HOJA DE METRADOS

OBRA : CONSTRUCCION DE HOSPEDAJE


LUGAR :
ESPECIALIDAD : ARQUITECTURA
FECHA :
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

09.00.00 MUROS Y TABIQUES DE ALBAÑILERÍA


09.01.00 MUROS DE LADRILLO CORRIENTE DE ARCILLA
09.01.02 Muro de Soga con Ladrillo Corriente de 24 x 12 x 6 m2
PRIMER PISO
EJE A-A 1 2.85 1.80 5.13
EJE B-B 1 7.78 2.80 21.78
EJE D-D 1 3.72 2.80 10.42
EJE E-E 1 2.82 1.80 5.08
EJE 1-1 1 13.91 2.80 38.95
EJE 2-2 ENTRE EJE B Y EJE D 1 9.35 2.80 26.18
EJE 4-4 ENETRE EJE B Y EJE C 1 4.68 2.80 13.10
EJE 5-5 1 11.26 2.80 31.53
HABITACION 1 -2-3-4 4 11.75 2.80 131.60
COCINA 2 7.15 2.80 40.04
HABITACION 5 1 13.06 2.80 36.57
HABITACION 6 1 9.21 2.80 25.79

SEDUNDO PISO
EJE A-A 1 2.85 2.80 7.98
EJE B-B 1 7.78 2.80 21.78
EJE D-D 1 3.72 2.80 10.42
EJE E-E 1 2.82 2.80 7.90
EJE 1-1 1 13.91 2.80 38.95
EJE 2-2 ENTRE EJE B Y EJE D 1 9.35 2.80 26.18
EJE 4-4 ENETRE EJE B Y EJE C 1 4.68 2.80 13.10
EJE 5-5 1 11.26 2.80 31.53
HABITACION 1 -2-3-4 4 11.75 2.80 131.60
HABITACION 5 1 13.06 2.80 36.57
HABITACION 6 1 9.21 2.80 25.79
HABITACION 7 1 11.34 2.80 31.75
HABITACION 8 1 11.34 2.80 31.75
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

Total de Muro para ladrillo Corriente m2 801.46

10.00.00 REVOQUES, ENLUCIDOS Y MOLDURAS


10.01.00 TARRAJEO PRIMARIO O RAYADO CON MORTERO 1:5 m2
Primer Piso
HABITACION 1 -2-3-4 4 11.75 2.80 131.60
COCINA 2 7.15 2.80 40.04
HABITACION 5 1 13.06 2.80 36.57
HABITACION 6 1 9.21 2.80 25.79

Segundo Piso 1 23.98 2.50 59.95


HABITACION 1 -2-3-4 4 11.75 2.80 131.60
HABITACION 5 1 13.06 2.80 36.57
HABITACION 6 1 9.21 2.80 25.79
HABITACION 7 1 11.34 2.80 31.75
HABITACION 8 1 11.34 2.80 31.75

Total de area a tarrajear m2 551.41

10.02.00 TARRAJEO EN INTERIORES CON MORTERO 1:5 m2


PIMER PISO
EJE A-A 1 2.85 1.80 5.13
EJE B-B 1 7.78 2.80 21.78
EJE D-D 1 3.72 2.80 10.42
EJE E-E 1 2.82 1.80 5.08
EJE 1-1 1 13.91 2.80 38.95
EJE 2-2 ENTRE EJE B Y EJE D 1 9.35 2.80 26.18
EJE 4-4 ENETRE EJE B Y EJE C 1 4.68 2.80 13.10
EJE 5-5 1 11.26 2.80 31.53
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

Segundo Piso
EJE A-A 1 2.85 2.80 7.98
EJE B-B 1 7.78 2.80 21.78
EJE D-D 1 3.72 2.80 10.42
EJE E-E 1 2.82 2.80 7.90
EJE 1-1 1 13.91 2.80 38.95
EJE 2-2 ENTRE EJE B Y EJE D 1 9.35 2.80 26.18
EJE 4-4 ENETRE EJE B Y EJE C 1 4.68 2.80 13.10
EJE 5-5 1 11.26 2.80 31.53
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

