HOJA DE METRADOS

OBRA : CONSTRUCCION DE
LUGAR :
ESPECIALIDAD : ARQUITECTURA
FECHA :
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

09.00.00 MUROS Y TABIQUES DE ALBAÑILERÍA


09.01.00 MUROS DE LADRILLO CORRIENTE DE ARCILLA
09.01.02 Muro de Soga con Ladrillo Corriente de 24 x 12 x 6 m2
PRIMER PISO
EJE A-A 1 14.13 2.75 38.86
1 4.37 2.75 12.02
1 4.78 2.75 13.15
1 4.78 2.75 13.15
EJEC-C 1 15.75 2.50 39.38
EJE D´-D´ 1 33.71 2.50 84.28
EJE D-D 1 12.26 2.50 30.65
EJE E´-E´ 1 11.78 2.50 29.45
EJE F-F 1 84.53 2.75 232.46
EJE F´-F´ 1 22.20 2.50 55.50
EJE 1-1 1 14.68 2.50 36.70
EJE 2-2 1 9.15 2.40 21.96
EJE 3-3 1 2.17 2.40 5.21
EJE 4-4 1 15.23 2.50 38.08
EJE 9-9 1 15.43 2.50 38.58
EJE 10-10 1 13.76 2.50 34.40
EJE 11´-11´ 1 20.61 2.50 51.53
EJE 12-12 1 6.85 2.50 17.13
EJE 13-13 1 3.91 2.50 9.78
EJE 14-14 1 13.71 2.50 34.28
EJE 15-15 1 13.73 2.70 37.07

SEDUNDO PISO
EJE A-A 1 4.88 1.15 5.61
EJEB-B 1 1.20 1.15 1.38
1 1.20 1.15 1.38
1 1.20 1.15 1.38
1 1.20 1.15 1.38
1 1.20 1.15 1.38
1 1.20 1.15 1.38
1 1.20 1.15 1.38
EJEC-C 1 42.50 2.70 114.75
1 11.20 2.50 28.00
Eje D-D 1 2.45 0.90 2.21
EJE F-F 1 68.39 2.70 184.65
EJE 1-1 1 25.00 2.50 62.50
Eje 2-2 1 20.38 2.50 50.95
EJE 3-3 1 13.55 2.50 33.88
Eje 4-4 1 9.93 2.50 24.83
EJE 5-5 1 4.20 2.50 10.50
EJE 6-6 1 1.20 1.15 1.38
EJE 9-9 1 17.18 2.50 42.95
EJE 10-10 1 17.42 2.50 43.55
EJE 11´-11´ 1 26.22 2.60 68.17
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

Total de Muro para ladrillo Corriente m2 1557.14

10.00.00 REVOQUES, ENLUCIDOS Y MOLDURAS


10.01.00 TARRAJEO PRIMARIO O RAYADO CON MORTERO 1:5 m2
Servicio Higienico Primer Piso 1 12.44 2.50 31.10
1 14.89 2.50 37.23
1 13.85 2.50 34.63
1 33.78 2.50 84.45
1 24.35 2.50 60.88
1 43.00 2.50 107.50

Servicio Higienico Segundo Piso 1 23.98 2.50 59.95


1 42.36 2.50 105.90
1 20.73 2.50 51.83
1 14.35 2.50 35.88

Servicio Higienico Azotea 1 6.90 2.60 17.94


1 1.20 2.10 2.52
Total de area a tarrajear m2 629.79

10.02.00 TARRAJEO EN INTERIORES CON MORTERO 1:5 m2


EJE A-A 1 14.13 2.75 38.86
1 4.37 2.75 12.02
1 4.78 2.75 13.15
1 4.78 2.75 13.15
EJEC-C 1 15.75 2.50 39.38
EJE D´-D´ 1 33.71 2.50 84.28

CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

EJE D-D 1 12.26 2.50 30.65


EJE E´-E´ 1 11.78 2.50 29.45
EJE F-F 1 84.53 2.75 232.46
EJE F´-F´ 1 22.20 2.50 55.50
EJE 1-1 1 14.68 2.50 36.70
EJE 2-2 1 9.15 2.40 21.96
EJE 3-3 1 2.17 2.40 5.21
EJE 4-4 1 15.23 2.50 38.08
EJE 9-9 1 15.43 2.50 38.58
EJE 10-10 1 13.76 2.50 34.40
EJE 11´-11´ 1 20.61 2.50 51.53
EJE 12-12 1 6.85 2.50 17.13
EJE 13-13 1 3.91 2.50 9.78
EJE 14-14 1 13.71 2.50 34.28
EJE 15-15 1 13.73 2.70 37.07

Segundo Piso
EJE A-A 1 4.88 1.15 5.61
EJEB-B 1 1.20 1.15 1.38
1 1.20 1.15 1.38
1 1.20 1.15 1.38
1 1.20 1.15 1.38
1 1.20 1.15 1.38
1 1.20 1.15 1.38
1 1.20 1.15 1.38
EJEC-C 1 42.50 2.70 114.75
1 11.20 2.50 28.00
Eje D-D 1 2.45 0.90 2.21
EJE F-F 1 68.39 2.70 184.65
EJE 1-1 1 25.00 2.50 62.50
Eje 2-2 1 20.38 2.50 50.95
EJE 3-3 1 13.55 2.50 33.88
Eje 4-4 1 9.93 2.50 24.83
EJE 5-5 1 4.20 2.50 10.50
EJE 6-6 1 1.20 1.15 1.38
EJE 9-9 1 17.18 2.50 42.95
EJE 10-10 1 17.42 2.50 43.55
EJE 11´-11´ 1 26.22 2.60 68.17
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

Total Areá de Tarrajeo en Interiores con mortero 1:4 m2 1518.29

10.03.00 TARRAJEO EN EXTERIORES MEZCLA 1 : 5 m2


PRIMER PISO
ENTRE, EJE 1-1 1 21.17 1.20 25.40
ENTRE, EJE 11-11 1 26.22 2.70 70.79
EJE A-A 1 4.48 2.70 12.10
ENTRE A´-A´ 1 21.60 1.20 25.92
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

SEGUNDO PISO
PRIMER PISO
ENTRE, EJE 1-1 1 21.17 1.20 25.40
ENTRE, EJE 11-11 1 26.22 2.70 70.79
EJE A-A 1 4.48 2.70 12.10
ENTRE A´-A´ 1 21.60 1.20 25.92

Total tarrajeo en exterior con mezcla 1:5 m2 268.43

10.05.00 TARRAJEO DE COLUMNAS m2


10.05.01 Tarrajeo de Superficie, Mezcla 1:5
Primer Piso

COLUMNAS DIAMTRO DE 60 CM 38 1.88 3.50 250.04


CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

Segundo Piso

COLUMNAS DIAMTRO DE 60 CM 38 1.88 3.50 250.04

Total Tarrajeo en Columnas con mezcla 1:4 m2 500.08

10.05.02 Vestiduras de Arista m


Primer Piso

COLUMNAS DIAMTRO DE 60 CM 38 0.40 3.50 53.20


CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

Segundo Piso

COLUMNAS DIAMTRO DE 60 CM 38 0.40 3.50 53.20

Total de Vestiduras de arista m 106.40

CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

10.06.00 TARRAJEO DE VIGAS


10.06.01 Tarrajeo de Superficies con mezcla 1:5 m2
PRIMER PISO
EJE A-A ENTRE EJE 1 -EJE 2 (VP-206) 1 9.37 0.25 2.34
EJE A-A ENTRE EJE 2 -EJE 3 (VP-207) 1 9.60 0.25 2.40
EJE A-A ENTRE EJE 3 -EJE 4 (VP-208) 1 7.55 0.25 1.89
EJE A-A ENTRE EJE 4 -EJE 5 (VP-209) 1 3.60 0.25 0.90
EJE A-A ENTRE EJE 5 -EJE 6 (VP-210) 1 7.55 0.25 1.89
EJE A-A ENTRE EJE 6-EJE 10 (VP-211) 1 4.95 0.25 1.24

