37031700173
FECHA DE EMISION : 1/20/2021 ESTADO DE PAGO O/S ZV00000CDB-001
PERIODO 8/17/2020 HASTA 10/20/2020 CONTRATISTA: B&B MURILLO S.A.C.
Rev 0 MONEDA CONTRATO NUEVOS SOLES
CONTRATO ANTERIOR HASTA LA FECHA
ITEM DESCRIPCION O/T, PROYECTO NATURALEZA PRECIO PRECIO
CONTRATO MARCO OBRAS MISCELANEAS CIVILES CENTRO COSTO GASTO UND UNITARIO TOTAL CANTIDAD COSTO CANTIDAD COSTO
1 Obras Civiles en planta PTAD y PTARI_OTM-998 CAP15021 GLB 31.73% 90,809.91 28,814.44 57.55% 52,259.05 89.28% 81,073.49
2 Excavación, perfilado de terreno para montaje de flujometro en tanque 2082_IO-805 CAP15021 GLB 66.94% 53,529.88 35,830.73 0.00% 0.00 66.94% 35,830.73
C. COSTO: FECHA FECHA FECHA TOTAL A PAGAR S/. 64,645.17 S/. 52,259.05 S/. 116,904.22
VALORIZACIÓN DE AVANCE DE OBRA Nº 02
PROYECTO: MINE MAINTENANCE FACILITIES RELOCATION PHASE II AND III N° CONTRATO: 37031700173 PRESUPUESTO DEL PROYECTO : 144,339.79
FINANCIA: SOCIEDAD MINERA CERRO VERDE N° OTM : GPIC-00000000-1700173-OTM-998 FECHA DE INICIO DE OBRA : 8/17/2020
PRESUPUESTO VALORIZACIONES
PARTIDA DESCRIPCION P.U TOTAL VALORIZACION ANTERIOR Nº VALORIZACION ACTUAL Nº 02 TOTAL ACUMULADO SALDO POR VALORIZAR
UND METRADO
S/. S/. METRADO VALORIZ.S/. % METRADO VALORIZ.S/. % METRADO VALORIZ.S/. % METRADO VALORIZ.S/. %
COSTO INDIRECTO
GASTOS GENERALES 42.8% GLB 1.00 42.80% 16801.29 0.67 11209.24 66.70% 0.33 6700.08 33.30% 1.00 17909.32 100.00% 0.00 0.00 0.00%
UTILIDAD 9.00% GLB 1.00 9.00% 3532.98 0.67 2357.08 66.70% 0.33 1408.90 33.30% 1.00 3765.98 100.00% 0.00 0.00 0.00%
CAMIONETA 4x4 DIA 18.00 352.86 6,351.48 18.00 6,351.48 100.00% 0.00 0.00% 18.00 6,351.48 100.00% 0.00 0.00 0.00%
MINIBUS DIA 18.00 240.00 4,320.00 18.00 4,320.00 100.00% 0.00 0.00% 18.00 4,320.00 100.00% 0.00 0.00 0.00%
DEDUCTIVO INDIRECTOS EXCLUSIVOS (% DEL INDIRECTO CONTRACTUAL) UND 1.00 -0.01 -447.51 -0.01 -298.56 -1.00% -0.01 -178.46 -1.00% -0.02 -477.02 -2.00% 1.00 29.51 100.00%
GASTOS GENERALES 42.80% GLB 1.00 42.80% 9940.22 0.00 0.00 0.00% 0.85 8448.31 85.00% 0.85 8448.31 85.00% 0.15 1491.91 15.00%
UTILIDAD 9.00% GLB 1.00 9.00% 2090.23 0.00 0.00 0.00% 0.85 1776.51 85.00% 0.85 1776.51 85.00% 0.15 313.72 15.00%
CAMIONETA 4x4 DIA 6.00 352.86 2,117.16 0.00 0.00% 6.00 2,117.16 100.00% 6.00 2,117.16 100.00% 0.00 0.00 0.00%
MINIBUS DIA 6.00 240.00 1,440.00 0.00 0.00% 6.00 1,440.00 100.00% 6.00 1,440.00 100.00% 0.00 0.00 0.00%
DEDUCTIVO INDIRECTOS EXCLUSIVOS (% DEL INDIRECTO CONTRACTUAL) UND 1.00 -0.01 -264.76 -0.01 0.00 -1.00% -0.01 -225.03 -1.00% -0.02 -225.03 -2.00% 1.00 0.00 100.00%
SUB TOTAL COSTO INDIRECTO 45881.09 23939.24 52.00% 21487.47 47.00% 45426.71 99.00% 0.00 0.00%
1.01.02 PROTECCION DE ELEMENTOS CIRCUNDANTES (TUBERIA) GLB 1.00 354.79 354.79 1.00 354.79 100.00% 0.00 0.00 0.00% 1.00 354.79 100.00% 0.00 0.00 0.00%
1.01.03 PANTALLA DE PROTECCION DE TRIPLAY (DESPRENDIMIENTOS EN TALUD) M 7.00 56.89 398.23 7.00 398.23 100.00% 0.00 0.00 0.00% 7.00 398.23 100.00% 0.00 0.00 0.00%
1.01.04 VIGIA DE TALUD DIA 3.00 172.50 517.50 3.00 517.50 100.00% 0.00 0.00 0.00% 3.00 517.50 100.00% 0.00 0.00 0.00%
1.02.01 DEMOLICIÓN DE PISOS DE CONCRETO ARMADO - MANUAL M3 0.25 545.58 136.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.25 136.40 100.00%
1.02.02 CARGUIO DE MATERIAL MANUAL M3 0.25 68.72 17.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.25 17.18 100.00%
1.02.03 TRANSPORTE DE MATERIAL < 5M3 VIAJE/KM 0.25 321.39 80.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.25 80.35 100.00%
1.03 EXCAVACIONES
1.03.01 EXCAVACIÓN MANUAL DE ZANJAS EN MATERIAL COMPACTADO H ≤ 1.2M M3 13.44 90.49 1,216.19 13.44 1,216.19 100.00% 0.00 0.00 0.00% 13.44 1,216.19 100.00% 0.00 0.00 0.00%
1.03.02 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA SUELTA H ≤ 1.2M M3 18.68 220.60 4,120.81 9.30 2,051.58 50.00% 0.00 0.00 0.00% 9.30 2,051.58 50.00% 9.38 2,069.23 50.00%
1.03.03 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA FIJA H ≤ 1.2M M3 8.00 327.91 2,623.28 8.00 2,623.28 100.00% 0.00 0.00 0.00% 8.00 2,623.28 100.00% 0.00 0.00 0.00%