Total Areá de Tarrajeo en Interiores con mortero 1:4 m2 310.00

10.03.00 TARRAJEO EN EXTERIORES MEZCLA 1 : 5 m2


PRIMER PISO
EJE 1-1 1 13.91 2.80 38.95
EJE 5-5 1 13.91 2.80 38.95
EJE A-A 1 2.85 2.80 7.98
EJE E-E 1 2.85 2.80 7.98
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

SEGUNDO PISO
EJE 1-1 1 13.91 2.80 38.95
EJE 5-5 1 13.91 2.80 38.95
EJE A-A 1 2.85 2.80 7.98
EJE E-E 1 2.85 2.80 7.98

Total tarrajeo en exterior con mezcla 1:5 m2 187.71

10.05.00 TARRAJEO DE COLUMNAS m2


10.05.01 Tarrajeo de Superficie, Mezcla 1:5
Primer Piso

COLUMNAS 35*35 24 1.40 2.80 94.08


CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

Segundo Piso

COLUMNAS 35*35 24 1.40 2.80 94.08

Total Tarrajeo en Columnas con mezcla 1:4 m2 188.16

10.05.02 Vestiduras de Arista m2


Primer Piso

COLUMNAS 35*35 24 0.20 2.80 13.44


CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

Segundo Piso

COLUMNAS 35*35 24 0.20 2.80 13.44

Total de Vestiduras de arista m2 26.88

CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

10.06.00 TARRAJEO DE VIGAS


10.06.01 Tarrajeo de Superficies con mezcla 1:5 m2
PRIMER PISO
EJE A-A ENTRE EJE 1 -EJE 2 (VP-100) 1 5.06 0.1 0.51
EJE A-A ENTRE EJE 2 -EJE 3 (VP-101) 1 4.06 0.1 0.41
EJE A-A ENTRE EJE 3 -EJE 4 (VP-101) 1 4.06 0.1 0.41
EJE A-A ENTRE EJE 4 -EJE 5 (VP-100) 1 5.07 0.1 0.51

EJE B-B ENTRE EJE 1 -EJE 2 (VP-100) 1 5.06 0.1 0.51


EJE B-B ENTRE EJE 2 -EJE 3 (VP-101) 1 4.06 0.1 0.41
EJE B-B ENTRE EJE 3 -EJE 4 (VP-101) 1 4.06 0.1 0.41
EJE B-B ENTRE EJE 4 -EJE 5 (VP-100) 1 5.07 0.1 0.51

EJE C-C ENTRE EJE 1 -EJE 2 (VP-100) 1 5.06 0.1 0.51


EJE C-C ENTRE EJE 4 -EJE 5 (VP-100) 1 5.07 0.1 0.51

EJE D-D ENTRE EJE 1 -EJE 2 (VP-100) 1 5.06 0.1 0.51


EJE D-D ENTRE EJE 2 -EJE 3 (VP-101) 1 4.06 0.1 0.41
EJE D-D ENTRE EJE 3 -EJE 4 (VP-101) 1 4.06 0.1 0.41
EJE D-D ENTRE EJE 4 -EJE 5 (VP-100) 1 5.07 0.1 0.51

EJE E-E ENTRE EJE 1 -EJE 2 (VP-100) 1 5.06 0.1 0.51


EJE E-E ENTRE EJE 2 -EJE 3 (VP-101) 1 4.06 0.1 0.41
EJE E-E ENTRE EJE 3 -EJE 4 (VP-101) 1 4.06 0.1 0.41
EJE E-E ENTRE EJE 4 -EJE 5 (VP-100) 1 5.07 0.1 0.51

