METRADO DE ESPECIALIDADES

PROYECTO: EDIFICIO MULTIFAMILIAR


COMPONENTE: METRADO ESTRUCTURAS

PARTIDA DESCRIPCION UND METRADO PU PARCIAL TOTAL OBSERVACION


OE.2 ESTRUCTURAS.
OE.2.3 OBRAS DE CONCRETO ARMADO
OE.2.3.1 CIMIENTOS REFORZADOS
OE.2.3.1.1 PARA EL CONCRETO m3 14.77
OE.2.3.1.2 PARA EL ENCOFRADO Y DESENCOFRADO m2 18.88
OE.2.3.1.3 PARA LA ARMADURA DE ACERO Kg 492.56
OE.2.3.2 ZAPATAS
OE.2.3.2.1 PARA EL CONCRETO m3 40.80
OE.2.3.2.2 PARA EL ENCOFRADO Y DESENCOFRADO m2 38.62
OE.2.3.2.3 PARA LA ARMADURA DE ACERO. Kg 2,306.56
OE.2.3.3 VIGAS DE CIMENTACIÓN
OE.2.3.3.1 PARA EL CONCRETO m3 0.73
OE.2.3.3.2 PARA EL ENCOFRADO Y DESENCOFRADO m2 4.86
OE.2.3.3.3 PARA LA ARMADURA DE ACERO Kg 177.23
OE.2.3.4 LOSAS DE CIMENTACIÓN
OE.2.3.4.1 PARA EL CONCRETO m3 54.32
OE.2.3.4.2 PARA EL ENCOFRADO Y DESENCOFRADO m2 27.09
OE.2.3.4.3 PARA LA ARMADURA DE ACERO. Kg 438.47
OE.2.3.5 SOBRECIMIENTOS REFORZADOS
OE.2.3.5.1 PARA EL CONCRETO m3 -
OE.2.3.5.2 PARA EL ENCOFRADO Y DESENCOFRADO m2 -
OE.2.3.5.3 PARA LA ARMADURA DE ACERO. Kg -
OE.2.3.14 PILOTES
OE.2.3.14.1 PARA LOS PILOTES
METRADO DE ESPECIALIDADES
PROYECTO: EDIFICIO MULTIFAMILIAR
COMPONENTE: METRADO ESTRUCTURAS

PARTIDA DESCRIPCION UND LARGO ANCHO ALTURA N° DE PARCIAL TOTAL OBSERVACION


VECES
OE.2.3 OBRAS DE CONCRETO ARMADO
OE.2.3.1 CIMIENTOS REFORZADOS
OE.2.3.1.1 PARA EL CONCRETO m3 14.77
Eje X20 m3 15.75 0.70 0.60 1.00 6.62
Eje X1 / Y1-Y2 m3 3.75 0.70 0.60 1.00 1.58
Eje X1 / Y2-Y11 m3 8.65 1.00 0.60 1.00 5.19
Eje X1 / Y11-Y13 m3 3.32 0.70 0.60 1.00 1.39
m3 - - 0.60 1.00 -
m3 - - 0.60 1.00 -
OE.2.3.1.2 PARA EL ENCOFRADO Y DESENCOFRADO m2 18.88
Eje X20 m2 15.75 0.60 1.00 9.45
Eje X1 / Y1-Y2 m2 3.75 0.60 1.00 2.25
Eje X1 / Y2-Y11 m2 8.65 0.60 1.00 5.19
Eje X1 / Y11-Y13 m2 3.32 0.60 1.00 1.99
m2 - 0.60 1.00 -
m2 - 0.60 1.00 -
OE.2.3.1.3 PARA LA ARMADURA DE ACERO Kg 492.56 ver detalle Acero
OE.2.3.2 ZAPATAS
OE.2.3.2.1 PARA EL CONCRETO m3 40.80
Zapata P3 m3 3.20 5.40 0.70 1.00 12.10
Zapata P4 m3 3.00 4.40 0.70 1.00 9.24
Zapata Z1 m3 10.40 3.12 0.60 1.00 19.47

