0.38 3.60 0.41
EJE 12-D (C-4) 2.00 AREA 0.08 3.60 0.60

EJE 9-A (C-5) 1.00 0.40 0.15 3.60 0.22


EJE 9-B (C-3) 1.00 AREA 0.07 3.60 0.24
EJE 9-C (C-12) 1.00 0.53 0.30 3.60 0.57
EJE 9-D (C-6) 1.00 0.30 0.15 3.60 0.16
EJE 9-D (C-4) 1.00 AREA 0.08 3.60 0.30

EJE 8 B (C-2) 1.00 0.30 0.30 3.60 0.32


EJE 8 C (C-4) 2.00 AREA 0.08 3.60 0.60

EJE 6 A (C-3) 2.00 AREA 0.07 3.60 0.49


EJE 6 B (C-8) 2.00 0.25 0.15 3.60 0.27
HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL
EJE 6 D (C-6) 1.00 0.30 0.15 3.60 0.16

EJE 5 (C-3) 3.00 AREA 0.07 3.60 0.73


EJE 5 (C-8) 2.00 0.25 0.15 3.60 0.27
EJE 5 (C-10) 1.00 AREA 0.08 3.60 0.30
EJE 5 (C-2) 1.00 0.30 0.30 3.60 0.32

EJE 4 (C-5) 1.00 0.40 0.15 3.60 0.22


EJE 4 (C-2) 1.00 0.30 0.30 3.60 0.32
EJE 4 (C-7) 1.00 0.40 0.15 3.60 0.22
EJE 4 (C-4) 1.00 AREA 0.08 3.60 0.30

EJE 2 (C-1) 1.00 AREA 0.07 3.60 0.25


EJE 2 (C-3) 1.00 AREA 0.07 3.60 0.24
EJE 2 (C-5) 1.00 0.40 0.15 3.60 0.22
EJE 2 (C-8) 3.00 0.25 0.15 3.60 0.41
EJE 2 (C-7) 2.00 0.40 0.15 3.60 0.43
EJE 2 (C-11) 1.00 AREA 0.06 3.60 0.22

EJE 1 (C-8) 2.00 0.25 0.15 3.60 0.27

VIGAS
VIGAS, CONCRETO F'C=210 KG/CM2 m3 7.83
VA-1 (0.25*0.20) EJE 13-13 (A-B-C-D) 1.00 8.00 0.25 0.20 0.40
VA-1 (0.25*0.20) EJE 9-10 (A-B-C-D) 1.00 8.00 0.25 0.20 0.40
VA-1 (0.25*0.20) EJE 8-7 (A-B-C-D) 1.00 8.00 0.25 0.20 0.40
VA-1 (0.25*0.20) EJE 6 (A-B) 1.00 3.50 0.25 0.20 0.18
VA-1 (0.25*0.20) EJE 4-3 (A-B-C-D) 1.00 8.00 0.25 0.20 0.40
VA-1 (0.25*0.20) EJE 2-2 (A-B-C-D) 1.00 8.00 0.25 0.20 0.40

VA-2 (0.25*0.40) EJE 5-5 (A-B-C-D) 1.00 8.00 0.25 0.40 0.80

VB (0.20*0.20) EJE 12-11 (B-C) 1.00 2.20 0.20 0.20 0.09


VB (0.20*0.20) EJE 12-11 (C-D) 1.00 1.55 0.20 0.20 0.06
VB (0.20*0.20) EJE C (13-9) 1.00 4.00 0.20 0.20 0.16
VB (0.20*0.20) EJE 6 (C-D) 1.00 2.15 0.20 0.20 0.09
VB (0.20*0.20) EJE C (8-9) 1.00 3.60 0.20 0.20 0.14
VB (0.20*0.20) EJE B (6-5) 1.00 2.20 0.20 0.20 0.09
HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL
VB (0.20*0.20) EJE B (5-4) 1.00 3.41 0.20 0.20 0.14
VB (0.20*0.20) EJE C (4-2) 1.00 2.25 0.20 0.20 0.09
VB (0.20*0.20) EJE 2 (B-C) 1.00 2.80 0.20 0.20 0.11
VB (0.20*0.20) EJE 2 (A-B) 1.00 3.78 0.20 0.20 0.15