1.03.04 REFINE, NIVELACIÓN Y COMPACTACIÓN CON EQUIPO LIVIANO M2 13.92 14.91 207.55 13.92 207.55 100.00% 0.00 0.00 0.00% 13.92 207.55 100.00% 0.00 0.00 0.00%
1.03.05 CARGUIO DE MATERIAL CON EQUIPO (P/ELIMINACION) M3 32.02 4.66 149.21 22.32 104.01 70.00% 0.00 0.00 0.00% 22.32 104.01 70.00% 9.70 45.20 30.00%
1.03.06 TRANSPORTE DE MATERIAL > 5M3 M3/KM 256.13 1.40 358.58 178.56 249.98 70.00% 0.00 0.00 0.00% 178.56 249.98 70.00% 77.57 108.60 30.00%
1.04 RELLENOS
1.04.01 PREPARACIÓN DE MATERIAL DE RELLENO M3 15.31 5.65 86.50 5.62 31.75 37.00% 0.00 0.00 0.00% 5.62 31.75 37.00% 9.69 54.75 63.00%
1.04.02 CARGUIO DE MATERIAL CON EQUIPO (MAT. DE PRESTAMO) M3 15.31 4.66 71.34 5.62 26.19 37.00% 0.00 0.00 0.00% 5.62 26.19 37.00% 9.69 45.15 63.00%
1.04.03 TRANSPORTE DE MATERIAL > 5M3 M3/KM 153.10 1.40 214.34 56.20 78.68 37.00% 0.00 0.00 0.00% 56.20 78.68 37.00% 96.90 135.66 63.00%
1.04.04 RELLENO COMPACTADO CON EQUIPO LIVIANO M3 12.76 76.90 981.24 4.68 359.89 37.00% 0.00 0.00 0.00% 4.68 359.89 37.00% 8.08 621.35 63.00%
1.04.05 RELLENO CON GRAVA M3 0.50 82.46 41.23 0.25 20.62 50.00% 0.00 0.00 0.00% 0.25 20.62 50.00% 0.25 20.61 50.00%
1.05.02 ENCOFRADO Y DESENCOFRADO CARAVISTA M2 41.84 74.29 3,108.29 41.84 3,108.29 100.00% 0.00 0.00 0.00% 41.84 3,108.29 100.00% 0.00 0.00 0.00%
1.05.03 ACERO DE REFUERZO F´Y 4200 KG/CM2 KG 966.20 2.75 2,657.05 896.60 2,465.65 93.00% 69.60 191.40 7.00% 966.20 2,657.05 100.00% 0.00 0.00 0.00%
1.05.04 CONCRETO F´C =280 KG/CM2 CEMENTO TIPO V – PREMEZCLADO M3 0.50 66.14 33.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.50 33.07 100.00%
1.05.05 CONCRETO F´C =280 KG/CM2 CEMENTO TIPO V – MANUAL M3 7.33 231.86 1,699.53 7.16 1,660.12 98.00% 0.17 39.42 2.00% 7.33 1,699.54 100.00% 0.00 -0.01 0.00%
1.05.06 ACABADO ENLUCIDO DE LOSA M2 10.80 18.85 203.58 10.80 203.58 100.00% 0.00 0.00 0.00% 10.80 203.58 100.00% 0.00 0.00 0.00%
2.01.02 PROTECCION DE ELEMENTOS CIRCUNDANTES (TUBERIAS, DRENAJE) EST 1.00 354.79 354.79 1.00 354.79 100.00% 0.00 0.00 0.00% 1.00 354.79 100.00% 0.00 0.00 0.00%
2.01.03 APUNTALAMIENTO DE ESTRUCTURAS (TUBERIAS, DRENAJES) EST 1.00 279.92 279.92 1.00 279.92 100.00% 0.00 0.00 0.00% 1.00 279.92 100.00% 0.00 0.00 0.00%
2.01.04 VIGIA DE ESPACIOS CONFINADOS DIA 1.00 172.50 172.50 0.00 0.00 0.00% 1.00 172.50 100.00% 1.00 172.50 100.00% 0.00 0.00 0.00%
2.02 DEMOLICIONES
2.02.01 DEMOLICIÓN DE PISOS DE CONCRETO ARMADO - MANUAL M3 0.95 545.58 518.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.95 518.30 100.00%
2.02.02 CARGUIO DE MATERIAL MANUAL M3 1.43 68.72 98.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.43 98.27 100.00%
2.02.03 TRANSPORTE DE MATERIAL < 5M3 VIAJE/KM 11.40 321.39 3,663.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.40 3,663.85 100.00%
2.03.02 EXCAVACIÓN MANUAL DE ZANJAS EN MATERIAL COMPACTADO H ≤ 1.2M M3 2.25 90.49 203.60 0.00 0.00 0.00% 2.25 203.60 100.00% 2.25 203.60 100.00% 0.00 0.00 0.00%
2.03.03 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA SUELTA H ≤ 1.2M M3 5.40 220.60 1,191.24 0.00 0.00 0.00% 5.40 1,191.24 100.00% 5.40 1,191.24 100.00% 0.00 0.00 0.00%
2.03.04 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA FIJA H ≤ 1.2M M3 1.35 327.91 442.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.35 442.68 100.00%
2.03.05 REFINE, NIVELACIÓN Y COMPACTACIÓN CON EQUIPO LIVIANO M2 3.00 14.91 44.73 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 44.73 100.00%
2.03.06 ACARREO DE MATERIAL < 50 M M3 1.00 68.72 68.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 68.72 100.00%
2.03.07 CARGUIO DE MATERIAL CON EQUIPO (P/ELIMINACION) M3 10.80 4.66 50.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.80 50.33 100.00%
2.03.08 TRANSPORTE DE MATERIAL > 5M3 M3/KM 86.40 1.40 120.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 86.40 120.96 100.00%
2.04 RELLENOS
2.04.01 PREPARACIÓN DE MATERIAL DE RELLENO M3 6.30 5.65 35.60 0.00 0.00 0.00% 6.30 35.60 100.00% 6.30 35.60 100.00% 0.00 0.00 0.00%
2.04.02 CARGUIO DE MATERIAL CON EQUIPO (MAT. DE PRESTAMO) M3 6.30 4.66 29.36 0.00 0.00 0.00% 6.30 29.36 100.00% 6.30 29.36 100.00% 0.00 0.00 0.00%