EJE B-B ENTRE EJE 1 -EJE 2 (VP-206) 1 9.37 0.25 2.34


EJE B-B ENTRE EJE 2 -EJE 3 (VP-207) 1 9.60 0.25 2.40
EJE B-B ENTRE EJE 3 -EJE 4 (VP-208) 1 7.55 0.25 1.89

EJE 1-1 VP (VP-204) 1 15.13 0.25 3.78


EJE 2-2 VP (VP-204) 1 20.75 0.25 5.19
EJE 3-3 VP (VP-204) 1 20.75 0.25 5.19
EJE 4-4 1 3.45 0.25 0.86
EJE 5-5 1 3.45 0.25 0.86
EJE 6-6 1 3.45 0.25 0.86
EJE 7-7 1 3.45 0.25 0.86
EJE 10-10 (VP-200) 1 19.21 0.25 4.80
EJE 11-11 (VP-200) 1 17.10 0.25 4.28
EJE 12-12 (VP-200) 1 14.75 0.25 3.69
EJE 13-13 (VP-200) 1 11.93 0.25 2.98
EJE 14-14 (VP-200) 1 9.12 0.25 2.28
EJE 15-15 (VS-202) 1 6.33 0.25 1.58
EJE 1-1 ENTRE EJE A- EJE B (VS-210) 1 10.84 0.25 2.71
EJE 1-1 ENTRE EJE B- EJE C (VS-209) 1 9.46 0.25 2.37

EJE 2-2 ENTRE EJE A- EJE B (VS-210) 1 10.84 0.25 2.71


EJE 2-2 ENTRE EJE B- EJE C (VS-209) 1 7.96 0.25 1.99

EJE 3-3 ENTRE EJE A- EJE B (VS-210) 1 10.84 0.25 2.71


EJE 3-3 ENTRE EJE B- EJE C (VS-209) 1 3.26 0.25 0.82

EJE 4-4 ENTRE EJE A- EJE B (VS-210) 1 10.84 0.25 2.71


EJE 5-5 ENTRE EJE A- EJE B (VS-210) 1 8.93 0.25 2.23
VS-206 3 5.85 0.25 4.39
VS -207 3 4.97 0.25 3.73
VS -205 2 5.60 0.25 2.80
VS -204 2 8.70 0.25 4.35
VS -200 3 9.90 0.25 7.43
VS -202 1 5.55 0.25 1.39
VS -203 1 11.33 0.25 2.83
VS -201 1 5.50 0.25 1.38
VS -208 1 4.57 0.25 1.14

SEGUNDO PISO
EJE A-A ENTRE EJE 1 -EJE 2 (VP-206) 1 9.37 0.25 2.34
EJE A-A ENTRE EJE 2 -EJE 3 (VP-207) 1 9.60 0.25 2.40
EJE A-A ENTRE EJE 3 -EJE 4 (VP-208) 1 7.55 0.25 1.89
EJE A-A ENTRE EJE 4 -EJE 5 (VP-209) 1 3.60 0.25 0.90
EJE A-A ENTRE EJE 5 -EJE 6 (VP-210) 1 7.55 0.25 1.89
EJE A-A ENTRE EJE 6-EJE 10 (VP-211) 1 4.95 0.25 1.24