m3 - - - 1.00 -
OE.2.3.2.2 PARA EL ENCOFRADO Y DESENCOFRADO m2 38.62
Zapata P3 m2 17.20 0.70 1.00 12.04
Zapata P4 m2 14.80 0.70 1.00 10.36
Zapata Z1 m2 27.04 0.60 1.00 16.22
m2 - - 1.00 -
OE.2.3.2.3 PARA LA ARMADURA DE ACERO. Kg 2,306.56 ver detalle Acero
OE.2.3.3 VIGAS DE CIMENTACIÓN
OE.2.3.3.1 PARA EL CONCRETO m3 0.73
VC / Eje Y4 m3 0.68 0.30 0.50 1.00 0.10
VC / Eje Y12 m3 1.58 0.30 0.50 1.00 0.24
VC / Eje X17-X19 m3 2.60 0.30 0.50 1.00 0.39
m3 - - - 1.00 -
OE.2.3.3.2 PARA EL ENCOFRADO Y DESENCOFRADO m2 4.86
VC / Eje Y4 m2 0.68 0.50 2.00 0.68
VC / Eje Y12 m2 1.58 0.50 2.00 1.58
VC / Eje X17-X19 m2 2.60 0.50 2.00 2.60
m2 - - 2.00 -
OE.2.3.3.3 PARA LA ARMADURA DE ACERO Kg 177.23 ver detalle Acero
OE.2.3.4 LOSAS DE CIMENTACIÓN
OE.2.3.4.1 PARA EL CONCRETO m3 54.32
Cisterna de consumo domestico y ACI m3 Area = 90.54 0.60 1.00 54.32
OE.2.3.4.2 PARA EL ENCOFRADO Y DESENCOFRADO m2 27.09
Cisterna de consumo domestico y ACI m2 Perimetro = 45.15 0.60 1.00 27.09
OE.2.3.4.3 PARA LA ARMADURA DE ACERO. Kg 438.47 ver detalle Acero
OE.2.3.5 SOBRECIMIENTOS REFORZADOS
OE.2.3.5.1 PARA EL CONCRETO m3
OE.2.3.5.2 PARA EL ENCOFRADO Y DESENCOFRADO m2
OE.2.3.5.3 PARA LA ARMADURA DE ACERO. Kg
OE.2.3.14 PILOTES
OE.2.3.14.1 PARA LOS PILOTES
N° de PESO (Kg.)
Long. Long.
PARTIDA DESCRIPCION Pieza (m)
N° Piezas Repeticio
Total(m) 1/4" 3/8" 1/2" 5/8" 3/4" 1" PARCIAL (Kg.) TOTAL (Kg.)
nes
0.25 0.56 0.99 1.55 2.24 3.97
OE.2.3.1.3 CIMIENTO CORRIDO, ACERO FY=4200 KG/CM2 492.56
Eje X20
Acero longitudinal 5/8" @ 0.25
15.70 5/8" 17.90 4 1 71.60 --- --- --- 111.12 --- --- 111.12

Acero transversal 5/8" @ 0.20


0.70 5/8" 0.92 64 1 58.88 --- --- --- 91.38 --- --- 91.38
Eje X1 / Y1-Y2
Acero longitudinal 5/8" @ 0.25
3.75 5/8" 4.27 4 1 17.08 --- --- --- 26.51 --- --- 26.51

Acero transversal 5/8" @ 0.20


0.70 5/8" 0.92 16 1 14.72 --- --- --- 22.85 --- --- 22.85
Eje X1 / Y2-Y11
Acero longitudinal 5/8" @ 0.20
8.65 5/8" 9.89 5 1 49.45 --- --- --- 76.75 --- --- 76.75

Acero transversal 5/8" @ 0.15


1.00 5/8" 1.22 59 1 71.98 --- --- --- 111.71 --- --- 111.71
Eje X1 / Y11-Y13
Acero longitudinal 5/8" @ 0.25
3.32 5/8" 3.84 4 1 15.36 --- --- --- 23.84 --- --- 23.84