2.04.03 TRANSPORTE DE MATERIAL > 5M3 M3/KM 50.40 1.40 70.56 0.00 0.00 0.00% 50.40 70.56 100.00% 50.40 70.56 100.00% 0.00 0.00 0.00%
2.04.04 RELLENO COMPACTADO CON EQUIPO LIVIANO M3 5.25 76.90 403.73 0.00 0.00 0.00% 5.25 403.73 100.00% 5.25 403.73 100.00% 0.00 0.00 0.00%
2.05.02 ENCOFRADO Y DESENCOFRADO CARAVISTA M2 21.76 74.29 1,616.55 13.96 1,037.09 64.00% 7.80 579.46 36.00% 21.76 1,616.55 100.00% 0.00 0.00 0.00%
2.05.03 ACERO DE REFUERZO F´Y 4200 KG/CM2 KG 478.40 2.75 1,315.60 188.40 518.10 39.00% 290.00 797.50 61.00% 478.40 1,315.60 100.00% 0.00 0.00 0.00%
2.05.04 CONCRETO F´C =280 KG/CM2 CEMENTO TIPO V – PREMEZCLADO M3 0.50 66.14 33.07 0.50 33.07 100.00% 0.00 0.00 0.00% 0.50 33.07 100.00% 0.00 0.00 0.00%
2.05.05 CONCRETO F´C =280 KG/CM2 CEMENTO TIPO V – MANUAL M3 3.58 231.86 830.06 1.20 278.23 34.00% 1.38 319.97 39.00% 2.58 598.20 73.00% 1.00 231.86 27.00%
2.05.06 ACABADO ENLUCIDO DE LOSA M2 3.00 18.85 56.55 3.00 56.55 100.00% 0.00 0.00 0.00% 3.00 56.55 100.00% 0.00 0.00 0.00%
3.02 EXCAVACIONES
3.02.01 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA SUELTA H ≤ 1.2M M3 4.20 220.60 926.52 1.68 370.61 40.00% 0.00 0.00 0.00% 1.68 370.61 40.00% 2.52 555.91 60.00%
3.02.02 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA FIJA H ≤ 1.2M M3 1.05 327.91 344.31 0.42 137.72 40.00% 0.00 0.00 0.00% 0.42 137.72 40.00% 0.63 206.59 60.00%
3.02.03 REFINE, NIVELACIÓN Y COMPACTACIÓN CON EQUIPO LIVIANO M2 7.50 14.91 111.83 3.00 44.73 40.00% 0.00 0.00 0.00% 3.00 44.73 40.00% 4.50 67.10 60.00%
3.02.04 ACARREO DE MATERIAL < 50 M M3 6.30 68.72 432.94 2.52 173.17 40.00% 0.00 0.00 0.00% 2.52 173.17 40.00% 3.78 259.77 60.00%
3.02.05 CARGUIO DE MATERIAL CON EQUIPO (P/ELIMINACION) M3 6.30 4.66 29.36 2.52 11.74 40.00% 0.00 0.00 0.00% 2.52 11.74 40.00% 3.78 17.62 60.00%
3.02.06 TRANSPORTE DE MATERIAL > 5M3 M3/KM 50.40 1.40 70.56 20.16 28.22 40.00% 0.00 0.00 0.00% 20.16 28.22 40.00% 30.24 42.34 60.00%
3.03 RELLENOS
3.03.01 PREPARACIÓN DE MATERIAL DE RELLENO M3 3.00 5.65 16.95 3.00 16.95 100.00% 0.00 0.00 0.00% 3.00 16.95 100.00% 0.00 0.00 0.00%
3.03.02 CARGUIO DE MATERIAL CON EQUIPO (MAT. DE PRESTAMO) M3 3.00 4.66 13.98 3.00 13.98 100.00% 0.00 0.00 0.00% 3.00 13.98 100.00% 0.00 0.00 0.00%
PRESUPUESTO VALORIZACIONES
PARTIDA DESCRIPCION P.U TOTAL VALORIZACION ANTERIOR Nº VALORIZACION ACTUAL Nº 02 TOTAL ACUMULADO SALDO POR VALORIZAR
UND METRADO
S/. S/. METRADO VALORIZ.S/. % METRADO VALORIZ.S/. % METRADO VALORIZ.S/. % METRADO VALORIZ.S/. %
3.03.03 TRANSPORTE DE MATERIAL > 5M3 M3/KM 24.00 1.40 33.60 24.00 33.60 100.00% 0.00 0.00 0.00% 24.00 33.60 100.00% 0.00 0.00 0.00%
3.03.04 RELLENO COMPACTADO CON EQUIPO LIVIANO M3 3.00 76.90 230.70 3.00 230.70 100.00% 0.00 0.00 0.00% 3.00 230.70 100.00% 0.00 0.00 0.00%
3.04.02 ACERO DE REFUERZO F´Y 4200 KG/CM2 KG 302.40 2.75 831.60 259.20 712.80 86.00% 0.00 0.00 0.00% 259.20 712.80 86.00% 43.20 118.80 14.00%
3.04.04 CONCRETO F´C =280 KG/CM2 CEMENTO TIPO V – MANUAL M3 3.36 231.86 779.05 3.36 779.05 100.00% 0.00 0.00 0.00% 3.36 779.05 100.00% 0.00 0.00 0.00%
3.04.05 ACABADO ENLUCIDO DE LOSA M2 24.00 18.85 452.40 9.60 180.96 40.00% 0.00 0.00 0.00% 9.60 180.96 40.00% 14.40 271.44 60.00%
A. MAYORES METRADOS
1.04 RELLENOS
1.05 CONCRETO ARMADO
2.00 BUZON COLECTOR
2.01 TRABAJOS PRELIMINARES
2.01.04 VIGIA DE ESPACIOS CONFINADOS DIA 3.00 172.50 517.50 0.00 0.00 0.00% 3.00 517.50 100.00% 3.00 517.50 100.00% 0.00 0.00 0.00%
2.02 DEMOLICIONES
2.03 EXCAVACIONES (INCL. DESCUBRIMIENTO DE TUBERIA)
2.03.02 EXCAVACIÓN MANUAL DE ZANJAS EN MATERIAL COMPACTADO H ≤ 1.2M M3 28.71 90.49 2,597.97 0.00 0.00 0.00% 28.71 2,597.97 100.00% 28.71 2,597.97 100.00% 0.00 0.00 0.00%
2.03.03 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA SUELTA H ≤ 1.2M M3 15.23 220.60 3,359.74 0.00 0.00 0.00% 15.23 3,359.74 100.00% 15.23 3,359.74 100.00% 0.00 0.00 0.00%
2.04 RELLENOS
2.04.01 PREPARACIÓN DE MATERIAL DE RELLENO M3 60.11 5.65 339.62 0.00 0.00 0.00% 60.11 339.62 100.00% 60.11 339.62 100.00% 0.00 0.00 0.00%