EJE 1-1 ENTRE EJE A -EJE B (VS-100) 1 4.96 0.05 0.25


EJE 1-1 ENTRE EJE B -EJE C (VS-100) 1 4.15 0.05 0.21
EJE 1-1 ENTRE EJE C -EJE D (VS-100) 1 4.15 0.05 0.21
EJE 1-1 ENTRE EJE D -EJE E (VS-100) 1 4.96 0.05 0.25

EJE 2-2 ENTRE EJE A -EJE B (VS-100) 1 4.96 0.05 0.25


EJE 2-2 ENTRE EJE B -EJE C (VS-100) 1 4.15 0.05 0.21
EJE 2-2 ENTRE EJE C -EJE D (VS-100) 1 4.15 0.05 0.21
EJE 2-2 ENTRE EJE D -EJE E (VS-100) 1 4.96 0.05 0.25

EJE 3-3 ENTRE EJE A -EJE B (VS-100) 1 4.96 0.05 0.25


EJE 3-3 ENTRE EJE D -EJE E (VS-100) 1 4.96 0.05 0.25

EJE 4-4 ENTRE EJE A -EJE B (VS-100) 1 4.96 0.05 0.25


EJE 4-4 ENTRE EJE B -EJE C (VS-100) 1 4.15 0.05 0.21
EJE 4-4 ENTRE EJE C -EJE D (VS-100) 1 4.15 0.05 0.21
EJE 4-4 ENTRE EJE D -EJE E (VS-100) 1 4.96 0.05 0.25

EJE 5-5 ENTRE EJE A -EJE B (VS-100) 1 4.96 0.05 0.25


EJE 5-5 ENTRE EJE B -EJE C (VS-100) 1 4.15 0.05 0.21
EJE 5-5 ENTRE EJE C -EJE D (VS-100) 1 4.15 0.05 0.21
EJE 5-5 ENTRE EJE D -EJE E (VS-100) 1 4.96 0.05 0.25

SEGUNDO PISO
EJE A-A ENTRE EJE 1 -EJE 2 (VP-100) 1 5.06 0.1 0.51
EJE A-A ENTRE EJE 2 -EJE 3 (VP-101) 1 4.06 0.1 0.41
EJE A-A ENTRE EJE 3 -EJE 4 (VP-101) 1 4.06 0.1 0.41
EJE A-A ENTRE EJE 4 -EJE 5 (VP-100) 1 5.07 0.1 0.51

EJE B-B ENTRE EJE 1 -EJE 2 (VP-100) 1 5.06 0.1 0.51


EJE B-B ENTRE EJE 2 -EJE 3 (VP-101) 1 4.06 0.1 0.41
EJE B-B ENTRE EJE 3 -EJE 4 (VP-101) 1 4.06 0.1 0.41
EJE B-B ENTRE EJE 4 -EJE 5 (VP-100) 1 5.07 0.1 0.51

EJE C-C ENTRE EJE 1 -EJE 2 (VP-100) 1 5.06 0.1 0.51


EJE C-C ENTRE EJE 4 -EJE 5 (VP-100) 1 5.07 0.1 0.51

EJE D-D ENTRE EJE 1 -EJE 2 (VP-100) 1 5.06 0.1 0.51


EJE D-D ENTRE EJE 2 -EJE 3 (VP-101) 1 4.06 0.1 0.41
EJE D-D ENTRE EJE 3 -EJE 4 (VP-101) 1 4.06 0.1 0.41
EJE D-D ENTRE EJE 4 -EJE 5 (VP-100) 1 5.07 0.1 0.51
EJE E-E ENTRE EJE 1 -EJE 2 (VP-100) 1 5.06 0.1 0.51
EJE E-E ENTRE EJE 2 -EJE 3 (VP-101) 1 4.06 0.1 0.41
EJE E-E ENTRE EJE 3 -EJE 4 (VP-101) 1 4.06 0.1 0.41
EJE E-E ENTRE EJE 4 -EJE 5 (VP-100) 1 5.07 0.1 0.51