Acero transversal 5/8" @ 0.20


0.70 5/8" 1.22 15 1 18.30 --- --- --- 28.40 --- --- 28.40

OE.2.3.2.3 ZAPATAS, PARA LA ARMADURA DE ACERO 2,306.56


Zapata P3
Fierro longitudinal
3.20 3/4" 3.12 37 1 115.44 --- --- --- --- 258.01 --- 258.01
Æ 3/4" @ 0.15
Fierro transversal
5.40 3/4" 4.60 23 1 105.80 --- --- --- --- 236.46 --- 236.46
Zapata P4
Fierro longitudinal
N° de PESO (Kg.)
Long. Long.
PARTIDA DESCRIPCION Pieza (m)
N° Piezas Repeticio
Total(m) 1/4" 3/8" 1/2" 5/8" 3/4" 1" PARCIAL (Kg.) TOTAL (Kg.)
nes
0.25 0.56 0.99 1.55 2.24 3.97
3.00 3/4" 2.92 31 1 90.52 --- --- --- --- 202.31 --- 202.31
Æ 3/4" @ 0.15
Fierro transversal
4.40 3/4" 3.60 21 1 75.60 --- --- --- --- 168.97 --- 168.97
Zapata Z1 --- --- --- --- --- --- ---
Fierro longitudinal --- --- --- --- --- --- ---
10.40 5/8" 10.32 22.00 2.00 454.08 --- --- --- 704.73 --- --- 704.73
Æ 3/4" @ 0.15 doble capa --- --- --- --- --- --- ---
Fierro transversal --- --- --- --- --- --- ---
3.12 5/8" 3.34 71.00 2.00 474.28 --- --- --- 736.08 --- --- 736.08
Æ 3/4" @ 0.15 doble capa --- --- --- --- --- --- ---
--- --- --- --- --- --- ---
--- --- --- --- --- --- ---

VIGAS DE CONEXIÓN 177.23


VC / Eje Y4
Acero Longitudinal Longitud de viga = 3.32
Superior 3/4" 3.68 4 1 14.72 --- --- --- --- 32.90 --- 32.90

Inferior 3/4" 3.68 3 1 11.04 --- --- --- --- 24.67 --- 24.67
Fierro para estribos
3/8" 1.48 28 1 41.44 --- 23.21 --- --- --- --- 23.21
0.42

0.22
VC / Eje Y12
Acero Longitudinal Longitud de viga = 4.11
Superior 3/4" 4.47 4 1 17.88 --- --- --- --- 39.96 --- 39.96

Inferior 3/4" 4.47 3 1 13.41 --- --- --- --- 29.97 --- 29.97
Fierro para estribos
3/8" 1.48 32 1 47.36 --- 26.52 --- --- --- --- 26.52
0.42

0.22

LOSA DE CIMENTACION 438.47


Cisterna de consumo domestico y ACI
N° de PESO (Kg.)
Long. Long.
PARTIDA DESCRIPCION Pieza (m)
N° Piezas Repeticio
Total(m) 1/4" 3/8" 1/2" 5/8" 3/4" 1" PARCIAL (Kg.) TOTAL (Kg.)
nes
0.25 0.56 0.99 1.55 2.24 3.97
Fierro longitudinal
6.95 1/2" 6.87 22 1 151.14 --- --- 150.23 --- --- --- 150.23
Æ 1/2" @ 0.25
Fierro transversal
5.10 1/2" 5.02 15 1 75.30 --- --- 74.85 --- --- --- 74.85
Fierro longitudinal
6.50 1/2" 6.50 22 1 143.00 --- --- 142.14 --- --- --- 142.14
Æ 1/2" @ 0.25
Fierro transversal
5.20 1/2" 5.12 14 1 71.68 --- --- 71.25 --- --- --- 71.25

TOTALES (Kilos) 0.00 49.73 438.47 1,440.81 993.26 0.00 2,922.27


TOTALES (Varillas) 0.00 10.00 49.00 103.00 49.00 0.00 211.00