VS-1 (0.25*0.35) EJE B (8-9) 1.00 2.10 0.25 0.35 0.18

VS-2 (0.15*0.40) EJE A (13-2) 1.00 17.00 0.15 0.40 1.02


VS-2 (0.15*0.40) EJE D (13-2) 1.00 17.00 0.15 0.40 1.02

VS-3 (0.30*0.35) EJE B (13-9) 1.00 4.25 0.30 0.35 0.45

V-101 (0.50*0.20) EJE B (8-9) 1.00 10.46 0.50 0.20 1.05

VR-1 (0.15*0.20) EJE 2 1.00 0.75 0.15 0.20 0.02

VIGAS, ENCOFRADO Y DESENCOFRADO m2 101.81

VA-1 (0.25*0.20) EJE 13-13 (A-B-C-D) 1.00 8.00 0.65 5.20


VA-1 (0.25*0.20) EJE 9-10 (A-B-C-D) 1.00 8.00 0.65 5.20
VA-1 (0.25*0.20) EJE 8-7 (A-B-C-D) 1.00 8.00 0.65 5.20
VA-1 (0.25*0.20) EJE 6 (A-B) 1.00 3.50 0.65 2.28
VA-1 (0.25*0.20) EJE 4-3 (A-B-C-D) 1.00 8.00 0.65 5.20
VA-1 (0.25*0.20) EJE 2-2 (A-B-C-D) 1.00 8.00 0.65 5.20

VA-2 (0.25*0.40) EJE 5-5 (A-B-C-D) 1.00 8.00 1.05 8.40

VB (0.20*0.20) EJE 12-11 (B-C) 1.00 2.20 0.60 1.32


VB (0.20*0.20) EJE 12-11 (C-D) 1.00 1.55 0.60 0.93
VB (0.20*0.20) EJE C (13-9) 1.00 4.00 0.60 2.40
VB (0.20*0.20) EJE 6 (C-D) 1.00 2.15 0.60 1.29
VB (0.20*0.20) EJE C (8-9) 1.00 3.60 0.60 2.16
VB (0.20*0.20) EJE B (6-5) 1.00 2.20 0.60 1.32
VB (0.20*0.20) EJE B (5-4) 1.00 3.41 0.60 2.05
VB (0.20*0.20) EJE C (4-2) 1.00 2.25 0.60 1.35
VB (0.20*0.20) EJE 2 (B-C) 1.00 2.80 0.60 1.68
VB (0.20*0.20) EJE 2 (A-B) 1.00 3.78 0.60 2.27
HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL
VS-1 (0.25*0.35) EJE B (8-9) 1.00 2.10 0.95 2.00
0.00
VS-2 (0.15*0.40) EJE A (13-2) 1.00 17.00 0.95 16.15
VS-2 (0.15*0.40) EJE D (13-2) 1.00 17.00 0.95 16.15

VS-3 (0.30*0.35) EJE B (13-9) 1.00 4.25 1.00 4.25

V-101 (0.50*0.20) EJE B (8-9) 1.00 10.46 0.90 9.41

VR-1 (0.15*0.20) EJE 2 1.00 0.75 0.55 0.41

VIGAS, ACERO FY=4200 KG/CM2 . kg 953.70


1.00 953.70 953.70

CURADO DE CONCRETO m2 101.81


VA-1 (0.25*0.20) EJE 13-13 (A-B-C-D) 1.00 8.00 0.65 5.20
VA-1 (0.25*0.20) EJE 9-10 (A-B-C-D) 1.00 8.00 0.65 5.20
VA-1 (0.25*0.20) EJE 8-7 (A-B-C-D) 1.00 8.00 0.65 5.20
VA-1 (0.25*0.20) EJE 6 (A-B) 1.00 3.50 0.65 2.28
VA-1 (0.25*0.20) EJE 4-3 (A-B-C-D) 1.00 8.00 0.65 5.20
VA-1 (0.25*0.20) EJE 2-2 (A-B-C-D) 1.00 8.00 0.65 5.20