EJE 1-1 ENTRE EJE A -EJE B (VS-100) 1 4.96 0.05 0.25


EJE 1-1 ENTRE EJE B -EJE C (VS-100) 1 4.15 0.05 0.21
EJE 1-1 ENTRE EJE C -EJE D (VS-100) 1 4.15 0.05 0.21
EJE 1-1 ENTRE EJE D -EJE E (VS-100) 1 4.96 0.05 0.25

EJE 2-2 ENTRE EJE A -EJE B (VS-100) 1 4.96 0.05 0.25


EJE 2-2 ENTRE EJE B -EJE C (VS-100) 1 4.15 0.05 0.21
EJE 2-2 ENTRE EJE C -EJE D (VS-100) 1 4.15 0.05 0.21
EJE 2-2 ENTRE EJE D -EJE E (VS-100) 1 4.96 0.05 0.25

EJE 3-3 ENTRE EJE A -EJE B (VS-100) 1 4.96 0.05 0.25


EJE 3-3 ENTRE EJE D -EJE E (VS-100) 1 4.96 0.05 0.25

EJE 4-4 ENTRE EJE A -EJE B (VS-100) 1 4.96 0.05 0.25


EJE 4-4 ENTRE EJE B -EJE C (VS-100) 1 4.15 0.05 0.21
EJE 4-4 ENTRE EJE C -EJE D (VS-100) 1 4.15 0.05 0.21
EJE 4-4 ENTRE EJE D -EJE E (VS-100) 1 4.96 0.05 0.25

EJE 5-5 ENTRE EJE A -EJE B (VS-100) 1 4.96 0.05 0.25


EJE 5-5 ENTRE EJE B -EJE C (VS-100) 1 4.15 0.05 0.21
EJE 5-5 ENTRE EJE C -EJE D (VS-100) 1 4.15 0.05 0.21
EJE 5-5 ENTRE EJE D -EJE E (VS-100) 1 4.96 0.05 0.25

Total de tarrajeo en vigas con mezcla 1:4 m2 24.91

10.06.02 Vestiduras de Arista m2


PRIMER PISO
EJE A-A ENTRE EJE 1 -EJE 2 (VP-100) 2 5.06 0.7 7.08
EJE A-A ENTRE EJE 2 -EJE 3 (VP-101) 2 4.06 0.7 5.68
EJE A-A ENTRE EJE 3 -EJE 4 (VP-101) 2 4.06 0.7 5.68
EJE A-A ENTRE EJE 4 -EJE 5 (VP-100) 2 5.07 0.7 7.10

EJE B-B ENTRE EJE 1 -EJE 2 (VP-100) 2 5.06 0.7 7.08


EJE B-B ENTRE EJE 2 -EJE 3 (VP-101) 2 4.06 0.7 5.68
EJE B-B ENTRE EJE 3 -EJE 4 (VP-101) 2 4.06 0.7 5.68
EJE B-B ENTRE EJE 4 -EJE 5 (VP-100) 2 5.07 0.7 7.10
EJE C-C ENTRE EJE 1 -EJE 2 (VP-100) 2 5.06 0.7 7.08
EJE C-C ENTRE EJE 4 -EJE 5 (VP-100) 2 5.07 0.7 7.10

EJE D-D ENTRE EJE 1 -EJE 2 (VP-100) 2 5.06 0.70 7.08


EJE D-D ENTRE EJE 2 -EJE 3 (VP-101) 2 4.06 0.70 5.68
EJE D-D ENTRE EJE 3 -EJE 4 (VP-101) 2 4.06 0.70 5.68
EJE D-D ENTRE EJE 4 -EJE 5 (VP-100) 2 5.07 0.70 7.10

EJE E-E ENTRE EJE 1 -EJE 2 (VP-100) 2 5.06 0.70 7.08


EJE E-E ENTRE EJE 2 -EJE 3 (VP-101) 2 4.06 0.70 5.68
EJE E-E ENTRE EJE 3 -EJE 4 (VP-101) 2 4.06 0.70 5.68
EJE E-E ENTRE EJE 4 -EJE 5 (VP-100) 2 5.07 0.70 7.10