EJE B-B ENTRE EJE 1 -EJE 2 (VP-206) 1 9.37 0.25 2.34


EJE B-B ENTRE EJE 2 -EJE 3 (VP-207) 1 9.60 0.25 2.40
EJE B-B ENTRE EJE 3 -EJE 4 (VP-208) 1 7.55 0.25 1.89

EJE 1-1 VP (VP-204) 1 15.13 0.25 3.78


EJE 2-2 VP (VP-204) 1 20.75 0.25 5.19
EJE 3-3 VP (VP-204) 1 20.75 0.25 5.19
EJE 4-4 1 3.45 0.25 0.86
EJE 5-5 1 3.45 0.25 0.86
EJE 6-6 1 3.45 0.25 0.86
EJE 7-7 1 3.45 0.25 0.86
EJE 10-10 (VP-200) 1 19.21 0.25 4.80
EJE 11-11 (VP-200) 1 17.10 0.25 4.28
EJE 12-12 (VP-200) 1 14.75 0.25 3.69
EJE 13-13 (VP-200) 1 11.93 0.25 2.98
EJE 14-14 (VP-200) 1 9.12 0.25 2.28
EJE 15-15 (VS-202) 1 6.33 0.25 1.58
EJE 1-1 ENTRE EJE A- EJE B (VS-210) 1 10.84 0.25 2.71
EJE 1-1 ENTRE EJE B- EJE C (VS-209) 1 9.46 0.25 2.37

EJE 2-2 ENTRE EJE A- EJE B (VS-210) 1 10.84 0.25 2.71


EJE 2-2 ENTRE EJE B- EJE C (VS-209) 1 7.96 0.25 1.99

EJE 3-3 ENTRE EJE A- EJE B (VS-210) 1 10.84 0.25 2.71


EJE 3-3 ENTRE EJE B- EJE C (VS-209) 1 3.26 0.25 0.82

EJE 4-4 ENTRE EJE A- EJE B (VS-210) 1 10.84 0.25 2.71


EJE 5-5 ENTRE EJE A- EJE B (VS-210) 1 8.93 0.25 2.23
VS-206 3 5.85 0.25 4.39
VS -207 3 4.97 0.25 3.73
VS -205 2 5.60 0.25 2.80
VS -204 2 8.70 0.25 4.35
VS -200 3 9.90 0.25 7.43
VS -202 1 5.55 0.25 1.39
VS -203 1 11.33 0.25 2.83
VS -201 1 5.50 0.25 1.38
VS -208 1 4.57 0.25 1.14

Total de tarrajeo en vigas con mezcla 1:4 m2 204.35

10.06.02 Vestiduras de Arista m2


PRIMER PISO
EJE A-A ENTRE EJE 1 -EJE 2 (VP-206) 2 9.37 0.80 14.99
EJE A-A ENTRE EJE 2 -EJE 3 (VP-207) 2 9.60 0.80 15.36
EJE A-A ENTRE EJE 3 -EJE 4 (VP-208) 2 7.55 0.80 12.08
EJE A-A ENTRE EJE 4 -EJE 5 (VP-209) 2 3.60 0.80 5.76
EJE A-A ENTRE EJE 5 -EJE 6 (VP-210) 2 7.55 0.80 12.08
EJE A-A ENTRE EJE 6-EJE 10 (VP-211) 2 4.95 0.80 7.92

EJE B-B ENTRE EJE 1 -EJE 2 (VP-206) 2 9.37 0.80 14.99


EJE B-B ENTRE EJE 2 -EJE 3 (VP-207) 2 9.60 0.80 15.36
EJE B-B ENTRE EJE 3 -EJE 4 (VP-208) 2 7.55 0.80 12.08
EJE 1-1 VP (VP-204) 2 15.13 0.80 24.21
EJE 2-2 VP (VP-204) 2 20.75 0.80 33.20
EJE 3-3 VP (VP-204) 2 20.75 0.80 33.20
EJE 4-4 2 3.45 0.80 5.52
EJE 5-5 2 3.45 0.80 5.52
EJE 6-6 2 3.45 0.80 5.52
EJE 7-7 2 3.45 0.80 5.52
EJE 10-10 (VP-200) 2 19.21 0.80 30.74
EJE 11-11 (VP-200) 2 17.10 0.80 27.36
EJE 12-12 (VP-200) 2 14.75 0.80 23.60
EJE 13-13 (VP-200) 2 11.93 0.80 19.09
EJE 14-14 (VP-200) 2 9.12 0.80 14.59
EJE 15-15 (VS-202) 2 6.33 0.70 8.86
EJE 1-1 ENTRE EJE A- EJE B (VS-210) 2 10.84 0.70 15.18
EJE 1-1 ENTRE EJE B- EJE C (VS-209) 2 9.46 0.70 13.24