2.04.02 CARGUIO DE MATERIAL CON EQUIPO (MAT. DE PRESTAMO) M3 60.11 4.66 280.11 0.00 0.00 0.00% 60.11 280.11 100.00% 60.11 280.11 100.00% 0.00 0.00 0.00%
2.04.03 TRANSPORTE DE MATERIAL > 5M3 M3/KM 480.86 1.40 673.20 0.00 0.00 0.00% 480.86 673.20 100.00% 480.86 673.20 100.00% 0.00 0.00 0.00%
2.04.04 RELLENO COMPACTADO CON EQUIPO LIVIANO M3 50.09 76.90 3,851.92 0.00 0.00 0.00% 50.09 3,851.92 100.00% 50.09 3,851.92 100.00% 0.00 0.00 0.00%
1.01.02 PROTECCION DE ELEMENTOS CIRCUNDANTES (TUBERIA) GLB 1.00 222.17 222.17 0.00 0.00% 1.00 222.17 100.00% 1.00 222.17 100.00% 0.00 0.00 0.00%
1.01.03 VIGIA DE TALUD DIA 2.00 172.50 345.00 0.00 0.00% 2.00 345.00 100.00% 2.00 345.00 100.00% 0.00 0.00 0.00%
1.02 DEMOLICIONES
1.02.01 DEMOLICIÓN DE PISOS DE CONCRETO ARMADO - MANUAL M3 0.25 545.58 136.40 0.00 0.00% 0.25 136.40 100.00% 0.25 136.40 100.00% 0.00 0.00 0.00%
1.02.02 ACARREO DE MATERIAL < 50 M M3 0.38 68.72 26.11 0.00 0.00% 0.38 26.11 100.00% 0.38 26.11 100.00% 0.00 0.00 0.00%
1.02.03 CARGUIO DE MATERIAL MANUAL M3 0.38 68.72 26.11 0.00 0.00% 0.38 26.11 100.00% 0.38 26.11 100.00% 0.00 0.00 0.00%
1.02.04 TRANSPORTE DE MATERIAL < 5M3 VIAJE/KM 0.50 321.39 160.70 0.00 0.00% 0.50 160.70 100.00% 0.50 160.70 100.00% 0.00 0.00 0.00%
1.03.02 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA SUELTA H ≤ 1.2M M3 9.79 220.60 2,159.67 0.00 0.00% 6.98 1,539.79 71.00% 6.98 1,539.79 71.00% 2.81 619.88 29.00%
1.03.03 EXCAVACIÓN MANUAL DE ZANJAS EN MATERIAL COMPACTADO H ≤ 1.8M M3 19.58 114.49 2,241.71 0.00 0.00% 13.95 1,597.14 71.00% 13.95 1,597.14 71.00% 5.63 644.57 29.00%
1.03.04 REFINE, NIVELACIÓN Y COMPACTACIÓN CON EQUIPO LIVIANO M2 19.20 14.91 286.27 0.00 0.00% 19.20 286.27 100.00% 19.20 286.27 100.00% 0.00 0.00 0.00%
1.03.05 ACARREO DE MATERIAL < 50 M M3 58.74 68.72 4,036.61 0.00 0.00% 41.86 2,876.62 71.00% 41.86 2,876.62 71.00% 16.88 1,159.99 29.00%
1.03.06 CARGUIO DE MATERIAL CON EQUIPO (P/ELIMINACION) M3 58.74 4.66 273.73 0.00 0.00% 41.86 195.07 71.00% 41.86 195.07 71.00% 16.88 78.66 29.00%
1.03.07 TRANSPORTE DE MATERIAL > 5M3 M3/KM 411.18 1.40 575.65 0.00 0.00% 292.99 410.19 71.00% 292.99 410.19 71.00% 118.19 165.46 29.00%
1.04 RELLENOS
1.04.01 ZARANDEO DE MATERIAL PROPIO (MANUAL) M3 1.20 46.70 56.04 0.00 0.00% 1.20 56.04 100.00% 1.20 56.04 100.00% 0.00 0.00 0.00%
1.04.02 RELLENO COMPACTADO CON EQUIPO LIVIANO M3 1.00 76.90 76.90 0.00 0.00% 1.00 76.90 100.00% 1.00 76.90 100.00% 0.00 0.00 0.00%
1.04.03 CONFORMACIÓN DE PRETIL DE TIERRA H=0.90 M ML 12.00 13.92 167.04 0.00 0.00% 1.20 16.70 10.00% 1.20 16.70 10.00% 10.80 150.34 90.00%
2.01.02 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA SUELTA H ≤ 1.2M M3 1.17 220.60 258.10 0.00 0.00% 1.17 258.10 100.00% 1.17 258.10 100.00% 0.00 0.00 0.00%
2.01.03 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA FIJA H ≤ 1.2M M3 1.17 327.91 383.65 0.00 0.00% 1.17 383.65 100.00% 1.17 383.65 100.00% 0.00 0.00 0.00%
2.01.04 REFINE, NIVELACIÓN Y COMPACTACIÓN CON EQUIPO LIVIANO M2 6.42 14.91 95.72 0.00 0.00% 6.42 95.72 100.00% 6.42 95.72 100.00% 0.00 0.00 0.00%
2.01.05 ACARREO DE MATERIAL < 50 M M3 4.27 68.72 293.43 0.00 0.00% 4.27 293.43 100.00% 4.27 293.43 100.00% 0.00 0.00 0.00%
2.01.06 CARGUIO DE MATERIAL CON EQUIPO (P/ELIMINACION) M3 4.27 4.66 19.90 0.00 0.00% 4.27 19.90 100.00% 4.27 19.90 100.00% 0.00 0.00 0.00%
2.01.07 TRANSPORTE DE MATERIAL > 5M3 M3/KM 34.18 1.40 47.85 0.00 0.00% 34.18 47.85 100.00% 34.18 47.85 100.00% 0.00 0.00 0.00%
2.02 RELLENOS
2.02.01 ZARANDEO DE MATERIAL PROPIO (MANUAL) M3 1.20 46.70 56.04 0.00 0.00% 1.20 56.04 100.00% 1.20 56.04 100.00% 0.00 0.00 0.00%
2.02.02 CARGUIO DE MATERIAL CON EQUIPO (MAT. DE PRESTAMO) M3 1.20 4.66 5.59 0.00 0.00% 1.20 5.59 100.00% 1.20 5.59 100.00% 0.00 0.00 0.00%
2.02.03 TRANSPORTE DE MATERIAL > 5M3 M3/KM 9.60 1.40 13.44 0.00 0.00% 9.60 13.44 100.00% 9.60 13.44 100.00% 0.00 0.00 0.00%
2.02.04 RELLENO COMPACTADO CON EQUIPO LIVIANO M3 1.00 76.90 76.90 0.00 0.00% 1.00 76.90 100.00% 1.00 76.90 100.00% 0.00 0.00 0.00%