EJE 1-1 ENTRE EJE A -EJE B (VS-100) 2 4.96 0.70 6.94


EJE 1-1 ENTRE EJE B -EJE C (VS-100) 2 4.15 0.70 5.81
EJE 1-1 ENTRE EJE C -EJE D (VS-100) 2 4.15 0.70 5.81
EJE 1-1 ENTRE EJE D -EJE E (VS-100) 2 4.96 0.70 6.94

EJE 2-2 ENTRE EJE A -EJE B (VS-100) 2 4.96 0.70 6.94


EJE 2-2 ENTRE EJE B -EJE C (VS-100) 2 4.15 0.70 5.81
EJE 2-2 ENTRE EJE C -EJE D (VS-100) 2 4.15 0.70 5.81
EJE 2-2 ENTRE EJE D -EJE E (VS-100) 2 4.96 0.70 6.94

EJE 3-3 ENTRE EJE A -EJE B (VS-100) 2 4.96 0.70 6.94


EJE 3-3 ENTRE EJE D -EJE E (VS-100) 2 4.96 0.70 6.94

EJE 4-4 ENTRE EJE A -EJE B (VS-100) 2 4.96 0.70 6.94


EJE 4-4 ENTRE EJE B -EJE C (VS-100) 2 4.15 0.70 5.81
EJE 4-4 ENTRE EJE C -EJE D (VS-100) 2 4.15 0.70 5.81
EJE 4-4 ENTRE EJE D -EJE E (VS-100) 2 4.96 0.70 6.94

EJE 5-5 ENTRE EJE A -EJE B (VS-100) 2 4.96 0.70 6.94


EJE 5-5 ENTRE EJE B -EJE C (VS-100) 2 4.15 0.70 5.81
EJE 5-5 ENTRE EJE C -EJE D (VS-100) 2 4.15 0.70 5.81
EJE 5-5 ENTRE EJE D -EJE E (VS-100) 2 4.96 0.70 6.94

SEGUNDO PISO
EJE A-A ENTRE EJE 1 -EJE 2 (VP-100) 2 5.06 0.7 7.08
EJE A-A ENTRE EJE 2 -EJE 3 (VP-101) 2 4.06 0.7 5.68
EJE A-A ENTRE EJE 3 -EJE 4 (VP-101) 2 4.06 0.7 5.68
EJE A-A ENTRE EJE 4 -EJE 5 (VP-100) 2 5.07 0.7 7.10

EJE B-B ENTRE EJE 1 -EJE 2 (VP-100) 2 5.06 0.7 7.08


EJE B-B ENTRE EJE 2 -EJE 3 (VP-101) 2 4.06 0.7 5.68
EJE B-B ENTRE EJE 3 -EJE 4 (VP-101) 2 4.06 0.7 5.68
EJE B-B ENTRE EJE 4 -EJE 5 (VP-100) 2 5.07 0.7 7.10

EJE C-C ENTRE EJE 1 -EJE 2 (VP-100) 2 5.06 0.7 7.08


EJE C-C ENTRE EJE 4 -EJE 5 (VP-100) 2 5.07 0.7 7.10

EJE D-D ENTRE EJE 1 -EJE 2 (VP-100) 2 5.06 0.70 7.08


EJE D-D ENTRE EJE 2 -EJE 3 (VP-101) 2 4.06 0.70 5.68
EJE D-D ENTRE EJE 3 -EJE 4 (VP-101) 2 4.06 0.70 5.68
EJE D-D ENTRE EJE 4 -EJE 5 (VP-100) 2 5.07 0.70 7.10

EJE E-E ENTRE EJE 1 -EJE 2 (VP-100) 2 5.06 0.70 7.08


EJE E-E ENTRE EJE 2 -EJE 3 (VP-101) 2 4.06 0.70 5.68
EJE E-E ENTRE EJE 3 -EJE 4 (VP-101) 2 4.06 0.70 5.68
EJE E-E ENTRE EJE 4 -EJE 5 (VP-100) 2 5.07 0.70 7.10