VA-2 (0.25*0.40) EJE 5-5 (A-B-C-D) 1.00 8.00 1.05 8.40

VB (0.20*0.20) EJE 12-11 (B-C) 1.00 2.20 0.60 1.32


VB (0.20*0.20) EJE 12-11 (C-D) 1.00 1.55 0.60 0.93
VB (0.20*0.20) EJE C (13-9) 1.00 4.00 0.60 2.40
VB (0.20*0.20) EJE 6 (C-D) 1.00 2.15 0.60 1.29
VB (0.20*0.20) EJE C (8-9) 1.00 3.60 0.60 2.16
VB (0.20*0.20) EJE B (6-5) 1.00 2.20 0.60 1.32
VB (0.20*0.20) EJE B (5-4) 1.00 3.41 0.60 2.05
VB (0.20*0.20) EJE C (4-2) 1.00 2.25 0.60 1.35
VB (0.20*0.20) EJE 2 (B-C) 1.00 2.80 0.60 1.68
VB (0.20*0.20) EJE 2 (A-B) 1.00 3.78 0.60 2.27

VS-1 (0.25*0.35) EJE B (8-9) 1.00 2.10 0.95 2.00

VS-2 (0.15*0.40) EJE A (13-2) 1.00 17.00 0.95 16.15


HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL
VS-2 (0.15*0.40) EJE D (13-2) 1.00 17.00 0.95 16.15

VS-3 (0.30*0.35) EJE B (13-9) 1.00 4.25 1.00 4.25


0.00
V-101 (0.50*0.20) EJE B (8-9) 1.00 10.46 0.90 9.41

VR-1 (0.15*0.20) EJE 2 1.00 0.75 0.55 0.41


HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL
HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL

COLUMNAS, ENCOFRADO Y DESENCOFRADO m2


COLUMNAS, ACERO FY=4200 KG/CM2 . kg
CURADO DE CONCRETO m2
COLUMNETAS
COLUMNETAS, CONCRETO F'C= 175 KG/CM2 m3
COLUMNETAS, ENCOFRADO Y DESENCOFRADO m2
COLUMNETAS, ACERO FY=4200 KG/CM2 . kg
CURADO DE CONCRETO m2
VIGAS
VIGAS, CONCRETO F'C=210 KG/CM2 m3
VIGAS, ENCOFRADO Y DESENCOFRADO m2
VIGAS, ACERO FY=4200 KG/CM2 . kg
CURADO DE CONCRETO m2
VIGUETAS DE ARRIOSTRE
HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL
VIGUETAS DE ARRIOSTRE, CONCRETO F'c= 175KG/CM2 m3
VIGUETAS DE ARRIOSTRE, ENCOFRADO Y DESENCOFRADO m2
VIGUETAS DE ARRIOSTRE, ACERO FY=4200 KG/CM2 . kg
CURADO DE CONCRETO m2
PARAPETO DE CONCRETO
PARAPETOS DE CONCRETO, CONCRETO F'C=175 KG/M3 m3
PARAPETOS DE CONCRETO, ENCOFRADO Y DESENCOFRADO m2
PARAPETOS DE CONCRETO, ACERO FY=4200 KG/CM2 kg
CURADO DE CONCRETO m2
LOSA MACIZA
LOSA MACIZA, CONCRETO F'C=210 KG/CM2 m3
LOSA MACIZA, ENCOFRADO Y DESENCOFRADO m2
LOSA MACIZA, ACERO FY=4200 KG/CM2. kg
CURADO DE CONCRETO m2
HOJA DE METRADOS
PRESUPUESTO:
SUBPRESUPUESTO: ESTRUCTURA
CLIENTE:
LUGAR:
ITEM DESCRIPCION UND. CANT L A H PARCIAL TOTAL