2.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA M2 28.40 74.29 2,109.84 0.00 0.00% 28.40 2,109.84 100.00% 28.40 2,109.84 100.00% 0.00 0.00 0.00%
2.03.03 ACERO DE REFUERZO F´Y 4200 KG/CM2 KG 395.20 2.75 1,086.80 0.00 0.00% 326.80 898.70 83.00% 326.80 898.70 83.00% 68.40 188.10 17.00%
2.03.04 CONCRETO F´C =280 KG/CM2 CEMENTO TIPO V – PREMEZCLADO M3 1.00 66.14 66.14 0.00 0.00% 1.00 66.14 100.00% 1.00 66.14 100.00% 0.00 0.00 0.00%
2.03.05 CONCRETO F´C =280 KG/CM2 CEMENTO TIPO V – MANUAL M3 4.16 231.86 964.54 0.00 0.00% 3.44 797.60 83.00% 3.44 797.60 83.00% 0.72 166.94 17.00%
2.03.06 ACABADO ENLUCIDO DE LOSA M2 1.00 18.85 18.85 0.00 0.00% 1.00 18.85 100.00% 1.00 18.85 100.00% 0.00 0.00 0.00%
2.04.02 MONTAJE DE ESTRUCTURA LIGERA H<= 6 MTS KG 446.46 4.18 1,866.20 0.00 0.00% 165.60 692.21 37.00% 165.60 692.21 37.00% 280.86 1,173.99 63.00%
2.04.03 PINTURA EN ESTRUCTURA METÁLICA M2 12.70 17.41 221.11 0.00 0.00% 12.70 221.11 100.00% 12.70 221.11 100.00% 0.00 0.00 0.00%
3.02 EXCAVACIONES
3.02.01 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA SUELTA H ≤ 1.2M M3 0.97 220.60 213.98 0.00 0.00% 0.97 213.98 100.00% 0.97 213.98 100.00% 0.00 0.00 0.00%
3.02.02 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA FIJA H ≤ 1.2M M3 0.24 327.91 78.70 0.00 0.00% 0.24 78.70 100.00% 0.24 78.70 100.00% 0.00 0.00 0.00%
3.02.03 REFINE, NIVELACIÓN Y COMPACTACIÓN CON EQUIPO LIVIANO M2 2.03 14.91 30.27 0.00 0.00% 2.03 30.27 100.00% 2.03 30.27 100.00% 0.00 0.00 0.00%
3.02.04 ACARREO DE MATERIAL < 50 M M3 1.45 68.72 99.64 0.00 0.00% 1.45 99.64 100.00% 1.45 99.64 100.00% 0.00 0.00 0.00%
3.02.05 CARGUIO DE MATERIAL CON EQUIPO (P/ELIMINACION) M3 1.45 4.66 6.76 0.00 0.00% 1.45 6.76 100.00% 1.45 6.76 100.00% 0.00 0.00 0.00%
3.02.06 TRANSPORTE DE MATERIAL > 5M3 M3/KM 11.62 1.40 16.27 0.00 0.00% 11.62 16.27 100.00% 11.62 16.27 100.00% 0.00 0.00 0.00%
3.03 RELLENOS
3.03.01 PREPARACIÓN DE MATERIAL DE RELLENO M3 1.00 5.65 5.65 0.00 0.00% 1.00 5.65 100.00% 1.00 5.65 100.00% 0.00 0.00 0.00%
3.03.02 CARGUIO DE MATERIAL CON EQUIPO (MAT. DE PRESTAMO) M3 1.00 4.66 4.66 0.00 0.00% 1.00 4.66 100.00% 1.00 4.66 100.00% 0.00 0.00 0.00%
3.03.03 TRANSPORTE DE MATERIAL > 5M3 M3/KM 1.00 1.40 1.40 0.00 0.00% 1.00 1.40 100.00% 1.00 1.40 100.00% 0.00 0.00 0.00%
3.03.04 RELLENO COMPACTADO CON EQUIPO LIVIANO M3 1.00 76.90 76.90 0.00 0.00% 1.00 76.90 100.00% 1.00 76.90 100.00% 0.00 0.00 0.00%
3.04.02 ACERO DE REFUERZO F´Y 4200 KG/CM2 KG 115.90 2.75 318.73 0.00 0.00% 115.90 318.73 100.00% 115.90 318.73 100.00% 0.00 0.00 0.00%
3.04.04 CONCRETO F´C =280 KG/CM2 CEMENTO TIPO V – MANUAL M3 1.22 231.86 282.87 0.00 0.00% 1.22 282.87 100.00% 1.22 282.87 100.00% 0.00 0.00 0.00%
B. MAYORES METRADOS_IO-805
PARTIDA DESCRIPCION P.U TOTAL VALORIZACION ANTERIOR Nº VALORIZACION ACTUAL Nº 02 TOTAL ACUMULADO SALDO POR VALORIZAR
UND METRADO
S/. S/. METRADO VALORIZ.S/. % METRADO VALORIZ.S/. % METRADO VALORIZ.S/. % METRADO VALORIZ.S/. %
SUB TOTAL COSTO DIRECTO PARTIDAS 62,480.16 26,189.81 35,393.45 61,583.26 15,539.08
1.00 SUB TOTAL VALORIZACION SIN IGV 108,361.25 50129.05 46.00% 56,880.92 52.49% 107,009.97 98.75% 15539.08 14.34%
GESTION DE COMPRA
PORCENTAJE GESTION DE COMPRA 10.0% GLB 1.00 10% 1,871.12 0.08 156.00 8.00% 0.25 475.41 25.00% 0.33 631.41 33.00% 0.67 1239.71 66.25%
PORCENTAJE GESTION DE COMPRA 10.0% GLB 1.00 10% 1,362.02 0.00 0.00 0.00% 0.17 230.43 17.00% 0.17 230.43 17.00% 0.83 1131.59 83.08%
1.00 MATERIALES
1.01 ACERO CORRUGADO fy = 4200 kg/cm2 GRADO 60 KG 1852.00 3.60 6,667.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,852.00 6,667.20 100.00%
1.02 PIEDRA CHANCADA 3/4" M3 15.00 68.00 1,020.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 1,020.00 100.00%
1.03 GRAVA D < 1" M3 1.00 68.00 68.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 68.00 100.00%
1.04 ARENA GRUESA M3 10.00 58.00 580.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 580.00 100.00%
1.05 MATERIAL DE PRESTAMO M3 50.00 60.00 3,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 50.00 3,000.00 100.00%