EJE 2-2 ENTRE EJE A- EJE B (VS-210) 2 10.84 0.70 15.18


EJE 2-2 ENTRE EJE B- EJE C (VS-209) 2 7.96 0.70 11.14

EJE 3-3 ENTRE EJE A- EJE B (VS-210) 2 10.84 0.70 15.18


EJE 3-3 ENTRE EJE B- EJE C (VS-209) 2 3.26 0.70 4.56

EJE 4-4 ENTRE EJE A- EJE B (VS-210) 2 10.84 0.70 15.18


EJE 5-5 ENTRE EJE A- EJE B (VS-210) 2 8.93 0.70 12.50
VS-206 6 5.85 0.70 24.57
VS -207 6 4.97 0.70 20.87
VS -205 4 5.60 0.70 15.68
VS -204 4 8.70 0.70 24.36
VS -200 6 9.90 0.70 41.58
VS -202 2 5.55 0.70 7.77
VS -203 2 11.33 0.70 15.86
VS -201 2 5.50 0.70 7.70
VS -208 2 4.57 0.70 6.40

SEGUNDO PISO
EJE A-A ENTRE EJE 1 -EJE 2 (VP-206) 2 9.37 0.80 14.99
EJE A-A ENTRE EJE 2 -EJE 3 (VP-207) 2 9.60 0.80 15.36
EJE A-A ENTRE EJE 3 -EJE 4 (VP-208) 2 7.55 0.80 12.08
EJE A-A ENTRE EJE 4 -EJE 5 (VP-209) 2 3.60 0.80 5.76
EJE A-A ENTRE EJE 5 -EJE 6 (VP-210) 2 7.55 0.80 12.08
EJE A-A ENTRE EJE 6-EJE 10 (VP-211) 2 4.95 0.80 7.92

EJE B-B ENTRE EJE 1 -EJE 2 (VP-206) 2 9.37 0.80 14.99


EJE B-B ENTRE EJE 2 -EJE 3 (VP-207) 2 9.60 0.80 15.36
EJE B-B ENTRE EJE 3 -EJE 4 (VP-208) 2 7.55 0.80 12.08

EJE 1-1 VP (VP-204) 2 15.13 0.80 24.21


EJE 2-2 VP (VP-204) 2 20.75 0.80 33.20
EJE 3-3 VP (VP-204) 2 20.75 0.80 33.20
EJE 4-4 2 3.45 0.80 5.52
EJE 5-5 2 3.45 0.80 5.52
EJE 6-6 2 3.45 0.80 5.52
EJE 7-7 2 3.45 0.80 5.52
EJE 10-10 (VP-200) 2 19.21 0.80 30.74
EJE 11-11 (VP-200) 2 17.10 0.80 27.36
EJE 12-12 (VP-200) 2 14.75 0.80 23.60
EJE 13-13 (VP-200) 2 11.93 0.80 19.09
EJE 14-14 (VP-200) 2 9.12 0.80 14.59
EJE 15-15 (VS-202) 2 6.33 0.70 8.86
EJE 1-1 ENTRE EJE A- EJE B (VS-210) 2 10.84 0.70 15.18
EJE 1-1 ENTRE EJE B- EJE C (VS-209) 2 9.46 0.70 13.24

