MOVILIZACION Y DESMOVILIZACION DE EQUIPOS

PROYECTO
"CONSTRUCCION DE MURO DE CONCRETO CICLOPEO LT=18M, TUCO BAJO, C.P. EL TUTO, DISTRITO DE BAMBAMARCA, PROVINCIA DE HUALGAYOC"

REGION :CAJAMARCA
PROVINCIA : HUALGAYOC
DISTRITO :BAMBAMARCA

FACTOR DE
MAQUINARIAS PESO KG COSTO S/./KG SUB TOTAL S/. N. VECES TOTAL S/.
PLATAFORMA

MIRAS Y JALONES 5.0 0.1422 6.0000 0.71 2.00 8.53


MEZCLADORA DE CONCRETO DE 11p3 18 HP 350.0 0.1422 6.0000 49.78 2.00 597.37
MOTOBOMBA 10 HP 4" 50.0 0.1422 6.0000 7.11 2.00 85.32
COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP 50.0 0.1422 6.0000 7.11 2.00 85.32
VIBRADOR DE CONCRETO 4 HP 1.50" 55.0 0.1422 6.0000 7.82 4.00 187.70
MOTOSOLDADORA DE 250 A 22.0 0.1422 6.0000 2.84 2.00 7.96
TEODOLITO 22.0 0.1422 6.0000 2.84 2.00 7.96
NIVEL DE INGENIERO 11.9 0.1422 6.0000 1.69 2.00 20.31

TOTAL (SIN IGV) S/. 1,000.00

COSTO TOTAL DE MOVILIZACION Y DESMOVILIZACION S/. = 1,000.00


ANALISIS DE FLETE RURAL CARRETERA TUCO BAJO HACIA EL PROYECTO (OBRA)
PROYECTO
"CONSTRUCCION DE MURO DE CONCRETO CICLOPEO LT=18M, TUCO BAJO, C.P. EL TUCO, DISTRITO DE
BAMBAMARCA, PROVINCIA DE HUALGAYOC"

REGION :CAJAMARCA
PROVINCIA : HUALGAYOC
DISTRITO :BAMBAMARCA

TRANSPORTAD
N° DESCRIPCION DE LOS MATERIALES UND CANTIDAD PESO UNIT.(KG) OS EN CAMION
(KG)

1 ALAMBRE NEGRO RECOCIDO # 16 kg 51.84 1.00 51.84


2 CLAVOS CON CABEZA DE 2 1/2", 3", 4" kg 52.20 1.00 52.20
3 CEMENTO PORTLAND TIPO I (42.5 kg) bls 1,063.37 42.50 45,193.14
4 YESO EN BOLSAS DE 25 kg bls 1.44 25.00 36.00
5 MADERA EUCALIPTO (p2) p2 712.80 4.00 2,851.20
6 TUBERIA F°G° 1 1/2" X 3.3 MM. m 85.40 3.00 256.20
7 AGREGADOS M3 261.67 72.84 19,059.93

PESO TOTAL DE LOS MATERIALES (KG) = 67,500.51

NUMERO DE VIAJES = PESO TOTAL DE MATERIAL 67,500.51 6.8


PESO CARGA CAMION 10,000.00

NUMERO DE VIAJES = 7+1 8

COSTO DE ALQUILER DE CAMION CARGA DE 12 TN. (SIN IGV) S/. 875


NUMERO DE VIAJES REQUERIDOS POR PESO (SIN IGV) S/. 8.00
CALCULO DE COSTO DE TRANSPORTE DE MATERIALES S/. = 7,000.00

COSTO TOTAL DE TRANSPORTE DE MATERIALES (SIN IGV ) S/. = 7,000.00

COSTO TOTAL DE ACARREO DE MATERIALES IN SITU (SIN IGV ) S/. = 20,250.30