EJE 1-1 ENTRE EJE A -EJE B (VS-100) 2 4.96 0.70 6.94


EJE 1-1 ENTRE EJE B -EJE C (VS-100) 2 4.15 0.70 5.81
EJE 1-1 ENTRE EJE C -EJE D (VS-100) 2 4.15 0.70 5.81
EJE 1-1 ENTRE EJE D -EJE E (VS-100) 2 4.96 0.70 6.94

EJE 2-2 ENTRE EJE A -EJE B (VS-100) 2 4.96 0.70 6.94


EJE 2-2 ENTRE EJE B -EJE C (VS-100) 2 4.15 0.70 5.81
EJE 2-2 ENTRE EJE C -EJE D (VS-100) 2 4.15 0.70 5.81
EJE 2-2 ENTRE EJE D -EJE E (VS-100) 2 4.96 0.70 6.94

EJE 3-3 ENTRE EJE A -EJE B (VS-100) 2 4.96 0.70 6.94


EJE 3-3 ENTRE EJE D -EJE E (VS-100) 2 4.96 0.70 6.94

EJE 4-4 ENTRE EJE A -EJE B (VS-100) 2 4.96 0.70 6.94


EJE 4-4 ENTRE EJE B -EJE C (VS-100) 2 4.15 0.70 5.81
EJE 4-4 ENTRE EJE C -EJE D (VS-100) 2 4.15 0.70 5.81
EJE 4-4 ENTRE EJE D -EJE E (VS-100) 2 4.96 0.70 6.94

EJE 5-5 ENTRE EJE A -EJE B (VS-100) 2 4.96 0.70 6.94


EJE 5-5 ENTRE EJE B -EJE C (VS-100) 2 4.15 0.70 5.81
EJE 5-5 ENTRE EJE C -EJE D (VS-100) 2 4.15 0.70 5.81
EJE 5-5 ENTRE EJE D -EJE E (VS-100) 2 4.96 0.70 6.94

Total de vestiduras en aristas m 464.60


CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

10.11.00 VESTIDURAS DE DERRAMES m


10.11.01 Vestiduras de Puertas 1 1 2.10 2.10
1 1 2.10 2.10
1 5 2.10 10.50
2 2 2.10 8.40
1 1 2.10 2.10
2 4 0.70 5.60
1 1 3.20 3.20
Total vestiduras de puertas m 34.00

10.11.02 Vestiduras de Ventanas m 2 1 1.60 3.20


2 1 1.60 3.20
2 1 0.50 1.00
2 1 1.70 3.40
2 1 1.70 3.40
2 1 1.40 2.80
2 1 2.80 5.60
2 1 2.50 5.00
2 1 1.10 2.20

Total de Vestiduras de Ventanas m 36.40

10.11.03 Vestiduras de Mampara m 2 2.40 4.80


2 2.40 4.80
2 2.72 5.44
Total de Vestiduras de Mampara m 15.04
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

11.00.00 CIELORASOS
11.03.00 CIELORASOS CON MEZCLA DE CEMENTO ARENA m2
PRIMER NIVEL
EJE 1-1,EJE 2-2 ENTRE EJE A-EJE B 1 4.34 4.15 18.01
EJE 2-2,EJE 3-3 ENTRE EJE A-EJE B 1 4.16 4.15 17.26
EJE 3-3,EJE 4-4 ENTRE EJE A-EJE B 1 4.16 4.15 17.26
EJE 4-4,EJE 5-5 ENTRE EJE A-EJE B 1 4.34 4.15 18.01