EJE 2-2 ENTRE EJE A- EJE B (VS-210) 2 10.84 0.70 15.18


EJE 2-2 ENTRE EJE B- EJE C (VS-209) 2 7.96 0.70 11.14

EJE 3-3 ENTRE EJE A- EJE B (VS-210) 2 10.84 0.70 15.18


EJE 3-3 ENTRE EJE B- EJE C (VS-209) 2 3.26 0.70 4.56

EJE 4-4 ENTRE EJE A- EJE B (VS-210) 2 10.84 0.70 15.18


EJE 5-5 ENTRE EJE A- EJE B (VS-210) 2 8.93 0.70 12.50
VS-206 6 5.85 0.70 24.57
VS -207 6 4.97 0.70 20.87
VS -205 4 5.60 0.70 15.68
VS -204 4 8.70 0.70 24.36
VS -200 6 9.90 0.70 41.58
VS -202 2 5.55 0.70 7.77
VS -203 2 11.33 0.70 15.86
VS -201 2 5.50 0.70 7.70
VS -208 2 4.57 0.70 6.40

Total de vestiduras en aristas m 1229.00


CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

10.08.00 TARRAJEO CON IMPERMEABILIZANTES m2


Tarrajeo con impermeabilizante para cisterna 2 1.55 1.70 5.27
2 1.55 2.20 6.82
1 0.15 1.70 0.26
Total de tarrajeo con impermeabilizante m2 12.35
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

10.11.00 VESTIDURAS DE DERRAMES m


10.11.01 Vestiduras de Puertas 1 1 2.10 2.10
1 2 2.10 4.20
1 5 2.10 10.50
2 2 2.10 8.40
1 1 2.10 2.10
1 1 1.20 1.20
1 2 1.00 2.00
2 4 0.90 7.20
2 4 0.70 5.60
1 1 3.20 3.20
Total vestiduras de puertas m 46.50

10.11.02 Vestiduras de Ventanas m 2 1 1.60 3.20


2 1 1.60 3.20
2 1 0.50 1.00
2 1 1.70 3.40
2 3 0.50 3.00
2 1 0.40 0.80
2 1 1.70 3.40
2 2 1.70 6.80
2 1 1.70 3.40
2 1 1.40 2.80
2 1 2.80 5.60
2 1 2.50 5.00
2 1 1.50 3.00
2 1 2.35 4.70
2 1 1.10 2.20

Total de Vestiduras de Ventanas m 67.30

10.11.03 Vestiduras de Mampara m 2 2.45 4.90


2 2.40 4.80
2 2.72 5.44
Total de Vestiduras de Mampara m 15.14
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

11.00.00 CIELORASOS
11.03.00 CIELORASOS CON MEZCLA DE CEMENTO ARENA m2
Primer Nivel
eje2-2,3-3,entreA-B 1 4.24 3.40 14.42
eje2-2,eje3-3,entreB-C 1 3.40 3.20 10.88
eje1-1,eje2-2,entreA-B 1 4.13 0.55 2.27
eje1-1,eje2-2,entreB-C 1 3.20 0.55 1.76
eje3-3,eje4-4,entreA-B 1 1.94 0.95 1.84
eje3-3,eje4-4,entreA-B 1 1.70 1.60 2.72
eje3-3,eje4-4,entreA-B 1 1.94 0.85 1.65
eje3-3,eje4-4.entreB-C 1 3.50 3.20 11.20
eje4-4,eje5-5,entreA-B 1 4.43 2.70 11.96
eje4-4,eje5-5,entreA-B 1 3.20 2.70 8.64
entre,eje5-5,5' -5' 1 4.55 0.50 2.28

Segundo Nivel
eje2-2,3-3,entreA-B 1 4.24 3.40 14.42
eje2-2,eje3-3,entreB-C 1 3.20 2.30 7.36
eje2-2,eje3-3,entreB-C 1 1.35 1.10 1.49
eje1-1,eje2-2,entreA-B 1 4.13 0.55 2.27
eje1-1,eje2-2,entreB-C 1 3.20 0.55 1.76
eje3-3,eje4-4,entreA-B 1 1.94 0.95 1.84
eje3-3,eje4-4,entreA-B 1 1.70 1.60 2.72
eje3-3,eje4-4,entreA-B 1 1.94 0.85 1.65
eje3-3,eje4-4.entreB-C 1 3.50 3.20 11.20
eje4-4,eje5-5,entreA-B 1 4.43 2.70 11.96
eje4-4,eje5-5,entreA-B 1 3.20 2.70 8.64
entre,eje5-5,5' -5' 1 4.55 0.50 2.28