1.06 CEMENTO PORTLAND TIPO V BOL 191.00 24.00 4,584.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 191.00 4,584.00 100.00%
1.07 CONCRETO PREMEZCLADO F'C= 280 kg/cm2 - CEMENTO V M3 1.00 680.00 680.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 680.00 100.00%
1.08 CURADOR DE CONCRETO GLN 6.00 32.00 192.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 192.00 100.00%
1.09 MASCARILLA N95 (COV.) UND 40.00 30.00 1,200.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 40.00 1,200.00 100.00%
1.10 PROTECTOR FACIAL (C0V) UND 6.00 60.00 360.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 360.00 100.00%
1.11 TRAJE TIVEK UND 12.00 30.00 360.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 360.00 100.00%
A. MATERIALES COMPRADOS
1.00 MATERIALES
1.01 PIEDRA CHANCADA 3/4 M3 15.00 59.00 885.00 15.00 885.00 100.00% 0.00 0.00 0.00% 15.00 885.00 100.00% 0.00 0.00 0.00%
1.02 ARENA GRUESA M3 15.00 45.00 675.00 15.00 675.00 100.00% 0.00 0.00 0.00% 15.00 675.00 100.00% 0.00 0.00 0.00%
BARRA DE CONSTRUCCION 1/2 X 9M. VAR 199.00 23.89 4,754.11 0.00 0.00 0.00% 199.00 4,754.11 100.00% 199.00 4,754.11 100.00% 0.00 0.00 0.00%
1.00 MATERIALES
1.01 ACERO CORRUGADO fy = 4200 kg/cm2 GRADO 60 KG 542.00 3.60 1,951.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 542.00 1,951.20 100.00%
1.02 FABRICACIÓN DE BARANDAS METALICAS SEGUN PLANOS KG 448.00 17.00 7,616.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 448.00 7,616.00 100.00%
1.03 PIEDRA CHANCADA 3/4" M3 6.00 68.00 408.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 408.00 100.00%
1.04 ARENA GRUESA M3 4.00 58.00 232.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 232.00 100.00%
1.05 MATERIAL DE PRESTAMO M3 10.00 SMCV SMCV 0.00 SMCV 0.00% 0.00 SMCV SMCV 0.00 SMCV SMCV 10.00 SMCV SMCV
1.06 CEMENTO TIPO V BOL 69.00 24.00 1,656.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 69.00 1,656.00 100.00%
1.07 CONCRETO PREMEZCLADO F'C= 280 kg/cm2 - CEMENTO V M3 1.05 660.00 693.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.05 693.00 100.00%
1.08 PINTURA ESMALTE EPOXICA GAL 0.50 320.00 160.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.50 160.00 100.00%
1.09 SOLVENTE PARA PINTURA EPOXICA GAL 0.50 320.00 160.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.50 160.00 100.00%
1.10 PINTURA ANTICORROSIVA EPOXICA GAL 0.50 320.00 160.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.50 160.00 100.00%
1.11 ALCOHOL, DESINFECTANTES, OTROS (COV) GLB 1.00 80.00 80.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 80.00 100.00%
1.12 MASCARILLA N95 (COV.) UND 12.00 29.00 348.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 348.00 100.00%
1.13 PROTECTOR FACIAL (C0V) UND 3.00 52.00 156.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 156.00 100.00%
B. MATERIALES COMPRADOS
1.00 MATERIALES
1.01 BARRA DE CONSTRUCCION 1/2 X 9M. VAR 61.00 28.22 1,721.66 0.00 0.00 0.00% 61.00 1,721.66 100.00% 61.00 1,721.66 100.00% 0.00 0.00 0.00%
1.02 MASCARILLA KN95 UND 50.00 10.10 505.00 0.00 0.00 0.00% 50.00 505.00 100.00% 50.00 505.00 100.00% 0.00 0.00 0.00%
1.03 VISOR DE POLICARBONATO CON FILO DE ALUMINIO- N/U 10.00 6.78 67.80 0.00 0.00 0.00% 10.00 67.80 100.00% 10.00 67.80 100.00% 0.00 0.00 0.00%
1.04 LEJIA (HIPOCLORITO DE SODIO 5.0%) X GALON - - - DARYZA UND 1.00 9.84 9.84 0.00 0.00 0.00% 1.00 9.84 100.00% 1.00 9.84 100.00% 0.00 0.00 0.00%
SUB TOTAL COSTO DIRECTO MATERIALES 32,331.40 1,560.00 7,058.41 8,618.41 0.00
2.00 TOTAL VALORIZACION MATERIALES SIN IGV 35,564.54 1,716.00 4.83% 7,764.25 21.83% 9,480.25 26.66% 0.00 0.00%
GESTION DE SUBCONTRATO
PORCENTAJE GESTION DE COMPRA 15.0% GLB 1.00 15% 54.00 1.00 54.00 100.00% 0.00 0.00 0.00% 1.00 54.00 100.00% 0.00 0.00 0.00%
1.00 SUBCONTRATO
1.01 ENSAYOS DE CONCRETO DIA 6.00 60.00 360.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.00 360.00 100.00%
A. SUBCONTRATO EJECUTADO
1.00 SUBCONTRATO
1.01 ENSAYOS DE CONCRETO DIA 6.00 60.00 360.00 6.00 360.00 100.00% 0.00 0.00% 6.00 360.00 100.00% 0.00 0.00 0.00%
SUB TOTAL COSTO DIRECTO SUBCONTRATO 360.00 360.00 0.00 360.00 0.00