EJE 1-1,EJE 2-2 ENTRE EJE B-EJE C 1 4.34 4.15 18.01


EJE 4-4,EJE 5-5 ENTRE EJE B-EJE C 1 4.34 4.15 18.01

EJE 1-1,EJE 2-2 ENTRE EJE C-EJE D 1 4.34 4.15 18.01


EJE 4-4,EJE 5-5 ENTRE EJE C-EJE D 1 4.34 4.15 18.01

EJE 1-1,EJE 2-2 ENTRE EJE D-EJE E 1 4.34 4.15 18.01


EJE 2-2,EJE 3-3 ENTRE EJE D-EJE E 1 4.16 4.15 17.26
EJE 3-3,EJE 4-4 ENTRE EJE D-EJE E 1 4.16 4.15 17.26
EJE 4-4,EJE 5-5 ENTRE EJE D-EJE E 1 4.34 4.15 18.01

SEGUNDO NIVEL
EJE 1-1,EJE 2-2 ENTRE EJE A-EJE B 1 4.34 4.15 18.01
EJE 2-2,EJE 3-3 ENTRE EJE A-EJE B 1 4.16 4.15 17.26
EJE 3-3,EJE 4-4 ENTRE EJE A-EJE B 1 4.16 4.15 17.26
EJE 4-4,EJE 5-5 ENTRE EJE A-EJE B 1 4.34 4.15 18.01

EJE 1-1,EJE 2-2 ENTRE EJE B-EJE C 1 4.34 4.15 18.01


EJE 4-4,EJE 5-5 ENTRE EJE B-EJE C 1 4.34 4.15 18.01

EJE 1-1,EJE 2-2 ENTRE EJE C-EJE D 1 4.34 4.15 18.01


EJE 4-4,EJE 5-5 ENTRE EJE C-EJE D 1 4.34 4.15 18.01

EJE 1-1,EJE 2-2 ENTRE EJE D-EJE E 1 4.34 4.15 18.01


EJE 2-2,EJE 3-3 ENTRE EJE D-EJE E 1 4.16 4.15 17.26
EJE 3-3,EJE 4-4 ENTRE EJE D-EJE E 1 4.16 4.15 17.26
EJE 4-4,EJE 5-5 ENTRE EJE D-EJE E 1 4.34 4.15 18.01

Total Cielorraso con mezcla de cemento arena m2 426.29


CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

11.04.00 VESTIDURAS EN FONDO DE ESCALERAS


11.04.01 Vestidura de Superficies m2
Primer Nivel
tramo1(rampa) 1 0.90 1.00 0.90
arranque desde nivel de piso a la rampa 1 1.00 0.15 0.15
tramo2
descanso 1 1.30 1.05 1.37
tramo3
descanso 1 1.30 1.00 1.30
Segundo Nivel a la Azotea
tramo1(rampa) 1 0.97 1.00 0.97
tramo2
descanso 1 1.30 1.05 1.37
tramo3
descanso 1 1.30 1.00 1.30
Caras laterales de escalera 1 1.60 1.60
Total de Vestiduras de Superficies m2 8.95

12.00.00 PISOS Y PAVIMENTOS


12.01.00 CONTRAPISOS de 5cm (Primer Nivel) m2 126.28 126.28
PISOS PORCELANATO
12.01.01 PRIMER NIVEL
HABITACION 1-2-3-4 4 AREA= 20.34 81.36
COCINA 1 AREA= 16.48 16.48
HABITACION 5 1 AREA= 37.88 37.88
HABITACION 6 1 AREA= 35.51 35.51
SALA 1 AREA= 83.11 83.11
AREA LIBRE 1 AREA= 73.31 73.31
PASADIZOS 1 AREA= 51.63 51.63
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