Total Cielorraso con mezcla de cemento arena m2 137.20


CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

11.04.00 VESTIDURAS EN FONDO DE ESCALERAS


11.04.01 Vestidura de Superficies m2
Primer Nivel
tramo1(rampa) 1 0.97 1.00 0.97
arranque desde nivel de piso a la rampa 1 1.00 0.17 0.17
tramo2
descanso 1 1.30 1.05 1.37
rampa 1 1.85 1.30 2.41
tramo3
descanso 1 1.30 1.00 1.30
rampa 1 0.97 1.00 0.97
Segundo Nivel a la Azotea
tramo1(rampa) 1 0.97 1.00 0.97
tramo2
descanso 1 1.30 1.05 1.37
rampa 1 1.85 1.30 2.41
tramo3
descanso 1 1.30 1.00 1.30
rampa 1 0.97 1.00 0.97
Caras laterales de escalera 1 1.60 1.60
Total de Vestiduras de Superficies m2 15.79

12.00.00 PISOS Y PAVIMENTOS


12.01.00 CONTRAPISOS de 5cm (Primer Nivel) m2 126.28 126.28
PISOS PORCELANATO
12.01.01 PRIMER NIVEL
CAFETERIA 1 AREA= 350.97 350.97
GUARDAROPA 1 AREA= 11.74 11.74
FOYER 1 AREA= 203.75 203.75
SALA DE USOS MULTIPLES 1 AREA= 87.75 87.75
SS.HH 1 AREA= 29.37 29.37
1 AREA= 9.87 9.87
1 AREA= 21.66 21.66
1 AREA= 21.66 21.66
1 AREA= 30.07 30.07
1 AREA= 29.92 29.92
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

ESCENARIO 1 AREA = 604.62 604.62


SALA DE ENSAYO N ° 1 1 AREA = 214.76 214.76
CUARTO DE TABALEROS 1 AREA = 21.89 21.89
CUARTO DE BOMBAS 1 AREA = 22.21 22.21
ESTAR EXTERIOR 1 AREA = 128.90 128.90

SEGUNDO NIVEL
SALA DE USOS MULTIPLES 2 1 AREA = 86.72 86.72
SALA DE USOS MULTIPLES 3 1 AREA = 86.13 86.13
SALA DE USOS MULTIPLES 4 1 AREA = 86.20 86.20
SALA DE PROFESORES 1 AREA = 174.98 174.98
CUARTO DE DIMERS 1 AREA = 12.00 12.00
CONSOLA DE CONTROL 1 AREA = 27.46 27.46
SALA DE ENSAYO 2 1 AREA = 148.21 148.21
FOYER 1 AREA = 366.19 366.19
SS.HH 1 AREA = 9.92 9.92
1 AREA = 21.48 21.48
1 AREA = 13.30 13.30
1 AREA = 21.03 21.03
1 AREA = 21.03 21.03
m2 2863.82

12.02.00 LOSETA m2
12.02.02 Loseta Veneciana m2
12.02.02.03 Loseta Veneciana de color claro 30 x 30 cm. Mortero 1:4 1 4.50 3.30 14.85
1 3.35 2.25 7.54
Total de Loseta Veneciana de 30 x 30 cm. m2 22.39
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