3.00 TOTAL VALORIZACION SCONTRATO SIN IGV 414.00 414.00 100.00% 0.00 0.00% 414.00 100.00% 0.00 0.00%
TOTAL VALORIZACION (1+2) SIN IGV 144,339.79 52,259.05 36.21% 64,645.17 44.79% 116,904.22 80.99% 0.00 0.00%
PLANILLA DE METRADOS
MINE MAINTENANCE FACILITIES RELOCATION PHASE II AND III
CANT. DE MEDIDAS
ITEM DESCRIPCION UND Parcial TOTAL VAL 01 VAL 02
ELEMENTOS L A H
1.03.02 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA SUELTA H ≤ 1.2M m3 9.30 9.30 0.00
EXCAVACION PARA CAJA 1.00 6.20 2.80 1.00 17.36
UÑAS 1.00 16.40 0.30 0.20 0.98
DREN 1.00 1.00 0.50 0.50 0.25
TOTAL EXCAVACION 18.59
TOTAL VOLUMEN PARTIDA 18.59 50% 9.30
1.03.03 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA FIJA H ≤ 1.2M m3 18.59 50% 9.30 9.30 9.30 0.00
1.03.04 REFINE, NIVELACIÓN Y COMPACTACIÓN CON EQUIPO LIVIANO m2 1.00 5.80 2.40 13.92 13.92 13.92 0.00
1.03.05 CARGUIO DE MATERIAL CON EQUIPO (P/ELIMINACION) m3 1.20 18.60 22.32 22.32 22.32 0.00
1.03.06 TRANSPORTE DE MATERIAL > 5M3 m3/km 1.20 18.60 8.00 km 178.56 178.56 178.56 0.00
1.04 RELLENOS
1.04.01 PREPARACIÓN DE MATERIAL DE RELLENO m3 5.62 5.62 0.00
TOTAL EXCAVACION PARA CAJA 1.00 18.60 18.60
CAJA DE CONCRETO -1.00 5.80 2.40 1.00 -13.92
4.68
PREPARACION 1.20 4.68 5.62
1.04.02 CARGUIO DE MATERIAL CON EQUIPO (MAT. DE PRESTAMO) m3 5.62 5.62 5.62 5.62 0.00
1.04.03 TRANSPORTE DE MATERIAL > 5M3 m3/km 5.62 10.00 km 56.20 56.20 56.20 0.00
1.04.04 RELLENO COMPACTADO CON EQUIPO LIVIANO m3 4.68 4.68 4.68 4.68 0.00
1.04.05 RELLENO CON GRAVA m3 1.00 1.00 0.50 0.50 0.25 0.25 0.25 0.00
1.05 CONCRETO ARMADO
1.05.01 CONCRETO F´C =100 KG/CM2 CEMENTO TIPO V – MANUAL m3 1.00 5.80 2.40 0.10 1.39 1.39 1.39 0.00
1.05.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 41.84 41.84 0.00
INTERIOR 2.00 5.40 1.05 11.34
2.00 2.00 1.05 4.20
EXTERIOR 2.00 5.80 1.25 14.50
2.00 2.40 1.25 6.00
BASES DE APOYO 4.00 1.60 0.125 0.80
OTROS 5.00
1.05.04 CONCRETO F´C =280 KG/CM2 CEMENTO TIPO V – PREMEZCLADO m3 0.00 0.00 0.00 0.00 0.00
1.05.05 CONCRETO F´C =280 KG/CM2 CEMENTO TIPO V – MANUAL m3 7.33 7.16 0.17
LOSA DE PISO 1.00 5.80 2.40 0.20 2.78
MUROS 2.00 5.80 0.20 1.05 2.44
2.00 2.40 0.20 1.05 1.01
BASES 4.00 0.40 0.40 0.15 0.10
OTROS 1.00 1.00
1.05.06 ACABADO ENLUCIDO DE LOSA m2 1.00 5.40 2.00 10.80 10.80 10.80 0.00
2.00 BUZON COLECTOR
2.01 TRABAJOS PRELIMINARES 0.00
2.01.01 BARANDA DE MADERA DE SEGURIDAD (TRANSITO PERSONAL SMCV) m 1.00 12.00 12.00 12.00 12.00 0.00
2.01.02 PROTECCION DE ELEMENTOS CIRCUNDANTES (TUBERIA) est 1.00 1.00 1.00 1.00 0.00
2.01.03 APUNTALAMIENTO DE ESTRUCTURAS (TUBERIAS, DRENAJES) est 1.00 1.00 1.00 1.00 0.00
2.01.04 VIGIA DE ESPACIOS CONFINADOS dia 1.00 4.00 4.00 4.00 0.00 4.00
2.02 DEMOLICIONES
2.02.01 DEMOLICIÓN DE PISOS DE CONCRETO ARMADO - MANUAL m3 0.00 0.00 0.00
BUZON EXI MUROS 0.00 2.00 1.00 0.20 1.10 0.00
0.00 2.00 0.80 0.20 1.10 0.00
PISOS 0.00 1.00 0.80 0.20 0.00
2.02.02 CARGUIO DE MATERIAL MANUAL m3 0.00 0.00 0.00 0.00 0.00 0.00
2.02.03 TRANSPORTE DE MATERIAL < 5M3 viaje/km 0.00 0.00 8.00 km 0.00 0.00 0.00 0.00
2.03 EXCAVACIONES
2.03.01 EXCAVACIÓN MANUAL DE ZANJAS EN MATERIAL COMPACTADO H > 1.8M m3 1.00 2.00 1.50 2.75 8.25 8.25 8.25 0.00
DESCUBRIMIENTO DE TUBERIA
2.03.02 EXCAVACIÓN MANUAL DE ZANJAS EN MATERIAL COMPACTADO H ≤ 1.2M m3 30.96 30.96 0.00 30.96
EXCAVACION INICIAL PARA TUBERIA 14.18 60% 8.51
EXCAVACION FINAL PARA TUBERIA 11.23 60% 6.74
EXCAVACION FINAL PARA TUBERIA 26.18 60% 15.71
2.03.03 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA SUELTA H ≤ 1.2M m3 0% 0.00 0.00 0.00 20.63 20.63 0.00 20.63
EXCAVACION INICIAL PARA TUBERIA 14.18 40% 5.67
EXCAVACION FINAL PARA TUBERIA 11.23 40% 4.49
EXCAVACION FINAL PARA TUBERIA 26.18 40% 10.47
2.03.04 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA FIJA H ≤ 1.2M m3 0.00 0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2.03.05 REFINE, NIVELACIÓN Y COMPACTACIÓN CON EQUIPO LIVIANO m2 0.00 3.00 1.00 0.00 0.00 0.00 0.00
2.03.06 ACARREO DE MATERIAL < 50 M m3 0.00 0.00 0.00 0.00 0.00
2.03.07 CARGUIO DE MATERIAL CON EQUIPO (P/ELIMINACION) m3 0.00 51.59 0.00 0.00 0.00 0.00