SEGUNDO NIVEL
HABITACION 1-2-3-4 4 AREA= 20.34 81.36
COCINA 1 AREA= 16.48 16.48
HABITACION 5 1 AREA= 37.88 37.88
HABITACION 6 1 AREA= 35.51 35.51
SALA 1 AREA= 83.11 83.11
PASADIZOS 1 AREA= 51.63 51.63

m2 685.24

CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

18.00.00 CARPINTERIA DE MADERA


18.01.00 PUERTAS
18.01.01 Puertas contraplacadas de 35 mm, de espesor marco 2"x3" m2 2 2.10 0.90 3.78
5 2.10 0.70 7.35
6 2.10 1.00 12.60
Total de madera para puertas m2 23.73
18.02.00 VENTANAS
18.02.01 Ventanas con Hojas m2 1 1.58 3.15 4.98
1 1.58 2.40 3.79
1 0.50 0.80 0.40
1 1.70 2.30 3.91
3 0.50 1.20 1.80
1 0.40 1.20 0.48
1 1.70 2.46 4.18
2 1.70 2.45 8.33
1 1.70 1.10 1.87
1 1.40 1.10 1.54
Total de madera para ventanas m2 31.28

18.03.00 MAMPARAS m2 1 2.45 3.33 8.16


1 2.40 3.33 7.99
1 2.72 3.20 8.70
Total de madera para mamparas m2 24.85

19.00.00 CARPINTERIA METÁLICA Y HERRERIA


19.01.00 VENTANAS DE FIERRO
19.01.01 Ventanas de fierro con seguridad m2 1 2.70 2.35 6.35 6.35

20.00.00 CERRAJERIA
20.01.00 BISAGRAS
20.01.01 Bisagras para puertas, de color negro Pz 39 39.00 39.00
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

20.02.00 CERRADURAS
20.02.03 Cerraduras para puertas interiores de llave interior Pz 17 17.00 17.00

20.03.00 SISTEMAS O MECANISMOS


20.03.01 Para puertas corredizas Juego 1 1.00 1.00
20.03.02 Para puertas levadizas Juego 1 1.00 1.00

20.04.00 ACCESORIOS DE CIERRE


20.04.01 Picaportes de empotrar Pz 4 4.00 4.00
20.04.04 Cerrojos Pz 3 3.00 3.00

21.00.00 VIDRIOS, CRISTALES Y SIMILARES


21.01.00 VIDRIOS Y CRISTALES P2
21.01.02 Vidrios y Cristales Semidobles P2 1 1.60 2.85 4.56
1 1.60 2.40 3.84
1 0.50 0.50 0.25
1 1.70 2.30 3.91
3 0.50 1.20 1.80
1 0.40 1.20 0.48
1 1.70 2.46 4.18
2 1.70 2.45 8.33
1 1.70 1.10 1.87
1 1.40 1.10 1.54
Area en m2 para vidrios y cristales semidobles 30.76
Area en p2 para vidrios y cristales semidobles x 10,76 P2 331.00

22.00.00 PINTURA
22.01.00 DE CIELORRASOS, MUROS
22.01.01 Cielorrasos al temple m2 2 165.23 330.46 330.46
22.01.05 Muros interiores al temple 2 manos m2 2 565.69 565.69 565.69
22.01.09 Muros Exteriores al temple 2 manos m2 2 47.25 47.25 47.25
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

24.00.00 APARATOS SANITARIOS Y ACCESORIOS


24.01.00 INODOROS
24.01.01 Inodoro Montecarlo Blanco Comercial Pz 4 4 4

24.02.00 LAVATORIOS
24.02.01 Lavatorio Sonnet 19 x 10 Blanco comercial Pz 5 5 5

24.06.00 LAVADEROS DE COCINA


24.06.01 Lavadero de Platos Pz 1 1 1

24.09.00 DUCHAS
24.09.01 Duchas Cromadas de cabeza giratoria Pz 4 4 4

24.11.00 JABONERAS
24.11.01 Jaboneras de losa blanca simple de 15x15 Pz 4 4 4

24.12.00 TOALLERAS
24.12.01 Toallera con soporte de Losa y barra plástica Pz 4 4 4

24.13.00 PAPELERAS
24.13.01 Papelera de Losa de Color de 15x15 Pz 4 4 4

24.20.00 COLOCACIÓN DE APARATOS SANITARIOS Pz 9 9 9