18.00.00 CARPINTERIA DE MADERA


18.01.00 PUERTAS
18.01.01 Puertas contraplacadas de 35 mm, de espesor marco 2"x3" m2 2 2.10 0.90 3.78
5 2.10 0.70 7.35
6 2.10 1.00 12.60
Total de madera para puertas m2 23.73
18.02.00 VENTANAS
18.02.01 Ventanas con Hojas m2 1 1.58 3.15 4.98
1 1.58 2.40 3.79
1 0.50 0.80 0.40
1 1.70 2.30 3.91
3 0.50 1.20 1.80
1 0.40 1.20 0.48
1 1.70 2.46 4.18
2 1.70 2.45 8.33
1 1.70 1.10 1.87
1 1.40 1.10 1.54
Total de madera para ventanas m2 31.28

18.03.00 MAMPARAS m2 1 2.45 3.33 8.16


1 2.40 3.33 7.99
1 2.72 3.20 8.70
Total de madera para mamparas m2 24.85

19.00.00 CARPINTERIA METÁLICA Y HERRERIA


19.01.00 VENTANAS DE FIERRO
19.01.01 Ventanas de fierro con seguridad m2 1 2.70 2.35 6.35 6.35

20.00.00 CERRAJERIA
20.01.00 BISAGRAS
20.01.01 Bisagras para puertas, de color negro Pz 39 39.00 39.00
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

20.02.00 CERRADURAS
20.02.03 Cerraduras para puertas interiores de llave interior Pz 17 17.00 17.00

20.03.00 SISTEMAS O MECANISMOS


20.03.01 Para puertas corredizas Juego 1 1.00 1.00
20.03.02 Para puertas levadizas Juego 1 1.00 1.00

20.04.00 ACCESORIOS DE CIERRE


20.04.01 Picaportes de empotrar Pz 4 4.00 4.00
20.04.04 Cerrojos Pz 3 3.00 3.00

21.00.00 VIDRIOS, CRISTALES Y SIMILARES


21.01.00 VIDRIOS Y CRISTALES P2
21.01.02 Vidrios y Cristales Semidobles P2 1 1.60 2.85 4.56
1 1.60 2.40 3.84
1 0.50 0.50 0.25
1 1.70 2.30 3.91
3 0.50 1.20 1.80
1 0.40 1.20 0.48
1 1.70 2.46 4.18
2 1.70 2.45 8.33
1 1.70 1.10 1.87
1 1.40 1.10 1.54
Area en m2 para vidrios y cristales semidobles 30.76
Area en p2 para vidrios y cristales semidobles x 10,76 P2 331.00

22.00.00 PINTURA
22.01.00 DE CIELORRASOS, MUROS
22.01.01 Cielorrasos al temple m2 2 165.23 330.46 330.46
22.01.05 Muros interiores al temple 2 manos m2 2 565.69 565.69 565.69
22.01.09 Muros Exteriores al temple 2 manos m2 2 47.25 47.25 47.25
CÓDIGO DESCRIPCIÓN UND N° VECES LARGO (m) ALTO(m) ANCHO(m) PARCIAL(m) TOTAL(m)

24.00.00 APARATOS SANITARIOS Y ACCESORIOS


24.01.00 INODOROS
24.01.01 Inodoro Montecarlo Blanco Comercial Pz 4 4 4

24.02.00 LAVATORIOS
24.02.01 Lavatorio Sonnet 19 x 10 Blanco comercial Pz 5 5 5

24.06.00 LAVADEROS DE COCINA


24.06.01 Lavadero de Platos Pz 1 1 1

24.09.00 DUCHAS
24.09.01 Duchas Cromadas de cabeza giratoria Pz 4 4 4

24.11.00 JABONERAS
24.11.01 Jaboneras de losa blanca simple de 15x15 Pz 4 4 4

24.12.00 TOALLERAS
24.12.01 Toallera con soporte de Losa y barra plástica Pz 4 4 4

24.13.00 PAPELERAS
24.13.01 Papelera de Losa de Color de 15x15 Pz 4 4 4

24.20.00 COLOCACIÓN DE APARATOS SANITARIOS Pz 9 9 9