2.03.08 TRANSPORTE DE MATERIAL > 5M3 m3/km 0.00 51.59 8.00 km 0.00 0.00 0.00 0.00
2.04 RELLENOS
2.04.01 PREPARACIÓN DE MATERIAL DE RELLENO m3 66.41 0.00 66.41
TOTAL EXCAVACION CAJA 1.00 51.59 51.59
CAJA 1.00 3.00 1.00 1.25 3.75
55.34
TOTAL PREPARACION 1.20 55.34 66.41
2.04.02 CARGUIO DE MATERIAL CON EQUIPO (MAT. DE PRESTAMO) m3 1.20 55.34 66.41 66.41 0.00 66.41
2.04.03 TRANSPORTE DE MATERIAL > 5M3 m3/km 1.20 55.34 8.00 km 531.26 531.26 0.00 531.26
2.04.04 RELLENO COMPACTADO CON EQUIPO LIVIANO m3 55.34 55.34 55.34 0.00 55.34
2.05 CONCRETO ARMADO
2.05.01 CONCRETO F´C =100 KG/CM2 CEMENTO TIPO V – MANUAL m3 1.00 3.00 1.00 0.10 0.30 0.30 0.30 0.00
2.05.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 21.76 13.96 7.80
MUROS INTERIORES 2.00 2.60 1.20 6.24
2.00 0.70 1.20 1.68
MUROS EXTERIORES 2.00 3.00 1.40 8.40
2.00 1.00 1.40 2.80
BASE DE APOYO 1.00 1.60 0.40 0.64
OTROS 2.00
2.05.04 CONCRETO F´C =280 KG/CM2 CEMENTO TIPO V – PREMEZCLADO m3 0.50 0.50 0.50 0.50 0.00
2.05.05 CONCRETO F´C =280 KG/CM2 CEMENTO TIPO V – MANUAL m3 2.58 1.20 1.38
LOSA DE PISO 1.00 3.00 1.00 0.20 0.60
MUROS 2.00 3.00 0.20 1.20 1.44
2.00 1.00 0.20 1.20 0.48
BASE DE APOYO 1.00 0.40 0.40 0.40 0.06
OTROS 0.00
2.05.06 ACABADO ENLUCIDO DE LOSA m2 1.00 3.00 1.00 3.00 3.00 3.00 0.00
2.01.01 EXCAVACIÓN MANUAL DE ZANJAS EN MATERIAL COMPACTADO H ≤ 1.2M m3 3.56 0.33 1.17 1.17 0.00 1.17
2.01.02 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA SUELTA H ≤ 1.2M m3 3.56 0.33 1.17 1.17 0.00 1.17
2.01.03 EXCAVACIÓN MANUAL DE ZANJAS EN ROCA FIJA H ≤ 1.2M m3 3.56 0.33 1.17 1.17 0.00 1.17
2.01.04 REFINE, NIVELACIÓN Y COMPACTACIÓN CON EQUIPO LIVIANO m2 6.42 0.00 6.42
BASE DE APOYO PARA TUBERIAS 1.00 2.40 0.60 1.44
MUROS DE CONCRETO 2.00 1.50 0.70 2.10
BASES PARA BARANDA 9.00 2.00 0.40 0.40 2.88
2.01.05 ACARREO DE MATERIAL < 50 M m3 1.20 3.56 4.27 4.27 0.00 4.27
2.01.06 CARGUIO DE MATERIAL CON EQUIPO (P/ELIMINACION) m3 1.20 3.56 4.27 4.27 0.00 4.27
2.01.07 TRANSPORTE DE MATERIAL > 5M3 m3/km 1.20 3.56 8.00 km 34.18 34.18 0.00 34.18
2.02 RELLENOS
2.02.01 ZARANDEO DE MATERIAL PROPIO (MANUAL) m3 1.20 1.00 1.20 1.20 0.00 1.20
2.02.02 CARGUIO DE MATERIAL CON EQUIPO (MAT. DE PRESTAMO) m3 1.20 1.00 1.20 1.20 0.00 1.20
2.02.03 TRANSPORTE DE MATERIAL > 5M3 m3/km 1.20 1.00 8.00 km 9.60 9.60 0.00 9.60
2.02.04 RELLENO COMPACTADO CON EQUIPO LIVIANO m3 1.00 1.00 1.00 0.00 1.00
2.03 CONCRETO ARMADO
2.03.01 CONCRETO F´C =100 KG/CM2 CEMENTO TIPO V – MANUAL m3 0.64 0.00 0.64
BASE DE APOYO PARA TUBERIAS 1.00 2.40 0.60 0.10 0.14
MUROS DE CONCRETO 2.00 1.50 0.70 0.10 0.21
BASES PARA BARANDA 9.00 2.00 0.40 0.40 0.10 0.29
2.03.03 ACERO DE REFUERZO F´Y 4200 KG/CM2 kg 3.44 m3 95.00 kg/m3 326.80 326.80 0.00 326.80
2.03.04 CONCRETO F´C =280 KG/CM2 CEMENTO TIPO V – PREMEZCLADO m3 1.00 1.00 1.00 0.00 1.00
2.03.05 CONCRETO F´C =280 KG/CM2 CEMENTO TIPO V – MANUAL m3 3.44 0.00 3.44
BASE DE APOYO PARA TUBERIAS 1.00 2.40 0.60 0.60 0.86
MUROS DE cimentacion 2.00 1.50 0.70 0.60 1.26
pantalla 2.00 1.50 0.20 1.00 0.60
BASES PARA BARANDA 9.00 0.40 0.40 0.50 0.72
2.03.06 ACABADO ENLUCIDO DE LOSA m2 1.00 1.00 1.00 0.00 1.00
2.04 ESTRUCTURA METALICA
2.04.01 FABRICACIÓN DE ESTRUCTURA LIGERA - BARANDAS kg 165.60 0.00 165.60
barandas lat horiz 1 1/2" 2.00 2.00 12.00 kg/m 48.00
vert 1 1/2" 4.00 2.00 0.60 kg/m 4.80
1 1/2" 6.00 2.00 1.10 kg/m 13.20
barandas coshoriz 1 1/2" 2.00 3.20 kg/m 6.40
vert 1 1/2" 2.00 0.60 kg/m 1.20
1 1/2" 2.00 1.10 kg/m 2.20
Acceso horiz 1 1/2" 2.00 2.00 2.00 kg/m 8.00
vert 1 1/2" 2.00 2.00 0.60 kg/m 2.40
1 1/2" 2.00 2.00 1.10 kg/m 4.40
Planchas metalicas y otros 75.00
2.04.02 MONTAJE DE ESTRUCTURA LIGERA H<= 6 MTS kg 165.60 165.60 165.60 0.00 165.60
2.04.03 PINTURA EN ESTRUCTURA METÁLICA m2 90.60 0.00 90.60
barandas lat horiz 1 1/2" 2.00 2.00 12.00 48.00
vert 1 1/2" 4.00 2.00 0.60 4.80
1 1/2" 6.00 2.00 1.10 13.20
barandas coshoriz 1 1/2" 2.00 3.20 6.40
vert 1 1/2" 2.00 0.60 1.20
1 1/2" 2.00 1.10 2.20
Acceso horiz 1 1/2" 2.00 2.00 2.00 8.00
vert 1 1/2" 2.00 2.00 0.60 2.40
1 1/2" 2.00 2.00 1.10 4.40